Monthly Report No. 18

3.4 Summary Of Work Progress

No. Work Description Progress (%)

1 Demolition & Site Clearance 94.32%

2 Earthwork 51.34%

3 Piling Works 56.70%

4 Bridge Work 0%

5 Crossover 29.64%

6 Road & Paving 0%

7 Road Furniture 0%

8 Drainage Works 22.77%

9 Mechanical & Electrical Work 0%

SEPTEMBER 2023
PROPOSED Kpg. Kebuaw/ Teluk Daloh/ Bungan Kecil Road, Mukah Division
Monthly Report No. 19

3.4 Summary Of Work Progress

No. Work Description Progress (%)

1 Demolition & Site Clearance 97.00%

2 Earthwork 58.13%

3 Piling Works 71.36%

4 Bridge Work 0%

5 Crossover 34.22%

6 Road & Paving 0%

7 Road Furniture 0%

8 Drainage Works 22.77%

9 Mechanical & Electrical Work 0%

OCTOBER 2023