) fullstop
Each (after fullstop) E should be capital
Post poned should be corrected as single word "Postponed"
1.2 can be named as "Objectives of the work"
1.2 point no 2 correct spelling thee as "the"
Page 2 Company name : You may think of better name than this
Turnover : You may assume and put as it is virtual company
Major sub-contractors : You can mention refer to page / section …
Estimation team has mentioned the names of sub-con
Page 3 Project specification : Clubhouse project is not very appropriate. You may
mention page no / section no etc
There is separate section on specifications. You may give reference to that
Page 7 Section 2.5.1 - Use Tender document or Tender BOQ. Tender bid BOQ doesn’t
sound appropriate
2.5.3 Wor (W) should be small and not capital. And it should be Works. In
contractual language, we use a word - WORKS e.g. RCC works, Waterproofing
works, Masonry works etc.
Page 8 On page no 2, you are mentioning budget as 29 Lacs and on page 8 , section
2.5.4, it is mentioned as 35.5 L.
Mention clearly that 35.5 L is inclusive of GST.
Use same figure both places
E.g. either mention 29 Lacs + 18% GST Extra or 35.5 L incl GST
Page 9 point (i) tractor trolley can easily enter the site
You have included services in 7.0 so title can be corrected as finishes &
services
Page 14 Fig No. 4, Put column no C1 and C5 in the box
Page 14 point e, (It) first letter after full stop is capital
fig no. 5, Whole pasting image in word, zoom in PDF, select image and then
paste to get clear image
Fig no. 6 ( same feedback as fig no 5)
Fig no. 7 ( same feedback as fig no 5)
Page 30 Point 21, shift to next page using page break command
Page 40 Start first line from start of page. Delete unwanted space
Page 53 Section 4.2.3. This project has fly ash brick masonry. Don’t use word
blockwork
Page 57 4.3.3 Checklist for blockwork ? We are using brick and not AAC blocks.
Add one more point. Metal beaning should be done at joints of dissimilar
material.
Non shrink grout mix mortar to be filled between beam soffit and last layer
Page 58-67 Use page break command effectively and format table well