Professional Documents
Culture Documents
Assala mu alykum My Name is saqib imran and I am the student of b.tech (civil) in sarhad
univeristy of science and technology peshawer.
I have written this notes by different websites and some by self and prepare it for the student and
also for engineer who work on field to get some knowledge from it.
or text me on 0341-7549889.
Saqib imran.
SAQIB IMRAN 1
2|P a g e
a) Single units work like doors, windows, trusses etc., are expressed in
numbers.
d) Works consists cubical contents which involve volume like earth work,
cement concrete, Masonry etc are expressed in Cubic metres.
1 Earthwork
SAQIB IMRAN 2
3|P a g e
2 Concrete
7. Reinforced concrete sunshade (specified width and height) CUM Per CUM
4 Brick work
5 Stone work
SAQIB IMRAN 3
4|P a g e
6 Wood work
1. Doors and windows frames or chaukhats, rafters, beams CUM Per CUM
7 Steel work
1. Steel reinforcement bars etc. in RCC and reinforced brick work Quintal Per Quintal
3. Rivets, bolts and nuts, anchor bolts, lewis bolts, holding down
Quintal Per quintal
bolts
8 Roofing
SAQIB IMRAN 4
5|P a g e
10 Flooring
3. Doors and window sills (CC or cement mortar plain) SQM Per SQM
Note:
SAQIB IMRAN 5
6|P a g e
1. Measurement shall be made for finished item of work and description of each
item shall include materials, transport, labour, fabrication tools and plant and all
types of overheads for finished the work in required shape, size and
specification.
4. Same type of work under different conditions and nature shall be measured
separately under separate items.
SAQIB IMRAN 6
7|P a g e
2 Surface dressing m2 m2
6 Jail works m2 m2
SAQIB IMRAN 7
8|P a g e
21 Iron railing m m
23 Centering, shuttering m2 m2
SAQIB IMRAN 8
9|P a g e
31 Grouting m2 m2
35 Supply of steel, G.I. sheet, bare electric line Quintal Per quintal
36 Supply of GI sheet m2 m2
SAQIB IMRAN 9
10 | P a g e
While measuring the quantities of masonry work, the wastage of materials such
as bricks, cement or sand is not taken into account. Also, the types and classes
of bricks, blocks or tiles are not considering while measuring the quantity of
work. This is taken care in pricing of the different masonry works. Each type of
masonry works are measured separately into categories to calculate exact cost
of construction based on its price.
SAQIB IMRAN 10
11 | P a g e
a) Facings
b) Backing to facings
SAQIB IMRAN 11
12 | P a g e
d) Furring to walls
e) Fire protection
5. Masonry work which requires cleaning of surface are measured in area such
as square meter or square feet.
7. Any joints in masonry structure such as expansion joints or control joints are
measured in length such as meter or feet with description of type of joint. Also
the type of joint filler material for the joint used is indicated in description.
8. For different types of mortar, or mortar with different types of admixtures are
measured separately. These are measured in volume such as cubic meter or
cubic feet.
10. Extra items in masonry construction such as anchor bolts, sleeves, brackets,
and similar items that are built into masonry are described in the measurement
and measured separately.
11. Enumerate weep holes where they are required to be formed using plastic
inserts and such like.
12. Measure rigid insulation to masonry work in square feet or square meters,
describing the type and thickness of material.
SAQIB IMRAN 12
13 | P a g e
For measurement of brick masonry, general rules specified above are used
along with following points:
Concrete block masonry are measured as general rules described above along
with following points:
SAQIB IMRAN 13
14 | P a g e
(2) Ends of beams, post, rafters, etc. up to 500 sq.cm or 0.05 sq.m in section.
(3) Bed plate, wall plate, bearing of balcony (chajja) and the like up to 10 cm
depth. bearing of floor and roof slabs are not deducted from masonry.
The quantities are calculated in cubic meter exclusive of steel reinforcement and
its bending but inclusive of centering and shuttering and fixing and binding
reinforcement in position. The reinforcement including its bending is taken up
separately under steel work in as per weight.
SAQIB IMRAN 14
15 | P a g e
Ground floor:
The base line concrete and floor finishing of cement concrete or stone or marble
or mosaic etc. are usually taken as one job or one item and the quantity is
calculated in square meter multiplying the length by the breadth.
The length and breadth are measured as inside dimensions from wall to wall of
superstructure. both the work of base concrete and floor finishing are paid
under one item.
Roof:
Supporting structure is taken separately in cubic meter and the lime concrete
terracing is computed in square meter with thickness specified under a separate
item including surface rendering smooth. The compacted thickness of lime
concrete terracing is 7.5 cm to 12 cm average. Lime concrete terracing may
also be calculated in cubic meter with average thickness.
Plastering:
SAQIB IMRAN 15
16 | P a g e
Plastering usually 12mm thick is calculated in square meter. for wall the
measurement are taken for whole face of the wall for both side as solid, and
deducting for opening are made in following manner.
(1) No deduction is made for the end of beams, posts, rafters etc.
(2) For small opening up to 0.5 square meter no deduction is made, and at the
time no additions are made for jambs, soffits and sills of these opening.
(3) For opening exceeding 0.5 square meter but not exceeding 3 square meter
deduction is made for one side and other face is allowed for jambs soffits and
sills which are not taken into account separately
(4) For opening above 3 square meter deduction is made for both faces of the
opening and the jambs, soffits and sills are into account and added.
Pointing:
Pointing in wall calculated in square meter for whole surface and deduction
similar to plastering is made.
Cornice:
Ornamental and large cornice is measured in running meter or running foots for
the complete work which includes masonry, plastering, moldings etc. and paid
for in running meter.
Similarly, string course, corbelling, coping etc are measured and paid for in
running meters for the complete work.
Pillars:
SAQIB IMRAN 16
17 | P a g e
Pillars are taken separately in cubic meter foe their net volume and quantities
are calculated.
Wood Works:
Wooden beams, posts, wooden roof trusses, doorpost etc. come under this
items and the quantities are computed in cubic meter. The dimension of finished
work shall be taken.
Iron Works:
This computed weight in kg or quintal and the quantities are calculated correctly
by multiplying the weights per running meters by length. the weight per running
meter can be obtained from the steel section book. For steel joint the length is
equal to the clear span plus two bearing the bearing may taken third forth
thickness of wall or 20 to30 cm.
The quantities are computed in square meter and are usually same as for
plastering. The inside is usually white washed or distempered and this item will
be same as for outside plaster. These item need not be calculated separately
but simply written as same as for outside plaster and inside plaster.
SAQIB IMRAN 17
18 | P a g e
In this article i will tell you how to calculate bricks in a wall. By the explanation describe
below, you can make your own MS Excel Brick calculator program to calculate bricks in
a wall.
As we know that there are 13.5 bricks in 1 cubic feet. So in 100 cubic feet there will be
1350 bricks.
SAQIB IMRAN 18
19 | P a g e
To calculate bricks in a wall, we need to know the dimensions of the wall. For instance,
if a wall is 10 feet long with 10 feet height and 9 inch thickness. Then we can find its
bricks in a following way. Multiply dimensions of wall. 10 feet x 10 feet x 0.75 feet. We
will get 75 cubic feet. We have seen above that there are 13.5 bricks in 1 cubic feet
brickwork. So there will be 75 x 13.5 =1012.5 bricks in 75 cubic feet. In this way we
calculate bricks in any wall with the known dimensions.
In feet
Length of wall in feet x height of wall in feet x thickness of wall in feet x 13.5 =
number of bricks
SAQIB IMRAN 19
20 | P a g e
In meter
length of wall in meter x height of wall in meter x thickness of wall in meter x 500 =
number of bricks
SAQIB IMRAN 20
21 | P a g e
MS SQUARE
WEIGHT (KGS ) = WIDTH X WIDTH X 0.00000785 X LENGTH.
Example : A Square of size 25mm and length 1 metre then the weight shall be.
25x25X 0.00000785 X 1000mm = 4.90 kgs/metre
MS ROUND
WEIGHT (KGS ) = 3.14 X 0.00000785 X ((diameter / 2)X( diameter / 2)) X LENGTH.
Example : A Round of 20mm diameter and length 1 metre then the weight shall be.
3.14 X 0.00000785 X ((20/2) X ( 20/2)) X 1000 mm = 2.46 kgs / metre
SS ROUND
DIA (mm) X DIA (mm) X 0.00623 = WEIGHT PER METRE
SS / MS Pipe
SAQIB IMRAN 21
22 | P a g e
BRASS SHEET
WEIGHT (KGS) = LENGTH (MM) X BREADTH (MM) X 0. 0000085 X THICKNESS
Example – The weight of brass sheet of thickness 1 mm, length 1220mm and breadth 355mm shall be
1220 X355X 0.0000085 X 1 = 3.68 Kgs/Sheet
Following table shows how can we convert various most commonly used units from one unit system
to another.
Units to convert Value
Pound per cubic inch to Kilogram per cubic 1 lb/in³ = 27679.9 047102 kg/m³
meter
Gallon per minute = Liter per second 1 Gallon per minute = 0.0631 Liter per second
Pound per square inch = Kilopascal 1 Psi (Pound Per Square Inch) = 6.894757 Kpa
(Kilopascal)
Acre foot per day = Cubic meter per second 1 Acre foot per day= 1428 (m3/s)
Cubic foot per second = Cubic meter per 1 ft³/s = 0.028316847 m³/s
second
Measurement units and standards are different in different countries but to maintain a standard, SI
units are mostly used when dealing with projects involving different countries or even different states.
SAQIB IMRAN 22
23 | P a g e
Small projects can be done with the locally used unit system but when the project is big, one standard
unit system is to be used.
Two most common system used in the United States are
United States Customary System (USCS)
System International (SI)
But the SI unit system is more widely used all over the worl d. Following is the table which shows how
you can convert USCS measurements in SI measurements. ( Just multiply the USCS amount with the
corresponding figure given in table below
BASIC STANDARDS:
1 inch = 25.4 millimeters = 2.54cm.
1 meter = 39.37 inches =1.09 yards.
1 liter = 0.22 galls (imp.)
1 gallon (imp.) = 4.546 liters.
1 gallon (US) = 3.785 liters.
1 Kilogram (kg) = 2.2046 pounds (lb).
MEASUREMENTS OF LENGTH:
1 foot = 12 inches.
1 yard = 3 feet.
1 furlong = 220 yards.
SAQIB IMRAN 23
24 | P a g e
1 mile = 8 fulongs.
1 Kilometer (Km) = 1000 meters.
1 meter (m) = 100 centimeters (cm).
1 cm = 10 millimeter (mm).
CONVERSION FACTORS:
1 cu. ft. = 28.317 liters.
1 cu. ft. = 0.028 cu. meters.
1 cu. ft. = 6.24 galls (imperial).
1 cu. ft. = 7.48 galls (US).
1 imp. gall = 1.20 galls (US), liquid.
1 imp. gall = 1.03 galls (US), dry.
MEASUREMENTS OF AREA:
1 Acre = 43560 sq. ft
1 Acre = 4046.46 sq. m
1 Acre = 8 Kanals.
1 Kanal = 20 Marlas.
1 Marla = 225 sq. ft (* in some regions 272 sq. ft)
1 Marla = 15.50 sq.m
SAQIB IMRAN 24
25 | P a g e
After estimating it is very important to know the unit weight of steel bars because, we estimate as 100
meter 20mm ø bar or 100 feet 16mm ø bar, etc (ø is the symbol of diameter).
But steel bar suppliers will not understand this notation, they measure the steel bars in weight. So we
have to order them in kg or quintal or ton. In this article, we will discuss how to calculate u nit weight of
steel bars of different diameter.
The formula is W = D²L/162
Where
W = Weight of steel bars.
D = Diameter of steel bars in mm.
L = Length of bars in meter.
Example 1: Calculate the weight of 60 meters long 12 mm ø bar.
Here, D = 12 mm.
L= 60 m.
We know that, W = D²L/162
W = 12² x 60/162 = 53 kg
Weight of 60 m 12mm ø bar is 53 kg.
Let’s look for another example.
Example 2: Calculate the weight of 100 m 16 mm ø bar.
Here, D = 16 mm.
L = 100 m.
W = 16² x 100/162 = 158 kg.
If we put 1 meter length for each diameter of steel bar in the formula then we will get the unit weight.
10mm ø bar = 10² x 1/162 = 0.617 kg/m
12mm ø bar = 12² x 1/162 = 0.888 kg/m
16mm ø bar = 16² x 1/162 = 1.580 kg/m
20mm ø bar = 20² x 1/162 = 2.469 kg/m
If we multiply the length of bars with this unit weight we will get the total weight of steel bars.
For example, total weight of 1000 meter long 20mm ø steel bar is,
1000 x 2.469 = 2469 kg.
Using the same method we can calculate the unit weight of different steel bars.
Here I have calculated in meter but we can also calculate in foot. To calculate in foot we have to use the
following formula:
W= D²L/533
Where D = Diameter of bars in mm.
L = Length of bars in foot.
HOW TO CALCULATE STEEL QUANTITY FOR RCC BEAM, COLUMN AND SLAB
Following are the steps to calculate the quantity of steel for RCC slab
1. Prepare a bar bending schedule in order to classify different shapes of bars (bent up bar, straight
anchor bar, eos bar, curtail bar etc) and diameters.
2. List down all the shapes of bars from the drawing.
3. Count the number of bars of each of those shapes.
4. Then calculate the cutting length of each of those bars.
SAQIB IMRAN 25
26 | P a g e
Cutting length of bar = (length of the member – deduction for cover on both sides) + development
length.
5. Then calculate the unit weight of each dia bars by the following formula:
W = d^2/162
Where d is the dia in mm and weight (w) in kg.
6. Then calculate weight of rebar
Weight of rebar= no of bars x cutting length x unit weight
7. Add all the weight to get the total steel quantity.
NOTE – 1. Minimum % of steel as per Indian standard are:
1. Beam (Teinsion reinforcement):
As = 0.85bd/fy of gross cross-section area.
2. Slab – 0.12% of total area
3. Column – 0.8% of cs area
2. Maximum % steel as per Indian standard are:
Beam – 4 % of cross-section area.
Slab – 4% of cross-section area.
column — 6% of cross-section area.
3. . Development Length is usually specified in the drawings, but if not thenyou can calculate it as,
D.L = Depth – 2 times cover
4. Binding wire = 10 grams per kg of reinforcement.
5. No. of stirrups = (length of member – 2 x cover ) / spacing + 1
SAQIB IMRAN 26
27 | P a g e
But these are now backdated (not wrong) and we don’t use them in today. Because No accurate values
were specified if we use more bars in a single member. Nowadays we are constructing 150+ floors
building. It is now possible with our modern techniques, equipment etc. Estimation of steel becomes
easier because of BBS.
Civil engineers who are working on site or freshers who are going to work at construction sites must
know how to prepare bar bending schedule. In this article, I will discuss some important things used in
preparing bar bending schedule.
These are just the basic things. In future, I will come up with some other articles related to BBS such as
BBS for beams, columns, slabs, footings etc.
HOOK LENGTH:
The hook is the extra length left at the 4th corner of a stirrup so that the stirrup retains its shape.
Generally, hook length is taken as 9d for one side.
Where d = Diameter of the bar.
The total length of stirrups = Total length of the bar + 2 x hook length (for two hooks)
= L + 2 x 9d
= L + 18d.
Where L = length of the bar for stirrup.
BEND LENGTH:
The bar is bent at the column end to tie with the footings. This extra length for bend is called bend
length.
Bend length is generally considered as 16 d
Bend Length = 16d
SAQIB IMRAN 27
28 | P a g e
DEVELOPMENT LENGTH:
Development length is the length of bar required for transferring the stress into concrete.
In simple words, the quantity of the rebar length that is actually required to be embedded into the
concrete to create the desired bond strength between steel and concrete and furthermore to produce
required stress for the steel in that area.
The formula for development is given below:
Development length (Ld) = d x σs/τbd
Where
d = Diameter of the bar.
σs = Stress in the bar at the section considered as design load
τbd = Design bond stress.
SAQIB IMRAN 28
29 | P a g e
LAP LENGTH:
Lap length is the overlapping length of two bars side by side which gives required design length. In RCC
structure if the length of a bar is not sufficiently available to make design length, lapping is done.
Suppose we need to build a 20 m tall building. But is there any 20 m bar available in the market? No, the
maximum length of rebar is usually 12 m, so we need to join two bars to get 20 m bar.
Lap length for tension members = 40d
Lap length for compression members = 50d.
d = Diameter of bars.
SAQIB IMRAN 29
30 | P a g e
Look at the image below. You may be seen this on the terrace (top floor) of buildings. This extra rebar is
left for future construction purpose. I hope you understand this.
CRANK LENGTH:
Generally, bars are bent near the support at an angle of 45°. The angle of bend may also be 30° in
shallow beams. The purpose of bend near the support is firstly to resist the negative bending moment
which occurs in the region of the support and secondly to resist the shear force which is greater at the
support.
SAQIB IMRAN 30
31 | P a g e
Where,
SAQIB IMRAN 31
32 | P a g e
Cutting Length = Clear Span of Slab + (2 x Development Length) + (2 x inclined length) – (45° bend x 4) –
(90° bend x 2)
Inclined length = D/(sin 45°) – dD/ (tan 45°) = (D/0.7071) – (D/1)= (1D – 0.7071D)/0.7071= 0.42 D
As you can see there are four 45°bends at the inner side (1,2,3 & 4) and two 90° bends ( a,b ).
45° = 1d ; 90° = 2d
Cutting Length = Clear Span of Slab + (2 X Ld) +(2 x 0.42D) – (1d x 4) – (2d x 2) [BBS Shape Codes]
Where,
d = Diameter of the bar.
Ld = Development length of bar.
D = Height of the bend bar.
In the above formula, all values are known except ‘D’.
So we need to find out the value of “D”.
D = Slab Thickness – (2 x clear cover) – (diameter of bar)
= 200 – (2 × 25) – 12
= 138 mm
Now, putting all values in the formula
Cutting Length = Clear Span of Slab + (2 x Ld) +(2 x 0.42D) – (1d x 4) – (2d x 2)
= 8000 + (2 x 40 x 12) +(2 x 0.42 x 138) – (1 x 12 x 4) – (2 x 12 x 2)
∴ Cutting Length = 8980 mm or 8.98 m.
So for the above dimension, you need to cut the main bars 8.98 m in length.
SAQIB IMRAN 32
33 | P a g e
SAQIB IMRAN 33
34 | P a g e
THE FORMULA D²L/162 FOR CALCULATING WEIGHT OF STEEL BARS FULLY DERIVED
SAQIB IMRAN 34
35 | P a g e
SAQIB IMRAN 35
36 | P a g e
SAQIB IMRAN 36
37 | P a g e
There are many building materials used in construction. In the below table we have tried to cover the
unit weight of building materials which are most commonly used at the construction site.
Material Unit Weight
SAQIB IMRAN 37
38 | P a g e
REQUIRED DATA:
1. Volume of the wall.
2. Volume of a standard brick.
3. Details of openings in the wall.
PROCEDURE:
1. First, calculate the volume of the wall to be built:
Let us assume,
The length of the wall (l) = 10 foot.
The height of the wall (h) = 10 foot.
Thickness of the wall (b) = 1 foot.
Calculate the volume of the wall by multiplying the length, height, and thickness.
SAQIB IMRAN 38
39 | P a g e
SAQIB IMRAN 39
40 | P a g e
STEP 6:
Divide The Total Surface Area Of The Wall By Surface Area Of One Block:
∴ Number of blocks = Surface Area of wall/Surface Area of a block = 91/1.0625 = 86
SAQIB IMRAN 40
41 | P a g e
SAQIB IMRAN 41
42 | P a g e
To calculate the quantity of materials in semi circular arch we need to calculate the volume of arch.
Volume of arch = Cross-section of arch x Arch length
We know Cross-section area = Thickness of arch x Breadth of arch = T x B
From the above image, you can see the thickness and breadth are 1 ft.
Cross-section of arch = 1 x 1 = 1 ft²
Now Arch length = Circumference of half circle (The arch is semi circular)
We know circumference of circle = 2πR
Circumference of half circle = 2πR/2 = πR
We don’t what is R. So we need to find out the ‘R’.
R = Half span + Thickness/2 = 4 +1/2 = 4.5 ft.
Arch length = πR =3.14 x 4.5 = 14.13 ft.
Quantity of materials in arch = 1 x 14.13 = 14.13 cft.
2. SEGMENTAL ARCH:
Given:
Span = 8 ft
Height = 2ft
Thickness = 1 ft
Breadth = 1ft
Central angle = 105°
SAQIB IMRAN 42
43 | P a g e
SOLUTION:
Volume arch = Cross-section of arch x Arch length
We know Cross-section area = Thickness of arch x Breadth of arch = T x B
Arch length = θπR/180
Now R = (a² + h²)/2h [a =half span = 8/2 =4]
=(4² + 3²)/2 x 3 = 25/6 =4.16 ft.
Arch length = (105 x 3.14 x 4.16)/180 = 7.61
Quantity of materials in arch = 1 x 7.61 = 7.61 cft.
Shuttering or formwork is a temporary, rigid structure in which the cast in situ concrete is p oured for
casting the members to required shape. Different formworks are used for different shape members.
SAQIB IMRAN 43
44 | P a g e
In this article, we will discuss how to calculate the shuttering area before construction.
Before calculating the shattering area first, we need to know how to calculate the peripheral length of
any shape.
PERIPHERAL LENGTH/PERIMETER:
We know that perimeter is the distance around a 2D (two dimensional) shape.
For example, square has four sides. Let ‘s’ be the length of one side, then
∴ The peripheral length = s+s+s+s = 4s
Rectangle has four sides also but the length and breadth is different, let one side length is ‘l’ and
breadth is ‘b’
∴ Peripheral length = l+b+l+b = 2l+2b
Now coming to the calculation of shuttering area.
Shttering area = Pheripheral length * Depth
Let me give you an example
SAQIB IMRAN 44
45 | P a g e
Check why 1.54 is multiplied with wet volume to get dry volume.
∴ Dry volume = 13.95 x 1.54 = 21.48 cu.m (approximately).
Generally, M20 grade concrete is predominantly used for construction purposes.
M20 = 1: 1.5: 3 (Cement:Sand:Aggregates) = (a:b:c)
QUANTITY OF CEMENT:
Quantity of cement = Dry volume x (a/{a+b+c}
Quantity of cement = Dry volume x (1/{1+1.5+3}) for M20 grade concrete.
= 21.48 x (1/5.5}) = 3.90 cu.m = 3.90 cu.m
We need the quantity of cement in terms of bags.
So by multiplying the quantity of cement with the density of cement, we will the get quantity of cement
in terms of kilograms.
Unit weight or Density of cement = 1440 kg/cu.m.
Quantity of cement in kg(s) = 1440 x 3.90 = 5616 kg
We know that 1 cement bag = 50 kgs
∴ No. of cement bags required = 5616/50 kg = 112.32 bags =112 bags.
QUANTITY OF SAND:
Quantity of sand = Dry volume x (b/{a+b+c}
∴ Quantity of sand = Dry volume x (1.5/{1+1.5+3}) for M20 grade concrete.
= 21.48 x (1.5/5.5}) = 5.85 cu.m
QUANTITY OF AGGREGATES:
Quantity of aggregates = Dry volume x (c/{a+b+c}
∴ Quantity of aggregates = Dry volume x (3/{1+1.5+3}) for M20 grade concrete .
= 21.48 x (3/5.5}) = 11.71 cu.m
SUMMARY:
Cement = 112 bags.
SAQIB IMRAN 45
46 | P a g e
COMPONENTS OF STAIRCASE:
STEPS:
A portion of stairway comprising the tread and riser which permits ascent and descent from one floor to
another.
TREAD:
The horizontal upper part of a step on which foot is placed in ascending or descending stairway.
RISER:
The vertical portion of a step providing support to the tread.
FLIGHT:
A series of steps without any platform, break or landing in their direction.
LANDING:
A platform or resting place provided between two flights.
Now coming to the calculation of concrete volume for the staircase.
Let’s take an example:
SAQIB IMRAN 46
47 | P a g e
SAQIB IMRAN 47
48 | P a g e
The height of the top of the landing from floor = Number of riser x Height of riser
= 12 x 0.5 = 6 feet.
The volume of concrete for waist slab = Inclined length of waist slab x Width of waist slab x Thickness of
waist slab
= 11′ x 5′ x 0.5′
= 27.5 cubic feet
∴ Volume of concrete for first flight = Volume of waist slab + Volume of steps
= 27.5+11 = 38.5 cubic feet
SAQIB IMRAN 48
49 | P a g e
In concrete calculation, we always multiply Wet volume with 1.54 to get dry volume. But do you know
what is 1.54 or where this 1.54 came from? If You don’t know, no problem. In this article, I will explain
what is 1.54 while calculating quantity of cement, sand, aggregates for concrete.
let us take a concrete cube.
SAQIB IMRAN 49
50 | P a g e
SAQIB IMRAN 50
51 | P a g e
SAQIB IMRAN 51
52 | P a g e
In some cases, cylindrical shape with suitable size is also sound to be a better choice.
204″L x 96″W
5000 gal 41,400 30,850 24
x93″H
165″L x 92″W x
3000 gal 20,300 23,320 23
76″H
147″L x 90″W x
2600 gal 18,100 20,625 24
73″H
162″L x 78″W x
2000 gal 16,100 15,675 19
64″H
145″L x 78″W x
1600 gal 14,000 11,270 16
61″H
111″L x 78″W x
1200 gal 11,400 9,532 17
61″H
96″L x 67″W x
800 gal 8,000 6,560 16
57″H
78″L x 56″W x
600 gal 6,600 3,810 14
60″H
SAQIB IMRAN 53
54 | P a g e
174″L x 90″W x
1600/1400 gal 23,000 22,410 22
73″H
162″L x 78″W x
1250/750 gal 16,400 15,725 19
64″H
145″L x 78″W x
1000/600 gal 14,700 12,705 17
61″H
SAQIB IMRAN 54
55 | P a g e
4. The minimum width and depth of a septic tank should be 0.75 m and 1 meter underneath water level.
The length should be 2 to 4 times of the width. The minimum capacity of a septic tank is granted 1 m3.
5. Every septic tank should be furnished with a ventilating channel minimum diameter of 5 cm.
HOW TO CALCULATE VOLUME OF CONCRETE, SHUTTERING AREA & BITUMEN PAINT AREA
FOR PLAIN FOOTING
In this article I will discuss how to calculate the volume of concrete, shuttering area and bitumen paint
area for plain footing (Square footing & Rectangular footing).
A. SQUARE FOOTING:
Given,
Length of footing = 0.5 m
Breadth of footing = 0.5 m
Depth of footing = 0.25 m
Size of column = 0.2 x 0.1
1. Volume of concrete = Area of sq. footing x Depth of sq footing
Area of sq. footing = L x B = 0.5 x 0.5 = 0.25 m²
Volume of concrete = 0.25 x 0.25 = 0.0625 m³.
2. Shuttering area = 2 (L + B) x D
= 2 (0.5+0.5) x 0.25
= 0.5m²
3. Bitumen paint area = Shuttering area + (Top area of footing – column area)
= 0.5 + [(0.5 x0.5) -(0.2 x 0.1)]
=0.5 + [0.25 – 0.2)]
= 0.73 m².
2. RECTANGULAR FOOTING:
SAQIB IMRAN 55
56 | P a g e
Given,
Length of footing = 1 m
Breadth of footing = 0.7 m
Depth of footing = 0.25 m
Size of column = 0.4 x 0.3
1. Volume of concrete = Area of sq. footing x Depth of sq footing
Area of sq. footing = L x B = 1 x 0.7 = 0.7 m²
Volume of concrete = 0.7 x 0.25 = 0.175 m³.
2. Shuttering area = 2 (L + B) x D
= 2 (1+0.7) x 0.25
= 0.85m²
3. Bitumen paint area = Shuttering area + (Top area of footing – column area)
= 0.85 + [(1 x0.7) -(0.4 x 0.3)]
=0.85 + [0.7 – 0.12)]
= 1.43 m².
SAQIB IMRAN 56
57 | P a g e
SAQIB IMRAN 57
58 | P a g e
SAQIB IMRAN 58
59 | P a g e
Shuttering oil are high quality mineral oil which is used on the shuttering plates/mould for easy removal
of shuttering.
WHY WE USE SHUTTERING OIL IN FORMWORK?
The main purposes of using shuttering oil are as follows:
1. Shuttering oil works as a releasing agent between shuttering plates and concrete. It helps easy
removal of shuttering at the time of deshuttering.
2. It gives a good and better finish after deshuttering.
3. It keeps the shuttering plates and mould in good condition and ensures repetitive use in more
projects.
HOW TO CALCULATE SHUTTERING OIL & ITS PRICE:
Let us calculate the quantity of shuttering oil for the above slab.
Length of slab = 12 m
Breadth of slab = 10 m
Area of slab = L x B = 12x 10 = 120 m²
There are two types of shuttering plates used in construction.
1. WOOD SHUTTERING:
Generally, 1 liter shuttering oil covers upto 30 to 40 m² area in wood shuttering.
The quantity of shuttering oil = Total area/1 liter covering area
= 120/30 = 4 litre
Price: Let the price of 1 liter shuttering oil = Rs. 250.
The price of 4 liter shuttering oil = 250 x 4 = Rs. 1000.
2. STEEL SHUTTERING:
Generally, 1 liter shuttering oil covers upto 60 to 70 m² area in steel shuttering.
The quantity of shuttering oil = Total area/1 liter covering area
= 120/60 = 2 litre
Price: Let the price of 1 liter shuttering oil is Rs. 250.
The price of 2 liter shuttering oil = 250 x 2 = Rs. 500.
SAQIB IMRAN 59
60 | P a g e
To calculate the volume of retaining wall we need to calculate the volume of retaining wall.
Here I have divided the retaining wall into two parts, part A is the base slab and part B is the stem of
retaining wall.
So Volume of retaining wall = Volume of base slab + Volume of stem.
Volume of base slab = l x b x h = 10 x 3 x 0.2 = 6 m³
The stem is a trapezoid.
So Volume of stem = [{(a + b)/2} x h] x l
= [{(0.5 + 0.2)/2} x 3] x 10
= 21 m³
The total volume of retaining wall = 6 + 21 = 27 m³
So the volume of concrete for the retaining wall = 27 m³
Let’s take another example:
EXAMPLE 2:
SAQIB IMRAN 60
61 | P a g e
Here I have divided the retaining wall into three parts, part A is the base slab, part B is the stem and part
C is the counterfort of the retaining wall.
The volume of retaining wall = Volume of base slab + Volume of stem + Volume of counterfort
= Volume of A + Volume of B + Volume of C
Volume of A = l x b x h = 12 x 2.5 x 0.2 = 6 m³
Part B is a trapezooid.
So Volume of B = [{(a + b)/2} x h] x l = [{(0.2 + 0.3)/2} x 3] x 12
= 9 m³
As part C is also a trapezoid
So
Volume of C = [{(a + b)/2} x h] x l = [{(0.5 + 2)/2} x 3] x 0.2 = 0.75 m³
In the above retaining wall there is 2 counterfort so
Volume of C = 0.75 x 2 = 1.5 m³
The total volume of retaining wall = 6 + 9 + 1.5 = 16.5 m³.
SAQIB IMRAN 61
62 | P a g e
SAQIB IMRAN 62
63 | P a g e
But for complex shaped land you cannot easily calculate the area. In that case, we use HERON’s Formula
which is given below:
SAQIB IMRAN 63
64 | P a g e
First of all, divide the land area into minimum possible no. of triangle. Then measure all the required
distance (like AB, AC, AE etc) by using a tape or chain.
1. FOR △ ACD:
AC = 10 feet.
CD = 12 feet.
AD = 14 feet.
S = (a + b + c)/2 = (10 + 12 + 14)/2 = 18 feet.
SAQIB IMRAN 64
65 | P a g e
2. FOR △AED:
AD = 14 feet.
AE = 14feet.
DE = 12 feet.
S = (a + b + c)/2 = (14+14+12)/2 = 20 feet.
3. FOR △AEB:
AB = 16 feet.
BE = 12 feet.
AE = 12 feet.
S = (a + b + c)/2 = (16 + 12 + 12)/2 = 20 feet.
SAQIB IMRAN 65
66 | P a g e
NOTE: This method does not give appropriate result for curve shaped area, for curve shaped area we
need to use difinite integral method.
CENTER LINE METHOD OF ESTIMATION:
There are three different methods of estimation.
SAQIB IMRAN 66
67 | P a g e
SAQIB IMRAN 67
68 | P a g e
2. SPAN:
According to ACI code 8.7.1 If the slab rests freely on its supports, the span length may be taken as equal
to the clear span plus the depth of the slab but need not exceed the distance between centers of
supports.
3. BAR SPACING:
The lateral spacing of the flexural bars should not exceed 3 times the thickness h or 18 inch
according to ACI code 7.6.5 The lateral spacing of temperature and shrinkage reinforcement should not
be placed farther apart than 5 times the slab thickness or 18 inch according to ACI code 7.12.2
4. MAXIMUM REINFORCEMENT RATIO:
Reinforcement ratio is the ratio of reinforcement area to gross concrete area based on total
depth of slab. One-way solid slabs are designed as rectangular sections subjected to shear and moment.
Thus, the maximum reinforcement ratio corresponds to a net tensile strain in the
reinforcement, €t of 0.004
5. MINIMUM REINFORCEMENT RATIO:
A) FOR TEMPERATURE AND SHRINKAGE REINFORCEMENT :
According to ACI Code 7.12.2.1
Slabs with Grade 40 or 50 deformed bars –> 0.0020
Slabs with Grade 60 deformed bars –> 0.0018
Slabs where reinforcement with yield strength Exceeding 60000 psi- ->( 0.0018 x 60000/fy)
B) FOR FLEXURAL REINFORCEMENT :
According to ACI Code 10.5.4, the minimum flexural reinforcement is not to be less than the shrinkage
reinforcement, or 0.0018
EXAMPLE PROBLEM:
A reinforced concrete slab is built integrally with its supports and consists of equal span of 15 ft. The
service live load is 100 psf and 4000 psi concrete is specified for use with steel with a yield stress equal
to 60000 psi. Design the slab following the provisions of the ACI code.
SAQIB IMRAN 68
69 | P a g e
THICKNESS ESTIMATION:
For being both ends continuous minimum slab thickness = L/28 =(15 x 120)/28= 6.43 in.
Let a trial thickness of 6.50 in.
LOAD CALCULATION:
Consider only a 1 ft width of beam.
Dead load = 150 x (6.50/12)) = 81 psf
Live load = 100 psf
Factored DL and LL ={81+1.2+(100 x 1.6)} =257 psf
DETERMINE MAXIMUM MOMENTS:
Factored moments at critical sections by ACI code :
At interior support : -M=1/9 x 0.257 x 152 = 6.43 k-ft
At midspan : +M=1/14 x 0.257 x 152 = 4.13 k-ft
At exterior support : -M=1/24 x 0.257 x 152 = 2.41 k-ft
Mmax = 6.43 k-ft
SAQIB IMRAN 69
70 | P a g e
= 2.64 in
CHECK FOR AVAILABILITY OF THICKNESS:
As ‘d’ is less than the effective depth of (6.50-1.00) = 5.50 in, the thickness of 6.50 in
can be adopted.
REINFORCEMENT CALCULATION:
Let, a = 1 inch
At interior support:
Similarly at Midspan:
As = (4.13 x 12)/(0.90 x 60 x 5.29) = 0.17 in²
At Exterior support:
As = (2.41 x 12)/(0.90 x 60 x 5.29) = 0.10 in²
MINIMUM REINFORCEMENT:
As = 0.0018 x 12 x 6.50 = 0.14 in²
So we have to provide this amount of reinforcement where As is less than 0.14 in².
SHRINKAGE REINFORCEMENT:
Minimum reinforcement for shrinkage and temperature is
As = 0.0018 x 12 x 6.50 = 0.14 in²
FINAL DESIGN:
SAQIB IMRAN 70
71 | P a g e
SAQIB IMRAN 71
72 | P a g e
SAQIB IMRAN 72
73 | P a g e
Spirals, on the other hand, serve in addition to these benefits in compensating for the strength loss due
to spalling of the outside concrete shell at ultimate column strength.
7. Ties:
For longitudinal bars, 32 mm or smaller, lateral ties 10 mm in diameter should be used. In our country
and in some neighboring countries, ties of 8 mm dia are used for column construction
Case 1: Walls with earth levelled with the top of the wall:
a) Horizontal pressure per sq.m (ph) at a depth of (h) meter below the levelled top is given by the
following formula:
Where
w = Weight of filling in kg/m3
ϕ = Angle of repose of the soil.
b) Total horizontal pressure (P) at a depth of (h) meter per meter length of the wall is given by the
following formula:
SAQIB IMRAN 73