5.
MORTAR
MRS, 4th QUARTER OF 2011 ( OCT to DEC ) DISTRICT LAHORE
Dry Material Required for Dry Material Required for
100 Cft. Wet (Ready) Mortar One Cum Wet (Ready) Mortar
S. No. Ratio of Mortar Cement Lime Cement Lime Sand
(50 Kg) Putty Sand (50 Kg.) Putty Cum.
Bag Cft. Cft. Bag. Cum
1 2 3 4 5 6 7 8
1 Cement : Sand
1 : 2 33.48 82 11.83 0.82
1 : 3 23.11 85 8.16 0.85
1 : 4 18.37 90 6.49 0.90
1 : 5 14.70 90 5.19 0.90
1 : 6 13.61 100 4.81 1.00
1 : 7 11.68 100 4.12 1.00
1 : 8 10.21 100 3.61 1.00
2 Cement : Lime : Sand
1 : 1 : 6 12.25 15.0 90 4.33 0.15 0.90
1 : 1 : 7 10.70 13.1 92 3.78 0.13 0.92
1 : 1 : 8 9.39 11.5 92 3.32 0.12 0.92
1 : 1 : 9 8.52 10.44 94 3.00 0.10 0.94
1 : 1 : 10 7.67 9.4 94 2.71 0.09 0.94
1 : 2 : 8 9.19 22.5 90 3.25 0.23 0.90
1 : 2 : 9 8.16 20.0 90 2.88 0.20 0.90
1 : 2 : 10 7.67 18.8 94 2.71 0.19 0.94
1 : 2 : 12 6.39 15.66 94 2.26 0.16 0.94
1 : 3 : 12 6.26 23.0 92 2.21 0.23 0.92
1 : 3 : 14 5.47 20.1 94 1.93 0.20 0.94
1 : 3 : 16 4.82 17.7 94 1.70 0.18 0.94
1 : ¼ : 3 23.11 7.0 85 8.16 0.07 0.85
3 Lime : Sand
1 : 2 43 86 0.43 0.86
1 : 3 31 93 0.31 0.93
Chap-5 (Mortar) Page 38
5. MORTAR
MRS, 4th QUARTER OF 2011 ( OCT to DEC ) DISTRICT LAHORE
Dry Material Required for 100 Cft. Dry Material Required for
Wet (Ready) Mortar one M3 Wet (Ready) Mortar
S. Ratio of Mortar Clay Lime Sand Surkhi Cinder Clay Lime Sand Surkhi Cinder
No. (Putty) (Putty)
Cft. Cft. Cft. Cft. Cft. M3 M3 M3 M3 M3
1 2 3 4 5 6 7 3 4 5 6 7
4 Mud 135 1.35
5 Lime : Surkhi
2 : 3 49.00 - 73.5 - 0.49 - 0.74 -
1 : 2 40.75 - 81.5 - 0.41 - 0.82 -
1 : 3 30.30 - 91.0 - 0.30 - 0.91 -
6 Lime : Sand : Surkhi
1 : 1 : 1 40.50 40.5 40.5 - 0.41 0.41 0.41
7 Lime : Cinder
1 : 1 57.0 - 57.0 - 0.57 - - 0.57
Wet material required for 100 Cft. Wet material required for 1M³ (35.32 Cft)
masonry (including wastage): masonry ( including wastage) :
1 Brick Masonry :
a) Mud Mortar 35.00 Cft 0.35 M3
b) Cement, Sand 25.00 Cft 0.25 M3
c) Cement, Lime (Putty) Sand 25.00 Cft 0.25 M3
d) Lime (Putty) Sand 25.00 Cft 0.25 M3
2 Stone Masonry :
a) Random rubble, uncoursed
i) Foundation and Plinth 45.00 Cft 0.45 M3
ii) Superstructure 40.00 Cft 0.40 M33
iii) Coursed 35.00 Cft 0.35 M
b) Ashlar Block in course or Scabled masonry 30.00 Cft 0.30 M3
c) Ashlar fine masonry 20.00 Cft 0.20 M3
(1) Cement 1 Cft. = 40.8233 Kg
Notes : (2) Unslaked lime 1.7 Cft. = 37.3242 Kg
(3) Slaked lime 2.5 Cft. = 37.3242 Kg
(4) Quick lime 40 Kg Will yield 2.6 Cft. lime putty.
Chap-5 (Mortar) Page 39