TIME SCHEDULE HOTEL HORISON KERTAJATI

DESEMBER JANUARI FEBRUARI MARET


1 2 3 4
NO URAIAN BOBOT M1 M2 M3 M4 M1 M2 M3 M4 M5 M1 M2 M3 M4 M1 M2 M3 M4
1-Dec 8-Dec 15-Dec 22-Dec 29-Dec 5-Jan 12-Jan 19-Jan 26-Jan 2-Feb 9-Feb 16-Feb 23-Feb 1-Mar 8-Mar 15-Mar 22-Mar
sd. sd. sd. sd. sd. sd. sd. sd. sd. sd. sd. sd. sd. sd. sd. sd. sd.
7-Dec 14-Dec 21-Dec 28-Dec 4-Jan 11-Jan 18-Jan 25-Jan 1-Feb 8-Feb 15-Feb 22-Feb 29-Feb 7-Mar 14-Mar 21-Mar 28-Mar
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

1 PEK. PERSIAPAN, PRASARANA DAN PENUNJANG 10.66% 0.67% 0.67% 0.67% 0.67% 0.67% 0.67% 0.67% 0.67% 0.67% 0.67% 0.67% 0.67% 0.67% 0.67% 0.67% 0.67%

2 PEKERJAAN TANAH 1.75% 1.75%


2.1.1 Pekerjaan Tanah 0.08% 0.04% 0.04%
2.1.2 Pekerjaan urugan
3 PEKERJAAN STRUKTUR BETON
3.1.1 Pile Cap 3.22% 1.07% 1.07% 1.07%
3.1.2 Tie Beam 3.92% 0.49% 0.49% 0.49% 0.49% 0.49% 0.49% 0.49% 0.49%
3.1.3 Plat semi Basement 5.82% 0.65% 0.65% 0.65% 0.65% 0.65% 0.65% 0.65% 0.65% 0.65%
3.2.1 Balok Dan Plat lt.Dasar 13.28% 1.11% 1.11% 1.11% 1.11% 1.11% 1.11% 1.11% 1.11% 1.11% 1.11% 1.11% 1.11%
3.2.2 Balok Dan Plat lt.2 8.29% 1.38% 1.38% 1.38% 1.38% 1.38% 1.38%
3.2.3 Balok Dan Plat lt.3 4.05% 1.01% 1.01% 1.01% 1.01%
3.2.4 Balok Dan Plat lt.4 3.96% 1.32% 1.32% 1.32%
3.2.5 Balok Dan Plat lt.5 3.85% 1.28% 1.28% 1.28%
3.2.6 Balok Dan Plat lt.6 3.81% 1.27% 1.27% 1.27%
3.2.7 Balok Dan Plat lt.7 3.80% 1.27% 1.27% 1.27%
3.2.8 Balok Dan Plat lt.8 3.88% 1.29% 1.29% 1.29%
3.2.10 Balok Dan Plat lt.Atap & LMR 4.605% 1.54% 1.54% 1.54%

4 PEKERJAAN TANGGA
4.1.1 Tangga 1 2.64% 0.38% 0.38% 0.38% 0.38% 0.38% 0.38% 0.38%

6 CONVENTION HALL
6.1.1 Pekerjaan struktur beton 0.94% 0.31% 0.31% 0.31%
6.1.2 Struktur baja 2.09% 0.42% 0.42% 0.42% 0.42% 0.42%

7 PEKERJAAN PENUNJANG
7.1.1 STP 1.05% 0.26% 0.26% 0.26% 0.26%
7.1.2 GWT 0.76% 0.25% 0.25% 0.25%
7.1.3 PEK. Lain Lain Lantai Basement 3.68% 0.61% 0.61% 0.61% 0.61% 0.61% 0.61%
7.1.4 PEK. Ramp 0.99% 0.33% 0.33% 0.33%
7.1.5 Pondasi DPT 5.45% 0.91% 0.91% 0.91% 0.91% 0.91% 0.91%
7.1.6 Sparator Beam 0.86% 0.29% 0.29% 0.29%
7.1.7 Canopy 1.85% 0.46% 0.46% 0.46% 0.46%
7.1.8 Struktur Lain lain lantai 2 1.24% 0.25% 0.25% 0.25% 0.25% 0.25%
7.1.9 Struktur Lain lain lantai (provisional) 1.42% 0.36% 0.36% 0.36% 0.36%
7.1.10 PEKERJAAN PROVISIONAL SUM 1.94% 0.65% 0.65% 0.65%
7.1.11 PEKERJAAN PENGAJUAN KONTRAKTOR 0.09% 0.05% 0.05%

Jumlah Total 100.00%


1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
Rencana Bobot /minggu 4.667% 2.918% 2.878% 2.910% 3.818% 4.132% 5.776% 8.073% 9.216% 10.184% 10.031% 10.069% 8.595% 8.042% 6.489% 2.201%
Rencana Kumulatif Bobot /minggu 4.667% 7.585% 10.462% 13.372% 17.191% 21.323% 27.098% 35.172% 44.388% 54.572% 64.603% 74.673% 83.27% 91.310% 97.799% 100.000%
Realisasi Bobot /minggu 2.418% 1.503% 2.230% 4.221% 2.868% 2.056% 7.338% 5.386% 5.729% 4.670% 2% 2%
Realisasi Kumulatif Bobot /minggu 2.418% 3.921% 6.151% 10.372% 13.240% 15.296% 22.634% 28.020% 33.749% 38.419% 39.919% 41.419%
Deviasi Bobot /minggu -2.249% -3.664% -4.311% -3.000% -3.951% -6.027% -4.464% -7.152% -10.639% -16.153% -24.684% -33.254%