1. Site Plan
2. Optimized Construction Programme
A. Site Logistic Plan
B. Project Organization Plan
C. Construction Execution Plan
D. Coordination
E. QA/QC Plan
F. HSE Plan
3. Prevention of Civil Complaints
SITE PLAN
1
SITE PLAN
A.OMNI HOSPITALS ALAM SUTRA
B.GRAND SERPONG KITCHEN
C.DEPO BANGUNAN
Sungai Cisadane D.PT. TUGU PAKULONAN
E.BUNDARAN ALAM SUTERA
CLIENT :
PT. HONG KONG KINGLAND
C
PROJECT LOCATION:
JL. RAYA SERPONG KM.8 PAKULONAN B D
SERPONG UTARA KOTA TANGERANG
STORIES : E
A N
2 FLOORS BASEMENT
3 FLOORS PODIUM
A
B
SITE EXISTING
CONDITION
SITE LOGISTIC PLAN
2B
CONCRETE SUPPLY
Main Batching Plant for Concrete Supply
Holcim
Serpong
Backup Batching Plant for Concrete Supply
Semen Indo Supplier Location Distance Arrival time Capacity
Serpong
Bojong
Holcim ±10,5 km 20-25 minutes TBA
Nangka
2B
Section 2B
PROJECT ORGANIZATION PLAN
1. Site Organization Structure
SITE ORGANIZATION PLAN
2B
SITE ORGANIZATION STRUCTURE
CONSTRUCTION EXECUTION PLAN
2B
NUMBER DUTY
PERSON IN CHARGE (STAFF) BREAKDOWNS OF PERSON / MONTH
NO OCCUPATION OF PERIODE 2021 2022 TOTAL
PERSON (mth) 1 2 3 4 5 6 7 8 9 10 11 (mth)
Construction Asbuild, maintenance
I STAFF
1 Project Manager 1 10 1 1 1 1 1 1 1 1 1 1 10
2 Site Manager STR 1 10 1 1 1 1 1 1 1 1 1 1 10
3 Site Manager ARS - - -
4 Chief Supervisor 1 10 1 1 1 1 1 1 1 1 1 1 10
5 Supervisor STR 4 10 4 4 4 4 4 4 4 4 4 4 40
6 Supervisor ARS - -
7 Receptionist - - -
8 GA / HRD 1 10 1 1 1 1 1 1 1 1 1 1 10
9 GA Staff - -
10 Engineering Manager 1 10 1 1 1 1 1 1 1 1 1 1 10
11 Site Engineer STR 1 10 1 1 1 1 1 1 1 1 1 1 10
12 Site Engineer ARS - - -
13 Chief Drafter - - -
14 Drafter struktur 2 10 1 1 2 2 2 2 2 2 2 2 18
15 Drafter arsitektur - -
16 Quality Control Manager 1 10 1 1 1 1 1 1 1 1 1 1 10
17 Quality Control 2 10 2 2 2 2 2 2 2 2 2 2 20
14 QS Senior 1 10 1 1 1 1 1 1 1 1 1 1 10
15 Quantity Surveyor 2 10 1 1 1 2 2 2 2 2 2 2 17
16 BBS 1 10 1 1 1 1 1 1 1 1 1 1 10
21 Chief Surveyor 1 10 1 1 1 1 1 1 1 1 1 1 10
22 Surveyor 2 10 2 2 2 2 2 2 2 2 2 2 20
23 Ass. Surveyor 4 10 4 4 4 4 4 4 4 4 4 4 40
24 Chief Mechanic 1 10 1 1 1 1 1 1 1 1 1 1 10
25 Mechanic 3 10 3 3 3 3 3 3 3 3 3 3 30
26 Ass. Mechanic - -
27 Chief Storage 1 10 1 1 1 1 1 1 1 1 1 1 10
28 Storage 3 10 3 3 3 3 3 3 3 3 3 3 30
29 Chasier 1 10 1 1 1 1 1 1 1 1 1 1 10
30 Cost Control - -
31 Scheduler 1 10 1 1 1 1 1 1 1 1 1 1 10
32 Safety Manager 1 10 1 1 1 1 1 1 1 1 1 1 10
33 Safety Supervisor 2 10 1 1 1 2 2 2 2 2 2 2 17
34 Safety Helper - -
35 Document control / Adm 1 10 1 1 1 1 1 1 1 1 1 1 10
Sub. Total II 9 40 9 9 9 9 9 9 9 9 9 9
III OPERATOR
1 Tower Crane 1 10 1 1 1 1 1 1 1 1 1 1 88
2 Genset
3 Concrete Pump 2 10 2 2 2 2 2 2 2 2 2 2 13
4 Passanger hoist 2 10 2 2 2 2 2 2 2 2 2 2 13
Agustus 2020
CONSTRUCTION EXECUTION PLAN
2
SITE TEMPORARY FACILITIES
SITE MANAGEMENT PLAN
CONSTRUCTION EXECUTION PLAN
2
SITE MANAGEMENT PLAN
WATER SUPPLY PLAN
Installation criteria Quantity
• Temporary water supply provided by pressurization pump
• Being operated by natural head pumping after installation of
temporary water supply at upper floor. Water • 1 x 4m3 (Basement 2 ) 2
• MEP Water tank shall be temporarily used during construction. Tank • 1 x 2m3 (4 th Floor)
Water
supply
Water Supply
Legend
Typikal Floor
Water Out- • 1EA floor 3
Water tank let
4th Floor
Septic
tank • septic tank of FRP for 100 persons(5m3) 1
Temporary
Closet • Women 2EA, Men 3EA 1
Office
Basement 2
City Water/DW
CONSTRUCTION EXECUTION PLAN
3
HEAVY EQUIPMENT PLAN
TOWER CRANE, HOIST, PLACING BOOM PLAN
STOK DAN
TOWER-2 FRITZ FUTURE DEVELOPMENT
PABRIKASI
JL.
AYR
AS
ACCESS TEMPORARY
PODIUM-RETAIL
ER
PO
NG
FUTURE DEVELOPMENT
FUTURE DEVELOPMENT
TOWER-3 VENETIAN
GALLERY M
ARKETING
Legend
Tower Crane
Material & Pasenger Hoist
CONSTRUCTION EXECUTION PLAN
3
HEAVY EQUIPMENT PLAN
ELEVATION TC #1 – JIB 65 M
TO
WE
R
PODIU
M
1
KEYPLAN
POTONGAN - 1
CONSTRUCTION EXECUTION PLAN
3
HEAVY
MAIN EQUIPMENT SPECIFICATION & SCHEDULE
EQUIPMENT PLAN
( Tower A8/A9) Type & Capacity Owned or Rent Quantity Image
Capacity : 12 Ton
#1 Boom : 65M Owned 1
Tip Load : 3,0 Ton
Tower Crane
Month
Duration
Description (Month) 1 2 3 4 5 6 7 8
8M
Construction Period 8
8M
Structural Level 5 - 33 8
Work
8M
TC #1 8
CONSTRUCTION EXECUTION PLAN
3
LIST EQUIPMENT
TAHUN STATUS
NO NAMA ALAT KAPASITAS JUMLAH PEMBUATAN MILIK/SEWA CATATAN
ZONE 2 ZONE 1
1 Set 1 Set
Note:
Formwork system by aluko table
ZONE 3
1 Set
Days 4
Days 2 -3
Days 5-8
Pouring day 1
CONSTRUCTION EXECUTION PLAN
Note:
Concrete mold for column and shearwall are using
Aluma Beam, Steel waler and plywood double phenolic
Note:
Concrete mold for column and shearwall are using
Aluko System
TC #1 JIB 65 M
TC #1 JIB 65 M
EL +22,300
A 7F
EL +15,900 A
6F
5F
5F
4F
3F 4F
2F 3F
2F
GF
B1 GF
KEYPLAN KEYPLAN B1
B2
B2
POTONGAN - A POTONGAN - A
CONSTRUCTION EXECUTION PLAN
6
PROGRESS SEQUENCE
(M+9) (M+14)
TC #1 JIB 65 M
EL +63,900
20F
19F
18F
17F
TC #1 JIB 65 M
16F
15F
EL +41,500 14F
13F 13F
12F 12F
11F 11F
Finishing work
10F 10F
9F 9F
8F 8F
A 7F A 7F
6F 6F
5F 5F
4F 4F
3F 3F
2F 2F
GF GF
KEYPLAN B1 KEYPLAN B1
B2 B2
POTONGAN - A POTONGAN - A
CONSTRUCTION EXECUTION PLAN
6
PROGRESS SEQUENCE
(M+28) (M+36)
TC #2– JIB 65 M EL +105.500
TC #2– JIB 65 M ROOF
32F
31F
30F
EL +83.100 29F
26F 28F
25F 27F
24F 26F
23F 20F
22F 19F
20F 18F
17F 17F
16F Finishing work 16F
Finishing work
15F 15F
14F 14F
13F 13F
12F 12F
11F 11F
10F 10F
9F 9F
8F 8F
A 7F A 7F
6F 6F
5F 5F
4F 4F
3F 3F
2F 2F
GF GF
KEYPLAN B1 KEYPLAN B1
B2 B2
POTONGAN - A POTONGAN - A
2D
Section 2D
COORDINATION
COORDINATION
2D
COORDINATION PROCEDURE
ACMV
P+S
Shop Drawing Shop Drawing Shop Drawing
Submission Management Approval
Electrical
Lift/Escalator
Coordination •
•
•
Submission
Feedback
Coordination Measures
RFI (Request For Information) Technical Meeting & Sub Contractor/NSC Coordination Meeting
• Creating log for RFI registration • To issue agenda 2 days prior to technical meeting
• Preparing RFI and sending out to relevant consultants • Updating consultant on RFI, shop drawings and submission
• Receiving RFI response from consultants and update RFI status
log • Discussion of technical issues amongst consultants,
• Discussing Inappropriate RFI response at technical meeting NSC/SC , Totalindo
COORDINATION
2D
COORDINATION PROCEDURE
NSC Coordination Management
NSC
COORDINATION
MANAGEMENT
Consultant
Inspection +
Defining Step by Step
& Main Contractor
Key Point Inspection +
Test Plan Sub Contractor
Sub Contractors
Method
Shop Drawing
Method of Briefing Trade Set-up
& Execution of
Construction & Demonstration Quality Finish
Material Work
(Trade) Workers (Mock Up) Standard
Submission
Training
QA/ QC PLAN
2E
DEFECT & HAND OVER PROCEDURE
Handover Procedure
Defect Clear Defect List Defect List
By QC Team
Yes
Completion Defect Clear?
of NCR No
Check by QC Team
No
Yes
Final Issue NCR
to Sub-con
Request for
Final Inspection
Yes
Defect Clear? No
Check by
Engineer
No
Yes
Defect Clear by
Main Contractor
Final Inspection
Issue Penalty to Sub-con
2F
Section 2F
HSE PLAN
1. Certificates
2. HSE Protocols Plan During Covid-19 (To Minimize
of spread inspection)
3. HSE Activities
4. Safety Facilities
HSE PLAN
2G
CERTIFICATES
• HSE Policy
• Compliance ISO,OHSAS,SMK3
• Responsibilities of Staff and Employees to Safety
• Environment Management Policy
• Competency of Human Resources
• Corporate Social Responsibilities
HSE PROTOCOLS PLAN DURING COVID-19 2G
(TO MINIMEMIZE SPREAD OF INSPECTION)
THE MAIN UNDERLYING APPROACHES ARE :
Reduce acces to site
Adapt work plan and activities to reduce close contact
Prioritize health and safety of staff, workers and their surrounding communities
Increase awareness of the workforce
Increase overall level of hygiene of the site
ACCESS TO SITE
Only essential visitors (Owner, Contractor, MK, Workers and guest with appointment ) should
be allowed on site
Entry and exit gates should be clearly marked and guarded;
Body temperature should be measured for all persons entering the site
Allow enough space for people to queuing in a safe manner at the entrance of the site while
they wash their hands and get screened
Ensure there are sufficient hand washing stations at the entrance and that they have water
and soap, as well as clearly display signs requesting persons entering to wash their hands
All persons should wash or clean their hands before entering and leaving the site
HSE PROTOCOLS PLAN DURING COVID-19
2G HSE PLAN
DURING CONSTRUCTION:
Workers should maintain physical distance
workers should wear masks
Meetings on site should be avoided at all times. Instruction to workers should be given in open
spaces and maintaining physical distance
If construction activities happen in an enclosed space, the site should be ventilated as much as
possible, for example leaving doors and windows open during the working day Increase overall
level of hygiene of the site
Due to potential sudden access restrictions, all materials and equipment should be carefully and
safely stored before leaving the site at the end of every day
When receiving and unloading goods and construction materials, workers should keep distance
from the drivers at all times. When possible, drivers should remain in their vehicles. If drivers must
unload the goods for safety reasons, they should do so without the help of the workers and they
should wash or clean their hands before and after. Any contact between deliverers and receivers
should be avoided (including delivery papers and pens for signature, etc.). It is recommend that
everyone needing to sign paperwork have their own pen or wash their hands after.
If possible, construction crews should be segregated and tasks allocated so they do not overlap.
It is suggested to establish crew shifts to be also applied for break, lunch and pray time
HSE PROTOCOLS PLAN DURING COVID-19
2G HSE PLAN
PLANNING PHASE :
Plan construction phases avoiding large group of workers and unnecessary overlap of crews
Basic Personal Protective Equipment (PPE) related to construction safety such as gloved and glasses
should be provided to workers depending on the tasks they are assigned to. In addition, each worker
should be provided with two or more reusable masks (not surgical/medical graded masks)
Additional hand washing stations including provision of clean water and soap, together with cleaning
and disinfection products may be required for construction sites opened prior to the outbreak. For new
construction site, plan and budget provision of these items
Preferably, every worker should be provided with a basic set of tools needed for the tasks they are
assigned to. Using of the same tool by multiple workers should be avoided. If tools are shared or stored
for later use by another person, they need to be disinfected/cleaned
Supervision should be strengthened including COVID-19 prevention principles, and supervisors oriented
on their new responsibilities
HSE PROTOCOLS PLAN DURING COVID-19
2G HSE PLAN
Director
Project Manager
HSE Manual
HSE Team
HSE Facilities
Training
Feedback
Feedback
Planning Education Auditing Regular Inspection
Check
HSE Management
on Site Safe Workplace
HSE PLAN
2G
HSE PLAN
SAFETY PROGRAM
TBM ALL EVERY DAY
MORNING EMPLOYEE
RESPONSIBILITIES OF EMPLOYEE
Implementing safe work Practices
Comply to Procedure and Regulation including PPE mandatory
Active participation during safety talk and other HSE meeting
Report all incidents and any identified hazard including safety deviation
Stop any unsafe act and condition
Maintain workplace cleanliness
Ensure all tools and equipment are in good condition
HSE PLAN
2G
HSE PLAN
HAZARD &RISK IN
Electrict shock
BUILDING
CONSTRUCTION
ACTIVITIES
Crushed by materials
• Weekly Meeting(Sub-Contractors)
• Weekly Meeting(Main Contractor)
Weekly
Safety Deck
HSE PLAN
2G
SAFETY FACILITIES
Safety Rail
HSE PLAN
2G
SAFETY FACILITIES
01 02 03
High Performance Optimized Construction Prevention of
Period Civil Complaints
Etc.
Neighborhood, Passenger Management & Feed Back
Feed Back
Project Location
Kingland Avenue
LEGEND
LOCATION PROJECT
OPEN SPACE
BUSSINES AREA
HOUSING
Thank
You