Department: Engineering (Planning)

Project: Proposed Alturas Ricemill- Loading/Utility Area


Location: Lumangog, Ubay, Bohol
Client: Alturas Group of Companies
Date: 19-Nov-20

EXECUTIVE SUMMARY/REV 1.0

Contract Milestone
Planned % Remarks
Planned Start Date 24-Mar-20 Elapsed Days: 240
Planned Finish Date 24-Mar-21 Remaining Days: 125
Revised Completion Date Calendar Days: 365
Scope % wt Planned % Planned Value Actual % Actual Value

PRELIMINARIES 9.14% 43.00% 3.93% 49.84% 4.56%

EARTHWORKS (Excavation, backfilling) 5.24% 38.20% 2.00% 60.16% 3.15%

COLUMN FOOTINGS 5.30% 88.15% 4.67% 75.00% 3.97%

COLUMN PEDESTAL 12.48% 87.49% 10.92% 68.00% 8.49%

WALL FOOTING AND CHB WALLS 28.68% 10.39% 2.98% 26.45% 7.59%

STRUCTURAL WORKS & ARCHITECTURAL WORKS 17.02% 49.73% 8.47% 52.55% 8.94%

SLAB ON GRADE 22.13% 0.36% 0.08% 55.48% 12.28%

Total 100.00% 33.05% 48.98%

Issues and Reminders Variance: 15.93%

1. Slippage at 2nd week of December

Prepared by: Checked by:

Rogemie Cherrehan Tano Neil E. Sabal


MCBI - Planner MCBI - Project in Charge

Approved by: Noted by:

Urbano Curit Mario Tancinco


MCBI - Project Manager MCBI - Operations Manager