Activity ID Activity Name Duration Start Finish RESPONSIBILITY LD 2023 2024 2025

milestone S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S


-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36
AMNS L2 Baseline 1019 07-Oct-22 22-Jul-25

GENERAL 45 07-Oct-22 20-Nov-22

AA00-G-0100 Coming Into Force of the Contract 0 07-Oct-22* AMNS/DAN

AA00-G-0200 Start of time schedule as per Contract 0 07-Oct-22 AMNS/DAN

AA00-G-0300 Preparation for Kick-off meeting 15 07-Oct-22 21-Oct-22 AMNS/DAN

AA00-G-0400 Kick-off meeting 15 22-Oct-22 05-Nov-22 AMNS/DAN

AA00-G-0500 Discussion of General Layout Drawing 15 22-Oct-22 05-Nov-22 AMNS/DAN

AA00-G-0600 Approval of layout drawing (Preliminary layout approval) 30 22-Oct-22 20-Nov-22 AMNS

BASIC ENGINEERING 365 07-Oct-22 06-Oct-23

AA00-BD-0100 GA Drawing for Ladle 31 07-Oct-22 06-Nov-22 AMNS

AA00-BD-0200 Basic data-Civil (Main load plan-for building column) 31 22-Oct-22 21-Nov-22 AMNS/DAN RD1

AA00-BD-0300 Basic data-Main process equipment Caster machine (load data in kN/m2) 61 07-Nov-22 06-Jan-23 DAN RD1

AA00-BD-0400 Basic data-Main process equipment Runout area (load data in kN/m2) 62 07-Dec-22 06-Feb-23 DAN RD1

AA00-BD-0500 Basic data-Building structure 30 22-Oct-22 20-Nov-22 AMNS

AA00-BD-0600 Basic data - Utility (Fluid balance table:Consumptions and TOPs) 90 07-Dec-22 06-Mar-23 DAN RD1

AA00-BD-0700 Basic Design-Civil for Caster machine area (1) 212 07-Nov-22 06-Jun-23 DAN RD1
(80% completion in 6m and rest 20% in 8m from zerodate)
AA00-BD-0800 Basic Design-Civil for Runout area (1) 90 07-Jan-23 06-Apr-23 DAN RD1

AA00-BD-0900 Basic Design-Civil for Caster Electrical & Hydraulic cabins (1) (80% completion in 7m and rest 20% in 150 07-Feb-23 06-Jul-23 DAN RD1
9m from zerodate)
AA00-BD-1000 Basic Design-Civil for Minor and Auxiliary equipment and final Elec bldg (maintenance area) 92 07-Jun-23 06-Sep-23 DAN RD1

AA00-BD-1100 Basic Design-Intermed. floors/platforms(incl. Major loads & fixing points for struct.)>>>Included in 0 07-Oct-22 DAN
caster machine area

AA00-BD-1200 Basic Design - Utility-Media consumption list and P&ID 243 07-Dec-22 06-Aug-23 DAN RD1

AA00-BD-1300 Basic Design - Equipment, Hydraulic and Lubrication systems 182 07-Dec-22 06-Jun-23 DAN

AA00-BD-1400 Basic Design - E&I (Including cable engineering & internal E-bldg layout) 214 07-Mar-23 06-Oct-23 DAN

AA00-BD-1500 Basic Design-Utility piping 153 07-Mar-23 06-Aug-23 DAN

AA00-BD-1600 Basic Design-Automation 273 07-Jan-23 06-Oct-23 DAN

AA00-BD-1700 Basic Design-AMNSI scope 0 07-Oct-22 DAN

DETAIL ENGINEERING 655 22-Dec-22 06-Oct-24

AA00-DD-0100 Detail Design-Piling 183 22-Dec-22 22-Jun-23 AMNS

AA00-DD-0200 Detail Design-Civil for all Buildings 212 07-Feb-23 06-Sep-23 AMNS

AA00-DD-0300 Detail Design-Civil for all Equipment 337 07-Mar-23 06-Feb-24 AMNS

AA00-DD-0400 Detail Design-Structure for Building 425 07-Jan-23 06-Mar-24 AMNS

AA00-DD-0500 Detail Design-Equipment related structure 244 07-Apr-23 06-Dec-23 AMNS

Actual Work Critical Milestone Doc. No : DPC6V4-AA00-N0000-AV002


Actual Milestone
2 X 2 STRAND SLAB CASTERS CC5 & CC6 Date Revision Checked Approved
28-Oct-22 First Issue SX MR
Activity - OVERALL LEVEL 2 SCHEDULE - 23-Nov-22 Revised SX MR
Milestone Page 1 of 3
Critical Activity
Activity ID Activity Name Duration Start Finish RESPONSIBILITY LD 2023 2024 2025
milestone S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36
AA00-DD-0600 Detail Design-OEM scope Major equipment 303 07-Feb-23 06-Dec-23 DAN

AA00-DD-0700 Detail Design-OEM scope Structures 303 07-Feb-23 06-Dec-23 DAN RD2

AA00-DD-0800 Detail Design-OEM scope Auxiliary equipment 184 07-Jul-23 06-Jan-24 DAN

AA00-DD-0900 Detail Design-OEM scope Utility piping CC5 183 07-Jun-23 06-Dec-23 DAN RD2

AA00-DD-1000 Detail Design-OEM scope Utility piping CC6 184 07-Aug-23 06-Feb-24 DAN RD2

AA00-DD-1100 Detail Design-OEM scope E&I (incl. Cable routing and tray engineerig) for CC5. Data fo CC5 will be 214 07-May-23 06-Dec-23 DAN RD2
used also for CC6

AA00-DD-1200 Detail Design-Automation 244 07-Jul-23 06-Mar-24 DAN RD2

AA00-DD-1300 Detail Design-Balance shop piping/cabling 215 07-Jul-23 06-Feb-24 AMNS

AA00-DD-1400 DD-Balance civil/structure (Roads, drain, platforms handrails. Etc) 335 07-Nov-23 06-Oct-24 AMNS

PROCUREMENT 151 07-Nov-22 06-Apr-23

AA00-PR-0100 Procurement of AMNSI scope items (Cranes, Structures, Water, E&A etc.) 151 07-Nov-22 06-Apr-23 AMNS

MANUFACTURING & SUPPLY 672 07-Apr-23 06-Feb-25

AA00-MF-0100 Manufacturing of Sellers imported equipment 427 07-Apr-23 06-Jun-24 DAN


(FOB acc. INCOTERMS 2020) wihtout OCP for CC5
AA00-MF-0200 Manufacturing of Sellers imported equipment 428 07-Jul-23 06-Sep-24 DAN
(FOB acc. INCOTERMS 2020) wihtout OCP for CC6

AA00-MF-0300 Manufacturing of Sellers imported equipment 427 07-Aug-23 06-Oct-24 DAN


(FOB acc. INCOTERMS 2020) OCP for CC5

AA00-MF-0400 "Manufacturing of Sellers imported equipment 427 07-Oct-23 06-Dec-24 DAN


(FOB acc. INCOTERMS 2020) OCP for CC6"
AA00-MF-0500 Manufacturing of Seller's local equipment CC5&CC6 519 07-Apr-23 06-Sep-24 DAN

AA00-MF-0600 FOB delivery of Online-Segments for CC5 (from end of 18m to 20m) (3) 61 07-Apr-24 06-Jun-24 DAN RD3

AA00-MF-0700 FOB delivery of Online-Segments for CC6 (from end of 21m to 23m) (3) 62 07-Jul-24 06-Sep-24 DAN RD3

AA00-MF-0800 Transport of Seller's imported equipment CC5&CC6 457 07-Sep-23 06-Dec-24 AMNS

AA00-MF-0900 Arrival at site of Seller's imported equipmetn CC5&CC6 458 07-Nov-23 06-Feb-25 AMNS

AA00-MF-1000 DAP delivery of Seller's local equipment (FOT at site) CC5 198 22-Nov-23 06-Jun-24 DAN

AA00-MF-1100 DAP delivery of Ladle turret (FOT at site) for CC5 (subject to receiving Ladle GA dwg in 1month from 0 07-Jan-24 DAN RD3
zero date, item2.0)

AA00-MF-1200 DAP delivery of Segment support frame (FOT at site) for CC5 (from end of 15m to 16m) 31 07-Jan-24 06-Feb-24 DAN RD3

AA00-MF-1300 DAP delivery of Seller's local equipment (FOT at site) CC6 259 22-Jan-24 06-Oct-24 DAN

AA00-MF-1400 DAP delivery of Ladle turret (FOT at site) for CC6 (subject to receiving Ladle GA dwg in 1month from 0 07-Mar-24 DAN RD3
zero date, item2.0)
AA00-MF-1500 DAP delivery of Segment support frame (FOT at site) for CC6 (from end of 17m to 18m) 31 07-Mar-24 06-Apr-24 DAN RD3

AA00-MF-1600 DAP delivery of OCP Seller's local equipment (FOT at site) CC5 92 07-Jul-24 06-Oct-24 DAN

AA00-MF-1700 DAP delivery of OCP Seller's local equipment (FOT at site) CC6 91 07-Sep-24 06-Dec-24 DAN

AA00-MF-1800 DAP delivery of interconnecting piping by Seller local (FOT at site) CC5 77 22-Mar-24 06-Jun-24 DAN RD3

AA00-MF-1900 DAP delivery of interconnecting piping by Seller local (FOT at site) CC6 77 22-May-24 06-Aug-24 DAN RD3

CONSTRUCTION 790 07-Jan-23 06-Mar-25

Actual Work Critical Milestone Doc. No : DPC6V4-AA00-N0000-AV002


Actual Milestone
2 X 2 STRAND SLAB CASTERS CC5 & CC6 Date Revision Checked Approved
28-Oct-22 First Issue SX MR
Activity - OVERALL LEVEL 2 SCHEDULE - 23-Nov-22 Revised SX MR
Milestone Page 2 of 3
Critical Activity
Activity ID Activity Name Duration Start Finish RESPONSIBILITY LD 2023 2024 2025
milestone S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36
AA00-CS-0100 Piling 212 07-Jan-23 06-Aug-23 AMNS

AA00-CS-0200 Civil work - Execution of bulding columns, equipment foundation , electrical room, casting platforms 382 22-Mar-23 06-Apr-24 AMNS

AA00-CS-0300 Structural steel work-Major execution of bay structure 321 22-Jul-23 06-Jun-24 AMNS

AA00-CS-0400 Structural steel work-Balance execution of bay structure(roof and wall cladding) 123 07-May-24 06-Sep-24 AMNS

AA00-CS-0500 Erection of caster Mechanical equipment CC5 260 22-Dec-23 06-Sep-24 AMNS

AA00-CS-0800 Erection of caster Electrical equipment CC5 214 07-Apr-24 06-Nov-24 AMNS

AA00-CS-0900 Utility piping CC5 244 07-Apr-24 06-Dec-24 AMNS

AA00-CS-1000 Hydraulics, Lubrication CC5 214 07-May-24 06-Dec-24 AMNS

AA00-CS-1100 Cabling CC5 306 07-Mar-24 06-Jan-25 AMNS

AA00-CS-1200 Instrumentation CC5 306 07-Mar-24 06-Jan-25 AMNS

AA00-CS-1300 Automation CC5 92 07-Jul-24 06-Oct-24 AMNS

AA00-CS-1400 Erection of caster Mechanical equipment CC6 259 22-Feb-24 06-Nov-24 AMNS

AA00-CS-1500 Erection of caster Electrical equipment CC6 214 07-Jun-24 06-Jan-25 AMNS

AA00-CS-1600 Utility piping CC6 273 07-Jun-24 06-Mar-25 AMNS

AA00-CS-1700 Hydraulics, Lubrication CC6 215 07-Jul-24 06-Feb-25 AMNS

AA00-CS-1800 Cabling CC6 304 07-May-24 06-Mar-25 AMNS

AA00-CS-1900 Instrumentation CC6 304 07-May-24 06-Mar-25 AMNS

AA00-CS-2000 Automation CC6 92 07-Nov-24 06-Feb-25 AMNS

COLD START AND INTEGRATED TEST 151 07-Nov-24 07-Apr-25

AA00-CT-0100 CC5 92 07-Nov-24 06-Feb-25 AMNS/DAN

AA00-CT-0200 R.F.I.O (Ready for Initial Operation) CC5 0 07-Feb-25 AMNS/DAN

AA00-CT-0300 CC6 90 07-Jan-25 06-Apr-25 AMNS/DAN

AA00-CT-0400 R.F.I.O (Ready for Initial Operation) CC6 0 07-Apr-25 AMNS/DAN

INDUSTRIAL COMMISSIONING AND ACCEPTANCE 165 07-Feb-25 22-Jul-25

AA00-IC-0100 Start of Industrial Commissioning / Hot start CC5 0 07-Feb-25 AMNS/DAN

AA00-IC-0200 Industrial Commissioning Certificate (I.C.) - Caster 5 15 07-Feb-25 21-Feb-25 AMNS/DAN LD4

AA00-IC-0300 Acceptance Testing CC5 89 22-Feb-25 21-May-25 AMNS/DAN

AA00-IC-0400 Provision Acceptance - Caster 5 0 22-May-25 AMNS/DAN

AA00-IC-0500 Start of Industrial Commissioning / Hot start CC6 0 07-Apr-25 AMNS/DAN

AA00-IC-0600 Industrial Commissioning Certificate (I.C.) - Caster 6 15 07-Apr-25 21-Apr-25 AMNS/DAN RD4

AA00-IC-0700 Acceptance Testing CC6 91 22-Apr-25 21-Jul-25 AMNS/DAN

AA00-IC-0800 Provision Acceptance - Caster 6 0 22-Jul-25 AMNS/DAN

Actual Work Critical Milestone Doc. No : DPC6V4-AA00-N0000-AV002


Actual Milestone
2 X 2 STRAND SLAB CASTERS CC5 & CC6 Date Revision Checked Approved
28-Oct-22 First Issue SX MR
Activity - OVERALL LEVEL 2 SCHEDULE - 23-Nov-22 Revised SX MR
Milestone Page 3 of 3