PT KUSUMA MEGAH GRUP

PENGAJUAN PROGRES PEMBANGUNAN

Perum THE 8 RESIDENCE Kavling 20


Kepala Tukang MISTARI Type Bangunan 62
KETERANGAN all in

PENGAJUAN
PROGRES PER MINGGU KEMARIN
N
URAIAN PEKERJAAN BOBOT TERMIN KE : 2 TERMIN KE : 3
O
TGl. Pengajuan : 12-Jan-22 TGl. Pengajuan : 05-Mar-22
% BOBOT % BOBOT
I PEKERJAAN TANAH & URUG
1 Uitzet & Bouwplank 0,34 100% 0,34 -
2 Galian Tanah 2,58 100% 2,58 -
3 Cor Pembesian Strouss & Footplate 3,63 100% 3,63 -
4 Cor Pembesian & Bekisting Sloof 1,46 100% 1,46 -

II PEKERJAAN PASANGAN Lantai 1


1 Pasangan Batu Bata lt. 1 5,06 90% 4,55 -
2 Cor Pembesian & Bekisting Kolom lt. 1 1,67 100% 1,67 -
3 Cor Pembesian & Bekisting Kolom Teras lt. 1 0,53 100% 0,53 -
4 Cor Pembesian & Bekisting Balok atas Jendela dan lt. 1 0,64 100% 0,64 -
5 Cor Pembesian & Bekisting Ring Balok lt. 1 1,27 0% - 100% 1,27
6 Cor Pembesian & Bekisting Kanopi lt. 1 0,80 80% 0,64 75% 0,6
7 Cor Pembesian & Bekisting Tangga lt. 1 2,15 0% - 100% 2,15
8 Plesteran & Acian lt. 1 5,00 40% 2 60% 3
9 Benangan Sudut lt. 1 2,00 0% - 60% 1,2

IIIPEKERJAAN PASANGAN Lantai 2


1 Cor Pembesian & Bekisting Dak Lt. 2 5,61 0% - 100% 5,61
2 Pasangan Batu Bata Lt. 2 5,06 0% - 95% 4,81
3 Cor Pembesian & Bekisting Kolom Lt. 2 1,29 0% - 100% 1,29
4 Cor Pembesian & Bekisting Balok Gantung Lt. 2 1,20 0% - 100% 1,2
5 Cor Pembesian & Bekisting Ring Balok Lt. 2 1,29 0% - 100% 1,29
6 Cor Pembesian & Bekisting talang Lt. 2 0,54 0% - 100% 0,54
5 Cor Pembesian & Bekisting Kanopi Lt. 2 0,80 0% - 100% 0,8
7 Cor Pembesian & Bekisting Gewel Lt. 2 1,00 0% - 100% 1
8 Plesteran & Acian Lt. 2 5,00 0% - -
9 Benangan Sudut Lt. 2 2,00 0% - -
10 Tali Air Atap 1,25 0% - -

IV PEKERJAAN KERAMIK Lantai 1

1 Pasangan Granit Dalam Ruangan Lt. 1 2,90 0% - -


2 Pasangan Keramik Teras Lt. 1 0,34 0% - -
3 Pasangan Keramik Lantai KM/WC Lt. 1 0,72 0% - -
4 Pasangan Keramik Dinding KM/WC Lt. 1 0,86 0% - -
5 Pasangan Keramik Dapur Lt. 1 0,50 0% - -
6 Pasangan Keramik Tangga Lt. 1 1,17 0% - -
7 Pasangan Keramik Carport Lt. 1 1,00 0% - -
8 Pasangan Keramik Fasad Lt. 1 0,60 0% - -
Jumlah 8,09 -

V PEKERJAAN KERAMIK Lantai 2


1 Pasangan Granit Dalam Ruangan Lt. 2 2,90 0% - -
2 Pasangan Keramik Lantai KM/WC Lt. 2 0,72 0% - -
3 Pasangan Keramik Dinding KM/WC Lt. 2 0,86 0% - -

VI PEKERJAAN ATAP

1 Rangka Atap (tanpa listplank) 2,50 0% - -


2 Genteng 1,50 0% - -
3 Bubungan 1,20 0% - -
4 Rangka Plafon (include listplank) 2,10 0% - -
5 Plafon 1,46 0% - -
Perum THE 8 RESIDENCE Kavling 20
Kepala Tukang MISTARI Type Bangunan 62
KETERANGAN all in

PENGAJUAN
PROGRES PER MINGGU KEMARIN
N
URAIAN PEKERJAAN BOBOT TERMIN KE : 2 TERMIN KE : 3
O
TGl. Pengajuan : 12-Jan-22 TGl. Pengajuan : 05-Mar-22
% BOBOT % BOBOT
VI PEKERJAAN CAT
I
1 Cat Dinding Lt. 1 4,45 0% - -
2 Cat Plafond Lt. 1 2,25 0% - -
3 Cat Dinding Lt. 2 4,45 0% - -
4 Cat Plafond Lt. 2 2,25 0% - -
5 Cat Daun Pintu 1,42 0% - -
6 Cat Genteng 1,80 0% - -
7 Cat No Drop 0,80 0% - -

VI PEKERJAAN PASANGAN KUSEN & PINTU


II
1 Kusen + daun jendela 0,00 #DIV/0! - -
2 Daun Pintu 0,95 0% - -
3 Handle Daun Pintu 0,50 0% - -
4 Pintu Kamar Mandi 0,76 0% - -

IX PEKERJAAN INSTALASI AIR

1 Septic tank & Resapan 2,50 65% 1,63 -


2 Bak Kontrol 0,46 0% - -
3 Bak Cuci / Kitchen Set 1,09 0% - -
4 Kloset / WC 0,79 0% - -
5 Pasang Kran 1/2" 0,56 0% - -
6 Pasang Pipa PVC 3/4" + 1/2" 0,49 0% - -
7 Pasangan Pipa PVC 2 1/2" + " (Air Kotor) 0,49 50% 0,25 25% 0,12
8 Pasangan Pipa PVC 4" (WC) 0,49 50% 0,25 -
Total Keseluruhan 100,00 25% 24,88

PARAF MANDOR

PARAF PENGAWAS

MENGETAHUI MANAGER TEKHNIK


SUMA MEGAH GRUP