PT KUSUMA MEGAH GRUP

PENGAJUAN PROGRES PEMBANGUNAN

Perum THE 8 RESIDENCE Kavling 20


Kepala Tukang MISTARI Type Bangunan 62
KETERANGAN all in

PENGAJUAN
PROGRES PER MINGGU KEMARIN
N
URAIAN PEKERJAAN BOBOT TERMIN KE : 2 TERMIN KE : 3
O ACC
TGl. Pengajuan : 12-Jan-22 TGl. Pengajuan : 05-Mar-22
% BOBOT % BOBOT %
5 Cor Pembesian & Bekisting Ring Balok lt. 1 1,27 0% - 100% 1,27
6 Cor Pembesian & Bekisting Kanopi lt. 1 0,80 80% 0,64 75% 0,6
7 Cor Pembesian & Bekisting Tangga lt. 1 2,15 0% - 100% 2,15
8 Plesteran & Acian lt. 1 5,00 40% 2 60% 3
9 Benangan Sudut lt. 1 2,00 0% - 60% 1,2
1 Cor Pembesian & Bekisting Dak Lt. 2 5,61 0% - 100% 5,61
2 Pasangan Batu Bata Lt. 2 5,06 0% - 95% 4,81
3 Cor Pembesian & Bekisting Kolom Lt. 2 1,29 0% - 100% 1,29
4 Cor Pembesian & Bekisting Balok Gantung Lt. 2 1,20 0% - 100% 1,2
5 Cor Pembesian & Bekisting Ring Balok Lt. 2 1,29 0% - 100% 1,29
6 Cor Pembesian & Bekisting talang Lt. 2 0,54 0% - 100% 0,54
5 Cor Pembesian & Bekisting Kanopi Lt. 2 0,80 0% - 100% 0,8
7 Cor Pembesian & Bekisting Gewel Lt. 2 1,00 0% - 100% 1
7 Pasangan Pipa PVC 2 1/2" + " (Air Kotor) 0,49 50% 0,25 25% 0,12
Total Keseluruhan 100,00 25% 24,88

PARAF MANDOR

PARAF PENGAWAS

MENGETAHUI MANAGER TEKHNIK