Fence

ACCOMPLISHMENT
Item Description Wgt % Material Labor Material Labor OVERALL
PERIMETER FENCE (217.96 lm)
A Earthworks
1 Excavation 1.21% 0.79% 0.42% 0.79% 0.13% 0.92%
2 Backfilling and Compaction 2.69% 1.75% 0.94% 0.00% 0.00% 0.00%
3 Gravel Base 0.54% 0.35% 0.19% 0.35% 0.05% 0.40%
B Concrete Works
1 Reinforced Concrete 15.22% 9.90% 5.33% 0.89% 0.53% 1.42%
C Masonry Works
1 CHB 5" 6.84% 4.44% 2.39% 2.22% 0.12% 2.34%
2 Cement 6.93% 4.51% 2.43% 0.00% 0.12% 0.12%
3 Sand 1.35% 0.88% 0.47% 0.00% 0.02% 0.02%
D Steel Works
1 16mmØ x 6.0m RSB 9.04% 5.87% 3.16% 2.94% 0.85% 3.79%
2 12mmØ x 6.0m RSB 4.05% 2.63% 1.42% 1.32% 0.38% 1.70%
3 10mmØ x 6.0m RSB 12.62% 8.20% 4.42% 4.10% 1.19% 5.29%
5 G.I. Tie Wire #16 1.25% 0.81% 0.44% 0.41% 0.12% 0.52%

E Formworks
1 Marine Plywood 4'x8'x1/4" 4.84% 3.14% 1.69% 0.63% 0.29% 0.92%
2 Coco Lumber 2"x3"x12' 8.01% 5.21% 2.80% 1.04% 0.45% 1.49%
3 Assorted Nails 0.10% 0.07% 0.04% 0.01% 0.01% 0.02%
F Painting
1 Painting 25.32% 16.46% 8.86% 0.00% 0.00% 0.00%
TOTAL 100.00% 65.00% 35.00%
18.96%