CONSTRUCT JALAN SP MERANTI 2

MARET 2023 Apr-23


Produktifitas
No Item Pekerjaan Volume Sat PA UA Quantity Proporsi
BCM/jam WH 20 21 22 23 24 25 26 27 28 30 31 1 2 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
Plan 2,25% 2,25% 2,25% 2,25% 2,25% 2,25% 2,25% 2,25% 2,25% 2,25% 2,25% 2,25% 2,25%
1 Pekerjaan Cut Soil 48000 m2 200 90% 85% 24 13 Hari 29,30% Aktual 2,25% 2,25% 2,25% 2,25%
Plan 2,25% 2,25% 2,25% 2,25% 2,25% 2,25% 2,25% 2,25% 2,25% 2,25% 2,25% 2,25%
2 Pekerjaan Fill Material 59800 m3 300 90% 75% 24 12 Hari 27,58% Aktual
Plan 2,25% 2,25% 2,25% 2,25% 2,25% 2,25% 2,25% 2,25% 2,25% 2,25% 2,25% 2,25%
3 Pemadatan Material 59800 m3 300 90% 75% 24 12 Hari 27,58% Aktual
Plan 2,25%
4 Crossfall & Paritan 1600 m3 250 90% 55% 24 1 Hari 1,21% Aktual
Plan 2,25%
5 Pembuatan Tanggul 1600 m3 100 90% 55% 24 1 Hari 3,02% Aktual
Plan 2,25% 2,25% 2,25% 2,25% 3,25%
6 Surfacing 7200 m3 120 90% 55% 24 5 Hari 11,32% Aktual
45 Hari 100%
Total Volume 169200 m3 % 2,3% 2,3% 2,3% 2,3% 2,3% 2,3% 2,3% 2,3% 2,3% 2,3% 2,3% 6,8% 6,8% 4,5% 4,5% 4,5% 4,5% 4,5% 4,5% 4,5% 4,5% 4,5% 4,5% 2,3% 4,5% 2,3% 2,3% 2,3% 3,3%
85,66% Plan kum 2,3% 5% 7% 9% 11% 14% 16% 18% 20% 23% 25% 32% 38% 43% 47% 52% 56% 61% 65% 70% 74% 79% 83% 86% 90% 92% 95% 97% 100%
% 2,3% 2,3% 2,3% 2,3% 0,0% 0,0% 0,0% 0,0% 0,0% 0,0% 0,0% 0,0% 0,0% 0,0% 0,0% 0,0% 0,0% 0,0% 0,0% 0,0% 0,0% 0,0% 0,0% 0,0% 0,0% 0,0% 0,0% 0,0% 0,0%
42 Aktual Kum 2,3% 4,5% 6,8% 9,0% 9,0% 9,0% 9,0% 9,0% 9,0% 9,0% 9,0% 9,0% 9,0% 9,0% 9,0% 9,0% 9,0% 9,0% 9,0% 9,0% 9,0% 9,0% 9,0% 9,0% 9,0% 9,0% 9,0% 9,0% 9,0%

UNIT ALLOCATION

• 1 x PC300  EX363
• 1 x DZ 85  DZ 864
• 1 x CP  CP 551

Plan Activity
• Loading Soil dan Mall Jalan

ACHIEVMENT

Progress:
Plan/Act = 9%/9%