ICON PLAZA PROJECT


CP-02 Phase 1
Production Learning Projection Curve
60% 100%

REBAR 90%
FORM
CONCRETING
50% CUM REBAR
CUM FORM
CUM CONRETING
80%

70%
40%

60%

30% 50%

Line Percentage
Bar Percentage

40%

20%
30%

20%
10%

10%
Period

0% Sep-2010 Oct-2010 Nov-2010 Dec-2010 Jan-2011 14-Feb-11 Target March 3


0%

REBAR 2% 55% 14% 5% 6% 6% 12%


FORM 1% 5% 5% 10% 18% 15% 46%
CONCRETING 2% 17% 30% 3% 14% 8% 26%
CUM REBAR 2% 57% 71% 76% 82% 88% 100%
CUM FORM 1% 6% 11% 21% 39% 54% 100%
CUM CONRETING 2% 19% 49% 53% 67% 74% 100%
Page 1
Chart1‐Ph1 qty
ICON PLAZA
CP-02
PHASE 1 COMPLETION
8,000 Quantity Curves Target 18,000

7,000
15,000

REBAR (100-kg)
6,000 FORM (m2)
CONCRETING (cu.m)
CUM REBAR (100-kg)
CUM FORM (m2)
CUM CONCRETING (m3)
12,000
5,000
Bar Qty

Line Qty
4,000 9,000

3,000
6,000

2,000

3,000
1,000
PERIOD

- -
Sep-2010 Oct-2010 Nov-2010 Dec-2010 Jan-2011 14-Feb-11 Target March 3
REBAR (100-kg) 245 6,739 1,674 618 761 695 1,480
FORM (m2) 155 774 810 1,630 2,952 2,397 7,390
CONCRETING (cu.m) 148 1,023 1,860 208 865 484 1,577
CUM REBAR (100-kg) 245 6,984 8,658 9,275 10,037 10,731 12,212
CUM FORM (m2) 155 929 1,739 3,370 6,322 8,719 16,109
CUM CONCRETING (m3) 148 1,171 3,031 3,239 4,104 4,588 6,165