Issues and Concerns Scope by Remarks Closed Date
1. Anchor Bolt repair MCC Manpower for repair (welder and in progress
fitter)
2. Lacking fabricated Erection Jigs MCC - Fabrication Incomplete delivery – raw materials
delivered on site i.e. radius plate,
finger bar; etc.
3. Center Column MCC - Fabrication Late delivery – Delivered: May 3 May 3
4. Center Ring MCC - Fabrication Late delivery – Delivered: May 12; May 12
incomplete; no gusset plate
5. Un-availability of 3rd Course Shell MCC - Fabrication Late delivery – Delivered: May 6, May 6
Plate- Tank 105
6. Shell Nozzle MCC - Fabrication Delivered: May 16; incomplete – no
repad; incomplete
7. Stairway step MCC - Fabrication Partial Delivery: May 12 no rail post,
incomplete- (steps only) for 4 tanks
8. Stairway inter-landing platform MCC - Fabrication Not yet delivered; partial delivery 10
June
9. Rail post - stairway MCC - Fabrication Pick up at Tanza: May 20 Partial
10. Scaffolder 1 personnel only
11. Scaffold Materials Incomplete - May 3; scaffold pipe only
12. Bracket Scaffold MCC - Fabrication Incomplete – need for erection and
welding for access and platform
13. Pipe Fittings 4”, 6”, 10” Incomplete – bolt & nuts, gasket,
elbows, flanges
14. Roof frames - Gantry MCC - Fabrication Drawing for review and analyzed – with additional plate support
erection sequence in connection of T2 and G1
ass’y.
15. Electrical Cables Not yet delivered on site; partial
delivery -10 June
16. Piping – 2” dia. + fittings Not yet delivered on site -
17. Purlins – delivered on site; May 31 delivered on site
unpainted
18. Stairway Handrails Not yet delivered
19. Access Stair - Gantry For replacement - Fabrication
20. Riser Support MCC - Fabrication Not comply with AFC drawing Riser and Foam line re-
arrangement
21.
SPI