Conversion

1berga =12meter
1kg/m = 0.222d (mm) ^2 divided by 36

Determination
of Material
consumption

General Formula

1. Assumed Concrete mix ratio------------------- = 1: 2: 4


Volume & concrete------------------------------ = xm3
22
a) Cement = 1/7 x m3 x1400kg x 1.3 shrinkage x 1.05 wastage.
b) Sand = 2/7 x m3 shrinkage x 1.15 wastage.
c) Gravel = 4/7 x m3 shrinkage x 1.15 wastage.

2. Assumed cement mortar mix ratio----------------- = 1:3


Volume of cement mortar--------------------------- = ym3

a) Cement = ¼ ym3 1400kg/ m3 x 1.2 shrinkage x 1.05 wastage.


b) Sand = ¾ ym3 x 1.2 shrinkage x 1.15 wastage.

3. From 1m3 of masonry work, it is assumed that 40 % of it is mortar for water tight structures
& 30% for other structures.

Assumed cement mortar mix ratio ------------------= 1:4


Volume of masonry work --------------------------= 1m3
Volume of mortar------------------------------------- = 0.4m3

a) Cement = 1/5 x 0.4m3 x 1400kg /m3 x 1.2 x 1.05 = 141.12kg =150kg = 1.5 qt
b) Sand = 4/5 x 0.4 m3 x 1.2x1.15= 0.44m3

Unit weight
Measured unit weight of fresh plain concrete = 2300kg/m3
“ “ “ of R.C = 2400kg /m3
“ “ “ of Cement = 1400kg /m3
“ “ “ of Sand = 1350kg /m3
“ “ “ of Gravel = 1300kg /m3
“ “ “ of stone gravel = 2400kg /m3
“ “ “ of River Sand = 1840kg /m3
“ “ “ of Cement mortar = 2300kg /m3
“ “ “ of Basaltic stone = 2700kg /m3

Standard concrete mix per 50 kg (Bag) Of Cement

 Standard box size : Length x width x height


50 x 40 x 16
50 x 40 x 18
50 x 40 x 20
1. Concrete
 Concrete and Nominal mix proportion Quantity of materials

23
Concrete C-5
 Mechanical mix
*Mix ratio ……… 1:3.5:8 Cement =153k/m3 of concrete
Box size……….. 40x50x18 Sand = 0.4186m3/m3
OR *
Mix ratio ………….1:4:6 Gravel = 0.9568 m3/m3
Box size……….. 40x50x20
Concrete C-10
 Mechanical mix
Mix ratio ……… 1:3:6 Cement =191.1kg/m3
Box size………(40x50x18) Sand = 0.4485m3/m3
Gravel = 0.897 m3/m3
Concrete C-15
 Mechanical mix
Mix ratio ……… 1:2:4 Cement = 273kg/m3
Box size……… (40x50x18) Sand = 0.427m3/m3
Gravel = 0.854 m3/m3
Concrete C-20
 Mechanical mix
Mix ratio ……… 1:2:3 Cement = 319 kg/m3
Box size………(40x50x18) Sand = 0.498m3/m3
Gravel = 0.748 m3/m3
Concrete C-25
 Mechanical mix
Mix ratio ……… 1:1.5:3 Cement = 348.00 kg/m3
Box size………(40x50x18) Sand = 0.408m3/m3
Gravel = 0.815 m3/m3
Concrete C-30
 Mechanical mix
Mix ratio … 1:1.5:2 Cement = 424 kg/m3 of Concrete
Box size……… (40x50x18) Sand = 0.498 m3/m3
Gravel = 0.607 m3/m3
Note:- It is advised to add 10% extra cement in hand mixing to make up for in adequate
mixing.
24
2. Natural stone masonry work
 40cm thick hard basaltic stone masonry of cement mortar (1:4 mix) in full joint for
foundation wall & water structures
Assumption:- From 1m3 of stone masonry work, 60% is assumed to be stone and the
remaining 40% is mortar.
Material Type Quantity of masonry
a) Basaltic stone-------------------- 0.75m3 /m3 of masonry
b) Mortar------------------------------0.42 m3 /m3
C) Cement ----------------------------148.176kg /m3
D) Sand -------------------------------- 0.484 m3 /m3

 40cm thick trachyite stone wall bedded in cement mortar (1:4) sides left for pointing or
plastering (for supper structures like building)
a) Trachytic Stone ------------------------------0.901 m3 /m3 of masonry
b) Cement mortar -------------------------------- 0.315 m3 /m3
c) Cement ----------------------------------------- 112kg /m3
d) Sand -------------------------------------------- 0.35 m3 /m3

3. Hollow concrete Block work


Assumptions :- Joint between block is 2cm, wastage …………..5%
 100 mm thick hollow concrete block wall bedded is cement mortar 1:4 both sides left for
pointing or plastering
a) Hollow concrete block -------------------- 12.5 Pcs/m2
b) Mortar (with 5% wastage)----------------0.0088m3/m2
c) Cement-------------------------------------- 3kg/ m2
d) Sand ---------------------------------------- 0.00976 m3/m2
 150mm thick concrete block wall bedded in cement mortar (1:4) both side left
for pointing or plastering
a) Hollow concrete block--------------------12.5 pcs/m2
b) Mortar -------------------------------------- 0.0149 m3/m2
c) Cement ------------------------------------- 5.26kg/m2
d) sand ---------------------------------------- 0.0165 m3/m2

25
 200mm thick concrete block wall bedded in cement mortar (1:4 mix) both side left for
pointing or plastering
a) Hollow concrete block ---------------------------------- = 12.5Pcs /m2
b) Mortar ------------------------------------------------------ = 0.021 m3/m2 of Block work
c) Cement ----------------------------------------------------- = 7.41kg /m2
d) Sand--------------------------------------------------------- = 0.0232 m3/m2
4. Mortar for plastering work
4.1 Plastering and pointing
4.1.1 Compo mortar -------------------------------------- m2------ Cement –--tl - 0.056
Lime - – Qtl - 0.089
Sand ---- m3 - 0.017
4.1.2 Cement plasters ---------------------------------- m2 -----Cement – Qtl – 0.073
Sand -- m3 - 0.018
4.1.3 Fire coat lime plastic----------------------------- m2-------- Lime -– Qtl – 0.026
Sand -- m3 - 0.003
4.1.4 Fire Coat gypsum plastic ----------------------- m2------Gypsum–--Qtl – 0.017
Lime – Qtl – 0.058
4.1.5 Fire coat cement plaster------------------------- m2 -----Cement – Qtl - 0.019
Sand -- Oll - 0.003
4.1.6 Fire renders coat --------------------------------- m2-----= Cement – Qtl – 0.013
Lime - – Qtl – 0.032
Sand -- m3 - 0.005
4.2. Cement pointing with mortar mix 1:3
4.2.1. Brick wall ----------------------------------------m2 -----Mortar - m3 - 0.0027
Cement –----Qtl - 0.0095
Sand --------- m3 - 0.002

4.2.2 Hollow concrete Block wall M2--------- m2--- Mortar ------- m3 - 0.0011
Cement –---- Qtl - 0.0039
Sand --------- m3 - 0.001
4.2.3 Stone wall-------------------------- m2 ---Mortar ----- M3 - 0.036
Cement –----Qtl - 0.0126
Sand ---------m3 -
0.0027
26
4.1.2 Cement plaster
i) Cement mortar (1:1 mix) for plastering work having thickness of 30mm with
a) Mortar ---------------------------------------------------------= 0.03 m3/m2
b) Cement ------------------------------------------------------- = 26.40kg/m2
c) Sand ---------------------------------------------------------- = 0.0207 m3/m2
ii) Ditto but cement mortar with 1:2mix
a) Mortar ---------------------------------------------------- = 0.03 m3/m2
b) Cement --------------------------------------------------- = 17.64kg /m2
c) Sand ------------------------------------------------------ = 0.03 m3/m2
iii) Ditto but cement mortar with 1:3mix
a) Mortar ---------------------------------------------------- = 0.03 m3/m2
b) Cement ---------------------------------------------------- = 13.23 kg/ m2
c) Sand-------------------------------------------------------- = 0.0311 m3/m2
iv) Ditto but cement mortar with 1:4 mix
a) Mortar ----------------------------------------------------- = 0.03 m3/m2
b) Cement---------------------------------------------------- = 10.58kg /m2
c) Sand ------------------------------------------------------ = 0.03312 m3/m2
V) Ditto but cement mortar with 1:4 mix
a) Mortar ----------------------------------------------------- = 0.03 m3/m2
b) Cement---------------------------------------------------- = 8.82kg /m2
c) Sand ------------------------------------------------------ = 0.0345 m3/m2
5. 30mm thick cement Sand Screeding 1:3; for irregularities Plus 5% wastage
 Volume of mortar -----------------------------= 0.0315 m3/m2
 Cement----------------------------------------- = 0.14qt /m2
 Sand-------------------------------------------- = 0.034 m3/m2
 Cement grout--------------------------------- = 1.5 lit /m2

6. One coat of tyro lean type rendering in cement sand mortar (1:4 mix) with
15% wastage (6mm-10mm)
a) Mortar ----------------------------------------------------- = 0.0115m3
b) Cement---------------------------------------------------- = 0.041 qt /m2

27
c) Sand ------------------------------------------------------ = 0.0127 m3/m2

7. Pointing of dressed stone masonry wall with cement mortar (1:3 mix)
including 15% wastage.
a) Mortar ----------------------------------------------------- = 0.00513 m3
b) Cement---------------------------------------------------- = 2.26kg (0.00226qt/m2)
c) Sand ------------------------------------------------------ = 0.00531 m3/m2 of pointing
8.. Pointing of fair faced concrete block wall with cement mortar (1:3 mix)
a) Mortar ----------------------------------------------------- = 0.00308 m3/m2
b) Cement---------------------------------------------------- = 0.014 qt/m2)
c) Sand ------------------------------------------------------ = 0.00319m3/m2

9. Pointing of burned brick wall with cement mortar (1:3 mix)


a) mortar -----------------------------------------------------= 0.00618 m3
b) cement----------------------------------------------------= 0.020 qt/m2
c) sand------------------------------------------------------ = 0.00638m3/m2
10. Flooring work
 20 x 200 x200mm terrazzo tile ( cement tile) flooring bedded in cement screed (1:3
mix)
a) Terrazzo tile (with 2% wastage-----------------------------= 25.5pcs / m2
b) 20mm thick bedding screed (mortar with 5% wastage )= 0.021 m3/m2
c) Cement ------------------------------------------------------ = 0.0926
d) Sand----------------------------------------------------------= 0.0217 m3/m2
e) Cement groute for pointing ------------------------------= 0.00168 m3/m2
f) Polishing chemical--------------------------------------- =
 20 x 200mm Plastic tile
a) Plastic tile (with 2% wastage) ----------------------------= 25.5
b) Adhesive including waste --------------------------------= 0.04 lit /m2
c) Polishing chemical-----------------------------------------=

 6mm x 150 x 150mm glazed ceramic wall bedded in cement mortar (1:3)
a) Ceramic tiles (with 2% waste) -------------------------= 45.3pes /m2
b) 10mm thick bedding with 5% wastage ---------------= 0.0105 m3/m2
28
c) Cement ---------------------------------------------------= 0.01086 m3/m2
d) Cement groute for pointing---------------------------= 0.0024 m3/m2

 20mm thick marble slate flooring bedded in cement mortar 1:3


a) Marble slate-----------------------------------------------------------------= 1.02 m3/m2
b) 20mm thick mortar bedding screed (with 10% wastage)-------------= 0.022 m3/m2
c) cement ----------------------------------------------------------------------= 0.097qt/ m2
d) Sand ------------------------------------------------------------------------= 0.023 m 3/m2
e) Cement groute for pointing with 20% waste-------------------------= 0.00072

 Cement tile skirting


o 20mm x 100mm x 200mm terrazzo tile skirting with bedding cement screed 1:3
mix
a) Terrazzo tile (cement tile) with 5% waste ------------------= 5.5pes /m2
b) Mortar -----------------------------------------------------------= 0.0011
c) Cement----------------------------------------------------------= 0.00485qt /m2
d) Chemical for polishing----------------------------------------=

 Timber skirting in Tid wood fixed on the wall


a) l0cm x 1.5cm timber ( with 10% wastage) ----------------= 1.10m /m2
b) Fixer + 5% waste ---------------------------------------------= 2.1pes /m2
 Plastic tile skirting
o 2mm x 100mm x 200mm plastic tile skirting with adhesive
a) Plastic tile (with 2% wastage)---------------------------------= 513Pes /m2
b) Adhesive --------------------------------------------------------= 0.4 lit /m2
11. Carpentry & joinery
 Standard nail size and No of nails per kg.
1. Nails Pes Kilo grams
1cm------------------------ 950 ------------------ 1kg
2cm----------------------- 815--------------------1kg
4cm----------------------- 546--------------------1kg
6cm----------------------- 275-------------------- 1kg
7cm----------------------- 180--------------------1kg
8cm----------------------- 127--------------------1kg
29
10cm---------------------- 63--------------------1kg
12cm---------------------- 44--------------------1kg
15cm---------------------- 29 -------------------1kg

Roofing nails :- 1kg---------- = 105pcs


Roofing nails:- 1 packet----- = 3kg=315pcs
Plastic washer:- 1packet---- = 300pcs

Assumption:-
a) Roof work ---- R. Nails = 14pcs /C.I sheet
Purline = 8cm nail (8pcs/ perline)
Truss = 10 or 12cm nail ( 20-35pcs /Truss)
b) Ceiling work ---- Batten = 8cm nail
Chip wood = 4 cm nail (80pcs/chipwood)
c) Band Iron ------- 6cm nail (10pcs/one Iron banding)

11.1 Eucalyptus truss for span up to 10m


a) 10-12cm diam upper & lower eucalyptus wood truss members
with 15% wastage ------------------------------------1.15mts/ml
b) nails----------------= 0.4kg/ml=0.04 x 10m = 25.2pcs of #10cm
C) Band Iron---------= 0.12kg/ml
d) 8-10cm diam vertical & diagonal truss member with wastage 15%= 1.15mts/ml
e) Nails------------= 0.06kg/m2
f) Band Iron---= 0.17kg/ m2

11.2. Purline
a) Diam-6-8cm eucalyptus wood purline with 10% wastage--------------= 1.1m/ml
b) Nails ----------------------------------------------------------------------------=0.013kg/ml

11.3. Zigba wood truss out of 5*10 &5/15cm up to 10m. Span


a) 5* 10cm zigba wood upper member in truss with 10% wastage--------=1.1m/ml
b) Nails --------------------------------------------------------------------------- = 0.0kg/ml
c) Band Iron-----------------------------------------------------------------------= 0.10kg/ml
d) 5*15cm zigba wood lower member in truss with 10% wastage---------=1.1m/ml
30
e) Nail ------------------------------------------------------------------------------= 0.04kg/ml
f) Iron band ------------------------------------------------------------------------= 0.2kg/m2

11.4. purline 5*7cm zigba wood purline with 5% wastage ----------------= 1.05m/ml
Nails---------------------------------------------------------------------------= 0.015kg/ml

11.5. Roof work


a) Roofing sheet----------------------------------------------------------= 1.25 m3/m2
b) Roofing nail (with 5% wastage)---------------------------------= 14Pc/CIS
c) Plastic washer --------------------------------------------------------=14Pc/CIS
d) 400mm 28 gauge roof ridge cover --------------------------------= 14Pc/CIS
e) 500mm wide roof valley cover in 38 28 gauge
f) Nail for ridge cover with 5% wastage -------------= 4.2x 5pes/m 0.028kg/m
g) plastic washer------------------------------------------= 5pes/m
L) Eave gutter 100x100m (girth not exceeding 400mm)
a) 0.5mm galvanized steel sheet +5% waste -------------------------- = 0.42 m3/ml
or ( 0.42 m2/m1 x 4.12kg /m2)----------------------------------------------= 1.73kg/ml
b) 3mm x 20mm and length of 400mm steel bracket with 5% wastage ----= 0.2kg/ml

11.6 Fascia Boord


a) 30cm zigba or Tid wood with 15%-------------- 1.15m/ml
b) Nails ------------------------------------------------ 0.015kg/ml
c) Bottens
11.7 Chip wood ceiling nailed on 4*5 zigba wood battens spaced 600cm c/c
a) 4*5cm zigba wood battens with 15% wastage -------------4m1.55 = 4.6m/m2
b) Chip wood with 10% wastage--------------------------------------------=1.10m2/m2
c) Nail of 6cm ------------------------------------------------------------------=0.07kg/m 2
d) Nail of 3cm-------------------------------------------------------------------= 0.07kg/m2
e) Corner list --------------------------------------------------------------------=
11.8 Ceiling/Soffti --------------------------------- m2--- Covering matrices –-- m2 - 1.05
=Batter---m-3 - 0.71
Eucalyptus braces--- m - 1.23
“Suspension-- m - 1.23

31
Nail --- kg - 0.17
11.9 Skirting timber ------------------------------- m--------------------- Board --- m - 1.10
Nail –---- kg - 0.05
11.10 Door ----------------------------------- No -----------------Door se - No - 1.05
Key/lock ---- No – 1.05
Hinge –------- N2 - 3.00
Pant –--------- Lit - 0.35

12. PANTING
12.1 Oil paint ------------------------------------------- m2 ----- 1st Coat--- --lit - 0.06
2nd Coat --- lit - 0.055
3rd Coat------ lit - 0.045
12.2 Plastic paint ---------------------------------------- m2-----------1st Coat -------lit - 0.10
2nd coat-------- lit - 0.08
3rd coat-------- lit - 0.066
12.3 Systemic enamel paint -------------------------------m2 Primer------- lit - 0.05
2nd coat------ lit - 0.07
3rd coat-------- lit - 0.055

13. GLAZINE
14.1 Glass -------------------------------------------- m2 Glass --------m2 - - 1.10
Putty -------Kg - 0.40
14SANITARY ENSTALATON
a) Pipes
14.1 Galvanized steal ----------------------------------m ----------pipes----- - m - 1.05
Joints Compound- gram - 2.00
Hemp – gram – 6.00
Accessories No - 0.20
14.2 PVC ----------------------------------------- m-------- pipes----- - m – 1.0
Accessories- No – 1.00
Adhesive – Kg – 0.12
14.3 Pre cost concert, diam.100mm---------------- m--------- pipe – m - 1.05
Mortar mix1:2- m3 - 0.0005

32
Cement -- Qtl - 0.0025
Sand – m3 – 0.001
14.4 Pre cost concert, diam.150mm -------- m pipe – m 1.05
Mortar mix1:2- m3 - 0.0012
Cement -- Qtl - 00.006
Sand – m3 – 0.001

14.5 Pre cost concert, diam. 200mm-------------- m pipe – m - 1.05


Mortar mix1:2- m3 - 0.002
Cement -- Qtl - .009
Sand – m3 – 0.001
14.6 Pre cost concert, diam. 300mm------------- m pipe – m - 1.05
Mortar mix1:2- m3 - .003
Cement -- Qtl - 0 .01
Sand – m3 – 0.002
14.7 Pre cost concert, diam. 400mm-------------- m pipe – m - 1.05
Mortar mix1:2- m3 - 0.005
Cement -- Qtl - 0.02
Sand – m3 – 0.002
14.8 Pre cost concert, diam. 500mm-------------- m pipe – m - 1.05
Mortar mix1:2- m3 - 0.007
Cement -- Qtl - 0.03
Sand – m3 – 0.002

14.9 Pre cost concert, diam. 600mm------ m pipe – m - 1.05


Mortar mix1:2- m3 - 0.05
Cement -- Qtl - 0.007
Sand – m3 – 0.002
14.10 Pre cost concert, diam. 800mm------ m pipe – m - 1.05
Mortar mix1:2- m3 - 0.005
Cement -- Qtl - 0.02
33
Sand – m3 – 0.002

14.11 Pre cost concert, diam. 1000mm---- m pipe – m - 1.05


Mortar mix1:2- m3 - 0.005
Cement -- Qtl - 0.02
Sand – m3 – 0.002
15. Fence work
- 100mm x 10mm thick & over all length of 2400mm fence post with wood sank in to
concrete + 5% waste.
a) 2400mm post + 5% wastage ------------------= one post with 2520mm
b) Barbed wire fence + 2% wastage-------------= 3.54m/ m2
c) concrete ( 1:2:4 mix)---------------------------= 0.045 m3/post
d) Nail #7 with 15% wastage --------------------= 5pcs /post or 0.028kg/post

16. Hard coring


- 25cm thick basaltic stone hard coring with 15% of decrease & waste ------=0.313m3/m2
- coarse gravel for blinding with average thickness of 7cm including
15% decrease & waste ------------------------------------------------------------= 0.08 m3/ m2
17. Form work
Assumptions
1) Timber form work and other scaffolding works can have a maximum of three usage
(can be re used 3 times) in similar work at one project.
2) Timber form work and other scaffolding work in contact with water bodies will have
only one project usage.
3) Steel panel as a form work can have 10 project usage
4) Amount of battens and other scaffolding works are constants for both types of form
work (Steel & timber)
17.1. Form work for slab on the ground (Form work for edge of slab at the ground not
exceeding 300mm)
a) 2.5cm thick board ( with 5% wastage) (4usage) ----------------------- 0.263 m3/ m2
b) batten of 50mmx75mm ( with 5% wastage) (4usage) ----------------- 0.6m/ m2
c) ǿ6cm Eucalyptus Strut ( with 5% wastage) (4usage) ----------------- 0.2.05m/ m2
d) ǿ12cm Eucalyptus pole (4usage) --------------------------------------- 0.715m/ m2
34
e) Nail #6 (with 10% wastage)--------------------------------- 39pcs/ m2= 0.142 kg/m2
f) Mould oil--------------------------------------------------------------------0.06lit/ m2
17.2. Form work for sides of the column of height 2.8m
a) 2.5cm thick boards ( with 5% wastage) (4usage) ----------------------- 0.263 m2/ m2
b) batten of 50mmx75mm (4usage) ------------------------------------------ 0.71m/ m2
c) ǿ8cm Eucalyptus (4usage) ------------------------------------------------- 2.75m/ m2
d) Nail #6 -------------------------------------------------------------24pcs/m2=0.0873kg/m2
#8------------------------------------- ------------------------10pcs/m2=0.079kg/m2
e) Mould Oil----------------------------------------------------------- 0.06 lit//m2

17.3. Form work for sides of the ground beam & footing width over 30cm with
thickness of 30cm
a) 2.5cm thick board ( with 5% wastage) (4usage) ----------------------- 0.263 m2/ m2
b) battens of 50mmx75mm (with 5% wastage) (4usage) ---- ------------ 0.6m/ m2
c) Scaffoldings
ǿ 6cm Eucalyptus strut (4usage) ---------------------- 2.05m/ m2
ǿ 12 Eucalyptus (4usage) -------------------------- -------------2.86m/m2
d) Nail #6 with 5% wastage --------------------------------------------------0.142kg/m2
e) Mould Oil--------------------------------------------------------------------- 0.06lit//m 2
17.4. Form work for sides of the top beam and lintel width over 30cm with thickness of
30cm
a) 2.5cm thick board ( with 5% wastage) (4usage) ----------------------- 0.263 m2/ m2
b) battens of 50mmx75mm (with 5% wastage) (4usage) ---- ------------ 0.71/ m2
c) Scaffoldings (4usage)

ǿ 12cm Eucalyptus -----------------------------------------------------0.75/m2

ǿ 10cm Eucalyptus---------------------------------------------------11.298m/ m2

ǿ 8cm Eucalyptus---------------------------------------------------11.298m/ m2

ǿ 6cm Eucalyptus--------------------------------------------------- 1.4m/ m2
d) Nail # 10 ------------------------------------------------------------------------------0556kg/m2
# 6 ------------------------------------------------------------------------------00945kg/m2
e) Mould Oil--------------------------------------------------------------------------- 0.06lit//m 2
17.5. Form work for slab above ground level (3m above G.L)
a) 2.5cm thick board (4usage) -------------------------------------- 0.263 m2/ m2

35
b) ǿ 10cm Eucalyptus @ 60cm c/c----------------------------------38.587m/m2
c) ǿ 8cm Eucalyptus @ 60cm c/c ------------------------------------7.35m/ m2
d) ǿ 6cm Eucalyptus--------------------------------------------------- 14.7m/ m2
e) Nail # 12 ----------------------------------------------------------- 0.295kg /m2
# 8--------------------------------------------------------------- 0.205kg /m2
17.6. Form work for sides of the walls (concrete wall) for a height of 1.05m
a) 2.5cm thick board (With 5% wastage (4usage) -------------------------- 0.263 m2/ m2
b) battens of 50mmx75mm (with 5% wastage) (4usage) --------------------- 0.6m/ m2
c) ǿ 10cm Eucalyptus pole (4pcs for 2.86m) with 3.6m height
-------------------------------------------------------------------------4.41m/ m 2= 1.102m/ m2
d) ǿ 8cm Eucalyptus horizontal member for strut-------- -------- 5.72m/m2 =1.43m/ m2
e)ǿ 6cm Eucalyptus strut with 5% wastage ---------------------------- 2.05m/ m2
f)Nail # 10 -------------------------------------------------------------------5pcs/m2 = 0.08kg/m2
# 6 -------------------------------------------------------------------39pcs/m2 = 0.142kg/m2
d) g) Mould Oil------------------------------------------------------------------0.06lit / m 2

18 Pipe laying work


a) G.I Pipe -------------------------------------------------------= lm/m
b) Fiber ---------------------------------------------------------= 1kg/1000m
c) Iron paint ----------------------------------------------------= 1 gallon/9oom

19. Reinforcement
a) 1 kg of soft wire for 100 kg of reinforcement
b) weight of reinforcement/m3 of concert ---------------= as per the design.

MATERIAL COMPONENTS AND QUANTITIES FOR UNIT WORK ITEM

Item Work Item Unit Material Component Unit Qty


No for Unit Work Item

36
20 STRUCTURAL STEEL
20.1 Truss Kg Stell Kg 1.05
20.2 Plates Kg Plate Kg 1.05
20.3 Angle ties Kg Ties Kg 1.05
20.4 Bolts No Bolt No 1.05
21 METAL WORK
21.1 Metal door (single leaf) No Door set No 1.05
Key/lock No 1.05
Hinge No 3.00
Paint lit 0.14
21.2 Metal Window No Window Set No 1.05
Hinge No 2.00
Handle No 1.00
Paint lit 0.14
22 PLASTERING AND POINTING
A) Two coats of plaster
22.1 Compo mortar M2 Cement Qtl 0.056
Lime Qtl 0.089
Sand M3 0.017
22.2 Cement plaster M2 Cement Qtl 0.037
Sand M3 0.018
22.3 Fine coat lime plaster M2 Lime Qtl 0.026
Sand M3 0.003
22.4 Fine coat gypsum plaster M2 Gypsum Qtl 0.017
Lime Qtl 0.058
22.5 Fine coat cement plaster M2 Cement Qtl 0.019
Sand m3 0.003
22.6 Final render coat M2 Cement Qtl 0.013
Lime Qtl 0.032
Sand M3 0.005
B Cement pointing with mortar mix 1:3
22.7 Brick wall M2 Mortar m3

37
Cement Atl
Sand m3
22.8 Hollow concrete Block wall M2 Mortar m3
Cement Atl
Sand m3
22.9 Stone wall M2 Mortar m3
Cement Atl
Sand m3
23 FLOOR AND WALL FINISH
23.1 Cement/Terrazzo/Marble flooring M2 Tile m2 1.03
&steps
Mortar m3 0.0204
Grouting m3 0.001
Cement Qtl 0.085
Sand M3 0.015
23.2 Ceramic wall tile(150x150mm) M2 Tile M2 45.3
Mortar M3 0.0102
Grouting M3 0.001
Cement Qtl 0.03
Sand M3 0.008
23.3 Mosaic tile(27x2mm) M2 Tile M2 1.02
Mortar M3 0.0102
Grouting M3 0.001
Cement Qtl 0.036
Sand M3 0.008
B) Cement screed
23.4 Mix 1:2 Mortar M3 1.26
Cement Qtl 5.88
Sand M3 0.84
23.5 Mix 1:3 M3 Mortar M3 1.26
Cement Qtl 4.41
Sand M3 0.95
23.6 Mix 1:4 M3 Mortar M3 1.26
38
Cement Qtl 3.53
Sand M3 1.01
23.7 PVC tile flooring M2 Tile M2 1.02
Adhesive kg 0.05
Skirting
23.8 Cement/Terrazzo/Marble M Tile M 1.05
Mortar M3 0.0013
Cement Atl 0.0046
Sand M3 0.001
23.9 PVC M Tile M 1.05
Adhesive Kg 0.015
23.10 Stone paving M3 Stone M2 1.05
Sand bed M3 0.105
Mortar M3 0.0378
Cement Qtl 0.176
Sand M3 0.025
24 PAINTING
24.1 Oil paint M2 1st Coat lit 0.06
2nd Coat lit 0.055
3rd Coat lit 0.045
24.2 Plastic paint M2 1st Coat lit 0.10
2nd Coat lit 0.08
3rd Coat lit 0.066
24.3 Synthetic enamel paint M2 1st Coat lit 0.05
2nd Coat lit 0.07
3rd Coat lit 0.055
25 GLAZING
25.1 Glass M2 Glass M2 1.10
26 SANITARY INSTALLATION Putty kg 1.40
a) Pipes
26.1 Galvanized stell M Pipes M 1.05

39
Joint Compound Gram 12.00
Hemp Gram 6.00
Accessories No 0.20
26.2 PVC M Pipes M 1.05
Accessories NO 1.00
Adhesive Kg 0.12
26.3 Pre cast concrete, diameter 100mm M Pipe M 1.05
Mortar ,mix 1!2 M3 0.0005
Cement Qtl 0.0025
Sand M3 0.001
26.4 Pre cast concrete, diameter 150mm M Pipe M 1.05
Mortar M3 0.0012
Cement Qtl 0.006
Sand M3 0.001
26.5 Pre cast concrete, diameter 200mm M Pipe M 1.05
Mortar M3 0.002
Cement Qtl 0.009
Sand M3 0.001
26.6 Pre cast concrete, diameter 300mm M Pipe M 1.05
Mortar M3 0.003
Cement Qtl 0.01
Sand M3 0.002
26.7 Pre Cast concrete, diameter 400mm M Pipe M 1.05
Mortar M3 0.005
Cement Qtl 0.02
Sand M3 0.003
26.8 Pre Cast concrete, diameter 500mm M Pipe M 1.05
Mortar M3 0.007
Cement Qtl 0.03
Sand M3 0.005
26.9 Pre Cast concrete, diameter 600mm M Pipe M 1.05
Mortar M3 0.0

40
Cement Qtl 0.05
Sand M3 0.007
26.10 Pre Cast concrete, diameter 800mm M Pipe M 1.05
Mortar M3 0.02
Cement Qtl 0.08
Sand M3 0.01
26.11 Pre Cast concrete, diameter 1000mm M Pipe M 1.05
Mortar M3 0.03
Cement Qtl 0.12
Sand M3 0.02
B) Sanitary Fixtures
26.12 WC/low flush No WC No. 1.05
Flexible pipe No. 1.05
Stop cock No. 1.05
26.13 WC/high flush No WC No. 1.05
Flexible pipe No. 1.05
Stop cock No. 1.05
Bracket for cistern No. 2.10
Fixer with plug No. 12.60
Hemp Kg 0.21
Mortar M3 0.001
26.14 Squatting pan WC No Pan No. 1.05
Flush cistern with pipe No. 1.05
Flexible pipe No. 1.05
Stop cock No. 1.05
Bracket for cistern No. 2.10
Fixer with plug No. 8.40
Hemp Kg 0.21
Mortar M3 0.05
B) Wash Hand Basin
26.15 WHB No WHB No. 1.05
Rubber plug No. 1.05

41
Chain with holder No. 1.05
Bracket No. 2.10
Fixer with plug No. 8.40
26.16 WHB with pedestal No WHB No. 1.05
Pedestal No. 1.05
Rubber plug No. 1.05
Chain with holder No. 1.05
Fixer with plug(floor) No. 4.20
Fixer with plug(Wall) No. 2.10
26.17 Urinal No Urinal No. 1.05
Fixer with plug No. 4.20
26.18 Bath tub No Tub No. 1.05
Drain d pipe & smell No. 1.05
trap
Chain, holder & plug No. 1.05
Hemp kg 0.12
26.19 Water heater No Heater No. 1.05
Check valve No. 1.05
Closing valve No. 1.05
Flex No. 2.10
Nipple No. 2.10
Hemp Kg. 0.03
No. 4.20
26.20 Shower unit No Shower No. 1.05
Drain& small trip No. 1.05
Mortar M3 0.06
hemp kg. 0.012
C) Sink
26.21 Single bowl No No 1.05
No 1.05
26.22 Double bowl No 1.05
No 2.1

42
26.23 Toilet paper holder No 1.05
No 2.10
26.24 Towel Rail/Hook No 1.05
No 2.10
26.25 Floor Drain No 1.05
Kg 0.12
26.26 Concrete trough Kg 0.32
No 1.05
No 1.05
Kg 0.12
M3 0.005
No 1.05
26.27 Valve Valve No 1.05
Kg 0.04
kg 0.02
27 ELECTRICAL INSTALLATION
a) pre cast concrete pipe
27.1 Diameter 100mm M Pipe M 1.05
Mortar, mix 1:2 M3 0.0005
Cement Qtl 0.0005
Sand M3 0.001
27.2 Diameter 150m Pipe No 1.15
Mortar, mix 1:2 M3 0.0012
Cement Qtl 0.006
Sand M3 0.001
27.3 Diameter 200mm M pipe No 1.05
Mortar, mix 1:2 M3 0.002
Cement Qtl 0.009
Sand M3 0.001
27.4 Main distribution board No Box 1.00
Circuit breaker, 1ph *
Circuit breaker, 3h *

43
Tumbler switch *
27.5 No Box 1.00
Circuit breaker, 1ph *
Circuit breaker, 3h *
Tumbler switch *
Cable 1.05
27.6 PVC Cable M Conduit 1.05
B) Light, power and socket Outlet
Light points
27.7 Residence/Dormitory/ Apartment No Conduit M 2.40
PVC conductors M 4.70
Junction box No 0.50
Connectors No 1.00
27.8 Work Shop/Store/ No Conduit M 10.50
PVC conductors M 21.00
Junction box No 1.00
Connectors No 1.00
27.9 Work shop/Store/Continuous No Conduit M 2.00
PVC conductors M 4.00
Junction box No 1.00
Connectors No 1.00
27.10 Office No Conduit M 8.70
PVC conductors M 7.70
Junction box No 1.00
Connectors No 1.00
Switch
27.11 Residence/Dormitory/Apartment No Switch No 1.00
Conductor M 4.70
Conduit M 2.40
27.12 Work Shop/Store/ No Switch No 1.00
Conductor M 24.40
Conduit M 12.20
27.13 Work shop/Store/Continuous No Switch No 1.00
44
Conductor M 13.70
Conduit M 6.85
27.14 Office No Switch No 1.00
Conductor M 3.70
Conduit M 2.00
Socket Outlet
27.15 Residence/Dormitory/Apartment No Out let No 1.00
Conductor M 11.2
Conduit M 5.60
Junction box No 1.00
27.16 Work Shop/Store/ No Out let No 1.00
Conductor M 33.00
Conduit M 16.50
27.17 Office Junction box No 1.00
Out let No 1.00
Conductor M 10.00
Conduit M 5.00
Junction box No 1.00
27.18 Bell point Push bottom No 1.00
Conductor M 4.70
Conduit M 2.40
Junction box No 0.33
27.19 Pan out let Switch No 1.00
Conductor M 8.00
Conduit M 4.00
Junction box No 1.00
27.20 Telephone outlet Switch No 1.00
Conduit M 4.00
27.21 TV outlet No Flat twin TV M 8.00
Conduit M 4.00
Junction box No 0.50

45
Fixtures
27.22 Bell System No Buzzer No 1.00
Indicator No 1.00
Transformer No 1.00
Fan No 1.00
Air conditioner No 1.00
Fitting No 1.00
Poles
27.26 Wood No Wood poles No 1.00
Galvanized Steel No Galvanized steel No 1.00
Conductors No
27.28 Bare copper M Bare copper M 1.05
27.29 Insulated Copper Insulated copper M 1.05

46
January 2009
Bahir Dar

47