Professional Documents
Culture Documents
DESIGN CALCULATION FOR CASTING OF BEAM &
SLABs AT 1ST FLORO TO 3RD FLOOR
FOR
CADANGAN MEMBINA 1 BLOK PEJABAT YANG
MENGANDUNGI:‐
I. 5 TINGKAT PEJABAT BERSERTA
II. 2 TINGKAT TEMPAT LETAK KENDERAAN
ARAS TANAH DAN ARAS BAWAH TANAH DI ATAS SEBAHAGIAN
LOT 3667, LOT KOMERSIAL, JALAN DESA KIARA, MUKIM BATU,
KUALA LUMPUR
UNTUK
TETUAN KIARAMAS DEVELOPMENT SDN. BHD.
Scope of Report
Description: Scaffolding Support (180mm thick) Drwg. Ref.: Checked By: Sheet No.: 1
Loading data
The proposed scaffolding is to support loads for casting of RC slabs with maximum
150mm thickness at all floor levels. Scaffolding frame is to be erected at level below
and back props to be provided if necessary.
The proposed temporary support for casting of RC slab using Huatraco scaffolding
frames spaced within allowable working load.
The scaffolding frames are spaced at maximum 1.8m c/c. Computation shall consider
loading on intermediate one frame:-
2”x4” timber joist at base @450mm c/c = 0.05 x 0.1 x 1000 x 6 x 1.8 = 54kg
12mm thick plywood rest on timber joist = 0.012 x 1.8 x 1.2 x 1000 = 26kg
Say DL = 8.95kN
Project: KCS Job No.: Designed By: Date: 03/10/2022
Description: Scaffolding Support (150mm thick) Drwg. Ref.: Checked By: Sheet No.: 2
For typical opened-leg scaffold frame, the bearing capacity per set = 10 tonnes
Consider the used condition of scaffolding frame, the load bearing capacity shall be
reduced to 50% = 5 tonnes
= 50kN < 12.19kN
OK
Thus, the loading from scaffolding frame is within the capacity of one scaffolding
frame.
Total UDL load available for scaffolding = 2(2) + 2(2.5) = 9.0kN/m2 < 5.64kN/m2 OK
Project: KCS Job No.: Designed By: Date: 03/10/2022
Description: Scaffolding Support (150mm thick) Drwg. Ref.: Checked By: Sheet No.: 3
Description: Scaffolding Support (RC Beam) Drwg. Ref.: Checked By: Sheet No.: 4
The proposed scaffolding is to support loads for casting of typical RC beam at 1st floor
to 3rd floor level with most critical size. Scaffolding frame is to be erected at level
below and back props to be provided if necessary.
The proposed temporary support for casting of RC beams using Huatraco scaffolding
frames spaced within allowable working load.
Consider the more critical case, i.e 450 x 600 dimension based on scaffolding spacing at
1m c/c,
2”x4” timber joist at base @450mm c/c = 0.05 x 0.1 x 1000 x 6 x 1.8 = 54kg
12mm thick plywood rest on timber joist = 0.012 x 1.8 x 1.2 x 1000 = 26kg
Say DL = 7.65kN
Project: KCS Job No.: Designed By: Date: 03/10/2022
Description: Scaffolding Support (RC Beam) Drwg. Ref.: Checked By: Sheet No.: 5
For typical opened-leg scaffold frame, the bearing capacity per set = 10 tonnes
Consider the used condition of scaffolding frame, the load bearing capacity shall be
reduced to 50% = 5 tonnes
= 50kN > 9.45kN
OK
Thus, the loading from scaffolding frame is within the capacity of one scaffolding
frame.
Total UDL load available for scaffolding = 2(2.0) + 2(2.5) = 9.0kN/m2 > 7.87kN/m2 OK
Project: KCS Job No.: Designed By: Date: 03/10/2022
Description: Scaffolding Support (RC Beam) Drwg. Ref.: Checked By: Sheet No.: 6