TIME SCHEDULE S CURVE

NEW CANOPY MAIN GATE LOT-41


Owner : PT. HM SAMPOERNA Tbk
CMS : PT. MANAJEMEN KONSTRUKSI UTAMA
Contractors : PT. MULIA DJASMINE SENTOSA
Project : New Canopy Main Gate LOT-41
Date : 18/10/23 - 16/12/23

November Desember

NO Description PERC (%) WEEK-1 WEEK-2 WEEK-3 WEEK-4 WEEK-5 WEEK-6 WEEK-7 WEEK-8

23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16

A Premilinary Work 8.3% 1% 1% 1% 1% 1% 1% 1% 1% 1% 1%


100%
Actual 1% 1% 1% 1% 1% 1% 1%

B Preparation 3.6% 1% 1% 1% 1% 1% 1% 1%

Actual 1% 1% 1% 1% 1% 1% 90%

C Fabrication 26.1% 1% 1% 1% 1% 1% 1% 1% 1% 1% 1% 1% 1% 1% 1% 1% 1% 1% 1% 1% 1% 1% 1% 1% 1% 1% 1% 1% 1% 1% 1% 1% 1% 1% 1% 1% 1% 1%

Actual 80%

D Fondation Canopy CB 18.0% 1% 1% 1% 1% 1% 1% 1% 1% 1% 1% 1% 1% 1% 1% 1% 1% 1% 1% 1% 1%

Actual 2% 1% 0%
70%
E Fondation Canopy CS1 7.5% 1% 1% 1% 1% 1% 1% 1% 1% 1% 1% 1% 1% 1% 1%

Actual 1% 1%
60%
F Fondation Canopy CS2 7.5% 1% 1% 1% 1% 1% 1% 1% 1% 1% 1% 1% 1% 1% 1%

Actual 1% 1% 1%

G Lifting Structure Frame Truss 2.9% 1% 1% 50%

Actual

H Steel Structure Canopy CB (Instalation) 4.3% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%


40%
Actual

I Steel Structure Canopy CS1 (Instalation) 2.0% 0% 0% 0% 0% 0% 0% 0%


30%
Actual

J Steel Structure Canopy CS2 (Instalation) 2.0% 0% 0% 0% 0% 0% 0% 0%

Actual 20%

K Roof Structure & Plumbing 14.5% 1% 1% 1% 1% 1% 1% 1% 1% 1% 1% 1% 1% 1% 1% 1% 1%

Actual
10%
L Finish & Clean Area 3.4% 0% 0% 0% 0% 0% 0%

Actual
0%
Total 100%

Planing 1% 1% 1% 2% 2% 2% 2% 2% 2% 2% 2% 2% 2% 2% 3% 3% 3% 3% 3% 3% 3% 3% 3% 2% 2% 2% 2% 2% 1% 1% 1% 1% 1% 2% 2% 2% 2% 2% 2% 2% 3% 3% 2% 2% 1% 1% 1% 1% 1% 0% 0% 0% 0% 0% 0%

Kumulatif 1% 3% 4% 6% 8% 11% 13% 15% 18% 20% 22% 24% 26% 28% 31% 34% 36% 39% 42% 44% 47% 49% 52% 55% 56% 58% 60% 61% 63% 64% 65% 67% 68% 70% 72% 74% 76% 78% 80% 82% 85% 89% 90% 92% 93% 94% 95% 96% 97% 97% 98% 98% 99% 99% 100%

Actual 1% 1% 3% 3% 4% 3% 2% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%

Kumulatif 1% 2% 5% 7% 11% 14% 17% 17% 17% 17% 17% 17% 17% 17% 17% 17% 17% 17% 17% 17% 17% 17% 17% 17% 17% 17% 17% 17% 17% 17% 17% 17% 17% 17% 17% 17% 17% 17% 17% 17% 17% 17% 17% 17% 17% 17% 17% 17% 17% 17% 17% 17% 17% 17% 17%

Karawang, Oktober 2023

Prepared By, Checked By, Approved By Acknowledged

M Bastian Dodi Bambang Hernowo Christian


Author Project Manager Construction Management Owner