Presentation Date: 09th MARCH 2023 1

CONSTRUCTION, COMPLETION AND MAINTENANCE OF GWC AL-WUKAIR LOGISTIC PARK – PHASE II


(PACKAGE 1) – 03 MARCH 2023
Project Metrics
WEEK NO. 47 – BASELINE WEEK NO. 47 – RECOVERY 2
PROGRESS PERCENTAGE ELAPSED TIME PROGRESS PERCENTAGE
-14.88%
2.02%
29%
88.69% 73.81% 71.79%
73.81%
71%

Plan Progress % Actual Progress % Recovery Progress % Actual Progress %


Time Spent to date Remaining Duration
Variance Variance

Milestone 1 - Completion of Milestone 2 - Completion of Milestone 3 - Physical


Particular Project Commencement
Engineering Precast Structure Erection Completion of all Works

Contractual / Planned 22-Mar-22 18-Aug-22 15-Jan-23 15-May-23

EOT - - -

Baseline 22-Mar-22 24-Nov-22 24-Dec-22 15-May-23

Recovery 22-Mar-22 24-Nov-22 24-Dec-22 15-May-23

Variance (+ / -) Forecasted - - - 0

Elapsed Days - 345 345 345

Remaining Days - 0 0 74

CONSTRUCTION, COMPLETION AND MAINTENANCE OF GWC AL-WUKAIR LOGISTIC PARK – PHASE II (PACKAGE 1)
3
PROJECT HIGH LEVEL RECOVERY UPDATE
4
CONSTRUCTION, COMPLETION AND MAINTENANCE OF GWC AL-WUKAIR LOGISTIC PARK – PHASE II
(PACKAGE 1) 03 March 2023 Recovery Program Update
120.00%

100%
100% 97.53%
100.00%
92.43%
84.91%
84.95%
75.72%
80.00% 71.79% 73.81% 71.85%

60.00%

43.27% 42.73%

40.00%

20.00%

0% 0% 0% 0% 0% 0%
0.00%
TOTAL GENERAL AUTHORITIES ENGINEERING PROCUREMENT CONSTRUCTION T&C CLOSE OUT Demobilization
PERMITS
#REF! ACTUAL
400
600
800

200

0
1,000
1,200
1,400
1,800
2,000

1,600
Mar-22 25
25

Apr-22 74
74

May-22 95
95

Jun-22 450
450

Jul-22 540
540

Aug-22 840
840

Sep-22 1,003
1,003

Oct-22 1,307
1307

Nov-22 1,568
1,568

Dec-22 1,697
1,797
PROJECT MANPOWER

Jan-23 1,700
1,654

Feb-23 1,705
Monthly Manpower Histogram Recovery VS Actual

1,607

Mar-23 1,743
1,664

Apr-23 1,746

May-23 1,250

Jun-23 454
5

Jul-23 87
50
100
150
200
250
300

0
124
GENERAL HELPER
110

185
CARPENTER
175

110

Recovery
STEEL FIXER
105

32

Actual
WELDER
29
268
MASON
255
70
WATERPROOF INSTALLER
68

ALUMINUM INSTALLER &ROLLER 77


SHUTTER 70

113
OPERATOR
110

11
ERECTOR HELPER
13
PROJECT MANPOWER

210
ELECTRICAL TECHNICIANS
204
MANPOWER RECOVERY VS ACTUAL - Mar 2022

43
PIPE FILTER
40

74
PLUMBER
70

57
ELV
55
6

60
SPLIT AC INSTALLER
55

86
TECHNICAL TEAM ( Assistant)
84
7
ADMIN ROOF WATERPROOFING PROGRESS (02.03.023)

FLOOR Admin Roof Admin Roof polyfoam Admin Roof Top


Admin roof Primer
BLOCK No. TILES Membrane and geotextile screed
m2 m2 % m2 % m2 % m2 %
BLOCK 13 1,200 1200 100.0% 1200 100.0% 1200 100.0% 1200 100.0%
BLOCK 7 1,200 1200 100.0% 1200 100.0% 1200 100.0% 1200 100.0%
BLOCK 5 1,200 1200 100.0% 1200 100.0% 1200 100.0% 1200 100.0%
BLOCK 14 1,200 1200 100.0% 1020 85.0% 600 50.0% 600 50.0%
BLOCK 8 1,200 1200 100.0% 1200 100.0% 1200 100.0% 1200 100.0%
BLOCK 11 1,200 1200 100.0% 1200 100.0% 1200 100.0% 1200 100.0%
BLOCK 6 1,200 1200 100.0% 1200 100.0% 1200 100.0% 1200 100.0%
BLOCK 9 1,200 1200 100.0% 1200 100.0% 1200 100.0% 1200 100.0%
BLOCK 3 1,200 1200 100.0% 1200 100.0% 1200 100.0% 1200 100.0%
BLOCK 12 1,200 1200 100.0% 1200 100.0% 1200 100.0% 1200 100.0%
BLOCK 10 1,200 1200 100.0% 1200 100.0% 1200 100.0% 1200 100.0%
BLOCK 4 1,200 1200 100.0% 1200 100.0% 1200 100.0% 1200 100.0%
BLOCK 1 1,200 1200 100.0% 1200 100.0% 618 51.5% 618 51.5%
BLOCK 2 1,200 1200 100.0% 1200 100.0% 643 53.6% 643 53.6%
Total 16,800 16800 100.0% 16620 98.9% 15061 89.6% 15061 89.6%
8

SURFACE PREPARATION & POLYUREA PROGRESS 02.03.023


Precoating Polyurea Top coat Water
Surface preparation MEP Roof Handover Primer Application
BLOCK No. to Aquaproof by preparation Application Application Leak Test
clearance AAE
m2 % m2 % m2 % m2 % m2 % %
BLOCK 13 8000 100.0% yes yes 8000 100.0% 8000 100.0% 8000 100.0% 8000 100.0% 0
BLOCK 7 8000 100.0% yes yes 8000 100.0% 8000 100.0% 8000 100.0% 8000 100.0% 0
BLOCK 11 8000 100.0% yes yes 8000 100.0% 8000 100.0% 8000 100.0% 7000 90.0% 0
BLOCK 5 8000 100.0% yes yes 8000 100.0% 8000 1000.0% 8000 100.0% 8000 100.0% 0
BLOCK 12 0 0.0% no no 0 0.0% 0 0.0% 0 0.0% 0 0.0% 0
BLOCK 8 8000 100.0% no no 0 0.0% 0 0.0% 0 0.0% 0 0.0% 0
BLOCK 6 6000 70.0% no no 0 0.0% 0 0.0% 0 0.0% 0 0.0% 0
BLOCK 9 8000 100.0% no no 8000 100.0% 0 0.0% 0 0.0% 0 0.0% 0
BLOCK 10 0 0.0% no no 0 0.0% 0 0.0% 0 0.0% 0 0.0% 0
BLOCK 3 8000 100.0% no no 8000 100.0% 0 0.0% 0 0.0% 0 0.0% 0
BLOCK 4 0 0.0% no no 0 0.0% 0 0.0% 0 0.0% 0 0.0% 0
BLOCK 1 7500 70.0% no no 0 0.0% 0 0.0% 0 0.0% 0 0.0% 0
BLOCK 2 8000 100.0% no no 0 0.0% 0 0.0% 0 0.0% 0 0.0% 0
BLOCK 14 8000 100.0% yes yes 8000 100.0% 2500 35.0% 2500 35.0% 540 5.0% 0
Total Progress 74.3% Progress 50.0% Progress 95.4% Progress 31.1% Progress 28.2%
9

PAINTING OF INTERNAL WALLS (02.03.2023)

Internal Walls
BLOCK No. Total 2nd Stucco 1st coat paint
Primer progress 1st Stucco progress
Area progress progress
m2 m2 Progress % m2 Progress m2 Progress m2 Progress
BLOCK 13 11,915 11,915 100% 11915 100% 11915 100% 11915 100%
BLOCK 7 11,915 11,915 100% 11915 100% 11915 100% 11915 100%
BLOCK 5 11,915 11,915 100% 11,915 100% 11915 100% 11915 100%
BLOCK 8 11,915 11,915 100% 11915 100% 11915 100% 11915 100%
BLOCK 11 11,915 11,915 100% 11,915 100% 11915 100% 11915 100%
BLOCK 6 11,915 11,915 100% 11915 100% 11915 100% 11584 97%
BLOCK 9 11,915 11,915 100% 11,915 100% 11915 100% 11915 100%
BLOCK 3 11,915 11,915 100% 11915 100% 11915 100% 11915 100%
BLOCK 12 11,915 11,915 100% 11,915 100% 11915 100% 11915 100.0%
BLOCK 10 11,915 11,915 100% 11915 100% 11915 100% 10591 89%
BLOCK 4 11,915 11,915 100% 11,617 98% 11617 98% 10724 90.0%
BLOCK 1 11,600 8,990 78% 7219 62% 0 0% 0 0%
BLOCK 2 10,660 10,279 96% 6,750 63% 4645 43.6% 0 0.0%
BLOCK 14 11,915 8,506 71% 8506 71% 7281 61% 7281 61%
Total 165,240 158,840 91.0% 153,242 92.7% 142,693 86.4% 135,500 82.0%
10
PAINTING OF INTERNAL CEILING & EXTERNAL FACAD0 2.03.023

Internal Ceiling External Paint


BLOCK No. Total 1st Stucco 2nd Stucco 1st coat paint Total
Primer progress Primer progress Splatter progress 1ST COAT PAINT progress
Area progress progress progress Area
m2 m2 % m2 % m2 % m2 % m2 m2 % m2 % m2 %
BLOCK 13 8,110 8,110 100% 8110 100% 8110 100% 8110 100% 5,310 5,310 100% 5,310 100% 5,310 100%
BLOCK 7 8,110 8,110 100% 8110 100% 8110 100% 8090 100% 5,310 5,283 100% 5,283 100% 5,283 100%
BLOCK 5 8,110 8,110 100% 8,110 100% 8110 100% 8110 100% 5,310 5,310 100% 5,310 100% 5,310 100%
BLOCK 8 8,110 8,110 100% 8110 100% 8110 100% 8110 100% 5,310 5,310 100% 5,310 100% 5,310 100%
BLOCK 11 8,110 8,110 100% 8,110 100% 8110 100% 8110 100% 5,310 5,310 100% 5,310 100% 5,310 100%
BLOCK 6 8,110 8,110 100% 8110 100% 8110 100% 7885 97% 5,310 5,310 100% 5,310 100% 5,310 100%
BLOCK 9 8,110 8,110 100% 8,087 100% 8087 100% 8087 100% 5,310 5,310 100% 5,310 100% 5,310 100%
BLOCK 3 8,110 8,110 100% 8110 100% 8110 100% 8110 100% 5,310 5,310 100% 5,310 100% 5,310 100%
BLOCK 12 8,110 8,110 100% 8,110 100% 8110 100.0% 8110 100% 5,310 5,310 100% 5,310 100% 5,310 100%
BLOCK 10 8,110 8,110 100% 7209 89% 8110 100% 7209 89% 5,310 5,310 100% 5,310 100% 5,310 100%
BLOCK 4 8,110 8,110 100% 7,907 98% 7907 97.5% 7299 90% 5,310 5,310 100% 5,310 100% 2,655 50%
BLOCK 1 8,110 6,285 78% 5033 62% 0 0% 0 0% 5,170 5,170 100% 4,714 91% 2,661 51%
BLOCK 2 8,110 8,110 100% 5,955 73% 3447 42.5% 1159 14% 4,750 4,750 100% 4,691 99% 2,307 49%
BLOCK 14 8,110 6,691 83% 5790 71% 4956 61% 4956 61% 5,310 5,310 100% 5,310 100% 5,310 100%
Total 113,540 110,296 97.1% 104,861 92.4% 97,388 85.8% 93,344 82.2% # 73,640 73,613 100.0% 73,098 99.26% 66,007 89.63%
11

TILE WORK PROGRESS 02.03.023

ADMIN
TOILET FLOOR TOILET FLOOR TILES TOILET WALLS TOILET WALLS TILES ADMIN DRY AREA FLOOR
FLOOR TILES
BLOCK No. TILES AREA PROGRESS TILES AREA PROGRESS TILES PROGRESS
AREA
m2 m2 Progress % m2 m2 Progress % m2 m2 Progress %
BLOCK 13 125 125 100.0% 760 760 100.0% 981 981 100.0%
BLOCK 7 125 125 100.0% 760 760 100.0% 981 981 100.0%
BLOCK 5 125 125 100.0% 760 760 100.0% 981 981 100.0%
BLOCK 14 125 66 52.5% 760 399 52.5% 981 981 100.0%
BLOCK 8 125 125 100.0% 760 760 100.0% 981 981 100.0%
BLOCK 11 125 125 100.0% 760 760 100.0% 981 981 100.0%
BLOCK 6 125 125 100.0% 760 760 100.0% 981 981 100.0%
BLOCK 9 125 125 100.0% 760 760 100.0% 981 905 92.2%
BLOCK 3 125 125 100.0% 760 739 97.2% 981 411 41.9%
BLOCK 12 125 125 100.0% 760 760 100.0% 981 491 50.0%
BLOCK 10 125 125 100.0% 760 760 100.0% 981 0 0.0%
BLOCK 4 125 0 0.0% 760 0 0.0% 981 0 0.0%
BLOCK 1 122 60 49.0% 740 285 38.5% 955 0 0.0%
BLOCK 2 111 0 0.0% 680 0 0.0% 877 0 0.0%

Total 1,738 1380 79.4% 10,540 8,263 78.4% 13,604 8674 63.8%
12

CEILING WORK PROGRESS 02.03.023

ADMIN CEILING TILES - ADMIN CEILING Framing ADMIN CEILING TILES


BLOCK No. Total Area INSTALLATION INSTALLATION

m2 m2 Progress % m2 Progress %
BLOCK 13 1,116 1116 100% 1116 100%
BLOCK 7 1,116 1116 100% 0 0%
BLOCK 5 1,116 1116 100% 0 0%
BLOCK 14 1,116 558 50% 0
BLOCK 8 1,116 1116 100% 0
BLOCK 11 1,116 1116 100% 0
BLOCK 6 1,116 187 17% 0
BLOCK 9 1,116 985 88% 0
BLOCK 3 1,116 0 0% 0
BLOCK 12 1,116 28 3% 0
BLOCK 10 1,116 0 0% 0
BLOCK 4 1,116 0 0% 0
BLOCK 1 1,087 0 0% 0
BLOCK 2 999 0 0% 0
Total 15,478 7338 47.0% 1116 7.1%
13
ALUMINUM DOORS & WINDOWS INSTALLATION PROGRESS 02.03.023
Aluminium Swing Door WINDOW 0.6m X 0.6m WINDOW 1m x 1m
Frame Glass Frame Glass Frame Glass
Total Total Total
BLOCK Done Done Done Total no of Done Done
Quantity Progress % Progress % Quantity Progress % Progress % Quantity Progress % Progress %
(doors) (doors) (Windows) completion (Windows) (Windows)

BLOCK 13 38 38 100% 38 100% 38 38 100% 38 100% 38 38 100% 38 100%


BLOCK 7 38 38 100% 31 82% 38 38 100% 38 100% 38 38 100% 38 100%
BLOCK 5 38 38 100% 27 71% 38 19 50% 19 50% 38 38 100% 38 100%
BLOCK 14 38 19 50% 19 50% 38 19 50% 19 50% 38 19 50% 19 50%
BLOCK 8 38 28.5 75% 20 53% 38 37 97% 19 50% 38 37 97% 27.5 72%
BLOCK 11 38 38 100% 38 100% 38 38 100% 38 100% 38 38 100% 38 100%
BLOCK 6 38 22.5 59% 19 50% 38 19 50% 19 50% 38 19 50% 19 50%
BLOCK 9 38 38 100% 38 100% 38 37 97% 18 47% 38 38 100% 38 100%
BLOCK 03 38 0 0% 0 0% 38 0 0% 0 0% 38 0 0% 0 0%
BLOCK 12 38 38 100% 38 100% 38 38 100% 37 97% 38 38 100% 38 100%
BLOCK 10 38 38 100% 28.5 75% 38 38 100% 19 50% 38 38 100% 28.5 75%
BLOCK 4 38 0 0% 0 0% 38 0 0% 0 0% 38 0 0% 0 0%
BLOCK 1 37 0 0% 0 0% 37 0 0% 0 0% 37 0 0% 0 0%
BLOCK 2 34 0 0% 0 0% 34 0 0% 0 0% 34 0 0% 0 0%
Total Progress 63% Progress 56% Progress 60% Progress 50% Progress 64% Progress 61%
14
WAREHOUSE STEEL DOOR INSTALLATION PROGRESS 02.03.023

Doors installation
block Total no of doors
installed doors progress %
block 13 114 114 100%
block 7 114 114 100%
block 5 114 114 100%
block 14 114 57 50%
block 8 114 114 100%
block 11 114 114 100%
block 6 114 114 100%
block 9 114 114 100%
block 03 114 89 78%
block 12 114 109 96%
block 10 114 104 91%
block 4 114 76 67%
block 1 111 74 67%
block 2 102 66 65%
Total 87%
15

ROLLER SHUTTER PROGRESS 02.03.023


Receiver W/
Motor
BLOCK Total Slat Curtain Set Shaft-Pipe Bracket Motor Cover Roll Cover Guide R&L S. Key Box Push Button Sensor 2NOS %Progress
Set Remotes
BLOCK 01 37 37 37 37 37 37 37 37 19 37 77.40%
BLOCK 02 34 34 34 34 34 34 34 34 19 34 77.81%
BLOCK 03 38 38 38 38 38 38 38 38 38 38 81.82%
BLOCK 04 38 38 38 38 38 38 38 38 19 38 77.27%
BLOCK 05 38 38 38 38 38 38 38 38 38 38 38 38 100.00%
BLOCK 06 38 38 38 38 38 38 38 38 38 38 81.82%
BLOCK 07 38 38 38 38 38 38 38 38 38 38 38 38 100.00%
BLOCK 08 38 38 38 38 38 38 38 38 38 38 38 38 100.00%
BLOCK 09 38 38 38 38 38 38 38 38 38 38 38 38 100.00%
BLOCK 10 38 38 38 38 38 38 38 38 38 38 19 19 90.91%
BLOCK 11 38 38 38 38 38 38 38 38 38 38 38 38 100.00%
BLOCK 12 38 38 38 38 38 38 38 38 38 38 38 38 100.00%
BLOCK 13 38 38 38 38 38 38 38 38 38 38 38 38 100.00%
BLOCK 14 38 19 19 22 19 19 19 19 34 19 19 19 54.31%
16

MARBLE INSALLATION PROGRESS 02.03.023


Threshold For Aluminium door Threshold For Toilet door External marble
BLOCK Total Total
installed installed Total Area installed
length progress % length progress % progress %
(m`) (m`) ( m2 ) (m2)
(m`) (m`)
BLOCK 13 95 95 100% 38 38 100% 240 114 47.37%
BLOCK 7 95 95 100% 38 38 100% 240 227 94.74%
BLOCK 5 95 95 100% 38 38 100% 240 196 81.58%
BLOCK 14 95 48 50% 38 19 50% 240 120 50.00%
BLOCK 8 95 95 100% 38 38 100% 240 227 94.74%
BLOCK 11 95 95 100% 38 38 100% 240 227 94.74%
BLOCK 6 95 95 100% 38 38 100% 240 221 92.11%
BLOCK 9 95 95 100% 38 38 100% 240 227 94.74%
BLOCK 03 95 95 100% 38 38 100% 240 76 31.58%
BLOCK 12 95 95 100% 38 38 100% 240 234 97.37%
BLOCK 10 95 95 100% 38 38 100% 240 234 97.37%
BLOCK 4 95 48 50% 38 0 0% 240 0 0.00%
BLOCK 1 92.5 41 45% 37 0 0% 234 0 0.00%
BLOCK 2 85 40 47% 34 0 0% 215 0 0.00%
Total Progress 85% Progress 75% Progress 62.59%
17
MOB SUNKEN EPOXY PROGRESS 02.03.023
1ST COAT of Final COAT of

Total No. of mob


BLOCK WORK PLASTERING Epoxy primer Epoxy stucco
Epoxy paint Epoxy paint

sunken

progress %

progress %

progress %

progress %

progress %

progress %
completed

completed

completed

completed

completed

completed
BLOCK

nos

nos

nos

nos

nos

nos
BLOCK 13 38 38 100% 38 100% 38 100% 38 100% 38 100% 38 100%
BLOCK 7 38 38 100% 38 100% 38 100% 38 100% 38 100% 38 100%
BLOCK 5 38 38 100% 38 100% 38 100% 38 100% 38 100% 38 100%
BLOCK 14 38 38 98% 37 95% 19 50% 19 50% 0 0% 0 0%
BLOCK 8 38 38 100% 38 100% 19 50% 19 50% 0 0% 0 0%
BLOCK 11 38 38 100% 38 100% 38 100% 38 100% 38 100% 29 76%
BLOCK 6 38 38 100% 38 100% 5 13% 0 0% 0 0% 0 0%
BLOCK 9 38 38 100% 38 100% 19 50% 0 0% 0 0% 0 0%
BLOCK 03 38 38 100% 38 100% 0 0% 0 0% 0 0% 0 0%
BLOCK 12 38 38 100% 38 100% 0 0% 0 0% 0 0% 0 0%
BLOCK 10 38 38 100% 38 100% 0 0% 0 0% 0 0% 0 0%
BLOCK 4 38 38 100% 38 100% 0 0% 0 0% 0 0% 0 0%
BLOCK 1 37 37 100% 20 51% 0 0% 0 0% 0 0% 0 0%
BLOCK 2 34 20 57% 14 41% 0 0% 0 0% 0 0% 0 0%
Total 96.76% 91.97% 40.23% 35.71% 28.57% 26.88%
18

FIRE SEALANT PROGRESS 02.03.023


Rockwool Application Fire sealant application
Block Total
Done warehouse progress % Done warehouse progress %
BLOCK 13 38 38 100% 38 100.00%
BLOCK 7 38 38 100% 38 100.00%
BLOCK 5 38 38 100% 38 100.00%
BLOCK 14 38 24.7 65% 25 65.00%
BLOCK 8 38 38 100% 38 100.00%
BLOCK 11 38 38 100% 38 100.00%
BLOCK 6 38 38 100% 38 100.00%
BLOCK 9 38 38 100% 38 100.00%
BLOCK 03 38 38 100% 38 100.00%
BLOCK 12 38 38 100% 38 100.00%
BLOCK 10 38 38 100% 38 100.00%
BLOCK 4 38 38 100% 8 21.05%
BLOCK 1 37 35 95% 0 0.00%
BLOCK 2 34 24 71% 0 0.00%
Total Progress 95% Progress 77.58%
19

MEP PROGRESS
20
LIGHTNING PROTECTION BORE HOLE & EARTH ROD FIXING PROGRESS - B3 BUILDINGS PROGRESS OF 05.03.023

Pit Refeferce B3-A1 B3-A2 B3-A3 B3-A4 B3-A5 B3-A6 B3-A7 B3-A8 B3-A9 B3-A10 B3-A11 B3-A12 B3-A13 B3-A14
LPE-01 ✓ X ✓ X X X ✓ X ✓ X ✓ ✓ X X
LPE-02 ✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓
LPE-03 ✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓
LPE-04 ✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓
LPE-05 ✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓
LPE-06 ✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓
LPE-07 ✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓
LPE-08 ✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓
LPE-09 ✓ X ✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓
LPE-10 ✓ X ✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓
LPE-11 ✓ X ✓ ✓ X X ✓ X ✓ X X X ✓ X
LPE-12 ✓ ✓ ✓ X X X ✓ X ✓ X X X ✓ X
LPE-13 ✓ ✓ ✓ X X X X X ✓ X X X X X
LPE-14 ✓ X ✓ X X X ✓ X ✓ X X X ✓ X
LPE-15 ✓ ✓ ✓ X X X ✓ X ✓ X X X ✓ X
LPE-16 ✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓
LPE-17 ✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓
LPE-18 ✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓
LPE-19 ✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓
LPE-20 ✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓
LPE-21 ✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓
LPE-22 ✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓
LPE-23 ✓ X ✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓
LPE-24 ✓ X ✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓
LPE-25 ✓ X ✓ X ✓ X ✓ X ✓ X ✓ ✓ ✓ ✓
LPE-26 ✓ X ✓ X ✓ X ✓ X ✓ X ✓ ✓ ✓ ✓
LPE-27 ✓ NA ✓ X ✓ X ✓ X ✓ X ✓ ✓ ✓ ✓
LPE-28 ✓ NA ✓ X X X ✓ X ✓ X ✓ ✓ ✓ ✓
TOTAL 28 17 28 19 21 18 27 18 28 18 23 23 26 22
21
LIGHTNING PROTECTION BORE HOLE & EARTH ROD FIXING PROGRESS – SUBSTATIONS 02.03.023

LIGHTNING PROTECTION BORE HOLE & EARTH ROD


FIXING PROGRESS - SUBSTATIONS
Pit Refeferce SS-05 SS-15 SS-16 SS-17 SS-18
LPE-01 X ✓ X X ✓
LPE-02 X ✓ X X X
LPE-03 X X X X X
LPE-04 X X X X ✓
LPE-05 NA NA NA X NA
LPE-06 NA NA NA X NA
TOTAL 0 2 0 0 2
22

PROGRESS OF INFRA (ELECTRICAL, MV, ELV Networks) 05.03.023

Total length Excavation completed Cable installation Containment installation


Sl. No System Remarks
in Meters length % Length % Completed Length % Completed
MV inspection by KM
1 MV Network 3500 2030 58% 1610 52% N/A N/A
completed.

Inspections ongoing,
Progressed on
2 LV Network 21500 11825 55% 10750 50% N/A N/A
External Lighting
Related works

Duct banks are in


3 ELV CCTV 7200 3456 48% 360 5% 3240 45% progress along with
the JRC installtion
Duct banks are in
4 TELECOM 8600 4128 48% 430 5% 3870 45% progress along with
the JRC installtion
MECHANICAL ( F. F) WORK PROGRESS 08.03.2023
23
A01 A02 A03 A04 A05 A06 A07 A08 A09 A10 A11 A12 A13 A14
S.n. ACTIVITIES DESCRIPTION
WH Ad WH Ad WH Ad WH Ad WH Ad WH Ad WH Ad WH Ad WH Ad WH Ad WH Ad WH Ad WH Ad WH Ad

Installation of Supports & Fire fighting mainline Piping


1 100% N/A 100% N/A 100% N/A 100% N/A 100% N/A 100% N/A 100% N/A 100% N/A 100% N/A 100% N/A 100% N/A 100% N/A 100% N/A 100% N/A
(roof)
2 Installation of Supports & Fire fighting Dropper Piping 70% N/A 20% N/A 95% N/A 95% N/A 95% N/A 95% N/A 95% N/A 95% N/A 95% N/A 95% N/A 95% N/A 95% N/A 100% N/A 100% N/A
3 Pressure test of Fire Fighting Piping N/A N/A N/A N/A 100% N/A 100% N/A 100% N/A 100% N/A 100% N/A N/A 100% N/A 10% N/A 100% N/A N/A
4 Installation of Fire Hose Cabinet N/A N/A 75% N/A 75% N/A 85% N/A 75% N/A 85% N/A 75% N/A 75% N/A 60% N/A 80% N/A 75% N/A 95% N/A 45% N/A
FIRE FIGHTING

5 Installation of Extinguishers N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A
6 Installation of fire fighting Isolating Valves N/A N/A N/A N/A 60% N/A N/A 60% N/A 40% N/A N/A N/A N/A N/A 90% N/A 40% N/A
7 Installation of FM200 Electrical conduits & wires 95% N/A N/A 95% N/A 30% N/A 95% N/A 50% N/A 95% N/A 50% N/A 95% N/A 50% N/A 95% N/A 50% N/A 95% N/A 50% N/A
8 Installation of FM200 Electrical devices N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A 85% N/A N/A 95% N/A N/A
9 Installation of FM200 piping 100% N/A 100% N/A 100% N/A 100% N/A 100% N/A 100% N/A 100% N/A 100% N/A 100% N/A 100% N/A 100% N/A 100% N/A 100% N/A 100% N/A
10 Pressure test of FM 200 Piping 10% N/A N/A 80% N/A N/A 100% N/A N/A 100% N/A N/A 100% N/A N/A 100% N/A N/A 100% N/A N/A
11 Installation of FM200 Nozzle & Cylinder N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A 30% N/A N/A
total firefighting percentage 83% 75% 91% 91% 95% 94% 95% 94% 95% 90% 96% 91% 98% 89%
32 fire pump room 27%
32 fire water tank 76%

sn Delivery delivery Status Balance material status


1 Fire Hose Cabinet 100.00%
2 Fire Hose reel 100.00%
3 Fire fighting valves inside building 95.00% Mar 23,2023
4 fire Extinguishers 0.00% Apr 15,2022
5 FM200 Nozzle & Cylinder 30.00% Apr 15,2023
6 fire water tanks 100.00%
7 Fire pump 0.00% Apr 25,2023
MECHANICAL ( WATER SUPPLY) PROGRESS 08.03.2023 24
A01 A02 A03 A04 A05 A06 A07 A08 A09 A10 A11 A12 A13 A14
S.n. ACTIVITIES DESCRIPTION
WH Ad WH Ad WH Ad WH Ad WH Ad WH Ad WH Ad WH Ad WH Ad WH Ad WH Ad WH Ad WH Ad WH Ad

12 Installation of PPR pipes above Ceiling N/A 100% N/A 100% N/A 100% N/A 100% N/A 100% N/A 100% N/A 100% N/A 100% N/A 100% N/A 100% N/A 100% N/A 100% N/A 100% N/A 100%
water supply

13 Installation of water heater & Connection N/A 100% N/A 100% N/A 100% N/A 100% N/A 100% N/A 100% N/A 100% N/A 100% N/A 100% N/A 100% N/A 100% N/A 100% N/A 100% N/A 100%
Building connections

14 Installation of Bip tap with piping 60% N/A 60% N/A 60% N/A 60% N/A 60% N/A 60% N/A 60% N/A 60% N/A 60% N/A 60% N/A 60% N/A 60% N/A 60% N/A 60% N/A
15 Pressure test of PPR Pipes & fittings N/A 100% N/A 100% N/A 100% N/A 100% N/A 100% N/A 100% N/A 100% N/A 100% N/A 100% N/A 100% N/A 100% N/A 100% N/A 100% N/A 100%
total water supply percentage 99% 99% 99% 99% 99% 99% 99% 99% 99% 99% 99% 99% 99% 99%

29 Potable Water Piping Works & Water Meter Cabinet N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A 50% N/A 30% N/A 50% N/A 30%

33 GRP Water Tank 7%

sn Delivery delivery Status Balance material status


1 PPR pipes and fitting 100.00%
2 PPR valves inside building 100.00%
3 Bip tap 100.00%
4 Water Meters & Cabinet 100.00%
5 Water heater 100.00%
6 GRP TANK 100.00%
9 domestic water pumps 85.00% 1 No of pumps-Mar 9
11 Domestic water valves for pump room 100.00%
MECHANICAL (DRAINAGE & STORM) WORK PROGRESS 08.03.2023 25
A01 A02 A03 A04 A05 A06 A07 A08 A09 A10 A11 A12 A13 A14
S.n. ACTIVITIES DESCRIPTION
WH Ad WH Ad WH Ad WH Ad WH Ad WH Ad WH Ad WH Ad WH Ad WH Ad WH Ad WH Ad WH Ad WH Ad

16 Sewage Water Piping 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100%
Drainage system

17 Gravity test of Sewage Water Piping 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100%

18 Installation of Area drain& C.O Cover 100% N/A 20% N/A 100% N/A 100% N/A 100% N/A 100% N/A 100% N/A 100% N/A 100% N/A 100% N/A 100% N/A 100% N/A 100% N/A 90% N/A

19 Installation of Sanitary wares N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A 50% N/A
total DRAINAGE SYSTEM percentage 71% 66% 71% 71% 71% 71% 71% 71% 71% 71% 71% 71% 85% 70%
20 Installation of Roof Drains Covers 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100%
Building connections STORM

21 Storm water piping 30% 30% 70% 70% 80% 80% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100%
22 Flow test of storm water Piping 100% 100%
total Storm water SYSTEM percentage 31% 31% 50% 75% 81% 94% 94% 94% 94% 94% 94% 94% 100% 94%

30 House Connection N/A N/A 15% N/A 70% N/A 75% N/A 100% N/A 100% N/A 100% N/A 100% N/A 100% N/A 100% N/A 100% N/A 100% N/A 50% N/A 50%

31 Installation of Neutralization tank & Connection N/A N/A 20% N/A N/A 50% N/A 50% N/A 100% N/A 100% N/A 100% N/A 100% N/A 100% N/A 100% N/A 60% N/A 50% N/A

total Building connections percentage 0% 5% 30% 25% 50% 50% 67% 67% 67% 67% 83% 77% 53% 43%

sn Delivery delivery Status Balance material status


1 Area drain, Roof Drains & C.O Cover 100.00%
2 Sanitary wares 100.00%
3 Neutralization tank 100.00%
26
MECHANICAL ( ACMV) WORK PROGRESS 08.03.2023

A01 A02 A03 A04 A05 A06 A07 A08 A09 A10 A11 A12 A13 A14
S.n. ACTIVITIES DESCRIPTION
WH Ad WH Ad WH Ad WH Ad WH Ad WH Ad WH Ad WH Ad WH Ad WH Ad WH Ad WH Ad WH Ad WH Ad

23 Installation of Duct & Accessories 95% N/A 95% N/A 70% N/A 95% N/A 95% N/A 95% N/A 100% N/A 95% N/A 95% N/A 95% N/A 100% N/A 95% N/A 100% N/A 97% N/A
24 Installation of louvers 10% N/A 5% N/A 80% N/A 47% N/A 95% N/A 95% N/A 100% N/A 100% N/A 100% N/A 100% N/A 100% N/A 100% N/A 100% N/A 50% N/A
ACMV system

25 Installation of ventilation Fan in Duct N/A N/A N/A N/A 100% N/A 100% N/A 100% N/A 100% N/A 70% N/A 10% N/A 100% N/A 10% N/A 100% N/A 50% N/A
26 Installation of toilet Extraction Fan N/A N/A N/A 50% N/A N/A 100% N/A 80% N/A 100% N/A 100% N/A 100% N/A 100% N/A 100% N/A 100% N/A 100% N/A 50%
27 Installation of refrigerant pipes N/A N/A N/A 100% N/A 10% N/A 100% N/A 100% N/A 100% N/A 100% N/A 100% N/A N/A 100% N/A 100% N/A 100% N/A 50%
28 Installation of split unit N/A N/A N/A N/A N/A 20% N/A N/A 50% N/A 50% N/A 50% N/A N/A 63% N/A N/A 100% N/A
total ACMV SYSTEM percentage 32% 31% 49% 38% 82% 77% 90% 89% 84% 52% 93% 65% 100% 55%

sn Delivery delivery Status Balance material status


1 Exhaust louvers 100.00%
2 Fresh air louvers 100.00%
3 toilet fans 100.00%
4 Ducted twin fans 90.00% by Mar 15,2023
5 refrigerant pipes 100.00%
6 Split unit 100.00%
ELECTRICAL WORK PROGRESS 08.03.2023 27
Light Industrial Type Warehouse

Admin

Admin

Admin

Admin

Admin

Admin

Admin

Admin

Admin

Admin

Admin

Admin

Admin

Admin
W.H

W.H

W.H

W.H

W.H

W.H

W.H

W.H

W.H

W.H

W.H

W.H

W.H

W.H
Lighting
Building No B3-A1 B3-A2 B3-A3 B3-A4 B3-A5 B3-A6 B3-A7 B3-A8 B3-A9 B3-A10 B3-A11 B3-A12 B3-A13 B3-A14

1st Fix 85% 85% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100%

2nd Fix 80% 80% 95% 95% 100% 95% 100% 100% 100% 85% 100% 95% 100% 100%

3rd Fix
T& C
Small Power
Building No B3-A1 B3-A2 B3-A3 B3-A4 B3-A5 B3-A6 B3-A7 B3-A8 B3-A9 B3-A10 B3-A11 B3-A12 B3-A13 B3-A14
1st Fix 85% 85% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100%
2nd Fix 80% 80% 95% 95% 100% 95% 100% 100% 100% 85% 100% 95% 100% 100%
3rd Fix
DB installation 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 50%
T& C
Fire alarm
Building No B3-A1 B3-A2 B3-A3 B3-A4 B3-A5 B3-A6 B3-A7 B3-A8 B3-A9 B3-A10 B3-A11 B3-A12 B3-A13 B3-A14
1st Fix 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100%
2nd Fix 95% 95% 100% 100% 100% 100% 100% 100% 100% 90% 100% 100% 100% 100%
3rd Fix 90% 25% 90% 35% 45% 95% 45%
FACP Installation
T& C
ELECTRICAL WORK PROGRESS 08.03.2023
28
Data & Telephone
Building No B3-A1 B3-A2 B3-A3 B3-A4 B3-A5 B3-A6 B3-A7 B3-A8 B3-A9 B3-A10 B3-A11 B3-A12 B3-A13 B3-A14
1st Fix 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100%
2nd Fix 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100%

3rd Fix 50% 90% 15% 2% 15% 90% 15%

Roof trunking 60% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100%
Data rack
100% 30% 100% 90% 100% 100% 100%
Installation
FO cabling 75% 70% 85% 45% 40% 40% 40% 60% 40%
Data rack T & C

CCTV System
Building No B3-A1 B3-A2 B3-A3 B3-A4 B3-A5 B3-A6 B3-A7 B3-A8 B3-A9 B3-A10 B3-A11 B3-A12 B3-A13 B3-A14

Roof trunking 60% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100%

Cabling 100% 100% 100% 100% 95% 95% 80% 100% 100%

CCTV Installation
CCTV Installation
@Infra
T&C

Electrical containment DB and SMB installation , cable pulling from DB to SMB @ Electrical room
Building No B3-A1 B3-A2 B3-A3 B3-A4 B3-A5 B3-A6 B3-A7 B3-A8 B3-A9 B3-A10 B3-A11 B3-A12 B3-A13 B3-A14
Electrical
60% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100%
containment Roof
Cable pulling DB to
100% 100% 100% 100% 100% 100% 90% 100% 100%
SMB
Meter Cabinet
Installation
Lighting and Small
power
Earthing and
Lightening
ELECTRICAL WORK PROGRESS 08.03.2023 29
ELV containment , DATA rack, FO Cable pulling@ ELV / TELECOM ROOM
Building No B3-A1 B3-A2 B3-A3 B3-A4 B3-A5 B3-A6 B3-A7 B3-A8 B3-A9 B3-A10 B3-A11 B3-A12 B3-A13 B3-A14
ELV containment
60% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100%
Roof
Data Rack
100% 100% 70% 85% 70% 100% 85%
Installation
FO cable pulling 50% 50% 60% 50% 60% 60% 50% 85% 50%
for Data
CCTV Rack 100% 100% 70% 85% 70% 100% 85%
Installation
FO cable pulling 40% 30% 30% 30% 40% 40% 40% 40% 30%
for CCTV
ACS Panel 100%
Installation

10% 20% 20%


ACS cable Pulling
ACS Device
Installation

External Infra

Under ground Duct Cable Pulling / Testing

Electrical Infra LV 48% 42%

Electrical Infra MV 55% 48%


CCTV Infra power
44% 40%
cable
External Lighting 44% 42%
Tel Infra 50% 0%
Fire alarm Infra 50% 0%
Earthing and
Lighteninfg NA 0%
Protection
Irrigation 0% 0%
30
ELECTRICAL WORK AT ROOF - PROGRESS 08.03.023
31

PROCUREMENT
32
PROCUREMENT – LONG LEAD ITEMS 08.03.023

Expected Delivery New Expected %


Sl.No Name of the Material Status
Date Delev. Date Delivery

Electrical Items
1 Emergency exit lights 15 March 2023 30 March 2023
12th of Feb. 2023 to from 15 Mar 2023
2 Internal lights
28th of April 23 to 28 April 2023
3 External Electric lighting fixtures for light poles 05 February 2023 11 March 2023
4 light poles 30 January 2023 Delivered
5 MICC cable lugs 31 December 2022 Delivered
6 Feeder Pillar 16 February 2022 Delivered 07 March 2023
7 Access Control system 30 January 2023 15 March 2023 70.00%
8 Fiber Optic Cables (24F) for ELV system 29 December 2022 Delivered
9 Cable glands and Cable lugs 31 December 2022 Delivered
10 Fire alarm system 10 February 2023 Delivered 08 March 2023
11 CCTV system 15 February 2023 15 March 2023 80.00%
12 Wiring accessories 20 February 2023 15 March 2023 70.00%
13 Isolator 30 January 2023 Delivered 28 February 2023
7 Nos Delivered,
14 Tranformer 11 March 2023 30 April 2023 63.63%
remaning 4 no.
15 11 KV switchgear 30 December 2022 Delivered
16 11 KV cables 30 December 2022 Delivered
17 Fiber Optic Cables for 11 KV cables 30 December 2022 Delivered
18 Telephone/Data system 15 January 2023 Delivered
33
PROCUREMENT – LONG LEAD ITEMS 08.03.023

Expected Delivery New Expected %


Sl.No Name of the Material Status
Date Delev. Date Delivery

Electrical Items
BALANCE 14 PICES FOR
19 Active component system 01 May 2023 527 PICES ARRIVED
CCTV
90.00%
20 UPS System 15 March 2023 30 March 2023
21 Switch Boards(DB/SMDB/MCC) 30 January 2023 Delivered
7Nos Delivered,
22 LV Switchgear 15 February 2023 12 March 2023 63.63%
remaning 4 no.
8Nos Delivered,
23 Power Factor Correction Capacitor 15 February 2023 12 March 2023 72.72%
remaning 3 no.
Mechanical items
1 Drain Pan for Substation Split AC 15 February 2023 Local fabrication 30 April 2023
2 Flexible Duct Connector 15 February 2023 Delivered
3 Identification Labels for Mechanical Services 20 February 2023 Local fabrication 30 April 2023
4 Multi Media Filter for Potable Water 15 January 2023 Delivered
5 Breeching Inlet 20 January 2023 Delivered
6 Aluminum Cladding 15 March 2023 Delivered
7 Modulating Float Valve 01 February 2023 Delivered
8 Sprinklers 15 January 2023 Delivered
9 FM 200 System (cylinder delivery 1-March -2023) 01 March 2023 Partially delivered 15 April 2023
10 Fire Blanket and Extinguishers 15 March 2023 Ex-stock
11 Fire Hydrant 15 January 2023 10 March 2023
12 Ventilation Fan (EAF) 15 February 2023 10 March 2023 90.00%

13 Split Type Room Air-Conditioner 10 February 2023 Delivered


34
PROCUREMENT – LONG LEAD ITEMS 08.03.023

Expected Delivery New Expected %


Sl.No Name of the Material Status
Date Delev. Date Delivery

Mechanical items
14 CRAC UNIT 25 February 2023 15 March 2023
15 Sanitary Wares And Accessories 31 January 2023 Delivered
16 GRP Water Storage Tank 15 February 2023 Delivered 28 February 2023
5 set Delivered,
17 Potable Water Pumps 05 February 2023 10 March 2023 71.43%
remaning 2 set
18 Transfer Pumps 10 March 2023 17 March 2023
19 Orion neutralization tanks 15 February 2023 Delivered 02 March 2023
20 Fire Fighting Valves (Pump room) 01 March 2023 23 March 2023 95.00%
2 on 15 April 023
21 Fire Fighting Pumps 01 May 2023
& 2 on 21 April 23
22 Float Valve & Strainer 15 January 2023 Delivered
23 Fire water tanks(Steel) 16 January 2023 Delivered
24 Pressure Reducing Valve Assy 01 March 2023 23 March 2023
Other Equipment (Air Release Valve with Ball Valve, Oblique Landing
25 15 January 2023 Delivered
Valve)
26 Alarm Check Valve Assy 16 January 2023 Delivered
27 Exhaust & Fresh air louvers 15 February 2023 Delivered
Civil
1 Polyurea 4th of March.23 7 Blocks Delivered 18 March 2023 50.00%
Time Lapse Camera –Progress Photographs Update
35
CAMERA BESIDE OOREDOO TOWER CAMERA TOWARD HIGHWAY SIDE
Time Lapse Camera –Progress Photographs Update 36
CAMERA TOWARD PHASE ONE CAMERA BESIDE AAE SITE OFFICES
37

BLOCKS PROGRESS
(ARCH)
BUILDING B3 - A13 & A14: Progress Photographs 8

08.03.2023 08.03.2023

A14 – Internal Finishes Work in Progress B3 -A14 – Ceiling Works on progress

08.03.2023 08.03.2023

B3 -A13 – Iexternal Finishing on progress B3 -A13 – Internal Finishes on Progress


BUILDING B3 - A11 & A12, ROAD 20: Progress Photographs 39

08.03.2023
08.03.2023

B3 -A12 – Door Shutter on Progress B3 -A12 – Alumenium Doors on progress

08.03.2023 08.03.2023

B3 -A11 –External Finishing on Progress B3 -A11 –Road Finishing in Progress


BUILDING B3 – A9 & A10 : Progress Photographs
40

08.03.2023
08.03.2023

B3 –A10 – Internal Finishing in Progress


B3 –A10 –Finishing work on Progress

08.03.2023
08.03.2023

B3 –A09- External Finishing on Progress B3 –A09 –External Finishing on Progress


BUILDING B3 – A7 & A8 : Progress Photographs 41

08.03.2023 08.03.2023

B3 –A8 –Internal Finishing on Progress


B3 –A8 Internal Finishing on Progress

08.03.2023 08.03.2023

B3 –A7 – External Entrances on Progress B3 –A7 – Roller Shutter Completed


BUILDING B3 – A5 & A6 : Progress Photographs 42

08.03.2023 08.03.2023

B3 –A6 – External Work on Progress B3 –A6 – Ceiling & Painting on Progress

08.03.2023 08.03.2023

B3 –A5 – External Entrance work on progress B3 –A5 – Rolling Shutter on Progress


BUILDING B3 – A3 & A4 : Progress Photographs
43

08.03.2023 08.03.2023

B3 –A4 –External Finishes on progress B3.A4. Roller Shutter on Progress

08.03.2023 08.03.2023

B3 –A3 – Internal Finshing on Progress B3 –A3 – Roller Shutter on progress


BUILDING B3 - A1 & A2 : Progress Photographs 44

08.03.2023
08.03.2023

B3 –A2 – Roller Shutter Work on Progress B3 –A2 –Internal Painting on progress

08.03.2023 08.03.2023

B3 –A1 – Roller Shutter on progress B3 –A1 –External enterance on progress


45

BLOCKS PROGRESS
(MEP)
BUILDING B3 – A09 & 11 Electrical room, IDF & Telecom : Progress Photographs
46

SMDB Installation & termination on Progress SMDB installation & termination on progress

Glanding & termination of power cable Rack installation & termination on Progress Fire alarm panel installation on Progress
Substation B9 – SS 15 & 17 Progress Photographs 47

08.03.2023
08.03.2023

LV panel installation on Progress Substation Transformer on Progress

08.03.2023 08.03.2023

Substation Transformer on Progress LV panel installation on Progress


Electrical system Progress Photographs
48

08.03.2023 08.03.2023

Cable tray cover on Progress DB & Trunking installation on progress

08.03.2023 23.02.2023
08.03.2023

CCTV Rack installation in admin on Progress Earthing rod & wire installation on Progress fire alarm Remote indicator in Progress (admin)
Electrical system Progress Photographs 49

08.03.2023

Small power wire pulling in roof on Progress ELV Trunking in admin on Progress

08.03.2023 08.03.2023

DB installation & power cable on progress Fire Alarm Siren Red Sound & White Flash Light Road crossing duct on Progress
Firefighting Progress Photographs 50

08.03.2023 08.03.2023 08.03.2023

Firefighting pipes on roof on Progress FM200 Conduit in Electrical & Firefighting riser valves installation on Progress
Telecom Room on Progress

08.03.2023 08.03.2023
08.03.2023

FM200 on progress Firefighting riser valves installation on Progress fire hose cabinet installation on Progress
Water supply, Drainage & Storm water Progress Photographs 51

08.03.2023
08.03.2023 08.03.2023

Water meter cabinet on progress Water supply system inside the building on progress Sanitary wares & Accessories on progress

08.03.2023
08.03.2023 08.03.2023

Area Drain & Clean out on progress Storm water riser on progress Water Hammer Arrestor on progress
Air Conditioning & Mechanical Ventilation system Progress Photographs 52

08.03.2023 08.03.2023 08.03.2023

AC Split unit installation on progress (Out dooor) Toilet Exhaust fan on progress
Louvers on progress

08.03.2023
08.03.2023
08.03.2023

Warehouse Exhaust fan / Duct on Progress


A/c refrigerant pipe on progress AC Split unit installation on progress (in door)
53

HOLDING TANKS
HOLDING TANKS 54

H. TANK-4 - Tank Access Shafts


Completed & Waterproofing on Progress
HOLDING TANKS 55

H. TANK-5 - Tank Access Shafts Completed & Waterproofing on progress


56

EXTERNAL WORKS
ROAD 29: Progress of works 57

Infrastructure Network Progress Sewer Potable Water Fire Fight Storm Water ELV &
Street Light LV IRR
Road 29 Network Network Network Network TELECOM

Sand Bedding Work 25% 60 % 95% 25% 0 0 0 90%


Pipe / Cable Laying 25% 60% 95% 0 0 90%
Backfill 10% 60% 95% 0 0 85%

IT 33 –first part Installation Backfilling &Excavation of main sewer on progress


Layers on progress Of STREET LIGHT On Progress
ROAD 20 : Progress of works 58
Infrastructure Sewer Potable Water Network Fire Fight Network Storm Water Network
Network Progress Network
Road 20
Pipe Laying 100% 100% 97% 100%
Manhole Installation 98% 98% - 98%

Sewer MH Benching in progress ROAD HUMP & INTERLOCK LAYER in


Acid & Sewer MH Cover in progress
progress
ROAD 19: Progress of works 59
Infrastructure Sewer Potable Water Network Fire Fight Network Storm Water Network
Network Progress Network
Road 19
Sand bedding Work 100% 98% 97% 100%
Pipe Laying 100% 98% 97% 100%

INTERLOCK LAYER in progress ROAD PREPARATION


ROAD 18: Progress of works 60
Infrastructure Sewer Potable Water Network Fire Fight Network Storm Water Network
Network Progress Network
Road 18
Pipe Laying 100% 96% 97% 98%
Manhole Installation 97% - - 98%

CURBSTONE & ROAD PREPARATION


ROAD 17: Progress of works 61
Infrastructure Sewer Potable Water Network Fire Fight Network Storm Water Network
Network Progress Network
Road 17
Pipe Laying 100% 97% 97% 100%
Manhole Installation 98% 98%

COMPACTION, GEOTEXTILE, SAND & INTERLOCK LAYER


INTERLOCK LAYER on progress
In The Car Parking Area
ROADS 16: Progress of works 62
Infrastructure Sewer Network Potable Water Network Fire Fight Network Storm Water Network
Network Progress
Road 16
Sand bedding 100% 97% 95% 97%
Pipe Laying 100% 97% 95% 97%

SEWER IC -CONNECTION DONE, CURBSTONE & ROAD PREPARATION IN PROGRESS


ROADS 15 : Progress of works 63
Infrastructure Sewer Network Potable Water Network Fire Fight Network Storm Water Network
Network Progress
Road 15
Sand bedding 50% 80% 90% 80
Pipe Laying 50% 80% 90% 80

INSPECTION CHAMBER INSULATION CONNECTIONS IN PROGRESS


ROAD 14: Progress of works 64
Infrastructure Network Progress Road Potable Water Fire Fight Storm Water
Sewer Network ELV & TELECOM MV IRR
14 Network Network Network
Sand Bedding Work 60% 70% NA 85% 90% 95% 95%
Pipe / Cable Laying 60% 70% NA 80% 80% 90% 95%
Backfill 60% 60% NA 80% 60% 65% 85%

GULLY & CONNECTION TO PIPE PW, IRR , MV, LV & ELV Backfill IC MH BLINDING DONE, PW Hose
STORM MH IN PROGRESS on progress Connection In Progress
ROAD 01: Progress of works 65
Infrastructure Network Potable Water Storm Water
Sewer Network Fire Fight Network Street Light ELV & TELECOM LV MV IRR
Progress Road 01 Network Network

Pipe / Cable Laying 70% 50% 50% 90% 0 5% 50%

Sand Bedding Work 70% 50% 50% 95% 0 10% 50% 50% 50%

Manhole Installation 70% 40% 10% 90% 70% 80% - -


Backfill 70% 0 0 60%

Road backfill layers STORM WATER MH DONE ,STREET LIHGT JRC MAIN SEWER LINE
in progress MH On Progress CONNECTION TO Ti-in
ROAD 02: Progress of works 66
Potable
Infrastructure Network Progress Sewer Fire Fight Storm Water ELV &
Water Street Light LV MV IRR
Road 02 Network Network Network TELECOM
Network
Sand Bedding Work 75% 90% 75% 90% 50% 90% 90% 90% 85%
Pipe / Cable Laying 75% 90% 75% 90% 50% 20% 85% 80% 85%
Backfill 75% 90% 75% 80% 40% 60% 55% 65% 85%

Road Gully's
Installation & CURBSTON & ROAD LAYERS MV, TELCOM, POWER &STREET LIGHT CAPEL LAYING in progress
connection In In Progress CURBSTONE
Progress
ROAD 24 : Progress of works 67
Infrastructure Network Progress Potable Water Fire Fight LV Network MV Network
Road 24 Network Network

Sand bedding 60% 80% 30% 0


Pipe Laying 50% 70% 0 0

R24- EXCAVATION & INSTALLATION OF POTABLE FIRE WATER IBACKFILL LAYERS IN


WATER IN PROGRESS LV Capel Bedding LAYERS IN PROGRESS
PROGRESS
68

SERVICE YARD
SERVICE YARD 69
(Plinths)

Irrigation tanks

Domestic tanks 1 & 2


SERVICE YARD 70

Fire Steel Tanks


SERVICE YARD- PUMP ROOM 71
72
CAFETERIA
73
EXTERNAL GRP TANKS
74

THANK YOU