You are on page 1of 1

3ML-102

ACCOMPLISHMENT
Item Description Wgt % Material Labor Material Labor OVERALL
3ML VST FOUNDATION
A Earthworks
1 Excavation 0.16% 0.11% 0.06% 0.11% 0.06% 0.16%
2 Backfill & Compaction 0.16% 0.11% 0.06% 0.11% 0.06% 0.16%
3 Sand Backfill 8.63% 5.61% 3.02% 5.61% 3.02% 8.63%
4 Lean Concrete 0.56% 0.36% 0.20% 0.36% 0.20% 0.56%
B Concrete Works
1 Ringwall 30.85% 20.05% 10.80% 20.05% 10.80% 30.85%
Premix Concrete 3000 psi, 28 days G1
C Steel Works
1 20mmØ x 6.0m RSB 5.30% 3.44% 1.85% 3.44% 1.85% 5.30%
2 16mmØ x 6.0m RSB 5.71% 3.71% 2.00% 3.71% 2.00% 5.71%
3 12mmØ x 6.0m RSB 7.57% 4.92% 2.65% 4.92% 2.65% 7.57%
4 10mmØ x 6.0m RSB 2.74% 1.78% 0.96% 1.78% 0.96% 2.74%
5 G.I. Tie Wire #16 1.45% 0.94% 0.51% 0.94% 0.51% 1.45%
D Formworks
1 Marine Plywood 4'x8'x1/4" 9.80% 6.37% 3.43% 6.37% 3.43% 9.80%
2 Coco Lumber 2"x3"x10' 13.23% 8.60% 4.63% 8.60% 4.63% 13.23%
3 16mmØ Tie Rod 5.44% 3.53% 1.90% 3.53% 1.90% 5.44%
4 Assorted Nails 0.71% 0.46% 0.25% 0.46% 0.25% 0.71%
E Plastering & Painting Works
1 Portland Cement 0.53% 0.34% 0.19% 0.00% 0.00% 0.00%
2 Sand 0.03% 0.02% 0.01% 0.00% 0.00% 0.00%
3 Epoxy Primer 0.39% 0.25% 0.14% 0.00% 0.00% 0.00%
F Sidewalk and Canal
1 Premix concrete 3.24% 2.10% 1.13% 0.00% 0.00% 0.00%
5 10mm dia x 6.0m RSB 2.41% 1.57% 0.84% 0.00% 0.00% 0.00%
6 #16 GI Tie Wire 0.04% 0.03% 0.02% 0.00% 0.00% 0.00%
7 CHB 4" 1.06% 0.69% 0.37% 0.00% 0.00% 0.00%
TOTAL 100.00% 65.00% 35.00% 92.29%