Refrigerant Compressor Selection & Liquefaction Study

Activity ID Activity Name Original Start Finish 2019 2020


Duration Nov Dec Jan Feb Mar Apr May Jun Jul
60 61 62 63 64 65 66 67 68
GT Driver & Li
Liquefaction Study
Refrigerant Co
Comp. Package & Liquef. Licensor Select. Study Execution
Refrigerant Compressor
Comp Package Selection Study (CTR-001)
LIQEXE-0000 Contract Effective Date 0.0d 18-Nov-19
LIQEXE-1000 Kick-Off Meeting 5.0d 18-Nov-19 22-Nov-19
LIQEXE-1025 Agree GT ISO/Site Rated Power 4.0d 25-Nov-19 28-Nov-19
LIQEXE-1030 Develop Technology Novelty Assessment Plan 15.0d 29-Nov-19 19-Dec-19
LIQEXE-1070 Prepare Specifications - Rotating Equipment 30.0d 29-Nov-19 09-Jan-20
LIQEXE-1080 Prepare Data Sheets - Rotating Equipment 10.0d 27-Dec-19 09-Jan-20
LIQEXE-1100 Prepare RFQ for GTs/Refrigerant Compressors 15.0d 20-Dec-19 09-Jan-20
LIQEXE-1105 Issue RFQ for GTs/Refrigerant Compressors 0.0d 09-Jan-20
LIQEXE-1120 Engage with GT Suppliers & Hold Price & Novelty Meetings - incl. Negotiate & Ob 21.0d 10-Jan-20 07-Feb-20
LIQEXE-1130 Receive Vendors Proposals 0.0d 07-Feb-20
LIQEXE-1140 Review Layout Implications 10.0d 03-Jan-20 16-Jan-20
LIQEXE-1150 Review Equipment/Unit Sizing - Preliminary Design 15.0d 03-Jan-20 23-Jan-20
LIQEXE-1160 Develop 'Delta' Equpiment Lists 15.0d 10-Jan-20 30-Jan-20
LIQEXE-1170 Develop OOM 'Delta' Equipment Cost Estimates 15.0d 17-Jan-20 06-Feb-20
LIQEXE-1175 Perform Technical Novelty Assurance Plan Workshop 5.0d 03-Feb-20 07-Feb-20
LIQEXE-1180 Issue Refrigerant Compressor Package Selection Report 15.0d 10-Feb-20 28-Feb-20
LIQEXE-1200 Prepare Technology/Novelty Assessment Report & Plan for FEED/EPC 10.0d 02-Mar-20 13-Mar-20
LIQEXE-1210 End of CTR-001 0.0d 13-Mar-20
Liquefaction Licensor
Licen Selection Study (CTR-002)
LIQEXE-1011 Define & Agree on a Facility Configuration 4.0d 25-Nov-19 28-Nov-19
LIQEXE-1020 Define & Agree on Cases to be Simulated 4.0d 25-Nov-19 28-Nov-19
LIQEXE-1050 Process Simulations for Each Configuration 25.0d 29-Nov-19 02-Jan-20
LIQEXE-1060 Prepare Capacity Report 10.0d 27-Dec-19 09-Jan-20
LIQEXE-1090 Prepare Liquefaction BoD - for CTR-002 20.0d 20-Dec-19 16-Jan-20
LIQEXE-2000 Confidentiality Agreements with Licensors 30.0d 29-Nov-19 13-Jan-20
LIQEXE-2020 Prepare Liquefaction BoD to Licensors 20.0d 27-Dec-19 24-Jan-20
LIQEXE-2050 Prepare SoW & RFQ to Licensors (Initial) 20.0d 10-Jan-20 06-Feb-20
LIQEXE-2060 Update SoW & RFQ to Licensors 15.0d 10-Feb-20 28-Feb-20
LIQEXE-2065 Update Configuration & Cases to be Simulated 5.0d 10-Feb-20 14-Feb-20
LIQEXE-2066 Update Liquefaction BoD to Licensors 5.0d 17-Feb-20 21-Feb-20
LIQEXE-2067 Issue Liquefaction BoO to Licensors 5.0d 24-Feb-20 28-Feb-20
LIQEXE-2070 Kick-Off with Licensors 0.0d 28-Feb-20
LIQEXE-2080 Issue SoW & RFQ to Licensors 5.0d 02-Mar-20 06-Mar-20
LIQEXE-2090 Engagement with Licensors 40.0d 09-Mar-20 06-May-20
LIQEXE-2100 Receive Licensors Proposals 0.0d 06-May-20
LIQEXE-2110 Review & Evaluate Licensors Packages 5.0d 08-May-20 14-May-20
LIQEXE-2120 Issue Licensor Selection Report 5.0d 15-May-20 22-May-20
LIQEXE-2130 End of CTR-002 0.0d 22-May-20

Remaining Level of Effort Date Revision Checked Approved

Actual Work
Forecast
Critical Remaining Work
Milestone