CONSTRUCTION GRAHA RENOVATION TIME SCHEDULE

2023

TAHUN 2023
No Working Plan Bobot July Agustus September Oktober November
17-23 24-31 '01-06 07-13 14-20 21-27 28-03 04-10 11-17 18-24 25-30 01-08 09-15 16-22 23-31 01-05 06-12 13-18

I General Work 2,44% 0,14% 0,14% 0,14% 0,14% 0,14% 0,14% 0,14% 0,14% 0,14% 0,14% 0,14% 0,14% 0,14% 0,14% 0,14% 0,14% 0,14%

Kick Of Meeting 0,05% 0,05%

II Interior Finishing Work

1 Drof off 1,56% 0,26% 0,26% 0,26% 0,26% 0,26% 0,26%

2 Lobby 1st Floor 9,93% 1,42% 1,42% 1,42% 1,42% 1,42% 1,42% 1,42%

3 Lobby 2nd Floor 10,89% 2,18% 2,18% 2,18% 2,18% 2,18%

4 Guest Area 2,37% 1,19% 1,19%

5 Corridor 8,41% 2,10% 2,10% 2,10% 2,10%

6 Guest Room 3,64% 0,61% 0,61% 0,61% 0,61% 0,61% 0,61%

7 Meeting Room 1 4,25% 0,71% 0,71% 0,71% 0,71% 0,71% 0,71%

8 Meeting Room 2 3,92% 0,65% 0,65% 0,65% 0,65% 0,65% 0,65%

9 Meeting Room 3 7,01% 1,00% 1,00% 1,00% 1,00% 1,00% 1,00% 1,00%

10 Trainning Room 3,43% 0,57% 0,57% 0,57% 0,57% 0,57% 0,57%

11 Gathering Room 15,85% 1,22% 1,22% 1,22% 1,22% 1,22% 1,22% 1,22% 1,22% 1,22% 1,22% 1,22% 1,22% 1,22%

12 Staircase 10,21% 1,46% 1,46% 1,46% 1,46% 1,46% 1,46% 1,46%

13 Lobby Multipurpose 1,95% 0,28% 0,28% 0,28% 0,28% 0,28% 0,28% 0,28%

14 Multipurpose Hall 6,12% 0,87% 0,87% 0,87% 0,87% 0,87% 0,87% 0,87%

15 Multipurpose Hall 1st Floor 7,98% 1,33% 1,33% 1,33% 1,33% 1,33% 1,33%

TOTAL 2,27% 2,36% 2,36% 4,33% 4,90% 4,90% 9,62% 10,79% 10,79% 10,01% 7,34% 7,57% 6,98% 3,15% 3,15% 3,15% 3,15% 3,15%
JUMLAH BOBOT % 100,00% 2,27% 2,36% 2,36% 4,33% 4,90% 4,90% 9,62% 10,79% 10,79% 10,01% 7,34% 7,57% 6,98% 3,15% 3,15% 3,15% 3,15% 3,15%
BOBOT RENCANA / MINGGU INI % 2,27% 4,64% 7,00% 11,33% 16,23% 21,14% 30,75% 41,55% 52,34% 62,35% 69,69% 77,26% 84,24% 87,39% 90,54% 93,70% 96,85% 100,00%
BOBOT AKTUAL MINGGU INI % 1,08% 1,08%
DEVIASI -1,19% -3,55%

PT.KUAT ANDAL NAN GEMILANG

AMIN
PROJECT MANAGER