Professional Documents
Culture Documents
t= 0.15
EVALUATED BY:
LIA M. MAYLON
Engineer A
QUANTITY COMPUTATION SHEET
VARIATION ORDER NO. 1
ILISAN SIP
ALICIA, ZAMBOANGA SIBUGAY
CONTRACT NO. NIAREG9-01222019-599
NAME OF CONTRACTOR: LONG ISLAND BUILDRES & CONSTRUCTION
NAME OF STRUCTURE/CANAL :
STATION :
PAY ITEM : 3000 psi Plain Concrete
t= 0.15
EVALUATED BY:
LIA M. MAYLON
Engineer A
INSPECTION AND INVESTIGATION SUMMARY
VARIATION ORDER NO.1
Contract No. : NIAREG9-03102020-676 LINEPROGRAMS-EXTENSION Contract Description: CONSTRUCTION OF CANALIZATION & CANAL STRUCTURES
Contractor : LAKEWOOD CONSTRUCTION COMPANY
Attachments:
Written Notice of the Contractor Variation Order No. 01,Plan & Profile if change in Stationing & Grade
Justifications Geotagged Pictures
Variation Order No. 01 N/A Variation Order No. 01, PERT/CPM Network Diagram
Variation Order No. 01, Masterlist of Work Items N/A Variation Order No. 01, Detailed Computation of Contract Time
Computation of Quantities N/A Logbook
Detailed Estimate of Unit Cost Joint Resolution of Salinding Barangay Officials
Plans and or Revised Plans
Variation Order No. 01 General Layout, if change in location
JUSTIFICATIONS
Proposed Variation Order No. 01
NIAREG9-03102020-676 LINEPROGRAMS-EXTENSION
CONCRETE
Class A Concrete (3000 psi) PLAIN Class A Concrete (3000 psi) PLAIN BASED ON ACTUAL FIELD
CONCRETE CONCRETE DECREASED OF QUANTITY CONDITION, APPROVED CROSS-
(4.03 cu.m) (3.42 cu.m) SECTION AND RECOMPUTATION
OF CONCRETE QUANTITIES
BASED ON ACTUAL FIELD
RSB (Reinforcing Steel Bars) CONDITION, APPROVED PLAN
RSB (Reinforcing Steel Bars)
(778.16 DECREASED OF QUANTITY AND CROSS-SECTION AND
(906.83 kgs) RECOMPUTATION OF
kgs)
REINFORCING BAR QUANTITIES
III CANAL STRUCTURES
3 CANAL STRUCTURES
Prop. Combination Cut & Cover and T.O.( LS) Main Canal 2 + 774 2 + 844 70.00 36.27 0.19 48.20 217.43 218.28 2.63 2.63
Prop. Check & Turn Out Ls Main Canal 3 + 104 0.37 0.40 0.48
Prop. Drainage Crossing Main Canal 3 + 144 - 3.00 2.98 Err:509
Prop. Check & Turn Out Ls Main Canal 3 + 164 0.65 2.14 1.26
Prop. Overchute Main Canal 3 + 204 1.44 3.52 2.08
Prop. Drainage Crossing Main Canal 3 + 324 #REF! 2.00 #REF! #REF!
Prop. Elev. Flume Main Canal 3 + 464 3 + 580 116.00 36.08 18.98 69.36 21.42
Sub - total = 186.00 72.35 #REF! 5.00 67.18 286.79 239.70 #REF! Err:509 2.63 2.63
916.00 1.00 153.06 72.35 #REF! 44.02 729.68 5.00 67.18
TOTAL 286.79 239.70 #REF! Err:509 2.63 2.63
MARIVIC B. ZAMORANOS DEXTER W. TSANG JADE J. BAGTASOS MARIA GERTRUDES P. GANIA GIRLIE M. DETALLA
Engineer B Contractor Senior Engineer A Supervising Engineer A Acting Division Manager
QUANTITY COMPUTATION SHEET
ILISAN SIP
Alicia, Zamboanga Sibugay
CONTRACT NO. NIAREG9-01222019-599
CONTRACTOR : LONG ISLAND BUILDERS AND CONSTRUCTION
NAME OF STRUCTURE/CANAL : ELEVATED FLUME
STATION : 3 + 464 3 + 580
PAY ITEM : 3000 psi Reinforced Concrete
AREAS
A. 0.14 x 0.45 0.06
, 0.14 0.14 B. 0.14 x 0.45 0.06
C. 0.12 x 0.63 0.08
0.45 0.20
0.45 A B
VOLUME= 0.20 x 113.70
, 0.12 C = 22.74
0.35
L=113.70 m. 22.74 cu.m.
FLUME SEAT
0.83 Area = 0.83 x 0.40
0.63 = 0.33
EVALUATED BY:
LIA M. MAYLON
Engineer A
QUANTITY COMPUTATION SHEET
ILISAN SIP
Alicia, Zamboanga Sibugay
CONTRACT NO. NIAREG9-01222019-599
CONTRACTOR : LONG ISLAND BUILDERS AND CONSTRUCTION
NAME OF STRUCTURE/CANAL : ELEVATED FLUME
STATION : 3 + 464 3 + 580
PAY ITEM : 3000 psi Reinforced Concrete
EVALUATED BY:
LIA M. MAYLON
Engineer A
QUANTITY COMPUTATION SHEET
ILISAN SIP
Alicia, Zamboanga Sibugay
CONTRACT NO. NIAREG9-01222019-599
CONTRACTOR : LONG ISLAND BUILDERS AND CONSTRUCTION
NAME OF STRUCTURE/CANAL : ELEVATED FLUME
STATION : 3 + 464 3 + 580
PAY ITEM : 3000 psi Reinforced Concrete
SKETCH COMPUTATION QTY. UNIT
TURN OUT
COW Area = Area whole - Area shaded
1.05
0.25 AREA= 1.05 x 0.65
= 0.68
0.25
0.40 Area sq. 0.25 x 0.25
0.65 = 0.06
Area tri. 0.50 0.25 0.25 2.00
0.25 = 0.06
Area = Area whole - (Area sq. + Area tri.)
, 0.25 Total Area= 0.68 - 0.13
= 0.56
Vol.= 0.56 x 0.13
t = 0.13 = 0.07 x 4.00 0.29 cu.m.
FILLET V = Area x length
0.15 Area= 0.50 0.15 0.15
, 0.15 = 0.01
Vol.= 0.01 0.51 4.00
L=0.51 m. 0.02 cu.m.
FLOORING
0.55 V = length x width x thickness
Area= 0.55 0.51 0.13 4.00
0.51 = 0.15
t = 0.13 0.15 cu.m.
SIDING 1 : SECTION E-E
0.30 VOL = length x width x thickness
Vol = 0.30 0.4 0.13 4.00
0.40 = 0.06
0.06 cu.m.
SIDING 1 : SECTION G-G
0.30 VOL = length x width x thickness
Vol = 0.30 0.41 0.13 4.00
0.41 = 0.06
0.06 cu.m.
SIDING 2: SECTION E-E
VOL=1/2 x (X1 + X2) x Length(thickness)
0.40
0.25 Vol = 0.5 0.65 0.25 0.13
= 0.01
0.25
TOTAL VOL.= 0.01 x 4.00 0.04 cu.m.
SIDING 2: SECTION G-G
VOL=1/2 x (X1 + X2) x Length(thickness)
0.41
0.25 Vol = 0.5 0.66 0.25 0.13
= 0.01
0.25
t = 0.13 TOTAL VOL.= 0.01 x 4.00 0.11 cu.m.
EVALUATED BY:
LIA M. MAYLON
Engineer A
QUANTITY COMPUTATION SHEET
ILISAN SIP
Alicia, Zamboanga Sibugay
CONTRACT NO. NIAREG9-01222019-599
CONTRACTOR : LONG ISLAND BUILDERS AND CONSTRUCTION
NAME OF STRUCTURE/CANAL : ELEVATED FLUME
STATION : 3 + 464 3 + 580
PAY ITEM : STRUCTURE/ROCK EXCAVATION/BACKFILL
SKETCH COMPUTATION
w = 2.00 m.
STRUCTURE EXCAVATION
Hatched Area (RED) = 34.68 sq.m.
Vol. = 34.68 x 2.00 = 69.36 cu.m.
ROCK EXCAVATION
Hatched Area (YELLOW)= 9.49 sq.m. Vol. = 9.49 x 2.00 = 18.98 cu.m.
STRUCTURE BACKFILL
Hatched Area = 10.71 sq.m.
w = 2.00
Vol. = 10.71 x 2.00 = 21.42 cu.m.
EVALUATED BY:
LIA M. MAYLON
Engineer A
Project Title: Ilisan SIP (Buffer)
Location : Alicia, Zamboanga Sibugay
CLASS "A" CONCRETE (3000 PSI) PLAIN
1. Fabrication, Placing & Dismantling of Forms
Output: 3.50 cu.m/day
LABOR COMPOSITION
Personnel Wages
1 Carpenters 612.77
1 - Laborers 296.00
TOTAL 908.77
Labor Cost:
Wages : 908.77 /day P 259.65 /cu.m
3.50 cu.m/day
SUMMARY
Wages P 1,510.46
Equipment Rental P 393.14
TOTAL P 1,903.60 /cu.m
ITEMS QTY. WAGES EQUIP. RENTAL CONST. MAT. FUEL & OIL SUNDRIES
Unit Cost Total Unit Cost Total Unit Cost Total Unit Cost Total Unit Cost Total
Cement 9.00 bags 0.00 0.00 346.18 3,115.62
Sand 0.45 cu.m. 0.00 0.00 1390.12 625.55
Gravel 0.90 cu.m. 0.00 0.00 1489.67 1,340.70
Form Lumber 25.00 bd.ft 0.00 0.00 43.78 1,094.50
Plywood 1.25 sheet 0.00 0.00 1121.81 1,402.26
CWN 1.00 kgs. 0.00 0.00 90.75 181.51
Concrete Demolition
INDIRECT COST
OCM 15% OF EDC 122.73 /cu.m.
PROFIT 10% OF EDC 81.82 /cu.m.
VAT 5% OF (EDC, OCM & PROFIT) 40.91 /cu.m.
TOTAL COST 1,063.63 /cu.m.
EVALUATED BYl
MA. GERTRUDES P. GANIA
Supervising Engineer A
QUANTITY COMPUTATION SHEET
VARIATION ORDER NO. 1
ILISAN SIP
ALICIA, ZAMBOANGA SIBUGAY
CONTRACT NO. NIAREG9-01222019-599
NAME OF CONTRACTOR: LONG ISLAND BUILDERS & CONSTRUCTION
NAME OF STRUCTURE/CANAL : Elevated Flume/MAIN CANAL
STATION : 2 + 604 - 2 + 39
PAY ITEM : 3000 psi Reinforced Concrete
COLUMN Total height = (2.85+2.80+2.75+2.78+2.08+1.44)
0.25
14.70
0.25
Volume= Length x width x height
H Vol= 0.25 0.25 14.70
Vol= 0.92
5.38 cu.m.
ABUTMENT 1 Total Height = (0.50)
0.68 = 0.50
Vol=Area x H x no. of abutment
H
0.25 Vol = 0.25 0.25 0.50
Vol = 0.03
0.03 cu.m.
0.95
0.68 *
VOL=Area x Length(thickness) x no. of footing
EVALUATED BYl
MA. GERTRUDES P. GANIA
Supervising Engineer A
QUANTITY COMPUTATION SHEET
VARIATION ORDER NO. 1
ILISAN SIP
ALICIA, ZAMBOANGA SIBUGAY
CONTRACT NO. NIAREG9-01222019-599
NAME OF CONTRACTOR: LONG ISLAND BUILDERS & CONSTRUCTION
NAME OF STRUCTURE/CANAL : Elevated Flume/MAIN CANAL
STATION : 2 + 604 - 2 + 39
PAY ITEM : 3000 psi Reinforced Concrete
SKETCH COMPUTATION QTY. UNIT
FLUME Vol = Area(Flume) x Length
AREAS
A. 0.14 x 0.50 0.07
0.14 0.14 B. 0.14 x 0.50 0.07
C. 0.12 x 0.68 0.08
0.50 0.22
0.50 A B
EVALUATED BYl
MA. GERTRUDES P. GANIA
Supervising Engineer A
QUANTITY COMPUTATION SHEET
VARIATION ORDER NO. 1
ILISAN SIP
ALICIA, ZAMBOANGA SIBUGAY
CONTRACT NO. NIAREG9-01222019-599
NAME OF CONTRACTOR: LONG ISLAND BUILDRES & CONSTRUCTION
NAME OF STRUCTURE/CANAL : Elevated Flume/MAIN CANAL
STATION : 2 + 604 - 2 + 39
PAY ITEM : STRUCTURE/ROCK EXCAVATION & STRUCTURE BACKFILL
SKETCH
STRUCTURE BACKFILL
Hatched Area = 21.54 sq.m.
W = 2.00 m.
Vol .= 21.54 x 2.00 = 49.02 cu.m.
EVALUATED BYl
MA. GERTRUDES P. GANIA
Supervising Engineer A
Republika ng Pilipinas
National Irrigation Administration
(Pambansang Pangasiwaan ng Patubig)
Region IX
Office Address: DA, RFO IX Research Division Compound ZAMBOANGA SIBUGAY IRRIGATION MANAGEMENT OFFICE
Sanito, Ipil, Zamboanga Sibugay, Philippines Smart Mobile No. : 09985660134
Email Address:niazambosibugaysvisimo@yahoo.com Globe Mobile No. : 09177052856
TIN: 000-916-415-151
We, the undersigned contractors have given due consideration to Difference in cost this Change: Php 3,063.48
the change proposed and hereby agree, if this proposal is approved, we will Net Cost of Previous Changes: Php 21,896,734.46
provide all equipments, furnish all materials except as may otherwise be noted Original Contract Amount: Php 21,899,797.94
above and perform any all services necessary for the prices shown on the Estimated Revised Contract Amount: Php 21,896,734.46
reverse side of this sheet. By reason of this proposed change 0 days
Contract time will be allowed
Checked by: JADE J. BAGTASOS Recommending for Approval: MARIA GERTRUDES P. GANIA
Senior Engineer A Supervising Engineer A
Approved by:
GIRLIE M. DETALLA
Acting Division Manager
QUANTITY COMPUTATION SHEET
VARIATION ORDER NO. 1
ILISAN SIP
ALICIA, ZAMBOANGA SIBUGAY
CONTRACT NO. NIAREG9-01222019-599
NAME OF CONTRACTOR: LONG ISLAND BUILDRES & CONSTRUCTION
NAME OF STRUCTURE/CANAL : BENCHFLUME / MC
STATION : STA. 2+664.00 - STA 2+774
PAY ITEM : 3000 PSI RC
LENGTH (L) : 110 meters
B VOLUME (Footwalk)=B*0.20*0.10*#Ftwalks
0.10
Vf= 0.60 *0.20*0.10* 23 0.28 cu.m.
0.20 m.
VOLUME(Column) = (Dc+0.13)*0.20*0.20*2*#Ftwalks
0.20
Dc + 0.13 Vc= (0.60 + 0.13) *0.20*0.20* 2*23 1.34 cu.m.
0.20
Evaluated by:
LIA M. MAYLON
Engineer A
QUANTITY COMPUTATION SHEET
VARIATION ORDER NO. 1
ILISAN SIP
ALICIA, ZAMBOANGA SIBUGAY
CONTRACT NO. NIAREG9-01222019-599
NAME OF CONTRACTOR: LONG ISLAND BUILDRES & CONSTRUCTION
NAME OF STRUCTURE/CANAL : BENCHFLUME / MC
STATION : STA. 2+844.00 - STA 3+104
PAY ITEM : 3000 PSI RC
LENGTH (L) : 260 meters
B VOLUME (Footwalk)=B*0.20*0.10*#Ftwalks
0.10
Vf= 0.40 *0.20*0.10* 53 0.42 cu.m.
0.20 m.
VOLUME(Column) = (Dc+0.13)*0.20*0.20*2*#Ftwalks
0.20
Dc + 0.13 Vc= (0.50 + 0.13) *0.20*0.20* 2*53 2.67 cu.m.
0.20
Evaluated by:
LIA M. MAYLON
Engineer A
QUANTITY COMPUTATION SHEET
VARIATION ORDER NO. 1
ILISAN SIP
ALICIA, ZAMBOANGA SIBUGAY
CONTRACT NO. NIAREG9-01222019-599
NAME OF CONTRACTOR: LONG ISLAND BUILDRES & CONSTRUCTION
NAME OF STRUCTURE/CANAL : BENCHFLUME / MC
STATION : STA. 3+104.00 - STA 3+164
PAY ITEM : 3000 PSI RC
LENGTH (L) : 60 meters
VOLUME (Footwalk)=B*0.20*0.10*#Ftwalks
B
0.10 Vf= 0.40 *0.20*0.10* 13 0.10 cu.m.
0.20 m.
VOLUME(Column) = (Dc+0.13)*0.20*0.20*2*#Ftwalks
Evaluated by:
LIA M. MAYLON
Engineer A
QUANTITY COMPUTATION SHEET
VARIATION ORDER NO. 1
ILISAN SIP
ALICIA, ZAMBOANGA SIBUGAY
CONTRACT NO. NIAREG9-01222019-599
NAME OF CONTRACTOR: LONG ISLAND BUILDRES & CONSTRUCTION
NAME OF STRUCTURE/CANAL : BENCHFLUME / MC
STATION : STA. 3+164.00 - STA 3+324
PAY ITEM : 3000 PSI RC
LENGTH (L) : 160 meters
B
0.10
VOLUME (Footwalk)=B*0.20*0.10*#Ftwalks
Vf= 0.25 *0.20*0.10* 33 0.17 cu.m.
0.20 m.
Evaluated by:
LIA M. MAYLON
Engineer A
QUANTITY COMPUTATION SHEET
VARIATION ORDER NO. 1
ILISAN SIP
ALICIA, ZAMBOANGA SIBUGAY
CONTRACT NO. NIAREG9-01222019-599
NAME OF CONTRACTOR: LONG ISLAND BUILDRES & CONSTRUCTION
NAME OF STRUCTURE/CANAL : BENCHFLUME / MC
STATION : STA. 3+324.00 - STA 3+464
PAY ITEM : 3000 PSI RC
LENGTH (L) : 140 meters
B VOLUME (Footwalk)=B*0.20*0.10*#Ftwalks
0.10
Vf= 0.40 *0.20*0.10* 29 0.23 cu.m.
0.20 m.
VOLUME(Column) = (Dc+0.13)*0.20*0.20*2*#Ftwalks
0.20
Dc + 0.13 Vc= (0.50 + 0.13) *0.20*0.20* 2*29 1.46 cu.m.
0.20
Evaluated by:
LIA M. MAYLON
Engineer A
Republic of the Philippines
NATIONAL IRRIGATION ADMINISTRATION
Region IX
Pagadian City
EARTHWORKS
VARIATION ORDER NO.-1
EARTHWORKS
AREAS
A. 0.14 x 0.45 0.06
, 0.14 0.14 B. 0.14 x 0.45 0.06
C. 0.12 x 0.63 0.08
0.45 0.20
0.45 A B
VOLUME= 0.20 x 113.57
, 0.12 C = 22.71
0.35
L=113.57 m. 22.71 cu.m.
FLUME SEAT
0.83 Area = 0.83 x 0.40
0.63 = 0.33
EVALUATED BY:
LIA M. MAYLON
Engineer A
QUANTITY COMPUTATION SHEET
ILISAN SIP
Alicia, Zamboanga Sibugay
CONTRACT NO. NIAREG9-01222019-599
CONTRACTOR : LONG ISLAND BUILDERS AND CONSTRUCTION
NAME OF STRUCTURE/CANAL : COMB ELEVATED FLUME & TO
STATION : 3 + 492 3 + 608
PAY ITEM : 3000 psi Reinforced Concrete
EVALUATED BY:
LIA M. MAYLON
Engineer A
QUANTITY COMPUTATION SHEET
ILISAN SIP
Alicia, Zamboanga Sibugay
CONTRACT NO. NIAREG9-01222019-599
CONTRACTOR : LONG ISLAND BUILDERS AND CONSTRUCTION
NAME OF STRUCTURE/CANAL : COMB ELEVATED FLUME & TO
STATION : 3 + 492 3 + 608
PAY ITEM : 3000 psi Reinforced Concrete
SKETCH COMPUTATION QTY. UNIT
TURN OUT
COW Area = Area whole - Area shaded
1.05
0.25 AREA= 1.05 x 0.65
= 0.68
0.25
0.40 Area sq. 0.25 x 0.25
0.65 = 0.06
Area tri. 0.50 0.25 0.25 2.00
0.25 = 0.06
Area = Area whole - (Area sq. + Area tri.)
, 0.25 Total Area= 0.68 - 0.13
= 0.56
Vol.= 0.56 x 0.13
t = 0.13 = 0.07 x 4.00 0.29 cu.m.
FILLET V = Area x length
0.15 Area= 0.50 0.15 0.15
, 0.15 = 0.01
Vol.= 0.01 0.51 4.00
L=0.51 m. 0.02 cu.m.
FLOORING
0.55 V = length x width x thickness
Area= 0.55 0.51 0.13 4.00
0.51 = 0.15
t = 0.13 0.15 cu.m.
SIDING 1 : SECTION E-E
0.30 VOL = length x width x thickness
Vol = 0.30 0.4 0.13 4.00
0.40 = 0.06
0.06 cu.m.
SIDING 1 : SECTION G-G
0.30 VOL = length x width x thickness
Vol = 0.30 0.41 0.13 4.00
0.41 = 0.06
0.06 cu.m.
SIDING 2: SECTION E-E
VOL=1/2 x (X1 + X2) x Length(thickness)
0.40
0.25 Vol = 0.5 0.65 0.25 0.13
= 0.01
0.25
TOTAL VOL.= 0.01 x 4.00 0.04 cu.m.
SIDING 2: SECTION G-G
VOL=1/2 x (X1 + X2) x Length(thickness)
0.41
0.25 Vol = 0.5 0.66 0.25 0.13
= 0.01
0.25
t = 0.13 TOTAL VOL.= 0.01 x 4.00 0.11 cu.m.
EVALUATED BY:
LIA M. MAYLON
Engineer A
QUANTITY COMPUTATION SHEET
ILISAN SIP
Alicia, Zamboanga Sibugay
CONTRACT NO. NIAREG9-01222019-599
CONTRACTOR : LONG ISLAND BUILDERS AND CONSTRUCTION
NAME OF STRUCTURE/CANAL : COMB ELEVATED FLUME & TO
STATION : 3 + 492 3 + 608
PAY ITEM : STRUCTURE/ROCK EXCAVATION/BACKFILL
SKETCH COMPUTATION
w = 2.00 m.
STRUCTURE EXCAVATION
Hatched Area (RED) = 34.68 sq.m.
Vol. = 34.68 x 2.00 = 69.36 cu.m.
ROCK EXCAVATION
Hatched Area (YELLOW)= 9.49 sq.m. Vol. = 9.49 x 2.00 = 18.98 cu.m.
EVALUATED BY:
LIA M. MAYLON
Engineer A
1
QUANTITY COMPUTATION SHEET
ILISAN SIP
Alicia, Zamboanga Sibugay
CONTRACT NO. NIAREG9-01222019-599
CONTRACTOR : LONG ISLAND BUILDERS AND CONSTRUCTION
NAME OF STRUCTURE/CANAL : COMB ELEVATED FLUME & TO
STATION : 3 + 492 3 + 608
PAY ITEM : STRUCTURE EXCAVATION/BACKFILL
A3 0.30
A2
1.65
A1 A2 1.11 1.65 1.05
A1
A3 0.30
V1 = A1 x H1
H2=H3 V1 = 1.65 0.43 0.75 4.00 2.13 cu.m.
H1 V2 = A2 x H2
V1 = 1.11 0.55 0.41 4.00 1.00 cu.m.
BACKFILL:
V1 = A1 x H1
H1 = 0.75 m. A1= 0.71 - 0.1365 0.57
H2 = 0.41 m. V1 = 0.57 x 0.75 4.00 1.72 cu.m.
H3 = 0.41 m. V2 = A3 x H3 x 2
V2+V3 = 0.30 0.55 0.41 4.00 0.27 cu.m.
EVALUATED BY:
LIA M. MAYLON
Engineer A
QUANTITY COMPUTATION SHEET
VARIATION ORDER NO. 1
ILISAN SIP
Alicia, Zamboanga Sibugay
NIAREG9-01222019-599
NAME OF CONTRACTOR : LONG ISLAND BUILDERS & CONSTRUCTION
NAME OF STRUCTURE/CANAL : CUT & COVER COMB. T.O. LS
STATION : 2+774.00 - 2+844.00 -
PAY ITEM : 3000 PSI STRUCTURAL CONCRETE
C. V = A * Htotal
0.15
1.00
0.15
Ht = (1.54+1.73+1.22)
0.10 0.15
0.15 x 0.15
fillet
= 4.49
V manhole
(1.30 x (0.90) - 1 (0.60))x 4.49 2.56 cu.m.
EVALUATED BY:
LIA M. MAYLON
Engineer A
QUANTITY COMPUTATION SHEET
VARIATION ORDER NO. 1
ILISAN SIP
ALICIA, ZAMBOANGA SIBUGAY
NIAREG9-01222019-599
NAME OF CONTRACTOR: LONG ISLAND BUILDRES & CONSTRUCTION
NAME OF STRUCTURE/CANAL : CHECK & TURN OUT L.S./MAIN CANAL
STATION : 2+774.00 - 2+844.00 -
PAY ITEM : 3000 psi Reinforced Concrete
Siding Inlet:
Siding: V = AREA x THICKNESS
AREA = 1/2(1.25+0.60)(0.90)
0.83
0.60 1.25
V = 0.83 x 0.13 x 2 sides 0.2158 cu.m.
0.90
Thickness = 0.13
Siding Outlet:
V = AREA x THICKNESS
AREA = 1/2(1.25+0.62)(1.30)
1.25 0.62 1.22
Flooring Inlet:
1.50
V = 0.66 x 1.50 x 0.13 0.13 cu.m.
0.66
T = 0.13
Flooring Outlet :
2.38
EVALUATED BY:
LIA M. MAYLON
Engineer A
CONCURRED BY: KADER S. MODAPIL 36.27
P.E. / CONTRACTOR SIDE UNIT cu.m.
EVALUATED BY:
LIA M. MAYLON
Engineer A
QUANTITY COMPUTATION SHEET
VARIATION ORDER NO. 1
ILISAN SIP
ALICIA, ZAMBOANGA SIBUGAY
CONTRACT NO. NIAREG9-01222019-599
NAME OF CONTRACTOR: LONG ISLAND BUILDRES & CONSTRUCTION
NAME OF STRUCTURE/CANAL : CHECK & TURN OUT L.S./MAIN CANAL
STATION : 2+774.00 - 2+844.00 -
PAY ITEM : 3000 psi Reinforced Concrete
1.05
0.25 Area = Areawhole - Area shaded
Area Whole = 1.05*0.25
0.25 0.68
0.40 Area Shaded = Area square + total area Triangle
0.65 Area Square = 0.30*0.25
0.06
0.25 Area Triangle0 =0 .25*0.25 0.5
0.03125
0.25 Area shaded = 0.09
t= 0.13 Area Total = 0.59
Vol = Area x thickness 0.59 0.13
0.0765375 1 0.08 cu.m.
Fillet
0.15
0.15 V = 1/2*0.15*0.15*2 0.51
0.0115 1.00 0.01 cu.m.
Flooring
0.51
0.60 Vol = 0.51 x 0.60 x 0.13 1.00
t= 0.13 0.04 0.04 cu.m
Siding
0.30
0.41
0.25 Vol = 0.50 x (0.41 + 0.25) x 0.30 x 0.13 x 2
t= 0.13 0.03
0.03 cu.m
Siding
EVALUATED BY:
LIA M. MAYLON
Engineer A
QUANTITY COMPUTATION SHEET
VARIATION ORDER NO. 1
ILISAN SIP
ALICIA, ZAMBOANGA SIBUGAY
CONTRACT NO. NIAREG9-11092018-599
NAME OF CONTRACTOR: LONG ISLAND BUILDRES & CONSTRUCTION
NAME OF STRUCTURE/CANAL : CUT & COVER
STATION : 3+636.00 - 3+671.50 -
PAY ITEM : 3000 PSI STRUCTURAL CONCRETE
0.15
1.30
C. V = A * Htotal
Ht = 0.73
0.15 0.15
1.00
0.10 0.15
= 0.73
H
0.15 x 0.15
fillet
V manhole
(1.30 x (0.90) - 1 (0.60))x 0.73 0.42 cu.m.
EVALUATED BY:
Footwalk
T = 0.10
1.30
V= 1.30 x 0.30 x 0.10 0.04 cu.m.
0.30
`
Flooring Inlet:
1.50
V = 0.66 x 1.50 x 0.13 0.13 cu.m.
0.66
T = 0.13
EVALUATED BY:
SKETCH COMPUTATION
w = 1.90 m.
STRUCTURE EXCAVATION
Hatched Area(blue) = 55.71 sq.m.
Vol. = 55.71 x 1.90 = 105.849 cu.m.
55.75 1.9 105.925
Rock Excavation
Hatched Area(blue) = 5.59 sq.m. 5.59 1.9000 10.62
Vol. = 5.59 x 1.90 = 10.62 cu.m.
EVALUATED BY:
Flooring
0.56
0.70 Vol = 0.70 x 0.61 x 0.13 2.00
t= 0.13 0.10 0.10 cu.m
Siding
0.35
0.56
0.30 Vol = 0.50 x (0.56 + 0.30) x 0.35 x 2
t= 0.13 0.30
0.30 cu.m
t= 0.10
cu.m.
t= 0.15
Flooring - INLET
C ² = 𝑎²+b²
1.50
t= 0.13
SIDINGS: Vol.rec. - Vol.hollow = Vol.total
V - hollow , considering 2 sides Area.rec. X thickness = vol.rec
1.50 A = 1.50 x 1.72
2.58 x 0.13
A1
0.58 0.335
1.72 Area.hollow x thickness = Vol.hollow
1.14 A2 A1 = 1/2 x 0.58 x 1.50
0.44 x0.13
1.00 0.057
0.50 A2 = 1/2 x 1.14 x 1.00
t= 0.13 0.57 x 0.13
0.074
Vol.rec. - Vol.hollow = Vol.total x 2 sides
(0.231)- (0.038+ 0.048)]
0.34 - 0.131 x2
= 0.4095 0.41
Sub-total 0.83
COMPUTED BY: MARIVIC B. ZAMORANOS
Engineering Assistant A
SHEET NO. TOTAL QUANTITY
CONCURRED BY: KADER S. MODAPIL 1
P.E./Contractor Side 3 UNIT
QUANTITY COMPUTATION SHEET
VARIATION ORDER NO. 1
ILISAN SIP
ALICIA, ZAMBOANGA SIBUGAY
CONTRACT NO. NIAREG9-11092018-577
NAME OF CONTRACTOR: LONG ISLAND BUILDRES & CONSTRUCTION
NAME OF STRUCTURE/CANAL : Drainage Crossing/MAIN CANAL
STATION : 1 + 048
PAY ITEM : 3000 psi Reinforced Concrete
VOLUME INLET
0.87 x 0.80 x 0.15
h-INLET 0.08
0.50 1.50
t= 0.15
Cut of wall - OUTLET
1.81 V= LxWxH
V= 1.81 0.13 0.8
= 0.188 0.19
0.8
t= 0.13
UNIT
cu.m.
cu.m.
cu.m.
cu.m.
ANTITY COMPUTATION SHEET
VARIATION ORDER NO. 1
ILISAN SIP
LICIA, ZAMBOANGA SIBUGAY
RACT NO. NIAREG9-11092018-577
UNIT
cu.m.
cu.m.
cu.m.
cu.m.
cu.m.
cu.m.
ANTITY COMPUTATION SHEET
VARIATION ORDER NO. 1
ILISAN SIP
LICIA, ZAMBOANGA SIBUGAY
RACT NO. NIAREG9-11092018-577
UNIT
cu.m.
cu.m.
cu.m.
cu.m.
Republic of the Philippines
NATIONAL IRRIGATION ADMINISTRATION
Region IX
Pagadian City
EARTHWORKS
Evaluated by:
LIA M. MAYLON
Engineer A
Republic of the Philippines
NATIONAL IRRIGATION ADMINISTRATION
Region IX
Pagadian City
EARTHWORKS
Evaluated by:
LIA M. MAYLON
Engineer A
Republic of the Philippines
NATIONAL IRRIGATION ADMINISTRATION
Region IX
Pagadian City
EARTHWORKS
Evaluated by:
LIA M. MAYLON
Engineer A
PIPELINE HDPE
TOTAL
BAR SIZE LENGTH QUANTIT
BAR DETAILS LENGTH
(mm) (m) Y
(m)
Strut Beam Sta. 2+460-2+960 (Lateral C)
vert.
(12mm ) 0.80 400 320.00
tie bars
(12mm ) 0.72 400 288.00
tie bars
C1 (12mm ) 0.72 176 126.72
tie bars
C1 (12mm ) 0.72 392 282.24
SAY
Computed by:
LIMAR F. JUMALON
Engineering Assistant B
EVALUATED BY:
EVALUATED BY:
EVALUATED BY:
EVALUATED BY:
EVALUATED BY:
EVALUATED BY:
TOTAL NO. TOTAL TOTAL
UNIT WT.
BARS PER NO. OF WEIGHT
kg/m (kg)
LENGTH 6m BARS
EVALUATED BY:
# of rcp
dia of RCP
EVALUATED BY:
0.6 0.61
thickness 0.13
Inlet warf
0.6 0.61
thickness 0.15
Inlet warf
CoW
depth
in elev.
b elev
Distance
inclined
flat
outlet warf
CoW
depth
b elev
Distance
inclined
#REF! flat
EVALUATED BY:
EVALUATED BY:
QUANTITY COMPUTATION SHEET
LOWER SIBUGUEY II RIS EXTENSION PROJECT CY 2016 REMAINING WORKS
Siay , Zamboanga Sibugay
NIAREG9-03102020-675
CONTRACT NO. NIAREG9-0822-2016-LINEPROJECT-026(INFRA)
CONTRACTOR : LAKEWOOD CONSTRUCTION COMPANY
NAME OF STRUCTURE/CANAL : RC PILE STRUT 20cm x 20cm
STATION : 3 + 217.75 to 3 + 572.75
PAY ITEM : 3000 PSI PLAIN CONCRETE
LENGTH (L) : 355 meters
PIPE LINE HDPE
Computed by:
RODEL J. YUNTING
PIC
Checked by: SHEET NO. TOTAL QUANTITY
1 2.02
cu.m.
1
Contractor UNIT
EVALUATED BY:
JADE J. BAGTASOS
QUANTITY COMPUTATION SHEET
LOWER SIBUGUEY II RIS EXTENSION PROJECT CY 2016 REMAINING WORKS
Siay , Zamboanga Sibugay
SKETCH COMPUTATION
QTY unit
# of pile=71.00 pair.
pile intervals=5.00 m.
Pile Driven
L.m = # of piles x length
= 81 x 2 x 9
= 1,278.00 l.m 1,278.00 l.m
𝑎²+b²
20cm
12cm
12cm 12cm 20cm
12cm
COMPUTED BY:
PREPARED BY: RODEL J. YUNTING Sub-total 1,278.00 l.m
Project-Incharge
SHEET NO. 1,278.00 l.m
CONCURRED BY: 1 TOTAL QUANTITY
Contractor 1
EVALUATED BY:
JADE J. BAGTASOS
QUANTITY COMPUTATION SHEET
LOWER SIBUGUEY II RIS EXTENSION PROJECT CY 2016 REMAINING WORKS
Siay , Zamboanga Sibugay
SKETCH COMPUTATION
4 pcs. x 9m 36 mtrs
6.00 mtr/ pcs
= 6.00 pcs
𝑎²+b²
20cm
12cm
12cm 12cm 20cm
12cm
COMPUTED BY:
PREPARED BY: RODEL J. YUNTING Sub-total
Project-Incharge
SHEET NO.
CONCURRED BY: 1 TOTAL QUANTITY
Contractor 1
EVALUATED BY:
CONTRACTOR : LAKEWOOD CONSTRUCTION COMPANY
NAME OF STRUCTURE/CANAL : RC PILE 20cm x 20cm x 6.00m
STATION : 3 + 201.75 to 3 + 572.75
PAY ITEM : RSB (Reinforcing Bars)
LENGTH (L) : 371 meters
SKETCH COMPUTATION
# of pile=75.00 pair. LATERAL TIES 12mm dia RSB
pile intervals=5.00 m. 24pcs. Sp. @ 5cm O.C.
22pcs. Sp. @ 5cm O.C.
45pcs. sp. @ 15cm O.C.
(12cm x 4)+ 10 cm = 0.58cm/pc
91 pcs x 0.58 m/pc 52.78 mtrs
. 6.00 mtr/ pcs
= 8.80 pcs say 9.00
4 pcs. x 9m 36 mtrs
6.00 mtr/ pcs
= 6.00 pcs
𝑎²+b²
20cm
12cm
12cm 12cm 20cm
12cm
COMPUTED BY:
PREPARED BY: RODEL J. YUNTING Sub-total
Project-Incharge
SHEET NO.
CONCURRED BY: 1 TOTAL QUANTITY
Contractor 1
EVALUATED BY:
EVALUATED BY:
EVALUATED BY:
EVALUATED BY:
EVALUATED BY:
NTITY COMPUTATION SHEET
EXTENSION PROJECT CY 2016 REMAINING WORKS
Siay , Zamboanga Sibugay
12mm 20mm
(0.888kg/m) (2.466kg/m)
4,219.78
7,812.29
4,219.78 7,812.29
12,032.06
12mm 20mm
(0.888kg/m) (2.466kg/m)
7,192.80
13,316.40
3.696
7,192.80 13,316.40
20,509.20
EVALUATED BY:
0.6
thickness
0.6
thickness
#REF!
EVALUATED BY:
EVALUATED BY:
QUANTITY COMPUTATION SHEET
VARIATION ORDER NO. 1
LOWER SIBUGUEY II RIS EXTENSION PROJECT CY2016 REMAINING WORKS
SIAY, ZAMBOANGA SIBUGAY
NIAREG9-03102020-676
NAME OF CONTRACTOR: LAKEWOOD CONSTRUCTION COMPANY
NAME OF STRUCTURE/CANAL : Road Crossing/LAT-C
STATION : 3+178 - 3+201.75
PAY ITEM : HDPE PIPE (355 MM DIAMETER)
19.31
3.94
2.85
13.71
1.96
0.80
W= 1.4 m
HORIZONTAL PIPE 13.71 / 6 = 2.285 SAY 2.5
INLET PIPE 2.85 / 6 = 0.475 SAY 0.5
OUTLET PIPE 3.94 / 6 = 0.66 SAY 1
No. of HDPE PIPE (355 mm diameter) SUB-TOTAL 4
DOUBLE PIPE TOTAL 8
8
COMPUTED BY: RODEL J. YUNTING Sub-Total TOTAL PCS
Project In-charge
SHEET NO. TOTAL QUANTITY
CONCURRED BY: 1 TOTAL 8.00
PE-CONTRACTOR 1 UNIT PCS
EVALUATED BY:
JADE J. BAGTASOS
QUANTITY COMPUTATION SHEET
VARIATION ORDER NO. 1
LOWER SIBUGUEY II RIS EXTENSION PROJECT CY2016 REMAINING WORKS
SIAY, ZAMBOANGA SIBUGAY
NIAREG9-03102020-676
NAME OF CONTRACTOR: LAKEWOOD CONSTRUCTION COMPANY
NAME OF STRUCTURE/CANAL : Road Crossing/LAT-C
STATION : 3+178 - 3+201.75
PAY ITEM : REINFORCING STEEL BAR (RSB)
TOTAL
TOTAL TOTAL
BAR SIZE LENGTH QUANTIT UNIT WT. NO. BARS
BAR DETAILS TOTAL LENGTH (m) NO. OF WEIGHT
(mm) (m) Y kg/m PER (kg)
6m BARS
LENGTH
FLOORING OUTLET
1.45
hor.
(10mm) 1.45 5 7.25 0.616 2.00 7.39
1.012
vert.
(10mm ) 1.012 7 7.08 0.616 1.00 3.70
hor.
(10mm) 7.34 0.616 2.00 7.39
0.94 vert.
(10mm ) 7.52 0.616 2.00 7.39
1.87
vert.
0.6 (10mm ) 0.60 5 3.00 0.616 1.00 3.70
SUB-TOTAL
10mm Ø = 9.00 33.26
Computed by: TOTAL 10mm Ø = 20.00 73.92
waste factor (15%)= 3.00 11.09
RODEL J. YUNTING TOTAL 10mm Ø= 23.00 85.01
PIC
Concurred by:
PE- Contractor
EVALUATED BY:
JADE J. BAGTASOS
QUANTITY COMPUTATION SHEET
VARIATION ORDER NO. 1
LOWER SIBUGUEY II RIS EXTENSION PROJECT CY2016 REMAINING WORKS
SIAY, ZAMBOANGA SIBUGAY
NIAREG9-03102020-676
NAME OF CONTRACTOR: LAKEWOOD CONSTRUCTION COMPANY
NAME OF STRUCTURE/CANAL : Road Crossing/LAT-C
STATION : 3+178 - 3+201.75
PAY ITEM : 3000 psi Plain Concrete
COLLAR OUTLET Area Concrete= Area Rec. - Area of pipe
Area Rec. = 1.11 * 0.755
1.11 Area Rec. = 0.838 sq.m
0.3 Area Concrete = 0.640 sq.m
w = 0.30 m.
area of pipe = 0.20 sq.m.
OUTLET FLOORING
t = 0.15 m.
1.55 Vol. Concrete = Area concrete x thickness
Vol. Concrete = 1.55 * 1.112 * 0.15
Vol. Concrete = 0.26 cu.m 0.26 cu.m.
1.112
0.15
COLLAR OUTLET (Connected To siphonic RD.CR Pipe)
Area Concrete= Area Rec. - Area of pipe
Area Rec. = 1.11 * 0.755
1.11 Area Rec. = 0.838 sq.m
0.3 Area Concrete = 0.640 sq.m
w = 0.30 m.
area of pipe = 0.20 sq.m.
Sub-total 1.12 cu.m.
COMPUTED BY: RODEL J. YUNTING
PIC
SHEET NO. TOTAL QUANTITY
CONCURRED BY: 2 2.44 cu.m.
PE-CONTRACTOR 2 UNIT
EVALUATED BY:
JADE J. BAGTASOS
QUANTITY COMPUTATION SHEET
VARIATION ORDER NO. 1
LOWER SIBUGUEY II RIS EXTENSION PROJECT CY2016 REMAINING WORKS
SIAY, ZAMBOANGA SIBUGAY
NIAREG9-03102020-676
NAME OF CONTRACTOR: LAKEWOOD CONSTRUCTION COMPANY
NAME OF STRUCTURE/CANAL : Drainage Crossing/LAT-C
STATION : 3 + 220
PAY ITEM : BOULDER BEDDING
80 60
15
15
W= 1.4 m
Hatched Area = 6.32 sq.m
Working Space = 0.30 m.
EVALUATED BY:
JADE J. BAGTASOS
QUANTITY COMPUTATION SHEET
VARIATION ORDER NO. 1
LOWER SIBUGUEY II RIS EXTENSION PROJECT CY2016 REMAINING WORKS
SIAY, ZAMBOANGA SIBUGAY
NIAREG9-03102020-676 LINEPROGRAMS-EXTENSION
NAME OF CONTRACTOR: LAKEWOOD CONSTRUCTION COMPANY
NAME OF STRUCTURE/CANAL : Drainage Crossing/LAT-C
STATION : 3 + 140
PAY ITEM : BOULDER BEDDING
80 60
15
15
W= 1.4 m
Hatched Area = 6.32 sq.m
Working Space = 0.30 m.
EVALUATED BY:
JADE J. BAGTASOS
QUANTITY COMPUTATION SHEET
VARIATION ORDER NO. 1
ILISAN SIP
ALICIA, ZAMBOANGA SIBUGAY
CONTRACT NO. NIAREG9-01222019-599
NAME OF CONTRACTOR: LONG ISLAND BUILDRES & CONSTRUCTION
NAME OF STRUCTURE/CANAL : CHECK & TO LS/MAIN CANAL
STATION : 3 + 104
PAY ITEM : 3000 psi Reinforced Concrete
1.00
0.2 Area = Areawhole - Area shaded
Area Whole = 1.00*0.70
0.25 0.65
0.40 Area Shaded = Area square + total area Triangle
0.65 Area Square = 0.20*0.25
0.05
0.25 Area Triangle0 =0 .25*0.25 0.5
0.03125
0.25 Area shaded = 0.08
t= 0.13 Area Total = 0.57
Vol = Area x thickness 0.57 0.13
0.07 1 0.07 cu.m.
Fillet
0.15
0.15 V = 1/2*0.15*0.15*2 0.46
0.0104 1.00 0.01 cu.m.
Flooring
0.46
0.45 Vol = 0.46 x 0.45 x 0.13 1.00
t= 0.13 0.03 0.03 cu.m
Siding
0.20
0.50
0.25 Vol = 0.50 x (0.50 + 0.25) x 0.20 x 0.13 x 2
t= 0.13 0.02
0.02 cu.m
Siding
LIA M. MAYLON
Engineer A
CONCURRED BY: KADER S. MODAPIL 1 0.16 0.16
P.E. / CONTRACTOR SIDE 2 UNIT cu.m
EVALUATED BY:
LIA M. MAYLON
Engineer A
QUANTITY COMPUTATION SHEET
VARIATION ORDER NO. 1
ILISAN SIP
ALICIA, ZAMBOANGA SIBUGAY
CONTRACT NO. NIAREG9-01222019-599
NAME OF CONTRACTOR: LONG ISLAND BUILDRES & CONSTRUCTION
NAME OF STRUCTURE/CANAL : Drainage Crossing/MAIN CANAL
STATION : 3 + 104
PAY ITEM : 3000 psi Reinforced Concrete
0.66
0.20 Footwalk
Vol = 0.66 0.20 0.10
0.01 0.01 cu.m.
t= 0.10
Siding
1.65 Vol = Vol(siding)*2 - V(groove)*2- Vcheck
EVALUATED BY:
LIA M. MAYLON
Engineer A
QUANTITY COMPUTATION SHEET
VARIATION ORDER NO. 1
ILISAN SIP
ALICIA, ZAMBOANGA SIBUGAY
CONTRACT NO. NIAREG9-01222019-599
NAME OF CONTRACTOR: LONG ISLAND BUILDRES & CONSTRUCTION
NAME OF STRUCTURE/CANAL : CHECK & TO LS/MAIN CANAL
STATION : 3 + 104
PAY ITEM : STRUCTURE EXCAVATION/BACKFILL
A3 0.30
A2
1.06
A1 A2 0.46 1.06 0.46
A1
A3 0.3
V1 = A1 x H1
H2=H3 V1 = 1.06 0.43 0.65 0.30 cu.m.
H1 V2 = A2 x H2
V1 = 0.46 0.45 0.50 0.10 cu.m.
BACKFILL:
V1 = A1 x H1
H1 = 0.65 m. A1= 0.48 - 0.0598 0.42
H2 = 0.50 m. V1 = 0.42 x 0.65 0.27 cu.m.
H3 = 0.50 m. V2 = A3 x H3 x 2
V2+V3 = 0.00 0.45 0.5 2.00 0.21 cu.m.
LIA M. MAYLON
Engineer A
CONCURRED BY: KADER S. MODAPIL 2
P.E. / CONTRACTOR SIDE 2
EVALUATED BY:
LIA M. MAYLON
Engineer A
QUANTITY COMPUTATION SHEET
VARIATION ORDER NO. 1
ILISAN SIP
ALICIA, ZAMBOANGA SIBUGAY
CONTRACT NO. NIAREG9-01222019-599
NAME OF CONTRACTOR: LONG ISLAND BUILDRES & CONSTRUCTION
NAME OF STRUCTURE/CANAL : CHECK & T.O./MAIN CANAL
STATION : 3 + 164
PAY ITEM : 3000 psi Reinforced Concrete
1.15
0.35 Area = Areawhole - Area shaded
Area Whole = 1.15*0.75
0.35 0.86
0.40 Area Shaded = Area square + total area Triangle
0.75 Area Square = 0.35*0.35
0.12
0.35 Area Triangle0 =0 .35*0.35 0.5
0.06125
0.35 Area shaded = 0.18
t= 0.13 Area Total = 0.68
Vol = Area x thickness 0.68 0.13
0.0882375 2 0.18 cu.m.
Fillet
0.15
0.15 V = 1/2*0.15*0.15*2 0.61
0.0137 2.00 0.03 cu.m.
Flooring
0.61
0.8 Vol = 0.61 x 0.80 x 0.13 2.00
t= 0.13 0.13 0.13 cu.m
Siding
0.30
0.52
0.35 Vol = 0.50 x (0.52 + 0.35) x 0.30 x 0.13 x 4
t= 0.13 0.07
0.07 cu.m
EVALUATED BY:
LIA M. MAYLON
Engineer A
QUANTITY COMPUTATION SHEET
VARIATION ORDER NO. 1
ILISAN SIP
ALICIA, ZAMBOANGA SIBUGAY
CONTRACT NO. NIAREG9-01222019-599
NAME OF CONTRACTOR: LONG ISLAND BUILDRES & CONSTRUCTION
NAME OF STRUCTURE/CANAL : Drainage Crossing/MAIN CANAL
STATION : 3 + 164
PAY ITEM : 3000 psi Reinforced Concrete
t= 0.10
cu.m.
EVALUATED BY:
LIA M. MAYLON
Engineer A
QUANTITY COMPUTATION SHEET
VARIATION ORDER NO. 1
ILISAN SIP
ALICIA, ZAMBOANGA SIBUGAY
CONTRACT NO. NIAREG9-11092018-577
NAME OF CONTRACTOR: LONG ISLAND BUILDRES & CONSTRUCTION
NAME OF STRUCTURE/CANAL : Drainage Crossing/MAIN CANAL
STATION : 3 + 164
A3 0.30
A2
1.75
A1 A2 1.21 1.75 0.61
A1
A3 0.30
V1 = A1 x H1
0.52 V1 = 1.75 x 0.43 x 0.75 2 1.13 cu.m.
H1 V2 = A2 x H2
V1 = 1.21 x 0.80 x 0.52 2 1.01 cu.m.
2.14
BACKFILL:
V1 = A1 x H1
H1 = 0.75 m. A1= 0.75 - 0.08 = 0.67
H2 = 0.52 m. V1 = 0.67 x 0.75 2 1.01 cu.m.
V3 = A3 x H3
V3 = 0.30 x 0.80 x 0.52 x 2 0.25 cu.m.
1.26 cu.m.
EVALUATED BY:
LIA M. MAYLON
Engineer A
MASTERLIST
LOWER SIBUGUEY II RIS EXTENSION PROJECT - CY 2016 REMAINING WORKS Package 3
NIAREG9-03102020-676 LINEPROGRAMS-EXTENSION
2nd PROGRESS BILLING
Sub - Total 371.00 552.00 69.56 - 2,194.00 1.31 306.36 569.82 - - 11,627.29
CANAL STRUCTURE
Drainage Crossing Lateral C 3 + 140.00
Prop. Road Crossing Lateral C 3 + 178.00 3 + 201.75 23.75
Drainage Crossing Lateral C 3 + 220.00
Sub - Total 23.75 - - - - - - - - - - -
GRAND-TOTAL 371.00 575.75 69.56 - 2,194.00 1.31 306.36 569.82 - - - - 11,627.29
Reinforced
HDPE Common Common Structure Structure Embankment
Concrete Boulder
STATIONING Length Length 355mmØ RSB Excavatio Backfill Excavatio Backfill (Haul
Gravel Piles 3000 Psi Plain Bedding
ITEM OF WORK Name of Canal with n (cu.m) (cu.m) n (cu.m) (cu.m) Borrow)
Bedding ( 0.20 x Concrete
accessories
0.20 x 6.0)
(pc)
(ln.m.)
Inlet Outlet ( m. ) ( m. ) kgs. Mech. Mech. Manual Manual cu.m cu.m
PACKAGE 3
CANALIZATION
Prop. Pipeline HDPE Lateral C 2 + 981.00 3 + 178.00 197.00 66.00
Lateral C 2 + 960.00 3 + 178.00 218.00 47.96 774.00 1.22 281.85 372.68 324.72 5,046.08
Lateral C 3 + 201.75 3 + 317.75 116.00 25.64 39.00 199.21 173.59
Prop. Pipeline HDPE Lateral C 3 + 317.75 3 + 338.75 21.00 7.00
Lateral C 3 + 201.75 3 + 216.75 15.00 54.00 0.09 24.51
Lateral C 3 + 216.75 3 + 217.75 1.00 54.00 0.09 24.51
Lateral C 3 + 217.75 3 + 572.75 355.00 1,278.00 2.02 447.29
Lateral C 3 + 201.75 3 + 572.75 371.00 8,804.27
Sub - Total 371.00 552.00 73.60 112.00 2,160.00 3.42 778.16 571.89 498.31 - 13,850.35
CANAL STRUCTURE
Drainage Crossing Lateral C 3 + 140.00 2.16 7.11 310.46 2.98 8.85
Prop. Road Crossing Lateral C 3 + 178.00 3 + 201.75 23.75 6.71 8.00 2.44 85.01 45.56 34.29 20.52
Drainage Crossing Lateral C 3 + 220.00 2.16 7.14 310.46 2.98 8.85
Sub - Total 23.75 11.03 8.00 - 16.69 705.93 - - 51.52 34.29 38.22 -
GRAND-TOTAL 371.00 575.75 84.63 120.00 2,160.00 20.11 1,484.09 571.89 498.31 51.52 34.29 38.22 13,850.35
Sub - Total 371.00 334.00 73.60 112.00 828.00 1.31 306.36 571.89 498.31 - 13,850.35
CANAL STRUCTURE
Drainage Crossing Lateral C 3 + 140.00 2.16 7.11 310.46 2.98 8.85
Prop. Road Crossing Lateral C 3 + 178.00 3 + 201.75 23.75 4.56 8.00 1.81 70.22 32.65 49.66 18.24
Drainage Crossing Lateral C 3 + 220.00 2.16 7.14 310.46 2.98 8.85
Sub - Total 23.75 8.88 8.00 - 16.06 691.14 - - 38.61 49.66 35.94 -
GRAND-TOTAL 371.00 357.75 82.48 120.00 828.00 17.37 997.50 571.89 498.31 38.61 49.66 35.94 13,850.35
2 CANALIZATION 6 10 7 7 7 9 7 7 7 10 7 7 7 9 7 5
PROJECTED 0.016% 0.027% 0.019% 0.019% 0.019% 0.024% 0.019% 0.019% 0.019% 0.027% 0.019% 0.019% 0.019% 0.024% 0.019% 0.013% 87.02%
2.1 COMMON EXCAVATION (Mech.) 571.89 cu.m P 69,701.95 0.32%
ACTUAL 8 6
PROJECTED 1.27% 2.53% 1.77% 1.77% 1.77% 2.53% 1.77% 1.77% 1.77% 2.28% 1.77% 1.77% 1.77% 2.53% 1.77% 1.77% 1.77% 2.28% 1.77% 1.77% 1.77% 2.53% 1.77% 1.77% 0.76%
2.3.a HAUL BORROW 13,850.35 cu.m P 10,264,909.90 46.88% 69.09%
ACTUAL 7 9 7 7 7 10 7 7 7 9 7 5
REINFORCED CONCRETE PILES PROJECTED 1.58% 2.04% 1.58% 1.58% 1.58% 2.26% 1.58% 1.58% 1.58% 2.04% 1.58% 1.13%
2.4 2,160.00 ln.m P 4,408,041.60 20.13% 62.91%
(0.20mx0.20mx6m)
ACTUAL 7 7 7 7 9 7 7 7 2
PROJECTED 0.04% 0.04% 0.04% 0.04% 0.05% 0.04% 0.04% 0.04% 0.01%
2.5 GRAVEL BEDDING 73.60 cu.m P 68,381.76 0.31%
ACTUAL 7 7 9 7 7 7 10 7 7
54.96%
PROJECTED 2.77% 2.77% 3.56% 2.77% 2.77% 2.77% 3.95% 2.77% 2.77%
2.6 HDPE 355mm DIA. W/ ACCESSORIES 112.00 pcs P 5,887,866.88 26.89%
ACTUAL
48.78%
2.7 CONCRETE 5 10
PROJECTED
30.96% 0.03% 0.03%
3.1 STRUCTURE EXCAVATION (Manual) 51.52 cu.m P 12,308.12 0.06%
ACTUAL 27.58% 3 3
TEMPORARY WORKS, PROJECTED 0.212% 0.297% 0.297% 0.297% 0.085% 0.170% 0.127%
99.89% 100.00%
CONSTRUCTION PLANT,
1 1.00 L.S P 325,000.00 1.484%
MOBILIZATION OF CONSTRUCTION
EQUIPMENT & DEMOBILIZATION ACTUAL
2 CANALIZATION 6 10 7 7 7 9 7 7 7 10 7 7 7 9 7 5
93.99%
PROJECTED 0.016% 0.027% 0.019% 0.019% 0.019% 0.024% 0.019% 0.019% 0.019% 0.027% 0.019% 0.019% 0.019% 0.024% 0.019% 0.013%
2.1 COMMON EXCAVATION (Mech.) 571.89 cu.m P 69,701.95 0.318%
ACTUAL 8 6
EMBANKMENT CONSTRUCTION
2.3
AND COMPACTION
5 10 7 7 7 10 7 7 7 9 7 7 7 10 7 7 7 9 7 7 7 10 7 77.72% 7 3
PROJECTED 1.267% 2.534% 1.774% 1.774% 1.774% 2.534% 1.774% 1.774% 1.774% 2.281% 1.774% 1.774% 1.774% 2.534% 1.774% 1.774% 1.774% 2.281% 1.774% 1.774% 1.774% 2.534% 1.774% 1.774% 0.760%
2.3.a HAUL BORROW 13,850.35 cu.m P 10,264,909.90 46.879%
ACTUAL 7 9 7 7 7 10 7 7 7 9 7 5
REINFORCED CONCRETE PILES PROJECTED 1.583% 2.036% 1.583% 1.583% 1.583% 2.262% 1.583% 1.583% 1.583% 2.036% 1.583% 1.131%
2.4 2,160.00 ln.m P 4,408,041.60 20.131%
(0.20mx0.20mx6m)
ACTUAL 7 7 7 7 9 7 7 7 2 67.70%
PROJECTED 0.036% 0.036% 0.036% 0.036% 0.047% 0.036% 0.036% 0.036% 0.010%
2.5 GRAVEL BEDDING 73.60 cu.m P 68,381.76 0.312%
ACTUAL 7 10 7 7 7
60.48%
PROJECTED 4.953% 7.076% 4.953% 4.953% 4.953%
2.6 HDPE 355mm DIA. W/ ACCESSORIES 112.00 pcs P 5,887,866.88 26.889%
ACTUAL 57.21%
2.7 CONCRETE 5 10
53.80%
CLASS A CONCRETE (3000 PSI) PROJECTED 0.049% 0.097%
2.7.a 3.42 cu.m P 31,931.95 0.15%
PLAIN CONCRETE
ACTUAL 49.41%
PROJECTED
34.32% 0.017% 0.017%
3.2 STRUCTURE BACKFILL (MANUAL) 34.29 cu.m P 7,540.37 0.034%
ACTUAL 30.95% 5 2
PROJECTED 0.212% 0.509% 0.810% 1.107% 2.459% 4.993% 6.770% 8.544% 10.334% 12.894% 14.687% 16.480% 19.856% 24.196% 27.572% 30.948% 34.324% 39.183% 42.590% 46.002% 49.410% 53.797% 57.210% 60.479% 67.701% 77.716% 86.060% 93.990% 99.890% 100.00%
CUMULATIVE PHYSICAL ACCOMPLISHMENT (%)
ACTUAL
2 CANAL STRUCTURES
Prop. Cut & Cover Main Canal 2 + 774 2 + 844 70.00 36.27 0.19 #REF! #REF!
Prop. Check & Turn Out Ls Main Canal 3 + 104 0.16 0.40 0.48
Prop. Check & Turn Out Ls Main Canal 3 + 164 0.65 2.14 1.26
Prop. Drainage Crossing Main Canal 3 + 324 #REF! 2.00 #REF! #REF!
Main Canal 3 + 464 3 + 580 116.00 36.08 0.73 69.36 21.42 3.13 1.99
Prop. Elev. Flume comb. TO L/S & R/S
Prop. Cut & Cover Main Canal 3 + 604 3 + 724 120.00 12.09 Err:509
Sub - total = 306.00 84.43 #REF! 2.00 #REF! #REF! #REF! Err:509
3 ROADS
2.63 2.63
TOTAL 129.41 84.43 #REF! #NAME? #NAME? 2.00 #REF! #REF! #REF! Err:509 2.63 2.63
400
14 14
60 60
BEN CH FLUME
EXCAVATION:
BACKFILL:
AREAS
A. 0.14 x 0.35 0.05
0.14 0.14 B. 0.14 x 0.35 0.05
C. 0.12 x 0.40 0.05
0.35 0.15
0.35 A B