RAB TYPE FRESIA SUDUT 1UNIT

23/08/2021 (REVISI)
ISPI GROUP START
MUNCHEN RK028/CITY-MUN/7/2023 6/10/2023 PROGRESS
OKTOBER 2023 November 2023 DESEMBER 2023 JANUARI 2024 FEBRUARI 2024 MARET 2024 April 2024 MEI 2024 JUNI 2024
NO JENIS PEKERJAAN BOBOT
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
I PEK PERSIAPAN 2.32% 2.2% 0.1% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%
II PEK TANAH & PONDASI 8.77% 0.0% 0.3% 3.7% 3.7% 0.3% 0.0% 0.5% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.1% 0.0% 0.0% 0.0% 0.0% 0.0% 0.2% 0.0% 0.0% 0.0%

III PEK BETON 10.34% 0.0% 0.0% 0.0% 1.9% 1.9% 0.0% 0.0% 2.5% 0.0% 0.0% 0.3% 0.1% 0.4% 0.8% 1.2% 0.5% 0.5% 0.3% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

IV PEK DINDING BATA RINGAN /P+A 42.36% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 1.7% 1.7% 1.7% 1.7% 1.7% 1.7% 1.7% 1.7% 1.7% 3.8% 2.1% 2.1% 2.1% 2.1% 2.1% 2.1% 3.0% 3.2% 3.2% 1.3% 0.0% 0.0% 0.0% 0.0%

V PEK KUSEN & PINTU 0.37% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% IDUL 0.0% 0.0% 0.0% 0.0% 0.0% 0.4% 0.0% 0.0%

VI PEK ATAP & PLAFOND 9.35% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 1.2% 0.3% 0.3% 0.8% 0.0%
FITRI 0.5% 0.5% 0.8% 0.0% 1.9% 2.9% 0.0% 0.0%

VII PEK LANTAI & KERAMIK 8.45% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 2.8% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.8% 1.0% 0.0% 0.9% 1.3% 1.3% 0.3% 0.0% 0.0% 0.0%

VIII PEK PLUMBING & SANITER 5.71% 0.0% 0.0% 0.0% 0.0% 2.6% 0.8% 0.0% 0.8% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%
2024 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.2% 1.3%

IX PEKERJAAN CAT 0.00%


X PEK INSTALASI LISTRIK 0.00%
XI PEK HALAMAN 12.34% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.7% 2.4% 0.0% 4.3% 4.8%

100% 2.2% 0.4% 3.7% 5.6% 4.7% 0.8% 0.5% 6.1% 1.7% 1.7% 2.0% 1.8% 2.1% 2.5% 2.9% 2.2% 2.2% 4.1% 2.1% 3.3% 2.4% 2.4% 3.8% 3.1% 0.0% 0.0% 0.0% 0.0% 3.5% 4.6% 5.4% 3.4% 4.8% 3.3% 4.6% 6.2%

RENCANA 2.2% 0.4% 3.7% 5.6% 4.7% 0.8% 0.5% 6.1% 1.7% 1.7% 2.0% 1.8% 2.1% 2.5% 2.9% 2.2% 2.2% 4.1% 2.1% 3.3% 2.4% 2.4% 3.8% 3.1% 0.0% 0.0% 0.0% 0.0% 3.5% 4.6% 5.4% 3.4% 4.8% 3.3% 4.6% 6.2%
KUMULATIF 2.2% 2.6% 6.3% 11.9% 16.7% 17.5% 17.9% 24.0% 25.7% 27.4% 29.4% 31.2% 33.3% 35.9% 38.7% 40.9% 43.0% 47.1% 49.2% 52.5% 54.9% 57.4% 61.2% 64.3% 64.3% 64.3% 64.3% 64.3% 67.8% 72.4% 77.8% 81.2% 86.0% 89.3% 93.8% 100.0%

REAL 2.2% 0.4% 3.7% 5.6% 4.7% 0.8% 0.5% 6.1% 1.7% 5.5% 9.7% 2.2% 2.1% 2.1% 2.1% 3.3% 8.7% 4.0% 0.9% 0.9% 0.9%
KUMULATIF 2.2% 2.6% 6.3% 11.9% 16.7% 17.5% 17.9% 24.0% 25.7% 31.2% 40.9% 43.0% 45.1% 47.1% 49.2% 52.5% 61.2% 65.2% 66.1% 66.9% 67.8%
Selisih 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 3.8% 11.5% 11.8% 11.7% 11.3% 10.5% 11.6% 18.1% 18.0% 16.8% 14.4% 12.9%

Yang Membuat,