SCHEDULE OF GROUND HACKING WORK FOR POWER SUPPLY CABLE AT RAJANG PORT AUTHORITY

Date
Work Description 10/8/2021 11/8/2021 12/8/2021 13/8/2021 14/8/2021

Setting out and preparation of barrier and safety signage(Phase 1)


Hacking work for the existing road at the phase 1 area
Lay the HDPE pipe sleeve for Underground SESCO Cable

Fill bedding material to surround cable pipe(HDPE). Temporary cover and compact
the excavated road with soil and gravel.

Remove the barrier from phase 1 area and setting out for phase 2 area. The
transition will start once all the excavated road are completely covered and
compacted.
Hacking work for the existing road at the phase 2 area
Continue lay the HDPE pipe sleeve for Underground SESCO Cable
Fill bedding material to surround cable pipe(HDPE). Temporary cover and compact
the excavated road with soil and gravel.

Constrcution Phase 1

Constrcution Phase 2