WEEKLY REPORT
WTP BTR PROJECT
DATE : 25 Mar 2023
PROGRESS
BOBOT / WEIGHT BOBOT / WEIGHT COMMULATIVE ACTUAL UNTIL PREVIOUS WEEK ACTUAL PROGRESS THIS WEEK COMMULATIVE ACTUAL UNTIL THIS WEEK COMMULATIVE PLAN
NO. URAIAN / DESCRIPTION QTY UoM DEVIATION
(INDIVIDUAL) (OVERALL) UNTIL THIS WEEK
INDIVIDUAL OVERALL INDIVIDUAL OVERALL INDIVIDUAL OVERALL
Ade Chandra
Senior Project Enginner Project Manager MEP Site Manager Contractors Representative
PLAN SCHEDULE
WTP BTR PROJECT
a b c d e 04-Feb 11-Feb 18-Feb 25-Feb 04-Mar 11-Mar 18-Mar 25-Mar 01-Apr 08-Apr 15-Apr 22-Apr 29-Apr
INSTALLATION 90,00%
9 BWRO
COMMISSIONING 10,00%
14 PRECOMMISSIONING 5,00% 2,50% 2,50%
15 COMMISSIONING 5,00% 5,00%
GRAND TOTAL
PROGRESS PLAN THIS WEEK (%) 1,08% 11,11% 12,52% 13,23% 17,39% 10,79% 11,12% 6,96% 5,80% 2,50% 7,50%
CUMMULATIVE PROGRESS THIS WEEK (%) 1,08% 12,19% 24,71% 37,93% 55,32% 66,12% 77,24% 84,20% 90,00% 92,50% 100,00%
ACTUAL PROGRESS
WTP BTR PROJECT
a b e 04-Feb 11-Feb 18-Feb 25-Feb 04-Mar 11-Mar 18-Mar 25-Mar 01-Apr 08-Apr 15-Apr 22-Apr 29-Apr
INSTALLATION 90,00%
PROGRESS PLAN THIS WEEK (%) 1,08% 11,11% 12,52% 13,23% 17,39% 10,79% 11,12% 6,96% 5,80% 2,50% 7,50%
CUMMULATIVE PROGRESS THIS WEEK (%) 1,08% 12,19% 24,71% 37,93% 55,32% 66,12% 77,24% 84,20% 90,00% 92,50% 100,00%
ACTUAL PROGRESS (%) 0,54% 9,78% 18,56% 18,56% 11,71% 12,13% 7,79% 2,93% 0,00% 0,00% 0,00%
COMMULATIVE ACTUAL PROGRESS (%) 0,54% 10,32% 28,88% 47,45% 59,15% 71,29% 79,07% 82,00%
DEVIATION (%) -0,53% -1,87% 4,17% 9,51% 3,83% 5,17% 1,84% -2,20%
S CURVE
WTP BTR PROJECT
Date : 25-03-2023
Period : 19/03/2023 - 25/03/2023
90,00%
80,00%
70,00%
60,00%
50,00%
40,00%
30,00%
20,00%
10,00%
0,00%
24-Jan 03-Feb 13-Feb 23-Feb 05-Mar 15-Mar 25-Mar 04-Apr
PERIOD 04-Feb 11-Feb 18-Feb 25-Feb 04-Mar 11-Mar 18-Mar 25-Mar 01-Apr 08-Apr 15-Apr 22-Apr
PLAN PROGRESS 1,08% 12,19% 24,71% 37,93% 55,32% 66,12% 77,24% 84,20% 90,00% 92,50% 100,00%
ACTUAL PROGRESS 0,54% 10,32% 28,88% 47,45% 59,15% 71,29% 79,07% 82,00%
WEEKLY REPORT
BTR PROJECT PT. Batutua Tembaga Raya
Manpower
Quantity (prsn)
No Role
Mon Tue Wed Thu Fri Sat Sun
1 Senior Project Engineer 1 1 1 1 1 1 1
2 Application Engineer 1 1 1 1 1 1 1
3 Supervisor 1 1 1 1 1 1 1
4 HSE 1 1 1 1 1 1 1
5 Surveyor
6 Fitter 2 2 3 3 3 3 3
7 Helper 2 2 3 3 3 3 3
Equipment List
Quantity (Unit)
No Equipment
Mon Tue Wed Thu Fri Sat Sun
1 Welding 1 2 2 2 2 2 2
2 Grinda 2 2 3 3 3 3 3
3 Dryer 1 1 1 1 1 1 1
4 Fire extinguisher 1 1 1 1 1 1 1
5 Drilling machine 1 1 2 2 2 2 2
Information :
Location :
RWTP
Information :
Location :
RWTP
Information :
Location :
RWTP
Location :
RWTP
Information :
Location :
RWTP
Information :
Location :
RWTP
Location :
RWTP
Information :
Location :
RWTP
Object : COAGULATION
,FLOCCULATION AND pH
AJUSTER TANK
Date : 25-Mar-23
SITE MATTER