You are on page 1of 667

Consultancy Services for preparation of DPR for development of

Economic Corridors, Inter Corridors and Feeder Routes to improve


the efficiency of freight movement in India under Bharatmala
Pariyojana (Lot-1) Package 1A (Bilasipura – Chapar – Tulungia –
Jogighopa – Gendera – Paikan – Dudhnoi – Guwahati Road (Length
225.000 km) in the State of Assam)
FINAL DETAILED PROJECT REPORT

PKG-5: (Ex.Ch.52.470km to Ex.Ch.71.500km)


(Design Ch.48.655km to Ch.67.556)

VOLUME – V : Technical Specification


VOLUME – VI : Rate Analysis
VOLUME – VII: Cost Estimates
VOLUME – VIII : Bill of Quantities

Start point of the project


road

End point of the project


road

Submitted To
National Highways & Infrastructure
Development Corporation Ltd.
PTI Building, 3rd Floor, 4, Parliament Street,
New Delhi-110001

Consultant
C. E. Testing Company Pvt. Ltd.
124-A, NSC Bose Road, Kolkata 700092

CET/4146/NHIDCL-ASSAM/FDPR Rev: R0 MAR, 2020


GENERAL ABSTRACT OF COST
Bilasipara-Jalukbari Road (PKG-5: Km 48.655 to Km 67.556 ) & (km 0.000 km to km1.071)
Length of Road (km) : 18.901
Length of CD & Bridge works (km) : 1.795
Length of Pavement excluding CD works (km) : 17.106

COST PER KM. OF


TOTAL COST % of Total Civil
Sl No DESCRIPTION OF WORKS TOTAL ROAD LENGTH
(IN Cr.) Works Cost
(IN Cr.)

A. ROAD WORKS
1 Site Clearance 1.11 0.06 0.26%
2 Earthwork, Erosion Control 33.82 1.79 8.00%
3 Sub-Base & Base Courses 48.16 2.55 11.40%
4 Bituminous surface 36.28 1.92 8.59%
5 Traffic signs, Road marking & other road appurtenances 8.42 0.45 1.99%
6 Drainage & Protection Works
a) RCC Cover Drain 5.46 0.29 1.29%
b) RE WALL 42.89 2.27 10.15%
c) RR Masonry Chute Drain 0.39 0.02 0.09%
d) Retaining Wall 3.93 0.21 0.93%
e) Toe Wall 2.03 0.11 0.48%
f) Ground Improvement Works (Sand Pile) 7.10 0.38 1.68%
7 Project Facilities
a) Bus Bay with passenger shelter 1.34 0.07 0.32%
8 Junction 1.37 0.07 0.32%
9 Service Road 6.55 0.35 1.55%
10 Utility Duct 4.46 0.24 1.06%
Total for Road Works= 203.31 10.78 48.12%
B. BRIDGES, CULVERTS & ROB
11 Major Bridges 12.58 0.67 2.98%
12 Minor Bridges 52.75 2.79 12.48%
13 ROB 117.29 6.21 27.76%
14 VUP 8.17 0.43 1.93%
15 Culvert 28.43 1.50 6.73%
16 Repairing & Rehabilitation of Bridges 0.004 0.0002 0.00%
Total for Structure Works= 219.22 11.60 51.88%
C. Cost of Civil Works in Cr. 422.53 22.35
Cost Put to the Tender 422.53
D. Maintenance for 5 years , i.e 2.5% on Civil cost ( C ) 10.56
E. GST @ 12% of ( C ) 50.70
F. Contingencies @ 2.8% of (C) 11.83
G. Supervision Consultancy Charges @ 3% of (C) 12.68
H. Agency Charges @ 3% of (C) 12.68

I. Escalation Cost @ 5% on ( C) during Construction Period(For 1 Years) 21.13

J. Total Centages and contigencies/GST ( J= D+E+F+G+H+I ) 119.58 6.33


Departmental Cost
a. LA Cost for Construction 45.73
b. Compensation for structures 25.17
c. Utility Shifting Cost 5.70
d. Environmental Mitigation Cost 1.54
K. Total Departmental Cost(K=a+b+c+d) 78.14
L. Total Capital Cost/(L=C+J+K) 620.25 32.82
Volume-V: Technical Specification
Consultancy Services for preparation of DPR for development of Final Detailed Project Report
Economic Corridors, Inter Corridors and Feeder Routes to improve the Technical Specification
efficiency of freight movement in India under Bharatmala Pariyojana
(Lot-1) Package 1A(Bilasipura-Chapar-Tulungia-Jogighopa-
Gendera-Paikan-Dudhnoi-Guwahati Road (Length 225.000 km),
PKG-5(Ex.Ch.52.470km to Ex.Ch.71.500km),(Design
Ch.48.655km to Ch.67.556km), in the State of Assam

Technical Specification
1.1 General

The Technical specifications covering the materials and the workmanship aspects as well as method of
measurements and payments are included in this section. These specifications cover the items of civil
and non-civil works coming under scope of this document. All work shall be carried out in conformity
with the same. The works shall be executed in accordance with good practices followed for achieving
high standards of workmanship, thus ensuring safety and durability of the construction. All codes and
standards referred to in these specifications shall be the latest thereof unless otherwise stated.

1.1.1. Inclusive Documents

The provisions of special conditions of contract, those specified elsewhere in the tender document, as
well as execution drawings and notes, or other specifications issued in writing by the Engineer shall form
part of the technical specifications of this project.

The attention of the contractor is drawn to those clauses of codes which require supporting
specification either by the Engineer or by 'Mutual agreement between the supplier and purchaser'. In
such cases, it is the responsibility of the tenderer /contractor to seek clarification on any uncertainty
and obtain prior approval of the Engineer before taking up the supply/construction. In absence of such
prior clarification, the Engineer's choice/design will be final and binding on the contractor without
involving separately any additional payment.

1.1.2. Defective Works

All defective works are liable to be demolished, rebuilt and defective materials replaced by the
contractor at his own cost. In the event of such works being accepted by carrying out repairs etc. as
specified by the Engineer the cost of repairs will be borne by the contractor.

1.2 Site Information

The information given hereunder and provided elsewhere in these documents is given in good faith by
the Employer but the Contractor shall satisfy himself regarding all aspects of site conditions and no
claim will be entertained on the plea that the information supplied by the Employer is erroneous or
insufficient.

1.2.1 Location

The area in which the works are located is mostly Plain terrain.

The Project Road starts at Beltoli (junction with SH-5) near Bilasipara road Passes through
village / localities namely Bilasipara, Gourang Nagar, Chirakuthi, Sonamukhi, Koliarkhal,
Tilapara, MohishBathan, Salkocha, Hatipota, Dhirghat, Arayarjhar, KharidaGossaigaon,
Chapar, Bahalpur, Nitya Bazar, KayetPipeara, Talguri, Salbari, Besimari, Boitamari, Borkhata
(Nolbari), Khagarpur, Uttar Salmara, Tulungia (junction with NH-117), Deohati, Choutaki,
Singimari, Nalipara, Kherkabari, Katashbari, Khoragaon, Garaimari, Chalantapara,
KabaitaryTinali, Oudubi, Jogighopa, Kharbhuja, Makri, Dakurivitha, Hadalpara, Kalyanpur,

Doc No: CET/4146/NHIDCL/Assam/FDPR Revision: R0 March 2020 Page:1


Consultancy Services for preparation of DPR for development of Final Detailed Project Report
Economic Corridors, Inter Corridors and Feeder Routes to improve Technical Specification
the efficiency of freight movement in India under Bharatmala
Pariyojana (Lot-1) Package 1A(Bilasipura-Chapar-Tulungia-
Jogighopa-Gendera-Paikan-Dudhnoi-Guwahati Road
(Length 225.000 km), PKG-5(Ex.Ch.52.470km to
Ex.Ch.71.500km),(Design Ch.48.655km to Ch.67.556km),
in the State of Assam

Solmari, Gendra, Balijan, Budhipara, Agia, Ulupara, AgiaPaharkata, KalpaniChandmari,


Bolbolla, Phaphanga, Godhar Bari, TukuraBormahara, Bhimajuli, Paikan, Krishnai, Jyoti
Nagar, MolanDubi, Beki Paul, Salpara, Darapara, Dabli, Letheng, Lela, Mondal gram,
Makhipara, Dudhnoi, Fafal, Puranibitha, Amjonga, Kachadal, Darangiri, Dosimapara,
Rangjuli, Dhanubhanga, Deoshila, Gathiapara, Kothakuthi, Dhupdhara, Sakite, Hakite,
Bandapara, Kukurmara, Rajapara, Dhupguri, Chukunai Para, Burgrui, Singra, BokoNagopara,
ChakBaho, BokoJarapara, BokoDakhurpara, Boko, Barpara, Turukpur, Turukpara,
AguckaBoko, lampara, Bripara, Bongaon market, Bamunigaon, Khabibe, Gobardhan, Kumi,
Chhaygaon, Champak Nagar, Kharavanga, Kukurmara, Bartezpur, Surutezpur, Rampur,
Bhagabatipara, Rajapokubi, Batarhat, Haligaon, Bijoynagar, Uparhali, Sarpara, Mirza,
Barkuchi, Sontola, Bongara, Khuikuchi, Bullapara, VIP chok, Kahikuchi, Azara,
Lankeswarandends at Jalukbari Interchange in Guwahati in the state of Assam. Existing
length of the project road is 215.578 Km and Design length is 214.520 Km. The entire
project road is divided in 16(sixteen) packages.

The PKG-5 of the project road starts from Tulungia(Junction with NH-117) and ends ater
Jogighopa Bridge (Ex.Ch.52.470km to Ex.Ch.71.500km). Design length of the PKG-5 comes
out as 18.901 km (Design Ch.48.655km to Ch.67.556km).The entire package falls under
Bongaigaon district of Assam.
1.2.2 General Climatic Conditions
As the Brahmaputra flows in Assam the climate here is cold and there is rainfall most of the month.
Geomorphic studies conclude that the Brahmaputra, the life-line of Assam is an antecedent river, older
than the Himalayas. 35 and 38 degree Celsius in Summer & around 6 to 8 degree Celsius in Winter.
Rainfall 2,818 mm average.

1.2.3 Seismic Zone


The works are located in Seismic Zone V as defined in IRC: 6-2000.

2. GENERAL REQUIREMENTS
The Technical Specifications in accordance with which the entire work described hereinafter shall be
constructed and completed by the Contractor shall comprise of the following:

2.2 PART-I: General Technical Specifications

The General Technical Specifications shall be the "SPECIFICATIONS FOR ROAD AND BRIDGE WORKS
(FIFTH REVISION, April 2013)”, issued by the Ministry of Road Transport & Highways, Government of
India and published by the Indian Roads Congress (IRC), with a cross reference to relevant Bureau of
Indian Standards (BIS) for materials or other aspects not covered by the IRC.

2.3 Additional Technical Specifications

The Additional Specifications shall comprise of specifications for particular item of works not already
covered in PART-I.

2.2.6. Additional Specifications

The following Appendices have been added to the “SPECIFICATIONS FOR ROAD AND BRIDGE WORKS”
(FIFTH REVISION, April 20013).

Doc No: CET/4146/NHIDCL/Assam/FDPR Revision: R0 March 2020 Page:2


Consultancy Services for preparation of DPR for development of Final Detailed Project Report
Economic Corridors, Inter Corridors and Feeder Routes to improve the Technical Specification
efficiency of freight movement in India under Bharatmala Pariyojana
(Lot-1) Package 1A(Bilasipura-Chapar-Tulungia-Jogighopa-
Gendera-Paikan-Dudhnoi-Guwahati Road (Length 225.000 km),
PKG-5(Ex.Ch.52.470km to Ex.Ch.71.500km),(Design
Ch.48.655km to Ch.67.556km), in the State of Assam

3. Appendix A-1 Specification for Passenger Shelter


4. Appendix A-2 Painting on Structures with Synthetic Enamel paints for Numbering & Span
Details of Bridges / Culverts and water Proof Cement Paint for Parapet,
Railing Kerb and Crash Barrier

ADDITIONAL TECHNICAL SPECIFICATION

Appendix A-1 :: SPECIFICATION FOR PASSENGER SHELTER

1. Scope

The work consists of providing passenger shelter including seating arrangement as per drawing.

2. Description

2.1 Passenger Shelter

It will be a permanent structure supported on R.C. columns at the corners and having sloped reinforced
concrete slab with protrusions on all sides. Panel walls on three sides shall be built with brick jail of
125mm thick set in cement mortar 1:4 (1 part cement : 4 parts sand). It shall have seating arrangement
with 100mm thick R.C. slab with raised back with atleast 1.5% reinforcement. The mix of concrete for
seating slab and back shall be nominal one with 1:2:4 (1 part cement : 2 parts sand : 4 parts stone chips)
and it will be finished with neat cement punning not less than 3mm thickness. The flooring shall be with
25mm thick I.P.S. flooring (1:2:4) over 100mm thick M-10 grade concrete. All walls, ceiling and roof top
shall be finished with cement mortar (1:4). The exposed surfaces of the structure shall be painted with
two coats of cement based paint of make and brand approved by the Engineer.

2.2 Raised Footpath

Raised footpath shall be constructed with one layer of Paver block laid over 100mm thick M-10
concrete. The joints of top layer of soling shall be filled up with cement mortar (1:3).

All works shall be done as per drawings.

3.0 Measurement for Payment

The passenger shelter shall be measured in number of finished constructed structure.

4.0 Rate

The Contract unit rate shall be payment in full for construction of the passenger shelter. Raised
footpath, ground preparation etc. shall be considered as incidental to work.

Doc No: CET/4146/NHIDCL/Assam/FDPR Revision: R0 March 2020 Page:3


Consultancy Services for preparation of DPR for development of Final Detailed Project Report
Economic Corridors, Inter Corridors and Feeder Routes to improve Technical Specification
the efficiency of freight movement in India under Bharatmala
Pariyojana (Lot-1) Package 1A(Bilasipura-Chapar-Tulungia-
Jogighopa-Gendera-Paikan-Dudhnoi-Guwahati Road
(Length 225.000 km), PKG-5(Ex.Ch.52.470km to
Ex.Ch.71.500km),(Design Ch.48.655km to Ch.67.556km),
in the State of Assam

Appendix A-2:: PAINTING OF STRUCTURES WITH SYNTHETIC ENAMEL PAINT FOR NUMBERING & SPAN DETAILS
OF BRIGES / CULVERTS AND WATER PROOF CEMENT PAINT FOR PARAPET, RAILING, KERB AND CRASH
BARRIER

1. Painting with Synthetic Enamel Paint

Materials

Synthetic enamel paint confirming to IS : 2932 of approved brand and manufacture and of the required
colour shall be used for the top coat and an undercoat of ordinary paint of shade to match the top coat as
recommended by the same manufacturer as far as top coat shall be used.

Painting on New Surface

Preparation of surface:

The surface shall be thoroughly cleaned and dusted off. All dirt, mortar droppings and grease shall be
thoroughly removed before painting is started. The prepared surface shall have received the approval of
the Engineer after inspection , before painting is commenced..

Application: The number of coats including the undercoat shall be as stipulated in the item.

(a) Under coat: One coat of the specified ordinary paint of shade suited to the shade of the top coat, shall
be applied and allowed to dry overnight. It shall be rubbed next day with the finest grade of wet
abrasive paper to ensure a smooth and even surface, free from brush marks and all loose particles
dusted off.

(b) Top Coat: Two top coats of synthetic enamel paint of desired shade shall be applied after the
undercoat is thoroughly dry. Additional finishing coats shall be applied if found necessary to ensure
properly uniform glossy surface.

Lettering and Numbering on New Surface:

The letters and numbers for bridges/culverts span and number shall be as per IRC-7-1971. The size of area
for painting shall be varied depend upon the numbers and letters. The background area and
letters/numbers shall be painted with one prime coat (under coat) and two coats (top coat) of synthetic
enamel paint.

Measurement for payment:

The painting of culverts /Bridges numbering and span arrangement shall be measured in number of each
side facing traffic.

Rate:

Rate shall include the cost of materials, labour and other operation described above to complete set of
letters and numbers required in each side facing traffic.

2. Water Proof Cement Painting

Material:

Doc No: CET/4146/NHIDCL/Assam/FDPR Revision: R0 March 2020 Page:4


Consultancy Services for preparation of DPR for development of Final Detailed Project Report
Economic Corridors, Inter Corridors and Feeder Routes to improve the Technical Specification
efficiency of freight movement in India under Bharatmala Pariyojana
(Lot-1) Package 1A(Bilasipura-Chapar-Tulungia-Jogighopa-
Gendera-Paikan-Dudhnoi-Guwahati Road (Length 225.000 km),
PKG-5(Ex.Ch.52.470km to Ex.Ch.71.500km),(Design
Ch.48.655km to Ch.67.556km), in the State of Assam

The water proof cement paint shall be (conforming to IS: 5410) of approved brand and manufacture.

The water cement paint shall be brought to the site of work by the contractor in its original container in
sealed condition. The material shall be brought in at a time in adequate to suffice for the whole work or
at least a fortnight’s work, the material be kept in the joint custody of the Contractor and the Engineer-
in-Charge. The empties shall not be removed from the site of work till the relevant item of the work has
been completed and permission obtained from the Engineer-in-Charge.

Preparation of Surface:

For New work, the surface shall be thoroughly cleaned of all mortar dropping, dirt, dust, algae, grease
and other foreign matter by brushing and washing. Pitting in plaster shall be made good and a coat of
waterproof cement paint shall be applied over patches after wetting them thoroughly.

Preparation of mix:

Cement paint shall be mixed in such quantities as can be used up within an hour of its mixing as
otherwise the mixture will set and thicken, affecting flow and finish, Cement paint shall be mixed with
water in two stages. The first stage shall comprise of 2 parts of cement paint and one part of water
stirred thoroughly and allowed to stand for 5 minutes. Care shall be taken to add the cement paint
gradually to the water and not vice versa. The second stage shall comprise of adding further one part of
water to the mix and stirring thoroughly to obtain a liquid of workable and uniform consistency. In all
cases the manufacturer’s instructions shall be followed meticulously.

The lids of cement paint drums shall be kept tightly closed when not in use, as by exposure to
atmosphere the cement paint rapidly becomes air set due to its hygroscopic qualities.

In case of cement paint brought in gunny bags, once the bag is opened, the contents should be
consumed in full on the day of its opening. If the same is not likely to be consumed in full, the balance
quantity should be transferred and preserved in an airtight container to avoid its exposure to
atmosphere.

Application:

The solution shall be applied on the clean and wetted surface with brushes or spraying machine. The
solution shall be kept well stirred during the period of application. It shall be applied on the surface
which is on the shady side of the building so that the direct heat of the sun on the surface is avoided.
The method of application of cement paint shall be as per manufacturer’s specification. The completed
surface shall be watered after the day’s work.

The second coat shall be applied after the first coat has been set for at least 24 hours. Before application
of the second or subsequent coats, the surface of the previous coat shall not be wetted.

For the work, the surface shall be treated with three or more coat of waterproof cement paint as found
necessary to get a uniform shade.

For old work, the treatment shall be with one or more coats as found necessary to get a uniform shade.

Precaution:

Doc No: CET/4146/NHIDCL/Assam/FDPR Revision: R0 March 2020 Page:5


Consultancy Services for preparation of DPR for development of Final Detailed Project Report
Economic Corridors, Inter Corridors and Feeder Routes to improve Technical Specification
the efficiency of freight movement in India under Bharatmala
Pariyojana (Lot-1) Package 1A(Bilasipura-Chapar-Tulungia-
Jogighopa-Gendera-Paikan-Dudhnoi-Guwahati Road
(Length 225.000 km), PKG-5(Ex.Ch.52.470km to
Ex.Ch.71.500km),(Design Ch.48.655km to Ch.67.556km),
in the State of Assam

Water proof cement paint shall not be applied on surfaces already treated with white wash, colour
wash, distemper dry or oil bound, varnishes, paints, etc. It shall not be applied on gypsums, wood and
metal surfaces.

If water proof cement paint is required to be applied on existing surfaces previously treated with white
wash, colour wash, etc., the surface shall be thoroughly cleaned by scrapping off all the white wash,
colour was etc., completely. Thereafter, a coat of cement primer shall be applied followed by two or
more coats of water proof cement paint.

Measurement for Payment:

The painting shall be measured in square metre of surface area treated.

Rate:

Rate shall include one prime coat and two coats of the paint over the prime coat including cost of all
labour and materials involved in all operations described above.

Doc No: CET/4146/NHIDCL/Assam/FDPR Revision: R0 March 2020 Page:6


Volume-VI: Rate Analysis
Input
INPUT
(A) Usage Rates of Plant and Machinery
Output of
Sl. No. Description of Machine Activity Output Unit Rate
Machine

P&M-001 Air Compressor General Purpose capacity in cfm 170/250 hour 334

Batching and Mixing Plant (a) 30 cum


P&M-002 Concrete Mixing cum/hour 20 hour 2302
capacity
Batching and Mixing Plant (b) 15 - 20
P&M-003 Concrete Mixing cum/hour 13 hour 1870
cum capacity
P&M-004 Bitumen Pressure Distributor Applying bitumen tack coat sqm/hour 1750 hour 1122

P&M-005 Bitumen Boiler oil fired Bitumen Spraying capacity in litre 1500 hour 209

Concrete Paver Finisher with 40 HP


P&M-006 Paving of concrete surface cum / hour 20 hour 2935
Motor

P&M-007 Concrete Pump of 45 & 30 cum capacity Pumping of concrete cum / hour 33 / 22 hour 275

P&M-008 Concrete Bucket For Pouring concrete capacity in cum 1 hour 18

P&M-009 Concrete Mixer (a) 0.4/0.28 cum Concrete Mixing cum/hour 2.5 hour 238
P&M-010 Concrete Mixer (b) 1 cum Concrete Mixing cum/hour 7.5 hour 238
P&M-011 Crane (a) 80 tonnes Lifting Purpose hour 1336
P&M-012 Cranes b) 35 tonnes Lifting Purpose hour 893
P&M-013 Cranes c) 3 tonnes Lifting Purpose hour 374
300/
P&M-014 Dozer D - 80 - A 12 Spreading /Cutting / Clearing cum/hour hour 3757
150/250
200/
P&M-015 Dozer D - 50 - A 15 Spreading /Cutting / Clearing cum/hour hour 2311
120/150

P&M-016 Emulsion Pressure Distributor Applying emulsion tack coat sqm/hour 1750 hour 843

P&M-017 Front End loader 1 cum bucket capacity Soil loading / Aggregate loading cum/hour 60 /25 hour 803

P&M-018 Generator (a) 125 KVA Genration of electric Energy KVA 100 hour 980

P&M-019 Generator( b) 63 KVA Genration of electric Energy KVA 50 hour 605

P&M-020 GSB Plant 50 cum Producing GSB cum/hour 40 hour 1341


P&M-021 Hotmix Plant - 120 TPH capacity DBM/BM/SDC/ Premix cum/hour 40 hour 26844
P&M-022 Hotmix Plant - 100 TPH capacity DBM/BM/SDC/ Premix cum/hour 30 hour 19496
P&M-023 Hotmix Plant - 60 to 90 TPH capacity DBM/BM/SDC/ Premix cum/hour 25 hour 16602
P&M-024 Hotmix Plant - 40 to 60 TPH capacity DBM/BM/SDC/ Premix cum/hour 17 hour 14560
P&M-025 Hydraulic Chip Spreader Surface Dressing sqm/hour 1500 hour 2799
Soil Ordinary/Soil Marshy / Soil 60 /60
P&M-026 Hydraulic Excavator of 1 cum bucket cum/hour hour 1622
Unsuitable /60
P&M-027 Integrated Stone Crusher 100THP Crushing of Spalls TPH 100 hour 8492
P&M-028 Integrated Stone Crusher 200 HP Crushing of Spalls TPH 200 hour 16924
P&M-029 Kerb Casting Machine Rm/hour 80 hour 334
capacity in
P&M-030 Mastic Cooker Mastic Wearing coat 1 hour 66
tonne
P&M-031 Mechanical Broom Hydraulic Surface Cleaning sqm/hour 1250 hour 396
200/200/
P&M-032 Motor Grader 3.35 mtr blade Clearing /Spreading /GSB /WBM cum/hour hour 2628
50/50
P&M-033 Mobile slurry seal equipment Mixing and laying slurry seal sqm/hour 2700 hour 2437
Paver Finisher Hydrostatic with sensor
P&M-034 Paving of DBM/ BM/SDC/ Premix cum/hour 40 hour 2753
control 100 TPH

P&M-035 Paver Finisher Mechanical 100 TPH Paving of WMM /Paving of DLC cum/hour 40/30 hour 1003

0.75 m dia to 1.2 m dia Boring


P&M-036 Piling Rig with Bantonite Pump Rm/hour 2 to 3 hour 5487
attachment
P&M-037 Pneumatic Road Roller Rolling of Asphalt Surface cum/hour 25 hour 1337
1.5 to
P&M-038 Pneumatic Sinking Plant Pneumatic Sinking of wells cum/hour hour 4061
2.00
P&M-039 Pot Hole Repair Machine Repair of potholes cum/hour 4 hour 1040

P&M-040 Prestressing Jack with Pump & access Stressing of steel wires/stands hour 133

P&M-041 Ripper Scarifying cum/hour 60 hour 36

P&M-042 Rotavator Scarifying cum/hour 25 hour 26

P&M-043 Road marking machine Road marking Sqm/hour 100 hour 124

P&M-044 Smooth Wheeled Roller 8 tonne Soil Compaction /BM Compaction cum/hour 70/25 hour 676

P&M-045 Tandem Road Roller Rolling of Aspalt Surface cum/hour 30 hour 1222
Transportation of soil, GSB,
P&M-046 Tipper - 5 cum Capacity in cum 5.5 km 470
WMM, Hotmix etc.
Transportation of soil, GSB,
P&M-047 Tipper - 5 cum Capacity in cum 5.5 tonne.km 71
WMM, Hotmix etc.
Transportation of soil, GSB,
P&M-048 Tipper - 5 cum Capacity in cum 5.5 hour 492
WMM, Hotmix etc.
Transportation of Concrete Mix to
P&M-049 Transit Mixer 4.0/4.5 cum cum/hour 4.5 hour 974
site
Transportation of Concrete Mix to
P&M-050 Transit Mixer 4/4.5 cum cum/hour 4.5 tonne.km 47
site
Transportation of Concrete Mix to
P&M-051 Transit Mixer 3.0 cum cum/hour 3 hour 893
site
Transportation of Concrete Mix to
P&M-052 Transit Mixer 3.0 cum cum/hour 3 tonne.km 41
site
P&M-053 Tractor Pulling capacity in HP 50 hour 380
P&M-054 Tractor with Rotevator Rate of Tractor + Rotevator hour 507
P&M-055 Tractor with Ripper Rate of Tractor 6+ Ripper hour 518
P&M-056 Truck 5.5 cum per 10 tonnes Material Transport capacity/cum 4.5 km 382
P&M-057 Truck 5.5 cum per 10 tonnes Material Transport capacity/cum 4.5 hour 518
P&M-058 Truck 5.5 cum per 10 tonnes Material Transport capacity/cum 4.5 tonne.km 4
100/60/6
P&M-059 Vibratory Roller 8 tonne Earth or soil / GSB / WBM cum/hour hour 1671
0
P&M-060 Water Tanker Water Transport capacity in KL 6 hour 518
P&M-061 Water Tanker Water Transport capacity in KL 6 km 21
P&M-062 Wet Mix Plant 60 TPH Wet Mix cum/hour 25 hour 1351
Sl. No. Description of Machine Unit 0

P&M-063 Air compressor with pneumatic chisel attachment for cutting hard clay. hour 334

P&M-064 Batch type cold mixing plant 100-120 TPH capacity producing an average output of 75 tonne per hour hour 2352

P&M-065 Belt conveyor system hour 2470


P&M-066 Boat to carry atleast 20 persons hour 235
P&M-067 Cement concrete batch mix plant @ 175 cum per hour (effective output) hour 6150
P&M-068 Cement concrete batch mix plant @ 75 cum per hour hour 4705
P&M-069 Cold milling machine @ 20 cum per hour hour 806
P&M-070 Crane 5 tonne capacity hour 806
P&M-071 Crane 10 tonne capacity hour 882
P&M-072 Crane 15 tonne capacity hour 912
P&M-073 Crane 20 tonne capacity hour 941
P&M-074 Crane 40 T capacity hour 994
P&M-075 Crane with grab 0.75 cum capacity hour 1394
P&M-076 Compressor with guniting equipment along with accessories hour 470
P&M-077 Drum mix plant for cold mixes of appropriate capacity but not less than 75 tonnes/hour. hour 2187
P&M-078 Epoxy Injection gun hour 353
P&M-079 Generator 33 KVA hour 366
P&M-080 Generator 100 KVA hour 730
P&M-081 Generator 250 KVA hour 1764
Induction, deinduction and erection of plant and equipment including all components and accessories
P&M-082 hour 4061
for pneumatic method of well sinking.
P&M-083 Joint Cutting Machine with 2-3 blades (for rigid pavement) hour 176
P&M-084 Jack for Lifting 40 tonne lifting capacity. day 235
P&M-085 Piling rig Including double acting pile driving hammer (Hydraulic rig) hrs 1176
P&M-086 Plate compactor hour 256
P&M-087 Snow blower equipment 140 HP @ 600 cum per hour hour 1176
P&M-088 Texturing machine (for rigid pavement) hour 941
P&M-089 Truck Trailor 30 tonne capacity hour 588
P&M-090 Vibrating Pile driving hammer complete with power unit and accessories. hour 1000
P&M-091 Wet Mix Plant 100 TPH hour 1967
P&M-092 Wet Mix Plant 75 TPH hour 1591
(B) Labour

Sl. No. Description of Labour Unit Rate

L-01 Blacksmith (IInd class) day 318

L-02 Blacksmith (Ist class)/ Welder/ Plumber/ Electrician day 353

L-03 Blaster (Stone cutter) day 353

L-04 Carpenter I Class day 353

L-05 Chiseller (Head Mazdoor) day 294

L-06 Driller (Jumper) day 294

L-07 Diver day 294

L-08 Fitter day 235

L-09 Mali day 235

L-10 Mason (IInd class) day 294

L-11 Mason (Ist class) day 353

L-12 Mate / Supervisor day 329

L-13 Mazdoor day 153

L-14 Mazdoor/Dresser (Semi Skilled) day 176

L-15 Mazdoor/Dresser/Sinker (Skilled) day 245

L-16 Medical Officer day 765

L-17 Operator(grouting) day 318

L-18 Painter I class day 353

L-19 Para medical personnel day 353


(C) Materials

Sl. No. Description Unit Rate

M-001 Stone Boulder of size 150 mm and below at Cruser Plant cum 1001

M-002 Supply of quarried stone 150 - 200 mm size for Hand Broken at site cum 882

M-003 Boulder with minimum size of 300 mm for Pitching at site cum 859

M-004 Coarse sand at Mixing Plant cum 1176

M-005 Coarse sand at Site cum 1176

M-006 Fine sand at Site cum 1294

M-007 Moorum at Site cum 687

M-008 Gravel/Quarry spall at Site Cum 970

M-009 Granular Material or hard murrum for GSB works at Site Cum 979

M-010 Granular Material or hard murrum for GSB works at Mixing Plant Cum 979

M-011 Fly ash conforming to IS: 3812 ( Part II & I) at HMP Plant/Batching Plant/ Crushing Plant Cum 1097

M-012 Filter media/Filter Material as per Table 300-3 (MoRT&H Specification) Cum 1191
Rate at
Rate at Quarry
Description Unit Plant (HMP
Site
/ Batching)
M-013 Close graded Granular sub-base Material 53 mm to 9.5 mm cum 1449 1449

M-014 Close graded Granular sub-base Material 37.5 mm to 9.5 mm cum 1567 1567

M-015 Close graded Granular sub-base Material 26.5 mm to 9.5 mm cum 1681 1681

M-016 Close graded Granular sub-base Material 9.5 mm to 4.75 mm cum 1681 1681

M-017 Close graded Granular sub-base Material 9.5 mm to 2.36 mm cum 1681 1681

M-018 Close graded Granular sub-base Material 4.75mm to 2.36 mm cum 1681 1681

M-019 Close graded Granular sub-base Material 4.75mm to 75 micron mm cum 1681 1681

M-020 Close graded Granular sub-base Material 2.36 mm cum 897 897

M-021 Stone crusher dust finer than 3mm with not more than 10% passing 0.075 sieve. cum 470 470

M-022 Coarse graded Granular sub-base Material 2.36 mm & below cum 861 861

M-023 Coarse graded Granular sub-base Material 4.75mm to 75 micron mm cum 1244 1244

M-024 Coarse graded Granular sub-base Material 4.75 mm to 2.36 mm cum 1567 1567

M-025 Coarse graded Granular sub-base Material 9.5 mm to 4.75 mm cum 1685 1685

M-026 Coarse graded Granular sub-base Material 26.5 mm to 4.75 mm cum 1661 1661

M-027 Coarse graded Granular sub-base Material 26.5 mm to 9.5 mm cum 1673 1673

M-028 Coarse graded Granular sub-base Material 37.5 mm to 9.5 mm cum 1508 1508

M-029 Coarse graded Granular sub-base Material 53 mm to 26 .5 mm cum 1402 1402

M-030 Aggregates below 5.6 mm cum 1411 1411

M-031 Aggregates 22.4 mm to 2.36 mm cum 1529 1529


M-032 Aggregates 22.4 mm to 5.6 mm cum 1529 1529
M-033 Aggregates 45 mm to 2.8 mm cum 1600 1600
M-034 Aggregates 45 mm to 22.4 mm cum 1588 1588
M-035 Aggregates 53 mm to 2.8 mm cum 1600 1600
M-036 Aggregates 53 mm to 22.4 mm cum 1529 1529
M-037 Aggregates 63 mm to 2.8 mm cum 1529 1529
M-038 Aggregates 63 mm to 45 mm cum 1470 1470
M-039 Aggregates 90 mm to 45 mm cum 1411 1411
M-040 Aggregates 10 mm to 5 mm cum 1529 1529
M-041 Aggregates 11.2 mm to 0.09 mm cum 1529 1529
M-042 Aggregates 13.2 mm to 0.09 mm cum 1588 1588
M-043 Aggregates 13.2 mm to 5.6 mm cum 1588 1588
M-044 Aggregates 13.2 mm to 10 mm cum 1588 1588
M-045 Aggregates 20 mm to 10 mm cum 1529 1529
M-046 Aggregates 25 mm to 10 mm cum 1411 1411
M-047 Aggregates 19 mm to 6 mm cum 1529 1529
M-048 Aggregates 37.5 mm to 19 mm cum 1529 1529
M-049 Aggregates 37.5 mm to 25 mm cum 1529 1529
M-050 Aggregates 6 mm nominal size cum 1411 1411
M-051 Aggregates 10 mm nominal size cum 1529 1529
M-052 Aggregates 13.2/12.5 mm nominal size cum 1588 1588
M-053 Aggregates 20 mm nominal size cum 1529 1529
M-054 Aggregates 25 mm nominal size cum 1470 1470
M-055 Aggregates 40 mm nominal size cum 1411 1411

Sl. No. Description Unit Rate

M-056 G.I. pipe 100 mm dia metre 1210


M-057 Acrylic polymer bonding coat litre 321
M-058 Alluminium Paint as per market rate litre 346
M-059 Aluminium alloy plate 2mm Thick as per market rate sqm 506
M-060 Aluminium alloy/galvanised steel as per market rate tonne 96331
Aluminium sheeting fixed with encapsulated lens type reflective sheeting including 2% towards
M-061 lettering, cost of angle iron, cost of drilling holes, nuts, bolts etc.and signs as applicable as per market sqm 618
rate
M-062 Aluminium studs 100 x 100 mm fitted with lense reflectors nos 515
M-062 Barbed wire as per market rate kg 99
M-063 Bearing (Cost of parts) as per market rate nos 141144
M-064 Bearing (Cast steel rocker bearing assembly of 250 tonne ) as per market rate nos 209952
Bearing (Elastomeric bearing assembly consisting of 7 internal layers of elastomer bonded to 6 nos.
M-065 nos 16937
internal reinforcing steel laminates by the process of vulcanisation,)as per market rate
M-066 Bearing (Forged steel roller bearing of 250 tonne)as per market rate nos 262440

Bearing (Pot type bearing assembly consisting of a metal piston supported by a disc, PTFE pads
M-067 providing sliding surfaces against stainless steel mating together with cast steel assemblies/fabricated nos 81511
structural steel assemblies duly painted with all components as per market rate

M-068 Bearing (PTFE sliding plate bearing assembly of 80 tonnes )as per market rate nos 21078
M-069 Bearing (Supply of sliding plate bearing of 80 tonne)as per market rate nos 14781
M-070 Bentonite as per market rate kg 19
M-071 Binding wire kg 93

M-073 Bitumen (VG-40 Grade) - Bongaigaon tonne 40000.00

M-074 Bitumen (VG-40 Grade) - Bongaigaon tonne 40000.00


M-076 Bitumen (emulsion) - Bongaigaon tonne 33000.00
M-077 Bitumen (VG-40 Grade) - Bongaigaon tonne 40000.00
M-084 Brick as per market rate each 8
M-085 C.I.shoes for the pile kg 99
M-086 Cement as per market rate tonne 8939
M-087 TMT bars (HYSD Bars) average rate tonne 44000.00
M-090 Coller for joints 300 mm dia as per market rate nos 692
M-091 Compressible Fibre Board(20mm thick) sqm 1976
M-092 Connectors/ Staples as per market rate each 87
M-093 Copper Plate(12m long x 250mmwide) kg 315
M-094 Corrosion resistant Structural steel as per market rate tonne 65209
M-095 Corrugated sheet, 3 mm thick, "Thrie" beam section railing as per market rate kg 99
M-096 Credit for excavated rock found suitable for use as per market rate cum 371
M-097 Curing compound as per market rate litre 371
M-091 Delineators from ISI certified firm as per the standard drawing given in IRC - 79 each 957
M-098 Earth Cost or compensation for earth taken from private land as per market rate cum 49
Elastomeric slab seal expansion joint assembly manufactured by using chloroprene, elastomer for
M-099 metre 16673
elastomeric slab unit conforming to clause 915.1 of IRC: 83 (part II), as per market rate
M-100 Electric Detonators @ 1 detonator for 1/2 gelatin stick of 125 gms each 100 nos 461
M-102 Epoxy compound with accessories for preparing epoxy mortar kg 957
M-103 Epoxy mortar kg 679
M-104 Epoxy primer as per market rate kg 618
M-101 Epoxy resin-hardner mix for prime coat kg 1328
M-105 Flag of red color cloth 600 x 600 mm as per market rate each 22
M-106 Flowering Plants as per market rate each 68
M-107 Galvanised MS flat clamp as per market rate nos 494
Galvanised steel wire crates of mesh size 100 mm x 100 mm woven with 4mm dia. GI wire in rolls of
M-108 sqm 355
required size as per market rate
M-109 Galvanised structural steel plate 200 mm wide, 6 mm thick, 24 m long as per market rate kg 111
M-110 Gelatin 80% kg 132
M-111 Geo grids(TGB-40) as per market rate sqm 279
M-112 Geomembrane(1.5mm thick) as per market rate sqm 389
M-113 Geonets(Geonet 121) as per market rate sqm 362
M-114 Geotextile(GNW-280) as per market rate sqm 135
M-115 Geotextile filter fabric(GNW-280) as per market rate sqm 158
M-116 GI bolt 10 mm Dia nos 15
M-117 Grouting pump with agitator as per market rate hour 420
M-118 Grass (Doob) as per market rate kg 27
M-119 Grass (Fine) as per market rate kg 37
M-120 HDPE pipes 75mm dia metre 222
M-121 HDPE pipes 90mm dia metre 272
M-122 Hedge plants as per market rate each 15
M-123 Helical pipes 600mm diameter as per market rate metre 173
M-124 Hot applied thermoplastic compound as per market rate litre 159
M-125 HTS strand tonne 148201
M-126 Joint Sealant Compound as per market rate kg 722
M-127 Jute netting, open weave, 2.5 cm square opening for seeding and Mulching as per market rate sqm 33
M-128 LDO for steam curing litre 43
M-129 M.S. Clamps nos 31
M-130 M.S. Clamps kg 71
M-131 M.S.shoes @ 35 Kg per pile of 15 m kg 77
M-132 Mild Steel bars as per market rate tonne 56458
Modular strip/box seal expansion joint including anchorage catering to a horizontal movement beyond
M-133 70 mm and upto 140mm assembly comprising of edge beams, central beam,2 modules chloroprene metre 166726
seal, anchorage elements, support and control system, all steel
Modular strip/box seal expansion joint catering to a horizontal movement beyond 140mm and upto
M-134 210mm box/box seal joint assembly containing 3 modules/cells and comprising of edge beams, two metre 221390
central beams, chloroprene seal, anchorage elements, support and
M-135 Nipples 12mm nos 34
M-136 Nuts and bolts as per market rate kg 88
M-137 Paint as per market rate litre 185
M-138 Pavement Marking Paint as per market rate litre 173
M-139 Paving Fabric(1.5mm thick) as per market rate sqm 370
M-140 Perforated geosynthetic pipe 150 mm dia as per market rate metre 524
M-141 Perforated pipe of cement concrete, internal dia 100 mm as per market rate metre 149
M-142 Pesticide as per market rate kg 395
M-143 Pipes 200 mm dia, 2.5 m long for drainage as per market rate metre 987
M-144 Plastic sheath, 1.25 mm thick for dowel bars as per market rate sqm 43
M-145 Plastic tubes 50 cm dia, 1.2 m high as per market rate nos 93
M-146 Polymer braids as per market rate metre 28
M-147 Pre moulded Joint filler,25 mm thick for expansion joint as per market rate sqm 926
M-148 Pre-coated stone chips of 13.2 mm nominal size cum 8028
M-149 Pre-moulded asphalt filler board sqm 1050
M-150 Pre-packed cement based polymer concrete of strength 45 Mpa at 28 days kg 99
M-151 Primer as per market rate kg 185
M-152 Quick setting compound as per market rate kg 43
M-153 Random Rubble Stone cum 803
M-157 Reflectorising glass beads as per market rate kg 148

M-158 Reinforcement strips 60 mm wide 5 mm thick as per clause 3102. (Copper Strips) as per market rate metre 1294
Reinforcement strips 60 mm wide 5 mm thick as per clause 3102. (Galvanised carbon steel strips) as per
M-159 metre 290
market rate
Reinforcement strips 60 mm wide 5 mm thick as per clause 3102. (Glass reinforced polymer/fibre
M-160 metre 776
reinforced polymer/polymeric strips) as per market rate
Reinforcement strips 60 mm wide 5 mm thick as per clause 3102. (Stainless steel strips) as per market
M-161 metre 776
rate

M-162 Reinforcement strips 60 mm wide 5 mm thick as per clause 3102. Aluminium strips) as per market rate metre 580

M-163 Rivets as per market rate each 5


M-164 Sand bags (Cost of sand and Empty cement bag) as per market rate nos 25
M-165 Sapling 2 m high 25 mm dia as per market rate each 111
M-166 Scrap tyres of size 900 x 20 as per market rate nos 49
M-167 Seeds as per market rate kg 74
M-168 Selected earth as per market rate cum 373
M-169 Separation Membrane of impermeable plastic sheeting 125 micron thick as per market rate sqm 40
M-170 Sheathing duct metre 100
M-171 Shrubs as per market rate each 25
M-172 Sludge / Farm yard manure @ 0.18 cum per 100 sqm at site of work for turfing as per market rate cum 99
M-174 Sodium vapour lamp (250 Watts ) as per market rate each 11115
M-175 Square Rubble Coursed Stone cum 1074
Steel circular hollow pole of standard specification for street lighting to mount light at 5 m height above
M-176 each 8233
deck level as per market rate
Steel circular hollow pole of standard specification for street lighting to mount light at 9 m height above
M-177 each 11762
road level as per market rate
M-178 Steel drum 300 mm dia 1.2 m high/empty bitumen drum as per market rate nos 73
M-179 Steel helmet and cushion block on top of pile head during driving. kg 59
M-180 Steel pipe 25 mm external dia as per IS:1239 as per market rate metre 114
M-181 Steel pipe 50 mm external dia as per IS:1239 as per market rate metre 204
M-182 Steel wire rope 20 mm as per market rate kg 155
M-183 Steel wire rope 40 mm as per market rate kg 266
M-184 Strip seal expansion join metre 9998
M-185 Structural Steel as per market rate tonne 60000
M-186 Super plastisizer admixture IS marked as per 9103-1999 as per market rate kg 167
Synthetic Geogrids as per clause 3102.8 and approved design and specifications.(TGU-150) as per
M-187 sqm 446
market rate
M-188 Through and bond stone each 7
M-189 Tie rods 20mm diameter as per market rate nos 61
M-190 Tiles size 300 x 300 mm and 25 mm thick as per market rate each 75
M-191 Timber cum 31347
M-192 Traffic cones with 150 mm reflective sleeve as per market rate nos 1853
M-193 Tube anchorage set complete with bearing plate, permanent wedges etc as per market rate nos 2100
M-194 Unstaked lime tonne 9571
M-195 Water as per market rate KL 56
M-197 Water based cement paint as per market rate litre 49

M-198 Welded steel wire fabric as per market rate kg 78

M-199 Wire mesh 50mm x 50mm size of 3mm wire kg 74


M-200 Wooden ballies 2" Dia for bracing as per market rate each 303
M-201 Wooden ballies 8" Dia and 9 m long as per market rate each 4755
M-202 Wooden packing as per market rate cum 34642
M-203 Wooden staff for fastening of flag 25 mm dia, 1.0 m long as per market rate each 99
As the cost of road works exceeds 50crores overhead
Overheads for Road Works 8%
considered 8%
Contractors profit for Road Works 10%
for input of Overheads or Contractors profit please type
Overheads for Bridge Works 0.25
in column C as like below

Overheads for Bridge Works Type symble of apostrope(') then input value then one
0.3
(Rehabilitation) space then symble of percentage (%) for example '08 %

Contractors profit for Bridge Works 0.1

Lead from Mixing Plant to working site 3 km

Lead for E/W borow area to site 3 km


Lead for fly ash from source to site 3 km
Items No. Summary of Rates calculated and used for analysis of rates of other items Unit Rate

per cm
Item 8.3 Printing new letter and figures of any shade (ii) English Roman height per 0.50
letter
Item 8.8 Painting Two Coats on New Concrete Surfaces sqm 58.00
Item 8.9 Painting angle iron post two coats sqm 52.00

Item 12.6 (B) Cement mortor 1:2 (Excluding OH & CP) cum 7256.00

Item 12.6 (A) Cement mortor 1:3 (Excluding OH & CP) cum 5945.00

Item 12.6 (D) Cement mortor 1:6 (Excluding OH & CP) cum 4298.00

Item 12.7 (A ) Course Rubble masonary in cement mortor 1:3 (including OH & CP) cum 5309.00

Item 12.7 ( B) Random Rubble masonary in cement mortor 1:6 (including OH & CP) cum 4830.00

Item 12.8 (A) PCC Grade M15 including OH & CP for Open Foundation by Mixer cum 7004.00

Item 12.8 (A) PCC Grade M15 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Mixer cum 4899.00

Item 12.8 (B)


PCC Grade M20 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Mixer cum 5438.00
PCC

Item 12.8 (C) RCC Grade M20 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Mixer cum 5510.00

Item 12.8 (C)


RCC Grade M20 including OH & CP for Open Foundation by Batching Plant cum 7693.00
RCC
RCC Grade M20 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by
Item 12.8 (C) cum 5380.00
Batching Plant

Item 12.8 (D) PCC Grade M25 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Mixer cum 5933.00

Item 12.8 (D) PCC Grade M25 including OH & CP for Open Foundation by Batching Plant cum 8282.00

PCC Grade M25 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by
Item 12.8 (D) cum 5806.00
Batching Plant

Item 12.8 (E) RCC Grade M25 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Mixer cum 6011.00

RCC Grade M25 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by
Item 12.8 (E) cum 6224.00
Batching Plant

Item 12.8 (F) PCC Grade M30 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Mixer cum 5986.00

PCC Grade M30 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by
Item 12.8 (F) cum 5855.00
Batching Plant

Item 12.8 (G) RCC Grade M30 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Mixer cum 6041.00

RCC Grade M30 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by
Item 12.8 (G) cum 6255.00
Batching Plant
Item 12.8 (H)
RCC Grade M35 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Mixer cum 6178.00
Case I
Item 12.8 (H)
RCC Grade M35 including OH & CP for Open Foundation by Batching Plant cum 9053.00
Case II

Item 12.8 (H) RCC Grade M35 excluding OH & CP for Open Foundation by Batching Plant cum 6874.00

RCC Grade M35 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by
Item 12.8 (H) cum 6674.00
Batching Plant
PCC Grade M20 for Open Foundation (Bottom Plug) Per Cum Basic Cost of Labour, Material &
Item 12.11 (C) i cum 6028.00
Mechinery by Mixer
PCC Grade M20 for Open Foundation (Bottom Plug) Per Cum Basic Cost of Labour, Material &
Item 12.11 (C) i cum 6134.00
Mechinery by Batching Plant
Item 12.11 (C) PCC Grade M25 for Open Foundation (Bottom Plug) Per Cum Basic Cost of Labour, Material &
cum 6323.00
ii Mechinery by Mixer
Item 12.11 (C) PCC Grade M25 for Open Foundation (Bottom Plug) Per Cum Basic Cost of Labour, Material &
cum 6427.00
ii Mechinery by Batching Plant
Item 12.11 (C) PCC Grade M30 for Open Foundation (Bottom Plug) Per Cum Basic Cost of Labour, Material &
cum 6377.00
iii Mechinery by Mixer
Item 12.11 (C) PCC Grade M30 for Open Foundation (Bottom Plug) Per Cum Basic Cost of Labour, Material &
cum 6484.00
iii Mechinery by Batching Plant
Item 12.11 (C) PCC Grade M35 for Open Foundation (Bottom Plug) Per Cum Basic Cost of Labour, Material &
cum 6502.00
iv Mechinery by Mixer
Item 12.11 (C)
PCC Grade M35 including OH & CP for Well Foundation (Bottom Plug) by Batching Plant cum 9490.00
iv
Item 12.11 (C) PCC Grade M35 for Open Foundation (Bottom Plug) Per Cum Basic Cost of Labour, Material &
cum 6606.00
iv Mechinery by Batching Plant
Item 12.11 (F)
PCC Grade M35 including OH & CP for Well Foundation (Well Cap) by Batching Plant cum 9053.00
iv

Item No. 3.13 Excavation for Structures (Manual Means) cum 158.00

Item No. 3.13 Excavation for Structures (Mechenical Meanse) cum 44.00

Item 14.1(A) RCC Grade M20 for super-structure including OH & CP by Batching Plant cum 9352.00
Item 14.1(B) RCC Grade M20 for super-structure including OH & CP by Batching Plant cum 10219.00
Item 14.1(E) RCC Grade M20 for super-structure including OH & CP by Batching Plant cum 11446.16
Item 14.1(C) RCC Grade M30 for super-structure including formwork and excluding OH & CP by Batching Plant cum 7514.00
Item 14.1(C) RCC Grade M30 for super-structure excluding formwork and excluding OH & CP by Batching Plant cum 6261.00
Item 14.2 A Supplying ,fitting and placing HYSD bar reinforcement in super-structure exncluding OH & CP tonne 49368.00
Item 13.6 Supplying, fitting and placing HYSD including OH & CP for sub-structure tonne 66780.00
Item 5.17 Fog Seal sqm 31.00
Item 5.21 Case-
Crack Prevention courses. Case-I Stress Absorbing Membrane (SAM) crack width less than 6 mm sqm 63.00
I
Item 5.21 Case-
Crack Prevention courses. Case-II Stress Absorbing Membrane (SAM) with crack width 6 mm to 9 mm sqm 74.00
II
Item 5.21 Case- Crack Prevention courses. Case-III Stress Absorbing Membrane (SAM) crack width above 9 mm and
sqm 97.00
IV cracked area above 50 %

Item 5.21 Case-


Crack Prevention courses. Case-IV Bitumen Impregnated Geotextile sqm 229.00
IV

Item 5.15 Case-


Slurry Seal Case-I 5 mm thickness sqm 63.00
I

Item 5.15 Case-


Slurry Seal Case-II 3 mm thickness sqm 41.00
II

Item 5.15 Case-


Slurry Seal Case III 1.5 mm thickness sqm 24.70
III

Item 5.9 Case-I Surface Dressing Case-I 19 mm nominal chipping size sqm 90.00

Item 5.9 Case-II Surface Dressing Case-II 13 mm nominal size chipping sqm 73.00
Summary
CHAPTER-1
CARRIAGE OF MATERIALS
Item No.
Descriptions Unit Rate (in Rs.)

Loading and unloading of stone boulder / stone aggregates / sand / kanker / moorum.
1.1 (Placing tipper at loading point, loading with front end loader, dumping, turning for cum 92.00
return trip, excluding time for haulage and return trip)
1.2 Loading and Unloading of Boulders by Manual Means cum 112.00

1.3 Loading and Unloading of Cement or Steel by Manual Means and stacking. tonne 162.00

1.4 Cost of Haulage Excluding Loading and Unloading

(i) Surfaced Road tonne.km 4.00

(ii) Unsurfaced Gravelled Road tonne.km 4.80

(iii) Katcha Track and Track in river bed / nallah bed and choe bed. tonne.km 9.80
Item No.
Descriptions Unit Rate (in Rs.)

CHAPTER-2
SITE CLEARANCE
Item No.
Descriptions Unit Rate (in Rs.)
2.1
Cutting of Trees, including Cutting of Trunks, Branches and Removal (Cutting of trees, including
cutting of trunks, branches and removal of stumps, roots, stacking of serviceable material with
all lifts and up to a lead of 1000 mtrs and earth filling in the depression/pit.)
(i) Girth from 300 mm to 600 mm each 162.00
(ii) Girth from 600 mm to 900 mm each 315.00
(iii) Girth from 900 mm to 1800 mm each 575.00
(iv) Girth above 1800 mm each 1060.00
2.2 Clearing Grass and Removal of Rubbish hectare 9865.00
2.3 Clearing and Grubbing Road Land .(Clearing and grubbing road land including uprooting rank
vegetation, grass, bushes, shrubs, saplings and trees girth up to 300 mm, removal of stumps of
trees cut earlier and disposal of unserviceable materials and stacking of serviceable material to
be used or auctioned up to a lead of 1000 metres including removal and disposal of top organic
soil not exceeding 150 mm in thickness.)
(i)
By Manual Means:-
A
In area of light jungle hectare 30047.00
B
In area of thorny jungle hectare 40363.00
(ii)
By Mechanical Means
A
In area of light jungle hectare 45871.00
B
In area of thorny jungle hectare 55418.00
2.4 Dismantling of Structures (Dismantling of existing structures like culverts, bridges, retaining
walls and other structure comprising of masonry, cement concrete, wood work, steel work,
including T&P and scaffolding wherever necessary, sorting the dismantled material, disposal of
unserviceable material and stacking the serviceable material with all lifts and lead of 1000
metres)
(i) Lime /Cement Concrete
I By Manual Means
A Lime Concrete, cement concrete grade M-10 and below cum 255.00
B Cement Concrete Grade M-15 & M-20 cum 295.00
C Prestressed / Reinforced cement concrete grade M-20 & above cum 737.00
II By Mechanical Means for items No. 202( b) & ( c)
A Cement Concrete Grade M-15 & M-20 cum 395.00
B Prestressed / Reinforced cement concrete grade M-20 & above cum 661.00
(ii) Dismantling Brick / Tile work
A In lime mortar cum 176.00
B In cement mortar cum 216.00
C In mud mortar cum 161.00
D Dry brick pitching or brick soling cum 153.00
(iii) Dismantling Stone Masonry
A Rubble stone masonry in lime mortar cum 192.00
B Rubble stone masonry in cement mortar. cum 216.00
C Rubble Stone Masonry in mud mortar. cum 176.00
D Dry rubble masonry cum 169.00
E Dismantling stone pitching/ dry stone spalls. cum 161.00
F Dismantling boulders laid in wire crates including opening of crates and stacking dismantled
cum 176.00
materials.
Item No.
Descriptions Unit Rate (in Rs.)

(iv) Wood work wrought framed and fixed in frames of trusses upto a height of 5 m above plinth
cum 429.00
level
(v) Steel work in all types of sections upto a height of 5 m above plinth level excluding cutting of
rivet.
A Including dismembering tonne 1028.00
B Excluding dismembering. tonne 752.00
C Extra over item No( V ) A and( V ) B for cutting rivets. tonne 8.20
(vi)
Scraping of bricks dismantled from brick work including stacking.
A 1000
In lime/Cement mortar 691.00
numbers
B 1000
In mud mortar 247.00
numbers
(vii) Scraping of Stone from dismantled stone masonry
A In cement and lime mortar cum 278.00
B In Mud mortar cum 58.00
(viii) Scarping plaster in lime or cement mortar from brick/ stone masonry sqm 9.30
(ix) Removing all type of hume pipes and stacking within a lead of 1000 metres including earthwork
and dismantling of masonry works.
A Up to 600 mm dia metre 102.00
B Above 600 mm to 900 mm dia metre 139.00
C Above 900 mm metre 238.00
2.5 Dismantling of Flexible Pavements (Dismantling of flexible pavements and disposal of
dismantled materials up to a lead of 1000 metres, stacking serviceable and unserviceable
materials separately)
I By Manual Means
A Bituminous courses cum 467.00
B Granular courses cum 346.00
II By Mechanical Means
A Bituminous course cum 240.00
2.6 Dismantling of Cement Concrete Pavement (Dismantling of cement concrete pavement by
mechanical means using pneumatic tools, breaking to pieces not exceeding 0.02 cum in volume
cum 994.00
and stock piling at designated locations and disposal of dismantled materials up to a lead of
1000 metres, stacking serviceable and unserviceable materials separately)
2.7 Dismantling Guard Rails (Dismantling guard rails by manual means and disposal of dismantled
material with all lifts and up to a lead of 1000 metres, stacking serviceable materials and metre 52.00
unserviceable materials separately.)
2.8 Dismantling Kerb Stone (Dismantling kerb stone by manual means and disposal of dismantled
metre 12.00
material with all lifts and up to a lead of 1000 metre)
2.9 Dismantling Kerb Stone channel (Dismantling kerb stone channel by manual means and
metre 18.00
disposal of dismantled material with all lifts and up to a lead of 1000 metre)
2.10 Dismantling Kilometre Stone (Dismantling of kilometre stone including cutting of earth,
foundation and disposal of dismantled material with all lifts and lead upto 1000 m and back
filling of pit.)
A 5th KM stone each 255.00
B Ordinary KM Stone each 144.00
C Hectometre Stone each 28.80
2.11 Dismantling of Fencing (Dismantling of barbed wire fencing/ wire mesh fencing including posts,
foundation concrete, back filling of pit by manual means including disposal of dismantled
metre 32.90
material with all lifts and up to a lead of 1000 metres, stacking serviceable material and
unserviceable material separately. )
2.12
Dismantling of CI Water Pipe Line (Dismantling of CI water pipe line 600 mm dia including
disposal with all lifts and lead upto 1000 metres and stacking of serviceable material and metre 88.00
unserviceable material separately under supervision of concerned department)
2.13
Removal of Cement Concrete Pipe of Sewer Gutter (Removal of cement concrete pipe of sewer
gutter 1500 mm dia under the supervision of concerned department including disposal with all
metre 140.00
lifts and up to a lead of 1000 metres and stacking of serviceable and unserviceable material
separately but excluding earth excavation and dismantling of masonry works.)
2.14 Removal of Telephone / Electric Poles and Lines (Removal of telephone / Electric poles including
excavation and dismantling of foundation concrete and lines under the supervision of
each 117.00
concerned department, disposal with all lifts and up to a lead of 1000 metres and stacking the
serviceable and unserviceable material separately)
Item No.
Descriptions Unit Rate (in Rs.)

CHAPTER-3
EARTH WORK, EROSION CONTROL AND DRAINAGE
Item No.
Descriptions Unit Rate (in Rs.)
3.1 Excavation in Soil by Manual Means. (Excavation for roadway in soil using manual means
including loading in truck for carrying of cut earth to embankment site with all lifts and lead
upto1000 metres.)
(i) Including Royality @ Rs. 15.0 per cum but excluding the cost of watering, rolling &
cum 149.00
compaction
(ii) Including Royality @ Rs. 15.0 per cum , cost of watering, rolling & compaction cum 166.00
Note In case there is a situation where the cross-section is of cut and fill and cut earth is required to
be used in embankment in the immediate vicinity, the item of carriage in the truck shall be cum 98.00
omitted. inclunding Royality @ Rs. 15.00 per cum.
3.2 (i) Excavation in ordinary rock by manual means (Excavation in ordinary rock using manual means
including loading in a truck and carrying of excavated material to embankment site with in all
cum 190.00
lifts and leads upto 1000 metres ) including royality @ Rs. 15.00 per cum but excluding cost of
watering , rolling & compaction
(ii)
Excavation in ordinary rock using manual means including loading in a truck and
carrying of excavated material to embankment site with in all lifts and leads upto 1000 cum 207.00
metres including royality @ Rs. 15.00 per cum, cost of watering , rolling & compaction
Note In case there is a situation where the cross-section is of cut and fill and cut earth is
required to be used in embankment in the immediate vicinity, the item of carriage in the cum 139.00
truck shall be omitted - inclunding Royality @ Rs. 15.00 per cum.
3.3 Excavation in Soil with Dozer with lead upto 100 metres (Excavation for road way in soil by
mechanical means including cutting and pushing the earth to site of embankment upto a
cum 151.00
distance of 100 metres (average lead50 metres), including trimming bottom and side slopes in
accordance with requirements of lines, grades and cross sections.)
3.4
Excavation in Ordinary Rock with Dozer with lead upto 100 metres (Excavation for roadway in
ordinary rock by deploying a dozer, 80 HP including cutting and pushing the cut earth to site of
cum 253.00
embankment upto a distance of 100 metres ( average lead 50 metres ), trimming bottom and
side slopes in accordance with the requirements of lines, grades and cross sections.
3.5
Excavation in Hard Rock (requiring blasting) with disposal upto 1000 metres (Excavation for
roadway in hard rock (requiring blasting) by drilling, blasting and breaking, trimming of bottom
cum 521.00
and side slopes in accordance with requirements of lines, grades and cross sections, loading
and disposal of cut road with in all lifts and leads upto 1000 metres )

3.6 Excavation in Soil using Hydraulic Excavator CK 90 and Tippers with disposal upto 1000 metres.
(Excavation for roadwork in soil with hydraulic excavator of0.9 cum bucket capacity including
cutting and loading in tippers, trimming bottom and side slopes, in accordance with
requirements of lines, grades and cross sections, and transporting to the embankment location
within all lifts and lead upto 1000m)
(i) Including Royality @ Rs. 15.00 per cum but excluding the cost of watering, rolling &
cum 83.00
compaction.
(ii)
Including Royality @ Rs. 15.00 per cum, cost of watering, rolling & compaction. cum 98.00

3.7 Excavation in Ordinary Rockusing Hydraulic ExcavatorCK-90 and Tippers with disposal upto
1000 metres. (Excavation for roadway in ordinary rock with hydraulic excavator of 0.9 cum
bucket capacity including cutting and loading in tippers, transporting to embankment site within
all lifts and lead upto 1000 m, trimming bottom and side slopes in accordance with
requirements of lines, grades and cross sections.)
(i) Including Royality @ Rs. 15.00 per cum but excluding the cost of watering, rolling &
cum 101.00
compaction.
(ii)
Including Royality @ Rs. 15.00 per cum, cost of watering, rolling & compaction. cum 117.00

3.8 Excavation in Hard Rock (blasting prohibited) (Excavation for roadway in hard rock (blasting
prohibited) with rock breakers including breaking rock, loading in tippers and disposal within
all lifts and lead upto 1000 metres, trimming bottom and side slopes in accordance with
requirements of lines, grades and cross sections.)
A Mechanised cum 261.00
B Manual Method cum 658.00
Item No.
Descriptions Unit Rate (in Rs.)

3.9
Excavation in Hard Rock (controlled blasting) with disposal upto 1000 metres (Excavation for
roadway in hard rock with controlled blasting by drilling, blasting and breaking, trimming of
cum 99.00
bottom and side slopes in accordance with requirements of lines, grades and cross sections,
loading and disposal of cut road with in all lifts and leads upto 1000 metres )
3.10 Excavation in Marshy Soil (Excavation for roadway in marshy soil with hydraulic excavator 0.9
cum bucket capacity including cutting and loading in tippers and disposal with in all lifts and
lead upto 1000 metres, trimming of bottom and side slopes in accordance with requirements of
lines, grades and cross sections.)
(i) Including Royality @ Rs. 15.00 per cum but excluding the cost of watering, rolling &
cum 90.00
compaction.
(ii)
Including Royality @ Rs. 15.00 per cum, cost of watering, rolling & compaction. cum 107.00

3.11 Removal of Unserviceable Soil with Disposal upto 1000 metres (Removal of unserviceable soil
including excavation, loading and disposal upto 1000 metres lead but excluding replacement by cum 60.00
suitable soil which shall be paid separately as per clause 305.)
3.12 Pre-splitting of Rock Excavation Slopes (Carrying out excavation in hard rock to achieve a
specified slope of the rock face by controlled use of explosives and blasting accessories in
properly aligned and spaced drill holes, collection of the excavated rock by a 80 HP dozer, sqm 120.00
loading in tipper by a front end loader and disposing of the material with all lifts and lead upto
1000 m, all as specified in clause No. 303)
3.13
Excavation for Structures (Earth work in excavation of foundation of structures as per drawing
and technical specification, including setting out, construction of shoring and bracing, removal
of stumps and other deleterious matter, dressing of sides and bottom, backfilling the excavation
earth to the extent required and utilising the remaining earth locally for road work.)
(i) Ordinary soil
A Manual Means (Depth upto 3 m) cum 158.00
B Mechanical Means (Depth upto 3 m) cum 44.00
(ii) Ordinary rock (not requiring blasting)
A Manual Means (Depth upto 3 m) cum 197.00
B Mechanical Means cum 59.00
(iii) Hard rock ( requiring blasting )
A Manual Means cum 374.00
(iv) Hard rock ( blasting prohibited )
A Mechanical Means cum 495.00
(v) Marshy soil
A Manual means ( upto 3 m depth) cum 540.00
B Mechanical Means cum 320.00
3.14 Scarifying Existing Granular Surface to a Depth of 50 mm by Manual Means (Scarifying the
existing granular road surface to a depth of 50 mm and disposal of scarified material within all sqm 17.40
lifts and leads upto 1000 metres. )
3.15 Scarifying existing bituminous surface to a depth of 50 mm by mechanical means (Scarifying
the existing bituminous road surface to a depth of 50 mm and disposal of scarified material with sqm 4.20
in all lifts and lead upto 1000 metres.)
3.16 Embankment Construction with Material Obtained from Borrow Pits (Construction of
embankment with approved material obtained from borrow pits with all lifts and leads,
transporting to site, spreading, grading to required slope and compacting to meet requirement
of table 300-2)
(i) Rolling with vibratory roller cum 266.00
(ii) Rolling with smooth wheeled roller cum 641.00
3.17 Construction of Embankment with Material Deposited from Roadway Cutting (Construction of
embankment with approved materials deposited at site from roadway cutting and excavation
from drain and foundation of other structures graded and compacted to meet requirement of
table 300-2)
(i) Rolling with vibratory roller cum 139.00
(ii) Rolling with smooth wheeled roller cum 130.00
3.18 Construction of Subgrade and Earthen Shoulders (Construction of subgrade and earthen
shoulders with approved material obtained from borrow pits with all lifts & leads, transporting to
site, spreading, grading to required slope and compacted to meet requirement of table No. 300-
2)
(i) Rolling with vibratory roller cum 322.00
(ii) Rolling with smooth wheeled roller cum 717.00
3.19 Compacting Original Ground
Case-I Compacting original ground supporting subgrade (Loosening of the ground upto a level of 500
mm below the subgrade level, watered, graded and compacted in layers to meet requirement of
table 300-2 for subgrade construction.)
(i) Rolling with vibratory roller cum 73.00
(ii) Rolling with smooth wheeled roller cum 63.00
Item No.
Descriptions Unit Rate (in Rs.)

Case-II Compacting original ground supporting embankment


(i) Rolling with vibratory roller cum 38.00
(ii) Rolling with smooth wheeled roller cum 28.00
3.20 Stripping and Storing Top Soil (Stripping, storing of top soil by road side at 15 m internal and re-
application on embankment slopes, cut slopes and other areas in localities where the available cum 143.00
embankment material is not conducive to plant growth)
3.21 Stripping, storing and re-laying top soil from borrow areas in agriculture fields. (Stripping of top
soil from borrow areas located in agriculture fields, storing at a suitable place, spreading and re-
cum 91.00
laying after taking the borrow earth to maintain fertility of the agricultural field, finishing it to
the required levels and satisfaction of the farmer.)
3.22 Turfing with Sods (Furnishing and laying of the live sods of perennial turf forming grass on
embankment slope, verges or other locations shown on the drawing or as directed by the sqm 31.00
engineer including preparation of ground, fetching of rods and watering)
3.23 Seeding and Mulching (Preparation of seed bed on previously laid top soil, furnishing and
placing of seeds, fertilizer, mulching material, applying bituminous emulsion at the rate of0.23
sqm 126.00
litres per sqm and laying and fixing jute netting, including watering for 3 months all as per
clause 308)
3.24 Surface Drains in Soil (Construction of unlined surface drains of average cross sectional area
0.40 sqm in soil to specified lines, grades, levels and dimensions to the requirement of clause
301 and 309. Excavated material to be used in embankment within a lead of50 metres (average
lead 25 metres))
A Mechanical means metre 69.00
B Manual Means metre 39.00
3.25 Surface Drains in Ordinary Rock (Construction of unlined surface drain of average cross
sectional area 0.4 sqm in ordinary rock to specified lines, grades, levels and dimensions as per
approved design and to the requirement of clause 301 to 309. Excavated material to be used in
embankment at site.)
A Mechanical Means metre 139.00
B Manual Means metre 59.00
3.27
Sub Surface Drains with Perforated Pipe (Construction of subsurface drain with perforated pipe
of 100 mm internal diameter of metal/ asbestos cement/ cement concrete/PVC, closely jointed,
perforations ranging from 3 mm to 6 mm depending upon size of material surrounding the pipe, metre 554.00
with 150 mm bedding below the pipe and 300 mm cushion above the pipe, cross section of
excavation 450 x 550 mm. Excavated material to be utilised in roadway at site )
3.28
Aggregate Sub- Surface Drains (Construction of aggregate sub surface drain 300 mm x 450 mm
metre 219.00
with aggregates conforming to table 300-4, excavated material to be utilised in roadway )
3.29 Underground Drain at Edge of Pavement (Construction of an underground drain 1 m x 1 m
(inside dimensions) lined with RCC-20 cm thick and covered with RCC slab10 cm in thickness on metre 3874.00
urban roads)
3.30 Preparation and Surface Treatment of formation. (Preparation and surface treatment of
formation by removing mud and slurry, watering to the extent needed to maintain the desired
sqm 2.00
moisture content, trimming to the required line, grade, profile and rolling with 8-10 tonne
smooth wheeled roller, complete as per clause 310.)
3.31 Construction of Rock fill Embankment (Construction of rock fill embankment with broken hard
rock fragments of size not exceeding 300 mm laid in layers not exceeding 500 mm thick
cum 65.00
including filling of surface voids with stone spalls, blinding top layer with granular material,
rolled with vibratory road roller, all complete as per clause 313)
3.32 Excavation in Hill Area in Soil by Mechanical Means (Excavation in soil in hilly area by
mechanical means including cutting and trimming of side slopes and disposing of excavated cum 157.00
earth with all lifts and lead upto 1000 metres)
3.33 Excavation in Hilly Area in Ordinary Rock by Mechanical Means not Requiring Blasting.
(Excavation in hilly area in ordinary rock not requiring ballasting by mechanical means including
cum 230.00
cutting and trimming of slopes and disposal of cut material with all lift and lead upto 1000
metres )
3.34 Excavation in Hilly Areas in Hard Rock Requiring Blasting (Excavation in hilly areas in hard rock
requiring blasting, by mechanical means including trimming of slopes and disposal of cut cum 286.00
material with all lifts and lead upto 1000 metres.)
3.36 Embankment Construction with Fly ash/Pond ash available from coal or lignite burning Thermal
Plants as waste material. (Construction of embankment with fly ash conforming to table 1 of
IRC: SP: 58 - 2001 obtained from coal or lignite burning thermal power stations as waste cum 460.00
material, spread and compacted in layer of 200mm thickness each at OMC, all as specified in
IRC: SP: 58-2001 and as per approved plans.)
Item No.
Descriptions Unit Rate (in Rs.)

CHAPTER-4
SUB-BASES, BASES ( NON- BITUMINOUS) AND SHOULDERS
Item No.
Descriptions Unit Rate (in Rs.)
4.1 Granular Sub-base with Close Graded Material (Table:- 400-1)
A Plant Mix Method (Construction of granular sub-base by providing close graded
Material, mixing in a mechanical mix plant at OMC, carriage of mixed Material to work
site, spreading in uniform layers with motor grader on prepared surface and
compacting with vibratory power roller to achieve the desired density, complete as per
clause 401 )
(i) for grading- I Material cum 2322.00
(ii) for grading- II Material cum 2384.00
(iii) for grading-III Material cum 2235.00
B By Mix in Place Method (Construction of granular sub-base by providing close graded
material, spreading in uniform layers with motor grader on prepared surface, mixing
by mix in place method with rotavator at OMC, and compacting with vibratory roller to
achieve the desired density, complete as per clause 401)
(i) for grading- I Material cum 2162.00
(ii) for grading- II Material cum 2224.00
(iii) for grading-III Material cum 2075.00
4.2 Granular Sub-Base with Coarse Graded Material ( Table:- 400- 2) (Construction of
granular sub-base by providing coarse graded material, spreading in uniform layers
with motor grader on prepared surface, mixing by mix in place method with rotavator
at OMC, and compacting with vibratory roller to achieve the desired density, complete
as per clause 401)
(i) for grading- I Material cum 2264.00
(ii) for grading- II Material cum 2341.00
(iii) for grading-III Material cum 2261.00
4.3 Lime Stabilisation for Improving Subgrade (Laying and spreading available soil in the
subgrade on a prepared surface, pulverising, mixing the spread soil in place with
rotavator with 3 % slaked lime having minimum content of 70% of CaO, grading with
motor grader and compacting with the road roller at OMC to the desired density to
form a layer of improved sub grade)
A By Mechanical Means cum 757.00
B By Manual Means cum 728.00
4.4 Lime Treated Soil for Sub- Base (Providing, laying and spreading soil on a prepared
sub grade, pulverising, mixing the spread soil in place with rotavator with 3 % slaked
lime with minimum content of 70% of CaO, grading with motor grader and cum 1295.00
compacting with the road roller at OMC to achieve at least 98%of the max dry density
to form a layer of sub base.)
4.5 Cement Treated Soil Sub Base/ Base (Providing, laying and spreading soil on a
prepared sub grade, pulverising, adding the designed quantity of cement to the
spread soil, mixing in place with rotavator, grading with the motor grader and cum 985.00
compacting with the road roller at OMC to achieve the desired unconfined
compressive strength and to form a layer of sub-base/base.)
4.6 Cement Treated Crushed Rock or combination as per clause 403.2 and table 400.4 in
Sub base/ Base (Providing, laying and spreading Material on a prepared sub grade,
adding the designed quantity of cement to the spread Material, mixing in place with
rotavator, grading with the motor grader and compacting with the road roller at OMC
to achieve the desired unconfined compressive strength and to form a layer of sub-
base/base.)
(i) For Sub-Base course cum 3479.00
(ii) For Base course cum 3073.00
4.7 Making 50 mm x 50 mm Furrows (Making 50 mm x 50 mm furrows, 25mm deep, 450
to the center line of the road and at one metre interval in the existing thin bituminous
wearing coarse including sweeping and disposal of excavated material within 1000
metres lead)
i) 25 mm deep furrow cutting sqm 2.30

ii) 50 mm deep furrow cutting sqm 4.60


Item No.
Descriptions Unit Rate (in Rs.)

4.8 Inverted Choke (Construction of inverted choke by providing, laying, spreading and
compacting screening B type/ coarse sand of specified grade in uniform layer on a cum 1766.00
prepared surface with motor grader and compacting with power roller etc)
Not
For moorum or gravel cum 1069.00
considered
For Koilwar sand cum 1766.00
Not
considered For Doriganj sand cum
1766.00
Not
For local sand cum 1934.00
considered
4.9 Water Bound Macadam (Providing, laying, spreading and compacting stone aggregates of
specific sizes to water bound macadam specification including spreading in uniform thickness,
hand packing, rolling with vibratory roller 8-10 tonnes / Smooth 3 wheeled Steel Roller in
stages to proper grade and camber, applying and brooming requisite type of screening/ binding
Materials to fill up the interstices of coarse aggregate, watering and compacting to the required
density.)
A By Manual Means
(i) Grading- I (Using Screening Crushable type such as Moorum or Gravel)
(a) Using Screening Crushable type such as Moorum or Gravel (with Vibratory Roller) cum 2513.00
With Smooth 3 wheeled Steel Roller cum 2507.00
(b) Using Screening Type-A (13.2mm Agg.) (with Vibratory Roller) cum 2843.00
With Smooth 3 wheeled Steel Roller cum 2836.00
(ii) Grading- II (Using Screening Crushable type such as Moorum or Gravel)
(a) Using Screening Crushable type such as Moorum or Gravel (with Vibratory Roller) cum 2592.00
With Smooth 3 wheeled Steel Roller cum 2586.00
(b) Using Screening Type-A (13.2mm Agg.) (with Vibratory Roller) cum 2720.00
With Smooth 3 wheeled Steel Roller cum 2714.00
(c) Using Screening Type-B (11.2mm Agg.) (with Vibratory Roller) cum 2902.00
With Smooth 3 wheeled Steel Roller cum 2848.00
(iii) Grading- III (Using Screening Crushable type such as Moorum or Gravel)
(a) Using Screening Crushable type such as Moorum or Gravel (with Vibratory Roller) cum 2677.00
With Smooth 3 wheeled Steel Roller cum 2670.00
(b) Using Screening Type-B (11.2mm Agg.) (with Vibratory Roller) cum 2938.00
With Smooth 3 wheeled Steel Roller cum 2932.00
B By Mechanical Means:
(i) Grading- I (Using Screening Crushable type such as Moorum or Gravel)
(a) Using Screening Crushable type such as Moorum or Gravel (with Vibratory Roller) cum 2447.00
With Smooth 3 wheeled Steel Roller cum 2440.00
(b) Using Screening Type-A (13.2mm Agg.) (with Vibratory Roller) cum 2776.00
With Smooth 3 wheeled Steel Roller cum 2770.00
(ii) Grading- II (Using Screening Crushable type such as Moorum or Gravel)
(a) Using Screening Crushable type such as Moorum or Gravel (with Vibratory Roller) cum 2526.00
With Smooth 3 wheeled Steel Roller cum 2520.00
(b) Using Screening Type-A (13.2mm Agg.) (with Vibratory Roller) cum 2653.00
With Smooth 3 wheeled Steel Roller cum 2647.00
(c) Using Screening Type-B (11.2mm Agg.) (with Vibratory Roller) cum 2836.00
With Smooth 3 wheeled Steel Roller cum 2781.00
(iii) Grading- III (Using Screening Crushable type such as Moorum or Gravel)
(a) Using Screening Crushable type such as Moorum or Gravel (with Vibratory Roller) cum 2610.00
With Smooth 3 wheeled Steel Roller cum 2604.00
(b) Using Screening Type-B (11.2mm Agg.) (with Vibratory Roller) cum 2872.00
With Smooth 3 wheeled Steel Roller cum 2866.00
4.10 Crushed Cement Concrete Sub-base / Base (Breaking and crushing of material obtained by
breaking damaged cement concrete slabs to size range not exceeding 75 mm as specified in
table 400.7 transporting the aggregates obtained from breaking of cement concrete slabs at a
lead of L km., laying and compacting the same as sub base/ base course, constructed as WBM
to clause 404 except the use of screening or binding Material.)

With Vibratory Roller cum 746.00


With Smooth 3 wheeled Steel Roller cum 739.00
Item No.
Descriptions Unit Rate (in Rs.)

4.11 Penetration Coat Over Top Layer of Crushed Cement Concrete Base (Spraying of bitumen over
cleaned dry surface of crushed cement concrete base at the rate of 25 kg per 10 sqm by a
sqm 31.70
bitumen pressure distributor, spreading of key aggregates at the rate of 0.13 cum per 10 sqm
by a mechanical gritter and rolling the surface as per clause 506.3.8)
4.12 Wet Mix Macadam (Providing, laying, spreading and compacting graded stone aggregate to
wet mix macadam specification including premixing the Material with water at OMC in
mechanical mix plant carriage of mixed Material by tipper to site, laying in uniform layers with
paver in sub- base / base course on well prepared surface and compacting with vibratory roller
to achieve the desired density.)
With Vibratory Roller cum 2350.00
With Smooth 3 wheeled Steel Roller cum 2932.00
4.13 Construction of Median and Island with Soil Taken from Roadway Cutting (Construction of
Median and Island above road level with approved material deposited at site from roadway
cum 192.00
cutting and excavation for drain and foundation of other structures, spread, graded and
compacted as per clause 407)
4.14 Construction of Median and Island with Soil Taken from Borrow Areas (Construction of median
and Island above road level with approved material brought from borrow pits, spread, sloped cum 259.00
and compacted as per clause 407)
4.16 Footpaths and Separators (Construction of footpath/separator by providing a 150 mm
compacted granular sub base as per clause 401 and 25 mm thick cement concrete grade M15,
sqm 1654.00
over laid with precast concrete tiles in cement mortar 1:3 including provision of all drainage
arrangements but excluding kerb channel.)
4.17 Crusher Run Macadam Base (Providing crushed stone aggregate, depositing on a prepared
surface by hauling vehicles, spreading and mixing with a motor grader, watering and
compacting with a vibratory roller to clause 410 to form a layer of sub-base/Base)
A By Mix in Place Method
(i) For 53 mm maximum size cum 2432.00
(ii) For 45 mm maximum size cum 2449.00
B By Mixing Plant :
(i) For 53 mm maximum size cum 3126.00
(ii) For 45 mm maximum size cum 3148.00
4.18
Lime, Fly ash stabalised soil sub-base (Construction of Sub-base using lime - fly ash admixture
with granular soil, free from organic matter/ deleterious material or clayey silts and low
plasticity clays having PI between 5 and 20 and liquid limit less than 25 and commercial dry
lime, slaked at site or pre-slaked with CaO content not less than 50%, fly ash to conform to cum 1234.00
gradation as per clause 4.3 of IRC: 88-1984, lime + fly ash content ranging between 10 to
30%, the minimum un-confined compressive strength and CBR value after 28 days curing and 4
days soaking to be 7.5 kg/sq, cm and 25% respectively, all as specified in IRC: 88-1984)
Item No.
Descriptions Unit Rate (in Rs.)

CHAPTER-5
BASES AND SURFACE COURSES (BITUMINOUS)
Item No.
Descriptions Unit Rate (in Rs.)
5.1

Prime coat (Providing and applying primer coat with bitumen emulsion on prepared surface of
granular Base including clearing of road surface and spraying primer at the rate of 0.60 kg/sqm sqm 25.00
using mechanical means.)

5.2 Tack coat


Providing and applying tack coat with bitumen emulsion using emulsion pressure distributor at
the rate of 0.20 kg per sqm on the prepared bituminous/granular surface cleaned with sqm 9.00
mechanical broom.
5.3 Bituminous Macadam (Providing and laying bituminous macadam with 100-120 TPH hot mix
plant producing an average output of 75 tonnes per hour using crushed aggregates of specified
grading premixed with bituminous binder, transported to site, laid over a previously prepared
surface with paver finisher to the required grade, level and alignment and rolled as per clauses
501.6 and 501.7 to achieve the desired compaction)
(i) for Grading I ( 40 mm nominal size ) cum 7471.00
(ii) for GradingII(19 mm nominal size) cum 7471.00
5.4 Bituminous Penetration Macadam (Construction of penetration macadam over prepared Base by
providing a layer of compacted crushed coarse aggregate using chips spreader with alternate
applications of bituminous binder and key aggregates and rolling with a smooth wheeled steel
roller 8-10 tonne capacity to achieve the desired degree of compaction)
A 50 mm thick sqm 390.00
B 75 mm thick sqm 533.00
5.5 Built-Up-Spray Grout (Providing, laying and rolling of built-up-spray grout layer over prepared
base consisting of a two layer composite construction of compacted crushed coarse aggregates
using motor grader for aggregates. key stone chips spreader may be used with application of
sqm 373.00
bituminous binder after each layer, and with key aggregates placed on top of the second layer
to serve as a Base conforming to the line, grades and cross-section specified, the compacted
layer thickness being 75 mm)
5.6 Dense Graded Bituminous Macadam (Providing and laying dense bituminous macadam with 100-
120 TPH batch type HMP producing an average output of 75 tonnes per hour using crushed
aggregates of specified grading, premixed with bituminous binder @ 4.0 to 4.5% by weight of
total mix of mix and filler, transporting the hot mix to work site, laying with a hydrostatic paver
finisher with sensor control to the required grade, level and alignment, rolling with smooth
wheeled, vibratory and tandem rollers to achieve the desired compaction as per MoRTH
specification clause No. 507 complete in all respects.)
(i) for Grading I ( 40 mm nominal size ) cum 5986.00
(ii) for GradingII(19 mm nominal size) cum 8967.00
5.7 Semi - Dense Bituminous Concrete (Providing and laying semi dense bituminous concrete with
100-120 TPH batch type HMP producing an average output of 75 tonnes per hour using crushed
aggregates of specified grading, premixed with bituminous binder @ 4.5 to 5 % of mix and
filler, transporting the hot mix to work site, laying with a hydrostatic paver finisher with sensor
control to the required grade, level and alignment, rolling with smooth wheeled, vibratory and
tandem rollers to achieve the desired compaction as per MoRTH specification clause No. 508
complete in all respects)
(i) for Grading I ( 13 mm nominal size ) cum 9646.00
(ii) for GradingII(10 mm nominal size) cum 10158.00
5.8 Bituminous Concrete (Providing and laying bituminous concrete with 100-120 TPH batch type
hot mix plant producing an average output of 75 tonnes per hour using crushed aggregates of
specified grading, premixed with bituminous binder @ 5.4 to 5.6 % of mix and filler,
transporting the hot mix to work site, laying with a hydrostatic paver finisher with sensor
control to the required grade, level and alignment, rolling with smooth wheeled, vibratory and
tandem rollers to achieve the desired compaction as per MORTH specification clause No. 509
complete in all respects)
(i) for Grading-I ( 13 mm nominal size ) cum 7119.00
(ii) for Grading-II(10 mm nominal size) cum 10230.00
5.9 Surface Dressing (Providing and laying surface dressing as wearing course in single coat using
crushed stone aggregates of specified size on a layer of bituminous binder laid on prepared
surface and rolling with 8-10 tonne smooth wheeled steel roller)
Case -1 19 mm nominal chipping size sqm 90.00
Case - II 13 mm nominal size chipping sqm 73.00
Item No.
Descriptions Unit Rate (in Rs.)

5.10
Open - Graded Premix Surfacing (Providing, laying and rolling of open - graded premix surfacing
of 20 mm thickness composed of 13.2 mm to 5.6 mm aggregates either using penetration
grade bitumen or cut-back or emulsion to required line, grade and level to serve as wearing
course on a previously prepared base, including mixing in a suitable plant, laying and rolling
with a smooth wheeled roller 8-10 tonne capacity, finished to required level and grades.)
(i) Case - I: Mechanical method using Penetration grade Bitumen and HMP of appropriate capacity
sqm 151.00
not less than 75 tonnes/hour .
(ii) Case - II: Open-Graded Premix Surfacing using cationic Bitumen Emulsion sqm 63.00
5.11
Close Graded Premix Surfacing/Mixed Seal Surfacing (Mechanical means using HMP of
appropriate capacity not less than 75 tonnes/hour. Providing, laying and rolling of close-graded
premix surfacing material of 20 mm thickness composed of 11.2 mm to 0.09 mm (Type-a) or
13.2 mm to 0.09 mm (Type-b) aggregates using penetration grade bitumen to the required
line, grade and level to serve as wearing course on a previously prepared base, including mixing
in a suitable plant, laying and rolling with a Smooth wheeled roller 8-10 tonne capacity, and
finishing to required level and grade. )

i) For Type A sqm 184.00


i) For Type B sqm 172.00
5.12 Seal Coat (Providing and laying seal coat sealing the voids in a bituminous surface laid to the
specified levels, grade and cross fall using Type A and B seal coats)
(i) Case - I : Type A sqm 66.00
(ii) Case - II : Type B (Providing and laying of premix sand seal coat with HMP of appropriate
capacity not less than 75 tonnes/ hours using crushed stone chipping 6.7 mm size and sqm 54.00
penetration bitumen of suitable grade.)
5.13
Supply of Stone Aggregates for Pavement Courses (Supply of stone aggregates from approved
sources confirming to the physical requirement, specified in the respective specified clauses,
including royalties, fees rents, collection, transportation, stacking and testing and measured in
cum as per clause 514.5 Competitive market rates to be ascertained. Alternatively, rates for cum
stone crushing given in chapter 1may be adopted, if found economical. In case for supply of
aggregates at site are not available, nearest crusher site may be ascertained. Loading and un-
loading charges and cost of carriage may be added to these rates to arrive at the cost at site.)
5.14 Mastic Asphalt (Providing and laying 25 mm thick mastic asphalt wearing course with paving
grade bitumen meeting the requirements given in table 500-29, prepared by using mastic
cooker and laid to required level and slope after cleaning the surface, including providing
antiskid surface with bitumen precoated fine-grained hard stone chipping of 13.2 mm nominal sqm 1117.00
size at the rate of 0.005cum per 10 sqm and at an approximate spacing of 10 cm center to
center in both directions, pressed into surface when the temperature of surfaces not less than
1000C, protruding 1 mm to 4 mm over mastic surface, all complete as per clause 515.)
5.15 Slurry Seal Providing and laying slurry seal consisting of a mixture of fine aggregates, portland
cement filler, bituminous emulsion and water on a road surface including cleaning of surface,
sqm
mixing of slurry seal in a suitable mobile plant, laying and compacting to provide even riding
surface)
(i) 5 mm thickness sqm 63.00
(ii) 3 mm thickness sqm 41.00
(iii) 1.5 mm thickness sqm 24.70
5.16 Recycling of Bituminous Pavement with Central Recycling Plant (Recycling pavement by cold
milling of exiting bituminous layers, planning the surface after cold milling, reclaiming excavated
material to the extent of 30 % of the required quantity, hauling and stock piling the reclaimed
material near the central recycling plant after carrying out necessary checks and evaluation, cum 7210.00
adding fresh material including rejuvenators as required, mixing in a hot mix plant, transporting
and laying at site and compacting to the required grade, level and thickness, all as specified in
clause 517.)
5.17 Fog Spray sqm 31.00
added
1.In case it is decided by the engineer to blind the fog spray, the following may be added sqm 7.70
5.18 Bituminous Cold Mix ( Including Gravel Emulsion) (Providing, laying and rolling of bituminous
cold mix on prepared base consisting of a mixture of unheated mineral aggregate and
emulsified or cutback bitumen, including mixing in a plant of suitable type and capacity,
transporting, laying, compacting and finishing to specified grades and levels.)
(i) Using bitumen emulsion and 9.5 mm or 13.2 mm nominal size aggregate cum 10624.00
(ii) Using bitumen emulsion and 19 mm or 26.5 mm nominal size aggregate cum 10627.00
(iii) Using cutback bitumen and 9.5 mm or 13.2 mm nominal size aggregate cum 3820.00
(iv) Using cutback bitumen and 19 mm or 26.5 mm nominal size aggregate cum 3816.00
5.19 Sand Asphalt Base Course (Providing, laying and rolling sand-asphalt base course composed of
sand, mineral filler and bituminous binder on a prepared sub-grade or sub-base to the lines,
cum 9155.00
levels, grades and cross sections as per the drawings including mixing in a plant of suitable type
and capacity, transporting, laying, compacting and finishing.)
Item No.
Descriptions Unit Rate (in Rs.)

5.21 Crack Prevention Courses


(i)
Stress Absorbing Membrane (SAM) crack width less than 6 mm (Providing and laying
of a stress absorbing membrane over a cracked road surface, with crack width below
6 mm after cleaning with a mechanical broom, using modified binder complying with
clause 521, sprayed at the rate of 9 kg per 10 sqm and spreading 5.6 mm crushed sqm 63.00
stone aggregates @ 0.11 cum per 10 sqm with hydraulic chip spreader, sweeping the
surface for uniform spread of aggregates and surface finished to conform to clause
902.)
(ii)
Stress Absorbing Membrane (SAM) with crack width 6 mm to 9 mm (Providing and
laying of a stress absorbing membrane over a cracked road surface, with crack width
6 to 9 mm after cleaning with a mechanical broom, using modified binder complying
sqm 74.00
with clause 521, sprayed at the rate of 11 kg per 10 sqm and spreading 11.2 mm
crushed stone aggregates @ 0.12 cum per 10 sqm, sweeping the surface for uniform
spread of aggregates and surface finished to conform to clause 902.)
(iii)
Stress Absorbing Membrane (SAM) crack width above 9 mm and cracked area above
50 % (Providing and laying a single coat of a stress absorbing membrane over a
cracked road surface, with crack width above 9 mm and cracked area above 50 %
after cleaning with a mechanical broom, using modified binder complying with clause sqm 97.00
521, sprayed at the rate of 15 kg per 10 sqm and spreading 11.2 mm crushed stone
aggregates @ 0.12 cum per 10 sqm, sweeping the surface for uniform spread of
aggregates and surface finished to conform to clause 902.)
(iv) Case - IV : Bitumen Impregnated Geotextile (Providing and laying a bitumen
impregnated geotextile layer after cleaning the road surface, geotextile conforming to
requirements of clause 704.3, laid over a tack coat with 1.05 kg per sqm of paving sqm 229.00
grade bitumen 80 - 100 penetration and constructed to the requirement of clause
704.4.5)
5.22
Recipe Cold Mix (Providing and laying of premix of crushed stone aggregates and
emulsion binder, mixed in a batch type cold mixing plant, laid over prepared surface,
by paver finisher, rolled with a pneumatic tyred roller initially and finished with a
smooth steel wheel roller, all as per clause 519.3)
(i) 75 mm thickness cum 7219.00
(ii) 40 mm thickness cum 9582.00
(iii) 25 mm thickness cum 10440.00
Item No.
Descriptions Unit Rate (in Rs.)

CHAPTER-6
CEMENT CONCRETE PAVEMENTS
Item No.
Descriptions Unit Rate (in Rs.)
6.1
Dry Lean Cement Concrete Sub- base (Construction of dry lean cement concrete Sub-
base over a prepared sub-grade with coarse and fine aggregate conforming to IS:
383, the size of coarse aggregate not exceeding 25 mm, aggregate cement ratio not
to exceed 15:1, aggregate gradation after blending to be as per table 600-1, cement
cum 4676.00
content not to be less than 150 kg/ cum, optimum moisture content to be determined
during trial length construction, concrete strength not to be less than 10 Mpa at 7
days, mixed in a batching plant, transported to site, laid with a paver with electronic
sensor, compacting with 8-10 tonnes vibratory roller, finishing and curing.)
6.2 Cement Concrete Pavement (Construction of un-reinforced, dowel jointed, plain
cement concrete pavement over a prepared sub base with 43 grade cement @ 400 kg
per cum, coarse and fine aggregate conforming to IS 383, maximum size of coarse
aggregate not exceeding 25 mm, mixed in a batching and mixing plant as per
approved mix design, transported to site, laid with a fixed form or slip form paver,
cum 9931.00
spread, compacted and finished in a continuous operation including provision of
contraction, expansion, construction and longitudinal joints, joint filler, separation
membrane, sealant primer, joint sealant, debonding strip, dowel bar, tie rod,
admixtures as approved, curing compound, finishing to lines and grades as per
drawing )
6.3
Rolled Cement Concrete Base (Construction of rolled cement concrete base course
with coarse and fine aggregate conforming to IS:383, the size of coarse aggregate not
exceeding 25 mm with minimum, aggregate cement ratio15:1 and minimum cement
content of 200 kg/cum, aggregate gradation to be as per table 600-4 after blending, cum 5208.00
mixing in batching plant at optimum moisture content, transporting to site, laying with
a paver with electronic sensor, compacting with 8-10 tonnes smooth wheeled
vibratory roller to achieve, the designed flexural strength, finishing and curing.)
6.4 Transition section between rigid and flexible pavement (Due to change in the
properties of materials and type of construction, a gradual changeover from rigid
pavement to flexible pavement is desirable to avoid any damage at the butting joint.
After provision of an expansion joint in the cement concrete slab, the thickness of slab
should be tapered to 10 cm over a length of 3 m towards the flexible pavement. The
deficiency of thickness caused due to tapering of the slab should be made up by the
asphaltic layers.)
6.5 Construction of Base/Sub-base of pavement with lean concrete - fly ash. (Construction
of Base/sub-base using cement, sand, fly ash and coarse aggregates proportioned as
per table 4 of IRC: 74/1979 and with water content ratio, slump and compressive
strength as defined in the said table, mix prepared in a batching and mixing plant and
cum 4523.00
compacted with a vibratory roller 8-10 tonnes capacity within the time limit laid down
vide clause 7.6.3 of IRC: 74-1979, construction joints properly formed at the end of
day's work, cured for 14 days, all as specified in IRC: 74-1979 and as per approved
plans.)
6.6 Cement - Fly ash concrete pavement. (Construction reinforced-reinforced, dowel
jointed, plain cement concrete pavement over a prepared sub base with 43 grade
cement, coarse and fine aggregate conforming to IS 383, maximum size of coarse
aggregate not exceeding 25 mm, replacing cement by fly ash to the extent of 15%
and sand by 10%, mixed in a batching and mixing plant as per approved mix design,
cum 9421.00
transported to site, laid with a fixed form or slip form paver, spread, compacted and
finished in a continuous operation including provision of contraction, expansion,
construction and longitudinal joints, joint filler, separation membrane, sealant primer,
joint sealant, debonding strip, dowel bar, tie rod, admixtures as approved, curing
compound, finishing to lines and grades as per drawing )
Item No.
Descriptions Unit Rate (in Rs.)

CHAPTER-7
GEOSYNTHETICS AND REINFORCED EARTH
Item No.
Descriptions Unit Rate (in Rs.)
7.1 Sub- Surface Drain with Geotextiles (Construction of sub surface drain 200 mm dia using
geotextiles treated with carbon black with physical properties as given in clause 702.2.3 formed
in to a stable network and a planar geocomposite structure, joints wrapped with geotextile to metre 1416.00
prevent ingress of soil, all as per clause 702 and approved drawings including excavation and
backfilling)
7.2 Narrow Filter Sub- Surface Drain (Construction of a narrow filter sub- surface drain consisting of
porous or perforated pipe laid in narrow trench surrounded by a geotextile filter fabric, with a
metre 1053.00
minimum of 450 mm overlap of fabric and installed as per clause 702.3 and 309.3.5 including
excavation and backfilling)
7.3 Laying Paving Fabric Beneath a Pavement Overlay (Providing and laying paving fabric with
physical requirements as per table 704-2 over a tack coat of paving grade Bitumen 80-100
penetration, laid at the rate of 1 kg per sqm over thoroughly cleaned and repaired surface to
sqm 512.00
provide a water resistant membrane and crack retarding layer. Paving fabric to be free of
wrinkling and folding and to be laid before cooling of tack coat, brooming and rolling of surface
with pneumatic roller to maximise paving fabric contact with pavement surface)
7.4
Laying Boulder Apron in Crates of Synthetic Geogrids (Providing, preparing and laying of
geogrid crated apron 1 m x 5 m, 600 mm thick including excavation and backfilling with baffles
at 1 metre interval, made with geogrids having characteristics as per clause 704.2, joining sides
with connectors/ring staples, top corners to be tie tensioned, placing of suitable cross interval
ties in layers of 300 mm connecting opposite side with lateral braces and tied with polymer cum 1329.00
braids to avoid bulging, constructed as per clause 704.3. filled with stone with minimum size of
200 mm and specific gravity not less than 2.65, packed with stone spalls, keyed to the
foundation recess in case of sloping ground and laid over a layer of geotextile to prevent
migration of fines, all as per clause 704 and laid as per clause 2503.3 and approved design.)
7.5
Reinforced Earth Retaining Wall (Reinforced earth retaining walls have four main components
as under: a) Excavation for foundation, foundation concrete and cement concrete grooved
seating in the foundation for facing elements (facia material). b) Facia material and its
placement. c) Assembling, joining with facing elements and laying of the reinforcing elements.
d) Earthfill with granular material which is to be retained by the wall.)

(i) Assembling, joining and laying of reinforcing elements.


A With reinforcing element of steel / Aluminium strips / polymeric strips.
Type 1 1.Galvanised carbon steel strips metre 381.00
Type 2 2.Copper Strips metre 1684.00
Type 3 3.Aluminium Strips metre 757.00
Type 4 4.Stainless steel strips metre 1012.00
Type 5 5.Glass reinforced polymer/fibre reinforced polymer/polymeric strips metre 1012.00
B With reinforcing elements of synthetic geogrids sqm 590.00
(ii) Facing elements of RCC sqm 1529.00
Item No.
Descriptions Unit Rate (in Rs.)

CHAPTER-8
TRAFFIC SIGNS, MARKINGS & OTHER ROAD APPURTENANCES
Item No.
Descriptions Unit Rate (in Rs.)
8.1 Cast in Situ Cement Concrete M20 kerb (Construction of cement concrete kerb with top and
bottom width 115 and 165 mm respectively, 250 mm high in M 20 grade PCC on M-10 grade
foundation 150 mm thick, foundation having 50 mm projection beyond kerb stone, kerb stone
laid with kerb laying machine, foundation concrete laid manually, all complete as per clause
408)
A Using Concrete Mixer metre 362.00
B Using Concrete Batching and Mixing Plant metre 363.00
8.2
Cast in Situ Cement Concrete M 20 Kerb with Channel (Construction of cement concrete kerb
with channel with top and bottom width 115 and 165 mm respectively, 250 mm high in M 20
grade PCC on M10 grade foundation 150 mm thick, kerb channel 300 mm wide, 50 mm thick in
PCC M20 grade, sloped towards the kerb, kerb stone with channel laid with kerb laying
machine, foundation concrete laid manually, all complete as per clause 408)
A Using Concrete Mixer metre 682.00
B Using Concrete Batching and Mixing Plant metre 688.00
8.3 Printing new letter and figures of any shade (Printing new letter and figures of any shade with
synthetic enamel paint black or any other approved colour to give an even shade)
(i)
Hindi ( Matras commas and the like not to be measured and paid for Half letter shall be cm height
0.80
counted as half ) per letter
(ii) cm height
English and Roman 0.50
per letter
8.4 Retro- reflectorised Traffic signs (Providing and fixing of retro- reflectorised cautionary,
mandatory and informatory sign as per IRC :67 made of encapsulated lens type reflective
sheeting vide clause 801.3, fixed over aluminium sheeting, 1.5 mm thick supported on a mild
steel angle iron post 75 mm x 75 mm x 6 mm firmly fixed to the ground by means of properly
designed foundation with M15 grade cement concrete 45 cm x 45 cm x 60 cm, 60 cm below
ground level as per approved drawing)
(i) 90 cm equilateral triangle each 2589.00
( ii ) 60 cm equilateral triangle each 2447.00
( iii ) 60 cm circular each 2540.00
( iv ) 80 mm x 60 mm rectangular each 2684.00
(v) 60 cm x 45 cm rectangular each 2530.00
(vi ) 60 cm x 60 cm square each 2596.00
( vii ) 90 cm high octagon each 2825.00
8.5
Direction and Place Identification signs upto 0.9 sqm size board. (Providing and erecting
direction and place identification retro-reflectorised sign asper IRC:67 made of encapsulated
lens type reflective sheeting vide clause 801.3, fixed over aluminium sheeting, 2 mm thick with
sqm 3335.00
area not exceeding 0.9 sqm supported on a mild steel single angle iron post 75 x 75 x 6 mm
firmly fixed to the ground by means of properly designed foundation with M15 grade cement
concrete 45 x 45 x 60 cm, 60 cm below ground level as per approved drawing)
8.6 Direction and Place Identification signs with size more than 0.9 sqm size board. (Providing and
erecting direction and place identification retro- reflectorised sign asper IRC :67 made of
encapsulated lens type reflective sheeting vide clause 801.3, fixed over aluminium sheeting, 2
mm thick with area exceeding 0.9 sqm supported on a mild steel angle iron post 75 mm x 75 sqm 3831.00
mm x 6 mm, 2 Nos. firmly fixed to the ground by means of properly designed foundation with M
15 grade cement concrete45 cm x 45 cm x 60 cm, 60 cm below ground level as per approved
drawing)
8.7
Overhead Signs (Providing and erecting overhead signs with a corrosion resistant aluminium
alloy sheet reflectorised with high intensity retro-reflective sheeting of encapsulated lense type
with vertical and lateral clearance given in clause 802.2 and 802.3 and installed as per clause
802.7 over a designed support system of aluminium alloy or galvanised steel trestles and
trusses of sections and type as per structural design requirements and approved plans)

A Truss and Vertical Support tonne 142869.00


B Aluminium alloy plate for over head sign tonne 679.00
8.8 Painting Two Coats on New Concrete Surfaces (Painting two coats after filling the surface with
sqm 58.00
synthetic enamel paint in all shades on new plastered concrete surfaces)
8.9 Painting on Steel Surfaces (Providing and applying two coats of ready mix paint of approved
sqm 52.00
brand on steel surface after through cleaning of surface to give an even shade)
8.10 Painting on Wood Surfaces (Providing and applying two coats of ready mix paint of approved
sqm 59.00
brand on wood surface after through cleaning of surface to give an even shade)
Item No.
Descriptions Unit Rate (in Rs.)

8.11 Painting Lines, Dashes, Arrows etc on Roads in Two Coats on New Work (Painting lines,
dashes, arrows etc on roads in two coats on new work with ready mixed road marking paint
conforming to IS:164 on bituminous surface, including cleaning the surface of all dirt, dust and
other foreign matter, demarcation at site and traffic control )
(i) Over 10 cm in width sqm 85.00
(ii) Up to 10 cm in width sqm 72.00
8.12 Painting Lines, Dashes, Arrows etc on Roads in Two Coats on Old Work (Painting lines, dashes,
arrows etc on roads in two coats on old work with ready mixed road marking paint confirming
to IS: 164 on bituminous surface, including cleaning the surface of all dirt, dust and other
foreign matter, demarcation at site and traffic control )
(i) Over 10 cm in width sqm 56.00
(ii) Up to 10 cm in width sqm 60.00
8.13 Road Marking with Hot Applied Thermoplastic Compound with Reflectorising Glass Beads on
Bituminous Surface (Providing and laying of hot applied thermoplastic compound 2.5 mm thick
including reflectorising glass beads @ 250 gms per sqm area, thickness of 2.5 mm is exclusive sqm 655.00
of surface applied glass beads as per IRC:35 .The finished surface to be level, uniform and free
from streaks and holes.)
8.14 Kilo Metre Stone (Reinforced cement concrete M15grade kilometre stone of standard design as
per IRC:8-1980, fixing in position including painting and printing etc)
(i) 5th kilometre stone (precast) each 3970.00
(ii) Ordinary Kilometer stone (Precast) each 2473.00
(iii) Hectometer stone (Precast) each 635.00
8.15
Road Delineators (Supplying and installation of delineators (road way indicators, hazard
markers, object markers), 80-100 cm high above ground level, painted black and white in 15
each 1258.00
cm wide stripes, fitted with 80 x 100 mm rectangular or 75 mm dia circular reflectorised panels
at the top, buried or pressed into the ground and confirming toIRC-79 and the drawings.)
8.16
Boundary pillar (Reinforced cement concrete M15 grade boundary pillars of standard design as
each 636.00
per IRC:25-1967, fixed in position including finishing and lettering but excluding painting)

8.17 G.I Barbed wire Fencing 1.2 metre high (Providing and fixing 1.2 metres high GI barbed wire
fencing with 1.8 m angle iron posts 40 mm x 40 mm x 6 mm placed every 3 metres center to
center founded in M15 grade cement concrete, 0.6 metre below ground level, every 15th post,
metre 341.00
last but one end post and corner post shall be strutted on both sides and end post on one side
only and provided with 9 horizontal lines and 2 diagonals interwoven with horizontal wires, fixed
with GI staples, turn buckles etc complete as per clause 807 )
8.18 G.I Barbed wire Fencing 1.8 metre high (Providing and fixing 1.8 metres high GI barbed wire
fencing with 2.4 m angle iron posts 50 mm x 50 mm x 6 mm placed every 3 metres center to
center founded in M15 grade cement concrete, 0.6 metre below ground level, every 15th post,
metre 558.00
last but one end post and corner post shall be strutted on both sides and end post on one side
only and provided with 12 horizontal lines and 2 diagonals interwoven with horizontal wires,
fixed with GI staples, turn buckles etc complete as per clause 807 )
8.20 Tubular Steel Railing on Medium Weight steel channel ( ISMC series) 100 mm x 50 mm
(Providing, fixing and erecting 50 mm dia steel pipe railing in 3 rows duly painted on medium
metre 2062.00
weight steel channels (ISMC series) 100 mm x 50 mm, 1.2 metres high above ground, 2 m
centre to centre, complete as per approved drawings)
8.21 Tubular Steel Railing on Precast RCC posts, 1.2 m high above ground level (Providing, fencing
and erecting 50 mm dia painted steel pipe railing in 3 rows on precast M20 grade RCC vertical
metre 1532.00
posts1.8 metres high (1.2 m above GL) with 3 holes 50 mm dia for pipe, fixed 2 metres centre
to, complete as per approved drawing)
8.22 Reinforced Cement Concrete Crash Barrier (Provision of an Reinforced cement concrete crash
barrier at the edges of the road, approaches to bridge structures and medians, constructed with
M-20 grade concrete with HYSD reinforcement conforming to IRC:21 and dowel bars 25 mm
dia, 450 mm long at expansion joints filled with pre-moulded asphalt filler board, keyed to the
structure on which it is built and installed as per design given in the enclosure to MOST circular
No. RW/NH - 33022/1/94-DO III dated 24 June 1994 as per dimensions in the approved
drawing and at locations directed by the Engineer, all as specified)
(i) M 20 grade concrete metre 3624.00
Item No.
Descriptions Unit Rate (in Rs.)

8.23 Metal Beam Crash Barrier


A Type - A, "W" : Metal Beam Crash Barrier (Providing and erecting a "W" metal beam crash
barrier comprising of 3 mm thick corrugated sheet metal beam rail, 70 cm above road/ground
level, fixed on ISMC series channel vertical post, 150 x 75 x 5 mm spaced 2 m centre to centre,
1.8 m high, 1.1 m below ground/road level, all steel parts and fitments to be galvanised by hot metre 3572.00
dip process, all fittings to conform to IS:1367 and IS:1364, metal beam rail to be fixed on the
vertical post with a spacer of channel section 150 x 75 x 5 mm, 330 mm long complete as per
clause 810)
B Type - B, "THRIE" : Metal Beam Crash Barrier (Providing and erecting a "Thrie" metal beam
crash barrier comprising of 3 mm thick corrugated sheet metal beam rail, 85 cm above
road/ground level, fixed on ISMC series channel vertical post, 150 x 75 x 5 mm spaced 2 m
centre to centre, 2 m high with 1.15 m below ground level, all steel parts and fitments to be metre 5370.00
galvanised by hot dip process, all fittings to conform to IS:1367 and IS:1364, metal beam rail to
be fixed on the vertical post with a space of channel section 150 x 75 x 5 mm, 546 mm long
complete as per clause 810)
8.25 Flexible Crash Barrier, Wire Rope Safety Barrier (Providing and erecting a wire rope safety
barrier with vertical posts of medium weight RS Joist (ISMB series) 100 mm x 75 mm (11.50
kg/m), 1.50 m long 0.85 m above ground and 0.65 m below ground level, split at the bottom
for better grip, embedded in M 15 grade cement concrete 450 x 450 x 450 mm, 1.50 m center
to center and with 4 horizontal steel wire rope 40 mm dia and anchored at terminal posts 15 m metre 3673.00
apart. Terminal post to be embedded in M 15 gradecementconcretefoundation2400 x 450 x 900
mm (depth), strengthened by a strut of RS joist 100 x 75 mm, 2 m long at 450 inclination and a
tie 100 x 8 mm, 1.50 m long at the bottom, all embedded in foundation concrete as per
approved design and drawing, rate excluding excavation and cement concrete.)
8.26 Anti - Glare Devices in Median
B Anti - Glare Screen with 25 mm steel pipe framework fixed with circular and rectangular vans
(Providing and erecting an anti - glare screen with 25 mm dia vertical pipes fabricated and
framed in the form of panels of one metre length and 1.75 mtr height fixed with circular vane
250 mm dia at top and rectangular vane 600 x 300 mm at the middle, made out of steel sheet metre 3078.00
of 3 mm thickness, end vertical pipes of the panel made larger for embedding in foundation
concrete, applying 2 coats of paint on all exposed surfaces, all as per approved design and
drawings.)
C Anti - Glare Screen with Rectangular Vane of MS sheet (Providing and erecting anti - glare
screen with rectangular vanes of size 750 x 500 mm made from MS sheet, 3 mm thick and fixed
on MS angle 50 x 50 x 6 mm at an angle of 450 to the direction of flow of traffic, 1.5 m center
metre 1050.00
to center, top edge of the screen 1.75 m above ground level, vertical post firmly embedded in
cement concrete foundation 0.60 m below ground level, applying 2 coats of paint on exposed
faces, all complete as per approved design and drawings)
8.27 Street Lighting (Providing and erecting street light mounted on a steel circular hollow pole of
standard specifications for street lighting, 9 m high spaced 40 m apart, 1.8 m overhang on both
sides if fixed in the median and on one side if fixed on the footpath, fitted with sodium vapour
lamp and fixed firmly in concrete foundation.)
(i) For Fixing in Median each 29043.00
(ii) For fixing in Footpath each 28985.00
8.28 Lighting on Bridges (Providing and fixing lighting on bridges, mounted on steel hollow circular
poles of standard specifications, 5 m high fixed on parapets with cement concrete, 20 m apart each 23524.00
and fitted with sodium vapour lamp)
8.29 Cable Duct Across the Road (Providing and laying of a reinforced cement concrete pipe duct,
300 mm dia, across the road (new construction), extending from drain to drain in cuts and toe
of slope to toe of slope in fills, constructing head walls at both ends, providing a minimum fill of
granular material over top and sides of RCC pipe as per IRC:98-1997, bedded on a 0.3 m thick
layer of granular material free of rock pieces, outer to outer distance of pipe at least half dia of
pipe subject to minimum 450 mm in case of double and triple row ducts, joints to be made leak
proof, invert level of duct to be above higher than ground level to prevent entry of water and
dirt, all as per IRC: 98 - 1997 and approved drawings.)
(ii) Double Row for two utility services metre 3854.00
Item No.
Descriptions Unit Rate (in Rs.)

8.30
Highway Patrolling and Traffic Aid Post (It is proposed to locate one Traffic Aid Post every 50-60
km of the highway. )
8.31
Items related to under pass/ subway/ overhead bridge/ overhead foot bridge (The items
involved for underpass/ subway/ overhead bridge/ overhead foot bridge are earthwork, plain
cement concrete, plastering, painting, information sign etc. The rates for these items are
available in respective chapters which can be adopted for the quantities derived from the
approved designs and drawings)

8.32 Traffic Control System and Communication system (Providing a traffic control centre and
communication system including telecommunication facilities and related accessories, CCTV,
radar, vehicle detection camera, central computer system These are specialised item of
telecommunication system and are the commercial products. The designer is required to
contact the manufacturers to ascertain market prices. In case of civil works required to be
executed for these installations, pricing may be done as per rates in relevant chapters for
quantities derived approved design and drawing.)
8.33 Gantry Mounted Variable Message Sign board (Providing and erecting gantry mounted variable
message sign board electronically operated capable of flashing the desired message over a
designed support system of aluminium alloy or galvanised steel, erected as per approved design
and drawings and with lateral clearance as per clause 802.3)
(i) Gantry Support System tonne 140833.00
(ii) Message Display (Message display board 6 sqm electronically operated with complete electronic
fitments for flashing the pre-determined messages.)
8.34 Traffic Impact Attenuators at Abutments and Piers
A
With Scrap Tyres (Provision and installation of traffic attenuators at abutment/pier of flyovers
bridges using scrap tyres of size 100 x 20 retrieved from trucks laid in 2 rows and 4 tiers, one sqm 1720.00
above the other and tied with 20 mm wire rope as per approved design and drawings.)
B
Using Plastic/Steel Barrel, Filled with Sand (Provision and installation of traffic impact attenuator
at abutment/pier of flyovers bridges using plastic/steel barrels 0.60 m dia and 1.0 m in height,
sqm 995.00
filled with sand in three rows and tied with20 mm steel wire rope as per approved design and
drawings)
C With HI - DRO cell Sandwich (Patented) ((In this patented HI - DRO cell system, water gets
discharged from plastic tubes on impact over a pre-determined time, thus absorbing the sqm 2645.00
energy))
8.35
Road Markers/Road Stud with Lense Reflector (Providing and fixing of road stud 100x 100 mm,
die cast in aluminium, resistant to corrosive effect of salt and grit, fitted with lense reflectors,
each 677.00
installed in concrete or asphaltic surface by drilling hole 30 mm upto a depth of 60 mm and
bedded in a suitable bituminous grout or epoxy mortar, all as per BS 873 part 4:1973)
8.36 Traffic Cone (Provision of red fluorescent with white reflective sleeve traffic cone made of low
density polyethylene (LDPE) material with a square base of 390 x 390 x 35 mm and a height of each 2203.00
770 mm, 4 kg in weight, placed at 1.5 m interval, all as per BS 873)
Item No.
Descriptions Unit Rate (in Rs.)

8.43
Portable Barricade in Construction Zone (Installation of a steel portable barricade with
horizontal rail 300 mm wide, 2.5 m in length fitted on a 'A' frame made with 45 x 45 x 5 mm
angle iron section, 1.5 m in height, horizontal rail painted (2 coats) with yellow and white each 3386.00
stripes, 150 mm in width at an angle of 450, 'A' frame painted with 2 coats of yellow paint,
complete as per IRC: SP : 55-2001 )

8.44 Permanent Type Barricade in Construction Zone


A
With Steel Components (Construction of a permanent type barricade made of steel
components, 1.5 m high from road level, fitted with 3 horizontal rails 200 mm wide and 4 m
each 5351.00
long on 50 x 50 x 5 mm angle iron vertical support, painted with yellow and white strips, 150
mm in width at an angle of450, complete as per IRC:SP:55-2001 )

B
With Wooden Components (Construction of a permanent type barricade made of wooden
components, 1.5 m high from road level, fitted with 3 horizontal planks 200 mm wide and 3.66
each 7347.00
m long on 100 x 100mm wooden vertical post, painted with yellow and white striups, 150 mm
in width at an angle of450, complete as per IRC:SP:55-2001 )

C
With Bricks (Construction of a permanent type barricade made with brick work in mud mortar,
1.5 m high, 4 m long, 600 mm thick, plastered with cement mortar 1:6, painted with yellow each 20137.00
and white strips)

8.45
Drum Delineator in Construction Zone (Provision of metal drum/empty bitumen drum
delineator, 300 mm in diameter, 800 mm high, filled with earth for stability, painted in
each 355.00
circumferential strips of alternate black and white 100 mm wide fitted with reflectors 3 Nos of
7.5 cm dia, all as per IRC:SP:55-2001)

8.46
Flagman (Positioning of a smart flagman with a yellow vest and a yellow cap and a red flag 600
each 341.00
x 600 mm securely fastened to a staff 1 m in length for guiding the traffic)
Item No.
Descriptions Unit Rate (in Rs.)

CHAPTER-9
PIPE CULVERTS
Item No.
Descriptions Unit Rate (in Rs.)

9.1 PCC 1:3:6 in Foundation (Plain cement concrete 1:3:6 mix with crushed stone aggregate 40
mm nominal size mechanically mixed, placed in foundation and compacted by vibration cum 5237.00
including curing for 14 days.)
9.2 Laying Reinforced Cement Concrete Pipe NP4/prestrssed concrete pipe on first class bedding in
single row . (Laying Reinforced cement concrete pipe NP4/prestrssed concrete pipe for culverts
on first class bedding of granular material in single row including fixing collar with cement
mortar 1:2 but excluding excavation, protection works, backfilling, concrete and masonry
works in head walls and parapets . )
A
1000 mm dia metre 8004.00
B
1200 mm dia metre 12989.00
9.3 Laying Reinforced Cement Concrete Pipe NP 4 /prestrssed concrete pipe on first class bedding
in double row . (Laying Reinforced cement concrete pipe NP4 /prestrssed concrete pipe for
culverts on first class bedding of granular material in double row including fixing collar with
cement mortar 1:2 but excluding excavation, protection works, backfilling, concrete and
masonry works in head walls and parapets . )
A
1000 mm dia metre 16334.00
B
1200 mm dia metre 26326.00
Item No.
Descriptions Unit Rate (in Rs.)

CHAPTER-10
MAINTENANCE OF ROADS
Item No.
Descriptions Unit Rate (in Rs.)
10.1 Restoration of Rain Cuts (Restoration of rain cuts with soil, moorum, gravel or a mixture of
these, clearing the loose soil, benching for 300 mm width, laying fresh material in layers not
cum 99.00
exceeding 250 mm and compacting with plate compactor or power rammers to restore the
original alignment, levels and slopes)
10.2 Maintenance of Earthen Shoulder (filling with fresh soil) (Making up loss of material/
irregularities on shoulder to the design level by adding fresh approved soil and compacting it sqm 54.00
with appropriate equipment.)
10.3 Maintenance of Earth Shoulder (stripping excess soil) (Stripping excess soil from the shoulder
sqm 17.00
surface to achieve the approved level and compacting with plate compactor)
10.4
Filling Pot- holes and Patch Repairs with open - graded Premix surfacing, 20mm. (Removal of
all failed material, trimming of completed excavation to provide firm vertical faces, cleaning of
surface, painting of tack coat on the sides and base of excavation as per clause 503, back sqm 148.00
filling the pot holes with hot bituminous material as per clause 511, compacting, trimming and
finishing the surface to form a smooth continuous surface, all as per clause 3004.2)
10.5 Filling Pot- holes and Patch Repairs with - Bituminous concrete, 40mm. (Removal of all failed
material, trimming of completed excavation to provide firm vertical faces, cleaning of surface,
painting of tack coat on the sides and base of excavation as per clause 503, back filling the pot
holes with hot bituminous material as per clause 504, compacting, trimming and finishing the
surface to form a smooth continuous surface, all as per clause 3004.2)
(i) for grading I Material sqm 391.00
(ii) for grading II Material sqm 392.00
10.6 Crack Filling (Filling of crack using slow - curing bitumen emulsion and applying crusher dust in
metre 3.00
case crack are wider than 3mm.)
10.7 Dusting (Applying crusher dust to areas of road where bleeding of excess bitumen has
sqm 1.10
occurred.)
10.8 A Fog Seal (ref item 5.17) sqm 31.00
B Crack Prevention courses. (ref item 5.21)
(i) Stress Absorbing Membrane (SAM) crack width less than 6 mm sqm 63.00
(ii) Stress Absorbing Membrane (SAM) with crack width 6 mm to 9 mm sqm 74.00
(iii)
Stress Absorbing Membrane (SAM) crack width above 9 mm and cracked area above 50 % sqm 97.00
(iv) Bitumen Impregnated Geotextile sqm 229.00
C Slurry Seal (ref item 5.15)
(i) 5 mm thickness sqm 63.00
(ii) 3 mm thickness sqm 41.00
(iii) 1.5 mm thickness sqm 24.70
D Surface Dressing for maintance works. (ref item 5.9)
(i) 19 mm nominal chipping size sqm 90.00
(ii) 13 mm nominal size chipping sqm 73.00
10.9 Repair of joint Grooves with Epoxy Mortar Repair of spalled joint grooves of contraction joints,
longitudinal joints and expansion joints in concrete pavements using epoxy mortar or epoxy metre 1351.00
concrete)
10.10 Repair of old Joints Sealant (Removal of existing sealant and re sealing of contraction,
metre 104.00
longitudinal or expansion joints in concrete pavement with fresh sealant material)
10.11 Hill Side Drain Clearance (Removal of earth from the choked hill side drain and disposing it on
metre 21.30
the valley side manually)
10.12 Land Slide Clearance in soil (Clearance of land slides in soil and ordinary rock by a bull-dozer D
cum 77.00
80 A-12, 180 HP and disposal of the same on the valley side)
10.13 Land slide Clearance in Hard Rock Requiring Blasting (Clearing of land slide in hard rock
cum 122.00
requiring blasting for 50% of the boulders and disposal of the same on the valley side.)
10.14 Snow Clearance on Roads with Dozer (Snow clearance from road surface by a bull- dozer 165
cum 5.30
Hp and disposing it on the valley side)
10.15 Snow Clearance on Roads with Snow Blowers (Snow clearance from road surface by a snow
cum 2.00
blower and disposing on the valley side.)
Item No.
Descriptions Unit Rate (in Rs.)

CHAPTER-11
HORTICULTURE
Item No.
Descriptions Unit Rate (in Rs.)
11.1 Spreading of Sludge Farm Yard Manure or/and good Earth (Spreading of sludge farm yard
manure or/ and good earth in required thickness (cost of sludge, farm- yard manure or/and cum 13.20
good earth to be paid for separately))
11.2 Grassing with ' Doobs' Grass (Grassing with 'Doobs' grass including watering and maintenance
of the lawn for 30 days or more till the grass forms a thick lawn free from weeds and fit for
moving including supplying good earth if needed)
(i) In rows 15 cm apart in either direction sqm 39.20
(ii) In rows 7.5 cm apart in either direction sqm 74.10
11.3 Making Lawns including Ploughing and Dragging with 'Swagha' Breaking of Clod (Making lawns
including ploughing and breaking of clod, removal of rubbish, dressing and supplying doobs
sqm 51.60
grass roots and planting at 15 cm apart, including supplying and spreading of farm yard
manure at rate of 0.18 cum per 100 sqm)
11.4 Maintenance of Lawns or Turfing of Slopes (Maintenance of lawns or Turfing of slopes (rough
sqm 180.00
grassing) for a period of one year including watering etc)
11.5 Turfing Lawns with Fine Grassing including Ploughing, Dressing (Turfing lawns with fine
grassing including ploughing, dressing including breaking of clods, removal of rubbish,
sqm 54.80
dressing and supplying doobs grass roots at 10 cm apart, including supplying and spreading of
farm yard manure at rate of0.6 cum per 100 sqm)
11.6 Maintenance of Lawns with Fine Grassing for the First Year sqm 191.00
11.7 a) Planting Permanent Hedges including Digging of Trenches (Planting permanent hedges
including digging of trenches, 60 cm wide and 45 cm deep, refilling the excavated earth mixed
metre 162.00
with farmyard manure, supplied at the rate of 4.65 cum per 100 metres and supplying and
planting hedge plants at 30 cm apart)
(b) Maintenance of Hedge for one year metre 133.00
11.8 a) Planting Flowering Plants and Shrubs in Central Verge km 56034.00
(b) Maintenance of Flowering Plants and Shrubs in Central Verge for one Year km 153446.00
11.9 Planting of Trees and their Maintenance for one Year (Planting of trees by the road side
(Avenue trees) in 0.60 m dia holes, 1 m deep dug in the ground, mixing the soil with decayed
each 744.00
farm yard/sludge mannure, planting the saplings, backfilling the trench, watering, fixing the
tree guard and maintaining the plants for one year)
11.10
Renovation Lawns including, Weeding, Forking the Ground, Top Dressing with Forked Soil
(Renovation lawns including, weeding, forking the ground, top dressing with forked soil,
watering and maintenance the lawns, for 30 days or more, till the grass forms a thick lawn, sqm 11.00
free from weeds, and fit for moving and disposal of rubbish as directed, including supplying
good earth, if needed but excluding the cost of well decayed farm yard manure)
11.11 Supply at Site Well Decayed Farm Yard Manure (Supply at site of work well decayed farm yard
manure, from any available source, approved by the engineer in charge including screening cum 117.00
and stacking)
11.14 Half Brick Circular Tree Guard, in 2nd class Brick, internal diametre 1.25 metres, and height
1.2 metres, above ground and 0.20 metre below ground (Half brick circular tree guard, in 2nd
class brick, internal diametre 1.25 metres, and height 1.2 metres, above ground and 0.20
each 2547.00
metre below ground, bottom two courses laid dry, and top three courses in cement mortar 1:6
( 1 cement 6 sand) and the intermediate courses being in dry honey comb masonry, as per
design complete)
11.15 Edging with 2nd class Bricks, laid dry lengthwise (Edging with 2nd class bricks, laid dry
lengthwise, including excavation, refilling, consolidation, with a hand packing and spreading metre 52.00
nearly surplus earth within a lead of 50 metres)
11.16
Making Tree Guard 53 cm dia and 1.3 m high as per design from empty bitumen drum (Making
tree guard 53 cm dia and 1.3 m high as per design from empty bitumen drum, slit suitably to
each 345.00
permit sun and air, (supplied by the department at stock issue rate) including providing and
fixing 2 nos MS sheet rings 50 x 0.5 mm with rivets, complete in all respect)
11.17
Making Tree Guard 53 cm dia and 2 metres high as per design from empty bitumen drums
(Making tree guard 53 cm dia and 2 metres high as per design from empty bitumen drums, slit
suitably to permit sun and air, ( supplied by the department at stock issue rate) including each 698.00
providing and fixing four legs 40 cm long of 30 x 3 mm MS riveted to tree guard and providing
and fixing 2 nos MS sheet rings 50 x 0.5 mm with rivets complete in all respects)
Item No.
Descriptions Unit Rate (in Rs.)

11.18 Wrought Iron and Mild Steel Welded Work (Wrought iron and mild steel welded work) (using
angles, square bars, tees and channel grills, grating frames, gates and tree guards of any
size and design etc. including cost of screens and welding rods or bolts and nuts complete fixed quintal 9202.00
in position but without the cost of excavation and concrete for fixing which will be paid
separately)
11.19 Tree Guard with MS Iron (Providing and fixing MS iron tree guard 60 cm dia and 2 metre high
above ground level formed of 4 Nos (25 x 6 mm) and 8 Nos (25 x 3 mm) vertical MS riveted to
each tree
3 Nos (25 x 6 mm) iron rings in two halves, bolted together with 8 mm dia and 30 mm long 2333.00
guard
bolts including painting two coats with paint of approved brand over a coat of priming,
complete in all respects.)
11.20
Tree Guard with MS Angle Iron and Steel Wire (Providing and fixing tree guard 0.60 metre
each tree
square, 2.00 metre high fabricated with MS angle iron 30 x 30 x 3 mm, MS iron 25 x 3 mm 3283.00
guard
and steel wire3 mm dia welded and fabricated as per design in two halves bolted together)
11.21
Compensatory Afforestation (Planting trees as compensatory afforestation at the rate of 290
trees per hectare at a spacing of 6 m by grubbing and leveling the ground upto a depth of 150
hectare 104674.00
mm, digging holes 0.9 m dia, 1 m deep, mixing farm yard/sludge manure with soil, planting
of sapling 2 m high with 25 cm dia stem, backfilling the hole and watering)
Item No.
Descriptions Unit Rate (in Rs.)

CHAPTER-12
FOUNDATIONS
Item No.
Descriptions Unit Rate (in Rs.)
12.1 Excavation for Structures (Earth work in excavation of foundation of structures as per drawing
and technical specification, including setting out, construction of shoring and bracing, removal
of stumps and other deleterious matter, dressing of sides and bottom and backfilling with
approved material.)
I Ordinary soil
A Manual Means
(i) upto 3 m depth cum 80.00
(ii) 3 m to 6 m depth cum 103.00
(iii) Above 6 m depth cum 137.00
B Mechanical Means
(i) Depth upto 3 m cum 63.00
(ii) Depth 3 m to 6 m cum 72.00
(iii) Depth above 6m cum 87.00
II Ordinary rock (not requiring blasting)
A Manual Means
(i) Depth upto 3 m cum 114.00
B Mechanical Means cum 82.00
III Hard rock ( requiring blasting )
A Manual Means cum 335.00
IV Hard rock ( blasting prohibited )
A Mechanical Means cum 390.00
V Marshy soil
(i) upto 3 m depth
A Manual means cum 368.00
B Mechanical Means cum 114.00
VI Back Filling in Marshy Foundation Pits cum 288.00
12.2 Filling Annular Space Around Footing in Rock (Lean cement concrete 1:3:6 nominal mix. Rate
may be taken as per items 13.4.)
12.3 Sand Filling in Foundation Trenches as per Drawing & Technical Specification cum 2202.00
12.4 PCC 1:3:6 in Foundation (Plain cement concrete 1:3:6 nominal mix in foundation with crushed
stone aggregate 40 mm nominal size mechanically mixed, placed in foundation and compacted cum 6082.00
by vibration including curing for 14 days.)
12.5 Brick masonry work in cement mortar in foundation complete excluding pointing and plastering,
as per drawing and technical specifications
(i) Rate for Brick Work in C. M. 1:2 in foundation cum 8823.00
(ii) Rate for Brick Work in C. M. 1:3 in foundation cum 8390.00
(iii) Rate for Brick Work in C. M. 1:4 in foundation cum 8093.00
(iv) Rate for Brick Work in C. M. 1:6 in foundation cum 7847.00
12.6 A Cement mortar1:3 (1cement :3 sand) cum 5945.00
B Cement mortar1:2 (1cement :2 sand) cum 7256.00
C Cement mortar1:4 (1cement :4 sand) cum 5044.00
D Cement mortar1:6 (1cement :6 sand) cum 4298.00
12.7 Stone masonry work in cement mortar 1:3 in foundation complete as drawing and Technical
Specification
(a) Square Rubble Coursed rubble masonry( first sort ) cum 5309.00
(b) Random Rubble Masonry cum 4391.00
12.8 Plain/Reinforced cement concrete in open foundation complete as per drawing and technical
specifications
A PCC Grade M15 cum 7004.00
B PCC Grade M20 cum 7776.00
Item No.
Descriptions Unit Rate (in Rs.)

C RCC Grade M20


Case I Using concrete mixer cum 7879.00
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 8184.00
D PCC Grade M25
Case I Using concrete Mixer cum 8463.00
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 8772.00
E RCC Grade M25
Case I Using concrete Mixer cum 8574.00
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 8878.00
F PCC Grade M30
Case I Using Concrete Mixer cum 8519.00
Case II Using Batching Plant, Transit Mixer and Concrete Pump cum 8820.00
G RCC Grade M30
Case I Using Concrete Mixer cum 8596.00
Case II Using Batching Plant, Transit Mixer and Concrete Pump cum 8901.00
H RCC Grade M35
Case I Using Concrete Mixer cum 8748.00
Case II Using Batching Plant, Transit Mixer and Concrete Pump cum 9053.00
12.9 Providing and constructing temporary island 16 m diameter for construction of well foundation
for 8m dia. Well.
A Assuming depth of water 1.0 m and height of island to be 1.25m including Royality for earth @
each 71034.00
Rs. 3768.00 for each Island.
B Assuming depth of water 4.0 m and height of island 4.5 m including Royality for earth @ Rs.
each 1085159.00
13565.00 for each Island.
C
Providing and constructing one span service road to reach island location from one pier location
metre 3029.00
to another pier location including Royality for earth @ Rs. 225.00 per m for service Road.

12.10 Providing and laying cutting edge of mild steel weighing 40 kg per metre for well foundation
tonne 109123.00
complete as per drawing and technical specification.
12.11 Plain/Reinforced cement concrete, in well foundation complete as per drawing and technical
specification
A Well curb
(i) RCC M20 Grade
Case I Using concrete mixer cum 9092.00
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 8877.00
(ii) RCC M25 Grade
Case I Using concrete mixer cum 9918.00
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 10270.00
(iii) RCC M35 Grade
Case I Using concrete mixer cum 10194.00
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 11012.00
B Well steining
(I) PCC M15 Grade cum 7410.00
(ii) PCC M20 Grade cum 8225.00
(iii) RCC M20 Grade
Case I Using concrete mixer cum 8334.00
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 8137.00
(iv) PCC M25 Grade
Case I Using concrete mixer cum 8974.00
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 8782.00
(v) RCC M25 Grade
Case I Using concrete mixer cum 9092.00
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 9414.00
(vi) PCC M30 Grade
Case I Using concrete mixer cum 9054.00
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 8856.00
Item No.
Descriptions Unit Rate (in Rs.)

(vii) RCC M30 Grade


Case I Using concrete mixer cum 9137.00
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 9461.00
(viii) RCC M35 Grade
Case I Using concrete mixer cum 9344.00
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 10094.00
(ix) RCC M40 Grade 10209.00
C Bottom Plug
(i) PCC Grade M20
Case I Using Concrete Mixer cum 8675.00
Case II Using Batching Plant, Transit Mixer and Crane/concrete pump cum 8809.00
(ii) PCC Grade M25
Case I Using Concrete Mixer cum 9102.00
Case II Using Batching Plant, Transit Mixer and Crane/concrete pump cum 9232.00
(iii) PCC Grade M30
Case I Using Concrete Mixer cum 9179.00
Case II Using Batching Plant, Transit Mixer and Crane/concrete pump cum 9313.00
(iv) PCC Grade M35
Case I Using Concrete Mixer cum 9360.00
Case II Using Batching Plant, Transit Mixer and Crane/concrete pump cum 9490.00
D Intermediate plug
(I) Grade M20 PCC
Case I Using Concrete Mixer cum 8289.00
Case II Using Batching Plant, Transit Mixer and Crane/concrete pump cum 8434.00
(ii) Grade M25 PCC
Case I Using Concrete Mixer cum 8694.00
Case II Using Batching Plant, Transit Mixer and Crane/concrete pump cum 8837.00
(iii) Grade M30 PCC
Case I Using Concrete Mixer cum 8768.00
Case II Using Batching Plant, Transit Mixer and Crane/concrete pump cum 8916.00
E Top plug
(i) Grade M15 PCC
Case I Using Concrete Mixer cum 6736.00
(ii) Grade M20 PCC
Case I Using Concrete Mixer cum 7477.00
(iii) Grade M25 PCC
Case I Using Concrete Mixer cum 8158.00
Case II Using Batching Plant, Transit Mixer and Crane/concrete pump cum 7983.00
(iv) Grade M30 PCC
Case I Using Concrete Mixer cum 8231.00
Case II Using Batching Plant, Transit Mixer and Crane/concrete pump cum 8051.00
F Well cap
(i) RCC Grade M20
Case I Using concrete Mixer cum 7802.00
Case II Using Batching Plant, Transit Mixer and Concrete Pump cum 8105.00
(ii) RCC Grade M25
Case I Using concrete Mixer cum 8574.00
Case II Using Batching Plant, Transit Mixer and Concrete Pump cum 8880.00
(iii) RCC Grade M30
Case I Using Concrete Mixer cum 8596.00
Case II Using Batching Plant, Transit Mixer and Concrete Pump cum 8900.00
Item No.
Descriptions Unit Rate (in Rs.)

(iv) RCC Grade M35


Case I Using Concrete Mixer cum 8748.00
Case II Using Batching Plant, Transit Mixer and Concrete Pump cum 9053.00
(v) RCC M40 Grade cum 9623.00
12.12
Sinking of 6 m external diameter well ( other than pneumatic method of sinking ) through all
types of strata namely sandy soil, clayey soil and rock as shown against each case, complete
as per drawing and technical specifications. Depth of sinking is reckoned from bed level.
A Sandy soil
(i) Depth below bed level upto 3.0 M metre 5092.00
(ii) Beyond 3m upto 10m depth metre 7419.00
(iii) Beyond 10m upto 20m
a
Add 5% for every additional meter depth of sinking over the rate of sinking for the previous
metre 9798.00
meter

(iv) Beyond 20m upto 30 m


a Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous
metre 18377.00
meter
b Add 20% of cost for Kentledge including supports, loading arrangement and Labour . 22052.00
(v) Beyond 30m upto 40 m metre
a Add 10% for every additional meter depth of sinking over the rate of sinking for the previous
43664.00
meter
b Add 20% of cost for Kentledge including supports, loading arrangement and Labour . metre 52396.00
B Clayey soil ( 6m dia. Well )
(i) Depth below bed level upto 3.0 M metre 7443.00
(ii) Beyond 3m upto 10m depth metre 15896.00
(iii) Beyond 10 m upto 20 m
a Add 5% for every additional meter depth of sinking over the rate of sinking for the previous
metre 20993.00
meter
b Add for dewatering @ 5% of cost, if required. metre 22043.00
(iv) Beyond 20m upto 30 m
a Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous
metre 39377.00
meter
b Add 5% of cost for dewatering of the cost, if required metre 51682.00
c
Add 25% of cost for Kentledge including supports, loading arrangement and Labour ). metre 49221.00
(v) Beyond 30m upto 40 m
a Add 10% for every additional meter depth of sinking over the rate of sinking for the previous
metre 93553.00
meter
b Add 5% of cost for dewatering, if required metre 117877.00
c Add 20% of cost for Kentledge including supports, loading arrangement and Labour). metre 112263.00
C Soft rock (6m dia well )
(i) Depth of soft rock strata upto 3m metre 17515.00
D Hard rock (6m dia well )
(i) Depth of soft rock strata upto 3m metre 20899.00
12.13
Sinking of 7 m external diameter well ( other than pneumatic method of sinking ) through all
types of strata namely sandy soil, clayey soil and rock as shown against each case, complete
as per drawing and technical specifications. Depth of sinking is reckoned from bed level.

A Sandy soil
(i) Depth below bed level upto 3.0 M metre 7946.00
(ii) Beyond 3m upto 10m depth metre 10800.00
(iii) Beyond 10m upto 20m
a Add 5% for every additional meter depth of sinking over the rate of sinking for the previous
metre 14263.00
meter
(iv) Beyond 20m upto 30 m
a Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous
metre 26753.00
meter
b
Add 20% of cost for Kentledge including supports, loading arrangement and Labour) . metre 32104.00
Item No.
Descriptions Unit Rate (in Rs.)

(v) Beyond 30m upto 40 m


a Add 10% for every additional meter depth of sinking over the rate of sinking for the previous
metre 63562.00
meter
b
Add 20% of cost for Kentledge including supports, loading arrangement, and Labour etc. metre 76275.00
B Clayey soil ( 7m dia. Well )
(I) Depth below bed level upto 3.0 M metre 10800.00
(ii) Beyond 3m upto 10m depth metre 16052.00
(iii) Beyond 10 m upto 20 m
a Add 5% for every additional meter depth of sinking over the rate of sinking for the previous
metre 21199.00
meter
b Add for dewatering @ 5% of cost, if required. metre 22259.00
(iv) Beyond 20m upto 30 m
a
Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous
metre 39764.00
meter

b Add 5% of cost for dewatering on the cost, if required metre 52190.00


c
Add 25% of cost for Kentledge including supports, loading arrangement and Labour ). metre 49705.00
(v) Beyond 30m upto 40 m
a Add 10% for every additional meter depth of sinking over the rate of sinking for the previous
metre 94474.00
meter
b Add 5% of cost for dewatering, if required metre 119037.00
c Add 20% of cost for Kentledge including supports, loading arrangement and Labour). 113369.00
C Soft rock ( 7m dia well )
(i) Depth of soft rock strata upto 3m metre 16453.00
D Hard rock ( 7m dia well )
(i) Depth upto 3 m metre 23171.00
12.14
Sinking of 8 m external diameter well ( other than pneumatic method of sinking ) through all
types of strata namely sandy soil, clayey soil and rock as shown against each case, complete
as per drawing and technical specifications. Depth of sinking is reckoned from bed level.
A Sandy soil
(i) Depth below bed level upto 3.0 M metre 9746.00
(ii) Beyond 3m upto 10m depth metre 12092.00
(iii) Beyond 10m upto 20m
a Add 5% for every additional meter depth of sinking over the rate of sinking for the previous
metre 15970.00
meter
(iv) Beyond 20m upto 30 m
a Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous
metre 29955.00
meter
b Add 20% of cost for Kentledge including supports, loading arrangement and Labour . metre 35946.00
(v) Beyond 30m upto 40 m
a Add 10% for every additional meter depth of sinking over the rate of sinking for the previous
metre 71170.00
meter
b
Add 20% of cost for Kentledge including supports, loading arrangement, and Labour etc. metre 85404.00
B Clayey soil ( 8m dia. Well )
(i) Depth upto 3.0 M metre 13216.00
(ii) Beyond 3m upto 10m depth metre 16495.00
(iii) Beyond 10 m upto 20 m
a Add 5% for every additional meter depth of sinking over the rate of sinking for the previous
metre 21783.00
meter
b
Add for dewatering @ 5% of cost, if required. metre 22872.00
(iv) Beyond 20m upto 30 m
a Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous
metre 40859.00
meter
b Add 5% of cost for dewatering on the cost, if required metre 53627.00
Item No.
Descriptions Unit Rate (in Rs.)

c
Add 25% of cost for Kentledge including supports, loading arrangement and Labour ). metre 51074.00
(v) Beyond 30m upto 40 m
a Add 10% for every additional meter depth of sinking over the rate of sinking for the previous
metre 97075.00
meter
b Add 5% of cost for dewatering, if required metre 122315.00
c
Add 20% of cost for Kentledge including supports, loading arrangement and Labour). metre 116490.00
C Soft rock ( 8m dia well )
(i) Depth in soft rock strata upto 3m metre 18274.00
D Hard rock ( 8m dia well )
(i) Depth in hard rock strata upto 3 m metre 22710.00
12.15
Sinking of 9 m external diameter well ( other than pneumatic method of sinking ) through all
types of strata namely sandy soil, clayey soil and rock as shown against each case, complete
as per drawing and technical specifications. Depth of sinking is reckoned from bed level.
A Sandy soil
(i) Depth below bed level upto 3.0 M metre 9812.00
(ii) Beyond 3m upto 10m depth metre 13276.00
(iii) Beyond 10m upto 20m
a Add 5% for every additional meter depth of sinking over the rate of sinking for the previous
metre 17534.00
meter
(iv) Beyond 20m upto 30 m
a Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous
metre 32889.00
meter
b Add 20% of cost for Kentledge including supports, loading arrangement and Labour . metre 39467.00
(v) Beyond 30m upto 40 m
a Add 10% for every additional meter depth of sinking over the rate of sinking for the previous
metre 78142.00
meter
b
Add 20% of cost for Kentledge including supports, loading arrangement, and Labour etc. metre 93770.00
B Clayey soil ( 9m dia. Well )
(i) Depth below bed level upto 3.0 M metre 13897.00
(ii) Beyond 3m upto 10m depth metre 17805.00
(iii) Beyond 10 m upto 20 m
a Add 5% for every additional meter depth of sinking over the rate of sinking for the previous
metre 23515.00
meter
b Add for dewatering @ 5% of cost, if required. metre 24691.00
(iv) Beyond 20m upto 30 m
a Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous
metre 44108.00
meter
b Add 5% of cost for dewatering on the cost, if required metre 57891.00
c
Add 25% of cost for Kentledge including supports, loading arrangement and Labour ). metre 55135.00
(v) Beyond 30m upto 40 m
a Add 10% for every additional meter depth of sinking over the rate of sinking for the previous
metre 104794.00
meter
b Add 5% of cost for dewatering, if required metre 132040.00
c Add 20% of cost for Kentledge including supports, loading arrangement and Labour). metre 125753.00
C Soft rock ( 9m dia well )
(i) Depth upto 3m metre 23424.00
D Hard rock ( 9m dia well )
(i) Depth of hard rock strata upto 3 m metre 26367.00
Item No.
Descriptions Unit Rate (in Rs.)

12.16
Sinking of 10 m external diameter well ( other than pneumatic method of sinking ) through all
types of strata namely sandy soil, clayey soil and rock as shown against each case, complete
as per drawing and technical specifications. Depth of sinking is reckoned from bed level.
A Sandy soil
(i) Depth below bed level upto 3.0 M metre 11985.00
(ii) Beyond 3m upto 10m depth metre 13966.00
(iii) Beyond 10m upto 20m
a Add 5% for every additional meter depth of sinking over the rate of sinking for the previous
metre 18444.00
meter
(iv) Beyond 20m upto 30 m
a Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous
metre 34598.00
meter
b Add 20% of cost for Kentledge including supports, loading arrangement and Labour . metre 41517.00
(v) Beyond 30m upto 40 m
a Add 10% for every additional meter depth of sinking over the rate of sinking for the previous
metre 82202.00
meter
b
Add 20% of cost for Kentledge including supports, loading arrangement, and Labour etc. metre 98642.00
B Clayey soil (10m dia. Well )
(i) Depth below bed level upto 3.0 M metre 14937.00
(ii) Beyond 3m upto 10m depth metre 17194.00
(iii) Beyond 10 m upto 20 m
a Add 5% for every additional meter depth of sinking over the rate of sinking for the previous
metre 22708.00
meter
b Add for dewatering @ 5% of cost, if required. metre 23844.00
(iv) Beyond 20m upto 30 m
a Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous
metre 42596.00
meter
'b Add 5% of cost for dewatering on the cost, if required metre 55907.00
c
Add 25% of cost for Kentledge including supports, loading arrangement and Labour ). metre 53245.00
(v) Beyond 30m upto 40 m
a Add 10% for every additional meter depth of sinking over the rate of sinking for the previous
metre 101201.00
meter
b Add 5% of cost for dewatering, if required metre 127514.00
c Add 20% of cost for Kentledge including supports, loading arrangement and Labour). 121442.00
C Soft rock (10m dia well )
(i) Depth of soft rock strata upto 3m metre 23932.00
D Hard rock (10m dia well )
(i) Depth of hard rock strata upto 3 m metre 31364.00
12.17
Sinking of 11 m external diameter well ( other than pneumatic method of sinking ) through all
types of strata namely sandy soil, clayey soil and rock as shown against each case, complete
as per drawing and technical specifications. Depth of sinking is reckoned from bed level.
A Sandy soil
(i) Depth from bed level upto 3.0 M metre 28098.00
(ii) Beyond 3m upto 10m depth metre 20684.00
(iii) Beyond 10m upto 20m
a Add 5% for every additional meter depth of sinking over the rate of sinking for the previous
metre 27316.00
meter
(iv) Beyond 20m upto 30 m
a Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous
metre 51238.00
meter
b Add 20% of cost for Kentledge including supports, loading arrangement and Labour . metre 61485.00
(v) Beyond 30m upto 40 m
a Add 10% for every additional meter depth of sinking over the rate of sinking for the previous
metre 121735.00
meter
b
Add 20% of cost for Kentledge including supports, loading arrangement, and Labour etc. metre 146082.00
B Clayey soil (11 m dia. Well )
(i) Depth from bed level upto 3.0 M metre 24939.00
(ii) Beyond 3m upto 10m depth metre 35126.00
(iii) Beyond 10 m upto 20 m
Item No.
Descriptions Unit Rate (in Rs.)

a Add 5% for every additional meter depth of sinking over the rate of sinking for the previous
metre 46390.00
meter
b Add for dewatering @ 5% of cost, if required. metre 48709.00
(iv) Beyond 20m upto 30 m
a Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous
metre 87016.00
meter
b Add 5% of cost for dewatering on the cost, if required metre 114209.00
c
Add 25% of cost for Kentledge including supports, loading arrangement and Labour ). metre 108770.00
(v) Beyond 30m upto 40 m
a Add 10% for every additional meter depth of sinking over the rate of sinking for the previous
metre 206737.00
meter
b Add 5% of cost for dewatering, if required metre 260489.00
c Add 20% of cost for Kentledge including supports, loading arrangement and Labour). metre 248085.00
C Soft rock (11m dia well )
(i) Depth of soft rock strata upto 3m metre 53857.00
D Hard rock (11m dia well )
(i) Depth of hard rock upto 3 m metre 71109.00
12.18
Sinking of 12 m external diameter well ( other than pneumatic method of sinking ) through all
types of strata namely sandy soil, clayey soil and rock as shown against each case, complete
as per drawing and technical specifications. Depth of sinking is reckoned from bed level.
A Sandy soil
(i) I) Depth below bed level upto 3.0 M metre 57230.00
(ii) Beyond 3m upto 10m depth metre 63454.00
(iii) Beyond 10m upto 20m
a Add 5% for every additional meter depth of sinking over the rate of sinking for the previous
metre 83802.00
meter
(iv) Beyond 20m upto 30 m
a Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous
metre 157190.00
meter
b Add 20% of cost for Kentledge including supports, loading arrangement and Labour . metre 188628.00
(v) Beyond 30m upto 40 m
a Add 10% for every additional meter depth of sinking over the rate of sinking for the previous
metre 373460.00
meter
b
Add 20% of cost for Kentledge including supports, loading arrangement, and Labour etc. metre 448152.00
B Clayey soil (12 m dia. Well )
(i) Depth below bed level upto 3.0 M metre 61650.00
(ii) Beyond 3m upto 10m depth metre 91074.00
(iii) Beyond 10 m upto 20 m
a Add 5% for every additional meter depth of sinking over the rate of sinking for the previous
metre 120279.00
meter
b Add for dewatering @ 5% of cost, if required. metre 126292.00
(iv) Beyond 20m upto 30 m
a Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous
metre 225611.00
meter
b Add 5% of cost for dewatering on the cost, if required metre 296114.00
c
Add 25% of cost for Kentledge including supports, loading arrangement and Labour ). metre 282013.00
(v) Beyond 30m upto 40 m
a Add 10% for every additional meter depth of sinking over the rate of sinking for the previous
metre 536020.00
meter
b Add 5% of cost for dewatering, if required metre 675385.00
c Add 20% of cost for Kentledge including supports, loading arrangement and Labour). metre 643224.00
C Soft rock (12m dia well )
(i) Depth of soft rock strata upto 3m metre 128833.00
D Hard rock (12m dia well )
(i) Depth of hard rock strata upto 3 m metre 166658.00
Item No.
Descriptions Unit Rate (in Rs.)

12.19
Sinking of Twin D Type well ( other than pneumatic method of sinking ) through all types of
strata namely sandy soil, clayey soil and rock as shown against each case, complete as per
drawing and technical specifications. Depth of sinking is reckoned from bed level.
A Sandy soil
(i) Depth from bed level upto 3.0 M metre 13015.00
(ii) Beyond 3m upto 10m depth metre 14007.00
(iii) Beyond 10m upto 20m
a Add 5% for every additional meter depth of sinking over the rate of sinking for the previous
metre 18498.00
meter
(iv) Beyond 20m upto 30 m
a Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous
metre 34697.00
meter
b Add 20% of cost for Kentledge including supports, loading arrangement and Labour . metre 41636.00
(v) Beyond 30m upto 40 m
a Add 10% for every additional meter depth of sinking over the rate of sinking for the previous
metre 82435.00
meter
b
Add 20% of cost for Kentledge including supports, loading arrangement, and Labour etc. metre 98922.00
B Clayey soil (Twin D Type Well )
(i) Depth below bed level upto 3.0 M metre 15105.00
(ii) Beyond 3m upto 10m depth metre 19087.00
(iii) Beyond 10 m upto 20 m
a Add 5% for every additional meter depth of sinking over the rate of sinking for the previous
metre 25209.00
meter
b Add for dewatering @ 5% of cost, if required. metre 26469.00
(iv) Beyond 20m upto 30 m
a Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous
metre 47286.00
meter
b Add 5% of cost for dewatering on the cost, if required metre 62063.00
c
Add 25% of cost for Kentledge including supports, loading arrangement and Labour ). metre 59107.00
(v) Beyond 30m upto 40 m
a Add 10% for every additional meter depth of sinking over the rate of sinking for the previous
metre 112344.00
meter
b Add 5% of cost for dewatering, if required metre 141554.00
c Add 20% of cost for Kentledge including supports, loading arrangement and Labour). metre 134813.00
C Soft rock (Twin D Type well )
(i) Depth of soft rock strata upto 3m metre 27770.00
D Hard rock (Twin D Type well )
(i) Depth of hard rock strata upto 3 m metre 34466.00
12.20
Pneumatic sinking of wells with equipment of approved design, drawing and specifications
worked by competent and trained personnel and comprising of compression and decompression
chambers, reducers, two air locks separately for men and plant & materials, arrangement for
supply of fresh air to working chambers, check valves, exhaust valves, shafts made from steel
plates of riveted construction not less than 6 mm thick to withstand an air pressure of 0.50 #VALUE!
MPa, controlled blasting of hard rock where required, staircases and 1 m wide landing plate
forms with railing, arrangement for compression and decompression, electric lighting of 50 V
maximum, proper rooms for rest and medical examinations and compliance with safety
precautions as per IS:4138, all as per clause1207.6 of MoRTH Specifications.

12.21 Sand filling in wells complete as per drawing and technical specifications cum 2202.00
12.22 Providing steel liner 10 mm thick for curbs and 6mm thick for steining of wells including
tonne 100170.00
fabricating and setting out as per detailed drawing
12.23 Bored cast-in-situ M35 grade R.C.C. pile excluding reinforcement complete as per drawing and
technical specifications and removal of excavated earth with all lifts and lead upto 1000 m. (Pile metre 7822.00
diameter-750 mm)
12.24 Bored cast-in-situ M35 grade R.C.C. pile excluding reinforcement complete as per drawing and
technical specifications and removal of excavated earth with all lifts and lead upto 1000 m. (Pile metre 13056.00
diameter-1000 mm)
Item No.
Descriptions Unit Rate (in Rs.)

12.25 Bored cast-in-situ M35 grade R.C.C. pile excluding reinforcement complete as per drawing and
technical specifications and removal of excavated earth with all lifts and lead upto 1000 m. (Pile metre 17085.00
diameter-1200 mm)
12.26 Driven cast-in-place vertical M35 grade R.C.C. pile excluding reinforcement complete as per
metre 5279.00
drawing and & Technical Specification (Pile diameter - 750 mm)
12.27 Driven cast-in-place vertical M35 grade R.C.C. piles excluding reinforcement complete as per
metre 8918.00
drawing and & Technical Specification (Pile diameter - 1000 mm)
12.28 Driven cast-in-place vertical M35 grade R.C.C. piles excluding reinforcement complete as per
metre 12923.00
drawing and & Technical Specification (Pile diameter - 1200 mm)
12.29 Driven precast vertical M35 grade R.C.C. piles excluding reinforcement complete as per drawing
metre 2860.00
and & Technical Specification (Pile Diameter=500 mm)
12.30 Driven precast vertical M35 grade R.C.C. piles excluding reinforcement complete as per drawing
metre 5058.00
and & Technical Specification (Pile Diameter=750 mm)
12.31 Driven precast vertical M35 grade R.C.C. piles excluding reinforcement complete as per drawing
metre 8558.00
and & Technical Specification (Pile Diameter=1000 mm)
12.32 Driven precast vertical M35 grade R.C.C. piles excluding reinforcement complete as per drawing
metre 1876.00
and & Technical Specification (Size of pile - 300 mm x 300 mm)
12.33 Driven precast vertical M35 grade R.C.C. piles excluding reinforcement complete as per drawing
metre 3274.00
and & Technical Specification (Size of pile - 500 mm x 500 mm)
12.34 Driven precast vertical M35 grade R.C.C. piles excluding reinforcement complete as per drawing
metre 6390.00
and & Technical Specification (Size of pile - 750 mm x 750 mm)
12.35 Driven vertical steel piles complete as per drawing and & Technical Specification (Section of the
metre 7387.00
pile - H Section steel column 400 x 250 mm (ISHB Series) )
12.36 Driven vertical steel piles complete as per drawing and & Technical Specification (Section of the
metre 8330.00
pile - H Section steel column 450 x 250 mm (ISHB Series) )
12.37
Pile load test on single vertical pile in accordance with IS:2911(Part-IV) tonne 6413.00
12.38 Cement concrete for reinforced concrete in pile cap complete as per drawing and Technical
Specification
A RCC Grade M20
(i) Using Concrete Mixer cum 7810.00
(ii) Using Batching Plant, Transit Mixer and Concrete Pump cum 8139.00
B RCC Grade M25
(i) Using concrete mixer. cum 8551.00
(ii) Using Batching Plant, Transit Mixer and Concrete Pump cum 8898.00
C RCC Grade M30
(i) Using concrete mixer. cum 8645.00
(ii) Using Batching Plant, Transit Mixer and Concrete Pump cum 8974.00
D RCC Grade M35
(i) Using concrete mixer. cum 8841.00
(ii) Using Batching Plant, Transit Mixer and Concrete Pump cum 9188.00
12.39 Levelling course for Pile cap cum 6595.00
12.40 Supplying, fitting and placing un-coated HYSD bar reinforcement in foundation complete as per
tonne 66702.00
drawing and technical specifications
12.41 Supplying, fitting and placing un-coated Mild steel reinforcement complete in foundation as per
tonne 84928.00
drawing and technical specification
Item No.
Descriptions Unit Rate (in Rs.)

CHAPTER-13
SUB-STRUCTURE
Item No.
Descriptions Unit Rate (in Rs.)
13.1 Brick masonry work in 1:3 in sub-structure complete excluding pointing and plastering, as per
cum 8616.00
drawing and technical specifications
13.2
Pointing with cement mortar (1:3 ) on brick work in substructure as per Technical specifications 10 sqm 611.00
13.3 Plastering with cement mortar (1:3 ) on brick work in sub-structure as per Technical
10 sqm 1543.00
specifications
13.4 Stone masonry work in cement mortar 1:3 for substructure complete as per drawing and
Technical Specifications
A Random Rubble Masonry cum 4984.00
B Coursed rubble masonry (first sort ) cum 5071.00
C Ashlar masonry ( first sort ) cum 6544.00
13.5 Plain/Reinforced cement concrete in sub-structure complete as per drawing and technical
specifications
A PCC Grade M15
(p) Height upto 5m cum 7410.00
B PCC Grade M20
(p) Height upto 5m cum 8225.00
C PCC Grade M25
(p) Height upto 5m
Case I Using concrete Mixer cum 8974.00
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 8782.00
(q) Height 5m to 10m
Case I Using concrete Mixer cum 9300.00
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 9101.00
(r) Height above 10m
Case I Using concrete Mixer cum 9708.00
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 9500.00
D PCC Grade M30
(p) Height upto 5m
Case I Using concrete Mixer cum 9054.00
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 8856.00
(q) Height 5m to 10m
Case I Using concrete Mixer cum 9383.00
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 9178.00
(r) Height above 10m
Case I Using concrete Mixer cum 9795.00
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 9580.00
E RCC Grade M20
(p) Height upto 5m
Case I Using concrete Mixer cum 8334.00
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 8137.00
(q) Height 5m to 10m
Case I Using concrete Mixer cum 8637.00
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 8433.00
(r) Height above 10m
Case I Using concrete Mixer cum 9016.00
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 8803.00
F RCC Grade M25
(p) Height upto 5m
Case I Using concrete Mixer cum 9092.00
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 9414.00
(q) Height 5m to 10m
Case I Using concrete Mixer cum 9389.00
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 9722.00
(r) Height above 10m
Case I Using concrete Mixer cum 9835.00
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 10184.00
G RCC Grade M30
(p) Height upto 5m
Case I Using concrete Mixer cum 9137.00
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 9461.00
Item No.
Descriptions Unit Rate (in Rs.)

(q) Height 5m to 10m


Case I Using concrete Mixer cum 9395.00
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 9727.00
(r) Height above 10m
Case I Using concrete Mixer cum 9760.00
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 10106.00
H RCC Grade M35
(p) Height upto 5m
Case I Using concrete Mixer cum 9344.00
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 10094.00
(q) Height 5m to 10m
Case I Using concrete Mixer cum 9548.00
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 10315.00
(r) Height above 10m
Case I Using concrete Mixer cum 9854.00
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 10645.00
13.6 Supplying, fitting and placing HYSD bar reinforcement in sub-structure complete as per
tonne 66780.00
drawing and technical specifications
13.7 Supplying, fitting and placing Mild steel reinforcement complete in sub-structure as per
tonne 84286.00
drawing and technical specification
13.8
Providing weep holes in Brick masonry/Plain/Reinforced concrete abutment, wing wall/return
wall with 100 mm dia AC pipe, extending through the full width of the structure with slope of 1V each 1869.00
:20H towards drawing foce. Complete as per drawing and Technical specifications

13.9 Back filling behind abutment, wing wall and return wall complete as per drawing and Technical
specification
A Granular material cum 1867.00
B Sandy material cum 2387.00
13.10
Providing and laying of Filter media with granular materials/stone crushed aggregates satisfying
the requirements laid down in clause 2504.2.2. of MoRTH specifications to a thickness of not
less than 600 mm with smaller size towards the soil and bigger size towards the wall and cum 2164.00
provided over the entire surface behind abutment, wing wall and return wall to the full height
compacted to a firm condition complete as per drawing and technical specification.

13.11
Supplying, fitting and fixing in position true to line and level cast steel rocker bearing
tonne
conforming to IRC: 83(Pt.-1) section IX and clause 2003 of MoRTH specifications complete 1168.00
capacity
including all accessories as per drawing and Technical Specifications.
13.12
Supplying, fitting and fixing in position true to line and level forged steel roller bearing
tonne
conforming to IRC: 83(Pt.-1) section IX and clause 2003 of MoRTH specifications complete 1459.00
capacity
including all accessories as per drawing and Technical Specifications.
13.13 Supplying, fitting and fixing in position true to line and level sliding plate bearing with PTFE
surface sliding on stainless steel complete including all accessories as per drawing and tonne
371.00
Technical Specifications and BS: 5400, section 9.1 & 9.2 (for PTFE) and clause 2004 of capacity
MoRTH Specifications.
13.14
Supplying, fitting and fixing in position true to line and level elastomeric bearing conforming to
cubic
IRC: 83 (Part-II) section IX and clause 2005 of MoRTH specifications complete including all 1.25
centimetre
accessories as per drawing and Technical Specifications.
13.15 Supplying, fitting and fixing in position true to line and level sliding plate bearing with stainless
tonne
steel plate sliding on stainless steel plate with mild steel matrix complete including all 260.00
capacity
accessories as per drawing and Technical Specifications.
13.16 Supplying, fitting and fixing in position true to line and level POT-PTFE bearing consisting of a
metal piston supported by a disc or unreinforced elastomer confined within a metal cylinder,
sealing rings, dust seals, PTFE surface sliding against stainless steel mating surface,
tonne
completre assembly to be of cast steel/fabricated structural steel, metal and elastomer 455.00
capacity
elements to be as per IRC: 83 part-I & II respectively and other parts conforming to BS: 5400,
section 9.1 & 9.2 and clause 2006 of MoRTH Specifications complete asper drawing and
approved technical specifications.
Item No.
Descriptions Unit Rate (in Rs.)

CHAPTER-14
SUPER-STRUCTURE
Item No.
Descriptions Unit Rate (in Rs.)
14.1 Furnishing and Placing Reinforced/Prestressed cement concrete in super-structure as per
drawing and Technical Specification
A RCC Grade M20
Case I Using Concrete Mixer
(i) For solid slab super-structure, 20-30% of (a+b+c)
(p) Height upto 5m cum 9003.00
(q) Height 5m to 10m cum 9378.00
(r) Height above 10m cum 9753.00
(ii) For T-beam & slab, 25-35% of (a+b+c)
(p) Height upto 5m cum 9378.00
(q) Height 5m to 10m cum 9753.00
(r) Height above 10m cum 10128.00
Case II Using Batching Plant, Transit Mixer and Concrete Pump
(i) For solid slab super-structure, 20-30% of (a+b+c)
(p) Height upto 5m cum 9352.00
(q) Height 5m to 10m cum 9742.00
(r) Height above 10m cum 10131.00
(ii) For T-beam & slab, 25-35% of (a+b+c)
(p) Height upto 5m cum 9742.00
(q) Height 5m to 10m cum 10131.00
(r) Height above 10m cum 10521.00
B RCC Grade M25
Case I Using Concrete Mixer
(i) For solid slab super-structure, 20-30% of (a+b+c)
(p) Height upto 5m cum 9858.00
(q) Height 5m to 10m cum 10269.00
(r) Height above 10m cum 10679.00
(ii) For T-beam & slab, 25-35% of (a+b+c)
(p) Height upto 5m cum 10269.00
(q) Height 5m to 10m cum 10679.00
(r) Height above 10m cum 11090.00
Case II Using Batching Plant, Transit Mixer and Concrete Pump
(i) For solid slab super-structure, 20-30% of (a+b+c)
(p) Height upto 5m cum 10219.00
(q) Height 5m to 10m cum 10645.00
(r) Height above 10m cum 11071.00
(ii) For T-beam & slab, 25-35% of (a+b+c)
(p) Height upto 5m cum 10645.00
(q) Height 5m to 10m cum 11071.00
(r) Height above 10m cum 11497.00
C RCC Grade M 30
Case I Using Concrete Mixer
(i) For solid slab super-structure, 20-30% of (a+b+c)
(p) Height upto 5m cum 9984.00
(q) Height 5m to 10m cum 10401.00
(r) Height above 10m cum 10817.00
(ii) For T-beam & slab, 25-35% of (a+b+c)
(p) Height upto 5m cum 10401.00
(q) Height 5m to 10m cum 10817.00
(r) Height above 10m cum 11233.00
Item No.
Descriptions Unit Rate (in Rs.)

Case II Using Batching Plant, Transit Mixer and Concrete Pump.


(i) For solid slab super-structure, 20-30% of (a+b+c)
(p) Height upto 5m cum 10331.00
(q) Height 5m to 10m cum 10762.00
(r) Height above 10m cum 11192.00
(ii) For T-beam & slab, 25-35% of (a+b+c)
(p) Height upto 5m cum 10762.00
(q) Height 5m to 10m cum 11192.00
(r) Height above 10m cum 11623.00
D RCC/PSC Grade M35
Case 1 Using concrete mixer.
(i) For solid slab super-structure, 18-28% of (a+b+c)
(p) Height upto 5m cum 10040.00
(q) Height 5m to 10m cum 10466.00
(r) Height above 10m cum 10891.00
(ii) For T-beam & slab, 23-33% of (a+b+c)
(p) Height upto 5m cum 10466.00
(q) Height 5m to 10m cum 10891.00
(r) Height above 10m cum 11317.00
(iii) For box girder and balanced cantilever, 38-58% of cost of concrete.
(p) Height upto 5m cum 11742.00
(q) Height 5m to 10m cum 12593.00
(r) Height above 10m cum 13444.00
Case II Using Batching Plant, Transit Mixer and Concrete Pump
(i) For solid slab super-structure, 18-28% of (a+b+c)
(p) Height upto 5m cum 10373.00
(q) Height 5m to 10m cum 10813.00
(r) Height above 10m cum 11252.00
(ii) For T-beam & slab, 23-33% of (a+b+c)
(p) Height upto 5m cum 10813.00
(q) Height 5m to 10m cum 11252.00
(r) Height above 10m cum 11692.00
(iii) For box girder and balanced cantilever, 38-58% of cost of concrete.
(p) Height upto 5m cum 12131.00
(q) Height 5m to 10m cum 13010.00
(r) Height above 10m cum 13890.00
E PSC Grade M-40
Case 1 Using concrete mixer.
(i) For solid slab super-structure, 20-30% of (a+b+c)
(p) Height upto 5m cum 10840.00
(q)
Height 5m to 10m cum 11292.00

(r) Height above 10m cum 11744.00


(ii) For T-beam & slab, 25-35% of (a+b+c)
(p) Height upto 5m cum 11292.00
(q) Height 5m to 10m cum 11744.00
(r) Height above 10m cum 12195.00
Case II Using Batching Plant, Transit Mixer and Concrete Pump
(i) For solid slab super-structure, 18-28% of (a+b+c)
(p) Height upto 5m cum 10959.00
(q) Height 5m to 10m cum 11424.00
(r) Height above 10m cum 11888.00
(ii) For T-beam & slab, 23-33% of (a+b+c)
(p) Height upto 5m cum 11424.00
(q) Height 5m to 10m cum 11888.00
(r) Height above 10m cum 12352.00
(iii) For box girder and balanced cantilever, 38-58% of cost of concrete.
(p) Height upto 5m cum 12817.00
(q) Height 5m to 10m cum 13745.00
(r) Height above 10m cum 14674.00
Item No.
Descriptions Unit Rate (in Rs.)

F
PSC Grade M-45

(i) For solid slab/voided slab super-structure, 16-26% of cost of concrete (a+b+c)
(p) Height upto 5m cum 11310.00
(q) Height 5m to 10m cum 11797.00
(r) Height above 10m cum 12285.00
(ii) For I-beam & slab including launching of precast girders by launching truss upto 40 m span, 21-
31% of cost of concrete.
(p) Height upto 5m cum 11797.00
(q) Height 5m to 10m cum 12285.00
(r) Height above 10m cum 12772.00
(iii) For cast-in-situ box girder, segmental construction and balanced cantilever, 36-56% of cost of
concrete.
(p) Height upto 5m cum 13260.00
(q) Height 5m to 10m cum 14235.00
(r) Height above 10m cum 15210.00
G PSC Grade M-50
(i) For cast-in-situ box girder, segmental construction and balanced cantilever, 35-55% of cost of
concrete
(p) Height upto 5m cum 13608.00
(q) Height 5m to 10m cum 14616.00
(r) Height above 10m cum 15624.00
H PSC Grade M- 55
(i) For cast-in-situ box girder, segmental construction and balanced cantilever, 35-55% of cost of
concrete
(p) Height upto 5m cum 14306.00
(q) Height 5m to 10m cum 15366.00
(r) Height above 10m cum 16426.00
14.2 a) Supplying, fitting and placing HYSD bar reinforcement in super-structure complete as per
tonne 67881.00
drawing and technical specifications
14.3 High tensile steel wires/strands including all accessories for stressing, stressing operations and
tonne 256357.00
grouting complete as per drawing and Technical Specifications
14.4 Providing and laying Cement concrete wearing coat M-30 grade including reinforcement
cum 13731.00
complete as per drawing and Technical Specifications
14.5 Mastic Asphalt (Providing and laying 12 mm thick mastic asphalt wearing course on top of deck
slab excluding prime coat with paving grade bitumen meeting the requirements given in table
500-29, prepared by using mastic cooker and laid to required level and slope after cleaning the
surface, including providing antiskid surface with bitumen precoated fine grained hard stone
sqm 326.00
chipping of 9.5 mm nominal size at the rate of 0.005cum per 10 sqm and at an approximate
spacing of 10 cm center to center in both directions, pressed into surface when the
temperature of surfaces not less than 100 deg. C, protruding 1 mm to 4 mm over mastic
surface, all complete as per clause 515.)
14.6
Construction of precast RCC railing of M30 Grade, aggregate size not exceeding 12 mm, true
to line and grade, tolurence of vertical RCC post not to exceed 1 in 500, centre to centre
metre 2094.00
spacing between vertical post not to exceed 2000 mm, leaving adequate space between
vertical post for expansion, complete as per approved drawings and technical specifications.
14.7
Construction of RCC railing of M30 Grade in-situ with 20 mm nominal size aggregate, true to
line and grade, tolurence of vertical RCC post not to exceed 1 in 500, centre to centre spacing
metre 2045.00
between vertical post not to exceed 2000 mm, leaving adequate space between vertical post
for expansion, complete as per approved drawings and technical specifications.
14.8 Providing, fitting and fixing mild steel railing complete as per drawing and Technical
metre 4044.00
Specification
14.9 Drainage Spouts complete as per drawing and Technical specification each 12494.00
14.10 PCC M15 Grade leveling course below approach slab complete as per drawing and Technical
cum 6736.00
specification
14.11 Reinforced cement concrete approach slab including reinforcement and formwork complete as
cum 12167.00
per drawing and Technical specification
14.13 Precast - pretensioned Girders (Providing, precasting, transportation and placing in position
cum 33937.00
precast pretensioned concrete girders as per drawing and technical specifications)
14.14 Providing and fixing Helical pipes in voided concrete slabs metre 401.00
Item No.
Descriptions Unit Rate (in Rs.)

14.16 Painting on concrete surface (Providing and applying 2 coats of water based cement paint to
unplastered concrete surface after cleaning the surface of dirt, dust, oil, grease, metre 55.00
efflorescence and applying paint @ of 1 litre for 2 Sq.m. )
14.17 Burried Joint (Providing and laying a burried expansion joint, expansion gap being 20 mm,
covered with 12 mm thick, 200 mm wide galvanised wieldable structural steel plate as per IS:
2062, placed symmetrical to centre line of the joint, resting freely over the top surface of the metre 2661.00
deck concrete, welding of 8 mm dia. 100 mm long galvanised nails spaced 300 mm c/c along
the centre line of the plate, all as specified in clause 2604.)
14.18 Filler joint
(i) Providing & fixing 2 mm thick corrugated copper plate in expansion joint complete as per
metre 2009.00
drawing & Technical Specification.
(ii) Providing & fixing 20 mm thick compressible fibre board in expansion joint complete as per
metre 684.00
drawing & Technical Specification.
(iii)
Providing and fixing in position 20 mm thick premoulded joint filler in expansion joint for fixed
ends of simply supported spans not exceeding 10 m to cater for a horizontal movement upto 20 metre 389.00
mm, covered with sealant complete as per drawing and technical specifications.

(iv) Providing and filling joint sealing compound as per drawings and technical specifications with
metre 18.50
coarse sand and 6% bitumen by weight
14.19 Asphaltic Plug joint (Providing and laying of asphaltic plug joint to provide for horizontal
movement of 25 mm and vertical movement of 2 mm, depth of joint varying from 75 mm to
100 mm, width varying from 500 mm to 750 mm (in traffic direction), covered with a closure
plate of 200mm x 6mm of wieldable structural steel conforming to IS: 2062, asphaltic plug to metre 2025.00
consist of polymer modified bitumen binder, carefully selected single size aggregate of 12.5
mm nominal size and a heat resistant foam caulking/backer rod, all as per approved drawings
and specifications.)
14.20 Elastomeric Slab Steel Expansion Joint (Providing and laying of an elastomeric slab steel
expansion joint, catering to right or skew (less than 20 deg., moderately curved with
maximum horizontal movement upto 50 mm, complete as per approved drawings and standard
metre 24105.00
specifications to be installed by the manufacturer/supplier or their authorised representative
ensuring compliance to the manufacturer's instructions for installation and clause 2606 of
MoRTH specifications for road & bridge works.)
14.21 Compression Seal Joint (Providing and laying of compression seal joint consisting of steel
armoured nosing at two edges of the joint gap suitably anchored to the deck concrete and a
preformed chloroprene elastomer or closed cell foam joint sealer compressed and fixed into the metre 7443.00
joint gap with special adhesive binder to cater for a horizontal movement upto 40 mm and
vertical movement of 3 mm.)
14.22 Strip Seal Expansion Joint (Providing and laying of a strip seal expansion joint catering to
maximum horizontal movement upto 70 mm, complete as per approved drawings and standard
metre 14462.00
specifications to be installed by the manufacturer/supplier or their authorised representative
ensuring compliance to the manufacturer's instructions for installation.)
14.23 Modular Strip / Box Seal Joint (Providing and laying of a modular strip Box steel expansion joint
including anchorage catering to a horizontal movement beyond 70 mm and upto 140mm,
complete as per approved drawings and standard specifications to be installed by the metre 229280.00
manufacturer/supplier or their authorised representative ensuring compliance to the
manufacturer's instructions for installation.)
14.24 Modular Strip / Box Seal Joint (Providing and laying of a modular strip box seal expansion joint
catering to a horizontal movement beyond 140mm and upto 210mm, complete as per
approved drawings and standard specifications to be installed by the manufacturer/supplier or metre 304450.00
their authorised representative ensuring compliance to the manufacturer's instructions for
installation.)
Item No.
Descriptions Unit Rate (in Rs.)

CHAPTER-15
RIVER TRAINING AND PROTECTION WORKS
Item No.
Descriptions Unit Rate (in Rs.)
15.1 Providing and laying boulders apron on river bed for protection against scour with stone
boulders weighing not less than 40 kg each complete as per drawing and Technical
specification.
A Boulder laid dry without wire crates. cum 1793.00
15.2 Boulder apron laid in wire crates (Providing and laying of boulder apron laid in wire crates
made with 4mm dia GI wire conforming to IS: 280 & IS:4826 in 100mm x 100mm mesh
cum 3572.00
(weaved diagonally) including 10% extra for laps and joints laid with stone boulders weighing
not less than 40 kg each.)
15.3
Cement concrete blocks (size 0.5 x 0.5 x 0.5 m) (Providing and laying of apron with cement
concrete blocks of size 0.5x0.5x0.5 m cast in-situ and made with nominal mix of M-15 grade cum 7144.00
cement concrete with a minimum cement content of 250 kg/cum as per IRC: 21-2000.)
15.4
Providing and laying Pitching on slopes laid over prepared filter media including boulder apron
laid dry in front of toe of embankment complete as per drawing and Technical specifications

A Stone/Boulder cum 1793.00


B
Cement Concrete blocks of size 0.3x0.3 x0.3 m cast in cement concrete of Grade M15 cum 7144.00
15.5 Providing and laying Filter material underneath pitching in slopes complete as per drawing and
cum 2281.00
Technical specification
15.6 Geotextile Filter (Laying of a geotextile filter between pitching and embankment slopes on
which pitching is laid to prevent escape of the embankment material through the voids of the
sqm 686.00
stone pitching/cement concrete blocks as well as to allow free movement of water without
creating any uplift head on the pitching.)
15.7
Toe protection (A toe wall for toe protection can either be in dry rubble masonry in case of dry
rubble pitching or pitching with stones in wire crates or it can be in PCC M15 nominal mix if
cement concrete block have been used for pitching . Rates for toe wall can be adopted from
respective clauses depending upon approved design. The rate for excavation for foundation,
dry rubble masonry and PCC M15 have been analysed and given in respective chapters.)
15.8 Providing and laying Flooring complete as per drawing and Technical specifications laid over
cement concrete bedding.
A Rubble stone laid in cement mortar 1:3 cum 6391.00
B Cement Concrete blocks Grade M15 cum 9408.00
15.9 Dry rubble Flooring cum 2057.00
15.10 Curtain wall complete as per drawing and Technical specification
A Stone masonry in cement mortar (1:3) cum 5309.00
B Cement concrete Grade M15 cum 7004.00
15.11 Flexible Apron :Construction of flexible apron 1 m thick comprising of loose stone boulders
cum 1819.00
weighing not less than 40 kg beyond curtain wall.
15.12 Gabian Structure for Retaining Earth (Providing and construction of a gabain structure for
retaining earth with segments of wire crates of size 7 m x 3 m x 0.6 m each divided into 1.5 m
compartments by cross netting, made from 4 mm galvanised steel wire @ 32 kg per 10 sqm
having minimum tensile strength of 300 Mpa conforming to IS:280 and galvanizing coating cum 3958.00
conforming to IS:4826, woven into mesh with double twist, mesh size not exceeding 100 x
100 mm, filled with boulders with least dimension of 200 mm, all loose ends to be tied with 4
mm galvanised steel wire)
15.13 Gabian Structure for Erosion Control, River Training Works and Protection works (Providing and
constructing gabain structures for erosion control, river training works and protection works
with wire crates of size 2 m x 1 m x 0.3 m each divided into 1m compartments by cross netting,
made from 4 mm galvanised steel wire @ 32 kg per 10 sqm having minimum tensile strength of cum 6891.00
300 Mpa conforming to IS:280 and galvanizing coating conforming to IS:4826, woven into
mesh with double twist, mesh size not exceeding 100 mm x 100 mm, filled with boulders with
least dimension of 200 mm, all loose ends to be securely tied with 4 mm galvanised steel wire.)
Item No.
Descriptions Unit Rate (in Rs.)

CHAPTER-16
REPAIR AND REHABILITATION
Item No.
Descriptions Unit Rate (in Rs.)
16.1 Removal of existing cement concrete wearing coat including its disposal complete as per
Technical specification without causing any detrimental effect to any part of the bridge
sqm 100.00
structure and removal of dismantled material with all lifts and lead upto 1000m (Thickness 75
mm)
16.2
Removal of existing asphaltic wearing coat comprising of 50 mm thick asphaltic concrete laid
sqm 75.00
over 12 mm thick mastic asphalt including disposal with all lift and lead upto 1000m.
16.3 Guniting concrete surface with cement mortar applied with compressor after cleaning surface
sqm 1707.00
and spraying with epoxy complete as per Technical specification
16.4
Providing and inserting nipples with approved fixing compound after drilling holes for grouting
as per Technical specifications including subsequent cutting/removal and sealing of the hole as each 132.00
necessary of nipples after completion of grouting with Cement/Epoxy
16.5 Sealing of cracks/porous concrete by injection process through nipples/Grouting complete as
per Technical specification.
A Cement Grout kg 171.00
B Cement mortar (1:1) Grouting kg 164.00
16.6 Patching of damaged concrete surface with polymer concrete and curing compounds, initiator
and promoter, available in present formulations, to be applied as per instructions of sqm 4616.00
manufacturer and as approved by the Engineer.
16.7 Sealing of crack / porous concrete with Epoxy Grout by injection through nipples complete as
kg 1651.00
per clause 2803.1.
16.8 Applying epoxy mortar over leached, honey combed and spalled concrete surface and exposed
sqm 1130.00
steel reinforcement complete as per Technical specification
16.9
Removal of defective concrete, cleaning the surface thoroughly, applying the shotcrete
mixture mechanically with compressed air under pressure, comprising of cement, sand,
coarse aggregates, water and quick setting compound in the proportion as per clause 2807.1.,
sqm 375.00
sand and coarse aggregates conforming to IS: 383 and table 1 of IS: 9012 respectively, water
cement ratio ranging from 0.35 to 0.50, density of gunite not less than 2000 kg/cum, strength
not less than 25 Mpa and workmanship conforming to clause 2807.6.

16.10 Applying pre-packed cement based polymer mortar of strength 45 Mpa at 28 days for
sqm 271.00
replacement of spalled concrete
16.11 Eproxy bonding of new concrete to old concrete sqm 1595.00
16.12 Providing external prestressing with high tensile steel wires/strands including drilling for
passage of prestessing steel, all accessories for stressing and stressing operation and grouting tonne 579219.00
complete as per drawing and Technical specification
16.13 Providing external prestressing with high tensile steel wires/strands including drilling for
passage of prestessing steel, all accessories for stressing and stressing operation and grouting tonne 546479.00
complete as per drawing and Technical specification
16.14 Providing external prestressing with high tensile steel wires/strands including drilling for
passage of prestessing steel, all accessories for stressing and stressing operation and grouting tonne 528332.00
complete as per drawing and Technical specification
16.15 Replacement of bearings complete as per Technical specification each 304486.00
16.16 Rectification of bearings as per Technical specifications each 206091.00
16.17 Replacement of Expansion Joints complete as per drawings metre 4453.00
16.18 Replacement of damaged concrete railing. metre 173.00
16.19 Replacement of crash barrier. metre 292.00
16.20 Replacement of damaged mild steel railing metre 149.00
16.21
Repair of crash barrier (Repair of concrete crash barrier with cement concrete of M-30 grade by
cutting and trimming the damaged portion to a regular shape, cleaning the area to be repaired metre 346.00
thoroughly, applying cement concrete after erection of proper form work.)
16.22
Repair of RCC Railing (Carrying out repair of RCC M30 railing to bring it to the original shape.) metre 204.00
16.23 Repair of steel Railing (Repair of steel railing to bring it to the original shape) metre 377.00
Analysis of Rate
CHAPTER - 1
CARRIAGE OF MATERIALS
Ref. to Remarks
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs / Input
Spec. ref.
1.1 Loading and Unloading of Stone Boulder/ Stone cum
aggregates/Sand/ Kanker/Moorum
Placing tipper at loading point, loading with front end
loader, dumping, turning for return trip, excluding time
for haulage and return trip
Unit = cum
Taking output = 5.5 cum
Time required for
i) Positioning of tipper at loading point 1 Min
ii) Loading by front end loader 1 cum bucket capacity @ 13 Min
25 cum per hour
iii) Maneuvering, reversing, dumping and turning for 2 Min
return
iv) Waiting time, unforeseen contingencies etc 4 Min
Total 20 Min
a) Machinery
Tipper 5.5 tonnes capacity hour 0.330 491.65 162.25 P&M-048
Front end-loader 1 cum bucket capacity @ 25 cum/hour hour 0.330 803.34 265.10 P&M-017

b) Overhead charges @ 8% on (a) 34.19


c) Contractor's profit @ 10% on (a+b) 46.15
Cost for 5.5 cum = a+b+c 507.69
Rate per cum = (a+b+c)/ 5.5 92.31
Note Unloading will be by tipping. say 92.00
1.2 Loading and Unloading of Boulders by Manual
Means
Unit = cum
Taking output = 5.5 cum
a) Labour
Mate day 0.110 329.34 36.23 L-12
Mazdoor for loading and unloading day 0.750 152.91 114.68 L-13
b) Machinery
Tipper 5.5 tonne capacity hour 0.750 491.65 368.74 P&M-048
c) Overhead charges @ 8% on (a+b) 41.57
d) Contractor's profit @ 10% on (a+b+c) 56.12
Cost for5.5 cum = a+b+c+d 617.34
Rate per cum = (a+b+c+d)/5.5 112.24
Note Unloading will be by tipping. say 112.00
1.3 Loading and Unloading of Cement or Steel by
Manual Means and Stacking.
Unit = tonne
Taking output = 10 tonnes
a) Labour
Mate day 0.080 329.34 26.35 L-12
Mazdoor for loading and unloading day 2.000 152.91 305.81 L-13
b) Machinery
Truck 10 tonne capacity hour 2.000 517.53 1035.06 P&M-057
c) Overhead charges @ 8% on (a+b) 109.38
d) Contractor's profit @ 10% on (a+b+c) 147.66
Cost for10 tonnes = a+b+c+d 1624.25
Rate per tonnes = (a+b+c+d)/10 162.43
say 162.00
Ref. to Remarks
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs / Input
Spec. ref.
1.4 Cost of Haulage Excluding Loading and Unloading

Haulage of materials by tipper excluding cost of loading,


unloading and stacking.
Unit = t.km
Taking output 10 tonnes load and lead 10 km = 100
t.km
(i) Surfaced Road
Speed with load : 25 km / hour.
Speed while Returning empty :35 km / hour.
a) Machinery.
Tipper 10 tonne capacity
Time taken for onward haulage with load hour 0.400 491.65 196.66 P&M-048
Time taken for empty return trip. hour 0.290 491.65 142.58 P&M-048
b) Overhead charges @ 8% on (a) 27.14
c) Contractor's profit @ 10% on (a+b) 36.64
cost for 100 t km = a+b+c 403.02
Rate per t.km = (a+b+c)/100 4.03
say 4.00
(ii) Unsurfaced Graveled Road
Speed with load: 20 km / hour
Speed for empty return trip :30 km / hour
a) Machinery
Tipper 10 tonnes capacity
Time taken for onward haulage with load hour 0.500 491.65 245.83 P&M-048
Time taken for empty return trip hour 0.330 491.65 162.25 P&M-048
b) Overhead charges @ 8% on (a) 32.65
c) Contractor's profit @ 10% on (a+b) 44.07
Cost for 100 t .km = a+b+c 484.79
Rate per t.Km = (a+b+c)/100 4.85
say 4.80
(iii) Katcha Track and Track in River Bed/Nallah Bed
and Choe Bed
Speed with load :10 km / hour
Speed while returning empty:15 km / hour
a) Machinery
Tipper 10 tonnes capacity
Time taken for onward haulage hour 1.000 491.65 491.65 P&M-048
Time taken for empty return trip hour 0.670 491.65 329.41 P&M-048
b) Overhead charges @ 8% on (a) 65.68
c) Contractor's profit @ 10% on (a+b) 88.67
Cost for 100 t .km = a+b+c 975.42
Rate per t.Km = (a+b+c)/100 9.75
say 9.80
Ref. to Remarks
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs / Input
Spec. ref.
1.5 Hand Broken Stone Aggregates 63 mm Nominal
Size
Supply of quarried stone, hand breaking into coarse
aggregate 63 mm nominal size (passing 80 mm and
retained on 50 mm sieve) and stacking as directed

Unit = cum
Taking output = 1 cum
a) Labour
Mate day 0.060 329.34 19.76 L-12
Mazdoor day 1.500 152.91 229.36 L-13
b) Material
Supply of quarried stone 150 - 200 mm size cum 1.100 882.15 970.37 M-002
c) Overhead charges @ 8% on (a+b) 97.56
d) Contractor's profit @ 10% on (a+b+c) 131.70
Rate per cum = a+b+c+d 1448.75
say 1449.00
1449.00
1.6 Crushing of Stone Aggregates 13.2 mm Nominal
Size
Crushing of stone boulders of 150 mm size in an
integrated stone crushing unit of 200 tonnes per hour
capacity comprising of primary and secondary crushing
units, belt conveyor and vibrating screens to obtain stone
aggregates of 13.2 mm nominal size.
Unit = cum
Taking Output = 600 cum at crusher location.
a) Labour
Mate day 0.760 329.34 250.30 L-12
Mazdoor Skilled day 2.000 244.65 489.30 L-15
Mazdoor including breaking of any oversize boulder. day 17.000 152.91 2599.40 L-13
b) Material
Stone Boulder of size 150 mm and below cum 800.000 1000.71 800568.77 M-001
c) Machinery
Integrated stone crusher of 200 TPH including belt conveyor Hour 6.000 16924.34 101546.05 P&M-028
and vibrating screens
Front end loader 1 cum bucket capacity Hour 20.000 803.34 16066.89 P&M-017
Tipper 5.5 cum capacity Hour 20.000 491.65 9833.03 P&M-048
d) Overhead charges @ 8% on (a+b+c) 74508.30
e) Contractor's profit @ 10% on (a+b+c+d) 100586.20
Cost for 600 cum = (a+b+c+d+e)x0.95 1051125.83
Rate per cum = (a+b+c+d+e) * 0.95 / 600 1751.88
say 1752.00
1752.00
Note 1. 800 cum of stone boulders are needed to get 600 cum of
stone chips of size 13.2 mm.
2. 95 per cent of above cost will be attributed to the production
of 600 cum of stone chips of 13.2 mm size and balance 5 per
cent to the production of stone dust which comes out as a by-
product.
3. The integrated stone crusher includes primary and secondary
crushing units.
Ref. to Remarks
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs / Input
Spec. ref.
1.7 Crushing of Stone Aggregates 20 mm Nominal
Size
Crushing of stone boulders of 150 mm size in an
integrated stone crushing unit of 200 tonnes per hour
capacity comprising of primary and secondary crushing
units, belt conveyor and vibrating screens to obtain stone
aggregates of 20 mm nominal size.
Unit = cum
Taking Output = 670 cum at crusher location.
a) Labour
Mate day 0.760 329.34 250.30 L-12
Mazdoor Skilled day 2.000 244.65 489.30 L-15
Mazdoor including breaking of any size boulder. day 17.000 152.91 2599.40 L-13
b) Material
Stone Boulder of size 150 mm and below cum 800.000 1000.71 800568.77 M-001
c) Machinery
Integrated stone crusher of 200 TPH including belt conveyor Hour 6.000 16924.34 101546.05 P&M-028
and vibrating screens
Front end loader 1 cum bucket capacity Hour 20.000 803.34 16066.89 P&M-017
Tipper 5.5 cum capacity Hour 20.000 491.65 9833.03 P&M-048
d) Overhead charges @ 8% on (a+b+c) 74508.30
e) Contractor's profit @ 10% on (a+b+c+d) 100586.20
Cost for 670 cum = (a+b+c+d+e)x0.90 995803.42
Rate per cum = (a+b+c+d+e) * 0.90 / 670 1486.27
say 1486.00
1486.00
Note 1. 800 cum of stone boulders are needed to get 600 cum of
stone chips of size 20 and 40 mm.
2. 90 per cent of above cost will be attributed to the production
of 670 cum of stone aggregates of 20mm size and balance 10
per cent will be for smaller size aggregates and stone dust
which comes out as a by-product.

3. The integrated stone crusher includes primary and secondary


crushing units.
1.8 Crushing of Stone Aggregates 40 mm Nominal
Size
Crushing of stone boulders of 150 mm size in an
integrated stone crushing unit of 200 tonnes per hour
capacity comprising of primary and secondary crushing
units, belt conveyor and vibrating screens to obtain stone
aggregates of 40 mm nominal size.
Unit = cum
Taking Output = 750 cum at crusher location.
a) Labour
Mate day 0.760 329.34 250.30 L-12
Mazdoor Skilled day 2.000 244.65 489.30 L-15
Mazdoor day 17.000 152.91 2599.40 L-13
b) Material
Stone Boulder of size 150 mm and below cum 800.000 1000.71 800568.77 M-001
c) Machinery
Integrated stone crusher of 200 TPH including belt conveyor Hour 6.000 16924.34 101546.05 P&M-028
and vibrating screens
Front end loader 1 cum bucket capacity Hour 20.000 803.34 16066.89 P&M-017
Tipper 5.5 cum capacity Hour 20.000 491.65 9833.03 P&M-048
d) Overhead charges @ 8% on (a+b+c) 74508.30
e) Contractor's profit @ 10% on (a+b+c+d) 100586.20
Cost for 750 cum = (a+b+c+d+e)x0.85 940481.01
Rate per cum = (a+b+c+d+e)x0.85/750 1253.97
say 1254.00
Note 1. 800 cum of stone boulders are needed to get 600 cum of
stone chips of size 13.2 mm.
2. 85 per cent of above cost will be attributed to the production
of 750 cum of stone aggregates of 40mm size and balance 15
per cent will be for smaller size aggregates and stone dust
which comes out as a by-product.

3. The integrated stone crusher includes primary and secondary


crushing units.
Ref. to Remarks
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs / Input
Spec. ref.
1.3 Loading and Unloading of Bricks by Manual Means and
(MoRD) Stacking.
(i) Loading of Bricks by Manual Means including a lead of
upto 30 m.
Unit = 1000 Nos.
Taking output = 2000 Nos.
a) Labour
Mate day 0.010 329.34 3.29 L-12

Mazdoor for loading and unloading day 0.250 152.91 38.23 L-13

b) Machinery
Truck 10 tonne capacity hour 0.330 517.53 170.78 P&M-057
c) Overhead charges @ 8% on (a+b) 16.98
d) Contractor's profit @ 10% on (a+b+c) 22.93

Cost for 2000 Nos. = a+b+c+d 252.22


Rate for 1000 Bricks = (a+b+c+d)/2000 126.11
say 126.00
(ii) UnLoading and Stacking of Bricks by Manual Means
including a lead of upto 30 m.
Unit = 1000 Nos.
Taking output = 2000 Nos.
a) Labour
Mate day 0.010 329.34 3.29 L-12

Mazdoor for loading and unloading day 0.250 152.91 38.23 L-13

b) Machinery
Truck 10 tonne capacity hour 0.330 517.53 170.78 P&M-057
c) Overhead charges @ 8% on (a+b) 16.98
d) Contractor's profit @ 10% on (a+b+c) 22.93

Cost for 2000 Nos. = a+b+c+d 252.22


Rate for 1000 Bricks = (a+b+c+d)/2000 126.11
say 126.00
Ref. to Remarks
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs / Input
Spec. ref.
1.6 Loading and Unloading of Bitumen Drums by Manual
(MoRD) Means
(i) Loading of Bitumen Drums by Manual Means including a
lead of upto 30 m.
Unit = tonne
Taking output = 10 tonnes
a) Labour
Mate day 0.060 329.34 19.76 L-12

Mazdoor for loading and unloading day 1.600 152.91 244.65 L-13

b) Machinery
Truck 10 tonne capacity hour 1.250 517.53 646.91 P&M-057
c) Overhead charges @ 8% on (a+b) 72.91
d) Contractor's profit @ 10% on (a+b+c) 98.42

Cost for10 tonnes = a+b+c+d 1082.65


Rate per tonnes = (a+b+c+d)/10 108.26
say 108.00
(ii) UnLoading of Bitumen Drums by Manual Means including
a lead of upto 30 m.
Unit = tonne
Taking output = 10 tonnes
a) Labour
Mate day 0.050 329.34 16.47 L-12

Mazdoor for loading and unloading day 1.200 152.91 183.49 L-13

b) Machinery
Truck 10 tonne capacity hour 1.250 517.53 646.91 P&M-057
c) Overhead charges @ 8% on (a+b) 67.75
d) Contractor's profit @ 10% on (a+b+c) 91.46

Cost for10 tonnes = a+b+c+d 1006.07


Rate per tonnes = (a+b+c+d)/10 100.61
say 101.00
Ref. to Remarks
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs / Input
Spec. ref.
1.6 Loading and Unloading of Hume Pipes
(MoRD)
(i) Loading of RCC Hume pipes by mechanical means including a lead upto 30 m
A. 1000 / 1200 mm dia Hume pipe
Unit = per pipe
Taking output = 9 pipes
a) Labour
Mate day 0.02 329.34 6.59
Mazdoor (Unskilled) day 0.50 152.91 76.45
b) Machinery
Truck hour 0.33 517.53 170.78
Crane hour 0.33 1,336.16 440.93
c) Overhead charges @ 8% on (a+b) 55.58

d) Contractor's profit @ 10% on (a+b+c) 75.03

Cost for 9 pipes = a+b+c+d 825.37


Rate per pipe = (a+b+c+d)/9 92.00
(ii) Unloading of RCC Hume pipe by manual means including a lead
upto 30 m
A. 1000/1200 mm dia RCC Hume pipes
Unit = per pipe
Taking output = 5 pipes
a) Labour
Mate day 0.04 329.34 13.17
Mazdoor (Unskilled) day 1.00 152.91 152.91
b) Machinery
Truck hour 2.00 517.53 1,035.06
c) Material
Wooden sleepers 250mm x 250mm x125mm hire hour 2.00 5.20 10.40
charges 3 nos sleeper
Crow bars 2 nos not less than 40 mm dia (hire- hour 2.00 5.20 10.40
charges)
d) Overhead charges @ 8% on (a+b) 97.75

e) Contractor's profit @ 10% on (a+b+c) 131.97

Cost for 5 pipes = a+b+c+d+e/5 1,451.66


Rate per pipe = (a+b+c+d+e) 290.00
CHAPTER - 2
SITE CLEARANCE
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
2.1 201 Cutting of Trees, including cutting of Trunks, Branches and
Removal
Cutting of trees, including cutting of trunks, branches and removal of
stumps, roots, stacking of serviceable material with all lifts and up to a
lead of 1000 metres and earth filling in the depression / pit.
Unit = Each
(i) Girth from 300 mm to 600 mm
a) Labour
Mate day 0.020 329.34 6.59 L-12
Mazdoors for cutting trees including cutting, refilling, compaction day 0.600 152.91 91.74 L-13
of backfilling and stacking of serviceable materials within 1000
metres lead by manual means.
b) Machinery
Tractor-trolley hour 0.100 379.91 37.99 P&M-053
c) Overhead charges @ 8% on (a+b) 10.91
d) Contractor's profit @ 10% on (a+b+c) 14.72
Rate for each tree = a+b+c+d 161.95
say 162.00
2.1 (ii) Girth from 600 mm to 900 mm
a) Labour
Mate day 0.040 329.34 13.17 L-12
Mazdoors for cutting trees including cutting, refilling, compaction day 0.900 152.91 137.62 L-13
of backfilling, and stacking of serviceable materials within 1000
metres lead by manual means
b) Machinery
Tractor-trolley hour 0.300 379.91 113.97 P&M-053
c) Overhead charges @ 8% on (a+b) 21.18
d) Contractor's profit @ 10% on (a+b+c) 28.59
Rate for each tree = a+b+c+d 314.54
say 315.00
2.1 (iii) Girth from 900 mm to 1800 mm
a) Labour
Mate day 0.080 329.34 26.35 L-12
Mazdoors for cutting trees including cutting, refilling, compaction day 2.000 152.91 305.81 L-13
of backfilling and stacking of serviceable materials within 1000
metres
b) Machinery
Tractor-trolley hour 0.400 379.91 151.97 P&M-053
c) Overhead charges @ 8% on (a+b) 38.73
d) Contractor's profit @ 10% on (a+b+c) 52.29
Rate for each tree = a+b+c+d 575.14
say 575.00
2.1 (iv) Girth above 1800 mm
a) Labour
Mate day 0.160 329.34 52.69 L-12
Mazdoors for cutting trees including cutting, refilling, compaction day 4.000 152.91 611.62 L-13
of backfilling and stacking of serviceable materials within 1000
metres
b) Machinery
Tractor-trolley hour 0.600 379.91 227.95 P&M-053
c) Overhead charges @ 8% on (a+b) 71.38
d) Contractor's profit @ 10% on (a+b+c) 96.36
Rate for each tree = a+b+c+d 1060.01
say 1060.00
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
2.2 201 Clearing Grass and Removal of Rubbish
Clearing grass and removal of rubbish up to a distance of 50 metres
outside the periphery of the area .
By Manual Means
Unit = Hectare
Taking output = 1 Hectare
a) Labour
Mate day 2.000 329.34 658.67 L-12
Mazdoor day 50.000 152.91 7645.30 L-13
b) Overhead charges @ 8% on (a) 664.32
c) Contractor's profit @ 10% on (a+b) 896.83
Rate per Hectare = a+b+c 9865.12
say 9865.00
2.3 201 Clearing and Grubbing Road Land .
Clearing and grubbing road land including uprooting rank vegetation,
grass, bushes, shrubs, saplings and trees girth up to 300 mm, removal
of stumps of trees cut earlier and disposal of unserviceable materials
and stacking of serviceable material to be used or auctioned, up to a
lead of 1000 metres including removal and disposal of top organic soil
not exceeding 150 mm in thickness.

Unit = Hectare
Taking output = 1 Hectare
2.3 (ii) By Mechanical Means
A In area of light jungle
a) Labour
Mate day 0.160 329.34 52.69 L-12
Mazdoor day 4.000 152.91 611.62 L-13
b) Machinery
Dozer 80 HP with attachment for removal of trees & stumps hour 10.000 3756.78 37567.83 P&M-014
Tractor-trolley hour 1.000 379.91 379.91 P&M-053
c) Overhead charges @ 8% on (a+b) 3088.96
d) Contractor's profit @ 10% on (a+b+c) 4170.10
Rate per Hectare = a+b+c+d 45871.13
say 45871.00
2.4 202 Dismantling of Structures
Dismantling of existing structures like culverts, bridges, retaining walls
and other structure comprising of masonry, cement concrete, wood
work, steel work, including T&P and scaffolding wherever necessary,
sorting the dismantled material, disposal of unserviceable material and
stacking the serviceable material with all lifts and lead of 1000 metres
Unit = cum
Taking output = 1.25 cum
(i) Lime /Cement Concrete
I By Manual Means
A Lime Concrete, cement concrete grade M-10 and below
a) Labour
Mate day 0.040 329.34 13.17 L-12
Mazdoor for dismantling and loading day 1.000 152.91 152.91 L-13
b) Machinery
Tractor-trolley hour 0.270 379.91 102.58 P&M-053
c) Overhead charges @ 8% on (a+b) 21.49
d) Contractor's profit @ 10% on (a+b+c) 29.01
Cost for 1.25 cum = a+b+c+d 319.16
Rate per cum = (a+b+c+d)/ 1.25 255.33
say 255.00
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
2.4 (i) B Cement Concrete Grade M-15 & M-20
a) Labour
Mate day 0.050 329.34 16.47 L-12
Mazdoor for dismantling and loading day 1.250 152.91 191.13 L-13
b) Machinery
Tractor-trolley hour 0.270 379.91 102.58 P&M-053
c) Overhead charges @ 8% on (a+b) 24.81
d) Contractor's profit @ 10% on (a+b+c) 33.50
Cost for 1.25 cum = a+b+c+d 368.49
Rate per cum = (a+b+c+d)/ 1.25 294.79
say 295.00
2.4 (i) C Prestressed / Reinforced cement concrete grade M-20 & above

a) Labour
Mate day 0.150 329.34 49.40 L-12
Blacksmith day 0.250 352.86 88.22 L-02
Mazdoor for dismantling, loading and unloading day 3.500 152.91 535.17 L-13
b) Machinery
Tractor-trolley hour 0.270 379.91 102.58 P&M-053
c) Overhead charges @ 8% on (a+b) 62.03
d) Contractor's profit @ 10% on (a+b+c) 83.74
Cost for 1.25 cum = a+b+c+d 921.13
Rate per cum = (a+b+c+d)/ 1.25 736.90
say 737.00
2.4 II By Mechanical Means for items No. 202( B)& ( C)
A Cement Concrete Grade M-15 & M-20
a) Labour
Mate day 0.020 329.34 6.59 L-12
Mazdoor for loading and unloading day 0.250 152.91 38.23 L-13
Mazdoor with Pneumatic breaker day 0.250 176.43 44.11 L-14
b) Machinery
Air Compressor 250 cfm with 2 leads of pneumatic breaker @ 1.5 hour 0.670 334.04 223.81 P&M-001
cum per hour
Tractor-trolley hour 0.270 379.91 102.58 P&M-053
c) Overhead charges @ 8% on (a+b) 33.22
d) Contractor's profit @ 10% on (a+b+c) 44.85
Cost for 1.25 cum = a+b+c+d 493.38
Rate per cum = (a+b+c+d)/ 1.25 394.71
say 395.00
2.4 II B Prestressed / reinforced cement concrete grade M-20 & above
a) Labour
Mate day 0.050 329.34 16.47 L-12
Mazdoor with Pneumatic breaker day 0.660 176.43 116.44 L-14
Blacksmith day 0.250 352.86 88.22 L-02
Mazdoor for loading and unloading day 0.250 152.91 38.23 L-13
b) Machinery
Air Compressor 250 cfm with 2 leads of pneumatic breaker @ hour 1.000 334.04 334.04 P&M-001
1.00 cum per hour
Tractor-trolley hour 0.270 379.91 102.58 P&M-053
c) Overhead charges @ 8% on (a+b) 55.68
d) Contractor's profit @ 10% on (a+b+c) 75.16
Cost for 1.25 cum = a+b+c+d 826.81
Rate per cum = (a+b+c+d)/ 1.25 661.45
say 661.00
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
2.4 (ii) Dismantling Brick / Tile work
A In lime mortar
a) Labour
Mate day 0.020 329.34 6.59 L-12
Mazdoor for dismantling, loading and unloading day 0.500 152.91 76.45 L-13
b) Machinery
Tractor-trolley hour 0.270 379.91 102.58 P&M-053
c) Overhead charges @ 8% on (a+b) 14.85
d) Contractor's profit @ 10% on (a+b+c) 20.05
Cost for 1.25 cum = a+b+c+d 220.51
Rate per cum = (a+b+c+d)/ 1.25 176.41
say 176.00
2.4 (ii) B In cement mortar
a) Labour
Mate day 0.030 329.34 9.88 L-12
Mazdoor for dismantling, loading and unloading day 0.750 152.91 114.68 L-13
b) Machinery
Tractor-trolley hour 0.270 379.91 102.58 P&M-053
c) Overhead charges @ 8% on (a+b) 18.17
d) Contractor's profit @ 10% on (a+b+c) 24.53
Cost for 1.25 cum = a+b+c+d 269.84
Rate per cum = (a+b+c+d)/ 1.25 215.87
say 216.00
2.4 (ii) C In mud mortar
a) Labour
Mate day 0.016 329.34 5.27 L-12
Mazdoor for dismantling and loading day 0.400 152.91 61.16 L-13
b) Machinery
Tractor-trolley hour 0.270 379.91 102.58 P&M-053
c) Overhead charges @ 8% on (a+b) 13.52
d) Contractor's profit @ 10% on (a+b+c) 18.25
Cost for 1.25 cum = a+b+c+d 200.78
Rate per cum = (a+b+c+d)/ 1.25 160.63
say 161.00
2.4 (ii) D Dry brick pitching or brick soling
a) Labour
Mate day 0.014 329.34 4.61 L-12
Mazdoor for Dismantling, loading and unloading day 0.350 152.91 53.52 L-13
b) Machinery
Tractor-trolley hour 0.270 379.91 102.58 P&M-053
c) Overhead charges @ 8% on (a+b) 12.86
d) Contractor's profit @ 10% on (a+b+c) 17.36
Cost for 1.25 cum = a+b+c+d 190.92
Rate per cum = (a+b+c+d)/ 1.25 152.73
say 153.00
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
2.4 (iii) Dismantling Stone Masonry
A Rubble stone masonry in lime mortar
a) Labour
Mate day 0.024 329.34 7.90 L-12
Mazdoor for dismantling, loading and unloading. day 0.600 152.91 91.74 L-13
b) Machinery
Tractor-trolley hour 0.270 379.91 102.58 P&M-053
c) Overhead charges @ 8% on (a+b) 16.18
d) Contractor's profit @ 10% on (a+b+c) 21.84
Cost for 1.25 cum = a+b+c+d 240.24
Rate per cum = (a+b+c+d)/ 1.25 192.19
say 192.00
2.4 (iii) B Rubble stone masonry in cement mortar.
a) Labour
Mate day 0.030 329.34 9.88 L-12
Mazdoor for dismantling, loading and unloading. day 0.750 152.91 114.68 L-13
b) Machinery
Tractor-trolley hour 0.270 379.91 102.58 P&M-053
c) Overhead charges @ 8% on (a+b) 18.17
d) Contractor's profit @ 10% on (a+b+c) 24.53
Cost for 1.25 cum = a+b+c+d 269.84
Rate per cum = (a+b+c+d)/ 1.25 215.87
say 216.00
2.4 (iii) C Rubble Stone Masonry in mud mortar.
a) Labour
Mate day 0.020 329.34 6.59 L-12
Mazdoor for dismantling, loading and unloading. day 0.500 152.91 76.45 L-13
b) Machinery
Tractor-trolley hour 0.270 379.91 102.58 P&M-053
c) Overhead charges @ 8% on (a+b) 14.85
d) Contractor's profit @ 10% on (a+b+c) 20.05
Cost for 1.25 cum = a+b+c+d 220.51
Rate per cum = (a+b+c+d)/ 1.25 176.41
say 176.00
2.4 (iii) D Dry rubble masonry
a) Labour
Mate day 0.018 329.34 5.93 L-12
Mazdoor for dismantling, loading and unloading. day 0.450 152.91 68.81 L-13
b) Machinery
Tractor-trolley hour 0.270 379.91 102.58 P&M-053
c) Overhead charges @ 8% on (a+b) 14.18
d) Contractor's profit @ 10% on (a+b+c) 19.15
Cost for 1.25 cum = a+b+c+d 210.65
Rate per cum = (a+b+c+d)/ 1.25 168.52
say 169.00
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
2.4 (iii) E Dismantling stone pitching/ dry stone spalls.
a) Labour
Mate day 0.016 329.34 5.27 L-12
Mazdoor for dismantling, loading and unloading. day 0.400 152.91 61.16 L-13
b) Machinery
Tractor-trolley hour 0.270 379.91 102.58 P&M-053
c) Overhead charges @ 8% on (a+b) 13.52
d) Contractor's profit @ 10% on (a+b+c) 18.25
Cost for 1.25 cum = a+b+c+d 200.78
Rate per cum = (a+b+c+d)/ 1.25 160.63
say 161.00
2.4 (iii) F Dismantling boulders laid in wire crates including opening of
crates and stacking dismantled materials.
a) Labour
Mate day 0.020 329.34 6.59 L-12
Mazdoor for dismantling, loading and unloading day 0.500 152.91 76.45 L-13
b) Machinery
Tractor-trolley hour 0.270 379.91 102.58 P&M-053
c) Overhead charges @ 8% on (a+b) 14.85
d) Contractor's profit @ 10% on (a+b+c) 20.05
Cost for 1.25 cum = a+b+c+d 220.51
Rate per cum = (a+b+c+d)/ 1.25 176.41
say 176.00
2.4 (iv) Wood Work wrought framed and fixed in frames of trusses upto
a height of 5 m above plinth level
a) Labour
Mate day 0.060 329.34 19.76 L-12
Carpenter day 0.500 352.86 176.43 L-04
Mazdoor for dismantling, loading and unloading. day 1.000 152.91 152.91 L-13
b) Machinery
Tractor-trolley hour 0.270 379.91 102.58 P&M-053
c) Overhead charges @ 8% on (a+b) 36.13
d) Contractor's profit @ 10% on (a+b+c) 48.78
Cost for 1.25 cum = a+b+c+d 536.59
Rate per cum = (a+b+c+d)/ 1.25 429.27
say 429.00
2.4 (v) Steel Work in all types of sections upto a height of 5 m above
plinth level excluding cutting of rivet.
Unit = tonne
Taking output = 1 tonne
A Including dismembering
a) Labour
Mate day 0.140 329.34 46.11 L-12
Blacksmith day 1.000 352.86 352.86 L-02
Mazdoor for dismantling, loading and unloading day 2.500 152.91 382.27 L-13
Add 2.5 per cent of cost of labour for gas cutting, ropes, pulleys etc. 19.53
b) Machinery
Tractor-trolley hour 0.170 379.91 64.59 P&M-053
c) Overhead charges @ 8% on (a+b) 69.23
d) Contractor's profit @ 10% on (a+b+c) 93.46
Rate per tonne = a+b+c+d 1028.03
say 1028.00
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
2.4 (v) B Excluding dismembering.
a) Labour
Mate day 0.220 329.34 72.45 L-12
Mazdoor for dismantling, loading and unloading day 2.000 152.91 305.81 L-13
Blacksmith day 0.500 352.86 176.43 L-02
Add 2.5 per cent of cost of labour for gas cutting, ropes, pulleys etc. 13.87
b) Machinery
Tractor-trolley hour 0.170 379.91 64.59 P&M-053
c) Overhead charges @ 8% on (a+b) 50.65
d) Contractor's profit @ 10% on (a+b+c) 68.38
Rate per tonne = a+b+c+d 752.18
say 752.00
2.4 (v) C Extra over item No( v ) A and( v ) B for cutting rivets.
Unit = each
Taking output = 10 rivets
a) Labour
Mate day 0.010 329.34 3.29 L-12
Blacksmith day 0.130 352.86 45.87 L-02
Mazdoor day 0.130 152.91 19.88 L-13
b) Overhead charges @ 8% on (a) 5.52
c) Contractor's profit @ 10% on (a+b) 7.46
Cost for 10 rivets = a+b+c 82.02
Rate for each rivet = ( a+b+c)/10 8.20
say 8.20
2.4 (vi) Scraping of Bricks Dismantled from Brick Work including
Stacking.
Unit = numbers
Taking output = 1000 numbers
A In lime/Cement mortar
a) Labour
Mate day 0.140 329.34 46.11 L-12
Mazdoor day 3.500 152.91 535.17 L-13
b) Overhead charges @ 8% on (a) 46.50
c) Contractor's profit @ 10% on (a+b) 62.78
Rate per1000 Nos = a+b+c 690.56
say 691.00
2.4 (iv) B In mud mortar
a) Labour
Mate day 0.050 329.34 16.47 L-12
Mazdoor day 1.250 152.91 191.13 L-13
b) Overhead charges @ 8% on (a) 16.61
c) Contractor's profit @ 10% on (a+b) 22.42
Rate per1000 Nos = a+b+c 246.63
say 247.00
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
2.4 (vii) Scraping of Stone from Dismantled Stone Masonry
Unit = cum
Taking output = 1 cum
A In cement and lime mortar
a) Labour
Mate day 0.060 329.34 19.76 L-12
Mazdoor day 1.400 152.91 214.07 L-13
b) Overhead charges @ 8% on (a) 18.71
c) Contractor's profit @ 10% on (a+b) 25.25
Rate per cum = a+b+c 277.79
say 278.00
2.4 (vii) B In Mud mortar

a) Labour
Mate day 0.010 329.34 3.29 L-12
Mazdoor day 0.300 152.91 45.87 L-13
b) Overhead charges @ 8% on (a) 3.93
c) Contractor's profit @ 10% on (a+b) 5.31
Rate per cum = a+b+c 58.41
say 58.00
2.4 (viii) Scarping Plaster in Lime or Cement Mortar from Brick/ Stone
Masonry
Unit = sqm
Taking output = 100 sqm
a) Labour
Mate day 0.160 329.34 52.69 L-12
Mazdoor for scarping and loading day 4.000 152.91 611.62 L-13
b) Machinery
Tractor-trolley hour 0.320 379.91 121.57 P&M-053
c) Overhead charges @ 8% on (a+b) 62.87
d) Contractor's profit @ 10% on (a+b+c) 84.88
Cost for 100 sqm = a+b+c+d 933.64
Rate per sqm = (a+b+c+d)/100 9.34
say 9.30
2.4 (ix) Removing all type of Hume Pipes and Stacking within a lead of
1000 metres including Earthwork and Dismantling of Masonry
Works.
Unit = metre
Taking output = 1 metre
A Up to 600 mm dia
a) Labour
Mate day 0.020 329.34 6.59 L-12
Mazdoor day 0.520 152.91 79.51 L-13
b) Overhead charges @ 8% on (a) 6.89
c) Contractor's profit @ 10% on (a+b) 9.30
Rate per metre = a+b+c 102.28
say 102.00
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
2.4 (ix) B Above 600 mm to 900 mm dia
a) Labour
Mate day 0.030 329.34 9.88 L-12
Mazdoor day 0.700 152.91 107.03 L-13
b) Overhead charges @ 8% on (a) 9.35
c) Contractor's profit @ 10% on (a+b) 12.63
Rate per metre = a+b+c 138.89
say 139.00
2.4 (ix) C Above 900 mm
a) Labour
Mate day 0.050 329.34 16.47 L-12
Mazdoor day 1.200 152.91 183.49 L-13
b) Overhead charges @ 8% on (a) 16.00
c) Contractor's profit @ 10% on (a+b) 21.60
Rate per metre = a+b+c 237.55
say 238.00
Note 1. The excavation of earth, dismantling of stone masonry work in head
walls and protection works is not included which is to be measured and
paid separately.
2. Credit for retrieved stone from masonry work may be taken as per
actual availability.
2.5 202 Dismantling of Flexible Pavements
Dismantling of flexible pavements and disposal of dismantled materials
up to a lead of 1000 metres, stacking serviceable and unserviceable
materials separately
Unit = cum
Taking output = 1 cum
I By Manual Means
A Bituminous courses
a) Labour
Mate day 0.060 329.34 19.76 L-12
Mazdoor for dismantling, loading and unloading day 1.500 152.91 229.36 L-13
b) Machinery
Tractor-trolley hour 0.380 379.91 144.37 P&M-053
c) Overhead charges @ 8% on (a+b) 31.48
d) Contractor's profit @ 10% on (a+b+c) 42.50
Rate per cum = a+b+c+d 467.46
say 467.00
2.5 I B Granular courses
a) Labour
Mate day 0.040 329.34 13.17 L-12
Mazdoor for dismantling, loading and unloading. day 1.000 152.91 152.91 L-13
b) Machinery
Tractor-trolley hour 0.330 379.91 125.37 P&M-053
c) Overhead charges @ 8% on (a+b) 23.32
d) Contractor's profit @ 10% on (a+b+c) 31.48
Rate per cum = a+b+c+d 346.24
say 346.00
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
2.5 II By Mechanical Means
A Bituminous course
a) Labour
Mate day 0.010 329.34 3.29 L-12
Mazdoor day 0.300 152.91 45.87 L-13
b) Machinery
Tractor-trolley hour 0.380 379.91 144.37 P&M-053
Farm tractor with ripper @ 60 cum per hour hour 0.017 517.53 8.80 P&M-055
c) Overhead charges @ 8% on (a+b) 16.19
d) Contractor's profit @ 10% on (a+b+c) 21.85
Rate per cum = a+b+c+d 240.37
say 240.00
2.6 202 Dismantling of Cement Concrete Pavement
Dismantling of cement concrete pavement by mechanical means using
pneumatic tools, breaking to pieces not exceeding 0.02 cum in volume
and stock piling at designated locations and disposal of dismantled
materials up to a lead of 1000 metres, stacking serviceable and
unserviceable materials separately

Unit = cum
Taking output = 1 cum
a) Labour
Mate day 0.030 329.34 9.88 L-12
Semi skilled mazdoor for operating pneumatic tools day 0.500 176.43 88.22 L-14
Mazdoors as helpers including loading and unloading day 0.500 152.91 76.45 L-13
b) Machinery
Air compressor 250 cfm with two leads for pneumatic cutters/ hour 1.000 334.04 334.04 P&M-001
hammers @ 1 cum per hour
Tractor-trolley hour 0.400 379.91 151.97 P&M-053
Joint Cutting Machine with 2-3 blades hour 1.000 176.43 176.43 P&M-083
c) Overhead charges @ 8% on (a+b) 66.96
d) Contractor's profit @ 10% on (a+b+c) 90.39
Rate per cum = a+b+c+d 994.34
say 994.00
Note The above analysis is for removal of complete pavement. In case full
depth repair work is required to be done after dismantling, provision of
a concrete cutting and sawing machine may be added for 0.25 hours.

2.7 202 Dismantling of Guard Rails


Dismantling guard rails by manual means and disposal of dismantled
material with all lifts and up to a lead of 1000 metres, stacking
serviceable materials and unserviceable materials separately.

Unit = running metre


Taking output = 1 metre
a) Labour
Mate day 0.006 329.34 1.98 L-12
Mazdoor including loading and unloading day 0.150 152.91 22.94 L-13
b) Machinery
Tractor-trolley hour 0.050 379.91 19.00 P&M-053
c) Overhead charges @ 8% on (a+b) 3.51
d) Contractor's profit @ 10% on (a+b+c) 4.74
Rate per metre = a+b+c+d 52.16
say 52.00
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
2.8 202 Dismantling of Kerb Stone
Dismantling kerb stone by manual means and disposal of dismantled
material with all lifts and up to a lead of 1000 metre

Unit = running metre


Taking output = 10 metre
a) Labour
Mate day 0.010 329.34 3.29 L-12
Mazdoor including loading and unloading day 0.150 152.91 22.94 L-13
b) Machinery
Tractor-trolley hour 0.200 379.91 75.98 P&M-053
c) Overhead charges @ 8% on (a+b) 8.18
d) Contractor's profit @ 10% on (a+b+c) 11.04
Cost for 10 m = a+b+c+d 121.43
Rate per metre = (a+b+c+d)/10 12.14
say 12.00
2.9 202 Dismantling of Kerb Stone Channel
Dismantling kerb stone channel by manual means and disposal of
dismantled material with all lifts and up to a lead of 1000 metre

Unit = running metre


Taking output = 10 metre
a) Labour
Mate day 0.015 329.34 4.94 L-12
Mazdoor including loading and unloading day 0.225 152.91 34.40 L-13
b) Machinery
Tractor-trolley hour 0.300 379.91 113.97 P&M-053
c) Overhead charges @ 8% on (a+b) 12.27
d) Contractor's profit @ 10% on (a+b+c) 16.56
Cost for 10 m = a+b+c+d 182.14
Rate per metre = (a+b+c+d)/10 18.21
say 18.00
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
2.10 202 Dismantling of Kilometre Stone
Dismantling of kilometre stone including cutting of earth, foundation
and disposal of dismantled material with all lifts and lead upto 1000 m
and back filling of pit.
Unit = Each
Taking output = one KM stone
A 5th KM stone
Quantity of cement concrete = 0.392 cum
a) Labour
Mate day 0.130 329.34 42.81 L-12
Mazdoor day 0.750 152.91 114.68 L-13
b) Machinery
Tractor-trolley hour 0.150 379.91 56.99 P&M-053
c) Overhead charges @ 8% on (a+b) 17.16
d) Contractor's profit @ 10% on (a+b+c) 23.16
Rate for one 5th KM stone = a+b+c+d 254.80
say 255.00
B Ordinary KM Stone
Quantity of cement concrete = 0.269 cum
a) Labour
Mate day 0.020 329.34 6.59 L-12
Mazdoor day 0.500 152.91 76.45 L-13
b) Machinery
Tractor-trolley hour 0.100 379.91 37.99 P&M-053
c) Overhead charges @ 8% on (a+b) 9.68
d) Contractor's profit @ 10% on (a+b+c) 13.07
Rate for one ordinary KM stone = a+b+c+d 143.78
say 144.00
CHAPTER - 3
EARTH WORK, EROSION CONTROL AND DRAINAGE
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
3.3 301 Excavation in Soil with Dozer with lead upto 100 metres

Excavation for road way in soil by mechanical means


including cutting and pushing the earth to site of embankment
upto a distance of 100 metres (average lead50 metres),
including trimming bottom and side slopes in accordance with
requirements of lines, grades and cross sections.

Unit = cum
Taking output = 180 cum
a) Labour
Mate day 0.080 329.34 26.35 L-12
Mazdoor day 2.000 152.91 305.81 L-13
b) Machinery
Dozer, 80 HP @ 30 cum per hour hour 6.000 3756.78 22540.70 P&M-014
c) Overhead charges @ 8% on (a+b) 1829.83
d) Contractor's profit @ 10% on (a+b+c) 2470.27
Cost for 180 cum = a+b+c+d 27172.95
Rate per cum = (a+b+c+d)/180 150.96
say 151.00
3.4 301 Excavation in Ordinary Rock with Dozer with lead upto
100 metres
Excavation for roadway in ordinary rock by deploying a
dozer, 80 HP including cutting and pushing the cut earth to
site of embankment upto a distance of 100 metres ( average
lead 50 metres ), trimming bottom and side slopes in
accordance with the requirements of lines, grades and cross
sections.
Unit = cum
Taking output = 108 cum
a) Labour
Mate day 0.120 329.34 39.52 L-12
Mazdoor day 3.000 152.91 458.72 L-13
b) Machinery
Dozer, 80 HP @ 20 cum per hour hour 6.000 3756.78 22540.70 P&M-014
c) Overhead charges @ 8% on (a+b) 1843.11
d) Contractor's profit @ 10% on (a+b+c) 2488.20
Cost for 108 cum = a+b+c+d 27370.25
Rate per cum = (a+b+c+d)/108 253.43
say 253.00
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
3.5 301 Excavation in Hard Rock (requiring blasting) with
disposal upto 1000 metres
Excavation for roadway in hard rock (requiring blasting) by
drilling, blasting and breaking, trimming of bottom and side
slopes in accordance with requirements of lines, grades and
cross sections, loading and disposal of cut road with in all lifts
and leads upto 1000 metres
Unit = cum
Taking 0utput = 180 cum
a) Labour
Mate day 0.220 329.34 72.45 L-12
Mazdoor day 3.000 152.91 458.72 L-13
Driller day 2.000 294.05 588.10 L-06
Blaster day 0.250 352.86 88.22 L-03
b) Machinery
Dozer, 80 HP @ 30 cum per hour hour 6.000 3756.78 22540.70 P&M-014
Air compressor, 250 cfm with 2 jack hammer hour 6.000 334.04 2004.24 P&M-001
Front end loader 1 cum bucket capacity hour 6.000 803.34 4820.07 P&M-017
Tipper10 tonne capacity hour 11.250 491.65 5531.08 P&M-048
c) Materials
Gelatin 80 per cent kg 63.000 131.73 8299.27 M-110
Electric Detonators @ 1 detonator for 2 gelatin sticks of each 252.000 4.61 1161.90 M-100 /100
125 gms each
Credit for excavated rock found suitable for use @ 50 cum 90.000 370.50 33345.27 M-096
per cent quantity blasted
d) Overhead charges @ 8% on (a+b+c) 6312.80
e) Contractor's profit @ 10% on (a+b+c+d) 8522.28
Cost for 180 cum = a+b+c+d+e 93745.09
Rate per cum = (a+b+c+d+e)/180 520.81
say 521.00
Note 1. The quality and availability of rock shall be checked before
affording credit.
2. In case some rock is issued to the contractor at site, the
item of carriage shall be reduced/restricted to that extent.
3.6 301 Excavation in Soil using Hydraulic Excavator CK 90 and
Tippers with Disposal upto 1000 metres.
Excavation for roadwork in soil with hydraulic excavator of
0.9 cum bucket capacity including cutting and loading in
tippers, trimming bottom and side slopes, in accordance with
requirements of lines, grades and cross sections, and
transporting to the embankment location within all lifts and
lead upto 1000m (including royality @ Rs. 24.00 per cum but
excluding watering, rolling & compaction)
Unit = cum
Taking output = 360 cum
a) Labour
Mate day 0.080 329.34 26.35 L-12
Mazdoor day 2.000 152.91 305.81 L-13
b) Machinery
Hydraulic excavator 0.9 cum bucket capacity @ 60 cum hour 6.000 1621.98 9731.88 P&M-026
per hour
Tipper 5.5 cum capacity, 4 trips per hour. hour 16.000 491.65 7866.43 P&M-048
c) Overhead charges @ 8% on (a+b) 1434.44
d) Contractor's profit @ 10% on (a+b+c) 1936.49
Cost for 360 cum = a+b+c+d 21301.39
Rate per cum = (a+b+c+d)/360 59.17
Royality @ Rs. 24.00 per Cum 24.00
Rate per cum 83.17
say 83.00
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
3.13 304 Earth work in excavation of foundation of structures as per
drawing and technical specification, including setting out,
construction of shoring and bracing, removal of stumps and
other deleterious matter, dressing of sides and bottom,
backfilling the excavation earth to the extent required and
utilising the remaining earth locally for road work.

(i) Ordinary soil


Unit = cum
Taking output = 10 cum
A Manual Means (Depth upto 3 m)
a) Labour
Mate day 0.320 329.34 105.39 L-12
Mazdoor day 8.000 152.91 1223.25 L-13
b) Overhead charges @ 8% on (a) 106.29
c) Contractor's profit @ 10% on (a+b) 143.49
Cost for 10 cum = a+b+c 1578.42
Rate per cum = (a+b+c)/10 157.84
say 158.00
Note Cost of dewatering may be added where required upto 10
per cent of labour cost Assessment for dewatering shall be
made as per site conditions..
3.13 (i) B Mechanical Means (Depth upto 3 m)
Unit = cum
Taking output = 300 cum
a) Labour
Mate day 0.320 329.34 105.39 L-12
Mazdoor day 8.000 152.91 1223.25 L-13
b) Machinery
Hydraulic excavator 1.0 cum bucket capacity hour 6.000 1621.98 9731.88 P&M-026
c) Overhead charges @ 8% on (a+b) 884.84
d) Contractor's profit @ 10% on (a+b+c) 1194.54
Cost for 300 cum = a+b+c+d 13139.89
Rate per cum = (a+b+c+d)/300 43.80
say 44.00
Note Cost of dewatering upto 5 per cent of (a+b) may be
added, where required. Assessment for dewatering shall be
made as per site conditions..
3.13 (ii) Ordinary Rock (not requiring blasting)
A Manual Means (Depth upto 3 m)
Unit = cum
Taking output = 10 cum
a) Labour
Mate day 0.400 329.34 131.73 L-12
Mazdoor day 10.000 152.91 1529.06 L-13
b) Overhead charges @ 8% on (a) 132.86
c) Contractor's profit @ 10% on (a+b) 179.37
Cost for 10 cum = a+b+c 1973.02
Rate per cum = (a+b+c)/10 197.30
say 197.00
Note Cost of dewatering upto 10 per cent of labour cost may be
added, where required. Assessment for dewatering shall be
made as per site conditions..
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
3.13 (ii) B Mechanical Means

Unit = cum
Taking output = 216 cum
a) Labour
Mate day 0.240 329.34 79.04 L-12
Mazdoor day 6.000 152.91 917.44 L-13
b) Machinery
Hydraulic excavator 1.0 cum bucket capacity hour 6.000 1621.98 9731.88 P&M-026
c) Overhead charges @ 8% on (a+b) 858.27
d) Contractor's profit @ 10% on (a+b+c) 1158.66
Cost for 216 cum = a+b+c+d 12745.29
Rate per cum = (a+b+c+d)/216 59.01
say 59.00
Note 1.Cost of dewatering upto 5 per cent of (a+b), may be
added, where required Assessment for dewatering shall be
made as per site conditions.
2.In case of rock, foundation beyond3 m is not dug and
hence not included.
3.13 (iii) Hard Rock ( requiring blasting )
A Manual Means
Unit = cum
Taking output = 10 cum
a) Labour
i) Mate day 0.530 329.34 174.55 L-12
ii) Driller day 0.840 294.05 247.00 L-06
iii) Blaster day 0.400 352.86 141.14 L-03
iv) Mazdoor day 12.000 152.91 1834.87 L-13
b) Machinery
Air Compressor 250 cfm with 2 jack hammer @ 15 cum hour 0.67 334.04 223.81 P&M-001
per hour
c) Material
Blasting Material kg 3.500 131.73 461.07 M-110
Detonator electric each 14.000 4.61 64.55 M-100 /100
d) Overhead charges @ 8% on (a+b+c) 251.76
e) Contractor's profit @ 10% on (a+b+c+d) 339.88
Cost for 10 cum = a+b+c+d+e 3738.63
Rate per cum = (a+b+c+d+e)/10 373.86
say 374.00
374.00
Note Cost of dewatering @ 10 per cent of labour cost may be
added, where required Assessment for dewatering shall be
made as per site conditions.
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
3.13 (iv) Hard Rock ( blasting prohibited )
Unit = cum
Taking output = 10 cum
A Mechanical Means
a) Labour
Mate day 0.200 329.34 65.87 L-12
Mazdoor day 5.000 152.91 764.53 L-13
b) Machinery
Air Compressor 250 cfm with 2 leads of pneumatic hour 10.000 334.04 3340.41 P&M-001
breaker @ 1 cum per hour
c) Overhead charges @ 8% on (a+b) 333.66
d) Contractor's profit @ 10% on (a+b+c) 450.45
Cost for 10 cum = a+b+c+d 4954.92
Rate per cum = (a+b+c+d)/10 495.49
say 495.00
Note 1. Cost of dewatering upto 5 per cent of (a+b), may be
added, where required Assessment for dewatering shall be
made as per site conditions.
2.In case of rock, foundation beyond 3 m is not dug and
hence not included.
3.13 (v) Marshy soil
Unit = cum
Taking output = 10 cum
A Manual means ( upto 3 m depth)
a) Labour
Mate/Supervisor day 0.400 329.34 131.73 L-12
Mazdoor day 10.000 152.91 1529.06 L-13
b) Machinery
Tractor-trolley hour 2.670 379.91 1014.37 P&M-053
c) Material
Selected earth for refilling cum 5.000 373.33 1866.63 M-168
d) Overhead charges @ 8% on (a+b+c) 363.34
e) Contractor's profit @ 10% on (a+b+c+d) 490.51
Cost for 10 cum = a+b+c+d+e 5395.65
Rate per cum = ( a+b+c+d+e)/ 10 539.56
say 540.00
Note 1. Cost of dewatering @ 30 per cent of (a), may be added,
where required Assessment for dewatering shall be made as
per site conditions.
2. Shoring & strutting 20 per cent of (a), where required may
be added
3. It is assumed that Marshy Soil will be available upto 3 m
depth only. For deeper excavation below 3 m depth, refer
analysis in item (i) to (iv) for ordinary soil
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
3.13 (v) B Mechanical Means

a) Labour
i) Mate day 0.080 329.34 26.35 L-12
ii) Mazdoor for dressing sides, bottom and backfilling day 2.000 152.91 305.81 L-13
b) Machinery
Hydraulic excavator 1.0 cum bucket capacity @ 60 cum hour 0.170 1621.98 275.74 P&M-026
per hour
Tipper 5.5 cum capacity, 4 trips per hour. hour 0.450 491.65 221.24 P&M-048
c) Material
Selected earth for refilling cum 5.000 373.33 1866.63 M-168
d) Overhead charges @ 8% on (a+b+c) 215.66
e) Contractor's profit @ 10% on (a+b+c+d) 291.14
Cost for 10 cum = a+b+c+d+e 3202.57
Rate per cum = (a+b+c+d+e)/10 320.26
say 320.00
Note 1. Cost of dewatering @ 20 per cent of (a+b) may be
added, where required
2. Shoring & strutting @ 10 per cent of (a+b), where
required may be added
3. It is assumed that Marshy Soil will be available upto 3 m
depth only. For deeper excavation below 3 m depth, refer
analysis in item (i) to (iv) for ordinary soil
3.15 305.4.3 Scarifying Existing Bituminous Surface to a depth of 50
mm by Mechanical Means
Scarifying the existing bituminous road surface to a depth of
50 mm and disposal of scarified material with in all lifts and
lead upto 1000 metres.
Unit = sqm
Taking output = 100 sqm
a) Labour
Mate day 0.010 329.34 3.29 L-12
Mazdoor day 0.250 152.91 38.23 L-13
b) Machinery
Tractor with ripper attachment @ 60 cum per hour hour 0.080 517.53 41.40 P&M-055
Front end loader 1 cum bucket capacity @ 25 cum per hour 0.200 803.34 160.67 P&M-017
hour
Tipper 5.5 cum capacity, 4 trips per hour. hour 0.230 491.65 113.08 P&M-048
c) Overhead charges @ 8% on (a+b) 28.53
d) Contractor's profit @ 10% on (a+b+c) 38.52
Cost for 100 sqm = a+b+c+d 423.73
Rate per sqm = (a+b+c+d)/100 4.24
say 4.20
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
3.16 305 Construction of Embankment with Material obtained
from Borrowpits
Construction of embankment with approved material obtained
from borrow pits with all lifts and leads, transporting to site,
spreading, grading to required slope and compacting to meet
requirement of table 300-2.
Unit = cum

a) Labour
Mate day 0.040 329.34 13.17 L-12
Mazdoor day 1.000 152.91 152.91 L-13
b) Machinery
Hydraulic Excavator1 cum bucket capacity @ 60 cum hour 1.670 1621.98 2708.71 P&M-026
per hour
Tipper 10 tonne capacity tonne.km 160 x L 4.12 1976.02 Lead =3 km
& P&M-047
Add 10 per cent of cost of carriage to cover cost of 100.00 30.00 3000.00
loading and unloading
Dozer 80 HP for spreading @ 200 cum per hour hour 0.500 3756.78 1878.39 P&M-014
Motor grader for grading @ 100 cum per hour hour 1.000 2627.63 2627.63 P&M-032
Water tanker6 KL capacity hour 4.000 517.53 2070.11 P&M-060
Vibratory roller 8 -10 tonnes @ 100 cum per hour hour 1.000 1671.38 1671.38 P&M-059
c) Material
Cost of water KL 24.000 55.58 1333.81 M-195
Compensation & Royality for earth taken from private cum 100.000 49.40 4940.04 M-098
land
d) Overhead charges @ 8% on (a+b+c) 1789.77
e) Contractor's profit @ 10% on (a+b+c+d) 2416.19
Cost for 100 cum = a+b+c+d+e 26578.13
Rate per cum = (a+b+c+d+e)/100 265.78
say 266.00
Note Compensation for earth will vary from place to place and will
have to be assessed realistically as per particular ground
situation. In case earth is available from Govt. land,
compensation for earth will not be required. The position is
required to be clearly stated in the cost estimate.
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
3.17 305 Construction of Embankment with Material Deposited
from Roadway Cutting
Construction of embankment with approved materials
deposited at site from roadway cutting and excavation from
drain and foundation of other structures graded and
compacted to meet requirement of table 300-2.
Unit = cum
Taking output = 100 cum
a) Labour
Mate day 0.020 329.34 6.59 L-12
Mazdoor day 0.500 152.91 76.45 L-13
b) Machinery
Dozer 80 HP for spreading @ 200 cum per hour hour 0.500 3756.78 1878.39 P&M-014
Motor grader for grading @ 100 cum per hour hour 1.000 2627.63 2627.63 P&M-032
Water tanker6 KL capacity hour 4.000 517.53 2070.11 P&M-060
Vibratory roller 8-10 tonnes @ 100 cum per hour hour 1.000 1671.38 1671.38 P&M-059
c) Material
Cost of water KL 24.000 55.58 1333.81 M-195
d) Overhead charges @ 8% on (a+b+c) 773.15
e) Contractor's profit @ 10% on (a+b+c+d) 1043.75
Rate for 100 cum = a+b+c+d+e 11481.27
Rate per cum = (a+b+c+d+e)/100 114.81
Royality @ Rs. 24.00 per Cum 24.00
say 139.00
Note In case the earth cutting is done by dozer and pushed for
filling in the embankment, the input of dozer in the cost of
embankment shall be deleted as the same is already
provided in the cost of excavation. However, if the earth is
dumped by tippers from roadway cutting, the input of dozer
for spreading is required to be provided.
3.18 305 Construction of Subgrade and Earthen Shoulders
Construction of sub-grade and earthen shoulders with
approved material obtained from borrow pits with all lifts &
leads, transporting to site, spreading, grading to required
slope and compacted to meet requirement of table No. 300-
2
Unit = cum
Taking output = 100 cum
a) Labour
Mate day 0.040 329.34 13.17 L-12
Mazdoor day 1.000 152.91 152.91 L-13
b) Machinery
Hydraulic excavator1 cum bucket capacity @ 60 cum hour 1.670 1621.98 2708.71 P&M-026
per hour
Tipper 10 tonne capacity tonne.km 175xL 4.12 2161.27 Lead =3 km
& P&M-047
Add 10 per cent of cost of carriage to cover cost of 100.00 45.00 4500.00
loading and unloading
Dozer 80 HP for spreading @ 200 cum per hour hour 0.500 3756.78 1878.39 P&M-014
Motor grader for grading @ 50 cum per hour hour 2.000 2627.63 5255.26 P&M-032
Water tanker with 6 km lead hour 4.000 517.53 2070.11 P&M-060
Vibratory roller 8-10 tonnes @ 80 cum per hour hour 1.250 1671.38 2089.23 P&M-059
c) Material
Cost of water KL 24.000 55.58 1333.81 M-195
Compensation & Royality for earth taken from private land cum 100.000 49.40 4940.04 M-098
d) Overhead charges @ 8% on (a+b+c) 2168.23
e) Contractor's profit @ 10% on (a+b+c+d) 2927.11
Cost for 100 cum = a+b+c+d+e 32198.24
Rate per cum = (a+b+c+d+e)/100 321.98
say 322.00
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
3.19 305.3.4 Compacting Original Ground
Case-I Compacting original ground supporting sub-grade
Loosening of the ground upto a level of 500 mm below the
sub-grade level, watered, graded and compacted in layers to
meet requirement of table 300-2 for sub-grade construction.

Unit = cum
Taking output = 600 cum
a) Labour
Mate day 0.120 329.34 39.52 L-12
Mazdoor day 3.000 152.91 458.72 L-13
b) Machinery
Tractor with ripper attachment hour 9.000 517.53 4657.75 P&M-055
Motor grader for grading hour 6.000 2627.63 15765.78 P&M-032
Water tanker 6 KL capacity hour 4.000 517.53 2070.11 P&M-060
Vibratory roller 8-10 tonne @ 80 cum/hour hour 7.500 1671.38 12535.35 P&M-059
c) Material
Cost of water KL 24.000 55.58 1333.81 M-195
d) Overhead charges @ 8% on (a+b+c) 2948.88
e) Contractor's profit @ 10% on (a+b+c+d) 3980.99
Cost for 600 cum = a+b+c+d+e 43790.93
Rate per cum = (a+b+c+d+e)/600 72.98
say 73.00
3.22 307 Turfing with Sods
Furnishing and laying of the live sods of perennial turf
forming grass on embankment slope, verges or other
locations shown on the drawing or as directed by the
engineer including preparation of ground, fetching of sods
and watering.
Unit = sqm
Taking output = 100 sqm
a) Labour
Mate day 0.120 329.34 39.52 L-12
Mazdoor for preparation of ground and fetching of sods day 3.000 152.91 458.72 L-13

b) Machinery
Water tanker including watering for 3 months hour 2.000 517.53 1035.06 P&M-060
Tractor-trolley hour 1.000 379.91 379.91 P&M-053
c) Material
Farm yard manure @ 0.18 cum per 100 sqm at site of cum 0.180 98.80 17.78 M-172
work
Cost of water KL 12.000 55.58 666.91 M-195
d) Overhead charges @ 8% on (a+b+c) 207.83
e) Contractor's profit @ 10% on (a+b+c+d) 280.57
Cost for 100 sqm = a+b+c+d+e 3086.30
Rate per 100 sqm = (a+b+c+d+e)/100 30.86

say 31.00
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
3.23 308 Seeding and Mulching
Preparation of seed bed on previously laid top soil, furnishing
and placing of seeds, fertilizer, mulching material, applying
bituminous emulsion at the rate of 0.23 litres per sqm and
laying and fixing jute netting, including watering for 3 months
all as per clause 308.
Unit = sqm
Taking output = 240 sqm
a) Labour
Mate day 0.400 329.34 131.73 L-12
Mazdoor day 10.000 152.91 1529.06 L-13
b) Machinery
Water tanker 6 KL capacity including watering for 3 hour 14.000 517.53 7245.39 P&M-060
months
Tractor-trolley hour 2.400 379.91 911.79 P&M-053
c) Material
Seeds kg 3.600 74.10 266.76 M-167
Sludge/Farm yard manure @ 0.18 cum per 100 sqm cum 0.430 98.80 42.48 M-172
Bitumen Emulsion litre 55.200 33.000 1821.60 M-076
Jute netting, open weave, 2.5 cm square opening sqm 264.000 33.35 8803.15 M-127
Cost of water for 3 months KL 84.000 55.58 4668.34 M-195
d) Overhead charges @ 8% on (a+b+c) 2033.62
e) Contractor's profit @ 10% on (a+b+c+d) 2745.39
Cost for 240 sqm = a+b+c+d+e 30199.33
Rate per sqm = (a+b+c+d+e)/240 125.83
say 126.00
126.00
3.24 309 Surface Drains in Soil
Construction of unlined surface drains of average cross
sectional area 0.40 sqm in soil to specified lines, grades,
levels and dimensions to the requirement of clause 301 and
309. Excavated material to be used in embankment within a
lead of 50 metres (average lead 25 metres)
Unit = metre
Taking output = 10 metres
A Mechanical means
a) Labour
Mate day 0.010 329.34 3.29 L-12
Mazdoor for dressing of bed and side of drain day 0.250 152.91 38.23 L-13
b) Machinery
Hydraulic Excavator 0.3 cum bucket capacity @ 30 hour 0.330 1621.98 535.25 P&M-026
metres per hour
c) Overhead charges @ 8% on (a+b) 46.14
d) Contractor's profit @ 10% on (a+b+c) 62.29
Cost for 10 metres = a+b+c+d 685.21
Rate per metre = (a+b+c+d)/10 68.52
say 69.00
3.24 B Manual Means
a) Labour
Mate day 0.080 329.34 26.35 L-12
Mazdoor day 2.000 152.91 305.81 L-13
b) Overhead charges @ 8% on (a) 26.57
c) Contractor's profit @ 10% on (a+b) 35.87
Cost for 10 metres = a+b+c 394.60
Rate per metre = (a+b+c)/10 39.46
say 39.00
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Note Where lining of drain is provided, quantity shall be worked out
based on approved design and drawing and priced on rate of
cement concrete of approved grade or stone/brick masonry
as the case may be.
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
3.25 309 Surface Drains in Ordinary Rock
Construction of unlined surface drain of average cross
sectional area 0.4 sqm in ordinary rock to specified lines,
grades, levels and dimensions as per approved design and to
the requirement of clause 301 to 309. Excavated material to
be used in embankment at site.
Unit = metre
Taking output = 10 metres
A Mechanical Means
a) Labour
Mate day 0.020 329.34 6.59 L-12
Mazdoor for dressing of bed and side of drain day 0.500 152.91 76.45 L-13
b) Machinery
Hydraulic Excavator 0.3 cum bucket capacity @ 15 hour 0.670 1621.98 1086.73 P&M-026
metres per hour
c) Overhead charges @ 8% on (a+b) 93.58
d) Contractor's profit @ 10% on (a+b+c) 126.33
Cost for 10 metres = a+b+c+d 1389.68
Rate per metre = (a+b+c+d)/10 138.97
say 139.00
3.25 B Manual Means
a) Labour
Mate day 0.120 329.34 39.52 L-12
Mazdoor day 3.000 152.91 458.72 L-13
b) Overhead charges @ 8% on (a) 39.86
c) Contractor's profit @ 10% on (a+b) 53.81
Cost for 10 metres = a+b+c 591.91
Rate per metre = (a+b+c)/10 59.19
say 59.00
3.26 309 Surface Drains in Hard Rock
Rate per metre may be worked out based on quantity of hard
rock as per design.
For rate of hard rock cutting, refer relevant item in this
chapter
3.27 309 Sub-Surface Drains with Perforated Pipe
Construction of subsurface drain with perforated pipe of 100
mm internal diameter of metal/ asbestos cement/ cement
concrete/PVC, closely jointed, perforations ranging from 3
mm to 6 mm depending upon size of material surrounding the
pipe, with 150 mm bedding below the pipe and 300 mm
cushion above the pipe, cross section of excavation 450 x
550 mm. Excavated material to be utilised in roadway at site.
Unit = metre
Taking output = 10 metres
a) Labour
Mate day 0.040 329.34 13.17 L-12
Mazdoor for excavation and back filling day 2.000 152.91 305.81 L-13
c) Material
Perforated pipe of cement concrete, internal dia 100 mm metre 10.000 148.82 1488.25 M-141

Crushed stone as per table 300-3 cum 2.400 1190.60 2857.43 M-012
d) Overhead charges @ 8% on (a+b+c) 373.17
e) Contractor's profit @ 10% on (a+b+c+d) 503.78
Cost for 10 metres = a+b+c+d+e 5541.62
Rate per metre = (a+b+c+d+e)/10 554.16
say 554.00
554.00
Note Type of pipe may be modified depending upon provision in
design.
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
3.28 309 Aggregate Sub-Surface Drains
Construction of aggregate sub surface drain 300 mm x 450
mm with aggregates conforming to table 300-4, excavated
material to be utilised in roadway.
Unit = metre
Taking output = 10 metres
a) Labour
Mate day 0.020 329.34 6.59 L-12
Mazdoor for excavation and back filling with aggregates day 1.500 152.91 229.36 L-13

b) Material
Crushed stone as per table 300-3 cum 1.350 1190.60 1607.31 M-012
c) Overhead charges @ 8% on (a+b) 147.46
d) Contractor's profit @ 10% on (a+b+c) 199.07
Cost for 10 metres = a+b+c+d 2189.78
Rate per metre = (a+b+c+d)/10 218.98
say 219.00
219.00
3.29 309 Underground Drain at Edge of Pavement
Construction of an underground drain 1 m x 1 m (inside
dimensions) lined with RCC-20 cm thick and covered with
RCC slab10 cm in thickness on urban roads.
Unit = Running metre
Taking output = one metre
a) Earthwork in soil cum 1.500 44.00 66.00 Item No.
3.13
b) RCC work M-20 cum 0.495 7693.00 3808.04 Item 12.8
(C) RCC
Rate per metre = (a+b) 3874.04
Rates for these items may be taken from chapters on earth say 3874.00
work and substructures respectively.
3874.00
3.30 310 Preparation and Surface Treatment of Formation.
Preparation and surface treatment of formation by removing
mud and slurry, watering to the extent needed to maintain the
desired moisture content, trimming to the required line,
grade, profile and rolling with 8-10 tonne smooth wheeled
roller, complete as per clause 310.
Unit = sqm
Taking output = 3500sqm
a) Labour
Mate day 0.280 329.34 92.21 L-12
Mazdoor day 6.000 152.91 917.44 L-13
Mazdoor skilled day 1.000 244.65 244.65 L-15
b) Machinery
Smooth 3 wheeled steel roller 8-10 tonnes hour 3.000 676.32 2028.95 P&M-044
Water tanker 6 KL, one trip per hour hour 3.000 517.53 1552.58 P&M-060
c) Material
Cost of water KL 18.000 55.58 1000.36 M-195
d) Overhead charges @ 8% on (a+b+c) 466.89
e) Contractor's profit @ 10% on (a+b+c+d) 630.31
Cost for 3500 sqm = a+b+c+d+e 6933.39
Rate per sqm = (a+b+c+d+e)/3500 1.98
say 2.00
2.00
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
3.31 313 Construction of Rock fill Embankment
Construction of rock fill embankment with broken hard rock
fragments of size not exceeding 300 mm laid in layers not
exceeding 500 mm thick including filling of surface voids with
stone spalls, blinding top layer with granular material, rolled
with vibratory road roller, all complete as per clause 313.

Unit = cum
Taking output = 100 cum
a) Labour
Mate day 0.040 329.34 13.17 L-12
Mazdoor day 1.500 152.91 229.36 L-13
b) Machinery
Dozer 80 HP for spreading @ 200 cum per hour hour 0.500 3756.78 1878.39 P&M-014
Vibratory road roller 8-10 tonnes @ 100 cum per hour hour 1.000 1671.38 1671.38 P&M-059

Water tanker 6 KL, one trip per hour hour 2.000 517.53 1035.06 P&M-060
c) Material
Cost of water KL 12.000 55.58 666.91 M-195
d) Overhead charges @ 8% on (a+b+c) 439.54
e) Contractor's profit @ 10% on (a+b+c+d) 593.38
Cost for 100 cum = a+b+c+d+e 6527.19
Rate per cum = (a+b+c+d+e)/100 65.27
say 65.00
65.00
Note It is assumed that rock is available locally at site from
roadway cutting. In case, portion of the rock requires
breaking to acceptable size of 300 mm, breaking charges will
have to be added.
EARTH WORK ON HILL ROAD
3.32 301 Excavation in Hill Area in Soil by Mechanical Means
Excavation in soil in hilly area by mechanical means including
cutting and trimming of side slopes and disposing of
excavated earth with all lifts and lead upto 1000 metres.
Unit = cum
Taking output = 260 cum
a) Labour
Mate day 0.240 329.34 79.04 L-12
Mazdoor for trimming slopes and helping in excavation day 6.000 152.91 917.44 L-13
etc.
b) Machinery
Dozer 80 HP (D-80 A 12)@ 43.28 cum per hour hour 6.000 3756.78 22540.70 P&M-014
Front end loader hour 6.000 803.34 4820.07 P&M-017
Tipper 5.5cum capacity, 4 trips per hour. hour 12.000 491.65 5899.82 P&M-048
c) Overhead charges @ 8% on (a+b) 2740.56
d) Contractor's profit @ 10% on (a+b+c) 3699.76
Cost for 260 cum = a+b+c+d 40697.39
Rate per cum = (a+b+c+d)/260 156.53
say 157.00
157.00
Note In case the land on the valley side is barren and there is no
objection for disposing of excavated earth on the valley side,
the provision of front end loader and tipper shall be deleted
as excavated earth shall be disposed off on the valley side.
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
3.33 301 Excavation in Hilly Area in Ordinary Rock by Mechanical
Means not Requiring Blasting.
Excavation in hilly area in ordinary rock not requiring blasting
by mechanical means including cutting and trimming of
slopes and disposal of cut material with all lift and lead upto
1000 metres.
Unit = cum
Taking output = 170 cum
a) Labour
Mate day 0.320 329.34 105.39 L-12
Mazdoor day 8.000 152.91 1223.25 L-13
b) Machinery
Dozer 80 HP (D-80 A 12)@ 28.32 cum per hour hour 6.000 3756.78 22540.70 P&M-014
Front end loader hour 7.000 803.34 5623.41 P&M-017
Tipper 5.5cum capacity, 4 trips per hour. hour 7.000 491.65 3441.56 P&M-048
c) Overhead charges @ 8% on (a+b) 2634.74
d) Contractor's profit @ 10% on (a+b+c) 3556.91
Cost for 170 cum = a+b+c+d 39125.96
Rate per cum = (a+b+c+d)/170 230.15
say 230.00
230.00
Note In case the land on the valley side is barren and there is no
objection for disposing of excavated earth on the valley side,
the provision of front end loader and tipper shall be deleted
as excavated earth can be disposed off on the valley side.

3.34 301 Excavation in Hilly Areas in Hard Rock Requiring


Blasting
Excavation in hilly areas in hard rock requiring blasting, by
mechanical means including trimming of slopes and disposal
of cut material with all lifts and lead upto 1000 metres.
Unit = cum
Taking output = 170 cum
a) Labour
Mate day 0.490 329.34 161.37 L-12
Mazdoor day 10.000 152.91 1529.06 L-13
Driller day 2.000 294.05 588.10 L-06
Blaster day 0.250 352.86 88.22 L-03
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
b) Machinery
Dozer 80 HP (D-80 A 12)@ 28.32 cum per hour hour 6.000 3756.78 22540.70 P&M-014
Air compressor 250 cfm with two jack hammer @ 20 hour 5.000 334.04 1670.20 P&M-001
cum per hour
Front end loader hour 7.000 803.34 5623.41 P&M-017
Tipper 5.5cum capacity, 4 trips per hour. hour 7.000 491.65 3441.56 P&M-048
c) Materials
Gelatine 80 per cent kg 35.000 131.73 4610.70 M-110
Electric Detonators @ 1 Detonator for 2 Gelatine sticks each 140.000 4.61 645.50 M-100 /100
of 125 gms each
d) Overhead charges @ 8% on (a+b+c) 3271.91
e) Contractor's profit @ 10% on (a+b+c+d) 4417.07
Cost for 170 cum = a+b+c+d+e 48587.81
Rate per cum = (a+b+c+d+e)/170 285.81
say 286.00
286.00
Note In case the land on the valley side is barren and there is no
objection for disposing of excavated earth on the valley side,
the provision of front end loader and tipper shall be deleted
as excavated earth can be disposed off on the valley side.

In case of hill roads, the altitude effect comes into play. The
output of men and machines decreases progressively after
2100 m elevation leading to increase in cost . High altitude
effect has been explained in the basic approach.
3.35 Work in Urban Roads
The cost of earth work in urban roads inhabited area will be
comparatively higher due to following reasons:
a) There is mixed traffic on urban roads like slow moving
hand and animal driven carts, rickshaws, cycles, two/ three
wheeler apart from the usual vehicular traffic resulting into
traffic jams. This causes loss of working time which may be in
the range of 10 -15 per cent
b) There is considerable disruption of traffic adversely
affecting the efficiency of the working parties including
machines due to congestion caused by pedestrian traffic,
local road side venders, parking of vehicles by the road side,
encroachments by the shopkeepers and local shops who
make use of the berms of the road in front of these shops
and unauthorised conversion of road berms into mini local
market The output of manpower and machines is
substantially reduced due to factors mentioned above.
c) Cost of living in urban areas is comparatively more
resulting into higher wages.
d) At times, work is executed during night time due to
heavy traffic during day time. This involves extra expenditure
by way of making arrangement for lighting and special
transport for working parties due to odd hour
In the light of above, the authorities engaged in preparing the
cost estimates may exercise their judgment and cater for the
additional cost to the extent of 2 to 3 per cent, keeping in
view the severity of factors mentioned above. Supporting
details for the extra cost based on the actual conditions in
specific cases will have to give in justification.
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
3.36 Suggesti Embankment Construction with Flyash/Pond ash
ve available from coal or lignite burning Thermal Plants as
waste material.
Construction of embankment with Flyash conforming to table
1 of IRC: SP: 58 - 2001 obtained from coal or lignite burning
thermal power stations as waste material, spread and
compacted in layer of 200mm thickness each at OMC, all as
specified in IRC: SP: 58-2001 and as per approved plans.

Unit = cum
Taking output = 360 cum
a) Labour
Mate day 0.160 329.34 52.69 L-12
Mazdoor day 4.000 152.91 611.62 L-13
b) Machinery
Hydraulic Excavator 0.9 cum bucket capacity @ 60 hour 6.000 1621.98 9731.88 P&M-026
cum/hour
Tipper 10Tcapacity flyash 360 x 1.2 = 432 tonnes tonne.km 432 x L 70.57 91461.31 Lead =3 km
& P&M-047
Add 10 per cent of cost of carriagefor loading and 9146.13
unloading
Dozer 80 HP for spreading @ 200 cum/hour hour 1.800 3756.78 6762.21 P&M-014
Motor Grader for grading @ 100 cum/hour hour 3.600 2627.63 9459.47 P&M-032
Water tanker6 KL capacity hour 12.000 517.53 6210.34 P&M-060
Vibratory Roller 8-10 tonne @ 100 cum/hour hour 3.600 1671.38 6016.97 P&M-059
c) Overhead charges @ 8% on (a+b) 11156.21
d) Contractor's profit @ 10% on (a+b+c) 15060.88
Cost for 360 cum = a+b+c+d 165669.72
Rate per cum = (a+b+c+d)/360 460.19
say 460.00
460.00
Note 1.As flyash is available free of cost as waste material from
Thermal Plants, cost of material has not been added.
2.The earth cover on sides and intermediate layers of earth
sandwiching the flyash have not been included in this
analysis. The same are required to be provided as per
approved design and priced separately as embankment
construction.
CHAPTER - 4
SUB-BASES, BASES ( NON- BITUMINOUS) AND SHOULDERS
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
4.1 401 Granular Sub-Base with Close Graded Material (Table:- 400-
1)
A Plant Mix Method
Construction of granular sub-base by providing close graded
Material, mixing in a mechanical mix plant at OMC, carriage of
mixed Material to work site, spreading in uniform layers with
motor grader on prepared surface and compacting with
vibratory power roller to achieve the desired density, complete
as per clause 401
Unit = cum
Taking output = 225 cum (450 tonne)
a) Labour
Mate day 0.400 329.34 131.73 L-12
Mazdoor skilled day 2.000 244.65 489.30 L-15
Mazdoor day 8.000 152.91 1223.25 L-13
b) Machinery
Wet mix plant @ 75 tonne capacity per hour hour 6.000 1591.40 9548.39 P&M-092
Electric generator 125 KVA hour 6.000 979.77 5878.65 P&M-018
Water tanker 6 KL capacity 5 km lead with one tripper hour hour 4.500 517.53 2328.88 P&M-060

Front end loader 1 cum bucket capacity hour 6.000 803.34 4820.07 P&M-017
Tipper 10 tonne tonne.km 450 x L 4.12 5557.55 Lead =3 km &
P&M-047
Add 10 per cent of cost of carriage to cover loading and 555.75
unloading
Motor Grader 110 HP hour 6.000 2627.63 15765.78 P&M-032
Vibratory roller 8-10 t hour 6.000 1671.38 10028.28 P&M-059
c) Material
Close graded Granular sub-base Material as per table 400-1

For Grading-I Material


53 mm to 9.5 mm @ 50 per cent cum 144.000 1449.36 208707.94 M-013
9.5 mm to 2.36 mm @ 20 per cent cum 57.000 1681.07 95821.11 M-017
2.36 mm below @ 30 per cent cum 86.400 896.55 77461.63 M-020
Cost of water KL 27.000 55.58 1500.54 M-195
OR
For Grading-II Material
26.5 mm to 9.5 mm @ 35 per cent cum 100.800 1681.07 169452.07 M-015
9.5 mm to 2.36 mm @ 25 per cent cum 72.000 1681.07 121037.19 M-017
2.36 mm below @ 40 per cent cum 115.200 896.55 103282.18 M-020
Cost of water KL 27.000 55.58 1500.54 M-195
OR
For Grading-III Material
9.5 mm to 4.75 mm @ 35 per cent cum 100.800 1681.07 169452.07 M-016
4.75 mm to 2.36 mm @ 12.5 per cent cum 36.000 1681.07 60518.60 M-018
2.36 mm below @ 52.5 per cent cum 151.200 896.55 135557.86 M-020
Cost of water KL 27.000 55.58 1500.54 M-195
4.1A (i) Rate per cum for grading-I Material
d) Overhead charges @ 8% on (a+b+c) 35185.51
e) Contractor's profit @ 10% on (a+b+c+d) 47500.44
Cost for 225 cum = a+b+c+d+e 522504.79
Rate per cum = (a+b+c+d+e)/225 2322.24
say 2322.00
2322.00
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
4.1A (ii) Rate per cum for grading-II Material

d) Overhead charges @ 8% on (a+b+c) 36127.97


e) Contractor's profit @ 10% on (a+b+c+d) 48772.76
Cost for 225 cum = a+b+c+d+e 536500.33
Rate per cum = (a+b+c+d+e)/225 2384.45
say 2384.00
2384.00
4.1A (iii) Rate per cum for grading-III Material
d) Overhead charges @ 8% on (a+b+c) 33868.54
e) Contractor's profit @ 10% on (a+b+c+d) 45722.52
Cost for 225 cum = a+b+c+d+e 502947.75
Rate per cum = (a+b+c+d+e)/225 2235.32
say 2235.00
2235.00
Note Any one of the grading for material may be adopted as per
design
4.1 B By Mix in Place Method
Construction of granular sub-base by providing close graded
material, spreading in uniform layers with motor grader on
prepared surface, mixing by mix in place method with rotavator
at OMC, and compacting with vibratory roller to achieve the
desired density, complete as per clause 401
Unit = cum
Taking output = 300 cum
a) Labour
Mate day 0.480 329.34 158.08 L-12
Mazdoor skilled day 2.000 244.65 489.30 L-15
Mazdoor unskilled day 10.000 152.91 1529.06 L-13
b) Machinery
Motor Grader 110 HP @ 50 cum hour 6.000 2627.63 15765.78 P&M-032
Vibratory roller 8 -10 tonne hour 6.000 1671.38 10028.28 P&M-059
Tractor - Rotavator hour 12.000 506.94 6083.31 P&M-054
Water tanker 6 KL capacity hour 3.000 517.53 1552.58 P&M-060
c) Material
Close graded Granular sub-base Material as per table 400-1

For Grading-I Material


53 mm to 9.5 mm @ 50 per cent cum 192.000 1449.36 278277.25 M-013
9.5 mm to 2.36 mm @ 20 per cent cum 76.000 1681.07 127761.48 M-017
2.36 mm below @ 30 per cent cum 115.200 896.55 103282.18 M-020
Cost of water KL 18.000 55.58 1000.36 M-195
OR
For Grading-II Material
26.5 mm to 9.5 mm @ 35 per cent cum 134.400 1681.07 225936.09 M-015
9.5 mm to 2.36 mm @ 25 per cent cum 96.000 1681.07 161382.92 M-017
2.36 mm below @ 40 per cent cum 153.600 896.55 137709.57 M-020
Cost of water KL 18.000 55.58 1000.36 M-195
OR
For Grading-III Material
9.5 mm to 4.75 mm @ 35 per cent cum 134.400 1681.07 225936.09 M-016
4.75 mm to 2.36 mm @ 12.5 per cent cum 48.000 1681.07 80691.46 M-018
2.36 mm below @ 52.5 per cent cum 201.600 896.55 180743.81 M-020
Cost of water KL 18.000 55.58 1000.36 M-195
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
4.1B (i) Rate per cum for grading-I Material
d) Overhead charges @ 8% on (a+b+c) 43674.21
e) Contractor's profit @ 10% on (a+b+c+d) 58960.19
Cost for 300 cum = a+b+c+d+e 648562.07
Rate per cum = (a+b+c+d+e)/300 2161.87
say 2162.00
2162.00
4.1B (ii) Rate per cum for grading-II Material
d) Overhead charges @ 8% on (a+b+c) 44930.83
e) Contractor's profit @ 10% on (a+b+c+d) 60656.62
Cost for 300 cum = a+b+c+d+e 667222.78
Rate per cum = (a+b+c+d+e)/300 2224.08
say 2224.00
2224.00
4.1B (iii) Rate per cum for grading-III Material
d) Overhead charges @ 8% on (a+b+c) 41918.25
e) Contractor's profit @ 10% on (a+b+c+d) 56589.64
Cost for 300 cum = a+b+c+d+e 622486.00
Rate per cum = (a+b+c+d+e)/300 2074.95
say 2075.00
2075.00
Note Any one of the grading for material may be adopted as per
design
4.2 401 Granular Sub-Base with Coarse Graded Material (Table:-
400- 2)
Construction of granular sub-base by providing coarse graded
material, spreading in uniform layers with motor grader on
prepared surface, mixing by mix in place method with rotavator
at OMC, and compacting with vibratory roller to achieve the
desired density, complete as per clause 401.
Unit = cum
Taking output = 300 cum
a) Labour
Mate day 0.400 329.34 131.73 L-12
Mazdoor skilled day 2.000 244.65 489.30 L-15
Mazdoor day 8.000 152.91 1223.25 L-13
b) Machinery
Mortar Grader 110 HP @ 50 cum per hour hour 6.000 2627.63 15765.78 P&M-032
Vibratory roller 8 -10 tonne hour 6.000 1671.38 10028.28 P&M-059
Water tanker 6 KL capacity hour 3.000 517.53 1552.58 P&M-060
c) Material
For coarse graded Granular sub-base Materials per table 400-2

For grading-I Material


53 mm to 26.5 mm @ 35 per cent cum 134.400 1402.31 188470.83 M-029
26.5 mm to 4.75 mm @ 45 per cent cum 172.800 1661.08 287034.05 M-026
2.36 mm below @ 20 per cent (Coarse Sand) cum 76.800 861.26 66144.82 M-022
Cost of water KL 18.000 55.58 1000.36 M-195
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
OR
For Grading-II Material
26.5 mm to 4.75 mm @ 75 per cent cum 288.000 1661.08 478390.09 M-026
2.36 mm below @ 25 per cent cum 96.000 861.26 82681.03 M-022
Cost of water KL 18.000 55.58 1000.36 M-195
OR
For Grading-III Material
9.5 mm to 4.75 mm @ 66 per cent cum 255.000 1684.60 429573.18 M-025
2.36 mm below @ 34 per cent cum 129.000 861.26 111102.63 M-022
Cost of water KL 18.000 55.58 1000.36 M-195
4.2 (i) Rate per cum for grading-I Material
d) Overhead charges @ 8% on (a+b+c) 45747.28
e) Contractor's profit @ 10% on (a+b+c+d) 61758.83
Cost for 300 cum = a+b+c+d+e 679347.09
Rate per cum = (a+b+c+d+e)/300 2264.49
say 2264.00
2264.00
4.2 (ii) Rate per cum for grading-II Material
d) Overhead charges @ 8% on (a+b+c) 47300.99
e) Contractor's profit @ 10% on (a+b+c+d) 63856.34
Cost for 300 cum = a+b+c+d+e 702419.73
Rate per cum = (a+b+c+d+e)/300 2341.40
say 2341.00
2341.00
4.2 (iii) Rate per cum for grading-III Material
d) Overhead charges @ 8% on (a+b+c) 45669.37
e) Contractor's profit @ 10% on (a+b+c+d) 61653.65
Cost for 300 cum = a+b+c+d+e 678190.11
Rate per cum = (a+b+c+d+e)/300 2260.63
say 2261.00
2261.00
Note Any one of the grading for material may be adopted as per
design
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
4.3 402 Lime Stabilisation for Improving Sub-grade
Laying and spreading available soil in the sub-grade on a
prepared surface, pulverising, mixing the spread soil in place
with rotavator with 3 per cent slaked lime having minimum
content of 70 per cent of CaO, grading with motor grader and
compacting with the road roller at OMC to the desired density
to form a layer of improved sub grade
Unit = cum
Taking output = 300 cum (525 tonne)
A By Mechanical Means
a) Labour
Mate day 0.360 329.34 118.56 L-12
Skilled mazdoor for alignment and geometrics day 1.000 244.65 244.65 L-15
Mazdoor for spraying lime day 8.000 152.91 1223.25 L-13
b) Machinery
Tractor with ripper and rotavator attachments @ 60 cum hour 12.000 517.53 6210.34 P&M-055
per hour for ripping and 25 cum per hour for mixing

Motor Grader 110 HP @ 50 cum per hour hour 6.000 2627.63 15765.78 P&M-032
Vibratory roller 8 - 10 tonne capacity hour 6.00x0.65* 1671.38 6518.38 P&M-059
Water tanker 6 KL capacity hour 12.000 517.53 6210.34 P&M-060
c) Material
Lime at site tonne 15.750 9571.33 150748.41 M-194
Cost of water KL 72.000 55.58 4001.43 M-195
d) Overhead charges @ 8% on (a+b+c) 15283.29
e) Contractor's profit @ 10% on (a+b+c+d) 20632.44
Cost for 300 cum= a+b+c+d+e 226956.87
Rate per cum =( a+b+c+d+e)/300 756.52
say 757.00
757.00
Note * Though vibratory roller is required only for 3 hours as per
norms, but the same has to be available at site for 6 hours as
other machines for spreading and mixing will take 6 hours. The
usage rates of roller have been multiplied with a factor of 0.65.

4.3 B By Manual Means


Unit = cum
Taking output = 150 cum (263 tonnes)
a) Labour
Mate day 1.440 329.34 474.24 L-12
Mazdoor skilled day 1.000 244.65 244.65 L-15
Mazdoor day 35.000 152.91 5351.71 L-13
b) Machinery
Vibratory roller 8 - 10 tonne @ 60 cum per hour hour 2.500 1671.38 4178.45 P&M-059
Water tanker 6 KL capacity hour 6.000 517.53 3105.17 P&M-060
c) Material
Lime at site tonne 8.000 9571.33 76570.62 M-194
Cost of water KL 36.000 55.58 2000.72 M-195
d) Overhead charges @ 8% on (a+b+c) 7354.04
e) Contractor's profit @ 10% on (a+b+c+d) 9927.96
Cost for 150 cum= a+b+c+d+e 109207.56
Rate per cum =( a+b+c+d+e)/150 728.05
say 728.00
728.00
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
4.4 402 Lime Treated Soil for Sub- Base
Providing, laying and spreading soil on a prepared sub grade,
pulverising, mixing the spread soil in place with rotavator with 3
per cent slaked lime with minimum content of 70 per cent of
CaO, grading with motor grader and compacting with the road
roller at OMC to achieve at least 98 per cent of the max dry
density to form a layer of sub base.
Unit = cum
Taking output = 300 cum (525 tonnes)
a) Labour
Mate day 0.480 329.34 158.08 L-12
Mazdoor skilled day 2.000 244.65 489.30 L-15
Mazdoor day 10.000 152.91 1529.06 L-13
b) Machinery
Excavator 0.90 cum bucket capacity hour 6.000 1621.98 9731.88 P&M-026
Tipper for carriage of soil tonne.km 525 x L 70.57 111150.90 Lead =3 km &
P&M-047
Add 10 per cent of cost of carriage to cover cost of 11115.09
loading and unloading
Motor Grader 110 HP @ 50 cum per hour hour 6.000 2627.63 15765.78 P&M-032
Vibratory roller 8 - 10 tonne hour 6.000 1671.38 10028.28 P&M-059
Tractor with Rotavator and blade @ 25 cum per hour hour 12.000 506.94 6083.31 P&M-054
Water tanker 6 KL capacity hour 12.000 517.53 6210.34 P&M-060
c) Material
Lime at site tonne 15.750 9571.33 150748.41 M-194
Cost of water KL 72.000 55.58 4001.43 M-195
d) Overhead charges @ 8% on (a+b+c) 26160.95
e) Contractor's profit @ 10% on (a+b+c+d) 35317.28
Cost for 300 cum = a+b+c+d+e 388490.09
Rate per cum= (a+b+c+d+e)/300 1294.97
say 1295.00
1295.00
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
4.5 403 Cement Treated Soil Sub Base/ Base
Providing, laying and spreading soil on a prepared sub grade,
pulverising, adding the designed quantity of cement to the
spread soil, mixing in place with rotavator, grading with the
motor grader and compacting with the road roller at OMC to
achieve the desired unconfined compressive strength and to
form a layer of sub-base/base.
Unit = cum
Taking output = 300 cum (525 tonnes)
For 4 per cent quantity of cement by weight of soil
a) Labour
Mate day 0.480 329.34 158.08 L-12
Mazdoor skilled day 2.000 244.65 489.30 L-15
Mazdoor day 10.000 152.91 1529.06 L-13
b) Machinery
Excavator 0.90 cum bucket capacity hour 6.000 1621.98 9731.88 P&M-026
Tipper for carriage of soil tonne.km 525 x L 4.12 6483.80 Lead =3 km &
P&M-047
Add 10 per cent of cost of carriage to cover cost of 648.38
loading and unloading
Motor Grader 110 HP @ 50 cum per hour hour 6.000 2627.63 15765.78 P&M-032
Vibratory roller 8 - 10 tonne hour 6.000 1671.38 10028.28 P&M-059
Tractor with Rotavator and blade @ 25 cum per hour hour 12.000 506.94 6083.31 P&M-054
Water tanker 6 KL capacity hour 12.000 517.53 6210.34 P&M-060
c) Material
Cement at site (@ 4 per cent of 525 tonne) tonne 21.000 8939.12 187721.52 M-086
Cost of water KL 72.000 55.58 4001.43 M-195
d) Overhead charges @ 8% on (a+b+c) 19908.09
e) Contractor's profit @ 10% on (a+b+c+d) 26875.93
Cost for 300 cum = a+b+c+d+e 295635.18
Rate per cum= (a+b+c+d+e)/300 985.45
say 985.00
985.00
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
4.6 403 Cement Treated Crushed Rock or combination as per
clause 403.2 and table 400.4in Sub base/ Base
Providing, laying and spreading Material on a prepared sub
grade, adding the designed quantity of cement to the spread
Material, mixing in place with rotavator, grading with the motor
grader and compacting with the road roller at OMC to achieve
the desired unconfined compressive strength and to form a
layer of sub-base/base.
Unit = cum
Taking output = 300 cum (600 tonnes)
Quantity of cement assumed as 4 per cent of quantity of
crushed rock by weight.
a) Labour
Mate day 0.480 329.34 158.08 L-12
Mazdoor skilled day 2.000 244.65 489.30 L-15
Mazdoor day 10.000 152.91 1529.06 L-13
b) Machinery
Motor Grader 110 HP @ 50 cum per hour hour 6.000 2627.63 15765.78 P&M-032
Vibratory roller 8 - 10 tonne hour 6.000 1671.38 10028.28 P&M-059
Tractor with Rotavator and blade @ 25 cum per hour hour 12.000 506.94 6083.31 P&M-054
Water tanker 6 KL capacity hour 10.000 517.53 5175.28 P&M-060
c) Material
Cement at site @ 4 per cent by weight of crushed tonne 24.000 8939.12 214538.88 M-086
aggregate (600 tonne)
Grading of material for sub-base course
37.5 mm to 9.5 mm @ 55 per cent cum 211.200 1566.98 330946.32 M-014
9.5 mm to 4.75 mm @ 20 per cent cum 76.800 1681.07 129106.34 M-025
4.75 mm to 75 micron @ 25 per cent cum 96.000 1681.07 161382.92 M-019
Cost of water KL 60.000 55.58 3334.53 M-195
or
Grading of material for Base course
37.5 mm to 9.5 mm @ 32.5 per cent cum 124.800 1508.17 188219.70 M-028
9.5 mm to 4.75 mm @ 5 per cent cum 19.200 1684.60 32344.33 M-025
4.75 mm to 75 micron @ 62.5 per cent cum 240.000 1243.53 298446.17 M-023
Cost of water KL 60.000 55.58 3334.53 M-195
4.6 (i) For Sub-Base course
d) Overhead charges @ 8% on (a+b+c) 70283.05
e) Contractor's profit @ 10% on (a+b+c+d) 94882.11
Cost for 300 cum = a+b+c+d+e 1043703.24
Rate per cum = (a+b+c+d+e)/300 3479.01
say 3479.00
Add extra cost of VAT on Materials 3479.00
4.6 (ii) For Base course
d) Overhead charges @ 8% on (a+b+c) 62089.02
e) Contractor's profit @ 10% on (a+b+c+d) 83820.17
Cost for 300 cum = a+b+c+d+e 922021.89
Rate per cum = (a+b+c+d+e)/300 3073.41
say 3073.00
3073.00
Note Quantities of aggregates provided under 'c' above are
uncompacted quantities.
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
4.7 404.3.1 Making 50 mm x 50 mm Furrows
Making 50 mm x 50 mm furrows, 25mm/ 50mm deep, 450 C to
the center line of the road and at one metre interval in the
existing thin bituminous wearing coarse including sweeping
and disposal of excavated material within 1000 metres lead
Unit = sqm
Taking output = 30 m x 7 m = 210 sqm
(i) 25mm deep furrow cutting
a) Labour
Mate day 0.080 329.34 26.35 L-12
Mazdoor day 2.000 152.91 305.81 L-13
b) Machinery
Tractor-trolley hour 0.200 379.91 75.98 P&M-053
c) Overhead charges @ 8% on (a+b) 32.65
d) Contractor's profit @ 10% on (a+b+c) 44.08
Cost for 210 sqm= a+b+c+d 484.87
Rate per sqm =(a+b+c+d)/210 2.31
say 2.30
(ii) 50mm deep furrow cutting
a) Labour
Mate day 0.160 329.34 52.69 L-12
Mazdoor day 4.000 152.91 611.62 L-13
b) Machinery
Tractor-trolley hour 0.400 379.91 151.97 P&M-053
c) Overhead charges @ 8% on (a+b) 65.30
d) Contractor's profit @ 10% on (a+b+c) 88.16
Cost for 210 sqm= a+b+c+d 969.74
Rate per sqm =(a+b+c+d)/210 4.62
say 4.60
4.8 404.3.2 Inverted Choke
Construction of inverted choke by providing, laying, spreading
and compacting screening B type/ coarse sand of specified
grade in uniform layer on a prepared surface with motor grader
and compacting with power roller etc
Unit = cum
Taking output = 600 cum
a) Labour
Mate day 0.920 329.34 302.99 L-12
Mazdoor skilled day 2.000 244.65 489.30 L-15
Mazdoor day 21.000 152.91 3211.03 L-13
b) Machinery
Motor Grader 110 HP hour 6.000 2627.63 15765.78 P&M-032
Vibratory roller 8-10 tonnes @ 60 cum per hour hour 6.000 1671.38 10028.28 P&M-059
Water tanker 6 KL capacity hour 18.000 517.53 9315.50 P&M-060
c) Material
Screening type 'B' or coarse sand cum 720.000 1176.20 846864.00 M-004
Cost of water KL 108.000 55.58 6002.15 M-195
d) Overhead charges @ 8% on (a+b+c) 71358.32
e) Contractor's profit @ 10% on (a+b+c+d) 96333.74
Cost for 600 cum = a+b+c+d+e 1059671.09
Rate per cum = ( a+b+c+d+e)/600 1766.12
say 1766.00
1766.00
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
4.9 404 Water Bound Macadam
Providing, laying, spreading and compacting stone aggregates
of specific sizes to water bound macadam specification
including spreading in uniform thickness, hand packing, rolling
with 3 wheeled steel/ vibratory roller 8-10 tonnes in stages to
proper grade and camber, applying and brooming requisite
type of screening/ binding Materials to fill up the interstices of
coarse aggregate, watering and compacting to the required
density.
A By Manual Means
Unit = cum
Taking output = 360 cum
a) Labour
Mate day 10.080 329.34 3319.71 L-12
Mazdoor skilled day 2.000 244.65 489.30 L-15
Mazdoor day 250.000 152.91 38226.50 L-13
b) Machinery

Vibratory roller 8 - 10 tonne @ 60cum per hour hour 6.000 1671.38 10028.28 P&M-059
or
Smooth 3 wheeled steel roller @ 30cum/hour hour 12.000
Water tanker 6 KL capacity hour 24.000 517.53 12420.67 P&M-060
c) Material ( Refer table 400 - 7, 8 & 9 )
4.9A (i) Grading-I
Aggregate
Grading-I 90 mm to 45 mm@ 1.21cum per 10 sqm for cum 435.600 1411.44 614823.26 M-039
compacted thickness of 100 mm

Stone Screening
Type A 13.2 mm for grading-I @ 0.27 cum per 10 sqm cum 97.200 1587.87 154340.96 M-042

OR
Crushable type such as Moorum or Gravel for grading-I @ cum 108.000 687.37 74236.10 M-007
0.30 cum per 10 sqm

Binding material
Binding Material @ 0.08cum per 10 sqm for grading I cum 28.800 687.37 19796.29 M-007
material
Cost of water KL 144.000 55.58 8002.86 M-195
4.9A (i) (a) Using Scrining Crushable type such as Moorum or Gravel
d) Overhead charges @ 8% on (a+b+c) 60923.73
e) Contractor's profit @ 10% on (a+b+c+d) 82247.04
Cost for 360 cum = a+b+c+d+e 904717.46
Rate per cum = (a+b+c+d+e)/360 2513.10
say 2513.00
2513.00
OR
4.9A (i) (b) Using Scrining Type-A (13.2mm agg.) with binding material
d) Overhead charges @ 8% on (a+b+c) 68915.83
e) Contractor's profit @ 10% on (a+b+c+d) 93036.37
Cost for 360 cum = a+b+c+d+e 1023400.04
Rate per cum = (a+b+c+d+e)/360 2842.78
say 2843.00
2843.00
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
4.9A (ii) Grading-II
Aggregate
Grading-II 63 mm to 45 mm /Grading-III 53 mm to 22.4 cum 435.600 1470.25 640440.90 M-038 / M-036
mm@ 0.91 cum per 10 sqm for compacted thickness of 75
mm

Stone Screening
Type A 13.2 mm for grading-II @ 0.12 cum per 10 sqm cum 57.600 1587.87 91461.31 M-042

OR
Crushable type such as Moorum or Gravel for grading II cum 105.590 687.37 72579.53 M-007
&III @ 0.22 cum per 10 sqm
OR
Type B11.2 mm for grading-III @ 0.20 cum per 10 sqm cum 96.010 1529.06 146805.05 M-041

Binding material
Binding Material @ 0.06cum per 10 sqm for grading II cum 28.800 687.37 19796.29 M-007
material
Cost of water KL 144.000 55.58 8002.86 M-195
4.9A (ii) (a) Using Screening Crushable type such as Moorum or Gravel
d) Overhead charges @ 8% on (a+b+c) 62840.62
e) Contractor's profit @ 10% on (a+b+c+d) 84834.84
Cost for 360 cum = a+b+c+d+e 933183.22
Rate per cum = (a+b+c+d+e)/360 2592.18
say 2592.00
Add extra cost of VAT on Materials 2592.00
OR
4.9A (ii) (b) Using Scrining Type-A (13.2mm agg.) with binding material
d) Overhead charges @ 8% on (a+b+c) 65934.87
e) Contractor's profit @ 10% on (a+b+c+d) 89012.07
Cost for 360 cum = a+b+c+d+e 979132.76
Rate per cum = (a+b+c+d+e)/360 2719.81
say 2720.00
Add extra cost of VAT on Materials 2720.00
4.9A (ii) (c) Using Scrining Type-B (11.2mm agg.) with binding material
d) Overhead charges @ 8% on (a+b+c) 70362.37
e) Contractor's profit @ 10% on (a+b+c+d) 94989.19
Cost for 360 cum = a+b+c+d+e 1044881.13
Rate per cum = (a+b+c+d+e)/360 2902.45
say 2902.00
2902.00
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
4.9A (iii) Grading-III
Aggregate
Grading-III 53 mm to 22.4 mm@ 0.91 cum per 10 sqm for cum 435.600 1529.06 666058.54 M-036
compacted thickness of 75 mm

Stone Screening
Type B 11.2 mm for grading-III @ 0.18 cum per 10 sqm cum 86.400 1529.06 132110.78 M-041

OR
Crushable type such as Moorum or Gravel for grading II cum 105.590 687.37 72579.53 M-007
&III @ 0.22 cum per 10 sqm

Binding material
Binding Material @ 0.06cum per 10 sqm for grading II cum 28.800 687.37 19796.29 M-007
material
Cost of water KL 144.000 55.58 8002.86 M-195
4.9A (iii) (a) Using Scrining Crushable type such as Moorum or Gravel
d) Overhead charges @ 8% on (a+b+c) 64890.03
e) Contractor's profit @ 10% on (a+b+c+d) 87601.54
Cost for 360 cum = a+b+c+d+e 963616.97
Rate per cum = (a+b+c+d+e)/360 2676.71
say 2677.00
Add extra cost of VAT on Materials 2677.00
OR
4.9A (iii) (b) Using Scrining Type-B (11.2mm agg.)
d) Overhead charges @ 8% on (a+b+c) 71236.23
e) Contractor's profit @ 10% on (a+b+c+d) 96168.92
Cost for 360 cum = a+b+c+d+e 1057858.09
Rate per cum = (a+b+c+d+e)/360 2938.49
say 2938.00
2938.00
( Anyone of the aggregate grading, screening and binding
material may be used as per design)
4.9 B By Mechanical Means:
Unit = cum
Taking output = 360 cum
a) Labour
Mate day 0.680 329.34 223.95 L-12
Mazdoor skilled day 2.000 244.65 489.30 L-15
Mazdoor day 15.000 152.91 2293.59 L-13
b) Machinery
Motor grader 110 HP @ 50cum/hr. for spreading hour 7.200 2627.63 18918.94 P&M-032
Vibratory roller 8-10 tonnes @ 60cum/hr. hour 6.000 1671.38 10028.28 P&M-059
or
Smooth 3 wheeled steel roller @ 30cum/hr. hour 12.000
Water tanker 6 KL capacity hour 24.000 517.53 12420.67 P&M-060
c) Material ( Refer table 400 - 7, 8 & 9 )
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
4.9B (i) Grading-I
Aggregate
Grading-I 90 mm to 45 mm@ 1.21cum per 10 sqm for cum 435.600 1411.44 614823.26 M-039
compacted thickness of 100 mm

Stone Screening
Type A 13.2 mm for grading-I @ 0.27 cum per 10 sqm cum 97.200 1587.87 154340.96 M-042

OR
Crushable type such as Moorum or Gravel for grading-I @ cum 108.000 687.37 74236.10 M-007
0.30 cum per 10 sqm

Binding material
Binding Material @ 0.08cum per 10 sqm for grading I cum 28.800 687.37 19796.29 M-007
material
Cost of water KL 144.000 55.58 8002.86 M-195
4.9B (i) (a) Using Scrining Crushable type such as Moorum or Gravel
d) Overhead charges @ 8% on (a+b+c) 59314.96
e) Contractor's profit @ 10% on (a+b+c+d) 80075.19
Cost for 360 cum = a+b+c+d+e 880827.11
Rate per cum = (a+b+c+d+e)/360 2446.74
say 2447.00
2447.00
OR
4.9B (i) (b) Using Scrining Type-A (13.2mm agg.) with binding material
d) Overhead charges @ 8% on (a+b+c) 67307.05
e) Contractor's profit @ 10% on (a+b+c+d) 90864.52
Cost for 360 cum = a+b+c+d+e 999509.68
Rate per cum = (a+b+c+d+e)/360 2776.42
say 2776.00
2776.00
4.9B (ii) Grading-II
Aggregate
Grading-II 63 mm to 45 mm /Grading-III 53 mm to 22.4 cum 435.600 1470.25 640440.90 M-038 / M-036
mm@ 0.91 cum per 10 sqm for compacted thickness of 75
mm

Stone Screening
Type A 13.2 mm for grading-II@ 0.12 cum per 10 sqm cum 57.600 1587.87 91461.31 M-042
OR
Crushable type such as Moorum or Gravel for grading II cum 105.590 687.37 72579.53 M-007
&III @ 0.22 cum per 10 sqm
OR
Type B 11.2 mm for grading-III @ 0.20 cum per 10 sqm cum 96.010 1529.06 146805.05 M-041

Binding material
Binding Material @ 0.06cum per 10 sqm for grading II cum 28.800 687.37 19796.29 M-007
material
Cost of water KL 144.000 55.58 8002.86 M-195
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
4.9B (ii) (a) Using Scrining Crushable type such as Moorum or Gravel
d) Overhead charges @ 8% on (a+b+c) 61231.84
e) Contractor's profit @ 10% on (a+b+c+d) 82662.99
Cost for 360 cum = a+b+c+d+e 909292.86
Rate per cum = (a+b+c+d+e)/360 2525.81
say 2526.00
2526.00
OR
4.9B (ii) (b) Using Scrining Type-A (13.2mm agg.) with binding material
d) Overhead charges @ 8% on (a+b+c) 64326.09
e) Contractor's profit @ 10% on (a+b+c+d) 86840.22
Cost for 360 cum = a+b+c+d+e 955242.41
Rate per cum = (a+b+c+d+e)/360 2653.45
say 2653.00
Add extra cost of VAT on Materials 2653.00
4.9B (ii) (c) Using Scrining Type-B (11.2mm agg.) with binding material
d) Overhead charges @ 8% on (a+b+c) 68753.59
e) Contractor's profit @ 10% on (a+b+c+d) 92817.34
Cost for 360 cum = a+b+c+d+e 1020990.77
Rate per cum = (a+b+c+d+e)/360 2836.09
say 2836.00
Add extra cost of VAT on Materials 2836.00
4.9B (iii) Grading-III
Aggregate
Grading-III 53 mm to 22.4 mm@ 0.91 cum per 10 sqm for cum 435.600 1529.06 666058.54 M-036
compacted thickness of 75 mm

Stone Screening
Type B 11.2 mm for grading-III @ 0.18 cum per 10 sqm cum 86.400 1529.06 132110.78 M-041

OR
Crushable type such as Moorum or Gravel for grading II cum 105.590 687.37 72579.53 M-007
&III @ 0.22 cum per 10 sqm

Binding material
Binding Material @ 0.06cum per 10 sqm for grading II cum 28.800 687.37 19796.29 M-007
material
Cost of water KL 144.000 55.58 8002.86 M-195
4.9B (iii) (a) Using Scrining Crushable type such as Moorum or Gravel
d) Overhead charges @ 8% on (a+b+c) 63281.25
e) Contractor's profit @ 10% on (a+b+c+d) 85429.69
Cost for 360 cum = a+b+c+d+e 939726.61
Rate per cum = (a+b+c+d+e)/360 2610.35
say 2610.00
Add extra cost of VAT on Materials 2610.00
OR
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
4.9B (iii) (b) Using Scrining Type-B (11.2mm agg.) with binding material
d) Overhead charges @ 8% on (a+b+c) 69627.46
e) Contractor's profit @ 10% on (a+b+c+d) 93997.07
Cost for 360 cum = a+b+c+d+e 1033967.73
Rate per cum = (a+b+c+d+e)/360 2872.13
say 2872.00
2872.00
Note As three wheeled smooth rollers are also very commonly used,
the same has been provided as an alternative.
4.10 405 Crushed Cement Concrete Sub-base / Base
Breaking and crushing of material obtained by breaking
damaged cement concrete slabs to size range not exceeding
75 mm as specified in table 400.7 transporting the aggregates
obtained from breaking of cement concrete slabs at a lead of L
km., laying and compacting the same as sub base/ base
course, constructed as WBM to clause 404 except the use of
screening or binding Material.
Unit = cum
Taking output =360 cum
a) Labour
Mate day 4.160 329.34 1370.04 L-12
Mazdoor skilled day 2.000 244.65 489.30 L-15
Mazdoor for crushing broken cement concrete day 102.000 152.91 15596.41 L-13
pavement/slabs into aggregate
b) Machinery
Motor Grader,110 HP @ 50 cum/hr. hour 6.000 2627.63 15765.78 P&M-032
Vibratory roller 8 - 10 tonne@ 60 cum per hour hour 6.000 1671.38 10028.28 P&M-059
or
Smooth 3 wheeled steel roller @ 30cum/hr. hour 12.000
Front end loader 1 cum bucket capacity hour 6.000 803.34 4820.07 P&M-017
Tipper 10 tonne capacity tonne.km 720 x L 70.57 152435.52 Lead =3 km &
P&M-047
Add 10 per cent of cost of carriage to cover cost of 15243.55
loading and unloading
Water tanker 6 KL capacity with 5 km lead @ 1 trip per hour 12.000 517.53 6210.34 P&M-060
hour
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
c) Material
Material available from dismantled concrete slab after crushing
/ breaking and only carriage is required to be provided

Cost of water KL 72.000 55.58 4001.43 M-195


d) Overhead charges @ 8% on (a+b+c) 18076.86
e) Contractor's profit @ 10% on (a+b+c+d) 24403.76
Cost for 360 cum = a+b+c+d+e 268441.34
Rate per cum = (a+b+c+d+e)/360 745.67
say 746.00
With Vibratory Roller 746.00
With Smooth 3 wheeled Steel Roller 739.00
Note 1. It is assumed that dismantling of concrete slab/pavement
has been considered separately. Hence same is not added in
this analysis. Only labour for crushing the dismantled slab into
aggregate has been added. Carriage from stock pile to work
site has been provided with a lead of L km.
2. In case of breaking of slabs is done locally without
involvement of transportation, the provision of tipper, front end
loader and loading/unloading charges may be deleted.
3. As three wheeled smooth steel rollers are commonly in use,
the same has been provided as an alternative.
4.11 405.2 Penetration Coat Over Top Layer of Crushed Cement
Concrete Base
Spraying of bitumen over cleaned dry surface of crushed
cement concrete base at the rate of 25 kg per 10 sqm by a
bitumen pressure distributor, spreading of key aggregates at
the rate of 0.13 cum per 10 sqm by a mechanical gritter and
rolling the surface as per clause 506.3.8
Unit = sqm
Taking output = 7500 sqm
a) Labour
Mate day 0.560 329.34 184.43 L-12
Mazdoor skilled day 2.000 244.65 489.30 L-15
Mazdoor day 12.000 152.91 1834.87 L-13
b) Machinery
Mechanical broom hydraulic @ 1250 sqm per hour hour 6.000 396.38 2378.28 P&M-031
Hydraulic self propelled chips spreader hour 6.000 2799.36 16796.14 P&M-025
Front end loader 1 cum bucket capacity hour 6.000 803.34 4820.07 P&M-017
Tipper 10 tonne capacity hour 6.000 491.65 2949.91 P&M-048
Vibratory roller 8 -10 tonnes @ 30 cum per hour hour 6.00x0.65* 1671.38 6518.38 P&M-059
Bitumen pressure distributor @ 1750 sqm per hour hour 4.280 1122.09 4802.57 P&M-004
c) Material
Crushed stone aggregate 11.2 mm size cum 97.500 1529.06 149083.35 M-051
Bitumen (60-70 grade) tonne 0.250 40000.00 10000.00 M-073
d) Overhead charges @ 8% on (a+b+c) 15988.58
e) Contractor's profit @ 10% on (a+b+c+d) 21584.59
Cost for 7500 sqm = a+b+c+d+e 237430.46
Rate per sqm = (a+b+c+d+e)/7500 31.66
say 31.70
12.30
Note Though vibratory roller is required only for 3 hours as per
norms, the same is required to be available at site for 6 hours
to match with other machines. The usage rates of vibratory
roller may be multiplied with a factor of 0.65.
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
4.12 406 Wet Mix Macadam
Providing, laying, spreading and compacting graded stone
aggregate to wet mix macadam specification including
premixing the Material with water at OMC in mechanical mix
plant carriage of mixed Material by tipper to site, laying in
uniform layers with paver in sub- base / base course on well
prepared surface and compacting with vibratory roller to
achieve the desired density.
Unit = cum
Taking output = 225 cum (495 tonnes)
a) Labour
Mate day 0.480 329.34 158.08 L-12
Mazdoor skilled day 2.000 244.65 489.30 L-15
Mazdoor day 10.000 152.91 1529.06 L-13
b) Machinery
Wet mix plant of 75 tonne hourly capacity hour 6.600 1591.40 10503.23 P&M-092
Electric generator 125 KVA hour 6.000 979.77 5878.65 P&M-018
Front end loader 1 cum capacity hour 6.000 803.34 4820.07 P&M-017
Paver finisher hour 6.000 1003.30 6019.79 P&M-035
Vibratory roller 8 - 10 tonne hour 6x0.65 1671.38 6518.38 P&M-059
or
Smooth 3 wheeled steel roller @ 8-10 tonnes. hour 12.000
Water tanker 6 KL capacity hour 3.000 517.53 1552.58 P&M-060
Tipper tonne.km 495 x L 4.12 6113.30 Lead =3 km &
P&M-047
Add 10 per cent of cost of carriage to cover cost of 611.33
loading and unloading
c) Material ( Table 400-11)
45 mm to 22.4 mm@ 30 per cent cum 89.100 1587.87 141479.22 M-034
22.4 mm to 2.36 mm @ 40 per cent cum 118.800 1529.06 181652.33 M-031
2.36 mm to 75 micron@ 30 per cent cum 89.100 861.26 76738.33 M-022
Cost of water KL 18.000 55.58 1000.36 M-195
d) Overhead charges @ 8% on (a+b+c) 35605.12
e) Contractor's profit @ 10% on (a+b+c+d) 48066.91
Cost for 225 cum = a+b+c+d+e 528736.04
Rate per cum = (a+b+c+d+e)/225 2349.94
say 2350.00
2350.00
Note 1. Though vibratory roller is required only for 3 hours as per
norms, the same is required to be available at site for 6 hours
to match with other machines. The usage rates of vibratory
roller may be multiplied with a factor of 0.65
2. As three wheeled smooth steel rollers are commonly in use,
the same has been provided as an alternative which can be
used if the thickness of individual layer does not exceed 100
mm.
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
4.13 407 Construction of Median and Island with Soil Taken from
Roadway Cutting
Construction of Median and Island above road level with
approved material deposited at site from roadway cutting and
excavation for drain and foundation of other structures, spread,
graded and compacted as per clause 407
Unit = cum
Taking output =21 cum
a) Labour
Mate day 0.240 329.34 79.04 L-12
Mazdoor day 6.000 152.91 917.44 L-13
b) Machinery
Water tanker 6 KL with 5 km lead and 1 trip per hour hour 1.000 517.53 517.53 P&M-060
Plate compactor @ 3.5 cum per hour hour 6.000 256.41 1538.47 P&M-086
c) Material
Cost of water KL 6.000 55.58 333.45 M-195
d) Overhead charges @ 8% on (a+b+c) 270.87
e) Contractor's profit @ 10% on (a+b+c+d) 365.68
Cost for 21 cum = a+b+c+d+e 4022.48
Rate per cum = (a+b+c+d+e)/21 191.55
say 192.00
192.00
Note This analysis provides for median and island with earthen top.
In case the surface is required to be turfed or planted with
shrubs, the same is required to be provided separately as per
analysis given in the chapter on horticulture. In case granular
fill is required to be paved, quantities of paving are required to
be calculated as per approved design and paid separately.
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
4.14 407 Construction of Median and Island with Soil Taken from
Borrow Areas
Construction of median and Island above road level with
approved material brought from borrow pits, spread, sloped
and compacted as per clause 407
Unit = cum
Taking output = 21 cum
a) Labour
Mate day 0.160 329.34 52.69 L-12
Mazdoor day 4.000 152.91 611.62 L-13
b) Machinery
Water tanker with 5 km lead hour 1.000 517.53 517.53 P&M-060
Plate Compactor @ 3.5 cum per hour hour 6.000 256.41 1538.47 P&M-086
Hydraulic Excavator1.0 cum bucket capacity @60 cum per hour 0.500 1621.98 810.99 P&M-026
hour
Tipper 10 tonne capacity tonne.km 52.5 x L 4.12 648.38 Lead =3 km &
P&M-047
Add 10 per cent of cost of transportation to cover cost of 64.84
loading and unloading
c) Material
Cost of water KL 6.000 55.58 333.45 M-195
d) Overhead charges @ 8% on (a+b+c) 366.24
e) Contractor's profit @ 10% on (a+b+c+d) 494.42
Cost for 21 cum = a+b+c+d+e 5438.64
Rate per cum = (a+b+c+d+e)/ 21 258.98
say 259.00
259.00
Note This analysis provides for median and island with earthen top.
In case the surface is required to be turfed or planted with
shrubs, the same is required to be provided separately as per
analysis given in the chapter on horticulture. In case surface
finish is of hard type, the same may be provided separately as
per approved design.
4.15 Construction of Shoulders
A. Earthen Shoulders
The rate as applicable for sub-grade construction may be
adopted.
B. Hard Shoulders
Rate as applicable for sub-base and or base may be adopted
as per approved design.
C. Paved shoulders
The rate may be adopted as applicable for different layers of
pavement depending upon approved design of paved
shoulders.
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
4.16 409 Footpaths and Separators
Construction of footpath/separator by providing a 150 mm
compacted granular sub base as per clause 401 and 25 mm
thick cement concrete grade M15, over laid with pre-cast
concrete tiles in cement mortar 1:3 including provision of all
drainage arrangements but excluding kerb channel..
Unit = sqm
Taking output = 300 sqm
a) Labour
Mate day 1.360 329.34 447.90 L-12
Mason day 4.000 352.86 1411.44 L-11
Mazdoor day 30.000 152.91 4587.18 L-13
b) Machinery
Vibratory road roller 8 -10 tonnes @60 cum per hour hour 0.750 1671.38 1253.54 P&M-059
Water tanker 6 KL capacity @ 1 trip per hour hour 2.000 517.53 1035.06 P&M-060
Concrete mixer 0.4/0.28 cum per hour hour 6.000 237.59 1425.55 P&M-009
c) Material
i) For Granular sub base material
53 mm to 26.5 mm @ 35 per cent cum 20.790 1402.31 29154.08 M-029
26.5 mm to 4.75 mm @ 45 per cent cum 26.730 1661.08 44400.58 M-026
2.36 mm below @ 20 per cent cum 11.880 861.26 10231.78 M-022
ii) For cement concrete grade M157.5 cum
Aggregate 12 mm crushed @ 0.9 cum of concrete cum 6.750 1587.87 10718.12 M-052
Sand @ 0.45 cum/cum of concrete cum 3.380 1176.20 3975.56 M-005
Cement tonne 1.880 8939.12 16805.55 M-086
iii) For cement plaster 1:3
Sand cum 3.840 1176.20 4516.61 M-005
Cement tonne 1.830 8939.12 16358.59 M-086
iv) Pre-cast cement concrete tiles
Tiles size 300 x 300 mm and 25 mm thick each 3300.000 75.34 248607.51 M-190
v) RCC pipes
Pipes 200 mm dia,2.5 m long for drainage metre 22.500 986.77 22202.39 M-143
vi) Cost of water KL 12.000 55.58 666.91 M-195
d) Overhead charges @ 8% on (a+b+c) 33423.87
e) Contractor's profit @ 10% on (a+b+c+d) 45122.22
Cost for 300 sqm = a+b+c+d+e 496344.42
Rate per sqm = (a+b+c+d+e)/300 1654.48
say 1654.00
1654.00
CHAPTER - 4
SUB-BASES, BASES ( NON- BITUMINOUS) AND SHOULDERS
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
4.12 406 RAP
Providing, laying, spreading and compacting graded stone
aggregate to wet mix macadam specification including
premixing the Material with water at OMC in mechanical mix
plant carriage of mixed Material by tipper to site, laying in
uniform layers with paver in sub- base / base course on well
prepared surface and compacting with vibratory roller to
achieve the desired density.
Unit = cum
Taking output = 225 cum (495 tonnes)
a) Labour
Mate day 0.480 329.34 158.08 L-12
Mazdoor skilled day 2.000 244.65 489.30 L-15
Mazdoor day 10.000 152.91 1529.06 L-13
b) Machinery
Wet mix plant of 75 tonne hourly capacity hour 6.600 1591.40 10503.23 P&M-092
Electric generator 125 KVA hour 6.000 979.77 5878.65 P&M-018
Front end loader 1 cum capacity hour 6.000 803.34 4820.07 P&M-017
Paver finisher hour 6.000 1003.30 6019.79 P&M-035
Vibratory roller 8 - 10 tonne hour 6x0.65 1671.38 6518.38 P&M-059
or
Smooth 3 wheeled steel roller @ 8-10 tonnes. hour 12.000
Water tanker 6 KL capacity hour 3.000 517.53 1552.58 P&M-060
Tipper tonne.km 495 x L 70.57 104799.42 Lead =3 km &
P&M-047
Add 10 per cent of cost of carriage to cover cost of 10479.94
loading and unloading
c) Material ( Table 400-11)
Use of Dismantling pavement(@60%) cum 1213.800 0.00
45 mm to 22.4 mm@ 30 per cent cum 35.640 1587.87 56591.69 M-034
22.4 mm to 2.36 mm @ 40 per cent cum 47.520 1529.06 72660.93 M-031
2.36 mm to 75 micron@ 30 per cent cum 861.26 0.00 M-022
Cost of water KL 18.000 55.58 1000.36 M-195
Cement @ 1 0 per cent of weight of aggregates. tonne 8.316 8939.12 74337.72
d) Overhead charges @ 8% on (a+b+c) 22640.12
e) Contractor's profit @ 10% on (a+b+c+d) 37997.93
Cost for 225 cum = a+b+c+d+e 417977.26
Rate per cum = (a+b+c+d+e)/225 1857.68
say 1858.00
1858.00
CHAPTER - 4
SUB-BASES, BASES ( NON- BITUMINOUS) AND SHOULDERS
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
4.1 401 Granular Sub-Base with Close Graded Material (Table:- 400-
1)
A Plant Mix Method
Construction of granular sub-base by providing close graded
Material, mixing in a mechanical mix plant at OMC, carriage of
mixed Material to work site, spreading in uniform layers with
motor grader on prepared surface and compacting with
vibratory power roller to achieve the desired density, complete
as per clause 401
Unit = cum
Taking output = 225 cum (450 tonne)
a) Labour
Mate day 0.400 329.34 131.73 L-12
Mazdoor skilled day 2.000 244.65 489.30 L-15
Mazdoor day 8.000 152.91 1223.25 L-13
b) Machinery
Wet mix plant @ 75 tonne capacity per hour hour 6.000 1591.40 9548.39 P&M-092
Electric generator 125 KVA hour 6.000 979.77 5878.65 P&M-018
Water tanker 6 KL capacity 5 km lead with one tripper hour hour 4.500 517.53 2328.88 P&M-060

Front end loader 1 cum bucket capacity hour 6.000 803.34 4820.07 P&M-017
Tipper 10 tonne tonne.km 450 x L 70.57 95272.20 Lead =3 km &
P&M-047
Add 10 per cent of cost of carriage to cover loading and 9527.22
unloading
Motor Grader 110 HP hour 6.000 2627.63 15765.78 P&M-032
Vibratory roller 8-10 t hour 6.000 1671.38 10028.28 P&M-059
c) Material
Close graded Granular sub-base Material as per table 400-1

For Grading-I Material


53 mm to 9.5 mm @ 50 per cent cum 1449.36 0.00 M-013
9.5 mm to 2.36 mm @ 20 per cent cum 1681.07 0.00 M-017
2.36 mm below @ 30 per cent cum 896.55 0.00 M-020
Cost of water KL 55.58 0.00 M-195
OR
For Grading-II Material
26.5 mm to 9.5 mm @ 35 per cent cum 1681.07 0.00 M-015
9.5 mm to 2.36 mm @ 25 per cent cum 1681.07 0.00 M-017
2.36 mm below @ 40 per cent cum 896.55 0.00 M-020
Cost of water KL 55.58 0.00 M-195
OR
For Grading-III Material
9.5 mm to 4.75 mm @ 35 per cent cum 1681.07 0.00 M-016
4.75 mm to 2.36 mm @ 12.5 per cent cum 1681.07 0.00 M-018
2.36 mm below @ 52.5 per cent cum 896.55 0.00 M-020
Cost of water KL 55.58 0.00 M-195
4.1A (i) Rate per cum for grading-I Material
d) Overhead charges @ 8% on (a+b+c) 12401.10
e) Contractor's profit @ 10% on (a+b+c+d) 16741.49
Cost for 225 cum = a+b+c+d+e 184156.34
Rate per cum = (a+b+c+d+e)/225 818.47
say 818.00
818.00
CHAPTER - 5
BASES AND SURFACE COURSES (BITUMINOUS)
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
5.1 502 Prime Coat
Providing and applying primer coat with bitumen
emulsion on prepared surface of granular Base including
clearing of road surface and spraying primer at the rate of
0.60 kg/sqm using mechanical means.
Unit = sqm
Taking output = 3500 sqm
a) Labour
Mate day 0.080 329.34 26.35 L-12
Mazdoor day 2.000 152.91 305.81 L-13
b) Machinery
Mechanical broom @ 1250 sqm per hour hour 2.800 396.38 1109.86 P&M-031
Air compressor 250 cfm hour 2.800 334.04 935.31 P&M-001
Bitumen pressure distributor @ 1750 sqm per hour hour 2.000 1122.09 2244.19 P&M-004
Water tanker 6 KL capacity @ 1 tripper hour hour 1.000 517.53 517.53 P&M-060
c) Material
Bitumen emulsion @ 0.6 kg per sqm tonne 2.100 33000.00 69300.00 M-076
Cost of water KL 6.000 55.58 333.45 M-195
d) Overhead charges @ 8% on (a+b+c) 5981.80
e) Contractor's profit @ 10% on (a+b+c+d) 8075.43
Cost for 3500 sqm = a+b+c+d+e 88829.74
Rate per sqm = (a+b+c+d+e)/3500 25.38
say 25.00
25.00
Note Bitumen primer has been provided @ 0.60 kg per sqm as per
clause 502.8. Payment shall be made with adjustment, plus or
minus, for the variation between this quantity and the actual
quantity approved by the Engineer after the preliminary trials
referred to in clause No. 502.4.3.
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
5.2 503 Tack Coat
Providing and applying tack coat with bitumen emulsion using
emulsion pressure distributor at the rate of 0.20 kg per sqm on
the prepared bituminous/granular surface cleaned with
mechanical broom. (on biuminous layer)

Unit = sqm
Taking output = 3500 sqm
a) Labour
Mate day 0.080 329.34 26.35 L-12
Mazdoor day 2.000 152.91 305.81 L-13
b) Machinery
Mechanical broom @ 1250 sqm per hour hour 2.800 396.38 1109.86 P&M-031
Air compressor 250 cfm hour 2.800 334.04 935.31 P&M-001
Emulsion pressure distributor @ 1750 sqm per hour hour 2.000 843.34 1686.67 P&M-016
c) Material
Bitumen emulsion @ 0.2 kg per sqm tonne 0.700 33000.00 23100.00 M-076
d) Overhead charges @ 8% on (a+b+c) 2173.12
e) Contractor's profit @ 10% on (a+b+c+d) 2933.71
Cost for 3500 sqm = a+b+c+d+e 32270.84
Rate per sqm = (a+b+c+d+e)/3500 9.22
say 9.00
9.00
Note 1. Bitumen emulsion has been provided @ 0.20 kg per sqm as
per clause 503.8. Payment shall be made with adjustment,
plus or minus, for the variation between this quantity and
actual quantity approved by the Engineer after preliminary
trials referred to in clause No. 503.4.3
2. An output of 3500 sqm has been considered in case of
prime coat and tack coat which can be covered by bituminous
courses on the same day.
5.3 504 Bituminous Macadam
Providing and laying bituminous macadam with 100-120 TPH
hot mix plant producing an average output of 75 tonnes per
hour using crushed aggregates of specified grading premixed
with bituminous binder, transported to site, laid over a
previously prepared surface with paver finisher to the required
grade, level and alignment and rolled as per clauses 501.6
and 501.7 to achieve the desired compaction.
Unit = cum
Taking output = 205 cum (450 tonnes)
a) Labour
Mate day 0.840 329.34 276.64 L-12
Mazdoor working with HMP, mechanical broom, paver, day 14.000 152.91 2140.68 L-13
roller, asphalt cutter and assistance for setting out lines,
levels and layout of construction
Skilled mazdoor for checking line & levels day 5.000 244.65 1223.25 L-15
b) Machinery
Batch mix HMP 100-120 TPH @ 75 tonne per hour actual hour 6.000 19495.52 116973.09 P&M-022
output
Mechanical broom hydraulic @ 1250 sqm per hour hour 2.200 396.38 P&M-031
Air compressor 250 cfm hour 2.200 334.04 734.89 P&M-001
Paver finisher hydrostatic with sensor control @ 75 cum hour 6.000 2753.48 16520.91 P&M-034
per hour
Generator 250 KVA hour 6.000 1764.30 10585.80 P&M-081
Front end loader 1 cum bucket capacity hour 6.000 803.34 4820.07 P&M-017
Tipper 10 tonne capacity tonne.km 450 x L 70.57 95272.20 Lead =3 km
& P&M-047
Add 10 per cent of cost of carriage to cover cost of loading 9527.22
and unloading
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Smooth wheeled roller 8-10 tonnes for initial break down hour 6.00x0.65* 676.32 2637.63 P&M-044
rolling.
Vibratory roller 8 tonnes for intermediate rolling. hour 6.00x0.65* 1671.38 6518.38 P&M-059
Finish rolling with 6-8 tonnes smooth wheeled tandem hour 6.00x0.65* 1222.07 4766.08 P&M-045
roller.
c) Material
i) Bitumen@ 3.3 per cent of mix tonne 14.850 40000.00 594000.00 M-073
weight of mix = 205 x 2.2 = 450 tonne
ii) Aggregate
Total weight of mix = 450 tonnes
Weight of bitumen = 14.85 tonnes
Weight of aggregate = 450 -14.85 = 435.15 tonnes
Taking density of aggregate = 1.5 ton/cum
Volume of aggregate = 290.1 cum
*Grading I ( 40 mm nominal size )
37.5 - 25 mm 15 per cent cum 43.510 1529.06 66529.40 M-049
25 - 10 mm 45 per cent cum 130.550 1411.44 184263.49 M-046
10 - 5 mm 25 per cent cum 72.530 1529.06 110902.72 M-040
5 mm and below15 per cent cum 43.510 1411.44 61411.75 M-030
or
GradingII(19 mm nominal size)
25 - 10 mm 40 per cent cum 116.040 1411.44 163783.50 M-046
10 - 5 mm 40 per cent cum 116.040 1529.06 177432.12 M-040
5 mm and below 20 per cent cum 58.020 1411.44 81891.75 M-030
* Any one of the alternative may be adopted as per approved
design
(i) for Grading I ( 40 mm nominal size )
d) Overhead charges @ 8% on (a+b+c) 103128.34
e) Contractor's profit @ 10% on (a+b+c+d) 139223.25
Cost for 205 cum = a+b+c+d+e 1531455.80
Rate per cum = (a+b+c+d+e)/205 (For Grading I) 7470.52
say 7471.00
7471.00
(ii) for GradingII(19 mm nominal size)
d) Overhead charges @ 8% on (a+b+c) 103128.34
e) Contractor's profit @ 10% on (a+b+c+d) 139223.25
Cost for 205 cum = a+b+c+d+e 1531455.80
Rate per cum = (a+b+c+d+e)/205 (For Grading-II) 7470.52
say 7471.00
7471.00
Note *1. Although the rollers are required only for 3 hours as per
norms of output, but the same have to be available at site for
six hours as the hot mix plant and paver will take six hours for
mixing and paving the output of 450 tonnes considered in this
analysis. To cater for the idle period of these rollers, their
usage rates have been multiplied by a factor of 0.65.
2.Quantity of Bitumen has been taken for analysis purpose.
The actual quantity will depend upon job mix formula.
3. Labour for traffic control, watch and ward and other
miscellaneous duties at site including sundries have been
included in administrative overheads of the contractor.
4. In case BM is laid over freshly laid tack coat, provision of
Mechanical broom and 2 mazdoors for the same shall be
deleted as the same has been included in the cost of tack
coat.
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
5.4 505 Bituminous Penetration Macadam
Construction of penetration macadam over prepared Base by
providing a layer of compacted crushed coarse aggregate
using chips spreader with alternate applications of bituminous
binder and key aggregates and rolling with a smooth wheeled
steel roller 8-10 tonne capacity to achieve the desired degree
of compaction
A 50 mm thick
Unit = sqm
Taking output = 4500 sqm (225 cum)
a) Labour
Mate day 0.320 329.34 105.39 L-12
Mazdoor including for brooming of key aggregates day 6.000 152.91 917.44 L-13
Mazdoor skilled day 2.000 244.65 489.30 L-15
b) Machinery
Hydraulic self propelled chip spreader both for aggregates hour 6.000 2799.36 16796.14 P&M-025
and key aggregates@ 1500 sqm per hour for 4500 x 2
sqm = 9000 sqm
Bitumen pressure distributor for @ 1750 sqm per hour hour 2.570 1122.09 2883.78 P&M-004
Tipper 5.5 cum capacity for carriage of aggregates from hour 10.000 491.65 4916.52 P&M-048
stockpile to chip spreader
Vibratory roller 8 tonnes hour 6.000 1671.38 10028.28 P&M-059
Front end loader 1 cum bucket capacity hour 6.000 803.34 4820.07 P&M-017
c) Material
Bitumen@ 5 kg per sqm tonne 22.500 40000.00 900000.00 M-073
Crushed stone coarse aggregate passing 45 mm and cum 270.000 1599.63 431900.64 M-033
retained on 2.8 mm sieve @ 0.06 cum per sqm
Key aggregates passing 22.4 mm and retained on 2.8 cum 67.500 1529.06 103211.55 M-031
mm sieve @ 0.015 cum per sqm
d) Overhead charges @ 8% on (a+b+c) 118085.53
e) Contractor's profit @ 10% on (a+b+c+d) 159415.46
Cost for 4500 sqm = a+b+c+d+e 1753570.09
Rate per sqm = (a+b+c+d+e)/4500 389.68
say 390.00
390.00
Note 2 tippers will be needed to match the capacity of chip spreader
and front end loader.
5.4 B 75 mm thick
Unit = sqm
Taking output = 4500 sqm (337.5 cum compacted).
a) Labour
Mate day 0.400 329.34 131.73 L-12
Mazdoor including for brooming of key aggregates day 8.000 152.91 1223.25 L-13
Mazdoor skilled day 2.000 244.65 489.30 L-15
b) Machinery
Hydraulic self propelled chip spreader both for aggregates hour 6.000 2799.36 16796.14 P&M-025
and key aggregates@ 1500 sqm per hour for 4500 x 2
sqm
Bitumen pressure distributor for@ 1750 sqm per hour hour 2.570 1122.09 2883.78 P&M-004
Tipper 5.5 cum capacity for carriage of aggregates from hour 10.000 491.65 4916.52 P&M-048
stockpile to chip spreader
Vibratory roller 8 tonnes hour 6.000 1671.38 10028.28 P&M-059
Front end loader 1 cum bucket capacity hour 6.000 803.34 4820.07 P&M-017
c) Material
Bitumen@ 6.8 kg per sqm tonne 30.600 40000.00 1224000.00 M-073
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Crushed stone coarse aggregate (loose passing 63 mm cum 405.000 1529.06 619269.30 M-037
and retained on 2.8 mm sieve @ 0.09 cum per sqm
Key aggregates passing 26.5 mm and retained on 2.8 cum 81.000 1661.08 134547.21 M-026
mm sieve @ 0.018 cum per sqm
d) Overhead charges @ 8% on (a+b+c) 161528.45
e) Contractor's profit @ 10% on (a+b+c+d) 218063.40
Cost for 4500 sqm = a+b+c+d+e 2398697.43
Rate per sqm = (a+b+c+d+e)/4500 533.04
say 533.00
533.00
Note 2 tippers and 2 rollers will be needed to match the capacity of
chip spreader and front end loader.
5.5 506 Built-up-Spray Grout
Providing, laying and rolling of built-up-spray grout layer over
prepared base consisting of a two layer composite
construction of compacted crushed coarse aggregates using
motor grader for aggregates. key stone chips spreader may be
used with application of bituminous binder after each layer,
and with key aggregates placed on top of the second layer to
serve as a Base conforming to the line, grades and cross-
section specified, the compacted layer thickness being 75 mm

Unit = sqm
Taking output = 3000 sqm (225 cum)
a) Labour
Mate day 0.400 329.34 131.73 L-12
Mazdoor including for brooming of key aggregates day 8.000 152.91 1223.25 L-13
Mazdoor skilled day 2.000 244.65 489.30 L-15
b) Machinery
Hydraulic self propelled chip spreader both for aggregates hour 6.000 2799.36 16796.14 P&M-025
and key aggregates@ 1500 sqm per hour for 3000 x 3
sqm
Bitumen pressure distributor for 3000 x 2 sqm @ 1750 hour 3.430 1122.09 3848.79 P&M-004
sqm per hour
Tipper 5.5 cum capacity hour 10.000 491.65 4916.52 P&M-048
Vibratory roller 8 tonnes hour 6.000 1671.38 10028.28 P&M-059
Front end loader 1 cum bucket capacity hour 6.000 803.34 4820.07 P&M-017
c) Material
Bitumen30 kg per 10 sqm @ 15 kg per 10 sqm for each tonne 9.000 40000.00 360000.00 M-073
layer
Crushed stone coarse aggregate passing 53 mm and cum 300.000 1599.63 479889.60 M-035
retained on 2.8 mm sieve @ 0.5 cum per 10 sqm for each
layer
Key aggregates passing 22.4 mm and retained on 2.8 cum 39.000 1529.06 59633.34 M-031
mm sieve @ 0.13 cum per 10 sqm
d) Overhead charges @ 8% on (a+b+c) 75342.16
e) Contractor's profit @ 10% on (a+b+c+d) 101711.92
Cost for 3000 sqm = a+b+c+d+e 1118831.08
Rate per sqm = (a+b+c+d+e)/3000 372.94
say 373.00
373.00
Note 2 tippers will be needed to match the capacity of hydraulic
chip spreader and front end loader.
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
5.6 507 Dense Graded Bituminous Macadam
Providing and laying dense graded bituminous macadam with
100-120 TPH batch type HMP producing an average output of
75 tonnes per hour using crushed aggregates of specified
grading, premixed with bituminous binder @ 4.0 to 4.5 per
cent by weight of total mix and filler, transporting the hot mix
to work site, laying with a hydrostatic paver finisher with
sensor control to the required grade, level and alignment,
rolling with smooth wheeled, vibratory and tandem rollers to
achieve the desired compaction as per MoRTH specification
clause No. 507 complete in all respects.
Unit = cum
Taking output = 195 cum (450 tonnes)
a) Labour
Mate day 0.840 329.34 276.64 L-12
Mazdoor working with HMP, mechanical broom, paver, day 14.000 152.91 2140.68 L-13
roller, asphalt cutter and assistance for setting out lines,
levels and layout of construction
Skilled mazdoor for checking line & levels day 5.000 244.65 1223.25 L-15
b) Machinery
Batch mix HMP @ 75 tonne per hour hour 6.000 19495.52 116973.09 P&M-022
Paver finisher hydrostatic with sensor control @ 75 cum hour 6.000 2753.48 16520.91 P&M-034
per hour
Generator 250 KVA hour 6.000 1764.30 10585.80 P&M-081
Front end loader 1 cum bucket capacity hour 6.000 803.34 4820.07 P&M-017
Tipper 10 tonne capacity tonne.km 450 x L 4.12 5557.55 Lead =3 km
& P&M-047
Add 10 per cent of cost of carriage to cover cost of loading 555.75
and unloading
smooth wheeled roller 8-10 tonnes for initial break down hour 6.00x0.65* 676.32 2637.63 P&M-044
rolling.
Vibratory roller 8 tonnes for intermediate rolling. hour 6.00x0.65* 1671.38 6518.38 P&M-059
Finish rolling with 6-8 tonnes smooth wheeled tandem hour 6.00x0.65* 1222.07 4766.08 P&M-045
roller.
c) Materials
Bitumen @ 4.5 per cent of weight of mix tonne 20.250 40000.00 810000.00 M-077
Aggregate
Total weight of mix = 450 tonnes
Weight of bitumen = 19.13 tonnes
Weight of aggregate = 450 -19.13 = 430.87 tonnes
Taking density of aggregate = 1.5 ton/cum
Volume of aggregate = 287.25 cum
Grading - II 19 mm (Nominal Size)
25 - 10 mm 30 per cent cum 86.160 1411.44 121609.67 M-046
10 - 5 mm 28 per cent cum 80.430 1529.06 122982.30 M-040
5 mm and below 40 per cent cum 114.900 1411.44 162174.46 M-030
Filler @ 2 per cent of weight of aggregates. tonne 8.620 9571.33 82504.84 M-194
* Any one of the alternative may be adopted as per approved
design
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
(ii) For GradingII (19 mm nominal size)
d) Overhead charges @ 8% on (a+b+c) 117747.77
e) Contractor's profit @ 10% on (a+b+c+d) 158959.49
Cost for 195 cum = a+b+c+d+e 1748554.35
Rate per cum = (a+b+c+d+e)/195 (For Grading-II) 8966.95
say 8967.00
8967.00
Note *1. Although the roller are required only for 3 hours as per
norms of output, but the same have to be available at site for
six hours as the hot mix plant and paver will take six hours for
mixing and paving the output of 450 tonnes considered in this
analysis. To cater for the idle period of these rollers, their
usage rates have been multiplied by a factor of 0.65.

2.Quantity of Bitumen has been taken for analysis purpose.


The actual quantity will depend upon job mix formula.
3. Labour for traffic control, watch and ward and other
miscellaneous duties at site including sundries have been
included in administrative overheads of the contractor.
4. In case DBM is laid over freshly laid tack coat, provision of
mechanical broom and 2 mazdoors shall be deleted as the
same has been included in the cost of tack coat.
5. The individual density for each size of aggregates to be
used for construction I.e. 37.5-25 mm, 25-10 mm etc. should
be found in the laboratory and accordingly the quantities
should be ammended for use in field. The average density of
1.5 tonne/cum is only a reference density in this Data Book.
6. The individual percentage of aggregates should be
calculated from the total weight of dry aggregates i.e..
excluding the weight of bitumen. The weight of filler will also
be 2 per cent by weight of dry aggregates.
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
5.8 509 Bituminous Concrete
Providing and laying bituminous concrete with 100-120 TPH
batch type hot mix plant producing an average output of 75
tonnes per hour using crushed aggregates of specified
grading, premixed with bituminous binder @ 5.4 to 5.6 per
cent of mix and filler, transporting the hot mix to work site,
laying with a hydrostatic paver finisher with sensor control to
the required grade, level and alignment, rolling with smooth
wheeled, vibratory and tandem rollers to achieve the desired
compaction as per MORTH specification clause No. 509
complete in all respects

Unit = cum
Taking output = 191 cum (450 tonnes)
a) Labour
Mate day 0.840 329.34 276.64 L-12
Mazdoor working with HMP, mechanical broom, paver, day 14.000 152.91 2140.68 L-13
roller, asphalt cutter and assistance for setting out lines,
levels and layout of construction
Skilled mazdoor for checking line & levels day 5.000 244.65 1223.25 L-15
b) Machinery
Batch mix HMP @ 75 tonne per hour hour 6.000 19495.52 116973.09 P&M-022
Paver finisher hydrostatic with sensor control @ 75 cum hour 6.000 2753.48 16520.91 P&M-034
per hour
Generator 250 KVA hour 6.000 1764.30 10585.80 P&M-081
Front end loader 1 cum bucket capacity hour 6.000 803.34 4820.07 P&M-017
Tipper 10 tonne capacity tonne.km 450 x L 4.12 5557.55 Lead =3 km
& P&M-047
Add 10 per cent of cost of carriage to cover cost of loading 555.75
and unloading
Smooth wheeled roller 8-10 tonnes for initial break down hour 6.00x0.65* 676.32 2637.63 P&M-044
rolling.
Vibratory roller 8 tonnes for intermediate rolling. hour 6.00x0.65* 1671.38 6518.38 P&M-059
Finish rolling with 6-8 tonnes smooth wheeled tandem hour 6.00x0.65* 1222.07 4766.08 P&M-045
roller.
c) Material
i) Bitumen@ 5.4 per cent of weight of mix tonne 24.300 40000.00 972000.00 M-077
ii) Aggregate
Total weight of mix = 450 tonnes
Weight of bitumen = 22.5 tonnes
Weight of aggregate = 450 -22.50 = 427.50 tonnes
Taking density of aggregate = 1.5 ton/cum
Volume of aggregate = 285 cum
or
Grading - II-13 mm (Nominal Size)
13.2 - 10 mm30 per cent cum 85.500 1587.87 135762.89 M-044
10 - 5 mm 25 per cent cum 71.250 1529.06 108945.53 M-040
5 mm and below43 per cent cum 122.550 1411.44 172971.97 M-030
Filler @ 2 per cent of weight of aggregates. tonne 8.620 9571.33 82504.84 M-194
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
5.8 (ii) for Grading-II (10 mm nominal size)
d) Overhead charges @ 8% on (a+b+c) 131580.88
e) Contractor's profit @ 10% on (a+b+c+d) 177634.19
Cost for 191 cum = a+b+c+d+e 1953976.13
Rate per cum = (a+b+c+d+e)/191 (For Grading-II) 10230.24
say 10230.00
10230.00
Note *1. Although the rollers are required only for 3 hours as per
norms of output, but the same have to be available at site for
six hours as the hot mix plant and paver will take six hours for
mixing and paving the output of 450 tonnes considered in this
analysis. To cater for the idle period of these rollers, their
usage rates have been multiplied by a factor of 0.65.

2.Quantity of Bitumen has been taken for analysis purpose.


The actual quantity will depend upon job mix formula.
3. Labour for traffic control, watch and ward and other
miscellaneous duties at site including sundries have been
included in administrative overheads of the contractor.
4. In case BC is laid over freshly laid tack coat, provision of
mechanical broom and 2 mazdoors shall be deleted as the
same has been included in the cost of tack coat.
5. The individual density for each size of aggregates to be
used for construction i.e. 37.5-25 mm, 25-10 mm etc. should
be found in the laboratory and accordingly the quantities
should be ammended for use in field. The average density of
1.5 tonne/cum is only a reference density in this Data Book.
6. The individual percentage of aggregates should be
calculated from the total weight of dry aggregates i.e..
excluding the weight of bitumen. The weight of filler will also
be 2 per cent by weight of dry aggregates.
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
5.2 503 Tack Coat
Providing and applying tack coat with bitumen emulsion using
emulsion pressure distributor at the rate of 0.20 kg per sqm on
the prepared bituminous/granular surface cleaned with
mechanical broom.(for granular surface)
Unit = sqm
Taking output = 3500 sqm
a) Labour
Mate day 0.080 329.34 26.35 L-12
Mazdoor day 2.000 152.91 305.81 L-13
b) Machinery
Mechanical broom @ 1250 sqm per hour hour 2.800 396.38 1109.86 P&M-031
Air compressor 250 cfm hour 2.800 334.04 935.31 P&M-001
Emulsion pressure distributor @ 1750 sqm per hour hour 2.000 843.34 1686.67 P&M-016
c) Material
Bitumen emulsion @ 0.4 kg per sqm tonne 1.400 33000.00 46200.00 M-076
d) Overhead charges @ 8% on (a+b+c) 4021.12
e) Contractor's profit @ 10% on (a+b+c+d) 5428.51
Cost for 3500 sqm = a+b+c+d+e 59713.64
Rate per sqm = (a+b+c+d+e)/3500 17.06
say 17.10
17.00
CHAPTER- 6
CEMENT CONCRETE PAVEMENTS
Ref. to Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
MoRTH Spec. Input ref.

6.1 601 Dry Lean Cement Concrete Sub- base


Construction of dry lean cement concrete Sub- base over a
prepared sub-grade with coarse and fine aggregate
conforming to IS: 383, the size of coarse aggregate not
exceeding 25 mm, aggregate cement ratio not to exceed
15:1, aggregate gradation after blending to be as per table
600-1, cement content not to be less than 150 kg/ cum,
optimum moisture content to be determined during trial
length construction, concrete strength not to be less than 10
Mpa at 7 days, mixed in a batching plant, transported to site,
laid with a paver with electronic sensor, compacting with 8-10
tonnes vibratory roller, finishing and curing.
Unit = cum
Taking output = 450 cum (990 tonne)
a) Labour
Mate day 1.120 329.34 368.86 L-12
Mazdoor skilled day 6.000 244.65 1467.90 L-15
Mazdoor day 22.000 152.91 3363.93 L-13
b) Machinery
Front end loader 1 cum bucket capacity hour 6.000 803.34 4820.07 P&M-017
Cement concrete batch mix plant @ 75 cum per hour hour 6.000 4704.80 28228.80 P&M-068
Electric generator 100 KVA hour 6.000 730.42 4382.52 P&M-080
Paver with electronic sensor hour 6.000 2753.48 16520.91 P&M-034
Vibratory roller 8-10 t capacity hour 8.000 1671.38 13371.04 P&M-059
Water tanker6 KL capacity hour 8.000 517.53 4140.22 P&M-060
Lead =3 km
Tipper tonne.km 990 x L 70.57 209598.84
& P&M-047
Add 10 per cent of cost of carriage to cover cost of loading
20959.88
and unloading
c) Material
Crushed stone coarse aggregate of 25 mm and 12.5 mm
M-052 and
nominal sizes graded as per table 600-1 @ 0.90 cum/cum of cum 405.000 1529.00 619245.00
M-054
concrete conforming to clause 602.2.4.
Coarse Sand as per IS: 383 @ 0.45 cum/cum of concrete cum 203.000 1176.20 238768.60 M-004
Cement @ 150 kg/cum of concrete tonne 67.500 8939.12 603390.60 M-086
Cost of water KL 48.000 55.58 2667.62 M-195
d) Overhead charges @ 8% on (a+b+c) 141703.58
e) Contractor's profit @ 10% on (a+b+c+d) 191299.84
Cost for 450 cum = a+b+c+d+e 2104298.21
Rate per cum = (a+b+c+d+e)/450 4676.22
say 4676.00
4676.00
Quantity provided for aggregate is for estimating purpose.
Note
Exact quantity shall be as per mix design.
Ref. to Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
MoRTH Spec. Input ref.

6.2 602 Cement Concrete Pavement


Construction of un-reinforced, dowel jointed, plain cement
concrete pavement over a prepared sub base with 43 grade
cement @ 400 kg per cum, coarse and fine aggregate
conforming to IS 383, maximum size of coarse aggregate not
exceeding 25 mm, mixed in a batching and mixing plant as
per approved mix design, transported to site, laid with a fixed
form or slip form paver, spread, compacted and finished in a
continuous operation including provision of contraction,
expansion, construction and longitudinal joints, joint filler,
separation membrane, sealant primer, joint sealant,
debonding strip, dowel bar, tie rod, admixtures as approved,
curing compound, finishing to lines and grades as per
drawing
Unit = cum
Taking output = 1050 cum (2415 tonne)
a) Labour
Mate day 2.000 329.34 658.67 L-12
Mazdoor skilled day 15.000 244.65 3669.74 L-15
Mazdoor day 35.000 152.91 5351.71 L-13
b) Machinery
Road Sweeper @ 1250 sqm per hour hour 2.800 396.38 1109.86 P&M-031
Front end loader 1 cum bucket capacity hour 18.000 803.34 14460.20 P&M-017
Cement concrete batch mix plant @ 175 cum per hour
hour 6.000 6150.35 36902.10 P&M-067
(effective output)
Electric generator 250 KVA hour 6.000 1764.30 10585.80 P&M-081
Slip form paver with electronic sensor hour 6.000 2934.62 17607.71 P&M-006
Water tanker6 KL capacity hour 36.000 517.53 18631.01 P&M-060
Lead =3 km
Transit truck agitator 5 cum capacity. tonne.km 2415xL 47.05 340862.76
& P&M-050
Add 10 per cent of cost of carriage to cover cost of loading
34086.28
and unloading
Concrete joint cutting machine . hour 12.000 176.43 2117.16 P&M-083
Texturing machine . hour 12.000 940.96 11291.52 P&M-088
Ref. to Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
MoRTH Spec. Input ref.
c) Material
Crushed stone coarse aggregates of 25mm and 12.5mm
M-052 and
nominal size @ 0.90 cum/cum of concrete conforming to cum 945.000 1529.00 1444905.00
M-054
clause 602.2.4. .
Sand as per IS: 383 and conforming to clause 602.2.4 @
cum 473.000 1176.20 556342.60 M-004
0.45 cum/cum of concrete
Cement 43 grade @ 400 kg/cum of concrete tonne 414.000 8939.12 3700795.68 M-086
32 mm mild steel dowel bars of grade S 240 tonne 9.450 56457.60 533524.32 M-132
16 mm deformed steel tie bars of grade S 415 tonne 1.170 44000.00 51480.00 M-087
Separation Membrane of impermeable plastic sheeting 125
sqm 3675.000 39.99 146966.19 M-169
micron thick
Pre moulded Joint filler, 25 mm thick for expansion joint. sqm 16.330 926.26 15125.78 M-147
Joint sealant kg 875.000 722.48 632170.74 M-126
Sealant primer kg 116.670 617.51 72044.31 M-104
Plastic sheath,1.25 mm thick for dowel bars sqm 46.670 43.23 2017.33 M-144
Curing compound liter 1850.000 370.50 685430.55 M-097
Super plastisizer admixture IS marked as per 9103-1999 @
kg 2070.000 166.73 345123.54 M-186
0.5 per cent by weight of cement
Cost of water KL 216.000 55.58 12004.30 M-195
Add 1 per cent of material for cost of miscellaneous
materials like tarpauline, Hessian cloth, metal cap, cotton /
compressible sponge and cradle for dowel bars, work bridges
for men to approach concrete surface without walking over it, 81979.30
cutting blades and bites, minor equipments like scabbling
machine, threads, ropes, guide wires and any other
unforeseen items.
d) Overhead charges @ 8% on (a+b+c) 702179.53
e) Contractor's profit @ 10% on (a+b+c+d) 947942.37
Cost for 1050cum = a+b+c+d+e 10427366.08
Rate per cum = (a+b+c+d+e)/1050 9930.82
say 9931.00
9931.00
The quantities for cement, coarse aggregate and fine
Note aggregates are for estimating only .The exact quantities will
be as per mix design.
CHAPTER-7
GEOSYNTHETICS AND REINFORCED EARTH
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
7.5 3100 Reinforced Earth Structures
Reinforced earth Structures have four main components as under:

a) Excavation for foundation, foundation concrete and cement


concrete grooved seating in the foundation for facing elements (facia
material).
b) Facia material and its placement.
c) Assembling, joining with facing elements and laying of the
reinforcing elements.
d) Earth fill with granular material which is to be retained by the wall.

Each component is analysed separately as under:


considering Average height of wall = 8 m.
7.5 3102 (i) Assembling, joining and laying of reinforcing elements.

A With reinforcing element of steel / Aluminium strips / polymeric


strips.
Unit = Running Metre
Taking Output = 450 m
a) Labour
Mate day 0.360 329.34 118.56 L-12
Mazdoor day 6.000 152.91 917.44 L-13
Mazdoor skilled day 3.000 244.65 733.95 L-15
b) Material
@ Reinforcement strips 60 mm wide 5 mm thick as per clause 3102.

1.Galvanised carbon steel strips metre 450*1.1 289.82 143458.76 M-159


or
2.Copper Strips metre 450*1.1 1293.82 640440.90 M-158
or
3.Aluminium Strips metre 450*1.1 579.63 286917.52 M-162
or
4.Stainless steel strips metre 450*1.1 776.29 384264.54 M-161
or
5.Glass reinforced polymer/fibre reinforced polymer/polymeric metre 450*1.1 776.29 384264.54 M-160
strips
@ Any one of the above alternative may be adopted as per approved
design.
Add 10 per cent of the cost of reinforcing strip towards accessories like
tie-strips, nuts and bolts and loops/lugs for joining reinforcing elements
with the facia pannels, overlaps, heat bonding or extension.

Type 1.Galvanised carbon steel strips


1
c) Overhead charges @ 8% on (a+b) 11618.30
d) Contractor's profit @ 10% on (a+b+c) 14522.87
Cost of 450 m = a+b+c+d 171369.87
Rate per metre =(a+b+c+d)/450 380.82
say 381.00
384.00
Type 2.Copper Strips
2
c) Overhead charges @ 8% on (a+b) 51376.87
d) Contractor's profit @ 10% on (a+b+c) 64221.08
Cost of 450 m = a+b+c+d 757808.80
Rate per metre =(a+b+c+d)/450 1684.02
say 1684.00
1698.00
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Type 3.Aluminium Strips
3
c) Overhead charges @ 8% on (a+b) 23095.00
d) Contractor's profit @ 10% on (a+b+c) 28868.75
Cost of 450 m = a+b+c+d 340651.21
Rate per metre =(a+b+c+d)/450 757.00
say 757.00
763.00
Type 4.Stainless steel strips
4
c) Overhead charges @ 8% on (a+b) 30882.76
d) Contractor's profit @ 10% on (a+b+c) 38603.45
Cost of 450 m = a+b+c+d 455520.69
Rate per metre =(a+b+c+d)/450 1012.27
say 1012.00
1021.00
Type 5.Glass reinforced polymer/fibre reinforced polymer/polymeric
5 strips
c) Overhead charges @ 8% on (a+b) 30882.76
d) Contractor's profit @ 10% on (a+b+c) 38603.45
Cost of 450 m = a+b+c+d 455520.69
Rate per metre =(a+b+c+d)/450 1012.27
say 1012.00
1021.00
7.5(i) B With reinforcing elements of synthetic geogrids
Unit = sqm
Taking output = 300 sqm
a) Labour
Mate day 0.360 329.34 118.56 L-12
Mazdoor day 6.000 152.91 917.44 L-13
Mazdoor skilled day 3.000 244.65 733.95 L-15
b) Material
Synthetic Geogrids as per clause 3102.8 and approved design sqm 300.000 446.37 133910.37 M-187
and specifications.
Add 10 per cent of the cost of reinforcing elements (synthetic 13391.04
geogrids) for accessories like tie-strips, nuts and bolts and
loops/lugs for joining reinforcing elements with the facia pannels,
overlaps and other protective elements for synthetic geogrids.

c) Overhead charges @ 8% on (a+b) 11925.71


d) Contractor's profit @ 10% on (a+b+c) 16099.71
Cost of 300 sqm of Synthetic geogrids = a+b+c+d 177096.77
Rate per sqm = (a+b+c+d)/ 300 590.32
say 590.00
635.00
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
7.5 3104 (ii) Facing elements of RCC
Unit = sqm
Taking output = 75 sqm
a) Labour
Mate day 0.180 329.34 59.28 L-12
Mazdoor day 3.000 152.91 458.72 L-13
Mazdoor skilled day 1.500 244.65 366.97 L-15
b) Machinery
Light crane with lifting capacity upto 3 tonne hour 6.000 374.03 2244.19 P&M-013
c) Material
Pre-cast RCC M-35 facing elements of size as per design and 18 cu.m 13.500 6178.00 83403.00 Item 12.8
cm thick for 75 sqm. (Refer Item 12.8 (H)) (H) Case I
HYSD steel @ 5 kg / sqm (Refer Item 12.6) tonnes 0.380 66780.00 25376.40 Item 13.6
Add 2 per cent of cost of facia pannels, for all necessary temporary 2175.59
form work, scaffolding and provision of loops/lugs for lifting of pannels
and joining the reinforcing elements.
d) Overhead charges @ 8% on (a+b) 250.33
e) Contractor's profit @ 10% on (a+b+d) 337.95
Cost for 75 sqm = a+b+c+d+e 114672.43
Rate per sqm = (a+b+c+d+e)/ 75 1528.97
say 1529.00
1529.00
Note 1.The specification and construction details to be adopted shall be as
per section 3100 of MoRTH Specification.
2.Drainage arrangement shall be made as per approved design and
drawings.
3.The quantity of filler media shall be calculated as per approved
design and specifications and shall be priced separately.The rate for
same to be adopted from chapter 15.
4.Excavation for foundation including foundation concrete and groove
in the foundation for seating of bottom most facia panel and capping
beam to be calculated as per design and priced separately. The rates
for excavation and foundation concrete shall be taken from the chapter
12 & 13 in bridge section.
5.The earth fill to be retained is not included in this analysis. The same
is to be worked out and provided separately complete as per clause
305.
, 6.For compaction of Earthwork, attention is invited to clause 3105.5 of
MoRTH Specification.
7.Length of reinforcing strips will vary with the height of wall and will be
as per approved design and drawings.
8.The type of reinforcing elements to be adopted shall be as per
approved design and specifications.
9.The market rate for supply of reinforcing elements and their
accessories are to be ascertained from reputed firms in the field of
earth reinforcement.
10.The earth fill material shall be clean, free draining, granular with
high friction and low cohesion, non-corrosive, coarse grained with not
10 per cent of particles passing 75 micron sieve, free of any
deleterious matter, chlorides, salts, acids, alkalies, mineral oil, fungus
and microbes and shall be of specified PH value.

11.Capping beam is to be priced separately as per approved design.


The rate for cement concrete shall be taken from the chapter of sub-
structure in bridge section.
12.The cost of reinforced earth retaining wall shall include following:
(I) Excavation for foundation including backfilling.
(ii) Foundation concrete as per approved design.
(iii) Cost of facial pannels and their erection .
(iv) Cost of reinforcing elements including their fixing and joining with
the facial pannels.
(v) Drainage arrangement including filter media as per approved design
and drawings.
13. The compacted earth filling to be retained shall form part of
embankment.
CHAPTER-8
TRAFFIC SIGNS, MARKINGS & OTHER ROAD APPURTENANCES
Ref.
to
Cost Remarks/ Input
Sr No MoRT Description Unit Quantity Rate Rs
Rs ref.
H
Spec.
8.1 408 Cast in Situ Cement Concrete M20 Kerb
Construction of cement concrete kerb with top and bottom width 115
and 165 mm respectively, 250 mm high in M 20 grade PCC on M-10
grade foundation 150 mm thick, foundation having 50 mm projection
beyond kerb stone, kerb stone laid with kerb laying machine,
foundation concrete laid manually, all complete as per clause 408
Unit = Running metre
Taking output = 360 metre
A. Using Concrete Mixer
Cement Concrete
Cement concrete of grade M20 = 12.60 cum
Cement concrete of grade M10 for base= 11.61 cum
Total Concrete = 24.21 cu.m
a) Labour
Mate day 0.720 329.34 237.12 L-12
Mason day 2.000 352.86 705.72 L-11
Mazdoor day 16.000 152.91 2446.50 L-13
b) Machinery
Kerb casting machine @ 60 metres/hour hour 6.000 334.04 2004.24 P&M-029
Concrete mixer 0.48/0.28 cum capacity hour 12.000 237.59 2851.11 P&M-009
Water tanker6 KL capacity hour 5.000 517.53 2587.64 P&M-060
c) Material
Crushed stone aggregate 20 mm nominal size 59 per cent cum 21.790 1529.06 33318.22 M-053
Coarse sand 30 per cent cum 10.900 1176.20 12820.58 M-005
Cement 11 per cent tonne 5.700 8939.12 50952.98 M-086
Cost of water KL 30.000 55.58 1667.26 M-195
d) Overhead charges @ 8% on (a+b+c) 8767.31
e) Contractor's profit @ 10% on (a+b+c+d) 11835.87
Cost for 360 meter = a+b+c+d+e 130194.56
Rate per metre = (a+b+c+d+e)/360 361.65
say 362.00
362.00
B Using Concrete Batching and Mixing Plant
Cement Concrete
Cement concrete of grade M20 = 12.60 cum
Cement concrete of grade M10 for base = 11.61 cum
Total Concrete = 24.21 cu.m
a) Labour
Mate day 0.120 329.34 39.52 L-12
Mason day 1.000 352.86 352.86 L-11
Mazdoor day 2.000 152.91 305.81 L-13
b) Machinery
Kerb casting machine @ 60 metres/hour hour 6.000 334.04 2004.24 P&M-029
Concrete batching and mixing plant @ 15 cum/hr. hour 1.600 1870.16 2992.25 P&M-003
Water tanker6 KL capacity hour 5.000 517.53 2587.64 P&M-060
Tipper 5.5 cum capacity hour 6.000 491.65 2949.91 P&M-048
c) Material
Crushed stone aggregate 20 mm nominal size 59 per cent cum 21.790 1529.06 33318.22 M-053
Coarse sand 30 per cent cum 10.900 1176.20 12820.58 M-004
Cement 11 per cent tonne 5.700 8939.12 50952.98 M-086
Cost of water KL 30.000 55.58 1667.26 M-195
d) Overhead charges @ 8% on (a+b+c) 8799.30
e) Contractor's profit @ 10% on (a+b+c+d) 11879.06
Cost for 360 meter = a+b+c+d+e 130669.65
Rate per metre = (a+b+c+d+e)/360 362.97
say 363.00
363.00
Ref.
to
Cost Remarks/ Input
Sr No MoRT Description Unit Quantity Rate Rs
Rs ref.
H
Spec.
8.4 801 Retro-Reflectorised Traffic Signs
Providing and fixing of retro- reflectorised cautionary, mandatory and
informatory sign as per IRC :67 made of high intensity grade
sheeting vide clause 801.3, fixed over aluminium sheeting, 1.5 mm
thick supported on a mild steel angle iron post 75 mm x 75 mm x 6
mm firmly fixed to the ground by means of properly designed
foundation with M15 grade cement concrete 45 cm x 45 cm x 60 cm,
60 cm below ground level as per approved drawing
Unit = Each
Taking output = one traffic sign
i) Excavation for foundation cum 0.216 158.00 34.13 item 3.13 (1) A
ii) Cement concrete M15 grade cum 0.120 7004.00 840.48 Item 12.8 (A)
iii) Painting angle iron post two coats sqm 0.430 52.00 22.36 Item 8.9
a) Labour (For fixing at site)
Mate day 0.010 329.34 3.29 L-12
Mazdoor day 0.250 152.91 38.23 L-13
b) Material
Mild steel angle iron 75 x 75 x 6 mm kg 19.000 60.000 1140.000 M-185 /1000
Aluminium sheeting fixed with encapsulated lens type reflective
sheeting of size including lettering and signs as applicable
Add 2 per cent of cost of angle iron towards cost of drilling holes,
22.80
nuts, bolts etc.
(i) 90 cm equilateral triangle sqm 0.350 617.51 216.13 M-061
or
( ii ) 60 cm equilateral triangle sqm 0.156 617.51 96.33 M-061
or
( iii ) 60 cm circular sqm 0.283 617.51 174.75 M-061
or
( iv ) 80 mm x 60 mm rectangular sqm 0.480 617.51 296.40 M-061
or
(v) 60 cm x 45 cm rectangular sqm 0.270 617.51 166.73 M-061
or
(vi ) 60 cm x 60 cm square sqm 0.360 617.51 222.30 M-061
or
( vii ) 90 cm high octagon sqm 0.672 617.51 414.96 M-061
c) Machinery
Tractor-trolley hour 0.010 379.91 3.80 P&M-053
(i) 90 cm equilateral triangle
d) Overhead charges @ 8% on (a+b+c) 113.94
e) Contractor's profit @ 10% on (a+b+c+d) 153.82
Rate per traffic sign = ( i+ii+iii+a+b+c+d+e) 2588.97
say 2589.00
2589.00
( ii ) 60 cm equilateral triangle
d) Overhead charges @ 8% on (a+b+c) 104.36
e) Contractor's profit @ 10% on (a+b+c+d) 140.88
Rate per traffic sign = ( i+ii+iii+a+b+c+d+e) 2446.65
say 2447.00
2447.00
( iii ) 60 cm circular
d) Overhead charges @ 8% on (a+b+c) 110.63
e) Contractor's profit @ 10% on (a+b+c+d) 149.35
Rate per traffic sign = ( i+ii+iii+a+b+c+d+e) 2539.82
say 2540.00
2540.00
Ref.
to
Cost Remarks/ Input
Sr No MoRT Description Unit Quantity Rate Rs
Rs ref.
H
Spec.
( iv ) 80 mm x 60 mm rectangular
d) Overhead charges @ 8% on (a+b+c) 120.36
e) Contractor's profit @ 10% on (a+b+c+d) 162.49
Rate per traffic sign = ( i+ii+iii+a+b+c+d+e) 2684.34
say 2684.00
2684.00
(v) 60 cm x 45 cm rectangular
d) Overhead charges @ 8% on (a+b+c) 109.99
e) Contractor's profit @ 10% on (a+b+c+d) 148.48
Rate per traffic sign = ( i+ii+iii+a+b+c+d+e) 2530.28
say 2530.00
2530.00
(vi ) 60 cm x 60 cm square
d) Overhead charges @ 8% on (a+b+c) 114.43
e) Contractor's profit @ 10% on (a+b+c+d) 154.49
Rate per traffic sign = ( i+ii+iii+a+b+c+d+e) 2596.31
say 2596.00
2596.00
( vii ) 90 cm high octagon
d) Overhead charges @ 8% on (a+b+c) 129.85
e) Contractor's profit @ 10% on (a+b+c+d) 175.29
Rate per traffic sign = ( i+ii+iii+a+b+c+d+e) 2825.19
say 2825.00
2825.00
1.Any one area of aluminium sheeting given at (i) to (vii) may be
Note
adopted as per site requirement and in accordance with IRC : 67

2.Rate for excavation, cement concrete M-15 and painting may be


taken from respective chapters
3. The depth of foundation and quantity of cement concrete in the
foundation are indicative. These may be increased for areas having
higher wind velocities like in coastal areas. This is applicable to all
road signs and directions boards.
Direction and Place Identification Signs upto 0.9 sqm Size
8.5 801
Board.
Providing and erecting direction and place identification retro-
reflectorised sign as per IRC:67 made of high intensity grade
sheeting vide clause 801.3, fixed over aluminium sheeting, 2 mm
thick with area not exceeding 0.9 sqm supported on a mild steel
single angle iron post 75 x 75 x 6 mm firmly fixed to the ground by
means of properly designed foundation with M15 grade cement
concrete 45 x 45 x 60 cm, 60 cm below ground level as per approved
drawing
Unit = sqm
Taking output = 0.9 sqm
i) Excavation for foundation cum 0.216 158.00 34.13 Item No. 3.13
ii) Cement concrete M15 grade cum 0.120 7004.00 840.48 Item 12.8 (A)
iii) Painting angle iron post two coats sqm 0.430 52.00 22.36 Item 8.9
a) Labour (For fixing at site)
Mate day 0.010 329.34 3.29 L-12
Mazdoor day 0.200 152.91 30.58 L-13
b) Material
60.000 1140.00 M-185 /1000
Mild steel angle iron 75 mm x 75 mm x 6 mm,2.85 metres long kg 19.000
Aluminium sheeting fixed with encapsulated lens type reflective 617.51 555.75 M-061
sqm 0.900
sheeting of size 0.9 sqm
Add 2 per cent of cost of materials for drilling holes, nuts, bolts,
33.92
fabrication etc.
Ref.
to
Cost Remarks/ Input
Sr No MoRT Description Unit Quantity Rate Rs
Rs ref.
H
Spec.
c) Machinery
Tractor-trolley hour 0.020 379.91 7.60 P&M-053
d) Overhead charges @ 8% on (a+b+c) 141.69
e) Contractor's profit @ 10% on (a+b+c+d) 191.28
Cost for 0.9 sqm =I+ii+ii+ a+b+c+d+e 3001.09
Rate per sqm (for sign having area upto 0.9 sqm) =
3334.55
(I+ii+iii+a+b+c+d+e)/0.90
say 3335.00
3335.00
I) Lettering and arrow marks on sign board to be provided separately
Note as per actual requirement. Rates for these items have been analysed
separately
ii) Rate for excavation, cement concrete M-15 and painting may be
taken from respective chapters
Direction and Place Identification Signs with size more than 0.9
8.6 801
sqm size Board.

Providing and erecting direction and place identification retro-


reflectorised sign as per IRC :67 made of high intensity grade
sheeting vide clause 801.3, fixed over aluminium sheeting, 2 mm
thick with area exceeding 0.9 sqm supported on a mild steel angle
iron post 75 mm x 75 mm x 6 mm, 2 Nos. firmly fixed to the ground
by means of properly designed foundation with M 15 grade cement
concrete45 cm x 45 cm x 60 cm, 60 cm below ground level as per
approved drawing

Unit = sqm
Taking output = 1.50 sqm
i) Excavation for foundation cum 0.430 158.00 67.94 Item No. 3.13
ii) Cement concrete M15 grade cum 0.240 7004.00 1680.96 Item 12.8 (A)
iii) Painting angle iron post 2 coats sqm 0.860 52.00 44.72 Item 8.9
a) Labour (For fixing at site)
Mate day 0.010 329.34 3.29 L-12
Mazdoor day 0.300 152.91 45.87 L-13
b) Material
Mild steel angle iron 75 mm x 75 mm x 6 mm, 2.85 metres long, 60.000 2280.00 M-185 /1000
kg 38.000
2 nos
Aluminium sheeting fixed with encapsulated lens type reflective 617.51 926.26 M-061
sqm 1.500
sheeting
Add 2 per cent of cost of materials for drilling holes, nuts, bolts,
64.13
fabrication etc.
c) Machinery
Tractor-trolley hour 0.020 379.91 7.60 P&M-053
d) Overhead charges @ 8% on (a+b+c) 266.17
e) Contractor's profit @ 10% on (a+b+c+d) 359.33
Cost for 1.5 sqm =I+ii+ii+ a+b+c+d+e 5746.28
Rate per sqm ( for sign having area more than 0.9 sqm) = (
3830.85
i+ii+iii+a+b+c+d+e)/1.50
say 3831.00
3831.00
i) Lettering and arrow marks on sign board to be provided separately
Note as per actual requirement. Rates for these items have been analysed
separately
ii) Rate for excavation, cement concrete M-15 and painting may be
taken from respective chapters
Ref.
to
Cost Remarks/ Input
Sr No MoRT Description Unit Quantity Rate Rs
Rs ref.
H
Spec.
8.7 802 Overhead Signs

Providing and erecting overhead signs with a corrosion resistant


2mm thick aluminium alloy sheet reflectorised with high intensity retro-
reflective sheeting of encapsulated lense type with vertical and
lateral clearance given in clause 802.2 and 802.3 and installed as
per clause 802.7 over a designed support system of aluminium alloy
or galvanised steel trestles and trusses of sections and type as per
structural design requirements and approved plans

A Truss and Vertical Support


Unit = tonne
Taking output = 1 tonne
a) Labour
Mate day 0.240 329.34 79.04 L-12
Blacksmith day 2.000 352.86 705.72 L-02
Mazdoor including for handling & fixing at site. day 4.000 152.91 611.62 L-13
b) Material
96330.78 101147.32 M-060
Aluminium alloy/galvanised steel including 5 per cent wastage tonne 1.050
Add 1 per cent on cost of material for nuts, bolts and drilling and
1011.47
welding consumables
Add 15 per cent on cost of material for fabrication of trusses as per
15323.82
approved design
c) Machinery
Crane 3 tonne capacity hour 3.000 374.03 1122.09 P&M-013
Truck hour 0.500 517.53 258.76 P&M-057
d) Overhead charges @ 8% on (a+b+c) 9620.79
e) Contractor's profit @ 10% on (a+b+c+d) 12988.06
Rate per tonne = (a+b+c+d+e) 142868.71
say 142869.00
142869.00
8.7 B Aluminium Alloy Plate for Over Head Sign
Unit = sqm
Taking output = 1 sqm
a) Labour
Mate day 0.020 329.34 6.59 L-12
Blacksmith day 0.100 352.86 35.29 L-02
Mazdoor day 0.150 152.91 22.94 L-13
b) Material
Aluminium alloy plate,2 mm thick, fixed with high intensity grade 506.35 506.35 M-059
sqm 1.000
sheeting vide clause 801.3
Miscellaneous
Add 1 per cent of cost of labour for lifting arrangement, like ladders,
0.65
pulleys, ropes etc
c) Overhead charges @ 8% on (a+b) 45.74
d) Contractor's profit @ 10% on (a+b+c) 61.76
Rate per sqm = (a+b+c+d) 679.31
say 679.00
679.00
1. The cost of excavation and foundation concrete for fixing of
Note vertical support system to be worked out separately as per the
approved drawing/design and to be included in the estimate.

2. Lettering and arrow marks on sign board to be provided separately


as per actual requirement. Rates for these items have been included
separately in this chapter.
Ref.
to
Cost Remarks/ Input
Sr No MoRT Description Unit Quantity Rate Rs
Rs ref.
H
Spec.
8.8 803 Painting Two Coats on New Concrete Surfaces
Painting two coats after filling the surface with synthetic enamel paint
in all shades on new plastered concrete surfaces
Unit = sqm
Taking output = 40 sqm
a) Labour
Mate day 0.120 329.34 39.52 L-12
Painter day 2.000 352.86 705.72 L-18
Mazdoor day 1.000 152.91 152.91 L-13
b) Material
Paint conforming to requirement of clause 803.3. Litre 6.000 172.90 1037.41 M-138

Add for scaffolding @ 1 per cent of labour cost where required 8.98
c) Overhead charges @ 8% on (a+b) 155.56
d) Contractor's profit @ 10% on (a+b+c) 210.01
Cost for 40 sqm = a+b+c+d 2310.11
Rate per sqm = (a+b+c+d)/40 57.75
say 58.00
58.00
8.9 803 Painting on Steel Surfaces
Providing and applying two coats of ready mix paint of approved
brand on steel surface after through cleaning of surface to give an
even shade
Unit = sqm
Taking output = 10 sqm
a) Labour
Mate day 0.030 329.34 9.88 L-12
Painter day 0.450 352.86 158.79 L-18
Mazdoor day 0.250 152.91 38.23 L-13
b) Material
Paint ready mixed approved brand. Litre 1.250 185.25 231.56 M-137
Add @ 1 per cent on cost of material for scaffolding 2.32
c) Overhead charges @ 8% on (a+b) 35.26
d) Contractor's profit @ 10% on (a+b+c) 47.60
Cost for 10 sqm = a+b+c+d 523.64
Rate per sqm= (a+b+c+d)/10 52.36
say 52.00
52.00
8.10 803 Painting on Wood Surfaces
Providing and applying two coats of ready mix paint of approved
brand on wood surface after thorough cleaning of surface to give an
even shade
Unit = sqm
Taking output = 10 sqm
a) Labour
Mate day 0.030 329.34 9.88 L-12
Painter day 0.500 352.86 176.43 L-18
Mazdoor day 0.200 152.91 30.58 L-13
b) Material
Paint ready mixed of approved brand. Litre 1.500 185.25 277.88 M-137
Add @ 1 per cent on cost of material for scaffolding 2.78
c) Overhead charges @ 8% on (a+b) 39.80
d) Contractor's profit @ 10% on (a+b+c) 53.74
Cost for 10 sqm = a+b+c+d 591.09
Rate per sqm = (a+b+c+d)/10 59.11
59.00
Ref.
to
Cost Remarks/ Input
Sr No MoRT Description Unit Quantity Rate Rs
Rs ref.
H
Spec.
Painting Lines, Dashes, Arrows etc on Roads in Two Coats on
8.11 803
New Work
Painting lines, dashes, arrows etc on roads in two coats on new work
with ready mixed road marking paint conforming to IS:164 on
bituminous surface, including cleaning the surface of all dirt, dust and
other foreign matter, demarcation at site and traffic control
(i) Over 10 cm in width
Unit = sqm
Taking output = 10 sqm
a) Labour
Mate day 0.090 329.34 29.64 L-12
Painter day 0.550 352.86 194.07 L-18
Mazdoor day 1.550 152.91 237.00 L-13
b) Material
Road marking Paint as per IS :164 Litre 1.480 172.90 255.89 M-138
c) Overhead charges @ 8% on (a+b) 57.33
d) Contractor's profit @ 10% on (a+b+c) 77.39
Cost for 10 sqm = a+b+c+d 851.33
Rate per sqm= (a+b+c+d)/10 85.13
say 85.00
85.00
8.11 (ii) Up to 10 cm in width
Unit = sqm
Taking output = 10 sqm
a) Labour
Mate day 0.070 329.34 23.05 L-12
Painter day 0.350 352.86 123.50 L-18
Mazdoor day 1.350 152.91 206.42 L-13
b) Material
Road marking paint Litre 1.480 172.90 255.89 M-138
c) Overhead charges @ 8% on (a+b) 48.71
d) Contractor's profit @ 10% on (a+b+c) 65.76
Cost for 10 sqm = a+b+c+d 723.34
Rate per sqm = (a+b+c+d)/10 72.33
say 72.00
72.00
Painting Lines, Dashes, Arrows etc on Roads in Two Coats on
8.12 803
Old Work
Painting lines, dashes, arrows etc on roads in two coats on old work
with ready mixed road marking paint conforming to IS: 164 on
bituminous surface, including cleaning the surface of all dirt, dust and
other foreign matter, demarcation at site and traffic control
(i) Over 10 cm in width
Unit = sqm
Taking output = 10 sqm
a) Labour
Mate day 0.060 329.34 19.76 L-12
Painter Ist class day 0.300 352.86 105.86 L-18
Mazdoor day 1.250 152.91 191.13 L-13
b) Material
Road marking paint Litre 0.900 172.90 155.61 M-138
c) Overhead charges @ 8% on (a+b) 37.79
d) Contractor's profit @ 10% on (a+b+c) 51.02
Cost for 10 sqm = a+b+c+d 561.17
Rate per sqm = (a+b+c+d)/10 56.12
56.00
Ref.
to
Cost Remarks/ Input
Sr No MoRT Description Unit Quantity Rate Rs
Rs ref.
H
Spec.
8.12 (ii) Up to 10 cm in width
Unit = sqm
Taking output = 10 sqm
a) Labour
Mate day 0.070 329.34 23.05 L-12
Painter Ist class day 0.350 352.86 123.50 L-18
Mazdoor day 1.350 152.91 206.42 L-13
b) Material
Road marking Paint Litre 0.900 172.90 155.61 M-138
c) Overhead charges @ 8% on (a+b) 40.69
d) Contractor's profit @ 10% on (a+b+c) 54.93
Cost for 10 sqm= a+b+c+d 604.20
Rate per sqm = (a+b+c+d)/10 60.42
say 60.00
60.00
Road Marking with Hot Applied Thermoplastic Compound with
8.13 803
Reflectorising Glass Beads on Bituminous Surface
Providing and laying of hot applied thermoplastic compound 2.5 mm
thick including reflectorising glass beads @ 250 gms per sqm area,
thickness of 2.5 mm is exclusive of surface applied glass beads as
per IRC:35 .The finished surface to be level, uniform and free from
streaks and holes.
Unit = sqm
Taking output = 640 sqm
a) Labour
Mate day 0.500 329.34 164.67 L-12
Mazdoor day 2.000 152.91 305.81 L-13
b) Machinery
Road marking machine @ 80 sqm per hour hour 8.000 123.50 988.01 P&M-043
Tractor-trolley hour 8.000 379.91 3039.30 P&M-053
c) Material
Hot applied thermoplastic compound Litre 2000.000 159.32 318632.58 M-124
Reflectorising glass beads kg 200.000 148.20 29640.24 M-157
d) Overhead charges @ 8% on (a+b+c) 28221.65
e) Contractor's profit @ 10% on (a+b+c+d) 38099.23
Cost for 640 sqm = a+b+c+d+e 419091.48
Rate per sqm = a+b+c+d+e)/640 654.83
say 655.00
655.00
1. A sealing primer may be applied in advance on cement concrete
pavement to ensure proper bonding. Any laitance and/or curing
Note
compound to be removed where paint is required to be applied on
concrete surface.
2.Cost of painter is already included in hire charges of road marking
machine.
Ref.
to
Cost Remarks/ Input
Sr No MoRT Description Unit Quantity Rate Rs
Rs ref.
H
Spec.
8.14 804 Kilometre Stone
Reinforced cement concrete M15grade kilometre stone of standard
design as per IRC:8-1980, fixing in position including painting and
printing etc
(i) 5th kilometre stone (precast)
Unit = Nos.
Taking output = 6 Nos.
a) M-15 grade of concrete cum 2.350 7004.00 16459.40 Item 12.8 (A)

b) Steel reinforcement @ 5 kg per sqm kg 22.080 66.780 1474.50 Item 13.6 /1000
c) Excavation in soil for foundation cum 1.680 158.00 265.44 Item No. 3.13

d) Painting two coats on concrete surface sqm 9.850 58.00 571.30 Item 8.8
e) Lettering on km post (average 30 letters of 10 cm per cm per 0.50 900.00 Item 8.3
1800.000
height each) letter
Transportation and fixing
f) Labour
Mate day 0.260 329.34 85.63 L-12
Mason day 0.600 352.86 211.72 L-11
Mazdoor including loading/unloading day 6.000 152.91 917.44 L-13
g) Machinery
Tractor-trolley hour 6.000 379.91 2279.48 P&M-053
h) Overhead charges @ 8% on (f+g) 279.54
i) Contractor's profit @ 10% on (f+g+h) 377.38
Cost for 6 Nos. 5th km stone = a+b+c+ d+e +f+g+h +i 23821.82
Rate for each 5th km stone = (a+b+c+d+e+f+g+h+i)/ 6 3970.30
say 3970.00
3970.00
8.14 (ii) Ordinary kilometer stone (precast)
Unit = Nos.
Taking output = 14 Nos.
a) M-15 grade of concrete cum 3.770 7004.00 26405.08 Item 12.8 (A)
b) Steel reinforcement @ 5 kg per sqm kg 26.320 66.780 1757.65 Item 13.6 /1000
158.00 437.66 Item No. 3.13
c) Excavation in soil for foundation cum 2.770

d) Painting two coats on concrete surface sqm 11.410 58.00 661.78 Item 8.8
e) Lettering on km post ( average 12 letters of 10 cm per cm per 0.50 840.00 Item 8.3
1680.000
height each) letter
Transportation and fixing
f) Labour
Mate day 0.320 329.34 105.39 L-12
Mason day 1.000 352.86 352.86 L-11
Mazdoor day 7.000 152.91 1070.34 L-13
g) Machinery
Tractor-trolley hour 6.000 379.91 2279.48 P&M-053
h) Overhead charges @ 8% on (f+g) 304.65
i) Contractor's profit @ 10% on (f+g+h) 411.27
Cost for 14 Nos. ordinary km stone = (a+b+ c+d+e+f+g+h+i) 34626.15

Rate for each ordinary km stone = (a+b+ c+d+e+f+g+h+j) /14 2473.30


say 2473.00
2473.00
Ref.
to
Cost Remarks/ Input
Sr No MoRT Description Unit Quantity Rate Rs
Rs ref.
H
Spec.
8.14 (iii) Hectometer stone (precast)
Unit = Nos.
Taking output = 33 Nos.
a) M-15 grade of concrete cum 1.580 7004.00 11066.32 Item 12.8 (A)

b) Steel reinforcement @ 5 kg per sqm kg 66.000 66.780 4407.48 Item 13.6 /1000
c) Excavation in soil for foundation cum 1.390 158.00 219.62 Item No. 3.13
d) Painting two coats on concrete surface sqm 6.270 58.00 363.66 Item 8.8
e) Lettering on km post (average 1 letter of 10 cm height per cm per 0.50 165.00 Item 8.3
330.000
each) letter
Transportation and fixing
f) Labour
Mate day 0.340 329.34 111.97 L-12
Mason day 1.500 352.86 529.29 L-11
Mazdoor day 7.000 152.91 1070.34 L-13
g) Machinery
Tractor-trolley hour 6.000 379.91 2279.48 P&M-053
h) Overhead charges @ 8% on (f+g) 319.29
i) Contractor's profit @ 10% on (f+g+h) 431.04
Cost for 33 Nos. Hectometer stone = (a+b+c+d+e+f+ g+h+i) 20963.49
Rate for each Hectometer stone = (a+b +c +d+e+f+ g+h+i) / 33 635.26
say 635.00
635.00
The rate for excavation, cement concrete, steel reinforcement,
Note
painting and lettering may be taken from respective chapters.
8.15 805 Road Delineators
Supplying and installation of delineators (road way indicators, hazard
markers, object markers), 80-100 cm high above ground level,
painted black and white in 15 cm wide strips, fitted with 80 x 100 mm
rectangular or 75 mm dia circular reflectorised panels at the top,
buried or pressed into the ground and conforming toIRC-79 and the
drawings.
Unit = Each
Taking output= 30 Nos.
a) Labour
Mate day 0.040 329.34 13.17 L-12
Mazdoor for fixing day 1.000 152.91 152.91 L-13
b) Material
Cost of approved type of delineators from ISI certified firm as 957.43 28722.80 M-091
each 30.000
per the standard drawing given in IRC - 79
Add 10 per cent cost of material for installation 2872.28
c) Overhead charges @ 8% on (a+b) 2540.89
d) Contractor's profit @ 10% on (a+b+c) 3430.21
Cost for 30 Nos. delineators = (a+b+ c+d) 37732.26
Rate per delineators = (a+b+c+d) /30 1257.74
say 1258.00
1258.00
In case of soft ground, a proper foundation may be provided as per
approved design. In case foundation is required to be provided, the
Note
items of excavation and foundation concrete are required to be
measured and paid separately.
Ref.
to
Cost Remarks/ Input
Sr No MoRT Description Unit Quantity Rate Rs
Rs ref.
H
Spec.
8.16 806 Boundary pillar
Reinforced cement concrete M15 grade boundary pillars of standard
design as per IRC:25-1967, fixed in position including finishing and
lettering but excluding painting
Unit = Each
Taking output = 57 Nos.
a) M-15 grade of the boundary stone cum 1.250 7004.00 8755.00 Item 12.8 (A)

b) Steel reinforcement kg 79.800 66.780 5329.04 Item 13.6 /1000


c) Excavation in soil cum 10.720 158.00 1693.76 Item No. 3.13

per letter 0.50 1140.00 Item 8.3


d) Lettering, each 10 cm high 2280.000
per cm high
Transportation and fixing
e) Labour
Mate day 0.570 329.34 187.72 L-12
Mazdoor day 14.250 152.91 2178.91 L-13
f) Machinery
Tractor-trolley hour 6.000 379.91 2279.48 P&M-053
g) Material
Stone spall cum 11.970 969.66 11606.82 M-008
h) Overhead charges @ 8% on (e+f+g) 1300.23
i) Contractor's profit @ 10% on (e+f+g+h) 1755.32
Cost for 57 Nos. boundary pillar = (a+b +c+d +e+ f+g+h+i ) 36226.28
Rate for each boundary pillar = (a+b+c+d+e+ f+g+h+i)/57 635.55
say 636.00
636.00
In case of soft ground, a proper foundation may be provided as per
approved design. In case foundation is required to be provided, the
Note
items of excavation and foundation concrete are required to be
measured and paid separately.
Ref.
to
Cost Remarks/ Input
Sr No MoRT Description Unit Quantity Rate Rs
Rs ref.
H
Spec.
8.17 807 G.I Barbed Wire Fencing 1.2 Metre High

Providing and fixing 1.2 metres high GI barbed wire fencing with 1.8
m angle iron posts 40 mm x 40 mm x 6 mm placed every 3 metres
center to center founded in M15 grade cement concrete, 0.6 metre
below ground level, every 15th post, last but one end post and
corner post shall be strutted on both sides and end post on one side
only and provided with 9 horizontal lines and 2 diagonals interwoven
with horizontal wires, fixed with GI staples, turn buckles etc complete
as per clause 807

Unit = per running metre


Taking output = 30 metres
a) Labour
Mate day 0.090 329.34 29.64 L-12
Blacksmith day 0.250 352.86 88.22 L-02
Mazdoor day 2.000 152.91 305.81 L-13
b) Material
Barbed wire 335 metres length @ 9.38 kg per 100 metres kg 31.420 98.80 3104.32 M-062
MS angle iron 40 mm x 40mm x 6 mm, 23 metres in length @ 60.000 4830.00 M-185 /1000
kg 80.500
3.5 kg per metre
Add for GI staple binding wire, drilling holes etc. @ 2 per cent of the
158.69
cost of material
c) Painting
Applying two coats of painting on exposed surface of angle iron 52.00 109.72 Item 8.9
sqm 2.110
posts ( Rate as per item no. 8.9)
d) Overhead charges @ 8% on (a+b) 681.33
e) Contractor's profit @ 10% on (a+b+d) 919.80
Cost for 30 metres fencing = a+b+c+d+e 10227.53
Rate per metre = (a+b+c+d+e)/30 340.92
say 341.00
341.00
Cost of excavation for foundation and foundation concrete to be
Note added separately in the cost estimate as per approved design. The
rate for these items may be taken from respective chapters.
Ref.
to
Cost Remarks/ Input
Sr No MoRT Description Unit Quantity Rate Rs
Rs ref.
H
Spec.
8.18 807 G.I Barbed Wire Fencing 1.8 Metre High
Providing and fixing 1.8 metres high GI barbed wire fencing with 2.4
m angle iron posts 50 mm x 50 mm x 6 mm placed every 3 metres
center to center founded in M15 grade cement concrete, 0.6 metre
below ground level, every 15th post, last but one end post and
corner post shall be strutted on both sides and end post on one side
only and provided with 12 horizontal lines and 2 diagonals
interwoven with horizontal wires, fixed with GI staples, turn buckles
etc complete as per clause 807
Unit = per running metre
Taking output = 30 metres
a) Labour
Mate day 0.120 329.34 39.52 L-12
Blacksmith day 0.400 352.86 141.14 L-02
Mazdoor day 2.500 152.91 382.27 L-13
b) Material
Barbed wire 428 metres length @ 9.38 kg per 100 metres kg 40.150 98.80 3966.85 M-062
MS angle iron 50 mm x 50 mm x 6 mm,33.8 metres in length @ 60.000 9120.00 M-185 /1000
kg 152.000
4.5 kg per metre
Add for GI staple, binding wire, drilling holes etc. @ 2 per cent
261.74
of the cost of material
c) Painting
Applying two coats of painting on exposed surface of angle iron 52.00 205.92 Item 8.9
sqm 3.960
posts
d) Overhead charges @ 8% on (a+b) 1112.92
e) Contractor's profit @ 10% on (a+b+d) 1502.44
Cost for 30 metres fencing = a+b+c+d+e 16732.80
Rate per metre fencing = (a+b+c +d+e)/30 557.76
say 558.00
558.00
Cost of excavation for foundation and foundation concrete to be
Note added separately in the cost estimate as per approved design. The
rate for these items may be taken from respective chapters.
Ref.
to
Cost Remarks/ Input
Sr No MoRT Description Unit Quantity Rate Rs
Rs ref.
H
Spec.
Tubular Steel Railing on Medium Weight Steel Channel ( ISMC
8.20 808
series) 100 mm x 50 mm
Providing, fixing and erecting 50 mm dia steel pipe railing in 3 rows
duly painted on medium weight steel channels (ISMC series) 100
mm x 50 mm, 1.2 metres high above ground, 2 m centre to centre,
complete as per approved drawings
Unit = Running metre
Taking output = 10metres
i) Excavation for foundation (6 Nos)6 x 0.6 x 0.6 x 0.6 cum 1.296 158.00 204.77 Item No. 3.13
7004.00 4538.59 Item 12.8 (A)
ii) Foundation concrete M-15 grade PCC 6 x 0.6 x 0.6 x 0.3 cum 0.648
iii) Painting of pipe sqm 4.710 52.00 244.92 Item 8.9
iv) Painting of channel section 6 nos,1.8 metres each 0.2 x 52.00 112.32 Item 8.9
sqm 2.160
1.8 x 6 = 2.16
a) Labour (For fixing at site)
Mate day 0.010 329.34 3.29 L-12
Mazdoor day 0.250 152.91 38.23 L-13
Plumber day 0.010 352.86 3.53 L-02
b) Material
Steel pipe 50 mm external dia as per IS:1239 metre 30.000 203.78 6113.30 M-181
Medium weight steel channel (ISMC series) 100 mm x 50 60.000 5961.60 M-185 /1000
kg 99.360
mm,10.8 metres length @ 9.2 kg per metre
Add for drilling holes @ 2 per cent of cost of channels 119.23
c) Machinery
Tractor-trolley hour 0.040 379.91 15.20 P&M-053
d) Overhead charges @ 8% on (a+b+c) 1388.40
e) Contractor's profit @ 10% on (a+b+c+d) 1874.34
Cost for 10 metre =i+ii+iii+iv+ a+b+c+d+e 20617.71
Rate per metre = (i+ii+iii+iv+a+b+c+d+e)/10 2061.77
say 2062.00
2062.00
Ref.
to
Cost Remarks/ Input
Sr No MoRT Description Unit Quantity Rate Rs
Rs ref.
H
Spec.
8.22 809 Reinforced Cement Concrete Crash Barrier
Provision of an Reinforced cement concrete crash barrier at the
edges of the road, approaches to bridge structures and medians,
constructed with M-20 grade concrete with HYSD reinforcement
conforming to IRC:21 and dowel bars 25 mm dia, 450 mm long at
expansion joints filled with pre-moulded asphalt filler board, keyed to
the structure on which it is built and installed as per design given in
the enclosure to MOST circular No. RW/NH - 33022/1/94-DO III
dated 24 June 1994 as per dimensions in the approved drawing and
at locations directed by the Engineer, all as specified
Unit = Linear metre
Taking output = 10 m
(i) a) M 20 grade concrete
M 20 grade concrete cum 3.000 7004.00 21012.00 Item 14.1(A)
b) Labour
Mate day 0.040 329.34 13.17 L-12
Mazdoor day 1.000 152.91 152.91 L-13
c) Material
HYSD steel reinforcement including dowel bars tonne 0.280 44000.00 12320.00 M-087
Pre-moulded asphalt filler board sqm 0.320 1049.76 335.92 M-149
d) Overhead charges @ 8% on (b+c) 1025.76
e) Contractor's profit @ 10% on (b+c+d) 1384.78
Cost for 10 metre = a+b+c+d+e 36244.54
Rate per metre = (a+b+c+d+e)/10 3624.45
say 3624.00
3624.00
i) Excavation and backfilling are incidental to work and not to be
Note
measured separately.
ii) Rate for RCC M 20 may be taken from chapter on super structure.
Ref.
to
Cost Remarks/ Input
Sr No MoRT Description Unit Quantity Rate Rs
Rs ref.
H
Spec.
8.23 810 Metal Beam Crash Barrier
A Type - A, "W" : Metal Beam Crash Barrier

Providing and erecting a "W" metal beam crash barrier comprising of


3 mm thick corrugated sheet metal beam rail, 70 cm above
road/ground level, fixed on ISMC series channel vertical post, 150 x
75 x 5 mm spaced 2 m centre to centre, 1.8 m high, 1.1 m below
ground/road level, all steel parts and fitments to be galvanised by hot
dip process, all fittings to conform to IS:1367 and IS:1364, metal
beam rail to be fixed on the vertical post with a spacer of channel
section 150 x 75 x 5 mm, 330 mm long complete as per clause 810

Unit = Running metre


Taking output = 4.5 metre length
a) Labour
Mate day 0.060 329.34 19.76 L-12
Blacksmith day 0.500 352.86 176.43 L-02
Mazdoor day 1.000 152.91 152.91 L-13
b) Machinery
Tractor-trolley hour 0.100 379.91 37.99 P&M-053
c) Material
Corrugated sheet,3 mm thick, "W" beam section railing,4.5 m in 60.000 2472.60 M-185 /1000
kg 41.210
length
Channel post 150 x 75 x 5 mm,1.8 m long,3 Nos @ 16.4 kg per 60.000 5313.60 M-185 /1000
kg 88.560
metre
Spacer 150 x 75 x 5 mm channel 0.33 m long,3 Nos @ 16.4 kg 60.000 974.40 M-185 /1000
kg 16.240
per metre
Nuts and bolts kg 20.000 87.69 1753.71 M-136
Add 25 per cent of the cost of material for fabrication, nuts, bolts
2628.58
and washers etc.)
d) Overhead charges @ 8% on (a+b+c) 1082.40
e) Contractor's profit @ 10% on (a+b+c+d) 1461.24
Cost for 4.5 metre = a+b+c+d+e 16073.62
Rate per metre = (a+b+c+d+e)/4.5 3571.91
say 3572.00
3572.00
Ref.
to
Cost Remarks/ Input
Sr No MoRT Description Unit Quantity Rate Rs
Rs ref.
H
Spec.
8.23 B Type - B, "THRIE" : Metal Beam Crash Barrier

Providing and erecting a "Thrie" metal beam crash barrier comprising


of 3 mm thick corrugated sheet metal beam rail, 85 cm above
road/ground level, fixed on ISMC series channel vertical post, 150 x
75 x 5 mm spaced 2 m centre to centre, 2 m high with 1.15 m below
ground level, all steel parts and fitments to be galvanised by hot dip
process, all fittings to conform to IS:1367 and IS:1364, metal beam
rail to be fixed on the vertical post with a space of channel section
150 x 75 x 5 mm, 546 mm long complete as per clause 810

Unit = Running metre


Taking output = 4.5 metre length
a) Labour
Mate day 0.060 329.34 19.76 L-12
Blacksmith day 0.500 352.86 176.43 L-02
Mazdoor day 1.000 152.91 152.91 L-13
b) Machinery
Tractor-trolley hour 0.100 379.91 37.99 P&M-053
c) Material
Corrugated sheet,3 mm thick, "Thrie" beam section railing,4.5 m 98.80 7206.53 M-095
kg 72.940
in length
Channel post 150 x 75 x 5 mm, 2 m long,3 Nos @ 16.4 kg per 60.000 5904.00 M-185 /1000
kg 98.400
metre
Spacer 150 x 75 x 5 mm channel 0.546 m long,3 Nos kg 26.860 60.000 1611.60 M-185 /1000
Nuts and bolts kg 30.000 87.69 2630.57 M-136
Add 15 per cent of the cost of material for fabrication, nuts, bolts
2602.91
and washers etc.)
d) Overhead charges @ 8% on (a+b+c) 1627.42
e) Contractor's profit @ 10% on (a+b+c+d) 2197.01
Cost for 4.5 metre = a+b+c+d+e 24167.12
Rate per metre= (a+b+c+d+e)/4.5 5370.47
say 5370.00
5370.00
In the case of median crash barrier, 'W' metal beam or thrie beam
section should be provided on both sides of the vertical posts fixed in
Note the median. Extra provision for metal beam railing and spacer is
required to be made when fixed in the median depending on
approved design.
Ref.
to
Cost Remarks/ Input
Sr No MoRT Description Unit Quantity Rate Rs
Rs ref.
H
Spec.

Sugge
8.27 Street Lighting
stive
Providing and erecting street light mounted on a steel circular hollow
pole of standard specifications for street lighting, 9 m high spaced 40
m apart, 1.8 m overhang on both sides if fixed in the median and on
one side if fixed on the footpath, fitted with sodium vapour lamp and
fixed firmly in concrete foundation.
Unit = Each
Taking output = one light
a) Labour
Mate day 0.030 329.34 9.88 L-12
Mazdoor day 0.500 152.91 76.45 L-13
Electrician day 0.250 352.86 88.22 L-02
b) Material
i) Steel circular hollow pole of standard specification for street 11762.00 11762.00 M-177
each 1.000
lighting to mount light at 9 m height above road level
ii) Sodium vapour lamp each 1.000 11115.09 11115.09 M-174
Add 5 per cent of cost of material for holder, electric cable,
1143.85
insulation, ladder, scaffolding etc
c) Painting
For Fixing in Median
Providing two coats of alluminium paint over steel circular hollow 52.00 299.00 Item 8.9
sqm 5.750
pipe with overhang on both sides
For fixing in Footpath
Providing two coats of alluminium paint over steel circular hollow 52.00 240.76 Item 8.9
sqm 4.630
pipe with overhang on one side
(i) For Fixing in Median
d) Overhead charges @ 8% on (a+b) 1935.64
e) Contractor's profit @ 10% on (a+b+d) 2613.11
Rate per light for fixing in Median= a+b+c+d+e 29043.25
say 29043.00
(ii) For fixing in Footpath
Rate per light for Fixing in Footpath = a+b+c+d+e 28985.01
say 28985.00
28985.00
The items of excavation and cement concrete foundation will be
measured and included separately in the estimate as per approved
Note
design and drawing. The rate for painting has been analysed in this
chapter.
Ref.
to
Cost Remarks/ Input
Sr No MoRT Description Unit Quantity Rate Rs
Rs ref.
H
Spec.
Sugge
8.29 Cable Duct Across the Road
stive
Providing and laying of a reinforced cement concrete pipe duct, 300
mm dia, across the road (new construction), extending from drain to
drain in cuts and toe of slope to toe of slope in fills, constructing head
walls at both ends, providing a minimum fill of granular material over
top and sides of RCC pipe as per IRC:98-1997, bedded on a 0.3 m
thick layer of granular material free of rock pieces, outer to outer
distance of pipe at least half dia of pipe subject to minimum 450 mm
in case of double and triple row ducts, joints to be made leak proof,
invert level of duct to be above higher than ground level to prevent
entry of water and dirt, all as per IRC: 98 - 1997 and approved
drawings.
8.29 Case(ii) Double row for two utility services
Unit = Running metre
Taking output = 20metres
a) Random Rubble brick/Brick masonry in cement mortar Item 12.7 ( B)
cum 3.370 4391.00 14797.67
1:6 for head wall both sides.
b) Labour
Mate day 0.050 329.34 16.47 L-12
Mazdoor day 2.000 152.91 305.81 L-13
Mazdoor skilled day 0.250 244.65 61.16 L-15
c) Material
Reinforced Cement Concrete pipe 300 mm dia metre 40.000 620.73 24829.11 M-156
Granular soil with PI less than 6 for bedding and sides of pipe 978.88 14095.88 M-009
cum 14.400
(0.6 x 0.6 x 40 m)
Collar for joints 300 mm dia each 18.000 691.61 12448.90 M-090
Cement mortar 1:2 for joints cum 0.040 7256.00 290.24 Item 12.6 (B)
d) Machinery
Tractor-trolley hour 1.000 379.91 379.91 P&M-053
e) Overhead charges @ 8% on (b+c+d) 4194.20
f) Contractor's profit @ 10% on (b+c+d+e) 5662.17
Cost for 20 metre = a+b+c+d+e+f 77081.53
Rate per metre = (a+b+c+d+e+f)/20 3854.08
say 3854.00
3854.00
1.Inspection chamber at both ends is the responsibility of the agency
Note
who is laying the duct. Hence not included.
2.The rates for stone masonry / brick masonry and cement mortar to
be adopted from respective clauses.
Sugge
8.30 Highway Patrolling and Traffic Aid Post
stive
It is proposed to locate one Traffic Aid Post every 50-60 km of the
highway.
The organisation and financial aspect are required to be finalised in
consultation with administrative and traffic authorities .
Sugge Items Related to Underpass/ Subway/ Overhead Bridge/
8.31
stive Overhead Foot Bridge
The items involved for underpass/ subway/ overhead bridge/
overhead foot bridge are earthwork, plain cement concrete,
plastering, painting, information sign etc. The rates for these items
are available in respective chapters which can be adopted for the
quantities derived from the approved designs and drawings
Ref.
to
Cost Remarks/ Input
Sr No MoRT Description Unit Quantity Rate Rs
Rs ref.
H
Spec.

Sugge
8.32 Traffic Control System and Communication System
stive
Providing a traffic control centre and communication system including
telecommunication facilities and related accessories, CCTV, radar,
vehicle detection camera, central computer system
These are specialised item of telecommunication system and are the
commercial products. The designer is required to contact the
manufacturers to ascertain market prices. In case of civil works
required to be executed for these installations, pricing may be done
as per rates in relevant chapters for quantities derived as per
approved design and drawing.
As regards the locations where such devices are required to be
installed, the traffic control authority should be consulted to finalise
the location
Sugge
8.33 Gantry Mounted Variable Message Sign Board
stive
Providing and erecting gantry mounted variable message sign board
electronically operated capable of flashing the desired message over
a designed support system of aluminium alloy or galvanised steel,
erected as per approved design and drawings and with lateral
clearance as per clause 802.3
(i) Gantry Support System
Unit = tonne
Taking output=1 tonne
a) Labour
Mate day 0.120 329.34 39.52 L-12
Mazdoor day 2.000 152.91 305.81 L-13
Blacksmith day 1.000 352.86 352.86 L-02
b) Material
96330.78 101147.32 M-060
Alluminium alloy/galvanised steel including 5 per cent wastage tonne 1.050

Add 15 per cent of cost of material for fabrication and erection. 15172.10

Add 1 per cent of cost of material for nuts, bolts and welding 1011.47
c) Machinery
Truck 10 tonne hour 1.000 517.53 517.53 P&M-057
d) Overhead charges @ 8% on (a+b+c) 9483.73
e) Contractor's profit @ 10% on (a+b+c+d) 12803.03
Rate per tonne = a+b+c+d+e 140833.37
say 140833.00
140833.00
Ref.
to
Cost Remarks/ Input
Sr No MoRT Description Unit Quantity Rate Rs
Rs ref.
H
Spec.
8.33 (ii) Message Display

Message display board 6 sqm electronically operated with complete


electronic fitments for flashing the pre-determined messages.

This is a specilised commercial product and the lumpsum rate


including erection at site is required to be as certained from the
market and including in the rate analysis. The size of the board will
vary depending upon specific location.
The rate for the gantry mounted variable sign would be the addition
of cost of gantry support system as per approved design determined
at (i) above and the cost of message display board as certained from
the market at (ii) above

Sugge
8.34 Traffic Impact Attenuators at Abutments and Piers
stive
A With Scrap Tyres
Provision and installation of traffic attenuators at abutment/pier of
flyovers bridges using scrap tyres of size 100 x 20 retrieved from
trucks laid in 2 rows and 4 tiers, one above the other and tied with 20
mm wire rope as per approved design and drawings.
Unit = sqm
Taking output = 20sqm
a) Labour
Mate day 0.080 329.34 26.35 L-12
Mazdoor day 1.500 152.91 229.36 L-13
Blacksmith day 0.250 352.86 88.22 L-02
b) Material
Scrap tyres of size 900 x 20 each 80.000 49.40 3952.03 M-166
20 mm steel wire rope kg 150.000 155.26 23288.76 M-182
Add 1 per cent of cost of wire rope for clamps etc. 232.89
c) Machinery
Tractor-trolley hour 3.000 379.91 1139.74 P&M-053
d) Overhead charges @ 8% on (a+b+c) 2316.59
e) Contractor's profit @ 10% on (a+b+c+d) 3127.39
Cost for 20 sqm = a+b+c+d+e 34401.32
Rate per sqm = (a+b+c+d+e)/20 1720.07
say 1720.00
1720.00
Ref.
to
Cost Remarks/ Input
Sr No MoRT Description Unit Quantity Rate Rs
Rs ref.
H
Spec.
8.34 B Using Plastic/Steel Barrel, Filled with Sand
Provision and installation of traffic impact attenuator at abutment/pier
of flyovers bridges using plastic/steel barrels 0.60 m dia and 1.0 m in
height, filled with sand in three rows and tied with20 mm steel wire
rope as per approved design and drawings
Unit = sqm
Taking output = 20sqm
a) Labour
Mate day 0.130 329.34 42.81 L-12
Mazdoor day 3.000 152.91 458.72 L-13
Blacksmith day 0.250 352.86 88.22 L-02
b) Material
Plastic barrels each 50.000
or
Steel barrels each 50.000 72.92 3646.22 M-178
Sand cum 8.000 1176.20 9409.60 M-004
20 mm steel wire rope kg 15.000 155.26 2328.88 M-182
Add 1 per cent of cost of wire rope for clamps etc. 23.29
c) Machinery
Tractor-trolley hour 2.000 379.91 759.83 P&M-053
d) Overhead charges @ 8% on (a+b+c) 1340.60
e) Contractor's profit @ 10% on (a+b+c+d) 1809.82
Cost for 20 sqm = a+b+c+d+e 19907.98
Rate per sqm = (a+b+c+d+e)/20 995.40
say 995.00
995.00
8.34 C With HI - DRO cell Sandwich (Patented)
(In this patented HI - DRO cell system, water gets discharged from
plastic tubes on impact over a pre-determined time, thus absorbing
the energy)
Providing and installing a patentend HI - DRO cell system as a traffic
impact attenuators, using plastic tubes 50 cm dia, 1.2 m in height, 25
mm opening at the top, placed in three rows, filled with water and
tied with a 20 mm steel wire rope
Unit = sqm
Taking output = 10sqm
a) Labour
Mate day 0.100 329.34 32.93 L-12
Mazdoor day 2.500 152.91 382.27 L-13
b) Material
Plastic tubes 50 cm dia,1.2 m high each 40.000 92.63 3705.03 M-145
Cost of water KL 12.000 55.58 666.91 M-195
20 mm steel wire rope kg 100.000 155.26 15525.84 M-182
Add 1 per cent of cost of wire rope for clamps etc. 155.26
c) Machinery
Tractor-trolley hour 2.000 379.91 759.83 P&M-053
Water tanker6 KL capacity hour 2.000 517.53 1035.06 P&M-060
d) Overhead charges @ 8% on (a+b+c) 1781.05
e) Contractor's profit @ 10% on (a+b+c+d) 2404.42
Cost for 10 sqm = a+b+c+d+e 26448.58
Rate per sqm = (a+b+c+d+e)/10 2644.86
say 2645.00
2645.00
Ref.
to
Cost Remarks/ Input
Sr No MoRT Description Unit Quantity Rate Rs
Rs ref.
H
Spec.

Sugge
8.35 Road Markers/Road Stud with Lense Reflector
stive

Providing and fixing of road stud 100x 100 mm, die-cast in


aluminium, resistant to corrosive effect of salt and grit, fitted with
lense reflectors, installed in concrete or asphaltic surface by drilling
hole 30 mm upto a depth of 60 mm and bedded in a suitable
bituminous grout or epoxy mortar, all as per BS 873 part 4:1973
Unit = Nos
Taking output = 50Nos
a) Labour
Mate day 0.040 329.34 13.17 L-12
Mazdoor day 1.000 152.91 152.91 L-13
b) Material
Aluminium studs 100 x 100 mm fitted with lense reflectors each 50.000 515.18 25758.78 M-062
Add 10 per cent of cost of material for fixing and installation 2575.88
c) Overhead charges @ 8% on (a+b) 2280.06
d) Contractor's profit @ 10% on (a+b+c) 3078.08
Cost for 50 studs = a+b+c+d 33858.88
Rate per studs = (a+b+c+d)/50 677.18
say 677.00
677.00
Sugge
8.36 Traffic Cone
stive
Provision of red fluorescent with white reflective sleeve traffic cone
made of low density polyethylene (LDPE) material with a square
base of 390 x 390 x 35 mm and a height of 770 mm, 4 kg in weight,
placed at 1.5 m interval, all as per BS 873
Unit = Running metre
Taking output = 68 Nos.
a) Labour
Mate day 0.020 329.34 6.59 L-12
Mazdoor day 0.500 152.91 76.45 L-13
b) Material
Traffic cones with 150 mm reflective sleeve each 68.000 1852.52 125971.02 M-192
c) Machinery
Tractor-trolley hour 0.100 379.91 37.99 P&M-053
d) Overhead charges @ 8% on (a+b+c) 10087.36
e) Contractor's profit @ 10% on (a+b+c+d) 13617.94
Cost for 68 Nos. = a+b+c+d+e 149797.36
Rate per metre = (a+b+c+d+e)/68 2202.90
say 2203.00
2203.00
Ref.
to
Cost Remarks/ Input
Sr No MoRT Description Unit Quantity Rate Rs
Rs ref.
H
Spec.

Sugge
8.37 Roadside Amenities
stive
A Rest areas
Providing plainly furnished accommodation for rest rooms,
dormitories, restaurants, stalls, shops, petrol pump, telephone booth,
first aid room, traffic aid post, police assistance booth, including
electricity, toilet and sewerage system
Pricing may be done based on current plinth area rates approved by
PWD/CPWD/MES for a particular zone. Area is required to be
assessed for specific location as per actual site conditions
Parking areas and bus laybyes for trucks, buses and light
B
vehicles
Pricing of parking areas may be done for the quantities of various
items based on the approved dimensions and pavement design for a
particular terrain and soil. Rates for items may be from respective
chapters.
C Lawn
Providing a lawn planted with grass and its maintenance
Pricing of lawn may be done as per rates given in the chapter on
horticulture for the quantities as per approved dimensions in the
drawings
Sugge
8.38 Rumble Strips
stive
Provision of 15 nos rumble strips covered with premix bituminous
carpet, 15-20 mm high at center, 250 mm wide placed at 1 m center
to center at approved locations to control speed, marked with white
strips of road marking paint.
Unit = sqm
Taking output = 100 sqm (including gaps)
The rate per sqm of premix carpet and road marking may be adopted
from chapter 5 & 8 respectively for the quantities calculated from
approved drawings
Ref.
to
Cost Remarks/ Input
Sr No MoRT Description Unit Quantity Rate Rs
Rs ref.
H
Spec.

Sugge
8.39 Policeman Umbrella
stive
Provision of a 2 m high (floor to roof) umbrella for traffic policeman at
road crossings, where necessary, installed on a raised platform, built
on a central support of a steel pipe 100 mm dia, roof made of 25 mm
dia steel pipe to provide covered area of 3 sqm, roofed with CGI
sheets, all steel parts to be given 2 coats of paint
Unit = each
Taking output = one number
Earthwork cum
Cement Concrete cum
brick masonry or cum
stone masonry cum
Painting sqm 2.500
a) Labour
Mate day 0.090
Mazdoor day 1.000
Blacksmith day 1.000
Welder day 0.250
b) Material
Steel pipe 100 mm dia metre 3.500
Steel pipe 25 mm dia metre 10.000
CGI sheets kg 8.000
Add 25 per cent of cost of material for fabrication
Add 2 per cent of cost of material for welding consumables, J-
hooks, washers etc.
c) Machinery
Tractor-trolley hour 0.500
d) Overheads @ per cent on (a+b+c)
e) Contractors Profit@ per cent on (a+b+c+d)
Rate per policeman umbrella = a+b+c+d+e

sugge
8.40 High Mast Pole Lighting at Interchanges and Flyovers
stive

Providing and erecting a high mast pole lighting with 30 m high hot
dip galvanised mast designed to withstand forces exerted with wind
speeds of 180 km per hour with 3 seconds gust, as per IS:875 (Part
3) - 1978, fitted with a base flange, door at the base of mast with
heavy duty internal lock, lantern carriage, suitable winching
arrangement for safe working load of 750 kg and high powered
electrically driven power tools for raising and lowering of lantern
carriage, flexible 8 core electric cable, lightening conductor, earthing
terminal, and fixing 2 nos aviation obstruction lights on top of the
mast, all complete as per approved design and drawings

This is a specialised work and is generally done by firms who


specialise in such jobs. The detailed designs and estimates are
submitted by the firms along with their tender for checks by the
Department. The cost of this work is required to be worked out based
on approved design, drawings and estimate of the lowest tender. A
separate contract for this work is concluded as the contractors for
road and bridge works generally donot undertake such jobs.
Ref.
to
Cost Remarks/ Input
Sr No MoRT Description Unit Quantity Rate Rs
Rs ref.
H
Spec.
8.41 Toll Plaza
The construction, operation and maintenance of Toll Plaza can be
broken into separate items of work as under based on the approved
design and drawings:-
a) Provision of toll collection service lane to separate different
categories of vehicles for purpose of toll collection. This involves
considerable increase in carriage way width
b) Provision of 2.5 m wide separators for different toll collection
service lanes for safety
c) Toll booths with integrated roof cover
d) Barrier gates for individual lanes
e) Provision of building to provide facility to toll plaza personnel

f) Toll plaza office equipment and furniture


g) Water supply, electricity, sanitation, septic-tank system and
drainage
h) Telephone, intercomes, wireless communication system
i) High mast lighting
j) Pavement marking
k) Overhead signs
l) Fixed message signs (Advance)
m) Variable message signs
n) Traffic cones and pylons
o) First aid post
p) Traffic aid post and security
The quantities for the above mentioned items may be calculated from
the approved design and drawings and their rates adopted from
respective chapters of the Standard Data Book
8.42 Safety Devices and Signs in Construction Zones
Provision and fixing of traffic signs for limited period at suitable
locations in construction zone comprising of warning zone, approach
transition zone, working zone and terminal transition zone with a
minimum distance of 60 cm from the edge of the kerb in case of
kerbed roads and 2 to 3 m from the edge of the carriageway in case
of un-kerbed roads, the bottom edge of the lowest sign plate to be
not less than 2 m above the road level, fixed on 60 mm x 60 mm x 6
mm angle iron post, founded and installed as per approved design
and drawings, removed and disposed of after completion of
construction work, all as per IRC:SP:55-2001
Unit = each
Taking output = one sign post
Following types of signs are required to be fixed in construction
zones for safety of traffic
a) Diversion one km ahead
b) Traffic sign ahead
c) Road ahead closed
d) Men at work
e) Road narrow
f) Single file traffic
g) Right lane diverted
h) Left lane diverted
i) Right lane closed
j) Left lane closed
Ref.
to
Cost Remarks/ Input
Sr No MoRT Description Unit Quantity Rate Rs
Rs ref.
H
Spec.

k) Median closed
l) Diversion to other carriageway
m) Traffic signal ahead
n) Two way traffic
o) Un - even road
p) Slippery road
q) Loose chippings
r) Dual carriageway ends
s) Diversion
t) Do not enter
u) Road closed
v) Stop
w) Slow
x) One way
y) Give way
z) Overtaking prohibited
aa) Speed limit
bb) Weight limit
cc) Height and length limit
dd) No stopping or standing
ee) Any other warning or regulatory safety sign as per site
requirement and consistent with IRC:SP:55-2001 and IRC:67
The rate for traffic signs are already worked out and given elsewhere
in this chapter. The same may be adopted.

sugge
8.43 Portable Barricade in Construction Zone
stive
Installation of a steel portable barricade with horizontal rail 300 mm
wide, 2.5 m in length fitted on a 'A' frame made with 45 x 45 x 5 mm
angle iron section, 1.5 m in height, horizontal rail painted (2 coats)
with yellow and white stripes, 150 mm in width at an angle of 450 C,
'A' frame painted with 2 coats of yellow paint, complete as per
IRC:SP:55-2001
Unit = each
Taking output = one steel portable barricade
a) Labour
Mate day 0.020 329.34 6.59 L-12
Mazdoor day 0.250 152.91 38.23 L-13
Painter day 0.500 352.86 176.43 L-18
Welder day 0.250 352.86 88.22 L-02
b) Material
Angle iron 45 x 45 x 5 mm kg 25.000 60.000 1500.00 M-185 /1000
MS sheet 300 mm wide,2.5 m long and 2.6 mm thick kg 15.000 60.000 900.00 M-185 /1000
Paint litre 0.500 185.25 92.63 M-137
Add 2 per cent of cost of steel for welding consumables, nuts &
48.00
bolts and drilling holes
c) Overhead charges @ 8% on (a+b) 228.01
d) Contractor's profit @ 10% on (a+b+c) 307.81
Rate per barricade = a+b+c+d 3385.90
say 3386.00
3386.00
Ref.
to
Cost Remarks/ Input
Sr No MoRT Description Unit Quantity Rate Rs
Rs ref.
H
Spec.

sugge
8.44 Permanent Type Barricade in Construction Zone
stive
A With steel components
Construction of a permanent type barricade made of steel
components, 1.5 m high from road level, fitted with 3 horizontal rails
200 mm wide and 4 m long on 50 x 50 x 5 mm angle iron vertical
support, painted with yellow and white strips, 150 mm in width at an
0
angle of 45 C, complete as per IRC:SP:55-2001
Unit = each
Taking output = one barricade
a) Labour
Mate day 0.050 329.34 16.47 L-12
Mazdoor day 0.300 152.91 45.87 L-13
Painter day 0.600 352.86 211.72 L-18
Welder day 0.300 352.86 105.86 L-02
b) Material
Angle iron 50 x 50 x 5 mm,2 m long,2 Nos. kg 15.000 60.000 900.00 M-185 /1000

MS sheet of 12 SWG,3 Nos of 200 mm width and 4 m length kg 50.000 60.000 3000.00 M-185 /1000
Paint litre 1.000 185.25 185.25 M-137
Add 1 per cent of cost of steel for welding consumables, nuts & bolts
39.00
and drilling holes
c) Overhead charges @ 8% on (a+b) 360.33
d) Contractor's profit @ 10% on (a+b+c) 486.45
Rate per barricade = a+b+c+d 5350.95
say 5351.00
5351.00
8.44 B With wooden components
Construction of a permanent type barricade made of wooden
components, 1.5 m high from road level, fitted with 3 horizontal
planks 200 mm wide and 3.66 m long on 100 x 100mm wooden
vertical post, painted with yellow and white strips, 150 mm in width at
an angle of 450 C, complete as per IRC:SP:55-2001
Unit = each
Taking output = one barricade
a) Labour
Mate day 0.050 329.34 16.47 L-12
Mazdoor day 0.300 152.91 45.87 L-13
Painter day 0.600 352.86 211.72 L-18
Carpenter day 0.600 352.86 211.72 L-04
b) Material
Timber cum 0.180 31346.67 5642.40 M-191
Add 1 per cent of cost of timber for nuts & bolts, nails, etc. 56.42
c) Overhead charges @ 8% on (a+b) 494.77
d) Contractor's profit @ 10% on (a+b+c) 667.94
Rate per barricade = a+b+c+d 7347.30
say 7347.00
7347.00
Ref.
to
Cost Remarks/ Input
Sr No MoRT Description Unit Quantity Rate Rs
Rs ref.
H
Spec.
8.44 C With bricks
Construction of a permanent type barricade made with brick work in
mud mortar, 1.5 m high, 4 m long, 600 mm thick, plastered with
cement mortar 1:6, painted with yellow and white strips
Unit = each
Taking output = one barricade
a) Labour
Mate day 0.240 329.34 79.04 L-12
Mazdoor day 3.000 152.91 458.72 L-13
Painter day 1.000 352.86 352.86 L-18
Mason day 2.000 352.86 705.72 L-11
b) Material
Brick each 1800.000 8.23 14820.12 M-084
Cement kg 22.000 8.939 196.66 M-086 /1000
Sand cum 0.090 1176.20 105.86 M-005
Paint litre 1.250 185.25 231.56 M-137
c) Overhead charges @ 8% on (a+b) 1356.04
d) Contractor's profit @ 10% on (a+b+c) 1830.66
Rate per barricade = a+b+c+d 20137.24
say 20137.00
20137.00
Ref.
to
Cost Remarks/ Input
Sr No MoRT Description Unit Quantity Rate Rs
Rs ref.
H
Spec.
Non-
Utility Duct
Sch
Unit = Running metre
Taking output = 20metres
b) Labour
Mate day 0.050 0.00 0.00 L-12
Mazdoor day 1.000 0.00 0.00 L-13
Mazdoor skilled day 0.250 0.00 0.00 L-15
c) Material
HDPE pipe 90 mm dia metre 60.000 231.00 13860.00 M-156
Granular soil with PI less than 6 for bedding and sides of pipe 0.00 0.00 M-009
cum
(0.6 x 0.6 x 20 m)
Collar for joints 300 mm dia each 0.000 0.00 0.00 M-090
Cement mortar 1:2 for joints cum 0.000 7256.00 0.00 Item 12.6 (B)
d) Machinery
Tractor-trolley hour 0.500 379.91 189.96 P&M-053
e) Overhead charges @ 8% on (b+c+d) 1124.00
f) Contractor's profit @ 10% on (b+c+d+e) 1517.40
Cost for 20 metre = a+b+c+d+e+f 16691.35
Rate per metre = (a+b+c+d+e+f)/20 834.57
say 835.00
835.00
CHAPTER-9
PIPE CULVERTS
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
9.1 408 PCC 1:3:6 in Foundation
Plain cement concrete 1:3:6 mix with crushed stone
aggregate 40 mm nominal size mechanically mixed, placed
in foundation and compacted by vibration including curing for
14 days.
Unit = cum
Taking output = 15 cum
a) Labour
Mate day 0.640 329.34 210.78 L-12
Mason day 1.000 352.86 352.86 L-11
Mazdoor day 15.000 152.91 2293.59 L-13
b) Material
40mm Aggregate at site cum 13.800 1411.44 19477.87 M-055
Sand at site cum 6.900 1176.20 8115.78 M-005
Cement at site tonne 3.300 8939.12 29499.10 M-086
Cost of water KL 18.000 55.58 1000.36 M-195
c) Machinery
Concrete mixer0.4/ 0.28 cum hour 6.000 237.59 1425.55 P&M-009
Generator set 33 KVA hour 6.000 365.80 2194.79 P&M-079
Water tanker6 KL capacity hour 3.000 517.53 1552.58 P&M-060
d) Overhead charges @ 8% on (a+b+c) 5289.86
e) Contractor's profit @ 10% on (a+b+c+d) 7141.31
Cost for 15 cum = a+b+c+d+e 78554.43
Rate per cum = (a+b+c+d+e)/15 5236.96
say 5237.00
5237.00
Note Vibrator is a part of minor T & P which is already included in
overhead charges of the contractor.
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
9.2 2900 Laying Reinforced Cement Concrete Pipe NP4 /
Prestressed Concrete Pipe on First Class Bedding in
Single Row .
Laying Reinforced cement concrete pipe NP4/prestressed
concrete pipe for culverts on first class bedding of granular
material in single row including fixing collar with cement
mortar 1:2 but excluding excavation, protection works,
backfilling, concrete and masonry works in head walls and
parapets .
Unit = metre
Taking output = 12.5 metres ( 5 pipes of 2.5 m length
each )
A 1000 mm dia
a) Labour
Mate day 0.180 329.34 59.28 L-12
Mason day 0.500 352.86 176.43 L-11
Mazdoor day 4.000 152.91 611.62 L-13
b) Material
Sand at site cum 0.070 1176.20 82.33 M-005
Cement at site tonne 0.050 8939.12 446.96 M-086
RCC pipe NP-4 /prestressed concrete pipe including metre 12.500 6275.03 78437.84 M-154
collar at site
Granular material passing 5.6 mm sieve for bedding cum 4.500 978.88 4404.96 M-009
c) Overhead charges @ 8% on (a+b) 6737.55
d) Contractor's profit @ 10% on (a+b+c) 9095.70
Cost for 12.5 metres = a+b+c+d 100052.68
Rate per metre = (a+b+c+d)/12.5 8004.21
say 8004.00
8004.00
Note 1. In case of cement craddle bedding, quantity of PCC M15 is
to be calculated as per design and priced separately and
added .
2. The rate analysis does not include excavation, cement
/masonry works in head walls, backfilling, protection works
and parapet walls. The same are to be calculated as per
approved design and drawings and priced separately on
rates available under respective sections
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
9.2 B 1200 mm dia
a) Labour
Mate day 0.280 329.34 92.21 L-12
Mason day 1.000 352.86 352.86 L-11
Mazdoor day 6.000 152.91 917.44 L-13
b) Material
Sand at site cum 0.090 1176.20 105.86 M-005
Cement at site tonne 0.070 8939.12 625.74 M-086
RCC pipe NP-4/prestressed concrete pipe including metre 12.500 10374.08 129676.05 M-155
collar at site
Granular material passing 5-6 mm sieve for class cum 5.000 978.88 4894.40 M-009
bedding
c) Overhead charges @ 8% on (a+b) 10933.16
d) Contractor's profit @ 10% on (a+b+c) 14759.77
Cost for 12.5 metres = a+b+c+d 162357.50
Rate per metre= (a+b+c+d)/12.5 12988.60
say 12989.00
12989.00
Note 1. In case of cement craddle bedding, quantity of PCC M15 is
to be calculated as per design and priced separately and
added .
2. The rate analysis does not include excavation, cement
/masonry works in head walls, backfilling, protection works
and parapet walls. The same are to be calculated as per
approved design and drawings and priced separately on
rates available under respective sections
9.3 2900 Laying Reinforced Cement Concrete Pipe NP4 /
Prestressed Concrete Pipe on First Class Bedding in
Double Row .
Laying Reinforced cement concrete pipe NP4 / prestressed
concrete pipe for culverts on first class bedding of granular
material in double row including fixing collar with cement
mortar 1:2 but excluding excavation, protection works,
backfilling, concrete and masonry works in head walls and
parapets .
Unit = metre
Taking output = 12.5 metres ( 10 pipes of 2.5 m length
each in two rows.)
A 1000 mm dia
a) Labour
Mate day 0.360 329.34 118.56 L-12
Mason day 1.000 352.86 352.86 L-11
Mazdoor day 8.000 152.91 1223.25 L-13
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
b) Material
Sand at site cum 0.140 1176.20 164.67 M-005
Cement at site tonne 0.100 8939.12 893.91 M-086
RCC pipe NP-4/prestressed concrete pipe including metre 25.000 6275.03 156875.68 M-154
collar at site
Granular material passing 5.6 mm sieve for bedding cum 12.500 978.88 12236.01 M-009
c) Overhead charges @ 8% on (a+b) 13749.19
d) Contractor's profit @ 10% on (a+b+c) 18561.41
Cost for 12.5 metres = a+b+c+d 204175.54
Rate per metre = (a+b+c+d)/12.5 16334.04
Note 1. In case of cement craddle bedding, quantity of PCC M15 is say 16334.00
to be calculated as per design and priced separately and
added .
16334.00
2. The rate analysis does not include excavation, cement
/masonry works in head walls, backfilling, protection works
and parapet walls. The same are to be calculated as per
approved design and drawings and priced separately on
rates available under respective sections
9.3 B 1200 mm dia
a) Labour
Mate day 0.560 329.34 184.43 L-12
Mason day 2.000 352.86 705.72 L-11
Mazdoor day 12.000 152.91 1834.87 L-13
b) Material
Sand at site cum 0.180 1176.20 211.72 M-005
Cement at site tonne 0.140 8939.12 1251.48 M-086
RCC pipe NP-4 /prestressed concrete pipe including metre 25.000 10374.08 259352.10 M-155
collar at site
Granular material passing 5-6 mm sieve for class cum 13.750 978.88 13459.61 M-009
bedding
c) Overhead charges @ 8% on (a+b) 22159.99
d) Contractor's profit @ 10% on (a+b+c) 29915.99
Cost for 12.5 metres = a+b+c+d 329075.91
Rate per metre= (a+b+c+d)/12.5 26326.07
Note 1. In case of cement craddle bedding, quantity of PCC M15 is say 26326.00
to be calculated as per design and priced separately and
added .
26326.00
2. The rate analysis does not include excavation, cement
/masonry works in head walls, backfilling, protection works
and parapet walls. The same are to be calculated as per
approved design and drawings and priced separately on
rates available under respective sections
CHAPTER- 10
MAINTENANCE OF ROADS
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
10.1 3002 Restoration of Rain Cuts
Restoration of rain cuts with soil, moorum, gravel or a
mixture of these, clearing the loose soil, benching for 300
mm width, laying fresh material in layers not exceeding 250
mm and compacting with plate compactor or power rammers
to restore the original alignment, levels and slopes
Unit = cum
Taking output = 10 cum
a) Labour
Mate day 0.080 329.34 26.35 L-12
Mazdoor day 2.000 152.91 305.81 L-13
b) Machinery
Excavator1.0 cum bucket capacity @ 60 cum per hour hour 0.130 1621.98 210.86 P&M-026
Tipper ( L is average lead in km for borrow earth) tonne.km 12 x L 4.12 148.20 Lead =3 km &
P&M-058
Add 10 per cent of cost of carriage towards loading and 14.82
unloading charges.
Plate compactor hour 0.500 256.41 128.21 P&M-086
c) Overhead charges @ 8% on (a+b) 66.74
d) Contractor's profit @ 10% on (a+b+c) 90.10
Cost for 10 cum = a+b+c+d 991.08
Rate per cum = (a+b+c+d)/10 99.11
say 99.00
Note Only 75 per cent of fresh material has been provided as 25
per cent can be retrieved at site from earth that is flown
down the slope in the form of slurry and deposited at the foot
of the rain cuts
10.3 3003 Maintenance of Earth Shoulder (stripping excess soil)

Stripping excess soil from the shoulder surface to achieve


the approved level and compacting with plate compactor
Unit = sqm
Taking output = 100 sqm
Assuming average depth of stripping as 75 mm
Quantity of earth cutting involved = 7.5 cum
a) Labour
Mate day 0.100 329.34 32.93 L-12
Mazdoor day 2.500 152.91 382.27 L-13
b) Machinery
Plate compactor @ 25 sqm per hour hour 4.000 256.41 1025.65 P&M-086
c) Overhead charges @ 8% on (a+b) 115.27
d) Contractor's profit @ 10% on (a+b+c) 155.61
Cost for 100 sqm = a+b+c+d 1711.72
Rate per sqm on = (a+b+c+d)100 17.12
say 17.00
Note The earth stripped from earthen shoulders to be dumped on
the side slopes locally for disposal.
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
10.4 3004.2 Filling Pot-holes and Patch Repairs with open-Graded
Premix surfacing, 20mm.
Removal of all failed material, trimming of completed
excavation to provide firm vertical faces, cleaning of surface,
painting of tack coat on the sides and base of excavation as
per clause 503, back filling the pot holes with hot bituminous
material as per clause 511, compacting, trimming and
finishing the surface to form a smooth continuous surface, all
as per clause 3004.2
Unit = Sqm
Taking out put = 10250 sqm (205 cum)(405 tonne)
a) Labour
Mate Day 3.760 329.34 1238.30 L-12
Mazdoor Day 90.000 152.91 13761.54 L-13
Mazdoor skilled Day 4.000 244.65 978.60 L-15
b) Machinery
Air compressor 250 cfm hour 6.000 334.04 2004.24 P&M-001
HMP 100-110 TPH Capacity hour 6.000 19495.52 116973.09 P&M-022
Tipper 10 tonnes capacity hour 45.000 491.65 22124.32 P&M-048
Smooth wheeled roller 8-10 tonnes hour 12.000 676.32 8115.78 P&M-044
c) Material
Crushed stone aggregates nominal size 13.2mm @ 0.18 cum 184.500 1587.87 292962.02 M-052
cum per 10 sqm
Crushed stone aggregates nominal size 11.2mm @ 0.09 cum 92.250 1529.06 141055.79 M-051
cum/10 sqm
Bitumen 80/100 @ 14.6 kg per 10 sqm tonne 14.970 40000.00 598800.00 M-074
Bitumen emulsion for tack coat including vertical sides tonne 2.460 33000.00 81180.00 M-076
of pot hole.
d) Overhead charges @ 8% on (a+b+c) 102335.49
e) Contractor's profit @ 10% on (a+b+c+d) 138152.92
Cost for 10250 sqm = a+b+c+d+e 1519682.09
Rate per sqm = (a+b+c+d+e)/10250 148.26
say 148.00
149.00
CHAPTER-11
HORTICULTURE
Ref. to
MoRT Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
H Input ref.
Spec.
11.1 307 Spreading of Sludge Farm Yard Manure or/and good
Earth
Spreading of sludge farm yard manure or/ and good earth in
required thickness (cost of sludge, farm yard manure or/and
good earth to be paid for separately)
Unit = cum
Taking output = 15 cum
a) Labour
Mate day 0.040 329.34 13.17 L-12
Mazdoor day 1.000 152.91 152.91 L-13
b) Overhead charges @ 8% on (a) 13.29
c) Contractor's profit @ 10% on (a+b) 17.94
Cost for 15 cum= a+b+c 197.30
Rate per cum = (a+b+c)/15 13.15
say 13.20
11.2 307 Grassing with ' Doobs' Grass
Grassing with 'Doobs' grass including watering and
maintenance of the lawn for 30 days or more till the grass
forms a thick lawn free from weeds and fit for moving
including supplying good earth if needed
Unit = sqm
Taking output = 100 sqm
(i) In rows 15 cm apart in either direction
a) Labour
Mate day 0.170 329.34 55.99 L-12
Mazdoor for grassing day 0.750 152.91 114.68 L-13
Mazdoor for maintenance for 30 days day 1.000 152.91 152.91 L-13
b) Machinery
Water tanker6 KL capacity hour 0.500 517.53 258.76 P&M-060
c) Material
Doob grass kg 100.000 27.17 2717.02 M-118
d) Overhead charges @ 8% on (a+b+c) 263.95
e) Contractor's profit @ 10% on (a+b+c+d) 356.33
Cost for 100 sqm = a+b+c+d+e 3919.64
Rate per sqm= (a+b+c+d+e)/100 39.20
say 39.20
11.2 (ii) In rows 7.5 cm apart in either direction
a) Labour
Mate day 0.220 329.34 72.45 L-12
Mazdoor for grassing. day 1.250 152.91 191.13 L-13
for maintenance for 30 days day 1.000 152.91 152.91 L-13
b) Machinery
Water tanker6 KL capacity hour 0.750 517.53 388.15 P&M-060
c) Material
Doob grass kg 200.000 27.17 5434.04 M-118
d) Overhead charges @ 8% on (a+b+c) 499.09
e) Contractor's profit @ 10% on (a+b+c+d) 673.78
Cost for 100 sqm = a+b+c+d+e 7411.55
Rate per sqm = (a+b+c+d+e)/100 74.12
say 74.10
Note In the case of horticulture one mate has been provided for
every 10 mazdoors as maintenance of grass and plants
require more care.
Ref. to
MoRT Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
H Input ref.
Spec.
11.3 307 Making Lawns including Ploughing and Dragging with
'Swagha' Breaking of Clod
Making lawns including ploughing and breaking of clod,
removal of rubbish, dressing and supplying doobs grass
roots and planting at 15 cm apart, including supplying and
spreading of farm yard manure at rate of 0.18 cum per 100
sqm
Unit = sqm
Taking output = 100 sqm
a) Labour
Mate day 0.150 329.34 49.40 L-12
Mazdoor for preparation of ground day 0.500 152.91 76.45 L-13
Mali for fetching doobs grass roots and grassing at 15 day 1.000 235.24 235.24 L-09
cm apart
b) Machinery
Water tanker6 KL capacity hour 0.500 517.53 258.76 P&M-060
Tractor with filler hour 0.010 379.91 3.80 P&M-053
c) Material
Supply of farm yard manure at site of work cum 0.180 98.80 17.78 M-172
Fine grass kg 100.000 37.05 3705.03 M-119
d) Overhead charges @ 8% on (a+b+c) 347.72
e) Contractor's profit @ 10% on (a+b+c+d) 469.42
Cost for 100 sqm = a+b+c+d+e 5163.61
Rate per sqm = (a+b+c+d+e)/100 51.64
say 51.60
11.4 307 Maintenance of Lawns or Turfing of Slopes
Maintenance of lawns or Turfing of slopes (rough grassing)
for a period of one year including watering etc
Unit = sqm
Taking output = 100 sqm
a) Labour
Mali day 10.000 235.24 2352.40 L-09
b) Machinery
Water tanker6 KL capacity hour 15.000 517.53 7762.92 P&M-060
c) Material
Cost of water KL 90.000 55.58 5001.79 M-195
d) Overhead charges @ 8% on (a+b+c) 1209.37
e) Contractor's profit @ 10% on (a+b+c+d) 1632.65
Cost for 100 sqm = a+b+c+d+e 17959.13
Rate per sqm = (a+b+c+d+e)/100 179.59
say 180.00
Ref. to
MoRT Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
H Input ref.
Spec.
11.5 307 Turfing Lawns with Fine Grassing including Ploughing,
Dressing
Turfing lawns with fine grassing including ploughing, dressing
including breaking of clods, removal of rubbish, dressing and
supplying doobs grass roots at 10 cm apart, including
supplying and spreading of farm yard manure at rate of 0.6
cum per 100 sqm
Unit = sqm
Taking output = 100 sqm
a) Labour
Mate day 0.250 329.34 82.33 L-12
Mazdoor for preparation of ground day 1.000 152.91 152.91 L-13
Mali for fetching doobs grass roots hedges and grassing day 1.500 235.24 352.86 L-09
at 10 cm apart
b) Machinery
Water tanker6 KL capacity hour 0.500 517.53 258.76 P&M-060
Tractor with tiller hour 0.010 379.91 3.80 P&M-053
c) Material
Supply of farm yard manure at site of work @ 0.6 cum cum 0.600 98.80 59.28 M-172
per 100 sqm
Fine grass kg 100.000 37.05 3705.03 M-119
d) Overhead charges @ 8% on (a+b+c) 369.20
e) Contractor's profit @ 10% on (a+b+c+d) 498.42
Cost for 100 sqm = a+b+c+d+e 5482.59
Rate per sqm = (a+b+c+d+e)/100 54.83
say 54.80
11.6 307 Maintenance of Lawns with Fine Grassing for the First
Year
Maintenance of lawns with fine grassing for the first year
including watering etc
Unit = sqm
Taking output = 100 sqm
a) Labour
Mali day 10.000 235.24 2352.40 L-09
b) Machinery
Water tanker6 KL capacity hour 20.000 517.53 10350.56 P&M-060
c) Material
Cost of water KL 60.000 55.58 3334.53 M-195
d) Overhead charges @ 8% on (a+b+c) 1283.00
e) Contractor's profit @ 10% on (a+b+c+d) 1732.05
Cost for 100 sqm = a+b+c+d+e 19052.53
Rate per sqm = (a+b+c+d+e)/100 190.53
say 191.00
Ref. to
MoRT Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
H Input ref.
Spec.
11.7 307 Planting and Maintaining of Permanent Hedges
(a) Planting permanent hedges including digging of
trenches
Planting permanent hedges including digging of trenches, 60
cm wide and 45 cm deep, refilling the excavated earth mixed
with farmyard manure, supplied at the rate of 4.65 cum per
100 metres and supplying and planting hedge plants at 30
cm apart
Unit = Running metre
Taking output = 100metre
a) Labour
Mate day 1.400 329.34 461.07 L-12
Mazdoor for digging of trench 60 cm wide and 45 cm day 10.000 152.91 1529.06 L-13
deep
Mazdoor for refilling the excavated earth mixed with cow day 4.000 152.91 611.62 L-13
dung, preparation of ground and digging of plant, from
the nursery carriage to site and planting in position

b) Machinery
Water tanker6 KL capacity hour 0.500 517.53 258.76 P&M-060
c) Material
Cost of hedge plants 2 rows at 30 cm apart each 2x340 14.82 10077.68 M-122
Supply of farm yard manure at site of work cum 4.670 98.80 461.40 M-172
Pesticide kg 0.250 395.20 98.80 M-142
Cost of water KL 3.000 55.58 166.73 M-195
d) Overhead charges @ 8% on (a+b+c) 1093.21
e) Contractor's profit @ 10% on (a+b+c+d) 1475.83
Cost for 100 metres = a+b+c+d+e 16234.17
Rate per metre = a+b+c+d+e)/100 162.34
say 162.00
(b) Maintenance of hedge for one year
Unit = Running metre
Taking output = 100 m
a) Labour
Mate day 3.000 329.34 988.01 L-12
Mazdoor day 30.000 152.91 4587.18 L-13
b) Machinery
Water tanker6 KL capacity hour 5.000 517.53 2587.64 P&M-060
c) Material
Manure sludge/Farm yard manure cum 2.000 98.80 197.60 M-172
Pesticide kg 0.500 395.20 197.60 M-142
Cost of water KL 30.000 55.58 1667.26 M-195
Cost of hedge plants @ 10 per cent casualty each 68.000 14.82 1007.77 M-122
d) Overhead charges @ 8% on (a+b+c) 898.65
e) Contractor's profit @ 10% on (a+b+c+d) 1213.17
Cost for 100 metres = a+b+c+d+e 13344.88
Rate per metre = a+b+c+d+e)/100 133.45
say 133.00
Ref. to
MoRT Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
H Input ref.
Spec.
11.8 307 Planting and Maintaining of Flowering Plants and
Shrubs
(a) Planting flowering plants and shrubs in central verge

Unit = Running metres 200 plants and 800 shrubs in two


rows in one km length of road where width of verge is
3m and above.
Taking output = 1000 metres
a) Labour
Mate day 1.200 329.34 395.20 L-12
Mazdoor day 12.000 152.91 1834.87 L-13
b) Machinery
Water tanker6 KL capacity hour 6.000 517.53 3105.17 P&M-060
c) Material
Plants each 200.000 67.93 13585.11 M-106
Shrubs each 800.000 24.70 19760.16 M-171
Manure sludge/Farm yard manure cum 63.640 98.80 6287.68 M-172
Pesticide kg 0.500 395.20 197.60 M-142
Cost of water KL 36.000 55.58 2000.72 M-195
d) Overhead charges @ 8% on (a+b+c) 3773.32
e) Contractor's profit @ 10% on (a+b+c+d) 5093.98
Rate per Km = (a+b+c+d+e) 56033.82
say 56034.00
56036.00
11.8 (b) Maintenance of flowering plants and shrubs in central
verge for one year
Unit = km
Taking output = one km
a) Labour
Mate day 36.000 329.34 11856.10 L-12
Mazdoor day 365.000 152.91 55810.69 L-13
b) Machinery
Water tanker6 KL capacity hour 90.000 517.53 46577.52 P&M-060
c) Material
Manure Sludge / farm yard manure at site cum 10.000 98.80 988.01 M-172
Cost of water KL 180.000 55.58 10003.58 M-195
Replacement of casualties @ 10 per cent
Plants each 20.000 67.93 1358.51 M-106
Shrubs each 80.000 24.70 1976.02 M-171
Pesticides kg 1.500 395.20 592.80 M-142
d) Overhead charges @ 8% on (a+b+c) 10333.06
e) Contractor's profit @ 10% on (a+b+c+d) 13949.63
Rate per Km for one year = (a+b+c+d+e) 153445.91
say 153446.00
153452.00
Ref. to
MoRT Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
H Input ref.
Spec.
11.9 307 Planting of Trees and their Maintenance for one Year

Planting of trees by the road side (Avenue trees) in 0.60 m


dia holes, 1 m deep dug in the ground, mixing the soil with
decayed farm yard/sludge manure, planting the saplings,
backfilling the trench, watering, fixing the tree guard and
maintaining the plants for one year
Unit = Each
Taking output = 10 trees
a) Labour
Mate day 1.700 329.34 559.87 L-12
Mazdoor for planting day 2.000 152.91 305.81 L-13
Mazdoor for maintenance for one year day 15.000 152.91 2293.59 L-13
b) Machinery
Water tanker6 KL capacity hour 2.000 517.53 1035.06 P&M-060
c) Material
Sapling 2 m high 25 mm dia each 10.000 111.15 1111.51 M-165
Farm yard manure cum 0.940 98.80 92.87 M-172
Pesticide kg 0.500 395.20 197.60 M-142
Cost of water KL 12.000 55.58 666.91 M-195
d) Overhead charges @ 8% on (a+b+c) 501.06
e) Contractor's profit @ 10% on (a+b+c+d) 676.43
Cost for 10 trees = a+b+c+d+e 7440.70
Rate per trees = (a+b+c+d+e)/10 744.07
say 744.00
744.00
11.10 308 Renovation Lawns including, Weeding, Forking the
Ground, Top Dressing with Forked Soil
Renovation lawns including, weeding, forking the ground, top
dressing with forked soil, watering and maintenance the
lawns, for 30 days or more, till the grass forms a thick lawn,
free from weeds, and fit for moving and disposal of rubbish
as directed, including supplying good earth, if needed but
excluding the cost of well decayed farm yard manure
Unit = sqm
Taking output = 100 sqm
a) Labour
Mate day 0.120 329.34 39.52 L-12
Mazdoor day 3.000 152.91 458.72 L-13
b) Machinery
Water tanker6 KL capacity hour 0.500 517.53 258.76 P&M-060
c) Material
Cost of water KL 3.000 55.58 166.73 M-195
d) Overhead charges @ 8% on (a+b+c) 73.90
e) Contractor's profit @ 10% on (a+b+c+d) 99.76
Cost for 100 sqm = a+b+c+d+e 1097.39
Rate per sqm = (a+b+c+d+e) / 100 10.97
say 11.00
Ref. to
MoRT Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
H Input ref.
Spec.
11.11 308.2 Supply at Site Well Decayed Farm Yard Manure
Supply at site of work well decayed farm yard manure, from
any available source, approved by the engineer in charge
including screening and stacking
Unit = cum
Taking output = one cum
a) Material
a) Cost of well decayed farm yard manure duly cum 1.000 98.80 98.80 M-172
screened, loading, carriage, unloading and stacking
at site
b) Overhead charges @ 8% on (a) 7.90
c) Contractor's profit @ 10% on (a+b) 10.67
Rate per cum = (a+b+c) 117.38
117.00
11.14 New Half Brick Circular Tree Guard, in 2nd Class Brick,
internal diametre 1.25 metres, and height 1.2 metres,
above ground and 0.20 metre below ground

Half brick circular tree guard, in 2nd class brick, internal


diametre 1.25 metres, and height 1.2 metres, above ground
and 0.20 metre below ground, bottom two courses laid dry,
and top three courses in cement mortar 1:6 (1 cement 6
sand) and the intermediate courses being in dry honey comb
masonry, as per design complete
Unit = Each
Taking output = one tree guard
a) Labour
Mate day 0.050 329.34 16.47 L-12
Mason day 0.250 352.86 88.22 L-11
Mazdoor day 0.250 152.91 38.23 L-13
b) Material
Brick 2nd class including carriage each 230.000 8.23 1893.68 M-084
Cement mortar 1:6 cum 0.025 4298.00 107.45 Item 12.6
(D)
c) Overhead charges @ 8% on (a+b) 171.52
d) Contractor's profit @ 10% on (a+b+c) 231.56
Rate per tree Guard = a+b+c+d 2547.12
say 2547.00
2566.00
Ref. to
MoRT Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
H Input ref.
Spec.
11.15 New Edging with 2nd Class Bricks, Laid Dry Lengthwise
Edging with 2nd class bricks, laid dry lengthwise, including
excavation, refilling, consolidation, with a hand packing and
spreading nearly surplus earth within a lead of 50 metres

Unit = Metre
Taking output= 10 metres
a) Labour
Mate day 0.002 329.34 0.66 L-12
Mason day 0.050 352.86 17.64 L-11
Mazdoor day 0.050 152.91 7.65 L-13
b) Material
Brick 2nd class including carriage each 50.000 8.23 411.67 M-084
c) Overhead charges @ 8% on (a+b) 35.01
d) Contractor's profit @ 10% on (a+b+c) 47.26
Cost for 10 metre = a+b+c+d 519.89
Rate per metre = (a+b+c+d)/10 51.99
say 52.00
18.80
11.16 New Making Tree Guard 53 cm dia and 1.3 m High as per
Design from Empty Bitumen Drums
Making tree guard 53 cm dia and 1.3 m high as per design
from empty bitumen drum, slit suitably to permit sun and air,
(supplied by the department at stock issue rate) including
providing and fixing 2 nos MS sheet rings 50 x 0.5 mm with
rivets, complete in all respect
Unit = Each
Taking output = one tree guard
a) Labour
Mate day 0.020 329.34 6.59 L-12
Blacksmith day 0.150 352.86 52.93 L-02
Mazdoor day 0.070 152.91 10.70 L-13
b) Material
Empty bitumen drum each 1.000 72.92 72.92 M-178
MS sheet 50 x 0.5 mm kg 0.650 60.00 39.00 M-185
/1000
Rivets 6 mm dia and 10 mm in length each 22.000 4.94 108.68 M-163
c) Overhead charges @ 8% on (a+b) 23.27
d) Contractor's profit @ 10% on (a+b+c) 31.41
Rate for each tree guard = a+b+c+d 345.50
say 345.00
347.00
Ref. to
MoRT Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
H Input ref.
Spec.
11.17 New Making Tree Guard 53 cm dia and 2 Metre High as per
Design from Empty Bitumen Drums
Making tree guard 53 cm dia and 2 metres high as per
design from empty bitumen drums, slit suitably to permit sun
and air, ( supplied by the department at stock issue rate)
including providing and fixing four legs 40 cm long of 30 x 3
mm MS riveted to tree guard and providing and fixing 2 nos
MS sheet rings 50 x 0.5 mm with rivets complete in all
respects
Unit = Each
Taking output = one tree guard
a) Labour
Mate 0.040 329.34 13.17 L-12
Blacksmith day 0.200 352.86 70.57 L-02
Mazdoor 0.200 152.91 30.58 L-13
b) Material
Empty bitumen drum each 1.500 72.92 109.39 M-178
MS sheet50 x 0.5 mm kg 0.650 60.00 39.00 M-185
/1000
Rivets 6 mm dia and 10 mm in length each 50.000 4.94 247.00 M-163
MSplate30 x 3 mm kg 1.300 60.00 78.00 M-185
/1000
c) Overhead charges @ 8% on (a+b) 47.02
d) Contractor's profit @ 10% on (a+b+c) 63.47
Rate for each tree guard = a+b+c+d 698.21
say 698.00
702.00
11.18 New Wrought Iron and Mild Steel Welded Work
Wrought iron and mild steel welded work (using angles,
square bars, tees and channel grills, grating frames, gates
and tree guards of any size and design etc. including cost of
screens and welding rods or bolts and nuts complete fixed in
position but without the cost of excavation and concrete for
fixing which will be paid separately
Unit = quintal
Taking output = one quintal
a) Labour
Mate day 0.450 329.34 148.20 L-12
Blacksmith/ welder for cutting to design and shape and day 2.000 352.86 705.72 L-02
jointing
Mazdoor for fixing and helper for Blacksmith/welder day 2.500 152.91 382.27 L-13
b) Material
Angle, tees, channels etc quintal 1.050 6000.00 6300.00 M-185 /10
Deduct the cost of scrap quintal 0.050 -2000.00 (100.00) M-185/10/3

Add 5 per cent of cost of material for welding rods and other 310.00
welding accessories
c) Overhead charges @ 8% on (a+b) 619.69
d) Contractor's profit @ 10% on (a+b+c) 836.59
Rate per quintal = a+b+c+d 9202.47
say 9202.00
9208.00
Ref. to
MoRT Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
H Input ref.
Spec.
11.19 New Tree Guard with MS Iron
Providing and fixing MS iron tree guard 60 cm dia and 2
metre high above ground level formed of 4 Nos (25 x 6 mm)
and 8 Nos (25 x 3 mm) vertical MS riveted to 3 Nos (25 x 6
mm) iron rings in two halves, bolted together with 8 mm dia
and 30 mm long bolts including painting two coats with paint
of approved brand over a coat of priming, complete in all
respects.
Unit = Each
Taking output = one tree guard
a) Labour
Mate day 0.050 329.34 16.47 L-12
Blacksmith day 0.250 352.86 88.22 L-02
Mazdoor day 0.250 152.91 38.23 L-13
b) Material
MS iron 25 x 6 mm kg 19.200 60.000 1152.00 M-185
/1000
MS iron 25 x 3 mm kg 9.600 60.000 576.00 M-185
/1000
Add 5 per cent of cost of material for riveting, bolting
and welding accessories
c) Machinery
Tractor-trolley hour 0.040 379.91 15.20 P&M-053
d) Painting
Painting two coats including priming sqm 1.770 52.00 92.04 Item 8.9
e) Overhead charges @ 8% on (a+b+c) 150.89
f) Contractor's profit @ 10% on (a+b+c+e) 203.70
Rate per tree guard =a+b+c+d+e+f 2332.73
say 2333.00
2333.00
Note 1 The items of excavation and concreting to be measured
and paid separately as per design .
2 . Rate of painting may be adopted from the chapter as
Traffic signs.
Ref. to
MoRT Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
H Input ref.
Spec.
11.20 New Tree Guard with MS Angle Iron and Steel Wire
Providing and fixing tree guard 0.60 metre square, 2.00
metre high fabricated with MS angle iron 30 x 30 x 3 mm, MS
iron 25 x 3 mm and steel wire3 mm dia welded and
fabricated as per design in two halves bolted together
Unit = Each
Taking output = one tree guard
a) Labour
Mate day 0.050 329.34 16.47 L-12
Blacksmith day 0.250 352.86 88.22 L-02
Welder day 0.250 352.86 88.22 L-02
Mazdoor day 0.250 152.91 38.23 L-13
b) Material
MS angle 30 x 30 x 3 mm kg 13.500 60.00 810.00 M-185
/1000
MS iron 25 x 3 mm kg 18.000 60.00 1080.00 M-185
/1000
Steel wire 3 mm dia kg 6.000 74.10 444.60 M-199
Add 5 per cent of cost of material for riveting, bolting 116.73
and welding accessories
c) Machinery
Tractor-trolley hour 0.040 379.91 15.20 P&M-053
d) Painting
Painting two coats including priming sqm 1.500 52.00 78.00 Item 8.9
e) Overhead charges @ 8% on (a+b+c) 215.81
f) Contractor's profit @ 10% on (a+b+c+e) 291.35
Rate per tree guard = a+b+c+d+e+f 3282.81
say 3283.00
3287.00
Ref. to
MoRT Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
H Input ref.
Spec.
11.21 New Compensatory Afforestation
Planting trees as compensatory afforestation at the rate of
290 trees per hectare at a spacing of 6 m by grubbing and
leveling the ground upto a depth of 150 mm, digging holes
0.9 m dia, 1 m deep, mixing farm yard/sludge manure with
soil, planting of sapling 2 m high with 25 cm dia stem,
backfilling the hole and watering
Unit = Hectare
Taking output = one hectare
a) Labour
i) Planting
Mate day 2.500 329.34 823.34 L-12
Mazdoor day 25.000 152.91 3822.65 L-13
ii) For Maintenance for one year
Mate day 5.000 329.34 1646.68 L-12
Mazdoor day 50.000 152.91 7645.30 L-13
b) Machinery
Dozer 80 HP @ 1000 sqm/hour hour 10.000 2311.23 23112.33 P&M-015
Water tanker6 KL capacity (for planting) hour 3.000 517.53 1552.58 P&M-060
Water tanker6 KL capacity (for maintenance) hour 25.000 517.53 12938.20 P&M-060
c) Material
Sapling 1 to 1.5 m high 2 cm dia stem each 290.000 88.92 25787.01 M-165 x 0.8

Add 10 per cent of sapling each 29.000 88.92 2578.70 M-165 x 0.8

Decayed farm yard/sludge manure (planting) cum 60.900 98.80 6016.97 M-172
Decayed farm yard/sludge manure (maintenance) cum 4.000 98.80 395.20 M-172
Pesticides for planting kg 0.500 395.20 197.60 M-142
Pesticides for maintenance kg 1.500 395.20 592.80 M-142
Cost of water KL 18.000 55.58 1000.36 M-195
d) Overhead charges @ 8% on (a+b+c) 7048.78
e) Contractor's profit @ 10% on (a+b+c+d) 9515.85
Rate per hectare = a+b+c+d+e 104674.36
say 104674.00
104682.00
CHAPTER-12
FOUNDATIONS
Ref. to Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
MoRTH Spec.
12.1 304 Excavation for Structures
Earth work in excavation of foundation of structures as per
drawing and technical specification, including setting out,
construction of shoring and bracing, removal of stumps and
other deleterious matter, dressing of sides and bottom and
backfilling with approved material.
I Ordinary soil
Unit = cum
Taking output = 10 cum
A Manual Means
(i) Depth upto 3 m
a) Labour
Mate day 0.14 329.34 46.11 L-12
Mazdoor day 3.50 152.91 535.17 L-13
b) Overhead charges @ 0.25 on (a) 145.32
c) Contractor's profit @ 0.1 on (a+b) 72.66
Cost for 10 cum = a+b+c 799.26
Rate per cum = (a+b+c)/10 79.93
say 80.00
Note 1. Cost of dewatering may be added where required upto, 10
percent of labour cost assessment for dewatering shall be
made as per site conditions.
2.The excavated earth can be used partially for backfilling of
foundation pit and partly for road work except for marshy soil.
Hence cost of disposal has not been added except for marshy
soil. This remark is common to all cases of item 12.1 excluding
marshy soil.
3.The cost of shoring and shuttering, where needed, may be
added @ 1 per cent on cost of excavation for open foundation.
12.1 (I) A (ii) Depth 3 m to 6 m

a) Labour
Mate/Supervisor day 0.18 329.34 59.28 L-12
Mazdoor day 4.50 152.91 688.08 L-13
b) Overhead charges @ 0.25 on (a) 186.84
c) Contractor's profit @ 0.1 on (a+b) 93.42
Cost for 10 cum = a+b+c 1027.62
Rate per cum = (a+b+c)/10 102.76
say 103.00
Note Cost of dewatering may be added where required upto 15 per
cent of labour cost. Assessment for dewatering shall be done as
per actual ground conditions.
12.1 (I) A (iii) Depth above 6 m

a) Labour
Mate/Supervisor day 0.24 329.34 79.04 L-12
Mazdoor day 6.00 152.91 917.44 L-13
b) Overhead charges @ 0.25 on (a) 249.12
c) Contractor's profit @ 0.1 on (a+b) 124.56
Cost for 10 cum = a+b+c 1370.16
Rate per cum = (a+b+c)/10 137.02
say 137.00

Note 1. Cost of dewatering may be added where required upto 20 per


cent of labour cost. Assessment for dewatering shall be made
as per site conditions..
Ref. to Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
MoRTH Spec.
12.1 (I) B Mechanical Means
(i) Depth upto 3 m
Unit = cum
Taking output = 240 cum
a) Labour
Mate day 0.32 329.34 105.39 L-12
Mazdoor day 8.00 152.91 1223.25 L-13
b) Machinery
Hydraulic excavator 1.0 cum bucket capacity hour 6.00 1621.98 9731.88 P&M-026
c) Overhead charges @ 0.25 on (a+b) 2765.13
d) Contractor's profit @ 0.1 on (a+b+c) 1382.56
Cost for 240 cum = a+b+c+d 15208.21
Rate per cum = (a+b+c+d)/240 63.37
say 63.00
63.00
Note Cost of dewatering upto 5 per cent of (a+b) may be added,
where required. Assessment for dewatering shall be made as
per site conditions..
12.1 (I) B (ii) Depth 3 m to 6 m

Unit = cum
Taking output = 210 cum
a) Labour
Mate day 0.32 329.34 105.39 L-12
Mazdoor day 8.00 152.91 1223.25 L-13
b) Machinery
Hydraulic excavator 1.0 cum bucket capacity hour 6.00 1621.98 9731.88 P&M-026

c) Overhead charges @ 0.25 on (a+b) 2765.13

d) Contractor's profit @ 0.1 on (a+b+c) 1382.56

Cost for 210 cum = a+b+c+d 15208.21

Rate per cum = (a+b+c+d)/210 72.42


say 72.00

72.00
Note Cost of dewatering upto 7.5 per cent of (a+b) may be added,
where required. Assessment for dewatering shall be made as
per site conditions..
12.1 (I) B (iii) Depth above 6m
Unit = cum
Taking output = 180 cum
a) Labour
Mate day 0.40 329.34 131.73 L-12

Mazdoor day 10.00 152.91 1529.06 L-13

b) Machinery
Hydraulic excavator 1.0 cum bucket capacity hour 6.00 1621.98 9731.88 P&M-026

c) Overhead charges @ 0.25 on (a+b) 2848.17

d) Contractor's profit @ 0.1 on (a+b+c) 1424.08

Cost for 180 cum = a+b+c+d 15664.93

Rate per cum = (a+b+c+d)/180 87.03


say 87.00

87.00
Note 1. Cost of dewatering upto 10 per cent of (a+b) may be added,
where required. Assessment for dewatering shall be made as
per site conditions.
2.Labour provided for excavation by mechanical means includes
that required for trimming of bottom and side slopes.
Ref. to Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
MoRTH Spec.
12.3 304 Sand Filling in Foundation Trenches as per Drawing &
Technical Specification
Unit = cum
Taking output = 1 cum
a) Labour
Mate day 0.01 329.34 3.29 L-12

Mazdoor day 0.30 152.91 45.87 L-13

b) Material
Sand (assuming 20 per cent voids) cum 1.20 1293.82 1552.58 M-006

c) Overhead charges @ 0.25 on (a+b) 400.44

d) Contractor's profit @ 0.1 on (a+b+c) 200.22

Rate per cum = a+b+c+d 2202.41


say 2202.00

2202.00
12.5 1300 Brick Masonry Work in Cement Mortar 1:3 in Foundation
complete excluding Pointing and Plastering, as per Drawing
and Technical Specifications.

Unit = cum
Taking output = 5 cum
a) Material
Bricks Ist class each 2500.00 8.23 20583.50 M-084

Cement mortar 1:3 (Rate as in Item 12.6 A sub-analysis) cum 1.20 5945.00 7134.00 Item 12.6
(A)
b) Labour
Mate day 0.48 329.34 158.08 L-12

Mason day 4.00 352.86 1411.44 L-11

Mazdoor day 8.00 152.91 1223.25 L-13

c) Overhead charges @ 0.25 on (a+b) 7627.57

d) Contractor's profit @ 0.1 on (a+b+c) 3813.78

Cost for 5 cum = a+b+c+d 41951.62

Rate per cum (a+b+c+d)/5 8390.32


say 8390.00
(i) Rate for Brick Work in C. M. 1:2 in foundation 8823.00
(ii) Rate for Brick Work in C. M. 1:3 in foundation 8390.00
(iii) Rate for Brick Work in C. M. 1:4 in foundation 8093.00
(iv) Rate for Brick Work in C. M. 1:6 in foundation 7847.00
12.6 Sub-analysis (A) Cement Mortar 1:3 (1 cement : 3 sand)

Unit = 1 cum
Taking output = 1 cum
a) Materials
Cement tonne 0.51 8939.12 4558.95 M-086

Sand cum 1.05 1176.20 1235.01 M-005

b) Labour
Mate day 0.04 329.34 13.17 L-12

Mazdoor day 0.90 152.91 137.62 L-13

Total Material and Labour = (a+b) say 5945.00

5945.00
Sub-analysis (B) Cement Mortar1:2 (1cement :2 sand)
(Addl.)
Unit = 1 cum
Taking output = 1 cum
a) Materials
Cement tonne 0.672 8939.12 6007.09 M-086

Sand cum 0.933 1176.20 1097.79 M-005

b) Labour
Mate day 0.04 329.34 13.17 L-12

Mazdoor day 0.90 152.91 137.62 L-13


Ref. to Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
MoRTH Spec.
Total Material and Labour = (a+b) say 7256.00

7256.00
Ref. to Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
MoRTH Spec.
Sub-analysis (C) Cement Mortar1:4 (1cement :4 sand)
(Addl.)
Unit = 1 cum
Taking output = 1 cum
a) Materials
Cement tonne 0.40 8939.12 3575.65 M-086

Sand cum 1.12 1176.20 1317.34 M-005

b) Labour
Mate day 0.04 329.34 13.17 L-12

Mazdoor day 0.90 152.91 137.62 L-13

Total Material and Labour = (a+b) say 5044.00

5044.00
Sub-analysis (D) Cement Mortar1:6 (1cement :6 sand)
(Addl.)
Unit = 1 cum
Taking output = 1 cum
a) Materials
Cement tonne 0.288 8939.12 2574.47 M-086

Sand cum 1.337 1176.20 1572.75 M-005

b) Labour
Mate day 0.04 329.34 13.17 L-12

Mazdoor day 0.90 152.91 137.62 L-13

Total Material and Labour = (a+b) say 4298.00

4298.00
12.7 1400 Stone Masonry Work in Cement Mortar 1:3 in Foundation
complete as per Drawing and Technical Specifications.

Unit = cum
Taking output = 5 cum
1405.4 (A) Square Rubble Coursed Rubble Masonry (first sort)
a) Material
Stone cum 5.50 1074.46 5909.52 M-175

Through and bond stone each 35.00 6.80 237.95 M-188

(35no.x0.24mx0.24mx0.39m = 0.79 cu.m)


Cement mortar 1:3 (Rate as in Item 12.6 A sub-analysis) cum 1.50 5945.00 8917.50 Item 12.6
(A)
b) Labour
Mate day 0.66 329.34 217.36 L-12

Mason day 7.50 352.86 2646.45 L-11

Mazdoor day 9.00 152.91 1376.15 L-13

c) Overhead charges @ 0.25 on (a+b) 4826.23

d) Contractor's profit @ 0.1 on (a+b+c) 2413.12

Cost for 5 cum = a+b+c+d 26544.28

Rate per cum (a+b+c+d)/5 5308.86


say 5309.00

5321.00
1405.3 (B) Random Rubble Masonry
( coursed/uncoursed )
Unit = cum
Taking output = 5 cum
a) Material
Stone cum 5.50 802.76 4415.16 M-153

Through and bond stone each 35.00 6.80 237.95 M-188

(35nos.x0.24mx0.24mx0.39m = 0.79 cu.m)


Cement mortar 1:3 (Rate as in Item 12.6 A sub-analysis) cum 1.55 5945.00 9214.75 Item 12.6
(A)
b) Labour
Mate day 0.62 329.34 204.19 L-12

Mason day 6.00 352.86 2117.16 L-11


Ref. to Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
MoRTH Spec.
Mazdoor day 9.00 152.91 1376.15 L-13

c) Overhead charges @ 0.25 on (a+b) 4391.34

d) Contractor's profit @ 0.1 on (a+b+c) 2195.67

Cost for 5 cum = a+b+c+d 21956.70

Rate per cum (a+b+c+d)/5 4391.34


say 4391.00

4401.00
Note The labour already considered in cement mortar has been taken
into account while proposing labour for masonry works.
Ref. to Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
MoRTH Spec.
12.8 1500, 1700 & Plain/Reinforced Cement Concrete in Open Foundation
2100 complete as per Drawing and Technical Specifications.

A PCC Grade M15


Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 4.13 8939.12 36918.57 M-086

Coarse sand cum 6.75 1176.20 7939.35 M-005

40 mm Aggregate cum 8.10 1411.44 11432.66 M-055

20 mm Aggregate cum 4.05 1529.06 6192.69 M-053

10 mm Aggregate cum 1.35 1529.06 2064.23 M-051

b) Labour
Mate day 0.86 329.34 283.23 L-12

Mason day 1.50 352.86 529.29 L-11

Mazdoor day 20.00 152.91 3058.12 L-13

c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 237.59 1425.55 P&M-009

Generator 63 KVA hour 6.00 604.57 3627.40 P&M-019

Per Cum Basic Cost of Labour, Material & Machinery 4899.00


(a+b+c)
d) Formwork @ 4 per cent on cost of concrete i.e. cost of 2938.84
material, labour and machinery

e) Overhead charges @ 0.25 on (a+b+c+d) 19102.49

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 9551.24

Cost for 15 cum = a+b+c+d+e+f 105063.67

Rate per cum = (a+b+c+d+e+f)/15 7004.24


say 7004.00

7004.00
Note Needle Vibrator is an item of minor T & P which is already
included in overhead charges. Hence not added in rate analysis
of cement concrete works.
12.8 B PCC Grade M20
Unit : cum
Taking output = 15 cum
a) Material
Cement tonne 5.16 8939.12 46125.86 M-086

Coarse sand cum 6.75 1176.20 7939.35 M-005

40 mm Aggregate cum 5.40 1411.44 7621.78 M-055

20 mm Aggregate cum 5.40 1529.06 8256.92 M-053

10 mm Aggregate cum 2.70 1529.06 4128.46 M-051

b) Labour
Mate day 0.86 329.34 283.23 L-12

Mason day 1.50 352.86 529.29 L-11

Mazdoor day 20.00 152.91 3058.12 L-13

c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 237.59 1425.55 P&M-009

Generator 33 KVA hour 6.00 365.80 2194.79 P&M-079

Per Cum Basic Cost of Labour, Material & Machinery 5438.00


(a+b+c)
d) Formwork @ 4 per cent on cost of concrete i.e. cost of 3262.53
material, labour and machinery
e) Overhead charges @ 0.25 on (a+b+c+d) 21206.47

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 10603.24

Cost for 15 cum = a+b+c+d+e+f 116635.60

Rate per cum = (a+b+c+d+e+f)/15 7775.71


say 7776.00

7776.00
Ref. to Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
MoRTH Spec.
12.8 C RCC Grade M20
12.8 C Case II With Batching Plant, Transit Mixer and Concrete Pump
Unit : cum
Taking Output = 120 cum
a) Material
Cement tonne 41.66 8939.12 372403.74 M-086

Coarse Sand cum 54.00 1176.20 63514.80 M-004

20 mm Aggregate cum 64.80 1529.06 99083.09 M-053

10 mm Aggregate cum 43.20 1529.06 66055.39 M-051

b) Labour
Mate day 0.84 329.34 276.64 L-12

Mason day 3.00 352.86 1058.58 L-11

Mazdoor day 18.00 152.91 2752.31 L-13

c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 2301.82 13810.94 P&M-002

Generator 100 KVA hour 6.00 730.42 4382.52 P&M-080

Loader 1 cum capacity hour 6.00 803.34 4820.07 P&M-017

Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 973.89 14608.40 P&M-049

Lead beyond 1 km, L-lead in km tonne.km 300L 47.05 42343.20 P&M-050


Lead= 3 km
Concrete Pump hour 6 275.23 1651.38 P&M-007

Per Cum Basic Cost of Labour, Material & Machinery 5724.00


(a+b+c)
d) Formwork @ 4 per cent on cost of concrete i.e. cost of 27470.44
material, labour and machinery
e) Overhead charges @ 0.25 on (a+b+c+d) 178557.88

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 89278.94

Cost for 120 cum = a+b+c+d+e+f 982068.33

Rate per cum = ( a+b+c+d+e+f )/120 8183.90


say 8184.00

8184.00
Ref. to Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
MoRTH Spec.
12.8 E RCC Grade M25
12.8 E Case II With Batching Plant, Transit Mixer and Concrete Pump
Unit: cum
Taking Output = 120 cum
a) Material
Cement tonne 48.38 8939.12 432474.63 M-086

Coarse sand cum 54.00 1176.20 63514.80 M-004

20 mm Aggregate cum 64.80 1529.06 99083.09 M-053

10 mm Aggregate cum 43.20 1529.06 66055.39 M-051

b) Labour
Mate day 0.84 329.34 276.64 L-12

Mason day 3.00 352.86 1058.58 L-11

Mazdoor day 18.00 152.91 2752.31 L-13

c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 2301.82 13810.94 P&M-002

Generator 100 KVA hour 6.00 730.42 4382.52 P&M-080

Loader 1 cum capacity 1 cum hour 6.00 803.34 4820.07 P&M-017

Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 973.89 14608.40 P&M-049

Transit Mixer 4 cum capacity lead beyond 1 Km, L - lead in tonne.km 300L 47.05 42343.20 P&M-050
Kilometer Lead= 3 km

Concrete Pump hour 6.00 275.23 1651.38 P&M-007

Per Cum Basic Cost of Labour, Material & Machinery 6224.00


(a+b+c)
d) Formwork @ 3.75 per cent on cost of concrete i.e. cost of 28006.20
material, labour and machinery
e) Overhead charges @ 0.25 on (a+b+c+d) 193709.54

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 96854.77

cost of 120 cum = a+b+c+d+e+f 1065402.46

Rate per cum (a+b+c+d+e+f )/120 8878.35


say 8878.00

8878.00
Ref. to Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
MoRTH Spec.
12.8 G RCC Grade M30
12.8 G Case II Using Batching Plant, Transit Mixer and Concrete Pump

Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 48.80 8939.12 436229.06 M-086

Coarse sand cum 54.00 1176.20 63514.80 M-004

20 mm Aggregate cum 64.80 1529.06 99083.09 M-053

10 mm Aggregate cum 43.20 1529.06 66055.39 M-051

b) Labour
Mate day 0.84 329.34 276.64 L-12

Mason day 3.00 352.86 1058.58 L-11

Mazdoor day 18.00 152.91 2752.31 L-13

c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 2301.82 13810.94 P&M-002

Generator 100 KVA hour 6.00 730.42 4382.52 P&M-080

Loader 1 cum capacity hour 6.00 803.34 4820.07 P&M-017

Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 973.89 14608.40 P&M-049

Transit Mixer 4 cum capacity lead beyond 1 Km, L - lead in tonne.km 300L 47.05 42343.20 P&M-050
Kilometer Lead= 3 km

Concrete Pump hour 6.00 275.23 1651.38 P&M-007

Per Cum Basic Cost of Labour, Material & Machinery 6255.00


(a+b+c)
d) Formwork @ 3.5 per cent of cost of concrete i.e. cost of 26270.52
material, labour and machinery
e) Overhead charges @ 0.25 on (a+b+c+d) 194214.23

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 97107.11

cost of 120 cum = a+b+c+d+e+f 1068178.25

Rate per cum (a+b+c+d+e+f )/120 8901.49


say 8901.00

8901.00
12.8 H RCC Grade M35
Case I Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 6.33 8939.12 56584.63 M-086

Coarse sand cum 6.75 1176.20 7939.35 M-005

20 mm Aggregate cum 8.10 1529.06 12385.39 M-053

10 mm Aggregate cum 5.40 1529.06 8256.92 M-051

b) Labour
Mate day 0.86 329.34 283.23 L-12

Mason day 1.50 352.86 529.29 L-11

Mazdoor day 20.00 152.91 3058.12 L-13

c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 237.59 1425.55 P&M-009

Generator 33 KVA hour 6.00 365.80 2194.79 P&M-079

Per Cum Basic Cost of Labour, Material & Machinery 6178.00


(a+b+c)
d) Formwork @ 3 per cent on a+b+c 2779.72

e) Overhead charges @ 0.25 on (a+b+c+d) 23859.25

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 11929.62

cost of 15 cum = a+b+c+d+e+f 131225.86

Rate per cum = (a+b+c+d+e+f)/15 8748.39


say 8748.00

8748.00
Ref. to Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
MoRTH Spec.
12.8 H Case II Using Batching Plant, Transit Mixer and Concrete Pump

Unit ; cum
Taking Output = 120 cum
a) Material
Cement tonne 50.64 8939.12 452677.04 M-086

Coarse sand cum 54.00 1176.20 63514.80 M-004

20 mm Aggregate cum 64.80 1529.06 99083.09 M-053

10 mm Aggregate cum 43.20 1529.06 66055.39 M-051

b) Labour
Mate day 0.84 329.34 276.64 L-12

Mason day 3.00 352.86 1058.58 L-11

Mazdoor day 18.00 152.91 2752.31 L-13

c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 2301.82 13810.94 P&M-002

Generator 100 KVA hour 6.00 730.42 4382.52 P&M-080

Loader1 cum capacity hour 6.00 803.34 4820.07 P&M-017

Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 973.89 14608.40 P&M-049

Transit Mixer 4 cum capacity lead beyond 1 Km, L - lead in tonne.km 300L 47.05 42343.20 P&M-050
Kilometer Lead= 3 km

Concrete Pump hour 6.00 275.23 1651.38 P&M-007

Per Cum Basic Cost of Labour, Material & Machinery 6392.00


(a+b+c)
d) Formwork @ 3 per cent on cost of concrete i.e. cost of 23011.03
material, labour and machinery
e) Overhead charges @ 0.25 on (a+b+c+d) 197511.35

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 98755.67

cost of 120 cum = a+b+c+d+e+f 1086312.42

Rate per cum = (a+b+c+d+e+f)/120 9052.60


say 9053.00

9053.00
Note: Where ever concrete is carried out using batching plant, transit
mixer, concrete pump, Admixtures @ 0.4 per cent of weight of
cement may be added for achieving desired slump of concrete.

WELL FOUNDATION
12.9 1200 Providing and Constructing Temporary Island 16 m
diameter for Construction of Well Foundation for 8m dia.
Well.
A Assuming depth of water 1.0 m and height of island to be
1.25 m including Royality for earth @ Rs. 3768.00 for each
Island.
Unit = 1 No
Taking output = 1 No.
a) Material
Earth (compacted) cum 251.20 49.4 12409.38 M-098

Sand bags each 750.00 24.70 18525.15 M-164

b) Labour
Mate day 0.40 329.34 131.73 L-12

Mazdoor for filling sand bags, stitching and placing day 15.00 152.91 2293.59 L-13

c) Machinery
Crane with grab 1 cum capacity hour 20.00 892.74 17854.72 P&M-012

Consumables @ 2.5 per cent of (c) above 446.37

d) Overhead charges @ 0.25 on (a+b+c) 12915.23

e) Contractor's profit @ 0.1 on (a+b+c+d) 6457.62

Rate per No. (a+b+c+d+e) 71033.79


say 71034.00

71034.00
Note It is assumed that earth will be available within the working
space of crane with grab bucket.
Ref. to Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
MoRTH Spec.
12.9 B Assuming depth of water 4.0 m and height of island 4.5 m
including Royality for earth @ Rs. 13565.00 for each Island.

Unit = 1No
Taking output = 1 No
a) Material
Earth (compacted) cum 904.32 49.40 44673.77 M-098

Sand bags each 6000.00 24.70 148201.20 M-164

Wooden ballies 8" Dia and 9 m long each 95.00 4754.79 451704.91 M-201

Wooden ballies 2" Dia for bracing metre 190.00 302.58 57489.72 M-200

b) Labour
Mate day 5.60 329.34 1844.28 L-12

Mazdoor for piling 8" dia ballies for piling 8" dia ballies day 18.00 152.91 2752.31 L-13

Mazdoor for bracing with 2" dia ballies day 12.00 152.91 1834.87 L-13

Mazdoor for filling sand bags, stitching and placing day 110.00 152.91 16819.66 L-13

c) Machinery
Crane with grab 1 cum capacity hour 50.00 892.74 44636.79 P&M-012

Consumables and other arrangements for piling ballies @ 2.5 19248.94


per cent of (a+b+c).
d) Overhead charges @ 0.25 on (a+b+c) 197301.61

e) Contractor's profit @ 0.1 on (a+b+c+d) 98650.81

Rate per No. (a+b+c+d+e) 1085158.86


say 1085159.00

#######
Note For other well diameters rate can be worked out on the basis of
cross-sectional area of well. The diameter of the island shall be
in the conformity with clause 1203.2 of MoRTH specifications.

12.9 C Providing and constructing one span service road to reach


island location from one pier location to another pier
location including Royality for earth @ Rs. 225.00 per m for
service Road.
Assuming span length 30 m, width of service road 10m and
depth of water 1m
Unit = 1 meter
Taking output = 30 metre
a) Material
Earth cum 450.00 49.40 22230.18 M-098

Sand bags each 300.00 24.70 7410.06 M-164

b) Labour
Mate day 0.24 329.34 79.04 L-12

Mazdoor for filling sand bags, stitching and placing day 6.00 152.91 917.44 L-13

c) Machinery
Front end Loader 1 cum capacity hour 27.00 803.34 21690.30 P&M-017

Tipper 5.5 cum capacity hour 28.00 491.65 13766.24 P&M-048

d) Overhead charges @ 0.25 on (a+b+c) 16523.32

e) Contractor's profit @ 0.1 on (a+b+c+d) 8261.66

Cost for 30 m (a+b+c+d+e) 90878.24

Rate per m (a+b+c+d+e)/30 3029.27


say 3029.00

3029.00
Ref. to Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
MoRTH Spec.
12.10 1200 & 1900 Providing and Laying Cutting Edge of Mild Steel weighing
40 kg per metre for Well Foundation complete as per
Drawing and Technical Specification.
Unit = 1 MT
Taking output = 1 MT
a) Material
Structural steel in plates, angles, etc including 5 per cent tonne 1.05 60000.00 63000.00 M-185
wastage
Nuts & bolts Kg 20.00 87.69 1753.71 M-136

b) Labour
(for cutting, bending, making holes, joining, welding and
erecting in position)
Mate day 1.32 329.34 434.72 L-12

Fitter day 5.50 235.24 1293.82 L-08

Blacksmith day 5.50 352.86 1940.73 L-02

Welder day 5.50 352.86 1940.73 L-02

Mazdoor day 16.50 152.91 2522.95 L-13

Electrodes, cutting gas and other consumables @ 10 per cent 6475.37


of cost of (a) above
c) Overhead charges @ 0.25 on (a+b) 19840.51

d) Contractor's profit @ 0.1 on (a+b+c) 9920.25

Rate per MT (a+b+c+d) 109122.80


say 109123.00

109123.00
12.11 1200, 1500 & Plain/Reinforced Cement Concrete, in Well Foundation
1700 complete as per Drawing and Technical Specification.

Unit = 1 cum
Taking output = 1 cum
A Well curb
(i) RCC M20 Grade
Same as for 12.8 (C) except for formwork which shall be@ 20
per cent of the cost of concrete instead of 4 per cent.
Case I Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) 5510.00 Item 12.8
(C)

d) formwork @ 20 per cent of the cost of concrete 1102.00

e) Overhead charges @ 0.25 on (a+b+c+d) 1653.00

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 826.50

Rate perm (a+b+c+d+e+f) 9091.50


say 9092.00

9092.00
12.11 A Case II With Batching Plant, Transit Mixer and Concrete Pump
(i)
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) 5380.00 Item 12.8
(C)
d) formwork @ 20 per cent of the cost of concrete 1076.00

e) Overhead charges @ 0.25 on (a+b+c+d) 1614.00

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 807.00

Rate perm (a+b+c+d+e+f) 8877.00


say 8877.00

8877.00
Ref. to Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
MoRTH Spec.
12.11 A (ii) RCC M25 Grade
Same as for 12.8 (E) except for formwork which shall be@ 20
per cent of the cost of concrete instead of 3.75 per cent.
Case I Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) 6011.00 Item 12.8
(E)

d) formwork @ 20 per cent of the cost of concrete 1202.20

e) Overhead charges @ 0.25 on (a+b+c+d) 1803.30

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 901.65

Rate perm (a+b+c+d+e+f) 9918.15


say 9918.00

9918.00
12.11 A Case II With Batching Plant, Transit Mixer and Concrete Pump
(ii)
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) 6224.00 Item 12.8
(E)
d) formwork @ 20 per cent of the cost of concrete 1244.80 DIR used
item
e) Overhead charges @ 0.25 on (a+b+c+d) 1867.20

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 933.60

Rate perm (a+b+c+d+e+f) 10269.60


say 10270.00

10270.00
12.11 A (iii) RCC M35 Grade
Same as for 12.8 (H) except for formwork which shall be@ 20
per cent of the cost of concrete instead of 3.0 per cent.
Case I Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) 6178.00 Item 12.8
(H) Case I

d) formwork @ 20 per cent of the cost of concrete 1235.60

e) Overhead charges @ 0.25 on (a+b+c+d) 1853.40

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 926.70

Rate perm (a+b+c+d+e+f) 10193.70


say 10194.00

10194.00
12.11 A Case II With Batching Plant, Transit Mixer and Concrete Pump
(iii)
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) 6674.00 Item 12.8
(H)
d) formwork @ 20 per cent of the cost of concrete 1334.80 DIR used
item
e) Overhead charges @ 0.25 on (a+b+c+d) 2002.20

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 1001.10

Rate perm (a+b+c+d+e+f) 11012.10


say 11012.00

11012.00
Note. If curb concrete is carried out within steel liner, cost of formwork
shall be excluded.

12.11 B Well steining


(I) PCC M15 Grade
Same as for 12.8 (A) except for formwork which shall be @ 10
per cent of the cost of concrete instead of 4 per cent.
Case I Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) 4899.00 Item 12.8
(A)

d) formwork @ 10 per cent of the cost of concrete 489.90

e) Overhead charges @ 0.25 on (a+b+c+d) 1347.23

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 673.61

Rate perm (a+b+c+d+e+f) 7409.74


say 7410.00

7410.00
Ref. to Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
MoRTH Spec.
12.11 B (ii) PCC M20 Grade
Same as for 12.8 (B) except for formwork which shall be @ 10
per cent of the cost of concrete instead of 4 per cent.
Case I Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) 5438.00 Item 12.8
(B) PCC

d) formwork @ 10 per cent of the cost of concrete 543.80

e) Overhead charges @ 0.25 on (a+b+c+d) 1495.45

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 747.73

Rate perm (a+b+c+d+e+f) 8224.98


say 8225.00

8225.00
12.11 B (iii) RCC M20 Grade
Same as for 12.8 (C) except for formwork which shall be @ 10
per cent of the cost of concrete instead of 4 per cent.
Case I Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) 5510.00 Item 12.8
(C)

d) formwork @ 10 per cent of the cost of concrete 551.00

e) Overhead charges @ 0.25 on (a+b+c+d) 1515.25

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 757.63

Rate perm (a+b+c+d+e+f) 8333.88


say 8334.00

8334.00
12.11 B Case II With Batching Plant, Transit Mixer and Concrete Pump
(iii)
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) 5380.00 Item 12.8
(C)

d) formwork @ 10 per cent of the cost of concrete 538.00

e) Overhead charges @ 0.25 on (a+b+c+d) 1479.50

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 739.75

Rate perm (a+b+c+d+e+f) 8137.25


say 8137.00

8137.00
12.11 B (iv) PCC M25 Grade
Same as for 12.8 (D) except for formwork which shall be @ 10
per cent of the cost of concrete instead of 4 per cent.
Case I Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) 5933.00 Item 12.8
(D)
d) formwork @ 10 per cent of the cost of concrete 593.30

e) Overhead charges @ 0.25 on (a+b+c+d) 1631.58

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 815.79

Rate perm (a+b+c+d+e+f) 8973.66


say 8974.00

8974.00
12.11 B Case II With Batching Plant, Transit Mixer and Concrete Pump
(iv)
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) 5806.00 Item 12.8
(D)
d) formwork @ 10 per cent of the cost of concrete 580.60

e) Overhead charges @ 0.25 on (a+b+c+d) 1596.65

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 798.33

Rate perm (a+b+c+d+e+f) 8781.58


say 8782.00

8782.00
Ref. to Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
MoRTH Spec.
'12.11 B (v) RCC M25 Grade
Same as for 12.8 (E) except for formwork which shall be @ 10
per cent of the cost of concrete instead of 3.5 per cent.
Case I Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) 6011.00 Item 12.8
(E)

d) formwork @ 10 per cent of the cost of concrete 601.10

e) Overhead charges @ 0.25 on (a+b+c+d) 1653.03

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 826.51

Rate perm (a+b+c+d+e+f) 9091.64


say 9092.00

9092.00
12.11 B Case II With Batching Plant, Transit Mixer and Concrete Pump
(v)
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) 6224.00 Item 12.8
(E)

d) formwork @ 10 per cent of the cost of concrete 622.40 DIR used


item
e) Overhead charges @ 0.25 on (a+b+c+d) 1711.60

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 855.80

Rate perm (a+b+c+d+e+f) 9413.80


say 9414.00

9414.00
'12.11 B (vi) PCC M30 Grade
Same as for 12.8 (F) except for formwork which shall be @ 10
per cent of the cost of concrete instead of 3.5 per cent.
Case I Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) 5986.00 Item 12.8
(F)

d) formwork @ 10 per cent of the cost of concrete 598.60

e) Overhead charges @ 0.25 on (a+b+c+d) 1646.15

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 823.08

Rate perm (a+b+c+d+e+f) 9053.83


say 9054.00

9054.00
12.11 B Case II With Batching Plant, Transit Mixer and Concrete Pump
(vi)
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) 5855.00 Item 12.8
(F)

d) formwork @ 10 per cent of the cost of concrete 585.50

e) Overhead charges @ 0.25 on (a+b+c+d) 1610.13

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 805.06

Rate perm (a+b+c+d+e+f) 8855.69


say 8856.00

8856.00
'12.11 B (vii) RCC M30 Grade
Same as for 12.8 (G) except for formwork which shall be @ 10
per cent of the cost of concrete instead of 3.5 per cent.
Case I Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) 6041.00 Item 12.8
(G)

d) formwork @ 10 per cent of the cost of concrete 604.10

e) Overhead charges @ 0.25 on (a+b+c+d) 1661.28

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 830.64

Rate perm (a+b+c+d+e+f) 9137.01


say 9137.00

9137.00
Ref. to Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
MoRTH Spec.
12.11 B Case II With Batching Plant, Transit Mixer and Concrete Pump
(vii)
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) 6255.00 Item 12.8
(G)
d) formwork @ 10 per cent of the cost of concrete 625.50

e) Overhead charges @ 0.25 on (a+b+c+d) 1720.13

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 860.06

Rate perm (a+b+c+d+e+f) 9460.69


say 9461.00

9461.00
'12.11 B (viii) RCC M35 Grade
Same as for 12.8 (H) except for formwork which shall be @ 10
per cent of the cost of concrete instead of 3 per cent.
Case I Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) 6178.00 Item 12.8
(H) Case I

d) formwork @ 10 per cent of the cost of concrete 617.80

e) Overhead charges @ 0.25 on (a+b+c+d) 1698.95

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 849.48

Rate perm (a+b+c+d+e+f) 9344.23


say 9344.00

9344.00
12.11 B Case II With Batching Plant, Transit Mixer and Concrete Pump
(viii)
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) 6674.00 Item 12.8
(H)

d) formwork @ 10 per cent of the cost of concrete 667.40 DIR used


item
e) Overhead charges @ 0.25 on (a+b+c+d) 1835.35

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 917.68

Rate perm (a+b+c+d+e+f) 10094.43


say 10094.00

10094.00
Ref. to Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
MoRTH Spec.
'12.11 B (ix) RCC M40 Grade
Using Batching Plant, Transit Mixer and Concrete Pump

Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 51.60 8939.12 461258.59 M-086

Coarse Sand cum 54.00 1176.20 63514.80 M-004

20 mm Aggregate cum 64.80 1529.06 99083.09 M-053

10 mm Aggregate cum 43.20 1529.06 66055.39 M-051

Admixture kg 206.00 166.73 34345.63 M-186

b) Labour
Mate day 0.84 329.34 276.64 L-12

Mason day 3.00 352.86 1058.58 L-11

Mazdoor day 18.00 152.91 2752.31 L-13

c) Machinery
Batching Plant hour 6.00 2301.82 13810.94 P&M-002

Generator 100 KVA hour 6.00 730.42 4382.52 P&M-080

Loader 1 cum capacity hour 6.00 803.34 4820.07 P&M-017

Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 973.89 14608.40 P&M-049

Transit Mixer 4 cum capacity for lead beyond 1 km. tonne.km 300xL 47.05 42343.20 Lead= 3 ,
P&M-050
Concrete Pump hour 6.00 275.23 1651.38 P&M-007

Per Cum Basic Cost of Labour, Material & Machinery 6750.00


(a+b+c)
d) Formwork @ 10 per cent on cost of concrete i.e. cost of 80996.15
material, labour and machinery
e) Overhead charges @ 0.25 on (a+b+c+d) 222739.43

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 111369.71

cost of 120 cum = a+b+c+d+e+f 1225066.84

Rate per cum = (a+b+c+d+e+f)/120 10208.89


say 10209.00

10209.00
Ref. to Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
MoRTH Spec.
12.11 C C Bottom Plug
Concrete to be placed using tremie pipe
Note: 10% extra cement to be added where under water
concreting is involved
(i) PCC Grade M20
Case I Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 5.55 8939.12 49612.12 M-086

Coarse sand cum 6.75 1176.20 7939.35 M-005

40 mm Aggregate cum 5.40 1411.44 7621.78 M-055

20 mm Aggregate cum 5.40 1529.06 8256.92 M-053

10 mm Aggregate cum 2.70 1529.06 4128.46 M-051

Admixture Kg 18.60 166.73 3101.11 M-186

b) Labour
Mate day 0.90 329.34 296.40 L-12

Mason day 1.50 352.86 529.29 L-11

Mazdoor day 20.00 152.91 3058.12 L-13

c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 237.59 1425.55 P&M-009

Generator 33 KVA hour 6.00 365.80 2194.79 P&M-079

Light Crane 3 tonnes capacity for handling tremie pipe hour 6.00 374.03 2244.19 P&M-013

Per Cum Basic Cost of Labour, Material & Machinery 6028.00


(a+b+c)
Add 5 per cent of cost of material and labour towards cost of 4227.18
forming sump, protective bunds, chiselling and making
arrangements for under water concreting with tremie pipe.
d) Overhead charges @ 0.25 on (a+b+c) 23658.82

e) Contractor's profit @ 0.1 on (a+b+c+d) 11829.41

cost of 15 cum = a+b+c+d+e 130123.48

Rate per cum = (a+b+c+d+e)/15 8674.90


say 8675.00

8675.00
Ref. to Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
MoRTH Spec.
12.11 C Case II Using Batching Plant, Transit Mixer and Crane/concrete
(i) pump
Unit ; cum
Taking Output = 120 cum
a) Material
Cement tonne 44.40 8939.12 396896.93 M-086

Coarse sand cum 54.00 1176.20 63514.80 M-004

20 mm Aggregate cum 64.80 1529.06 99083.09 M-053

10 mm Aggregate cum 43.20 1529.06 66055.39 M-051

Admixture Kg 148.80 166.73 24808.88 M-186

b) Labour
Mate day 0.88 329.34 289.82 L-12

Mason day 3.00 352.86 1058.58 L-11

Mazdoor day 18.00 152.91 2752.31 L-13

c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 2301.82 13810.94 P&M-002

Generator 100 KVA hour 6.00 730.42 4382.52 P&M-080

Loader 1 cum capacity hour 6.00 803.34 4820.07 P&M-017

Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 973.89 14608.40 P&M-049

Transit Mixer 4 cum capacity, lead beyond 1 Km, L - lead in tonne.km 300L 47.05 42343.20 P&M-050
Kilometer Lead= 3 km

Concrete Pump hour 6.00 275.23 1651.38 P&M-007

Per Cum Basic Cost of Labour, Material & Machinery 6134.00


(a+b+c)
Add 5 per cent of cost of material and labour towards cost of 32722.99
forming sump, protective bunds, chiselling and making
arrangements for under water concreting with tremie pipe.
d) Overhead charges @ 0.25 on (a+b+c) 192199.83

e) Contractor's profit @ 0.1 on (a+b+c+d) 96099.91

cost of 120 cum = a+b+c+d+e 1057099.04

Rate per cum = (a+b+c+d+e)/120 8809.16


say 8809.00

8809.00
Ref. to Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
MoRTH Spec.
'12.11 C (ii) PCC Grade M25
Case I Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 5.99 8939.12 53545.33 M-086

Coarse sand cum 6.75 1176.20 7939.35 M-005

40 mm Aggregate cum 5.40 1411.44 7621.78 M-055

20 mm Aggregate cum 5.40 1529.06 8256.92 M-053

10 mm Aggregate cum 2.70 1529.06 4128.46 M-051

Admixture Kg 21.60 166.73 3601.29 M-186

b) Labour
Mate day 0.90 329.34 296.40 L-12

Mason day 1.50 352.86 529.29 L-11

Mazdoor day 20.00 152.91 3058.12 L-13

c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 237.59 1425.55 P&M-009

Generator 33 KVA hour 6.00 365.80 2194.79 P&M-079

Light Crane of 3 tonnes capacity for handling tremie pipe hour 6.00 374.03 2244.19 P&M-013

Per Cum Basic Cost of Labour, Material & Machinery 6323.00


(a+b+c)
Add 5 per cent of cost of material and labour towards cost of 4448.85
forming sump, protective bunds, chiselling and making
arrangements for under water concreting with tremie pipe.
d) Overhead charges @ 0.25 on (a+b+c) 24822.58

e) Contractor's profit @ 0.1 on (a+b+c+d) 12411.29

cost of 15 cum = a+b+c+d+e 136524.19

Rate per cum = (a+b+c+d+e)/15 9101.61


say 9102.00

9102.00
Ref. to Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
MoRTH Spec.
12.11 C Case II Using Batching Plant, Transit Mixer and Crane/concrete
(ii) pump
Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 47.88 8939.12 428005.07 M-086

Coarse sand cum 54.00 1176.20 63514.80 M-004

20 mm Aggregate cum 64.80 1529.06 99083.09 M-053

10 mm Aggregate cum 43.20 1529.06 66055.39 M-051

Admixture Kg 172.80 166.73 28810.31 M-186

b) Labour
Mate day 0.88 329.34 289.82 L-12

Mason day 3.00 352.86 1058.58 L-11

Mazdoor day 18.00 152.91 2752.31 L-13

c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 2301.82 13810.94 P&M-002

Generator 100 KVA hour 6.00 730.42 4382.52 P&M-080

Loader 1 cum capacity hour 6.00 803.34 4820.07 P&M-017

Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 973.89 14608.40 P&M-049

Transit Mixer 4 cum capacity, lead beyond 1 Km, L - lead in tonne.km 300L 47.05 42343.20 P&M-050
Kilometer Lead= 3 km

Concrete Pump hour 6.00 275.23 1651.38 P&M-007

Per Cum Basic Cost of Labour, Material & Machinery 6427.00


(a+b+c)
Add 5 per cent of cost of material and labour towards cost of 34478.47
forming sump, protective bunds, chiselling and making
arrangements for under water concreting with tremie pipe.
d) Overhead charges @ 0.25 on (a+b+c) 201416.09

e) Contractor's profit @ 0.1 on (a+b+c+d) 100708.04

cost of 120 cum = a+b+c+d+e 1107788.48

Rate per cum = (a+b+c+d+e)/120 9231.57


say 9232.00

9232.00
Ref. to Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
MoRTH Spec.
'12.11 C (iii) PCC Grade M30
Case I Using Concrete Mixer
Unit = 1 cum
Taking output = 15 cum
a) Material
Cement tonne 6.08 8939.12 54349.85 M-086

Coarse sand cum 6.75 1176.20 7939.35 M-005

40 mm Aggregate cum 5.40 1411.44 7621.78 M-055

20 mm Aggregate cum 5.40 1529.06 8256.92 M-053

10 mm Aggregate cum 2.70 1529.06 4128.46 M-051

Admixture Kg 21.60 166.73 3601.29 M-186

b) Labour
Mate day 0.90 329.34 296.40 L-12

Mason day 1.50 352.86 529.29 L-11

Mazdoor day 20.00 152.91 3058.12 L-13

c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 237.59 1425.55 P&M-009

Generator 33 KVA hour 6.00 365.80 2194.79 P&M-079

Light Crane of 3 tonnes capacity for handling tremie pipe hour 6.00 374.03 2244.19 P&M-013

Per Cum Basic Cost of Labour, Material & Machinery 6377.00


(a+b+c)
Add 5 per cent of cost of material and labour towards cost of 4489.07
forming sump, protective bunds, chiselling and making
arrangements for under water concreting with tremie pipe.
d) Overhead charges @ 0.25 on (a+b+c) 25033.77

e) Contractor's profit @ 0.1 on (a+b+c+d) 12516.88

cost of 15 cum = a+b+c+d+e 137685.72

Rate per cum = (a+b+c+d+e)/15 9179.05


say 9179.00

9179.00
Ref. to Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
MoRTH Spec.
12.11 C Case II Using Batching Plant, Transit Mixer and Crane/concrete
(iii) pump
Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 48.64 8939.12 434798.80 M-086

Coarse sand cum 54.00 1176.20 63514.80 M-004

20 mm Aggregate cum 64.80 1529.06 99083.09 M-053

10 mm Aggregate cum 43.20 1529.06 66055.39 M-051

Admixture Kg 172.80 166.73 28810.31 M-186

b) Labour
Mate day 0.88 329.34 289.82 L-12

Mason day 3.00 352.86 1058.58 L-11

Mazdoor day 18.00 152.91 2752.31 L-13

c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 2301.82 13810.94 P&M-002

Generator 100 KVA hour 6.00 730.42 4382.52 P&M-080

Loader 1 cum capacity hour 6.00 803.34 4820.07 P&M-017

Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 973.89 14608.40 P&M-049

Transit Mixer 4 cum capacity, lead beyond 1 Km, L - lead in tonne.km 300L 47.05 42343.20 P&M-050
Kilometer Lead= 3 km

Concrete Pump hour 6.00 275.23 1651.38 P&M-007

Per Cum Basic Cost of Labour, Material & Machinery 6484.00


(a+b+c)
Add 5 per cent of cost of material and labour towards cost of 34818.15
forming sump, protective bunds, chiselling and making
arrangements for under water concreting with tremie pipe.
d) Overhead charges @ 0.25 on (a+b+c) 203199.44

e) Contractor's profit @ 0.1 on (a+b+c+d) 101599.72

cost of 120 cum = a+b+c+d+e 1117596.93

Rate per cum = (a+b+c+d+e)/120 9313.31


say 9313.00

9313.00
Ref. to Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
MoRTH Spec.
'12.11 C (iv) PCC Grade M35
Case I Using Concrete Mixer
Unit = 1 cum
Taking output = 15 cum
a) Material
Cement tonne 6.29 8939.12 56227.06 M-086

Coarse sand cum 6.75 1176.20 7939.35 M-005

40 mm Aggregate cum 5.40 1411.44 7621.78 M-055

20 mm Aggregate cum 5.40 1529.06 8256.92 M-053

10 mm Aggregate cum 2.70 1529.06 4128.46 M-051

Admixture Kg 21.60 166.73 3601.29 M-186

b) Labour
Mate day 0.90 329.34 296.40 L-12

Mason day 1.50 352.86 529.29 L-11

Mazdoor day 20.00 152.91 3058.12 L-13

c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 237.59 1425.55 P&M-009

Generator 33 KVA hour 6.00 365.80 2194.79 P&M-079

Light Crane of 3 tonnes capacity for handling tremie pipe hour 6.00 374.03 2244.19 P&M-013

Per Cum Basic Cost of Labour, Material & Machinery 6502.00


(a+b+c)
Add 5 per cent of cost of material and labour towards cost of 4582.93
forming sump, protective bunds, chiselling and making
arrangements for under water concreting with tremie pipe.
d) Overhead charges @ 0.25 on (a+b+c) 25526.54

e) Contractor's profit @ 0.1 on (a+b+c+d) 12763.27

cost of 15 cum = a+b+c+d+e 140395.95

Rate per cum = (a+b+c+d+e)/15 9359.73


say 9360.00

9360.00
Ref. to Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
MoRTH Spec.
12.11 C Case II Using Batching Plant, Transit Mixer and Crane/concrete
(iv) pump
Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 50.28 8939.12 449458.95 M-086

Coarse sand cum 54.00 1176.20 63514.80 M-004

20 mm Aggregate cum 64.80 1529.06 99083.09 M-053

10 mm Aggregate cum 43.20 1529.06 66055.39 M-051

Admixture Kg 172.80 166.73 28810.31 M-186

b) Labour
Mate day 0.88 329.34 289.82 L-12

Mason day 3.00 352.86 1058.58 L-11

Mazdoor day 18.00 152.91 2752.31 L-13

c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 2301.82 13810.94 P&M-002

Generator 100 KVA hour 6.00 730.42 4382.52 P&M-080

Loader 1 cum capacity hour 6.00 803.34 4820.07 P&M-017

Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 973.89 14608.40 P&M-049

Transit Mixer 4 cum capacity, lead beyond 1 Km, L - lead in tonne.km 300L 47.05 42343.20 P&M-050
Kilometer Lead= 3 km

Concrete Pump hour 6.00 275.23 1651.38 P&M-007

Per Cum Basic Cost of Labour, Material & Machinery 6606.00


(a+b+c)
Add 5 per cent of cost of material and labour towards cost of 35551.16
forming sump, protective bunds, chiselling and making
arrangements for under water concreting with tremie pipe.
d) Overhead charges @ 0.25 on (a+b+c) 207047.73

e) Contractor's profit @ 0.1 on (a+b+c+d) 103523.87

cost of 120 cum = a+b+c+d+e 1138762.53

Rate per cum = (a+b+c+d+e)/120 9489.69


say 9490.00

9490.00
12.11 D Intermediate plug
(i) Grade M20 PCC
Same as in bottom plug concrete, excluding cost of forming
sump, protective bunds, chiseling etc.
Case I Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) 6028.00

d) Overhead charges @ 0.25 on (a+b+c) 1507.00

e) Contractor's profit @ 0.1 on (a+b+c+d) 753.50

Rate per cum = (a+b+c+d+e) 8288.50


say 8289.00

8289.00
12.11 D Case II Using Batching Plant, Transit Mixer and Crane/concrete
(i) pump
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) 6134.00

d) Overhead charges @ 0.25 on (a+b+c) 1533.50

e) Contractor's profit @ 0.1 on (a+b+c+d) 766.75

Rate per cum = (a+b+c+d+e) 8434.25


say 8434.00

8434.00
Ref. to Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
MoRTH Spec.
'12.11 D (ii) Grade M25 PCC
Same as in bottom plug concrete, excluding cost of forming
sump, protective bunds, chiseling etc.
Case I Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) 6323.00

d) Overhead charges @ 0.25 on (a+b+c) 1580.75

e) Contractor's profit @ 0.1 on (a+b+c+d) 790.38

Rate per cum = (a+b+c+d+e) 8694.13


say 8694.00

8694.00
12.11 D Case II Using Batching Plant, Transit Mixer and Crane/concrete
(ii) pump
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) 6427.00

d) Overhead charges @ 0.25 on (a+b+c) 1606.75

e) Contractor's profit @ 0.1 on (a+b+c+d) 803.38

Rate per cum = (a+b+c+d+e) 8837.13


say 8837.00

8837.00
'12.11 D (iii) Grade M30 PCC
Same as in bottom plug concrete, excluding cost of forming
sump, protective bunds, chiseling etc.
Case I Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) 6377.00

d) Overhead charges @ 0.25 on (a+b+c) 1594.25

e) Contractor's profit @ 0.1 on (a+b+c+d) 797.13

Rate per cum = (a+b+c+d+e) 8768.38


say 8768.00

8768.00
12.11 D Case II Using Batching Plant, Transit Mixer and Crane/concrete
(iii) pump
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) 6484.00

d) Overhead charges @ 0.25 on (a+b+c) 1621.00

e) Contractor's profit @ 0.1 on (a+b+c+d) 810.50

Rate per cum = (a+b+c+d+e) 8915.50


say 8916.00

8916.00
12.11 E Top plug
(i) Grade M15 PCC
Same as Item 12.8(a) excluding formwork
Case I Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) 4899.00

d) Overhead charges @ 0.25 on (a+b+c) 1224.75

e) Contractor's profit @ 0.1 on (a+b+c+d) 612.38

Rate per cum = (a+b+c+d+e) 6736.13


say 6736.00
'12.11 E (ii) Grade M20 PCC 6736.00
Same as Item 12.8(b) excluding formwork
Case I Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) 5438.00

d) Overhead charges @ 0.25 on (a+b+c) 1359.50

e) Contractor's profit @ 0.1 on (a+b+c+d) 679.75

Rate per cum = (a+b+c+d+e) 7477.25


say 7477.00
Ref. to Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
MoRTH Spec.
'12.11 E (iii) Grade M25 PCC 7477.00
Same as Item 12.8 (d) excluding formwork
Case I Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) 5933.00

d) Overhead charges @ 0.25 on (a+b+c) 1483.25

e) Contractor's profit @ 0.1 on (a+b+c+d) 741.63

Rate per cum = (a+b+c+d+e) 8157.88


say 8158.00

8158.00
12.11 E Case II Using Batching Plant, Transit Mixer and Crane/concrete
(iii) pump
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) 5806.00

d) Overhead charges @ 0.25 on (a+b+c) 1451.50

e) Contractor's profit @ 0.1 on (a+b+c+d) 725.75

Rate per cum = (a+b+c+d+e) 7983.25


say 7983.00

7983.00
'12.11 E (iv) Grade M30 PCC
Same as Item 12.8(f) excluding formwork
Case I Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) 5986.00

d) Overhead charges @ 0.25 on (a+b+c) 1496.50

e) Contractor's profit @ 0.1 on (a+b+c+d) 748.25

Rate per cum = (a+b+c+d+e) 8230.75


say 8231.00

8231.00
12.11 E Case II Using Batching Plant, Transit Mixer and Crane/concrete
(iv) pump
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) 5855.00

d) Overhead charges @ 0.25 on (a+b+c) 1463.75

e) Contractor's profit @ 0.1 on (a+b+c+d) 731.88

Rate per cum = (a+b+c+d+e) 8050.63


say 8051.00

8051.00
Ref. to Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
MoRTH Spec.
12.11 F Well cap
(i) RCC Grade M20
Case I Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 5.12 8939.12 45768.29 M-086

Coarse sand cum 6.75 1176.20 7939.35 M-005

20 mm Aggregate cum 8.10 1529.06 12385.39 M-053

10 mm Aggregate cum 5.40 1529.06 8256.92 M-051

b) Labour
Mate day 0.86 329.34 283.23 L-12

Mason day 1.50 352.86 529.29 L-11

Mazdoor day 20.00 152.91 3058.12 L-13

c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 237.59 1425.55 P&M-009

Generator 33 KVA hour 6.00 365.80 2194.79 P&M-079

Form Work @ 4 per cent of a+b+c 3273.64

d) Overhead charges @ 0.25 on (a+b+c) 21278.64

e) Contractor's profit @ 0.1 on (a+b+c+d) 10639.32

cost of 15 cum = a+b+c+d+e 117032.54

Rate per cum = (a+b+c+d+e)/15 7802.17


say 7802.00

7802.00
12.11 F Case II Using Batching Plant, Transit Mixer and Concrete Pump
(i)
Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 40.92 8939.12 365788.79 M-086

Coarse sand cum 54.00 1176.20 63514.80 M-004

20 mm Aggregate cum 64.80 1529.06 99083.09 M-053

10 mm Aggregate cum 43.20 1529.06 66055.39 M-051

b) Labour
Mate day 0.84 329.34 276.64 L-12

Mason day 3.00 352.86 1058.58 L-11

Mazdoor day 18.00 152.91 2752.31 L-13

c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 2301.82 13810.94 P&M-002

Generator 100 KVA hour 6.00 730.42 4382.52 P&M-080

Loader (capacity 1 cum) hour 6.00 803.34 4820.07 P&M-017

Transit Mixer ( capacity 4.0 cu.m )


Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 973.89 14608.40 P&M-049

Lead beyond 1 Km, L - lead in Kilometer tonne.km 300L 47.05 42343.20 P&M-050
Lead= 3 km
Concrete Pump hour 6.00 275.23 1651.38 P&M-007

Formwork @ 4 per cent of (a+b+c) 27205.84

d) Overhead charges @ 0.25 on (a+b+c) 176837.99

e) Contractor's profit @ 0.1 on (a+b+c+d) 88419.00

cost of 120 cum = a+b+c+d+e 972608.95

Rate per cum = (a+b+c+d+e)/120 8105.07


say 8105.00

8105.00
Ref. to Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
MoRTH Spec.
12.11 F (ii) RCC Grade M25
Case I Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 6.05 8939.12 54081.68 M-086

Coarse sand cum 6.75 1176.20 7939.35 M-005

20 mm Aggregate cum 8.10 1529.06 12385.39 M-053

10 mm Aggregate cum 5.40 1529.06 8256.92 M-051

b) Labour
Mate day 0.86 329.34 283.23 L-12

Mason day 1.50 352.86 529.29 L-11

Mazdoor day 20.00 152.91 3058.12 L-13

c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 237.59 1425.55 P&M-009

Generator 33 KVA hour 6.00 365.80 2194.79 P&M-079

Form Work @ 3.75 per cent of a+b+c 3380.79

d) Overhead charges @ 0.25 on (a+b+c) 23383.78

e) Contractor's profit @ 0.1 on (a+b+c+d) 11691.89

cost of 15 cum = a+b+c+d+e 128610.77

Rate per cum = (a+b+c+d+e)/15 8574.05


say 8574.00

8574.00
12.11 F Case II Using Batching Plant, Transit Mixer and Concrete Pump
(ii)
Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 48.40 8939.12 432653.41 M-086

Coarse sand cum 54.00 1176.20 63514.80 M-004

20 mm Aggregate cum 64.80 1529.06 99083.09 M-053

10 mm Aggregate cum 43.20 1529.06 66055.39 M-051

b) Labour
Mate day 0.84 329.34 276.64 L-12

Mason day 3.00 352.86 1058.58 L-11

Mazdoor day 18.00 152.91 2752.31 L-13

c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 2301.82 13810.94 P&M-002

Generator 100 KVA hour 6.00 730.42 4382.52 P&M-080

Loader (capacity 1 cum) hour 6.00 803.34 4820.07 P&M-017

Transit Mixer ( capacity 4.0 cu.m )


Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 973.89 14608.40 P&M-049

Lead beyond 1 Km, L - lead in Kilometer tonne.km 300L 47.05 42343.20 P&M-050
Lead= 3 km
Concrete Pump hour 6.00 275.23 1651.38 P&M-007

Formwork @ 3.75 per cent of ( a+b+c) 28012.90

d) Overhead charges @ 0.25 on (a+b+c) 193755.91

e) Contractor's profit @ 0.1 on (a+b+c+d) 96877.95

cost of 120 cum = a+b+c+d+e 1065657.50

Rate per cum = (a+b+c+d+e)/120 8880.48


say 8880.00

8880.00
Ref. to Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
MoRTH Spec.
12.11 F (iii) RCC Grade M30
Case I Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 6.10 8939.12 54528.63 M-086

Coarse sand cum 6.75 1176.20 7939.35 M-005

20 mm Aggregate cum 8.10 1529.06 12385.39 M-053

10 mm Aggregate cum 5.40 1529.06 8256.92 M-051

b) Labour
Mate day 0.86 329.34 283.23 L-12

Mason day 1.50 352.86 529.29 L-11

Mazdoor day 20.00 152.91 3058.12 L-13

c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 237.59 1425.55 P&M-009

Generator 33 KVA hour 6.00 365.80 2194.79 P&M-079

Formwork @ 3.5 per cent of (a+b+c) 3171.04

d) Overhead charges @ 0.25 on (a+b+c) 23443.08

e) Contractor's profit @ 0.1 on (a+b+c+d) 11721.54

cost of 15 cum = a+b+c+d+e 128936.94

Rate per cum = (a+b+c+d+e)/15 8595.80


say 8596.00

8596.00
12.11 F Case II Using Batching Plant, Transit Mixer and Concrete Pump
(iii)
Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 48.79 8939.12 436139.66 M-086

Coarse sand cum 54.00 1176.20 63514.80 M-004

20 mm Aggregate cum 64.80 1529.06 99083.09 M-053

10 mm Aggregate cum 43.20 1529.06 66055.39 M-051

b) Labour
Mate day 0.84 329.34 276.64 L-12

Mason day 3.00 352.86 1058.58 L-11

Mazdoor day 18.00 152.91 2752.31 L-13

c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 2301.82 13810.94 P&M-002

Generator 100 KVA hour 6.00 730.42 4382.52 P&M-080

Loader (capacity 1 cum) hour 6.00 803.34 4820.07 P&M-017

Transit Mixer ( capacity 4.0 cu.m )


Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 973.89 14608.40 P&M-049

Lead beyond 1 Km, L - lead in Kilometer tonne.km 300L 47.05 42343.20 P&M-050
Lead= 3 km
Concrete Pump hour 6.00 275.23 1651.38 P&M-007

Formwork @ 3.5 per cent of (a+b+c) 26267.39

d) Overhead charges @ 0.25 on (a+b+c) 194191.10

e) Contractor's profit @ 0.1 on (a+b+c+d) 97095.55

cost of 120 cum = a+b+c+d+e 1068051.03

Rate per cum = (a+b+c+d+e)/120 8900.43


say 8900.00

8900.00
Ref. to Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
MoRTH Spec.
12.11 F (iv) RCC Grade M35
Case I Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 6.33 8939.12 56584.63 M-086

Coarse sand cum 6.75 1176.20 7939.35 M-005

20 mm Aggregate cum 8.10 1529.06 12385.39 M-053

10 mm Aggregate cum 5.40 1529.06 8256.92 M-051

b) Labour
Mate day 0.86 329.34 283.23 L-12

Mason day 1.50 352.86 529.29 L-11

Mazdoor day 20.00 152.91 3058.12 L-13

c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 237.59 1425.55 P&M-009

Generator 33 KVA hour 6.00 365.80 2194.79 P&M-079

Formwork @ 3 per cent of (a+b+c) 2779.72

d) Overhead charges @ 0.25 on (a+b+c) 23859.25

e) Contractor's profit @ 0.1 on (a+b+c+d) 11929.62

cost of 15 cum = a+b+c+d+e 131225.86

Rate per cum = (a+b+c+d+e)/15 8748.39


say 8748.00

8748.00
12.11 F Case II Using Batching Plant, Transit Mixer and Concrete Pump
(iv)
Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 50.64 8939.12 452677.04 M-086

Coarse sand cum 54.00 1176.20 63514.80 M-004

20 mm Aggregate cum 64.80 1529.06 99083.09 M-053

10 mm Aggregate cum 43.20 1529.06 66055.39 M-051

b) Labour
Mate day 0.84 329.34 276.64 L-12

Mason day 3.00 352.86 1058.58 L-11

Mazdoor day 18.00 152.91 2752.31 L-13

c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 2301.82 13810.94 P&M-002

Generator 100 KVA hour 6.00 730.42 4382.52 P&M-080

Loader (capacity 1 cum) hour 6.00 803.34 4820.07 P&M-017

Transit Mixer ( capacity 4.0 cu.m )


Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 973.89 14608.40 P&M-049

Lead beyond 1 Km, L - lead in Kilometer tonne.km 300L 47.05 42343.20 P&M-050
Lead= 3 km
Concrete Pump hour 6.00 275.23 1651.38 P&M-007

Formwork @ 3 per cent of (a+b+c) 23011.03

d) Overhead charges @ 0.25 on (a+b+c) 197511.35

e) Contractor's profit @ 0.1 on (a+b+c+d) 98755.67

cost of 120 cum = a+b+c+d+e 1086312.42

Rate per cum = (a+b+c+d+e)/120 9052.60


say 9053.00

9053.00
Note Where ever concrete is carried out using batching plant, transit
mixer, concrete pump, Admixtures @ 0.4 per cent of weight of
cement may be added for achieving desired slump of concrete.
Ref. to Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
MoRTH Spec.
'12.11 F (v) RCC M40 Grade
Using Batching Plant, Transit Mixer and Concrete Pump

Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 52.20 8939.12 466622.06 M-086

Coarse Sand cum 54.00 1176.20 63514.80 M-004

20 mm Aggregate cum 64.80 1529.06 99083.09 M-053

10 mm Aggregate cum 43.20 1529.06 66055.39 M-051

Admixture kg 206.00 166.73 34345.63 M-186

b) Labour
Mate day 0.84 329.34 276.64 L-12

Mason day 3.00 352.86 1058.58 L-11

Mazdoor day 18.00 152.91 2752.31 L-13

c) Machinery
Batching Plant hour 6.00 2301.82 13810.94 P&M-002

Generator 100 KVA hour 6.00 730.42 4382.52 P&M-080

Loader 1 cum capacity hour 6.00 803.34 4820.07 P&M-017

Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 973.89 14608.40 P&M-049

Transit Mixer 4 cum capacity for lead beyond 1 km. tonne.km 300.L 47.05 42343.20 P&M-050
Lead= 3 km

Concrete Pump hour 6.00 275.23 1651.38 P&M-007

Formwork @ 3 per cent on cost of concrete i.e. cost of 24459.75


material, labour and machinery
d) Overhead charges @ 0.25 on (a+b+c) 209946.19

e) Contractor's profit @ 0.1 on (a+b+c+d) 104973.10

cost of 120 cum = a+b+c+d+e 1154704.06

Rate per cum = (a+b+c+d+e)/120 9622.53


say 9623.00

9623.00
12.12 Section 1200 Sinking of 6 m external diameter well (other than pneumatic
method of sinking) through all types of strata namely sandy
soil, clayey soil and rock as shown against each case,
complete as per drawing and technical specifications.
Depth of sinking is reckoned from bed level.

Unit = Running Meter.


Taking output = 1 m
Diameter of well - 6 m.
A Sandy Soil
(i) Depth below bed level upto 3.0 M
Rate of sinking = 0.50 m per hour.
a) Labour
Mate day 0.12 329.34 39.52 L-12

Sinker ( skilled ) day 1.00 244.65 244.65 L-15

Sinking helper ( semi-skilled ) day 2.00 176.43 352.86 L-14

b) Machinery
Hire & running charges of crane with grab bucket of 0.75 hour 2.00 1393.80 2787.59 P&M-075
cum capacity and accessories.
Consumables in sinking @10 per cent of (b) 278.76

c) Overhead charges @ 0.25 on (a+b) 925.85

d) Contractor's profit @ 0.1 on (a+b+c) 462.92

Rate per metre = (a+b+c+d) 5092.15


say 5092.00
Ref. to Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
MoRTH Spec.
12.12 A (ii) Beyond 3m upto 10m depth
Rate of sinking = 0.33 m per hour.
a) Labour
Mate day 0.15 329.34 49.40 L-12

Sinker day 1.25 244.65 305.81 L-15

Sinking helper ( semi-skilled ) day 2.50 176.43 441.08 L-14

b) Machinery
Hire & running charges of crane with grab bucket of 0.75 hour 3.00 1393.80 4181.39 P&M-075
cum capacity and accessories
Consumables in sinking @10 per cent of (b) 418.14

c) Overhead charges @ 0.25 on (a+b) 1348.95

d) Contractor's profit @ 0.1 on (a+b+c) 674.48

Rate per metre = (a+b+c+d) 7419.25


say 7419.00
12.12 A (iii) Beyond 10m upto 20m
a Add 5 per cent for every additional meter depth of sinking over
the rate of sinking for the previous meter
11th m 5% 7790.00

12th m 5% 8180.00

13th m 5% 8589.00

14th m 5% 9018.00

15th m 5% 9469.00

16th m 5% 9942.00

17th m 5% 10439.00

18th m 5% 10961.00

19th m 5% 11509.00

20th m 5% 12084.00

Total Cost from 10m upto 20m 97981.00

Avg Rate per metre 9798.00


12.12 A (iv) Beyond 20m upto 30 m
a Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 20 per cent of cost for Kentledge including supports, (a) (b) Including
loading arrangement and Labour. 20% for
Kentledge
21st m 7.5% 12990.00 15588.00

22nd m 7.5% 13964.00 16757.00

23rd m 7.5% 15011.00 18013.00

24th m 7.5% 16137.00 19364.00

25th m 7.5% 17347.00 20816.00

26th m 7.5% 18648.00 22378.00

27th m 7.5% 20047.00 24056.00

28th m 7.5% 21551.00 25861.00

29th m 7.5% 23167.00 27800.00

30th m 7.5% 24905.00 29886.00

Total Cost from 20m upto 30m 183767.00 220519.00

Avg Rate per metre 18377.00 22052.00


Ref. to Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
MoRTH Spec.
12.12 A (v) Beyond 30m upto 40 m
a Add 10 per cent for every additional meter depth of sinking over
the rate of sinking for the previous meter
b Add 20 per cent of cost for Kentledge including supports, (a) (b)Including
loading arrangement and Labour. 20% for
Kentledge
31st m 10% 27396.00 32875.00

32nd 10% 30136.00 36163.00

33rd m 10% 33150.00 39780.00

34th m 10% 36465.00 43758.00

35th m 10% 40112.00 48134.00

36th m 10% 44123.00 52948.00

37th m 10% 48535.00 58242.00

38th m 10% 53389.00 64067.00

39th m 10% 58728.00 70474.00

40th m 10% 64601.00 77521.00

Total Cost from 30m upto 40m 436635.00 523962.00

Avg Rate per metre 43664.00 52396.00


12.12 B Clayey Soil ( 6m dia. Well )
Unit = Running Meter.
Taking output = 1 meter
(i) Depth below bed level upto 3.0 M
Rate of sinking = 0.33 m per hour.
a) Labour
Mate day 0.15 329.34 49.40 L-12

Sinker ( skilled ) day 1.50 244.65 366.97 L-15

Sinking helper ( semi-skilled ) day 2.25 176.43 396.97 L-14

b) Machinery
Hire & running charges of crane with grab bucket of 0.75 hour 3.00 1393.80 4181.39 P&M-075
cum capacity and accessories
Consumables in sinking @ 10 per cent of (b) 418.14

c) Overhead charges @ 0.25 on (a+b) 1353.22

d) Contractor's profit @ 0.1 on (a+b+c) 676.61

Rate per metre = (a+b+c+d) 7442.70


say 7443.00
12.12 B (ii) Beyond 3m upto 10m depth
Rate of sinking = 0.17 m per hour.
a) Labour
Mate day 0.30 329.34 98.80 L-12

Sinker day 3.00 244.65 733.95 L-15

Sinking helper ( semi-skilled ) day 4.50 176.43 793.94 L-14

b) Machinery
Hire & running charges of crane with grab bucket of 0.75 hour 6.00 1393.80 8362.78 P&M-075
cum capacity and accessories.
Air compressor with pneumatic chisel attachment for cutting hour 2.00 334.04 668.08 P&M-063
hard clay.
Consumables in sinking @ 10 per cent of (b) 903.09

c) Overhead charges @ 0.25 on (a+b) 2890.16

d) Contractor's profit @ 0.1 on (a+b+c) 1445.08

Rate per metre = (a+b+c+d) 15895.87


say 15896.00
Ref. to Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
MoRTH Spec.
12.12 B (iii) Beyond 10 m upto 20 m
a Add 5 per cent for every additional meter depth of sinking over
the rate of sinking for the previous meter
b Add for dewatering @ 5 per cent of cost, if required. (a)(b)Including
for dewatering
@ 5% of
cost, if
11th m 5% 16691.00 required
17526.00

12th m 5% 17526.00 18402.00

13th m 5% 18402.00 19322.00

14th m 5% 19322.00 20288.00

15th m 5% 20288.00 21302.00

16th m 5% 21302.00 22367.00

17th m 5% 22367.00 23485.00

18th m 5% 23485.00 24659.00

19th m 5% 24659.00 25892.00

20th m 5% 25892.00 27187.00

Total Cost from 10m upto 20m 209934.00 220430.00

Avg Rate per metre 20993.00 22043.00


12.12 B (iv) Beyond 20m upto 30 m
a Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 5 per cent of cost for dewatering of the cost, if required
c Add 25 per cent of cost for Kentledge including supports, (a) (c)Including (b) Including 5%
loading arrangement and Labour ). 25% for for dewatering, if
Kentledge required

21st m 7.5% 27834.00 34793.00 36533.00

22nd m 7.5% 29922.00 37403.00 39273.00

23rd m 7.5% 32166.00 40208.00 42218.00

24th m 7.5% 34578.00 43223.00 45384.00

25th m 7.5% 37171.00 46464.00 48787.00

26th m 7.5% 39959.00 49949.00 52446.00

27th m 7.5% 42956.00 53695.00 56380.00

28th m 7.5% 46178.00 57723.00 60609.00

29th m 7.5% 49641.00 62051.00 65154.00

30th m 7.5% 53364.00 66705.00 70040.00

Total Cost from 20m upto 30m 393769.00 492214.00 516824.00

Avg Rate per metre 39377.00 49221.00 51682.00


12.12 B (v) Beyond 30m upto 40 m
a Add 10 per cent for every additional meter depth of sinking over
the rate of sinking for the previous meter
b Add 5 per cent of cost for dewatering, if required
c Add 20 per cent of cost for Kentledge including supports, (a) (b) Including (b)Including 5%
loading arrangement and Labour). 20% for for dewatering, if
Kentledge required

31st m 10% 58700.00 70440.00 73962.00

32nd 10% 64570.00 77484.00 81358.00

33rd m 10% 71027.00 85232.00 89494.00

34th m 10% 78130.00 93756.00 98444.00

35th m 10% 85943.00 103132.00 108289.00

36th m 10% 94537.00 113444.00 119116.00

37th m 10% 103991.00 124789.00 131028.00

38th m 10% 114390.00 137268.00 144131.00

39th m 10% 125829.00 150995.00 158545.00

40th m 10% 138412.00 166094.00 174399.00

Total Cost from 30m upto 40m 935529.00 1122634.00 1178766.00

Avg Rate per metre 93553.00 112263.00 117877.00


Ref. to Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
MoRTH Spec.
12.12 C Soft Rock (6m dia well )
Unit = Running Meter.
Taking output = 1 m
Depth in Soft rock strata up to 3m
Rate of sinking = 0.25 m per hour.
a) Labour
Mate day 0.92 329.34 302.99 L-12

Sinker ( skilled ) day 3.00 244.65 733.95 L-15

Sinking helper ( semi-skilled ) day 20.00 176.43 3528.60 L-14

Diver day 0.50 294.05 147.03 L-07

b) Machinery
Hire & running charges of crane with grab bucket of 0.75 hour 4.00 1393.80 5575.19 P&M-075
cum capacity and accessories.
Air compressor with pneumatic breakers hour 3.50 334.04 1169.14 P&M-063

Consumables in sinking @ 10 per cent of (b) 674.43

Add for dewatering @ of 5 per cent of (a+b), if required 606.57

c) Overhead charges @ 0.25 on (a+b) 3184.47

d) Contractor's profit @ 0.1 on (a+b+c) 1592.24

Rate per metre = (a+b+c+d) 17514.60


say 17515.00
12.12 D Hard Rock (6m dia well )
Unit = Running Meter
Taking output = 1 m
Depth in hard rock strata upto 3 m
Rate of sinking = 0.17 m per hour.
a) Material
Gelatine 80 per cent Kg 4.00 131.73 526.94 M-110

Electric Detonators each 18.00 4.61 82.99 M-100/100

b) Labour
Mate day 1.56 329.34 513.76 L-12

Driller day 2.00 294.05 588.10 L-06

Blaster day 0.25 352.86 88.22 L-03

Mazdoor day 12.00 152.91 1834.87 L-13

Mazdoor (Skilled) day 4.00 244.65 978.60 L-15

c) Machinery
Hire & running charges of crane with grab bucket of 0.75 hour 6.00 1393.80 8362.78 P&M-075
cum capacity and accessories.
Hire & running charges of compressor with pneumatic hour 2.00 334.04 668.08 P&M-063
breaker/Jack hammer for drilling.
Dewatering @ 5 per cent of cost of (b+c), if required. 651.72

Consumables in sinking @ 10 per cent of cost of (b). 903.09

d) Overhead charges @ 0.25 on (a+b+c) 3799.79

e) Contractor's profit @ 0.1 on (a+b+c+d) 1899.89

Rate per metre = (a+b+c+d+e) 20898.83


say 20899.00

20904.00
Ref. to Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
MoRTH Spec.
12.13 Section 1200 Sinking of 7 m external diameter well ( other than
pneumatic method of sinking ) through all types of strata
namely sandy soil, clayey soil and rock as shown against
each case, complete as per drawing and technical
specifications. Depth of sinking is reckoned from bed level.

Unit = Running Meter.


Taking output = 1 m
Diameter of well - 7 m.
A Sandy Soil
(i) Depth below bed level upto 3.0 M
Rate of sinking = 0.30 m per hour.
a) Labour
Mate day 0.15 329.34 49.40 L-12

Sinker ( skilled ) day 1.25 244.65 305.81 L-15

Sinking helper ( semi-skilled ) day 2.50 176.43 441.08 L-14

b) Machinery
Hire & running charges of crane with grab bucket of 0.75 hour 3.25 1393.80 4529.84 P&M-075
cum capacity and accessories.
Consumables in sinking @10 per cent of (b) 452.98

c) Overhead charges @ 0.25 on (a+b) 1444.78

d) Contractor's profit @ 0.1 on (a+b+c) 722.39

Rate per metre = (a+b+c+d) 7946.28


say 7946.00
12.13 A (ii) Beyond 3m upto 10m depth
Rate of sinking = 0.22 m per hour.
a) Labour
Mate day 0.18 329.34 59.28 L-12

Sinker day 1.50 244.65 366.97 L-15

Sinking helper ( semi-skilled ) day 3.00 176.43 529.29 L-14

b) Machinery
Hire & running charges of crane with grab bucket of 0.75 hour 4.50 1393.80 6272.09 P&M-075
cum capacity and accessories.
Consumables in sinking @10 per cent of (b) 627.21

c) Overhead charges @ 0.25 on (a+b) 1963.71

d) Contractor's profit @ 0.1 on (a+b+c) 981.86

Rate per metre = (a+b+c+d) 10800.41


say 10800.00
12.13 A (iii) Beyond 10m upto 20m
a Add 5 per cent for every additional meter depth of sinking over
the rate of sinking for the previous meter
11th m 5% 11340.00

12th m 5% 11907.00

13th m 5% 12502.00

14th m 5% 13127.00

15th m 5% 13783.00

16th m 5% 14472.00

17th m 5% 15196.00

18th m 5% 15956.00

19th m 5% 16754.00

20th m 5% 17592.00

Total Cost from 10m upto 20m 142629.00

Avg Rate per metre 14263.00


Ref. to Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
MoRTH Spec.
12.13 A (iv) Beyond 20m upto 30 m
a Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 20 per cent of cost for Kentledge including supports, (a) (b)Including
loading arrangement and Labour). 20% for
Kentledge
21st m 7.5% 18911.00 22693.00

22nd m 7.5% 20329.00 24395.00

23rd m 7.5% 21854.00 26225.00

24th m 7.5% 23493.00 28192.00

25th m 7.5% 25255.00 30306.00

26th m 7.5% 27149.00 32579.00

27th m 7.5% 29185.00 35022.00

28th m 7.5% 31374.00 37649.00

29th m 7.5% 33727.00 40472.00

30th m 7.5% 36257.00 43508.00

Total Cost from 20m upto 30m 267534.00 321041.00

Avg Rate per metre 26753.00 32104.00


12.13 A (v) Beyond 30m upto 40 m
a Add 10 per cent for every additional meter depth of sinking over
the rate of sinking for the previous meter
b Add 20 per cent of cost for Kentledge including supports, (a) (b)Including
loading arrangement, and Labour etc. 20% for
Kentledge
31st m 10% 39883.00 47860.00

32nd 10% 43871.00 52645.00

33rd m 10% 48258.00 57910.00

34th m 10% 53084.00 63701.00

35th m 10% 58392.00 70070.00

36th m 10% 64231.00 77077.00

37th m 10% 70654.00 84785.00

38th m 10% 77719.00 93263.00

39th m 10% 85491.00 102589.00

40th m 10% 94040.00 112848.00

Total Cost from 30m upto 40m 635623.00 762748.00

Avg Rate per metre 63562.00 76275.00


12.13 B Clayey Soil ( 7m dia. Well )
Unit = Running Meter.
Taking output = 1 cum
(I) Depth below bed level upto 3.0 M
Rate of sinking = 0.22 m per hour.
a) Labour
Mate day 0.18 329.34 59.28 L-12

Sinker ( skilled ) day 1.50 244.65 366.97 L-15

Sinking helper ( semi-skilled ) day 3.00 176.43 529.29 L-14

b) Machinery
Hire & running charges of crane with grab bucket of 0.75 hour 4.50 1393.80 6272.09 P&M-075
cum capacity and accessories.
Consumables in sinking @ 10 per cent of (b) 627.21

d) Overhead charges @ 0.25 on (a+b) 1963.71

e) Contractor's profit @ 0.1 on (a+b+c) 981.86

Rate per metre = (a+b+c+d) 10800.41


say 10800.00
Ref. to Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
MoRTH Spec.
12.13 B (ii) Beyond 3m upto 10m depth
Rate of sinking = 0.17 m per hour.
a) Labour
Mate day 0.26 329.34 85.63 L-12

Sinker day 2.00 244.65 489.30 L-15

Sinking helper ( semi-skilled ) day 4.00 176.43 705.72 L-14

b) Machinery
Hire & running charges of crane with grab bucket of 0.75 hour 6.00 1393.80 8362.78 P&M-075
cum capacity and accessories.
Air compressor with pneumatic chisel attachment for cutting hour 3.25 334.04 1085.63 P&M-063
hard clay.
Consumables in sinking @ 10 per cent of (b) 944.84

c) Overhead charges @ 0.25 on (a+b) 2918.48

d) Contractor's profit @ 0.1 on (a+b+c) 1459.24

Rate per metre = (a+b+c+d) 16051.62


say 16052.00
12.13 B (iii) Beyond 10 m upto 20 m
a Add 5 per cent for every additional meter depth of sinking over
the rate of sinking for the previous meter
b Add for dewatering @ 5 per cent of cost, if required. (a)
(b) Including
for dewatering
@ 5% of
cost, if
11th m 5% 16854.00 required
17697.00

12th m 5% 17697.00 18582.00

13th m 5% 18582.00 19511.00

14th m 5% 19511.00 20487.00

15th m 5% 20487.00 21511.00

16th m 5% 21511.00 22587.00

17th m 5% 22587.00 23716.00

18th m 5% 23716.00 24902.00

19th m 5% 24902.00 26147.00

20th m 5% 26147.00 27454.00

Total Cost from 10m upto 20m 211994.00 222594.00

Avg Rate per metre 21199.00 22259.00


12.13 B (iv) Beyond 20m upto 30 m
a Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 5 per cent of cost for dewatering on the cost, if required
c Add 25 per cent of cost for Kentledge including supports, (a) ( c) Including (b) Including 5%
loading arrangement and Labour ). 25% for for dewatering, if
Kentledge required

31st m 7.5% 28108.00 35135.00 36892.00

32nd 7.5% 30216.00 37770.00 39659.00

33rd m 7.5% 32482.00 40603.00 42633.00

34th m 7.5% 34918.00 43648.00 45830.00

35th m 7.5% 37537.00 46921.00 49267.00

36th m 7.5% 40352.00 50440.00 52962.00

37th m 7.5% 43378.00 54223.00 56934.00

38th m 7.5% 46631.00 58289.00 61203.00

39th m 7.5% 50128.00 62660.00 65793.00

40th m 7.5% 53888.00 67360.00 70728.00

Total Cost from 30m upto 40m 397638.00 497049.00 521901.00

Avg Rate per metre 39764.00 49705.00 52190.00


Ref. to Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
MoRTH Spec.
12.13 B (v) Beyond 30m upto 40 m
a Add 10 per cent for every additional meter depth of sinking over
the rate of sinking for the previous meter
b Add 5 per cent of cost for dewatering, if required
c Add 20 per cent of cost for Kentledge including supports, (a) ( c) Including (b) Including 5%
loading arrangement and Labour). 20% for for dewatering, if
Kentledge required

31st m 10% 59277.00 71132.00 74689.00

32nd 10% 65205.00 78246.00 82158.00

33rd m 10% 71726.00 86071.00 90375.00

34th m 10% 78899.00 94679.00 99413.00

35th m 10% 86789.00 104147.00 109354.00

36th m 10% 95468.00 114562.00 120290.00

37th m 10% 105015.00 126018.00 132319.00

38th m 10% 115517.00 138620.00 145551.00

39th m 10% 127069.00 152483.00 160107.00

40th m 10% 139776.00 167731.00 176118.00

Total Cost from 30m upto 40m 944741.00 1133689.00 1190374.00

Avg Rate per metre 94474.00 113369.00 119037.00


12.13 C Soft Rock ( 7m dia well )
Unit = Running Meter.
Taking output = 1 m
Depth in soft rock strata upto 3m
Rate of sinking = 0.22 m per hour.
a) Labour
Mate day 0.58 329.34 191.01 L-12

Sinker ( skilled ) day 4.00 244.65 978.60 L-15

Sinking helper ( semi-skilled ) day 10.00 176.43 1764.30 L-14

Diver day 0.75 294.05 220.54 L-07

b) Machinery
Hire & running charges of crane with grab bucket of 0.75 hour 4.50 1393.80 6272.09 P&M-075
cum capacity and accessories.
Air compressor with pneumatic breakers hour 3.75 334.04 1252.65 P&M-063

Consumables in sinking @ 10 per cent of (b) 752.47

Add for dewatering @ of 5 per cent of (a+b), if required 533.96

c) Overhead charges @ 0.25 on (a+b) 2991.41

d) Contractor's profit @ 0.1 on (a+b+c) 1495.70

Rate per metre = (a+b+c+d) 16452.73


say 16453.00
Ref. to Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
MoRTH Spec.
12.13 D Hard Rock ( 7m dia well )
Unit = Running Meter
Taking output = 1 m
Depth in Hard rock strata up to 3 m
Rate of sinking = 0.17 m per hour.
a) Material
Gelatine 80 per cent Kg 7.00 131.73 922.14 M-110

Electric Detonators each 30.00 4.61 138.32 M-100/100

b) Labour
Mate day 1.60 329.34 526.94 L-12

Driller day 2.00 294.05 588.10 L-06

Blaster day 0.25 352.86 88.22 L-03

Mazdoor day 18.00 152.91 2752.31 L-13

Mazdoor (Skilled) day 4.00 244.65 978.60 L-15

Diver day 0.50 294.05 147.03 L-07

c) Machinery
Hire & running charges of crane with grab bucket of 0.75 hour 6.00 1393.80 8362.78 P&M-075
cum capacity and accessories.
Hire & running charges of compressor with pneumatic hour 2.00 334.04 668.08 P&M-063
breaker/Jack hammer for drilling.
Dewatering @ 5 per cent of cost of (b+c), if required. 705.60

Consumables in sinking @ 10 per cent of cost of (b). 973.65

d) Overhead charges @ 0.25 on (a+b+c) 4212.94

e) Contractor's profit @ 0.1 on (a+b+c+d) 2106.47

Rate per metre = (a+b+c+d+e) 23171.17


say 23171.00

23171.00
12.14 Section 1200 Sinking of 8 m external diameter well ( other than
pneumatic method of sinking ) through all types of strata
namely sandy soil, clayey soil and rock as shown against
each case, complete as per drawing and technical
specifications. Depth of sinking is reckoned from bed level.

Unit = Running Meter.


Taking output = 1 m
Diameter of well - 8 m.
A Sandy Soil
(i) Depth below bed level upto 3.0 M
Rate of sinking @ 0.25 m/hour
a) Labour
Mate day 0.18 329.34 59.28 L-12

Sinker ( skilled ) day 1.50 244.65 366.97 L-15

Sinking helper ( semi-skilled ) day 3.00 176.43 529.29 L-14

b) Machinery
Hire & running charges of crane with grab bucket of 0.75 hour 4.00 1393.80 5575.19 P&M-075
cum capacity and accessories.
Consumables in sinking @10 per cent of (b) 557.52

c) Overhead charges @ 0.25 on (a+b) 1772.06

d) Contractor's profit @ 0.1 on (a+b+c) 886.03

Rate per metre = (a+b+c+d) 9746.35


say 9746.00
Ref. to Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
MoRTH Spec.
12.14 A (ii) Beyond 3m upto 10m depth
Rate of sinking @ 0.20 m/hour
a) Labour
Mate day 0.25 329.34 82.33 L-12

Sinker day 1.75 244.65 428.14 L-15

Sinking helper ( semi-skilled ) day 3.50 176.43 617.51 L-14

b) Machinery
Hire & running charges of crane with grab bucket of 0.75 hour 5.00 1393.80 6968.99 P&M-075
cum capacity and accessories.
Consumables in sinking @10 per cent of (b) 696.90

c) Overhead charges @ 0.25 on (a+b) 2198.46

d) Contractor's profit @ 0.1 on (a+b+c) 1099.23

Rate per metre = (a+b+c+d) 12091.56


say 12092.00
12.14 A (iii) Beyond 10m upto 20m
a Add 5 per cent for every additional meter depth of sinking over
the rate of sinking for the previous meter
11th m 5% 12696.00

12th m 5% 13331.00

13th m 5% 13998.00

14th m 5% 14698.00

15th m 5% 15433.00

16th m 5% 16205.00

17th m 5% 17015.00

18th m 5% 17866.00

19th m 5% 18759.00

20th m 5% 19697.00

Total Cost from 10m upto 20m 159698.00

Avg Rate per metre 15970.00


12.14 A (iv) Beyond 20m upto 30 m
a Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 20 per cent of cost for Kentledge including supports, (a) (b) Including
loading arrangement and Labour. 20% for
Kentledge
21st m 7.5% 21174.00 25409.00

22nd m 7.5% 22762.00 27314.00

23rd m 7.5% 24469.00 29363.00

24th m 7.5% 26304.00 31565.00

25th m 7.5% 28277.00 33932.00

26th m 7.5% 30398.00 36478.00

27th m 7.5% 32678.00 39214.00

28th m 7.5% 35129.00 42155.00

29th m 7.5% 37764.00 45317.00

30th m 7.5% 40596.00 48715.00

Total Cost from 20m upto 30m 299551.00 359462.00

Avg Rate per metre 29955.00 35946.00


Ref. to Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
MoRTH Spec.
12.14 A (v) Beyond 30m upto 40 m
a Add 10 per cent for every additional meter depth of sinking over
the rate of sinking for the previous meter
b Add 20 per cent of cost for Kentledge including supports, (a) (b) Including
loading arrangement, and Labour etc. 20% for
Kentledge
31st m 10% 44656.00 53587.00

32nd 10% 49122.00 58946.00

33rd m 10% 54034.00 64841.00

34th m 10% 59437.00 71324.00

35th m 10% 65381.00 78457.00

36th m 10% 71919.00 86303.00

37th m 10% 79111.00 94933.00

38th m 10% 87022.00 104426.00

39th m 10% 95724.00 114869.00

40th m 10% 105296.00 126355.00

Total Cost from 30m upto 40m 711702.00 854042.00

Avg Rate per metre 71170.00 85404.00


12.14 B Clayey Soil ( 8m dia. Well )
Unit = Running Meter.
Taking output = 1 meter
(i) Depth from bed level upto 3.0 M
Rate of sinking @ 0.18 m/hour
a) Labour
Mate day 0.22 329.34 72.45 L-12

Sinker ( skilled ) day 2.00 244.65 489.30 L-15

Sinking helper ( semi-skilled ) hour 3.50 176.43 617.51 L-14

b) Machinery
Hire & running charges of crane with grab bucket of 0.75 5.50 1393.80 7665.88 P&M-075
cum capacity and accessories.
Consumables in sinking @ 10 per cent of (b) 766.59

c) Overhead charges @ 0.25 on (a+b) 2402.93

d) Contractor's profit @ 0.1 on (a+b+c) 1201.47

Rate per metre = (a+b+c+d) 13216.13


say 13216.00
12.14 B (ii) Beyond 3m upto 10m depth
Rate of sinking @ 0.17 m/hour
a) Labour
Mate day 0.32 329.34 105.39 L-12

Sinker day 2.50 244.65 611.62 L-15

Sinking helper ( semi-skilled ) day 4.50 176.43 793.94 L-14

b) Machinery
Hire & running charges of crane with grab bucket of 0.75 hour 6.00 1393.80 8362.78 P&M-075
cum capacity and accessories.
Air compressor with pneumatic chisel attachment for cutting hour 3.50 334.04 1169.14 P&M-063
hard clay.
Consumables in sinking @ 10 per cent of (b) 953.19

c) Overhead charges @ 0.25 on (a+b) 2999.02

d) Contractor's profit @ 0.1 on (a+b+c) 1499.51

Rate per metre = (a+b+c+d) 16494.59


say 16495.00
Ref. to Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
MoRTH Spec.
12.14 B (iii) Beyond 10 m upto 20 m
a Add 5 per cent for every additional meter depth of sinking over
the rate of sinking for the previous meter
b Add for dewatering @ 5 per cent of cost, if required. (a)
(b) Including
for dewatering
@ 5% of
cost, if
11th m 5% 17319.00 18185.00

12th m 5% 18185.00 19094.00

13th m 5% 19094.00 20049.00

14th m 5% 20049.00 21051.00

15th m 5% 21051.00 22104.00

16th m 5% 22104.00 23209.00

17th m 5% 23209.00 24369.00

18th m 5% 24369.00 25587.00

19th m 5% 25587.00 26866.00

20th m 5% 26866.00 28209.00

Total Cost from 10m upto 20m 217833.00 228723.00

Avg Rate per metre 21783.00 22872.00


12.14 B (iv) Beyond 20m upto 30 m
a Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 5 per cent of cost for dewatering on the cost, if required
c Add 25 per cent of cost for Kentledge including supports, (a) (c)Including (b) Including 5%
loading arrangement and Labour ). 25% for for dewatering, if
Kentledge required

31st m 7.5% 28881.00 36101.00 37906.00

32nd 7.5% 31047.00 38809.00 40749.00

33rd m 7.5% 33376.00 41720.00 43806.00

34th m 7.5% 35879.00 44849.00 47091.00

35th m 7.5% 38570.00 48213.00 50624.00

36th m 7.5% 41463.00 51829.00 54420.00

37th m 7.5% 44573.00 55716.00 58502.00

38th m 7.5% 47916.00 59895.00 62890.00

39th m 7.5% 51510.00 64388.00 67607.00

40th m 7.5% 55373.00 69216.00 72677.00

Total Cost from 30m upto 40m 408588.00 510736.00 536272.00

Avg Rate per metre 40859.00 51074.00 53627.00


12.14 B (v) Beyond 30m upto 40 m
a Add 10 per cent for every additional meter depth of sinking over
the rate of sinking for the previous meter
b Add 5 per cent of cost for dewatering, if required
c Add 20 per cent of cost for Kentledge including supports, (a) (c ) Including (b) Including 5%
loading arrangement and Labour). 20% for for dewatering, if
Kentledge required

31st m 10% 60910.00 73092.00 76747.00

32nd 10% 67001.00 80401.00 84421.00

33rd m 10% 73701.00 88441.00 92863.00

34th m 10% 81071.00 97285.00 102149.00

35th m 10% 89178.00 107014.00 112365.00

36th m 10% 98096.00 117715.00 123601.00

37th m 10% 107906.00 129487.00 135961.00

38th m 10% 118697.00 142436.00 149558.00

39th m 10% 130567.00 156680.00 164514.00

40th m 10% 143624.00 172349.00 180966.00

Total Cost from 30m upto 40m 970751.00 1164900.00 1223145.00

Avg Rate per metre 97075.00 116490.00 122315.00


Ref. to Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
MoRTH Spec.
12.14 C Soft Rock ( 8m dia well )
Unit = Running Meter.
Taking output = 1 m
Depth in soft rock strata upto 3m
Rate of sinking @ 0.20 m/hour
a) Labour
Mate day 0.68 329.34 223.95 L-12

Sinker ( skilled ) day 4.00 244.65 978.60 L-15

Sinking helper ( semi-skilled ) day 12.00 176.43 2117.16 L-14

Diver day 1.00 294.05 294.05 L-07

b) Machinery
Hire & running charges of crane with grab bucket of 0.75 hour 5.00 1393.80 6968.99 P&M-075
cum capacity and accessories.
Air compressor with pneumatic breakers hour 3.75 334.04 1252.65 P&M-063

Consumables in sinking @ 10 per cent of (b) 822.16

Add for dewatering @ of 5 per cent of (a+b), if required 632.88

c) Overhead charges @ 0.25 on (a+b) 3322.61

d) Contractor's profit @ 0.1 on (a+b+c) 1661.30

Rate per metre = (a+b+c+d) 18274.35


say 18274.00
12.14 D Hard Rock ( 8m dia well )
Unit = Running Meter
Taking output = 1 m
Depth in hard rock strata upto 3 m
Rate of sinking @ 0.17 m/hour
a) Material
Gelatine 80 per cent Kg 8.00 131.73 1053.88 M-110

Electric Detonators each 32.00 4.61 147.54 M-100/100

b) Labour
Mate day 1.09 329.34 358.98 L-12

Driller day 2.00 294.05 588.10 L-06

Blaster day 0.25 352.86 88.22 L-03

Mazdoor day 20.00 152.91 3058.12 L-13

Mazdoor (Skilled) day 4.00 244.65 978.60 L-15

c) Machinery
Hire & running charges of crane with grab bucket of 0.75 hour 6.00 1393.80 8362.78 P&M-075
cum capacity and accessories.
Hire & running charges of compressor with pneumatic hour 2.00 334.04 668.08 P&M-063
breaker/Jack hammer for drilling.
Dewatering @ 5 per cent of cost of (b+c), if required. 705.14

Consumables in sinking @ 10 per cent of cost of (b). 507.20

d) Overhead charges @ 0.25 on (a+b+c) 4129.16

e) Contractor's profit @ 0.1 on (a+b+c+d) 2064.58

Rate per metre = (a+b+c+d+e) 22710.37


say 22710.00

22710.00
Ref. to Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
MoRTH Spec.
12.15 Section 1200 Sinking of 9 m external diameter well ( other than
pneumatic method of sinking ) through all types of strata
namely sandy soil, clayey soil and rock as shown against
each case, complete as per drawing and technical
specifications. Depth of sinking is reckoned from bed level.

Unit = Running Meter.


Taking output = 1 m
Diameter of well - 9 m.
A Sandy Soil
(i) Depth below bed level upto 3.0 M
Rate of sinking @ 0.25 m/hour
a) Labour
Mate day 0.19 329.34 62.57 L-12

Sinker ( skilled ) day 1.50 244.65 366.97 L-15

Sinking helper ( semi-skilled ) day 3.25 176.43 573.40 L-14

b) Machinery
Hire & running charges of crane with grab bucket of 0.75 hour 4.00 1393.80 5575.19 P&M-075
cum capacity and accessories.
Consumables in sinking @10 per cent of (b) 557.52

c) Overhead charges @ 0.25 on (a+b) 1783.91

d) Contractor's profit @ 0.1 on (a+b+c) 891.96

Rate per metre = (a+b+c+d) 9811.52


say 9812.00
12.15 A (ii) Beyond 3m upto 10m depth
Rate of sinking @ 0.18 m/hour
a) Labour
Mate day 0.27 329.34 88.92 L-12

Sinker day 1.75 244.65 428.14 L-15

Sinking helper ( semi-skilled ) day 4.00 176.43 705.72 L-14

b) Machinery
Hire & running charges of crane with grab bucket of 0.75 hour 5.50 1393.80 7665.88 P&M-075
cum capacity and accessories.
Consumables in sinking @10 per cent of (b) 766.59

c) Overhead charges @ 0.25 on (a+b) 2413.81

d) Contractor's profit @ 0.1 on (a+b+c) 1206.91

Rate per metre = (a+b+c+d) 13275.97


say 13276.00
12.15 A (iii) Beyond 10m upto 20m
a Add 5 per cent for every additional meter depth of sinking over
the rate of sinking for the previous meter
11th m 5% 13940.00

12th m 5% 14637.00

13th m 5% 15369.00

14th m 5% 16137.00

15th m 5% 16944.00

16th m 5% 17791.00

17th m 5% 18681.00

18th m 5% 19615.00

19th m 5% 20596.00

20th m 5% 21626.00

Total Cost from 10m upto 20m 175336.00

Avg Rate per metre 17534.00


Ref. to Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
MoRTH Spec.
12.15 A (iv) Beyond 20m upto 30 m
a Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 20 per cent of cost for Kentledge including supports, (a) (b) Including
loading arrangement and Labour. 20% for
Kentledge
21st m 7.5% 23247.95 27898.00

22nd m 7.5% 24992.00 29990.00

23rd m 7.5% 26866.00 32239.00

24th m 7.5% 28881.00 34657.00

25th m 7.5% 31047.00 37256.00

26th m 7.5% 33376.00 40051.00

27th m 7.5% 35879.00 43055.00

28th m 7.5% 38570.00 46284.00

29th m 7.5% 41463.00 49756.00

30th m 7.5% 44573.00 53488.00

Total Cost from 20m upto 30m 328894.95 394674.00

Avg Rate per metre 32889.00 39467.00


12.15 A (v) Beyond 30m upto 40 m
a Add 10 per cent for every additional meter depth of sinking over
the rate of sinking for the previous meter
b Add 20 per cent of cost for Kentledge including supports, (a) (b) Including
loading arrangement, and Labour etc. 20% for
Kentledge
31st m 10% 49030.30 58836.00

32nd 10% 53933.00 64720.00

33rd m 10% 59326.00 71191.00

34th m 10% 65259.00 78311.00

35th m 10% 71785.00 86142.00

36th m 10% 78964.00 94757.00

37th m 10% 86860.00 104232.00

38th m 10% 95546.00 114655.00

39th m 10% 105101.00 126121.00

40th m 10% 115611.00 138733.00

Total Cost from 30m upto 40m 781415.30 937698.00

Avg Rate per metre 78142.00 93770.00


12.15 B Clayey Soil ( 9m dia. Well )
Unit = Running Meter.
Taking output = 1 cum
(i) Depth below bed level upto 3.0 M
Rate of sinking 0.17 m / hour
a) Labour
Mate day 0.24 329.34 79.04 L-12

Sinker ( skilled ) day 2.25 244.65 550.46 L-15

Sinking helper ( semi-skilled ) day 3.75 176.43 661.61 L-14

b) Machinery
Hire & running charges of crane with grab bucket of 0.75 hour 5.75 1393.80 8014.33 P&M-075
cum capacity and accessories.
Consumables in sinking @ 10 per cent of (b) 801.43

c) Overhead charges @ 0.25 on (a+b) 2526.72

d) Contractor's profit @ 0.1 on (a+b+c) 1263.36

Rate per metre = (a+b+c+d) 13896.96


say 13897.00
Ref. to Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
MoRTH Spec.
12.15 B (ii) Beyond 3m upto 10m depth
Rate of sinking 0.15 m / hour
a) Labour
Mate day 0.34 329.34 111.97 L-12

Sinker day 2.50 244.65 611.62 L-15

Sinking helper ( semi-skilled ) day 5.00 176.43 882.15 L-14

b) Machinery
Hire & running charges of crane with grab bucket of 0.75 hour 6.50 1393.80 9059.68 P&M-075
cum capacity and accessories.
Air compressor with pneumatic chisel attachment for cutting hour 3.75 334.04 1252.65 P&M-063
hard clay.
Consumables in sinking @ 10 per cent of (b) 1031.23

c) Overhead charges @ 0.25 on (a+b) 3237.33

d) Contractor's profit @ 0.1 on (a+b+c) 1618.66

Rate per metre = (a+b+c+d) 17805.31


say 17805.00
12.15 B (iii) Beyond 10 m upto 20 m
a Add 5 per cent for every additional meter depth of sinking over
the rate of sinking for the previous meter
b Add for dewatering @ 5 per cent of cost, if required. (a)
(b) Including
for dewatering
@ 5% of
cost, if
11th m 5% 18695.00 required
19630.00

12th m 5% 19630.00 20612.00

13th m 5% 20612.00 21643.00

14th m 5% 21643.00 22725.00

15th m 5% 22725.00 23861.00

16th m 5% 23861.00 25054.00

17th m 5% 25054.00 26307.00

18th m 5% 26307.00 27622.00

19th m 5% 27622.00 29003.00

20th m 5% 29003.00 30453.00

Total Cost from 10m upto 20m 235152.00 246910.00

Avg Rate per metre 23515.00 24691.00


12.15 B (iv) Beyond 20m upto 30 m
a Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 5 per cent of cost for dewatering on the cost, if required
c Add 25 per cent of cost for Kentledge including supports, (a) ( c) Including (b) Including 5%
loading arrangement and Labour ). 25% for for dewatering, if
Kentledge required

31st m 7.5% 31178.00 38973.00 40922.00

32nd 7.5% 33516.00 41895.00 43990.00

33rd m 7.5% 36030.00 45038.00 47290.00

34th m 7.5% 38732.00 48415.00 50836.00

35th m 7.5% 41637.00 52046.00 54648.00

36th m 7.5% 44760.00 55950.00 58748.00

37th m 7.5% 48117.00 60146.00 63153.00

38th m 7.5% 51726.00 64658.00 67891.00

39th m 7.5% 55605.00 69506.00 72981.00

40th m 7.5% 59775.00 74719.00 78455.00

Total Cost from 30m upto 40m 441076.00 551346.00 578914.00

Avg Rate per metre 44108.00 55135.00 57891.00


Ref. to Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
MoRTH Spec.
12.15 B (v) Beyond 30m upto 40 m
a Add 10 per cent for every additional meter depth of sinking over
the rate of sinking for the previous meter
b Add 5 per cent of cost for dewatering, if required
c Add 20 per cent of cost for Kentledge including supports, (a) ( c) Including (b) Including 5%
loading arrangement and Labour). 20% for for dewatering, if
Kentledge required

31st m 10% 65753.00 78904.00 82849.00

32nd 10% 72328.00 86794.00 91134.00

33rd m 10% 79561.00 95473.00 100247.00

34th m 10% 87517.00 105020.00 110271.00

35th m 10% 96269.00 115523.00 121299.00

36th m 10% 105896.00 127075.00 133429.00

37th m 10% 116486.00 139783.00 146772.00

38th m 10% 128135.00 153762.00 161450.00

39th m 10% 140949.00 169139.00 177596.00

40th m 10% 155044.00 186053.00 195356.00

Total Cost from 30m upto 40m 1047938.00 1257526.00 1320403.00

Avg Rate per metre 104794.00 125753.00 132040.00


12.15 C Soft Rock ( 9m dia well )
Unit = Running Meter.
Taking output = 1 m
Depth in soft rock strata up to 3m
Rate of sinking 0.15 m / hour
a) Labour
Mate day 0.76 329.34 250.30 L-12

Sinker ( skilled ) day 4.00 244.65 978.60 L-15

Sinking helper ( semi-skilled ) day 14.00 176.43 2470.02 L-14

Diver day 1.20 294.05 352.86 L-07

b) Machinery
Hire & running charges of crane with grab bucket of 0.75 hour 6.50 1393.80 9059.68 P&M-075
cum capacity and accessories.
Air compressor with pneumatic breakers hour 4.00 334.04 1336.16 P&M-063

Consumables in sinking @ 10 per cent of (b) 1039.58

Add for dewatering @ of 5 per cent of (a+b), if required 1548.72

c) Overhead charges @ 0.25 on (a+b) 4258.98

d) Contractor's profit @ 0.1 on (a+b+c) 2129.49

Rate per metre = (a+b+c+d) 23424.39


say 23424.00
Ref. to Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
MoRTH Spec.
12.15 D Hard Rock ( 9m dia well )
Unit = Running Meter
Taking output = 1 m
Depth in hard rock strata upto 3 m
Rate of sinking 0.15 m / hour
a) Material
Gelatine 80 per cent Kg 10.00 131.73 1317.34 M-110

Electric Detonators each 40.00 4.61 184.43 M-100/100

b) Labour
Mate day 1.17 329.34 385.32 L-12

Driller day 2.00 294.05 588.10 L-06

Blaster day 0.25 352.86 88.22 L-03

Mazdoor day 22.00 152.91 3363.93 L-13

Mazdoor (Skilled) day 4.00 244.65 978.60 L-15

Diver day 1.00 294.05 294.05 L-07

c) Machinery
Hire & running charges of crane with grab bucket of 0.75 hour 7.00 1393.80 9756.58 P&M-075
cum capacity and accessories.
Hire & running charges of compressor with pneumatic hour 2.50 334.04 835.10 P&M-063
breaker/Jack hammer for drilling.
Dewatering @ 5 per cent of cost of (b+c), if required. 814.49

Consumables in sinking @ 10 per cent of cost of (b). 569.82

d) Overhead charges @ 0.25 on (a+b+c) 4794.00

e) Contractor's profit @ 0.1 on (a+b+c+d) 2397.00

Rate per metre = (a+b+c+d+e) 26366.98


say 26367.00

26367.00
12.16 1200 Sinking of 10 m external diameter well ( other than
pneumatic method of sinking ) through all types of strata
namely sandy soil, clayey soil and rock as shown against
each case, complete as per drawing and technical
specifications. Depth of sinking is reckoned from bed level.

Unit = Running Meter


Taking output = 1 m
Diameter of well - 10 m.
A Sandy Soil
(i) Depth below bed level upto 3.0 M
Rate of sinking 0.20 m / hour
a) Labour
Mate day 0.20 329.34 65.87 L-12

Sinker ( skilled ) day 1.50 244.65 366.97 L-15

Sinking helper ( semi-skilled ) day 3.50 176.43 617.51 L-14

b) Machinery
Hire & running charges of crane with grab bucket of 0.75 hour 5.00 1393.80 6968.99 P&M-075
cum capacity and accessories.
Consumables in sinking @10 per cent of (b) 696.90

c) Overhead charges @ 0.25 on (a+b) 2179.06

d) Contractor's profit @ 0.1 on (a+b+c) 1089.53

Rate per metre = (a+b+c+d) 11984.82


say 11985.00
Ref. to Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
MoRTH Spec.
12.16 A (ii) Beyond 3m upto 10m depth
Rate of sinking 0.17 m / hour
a) Labour
Mate day 0.31 329.34 102.09 L-12

Sinker day 2.00 244.65 489.30 L-15

Sinking helper ( semi-skilled ) day 4.25 176.43 749.83 L-14

b) Machinery
Hire & running charges of crane with grab bucket of 0.75 hour 5.75 1393.80 8014.33 P&M-075
cum capacity and accessories.
Consumables in sinking @10 per cent of (b) 801.43

c) Overhead charges @ 0.25 on (a+b) 2539.25

d) Contractor's profit @ 0.1 on (a+b+c) 1269.62

Rate per metre = (a+b+c+d) 13965.86


say 13966.00
12.16 A (iii) Beyond 10m upto 20m
a Add 5 per cent for every additional meter depth of sinking over
the rate of sinking for the previous meter
11th m 5% 14664.00

12th m 5% 15397.00

13th m 5% 16167.00

14th m 5% 16975.00

15th m 5% 17824.00

16th m 5% 18715.00

17th m 5% 19651.00

18th m 5% 20634.00

19th m 5% 21666.00

20th m 5% 22749.00

Total Cost from 10m upto 20m 184442.00

Avg Rate per metre 18444.00


12.16 A (iv) Beyond 20m upto 30 m
a Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 20 per cent of cost for Kentledge including supports, (a) (b) Including
loading arrangement and Labour. 20% for
Kentledge
21st m 7.5% 24455.00 29346.00

22nd m 7.5% 26289.00 31547.00

23rd m 7.5% 28261.00 33913.00

24th m 7.5% 30381.00 36457.00

25th m 7.5% 32660.00 39192.00

26th m 7.5% 35110.00 42132.00

27th m 7.5% 37743.00 45292.00

28th m 7.5% 40574.00 48689.00

29th m 7.5% 43617.00 52340.00

30th m 7.5% 46888.00 56266.00

Total Cost from 20m upto 30m 345978.00 415174.00

Avg Rate per metre 34598.00 41517.00


Ref. to Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
MoRTH Spec.
12.16 A (v) Beyond 30m upto 40 m
a Add 10 per cent for every additional meter depth of sinking over
the rate of sinking for the previous meter
b Add 20 per cent of cost for Kentledge including supports, (a) (b) Including
loading arrangement, and Labour etc. 20% for
Kentledge
31st m 10% 51577.00 61892.00

32nd 10% 56735.00 68082.00

33rd m 10% 62409.00 74891.00

34th m 10% 68650.00 82380.00

35th m 10% 75515.00 90618.00

36th m 10% 83067.00 99680.00

37th m 10% 91374.00 109649.00

38th m 10% 100511.00 120613.00

39th m 10% 110562.00 132674.00

40th m 10% 121618.00 145942.00

Total Cost from 30m upto 40m 822018.00 986421.00

Avg Rate per metre 82202.00 98642.00


12.16 B Clayey Soil (10m dia. Well )
Unit = Running Meter
Taking output = 1 cum
(i) Depth below bed level upto 3.0 M
Rate of sinking 0.18m/hour.
a) Labour
Mate day 0.25 329.34 82.33 L-12

Sinker ( skilled ) day 2.50 244.65 611.62 L-15

Sinking helper ( semi-skilled ) day 5.50 176.43 970.37 L-14

b) Machinery
Hire & running charges of crane with grab bucket of 0.75 hour 6.00 1393.80 8362.78 P&M-075
cum capacity and accessories.
Consumables in sinking @ 10 per cent of (b) 836.28

c) Overhead charges @ 0.25 on (a+b) 2715.85

d) Contractor's profit @ 0.1 on (a+b+c) 1357.92

Rate per metre = (a+b+c+d) 14937.15


say 14937.00
12.16 B (ii) Beyond 3m upto 10m depth
Rate of sinking 0.15m/hour.
a) Labour
Mate day 0.40 329.34 131.73 L-12

Sinker day 3.00 244.65 733.95 L-15

Sinking helper ( semi-skilled ) day 5.50 176.43 970.37 L-14

b) Machinery
Hire & running charges of crane with grab bucket of 0.75 hour 6.00 1393.80 8362.78 P&M-075
cum capacity and accessories.
Air compressor with pneumatic chisel attachment for cutting hour 4.00 334.04 1336.16 P&M-063
hard clay
Consumables in sinking @ 10 per cent of (b) 969.89

c) Overhead charges @ 0.25 on (a+b) 3126.22

d) Contractor's profit @ 0.1 on (a+b+c) 1563.11

Rate per metre = (a+b+c+d) 17194.22


say 17194.00
Ref. to Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
MoRTH Spec.
12.16 B (iii) Beyond 10 m upto 20 m
a Add 5 per cent for every additional meter depth of sinking over
the rate of sinking for the previous meter
b Add for dewatering @ 5 per cent of cost, if required. (a)
(b) Including
for dewatering
@ 5% of
cost, if
11th m 5% 18054.00 required
18957.00

12th m 5% 18957.00 19905.00

13th m 5% 19905.00 20900.00

14th m 5% 20900.00 21945.00

15th m 5% 21945.00 23042.00

16th m 5% 23042.00 24194.00

17th m 5% 24194.00 25404.00

18th m 5% 25404.00 26674.00

19th m 5% 26674.00 28008.00

20th m 5% 28008.00 29408.00

Total Cost from 10m upto 20m 227083.00 238437.00

Avg Rate per metre 22708.00 23844.00


12.16 B (iv) Beyond 20m upto 30 m
a Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 5 per cent of cost for dewatering on the cost, if required
c Add 25 per cent of cost for Kentledge including supports, (a) ( c) Including (b) Including 5%
loading arrangement and Labour ). 25% for for dewatering, if
Kentledge required

31st m 7.5% 30109.00 37636.00 39518.00

32nd 7.5% 32367.00 40459.00 42482.00

33rd m 7.5% 34795.00 43494.00 45669.00

34th m 7.5% 37405.00 46756.00 49094.00

35th m 7.5% 40210.00 50263.00 52776.00

36th m 7.5% 43226.00 54033.00 56735.00

37th m 7.5% 46468.00 58085.00 60989.00

38th m 7.5% 49953.00 62441.00 65563.00

39th m 7.5% 53699.00 67124.00 70480.00

40th m 7.5% 57726.00 72158.00 75766.00

Total Cost from 30m upto 40m 425958.00 532449.00 559072.00

Avg Rate per metre 42596.00 53245.00 55907.00


12.16 B (v) Beyond 30m upto 40 m
a Add 10 per cent for every additional meter depth of sinking over
the rate of sinking for the previous meter
b Add 5 per cent of cost for dewatering, if required
c Add 20 per cent of cost for Kentledge including supports, (a) ( c) Including (b) Including 5%
loading arrangement and Labour). 20% for for dewatering, if
Kentledge required

31st m 10% 63499.00 76199.00 80009.00

32nd 10% 69849.00 83819.00 88010.00

33rd m 10% 76834.00 92201.00 96811.05

34th m 10% 84517.00 101420.00 106491.00

35th m 10% 92969.00 111563.00 117141.15

36th m 10% 102266.00 122719.00 128854.95

37th m 10% 112493.00 134992.00 141741.60

38th m 10% 123742.00 148490.00 155914.50

39th m 10% 136116.00 163339.00 171505.95

40th m 10% 149728.00 179674.00 188657.70

Total Cost from 30m upto 40m 1012013.00 1214416.00 1275136.90

Avg Rate per metre 101201.00 121442.00 127514.00


Ref. to Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
MoRTH Spec.
12.16 C Soft Rock (10m dia well )
Unit = Running Meter.
Taking output = 1 m
Depth in soft rock strata upto 3m
Rate of sinking 0.14m/hour.
a) Labour
Mate day 0.86 329.34 283.23 L-12

Sinker ( skilled ) day 4.00 244.65 978.60 L-15

Sinking helper ( semi-skilled ) day 16.00 176.43 2822.88 L-14

Diver day 1.40 294.05 411.67 L-07

b) Machinery
Hire & running charges of crane with grab bucket of 0.75 hour 7.00 1393.80 9756.58 P&M-075
cum capacity and accessories.
Air compressor with pneumatic breakers hour 4.25 334.04 1419.67 P&M-063

Consumables in sinking @ 10 per cent of (b) 1117.63

Add for dewatering @ 5 per cent of cost, if required 614.69

c) Overhead charges @ 0.25 on (a+b) 4351.24

d) Contractor's profit @ 0.1 on (a+b+c) 2175.62

Rate per metre = (a+b+c+d) 23931.80


say 23932.00
12.16 D Hard Rock (10m dia well )
Unit = Running Meter.
Taking output = 1 m
Depth in hard rock strata upto 3 m
Rate of sinking 0.12 m/ hour.
a) Material
Gelatine 80 per cent Kg 11.00 131.73 1449.08 M-110

Electric Detonators each. 44.00 4.61 202.87 M-100/100

b) Labour
Mate day 1.27 329.34 418.26 L-12

Driller day 2.00 294.05 588.10 L-06

Blaster day 0.25 352.86 88.22 L-03

Mazdoor day 24.00 152.91 3669.74 L-13

Mazdoor (Skilled) day 4.00 244.65 978.60 L-15

c) Machinery
Hire & running charges of crane with grab bucket of 0.75 hour 8.50 1393.80 11847.27 P&M-075
cum capacity and accessories.
Hire & running charges of compressor with pneumatic hour 3.00 334.04 1002.12 P&M-063
breaker/Jack hammer or drill
Dewatering @ 5 per cent of cost (c), if required. 642.47

Consumables in sinking @ 10 per cent of cost of (b+c). 1923.48

d) Overhead charges @ 0.25 on (a+b+c) 5702.55

e) Contractor's profit @ 0.1 on (a+b+c+d) 2851.28

Rate per metre = (a+b+c+d+e) 31364.04


say 31364.00

31364.00
Ref. to Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
MoRTH Spec.
12.17 1200 Sinking of 11 m external diameter well ( other than
pneumatic method of sinking ) through all types of strata
namely sandy soil, clayey soil and rock as shown against
each case, complete as per drawing and technical
specifications. Depth of sinking is reckoned from bed level.

Unit = Running Meter


Taking output = 0.50 m
Diameter of well - 11 m.
A Sandy Soil
(i) Depth from bed level upto 3.0 M
Rate of sinking @ 0.15 m/hour
a) Labour
Mate day 0.21 329.34 69.16 L-12

Sinker ( skilled ) day 1.50 244.65 366.97 L-15

Sinking helper (semi-skilled) day 3.30 176.43 582.22 L-14

b) Machinery
Hire & running charges of crane with grab bucket of 0.75 hour 6.00 1393.80 8362.78 P&M-075
cum capacity and accessories.
Consumables in sinking @10 per cent of (b) 836.28

d) Overhead charges @ 0.25 on (a+b+c) 2554.35

e) Contractor's profit @ 0.1 on (a+b+c+d) 1277.18

Cost for 0.5m = a+b+c+d 14048.94

Rate per metre = (a+b+c+d)/0.50 28097.89


say 28098.00
12.17 A (ii) Beyond 3m upto 10m depth
Rate of sinking @ 0.13 m/hour
a) Labour
Mate day 0.32 329.34 105.39 L-12

Sinker day 2.00 244.65 489.30 L-15

Sinking helper (semi-skilled) day 4.50 176.43 793.94 L-14

b) Machinery
Hire & running charges of crane with grab bucket of 0.75 hour 4.00 1393.80 5575.19 P&M-075
cum capacity and accessories.
Consumables in sinking @10 per cent of (b) 557.52

c) Overhead charges @ 0.25 on (a+b+c) 1880.33

d) Contractor's profit @ 0.1 on (a+b+c+d) 940.17

Cost for 0.5m = a+b+c+d 10341.83

Rate per metre = (a+b+c+d)/0.50 20683.65


say 20684.00
12.17 A (iii) Beyond 10m upto 20m
a Add 5 per cent for every additional meter depth of sinking over
the rate of sinking for the previous meter
11th m 5% 21718.00

12th m 5% 22804.00

13th m 5% 23944.00

14th m 5% 25141.00

15th m 5% 26398.00

16th m 5% 27718.00

17th m 5% 29104.00

18th m 5% 30559.00

19th m 5% 32087.00

20th m 5% 33691.00

Total Cost from 10m upto 20m 273164.00

Avg Rate per metre 27316.00


Ref. to Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
MoRTH Spec.
12.17 A (iv) Beyond 20m upto 30 m
a Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 20 per cent of cost for Kentledge including supports, (a) (b)Including
loading arrangement and Labour. 20% for
Kentledge
21st m 7.5% 36218.00 43462.00

22nd m 7.5% 38934.00 46721.00

23rd m 7.5% 41854.00 50225.00

24th m 7.5% 44993.00 53992.00

25th m 7.5% 48367.00 58040.00

26th m 7.5% 51995.00 62394.00

27th m 7.5% 55895.00 67074.00

28th m 7.5% 60087.00 72104.00

29th m 7.5% 64594.00 77513.00

30th m 7.5% 69439.00 83327.00

Total Cost from 20m upto 30m 512376.00 614852.00

Avg Rate per metre 51238.00 61485.00


12.17 A (v) Beyond 30m upto 40 m
a Add 10 per cent for every additional meter depth of sinking over
the rate of sinking for the previous meter
b Add 20 per cent of cost for Kentledge including supports, (a) (b) Including
loading arrangement, and Labour etc. 20% for
Kentledge
31st m 10% 76383.00 91660.00

32nd 10% 84021.00 100825.00

33rd m 10% 92423.00 110908.00

34th m 10% 101665.00 121998.00

35th m 10% 111832.00 134198.00

36th m 10% 123015.00 147618.00

37th m 10% 135317.00 162380.00

38th m 10% 148849.00 178619.00

39th m 10% 163734.00 196481.00

40th m 10% 180107.00 216128.00

Total Cost from 30m upto 40m 1217346.00 1460815.00

Avg Rate per metre 121735.00 146082.00


12.17 B Clayey Soil (11 m dia. Well )
Unit = Running Meter
Taking output = 0.50 meter
(i) Depth from bed level upto 3.0 M
Rate of sinking @ 0.10 m/hour
a) Labour
Mate day 0.26 329.34 85.63 L-12

Sinker ( skilled ) day 2.50 244.65 611.62 L-15

Sinking helper (semi-skilled) day 4.00 176.43 705.72 L-14

b) Machinery
Hire & running charges of crane with grab bucket of 0.75 hour 5.00 1393.80 6968.99 P&M-075
cum capacity and accessories.
Consumables in sinking @ 10 per cent of (b) 696.90

c) Overhead charges @ 0.25 on (a+b) 2267.21

d) Contractor's profit @ 0.1 on (a+b+c) 1133.61

Cost for 0.5m = a+b+c+d 12469.68

Rate per metre = (a+b+c+d)/0.50 24939.35


say 24939.00
Ref. to Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
MoRTH Spec.
12.17 B (ii) Beyond 3m upto 10m depth
Rate of sinking @ 0.08 m/hour
a) Labour
Mate day 0.43 329.34 141.61 L-12

Sinker day 3.50 244.65 856.27 L-15

Sinking helper (semi-skilled) day 5.75 176.43 1014.47 L-14

b) Machinery
Hire & running charges of crane with grab bucket of 0.75 hour 6.00 1393.80 8362.78 P&M-075
cum capacity and accessories.
Air compressor with pneumatic chisel attachment for cutting hour 4.25 334.04 1419.67 P&M-063
hard clay
Consumables in sinking @ 10 per cent of (b) 978.25

c) Overhead charges @ 0.25 on (a+b) 3193.27

d) Contractor's profit @ 0.1 on (a+b+c) 1596.63

Cost for 0.5m = a+b+c+d 17562.96

Rate per metre = (a+b+c+d)/0.50 35125.92


say 35126.00
12.17 B (iii) Beyond 10 m upto 20 m
a Add 5 per cent for every additional meter depth of sinking over
the rate of sinking for the previous meter
b Add for dewatering @ 5 per cent of cost, if required. (a)(b)Including
for dewatering
@ 5% of
cost, if
11th m 5% 36882.00 38726.00

12th m 5% 38726.00 40662.00

13th m 5% 40662.00 42695.00

14th m 5% 42695.00 44830.00

15th m 5% 44830.00 47072.00

16th m 5% 47072.00 49426.00

17th m 5% 49426.00 51897.00

18th m 5% 51897.00 54492.00

19th m 5% 54492.00 57217.00

20th m 5% 57217.00 60078.00

Total Cost from 10m upto 20m 463899.00 487094.00

Avg Rate per metre 46390.00 48709.00


12.17 B (iv) Beyond 20m upto 30 m
a Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 5 per cent of cost for dewatering on the cost, if required
c Add 25 per cent of cost for Kentledge including supports, (a) (c)Including (b)Including 5%
loading arrangement and Labour ). 25% for for dewatering, if
Kentledge required

21st m 7.5% 61508.00 76885.00 80729.00

22nd 7.5% 66121.00 82651.00 86784.00

23rd m 7.5% 71080.00 88850.00 93293.00

24th m 7.5% 76411.00 95514.00 100290.00

25th m 7.5% 82142.00 102678.00 107812.00

26th m 7.5% 88303.00 110379.00 115898.00

27th m 7.5% 94926.00 118658.00 124591.00

28th m 7.5% 102045.00 127556.00 133934.00

29th m 7.5% 109698.00 137123.00 143979.00

30th m 7.5% 117925.00 147406.00 154776.00

Total Cost from 20m upto 30m 870159.00 1087700.00 1142085.00

Avg Rate per metre 87016.00 108770.00 114209.00


Ref. to Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
MoRTH Spec.
12.17 B (v) Beyond 30m upto 40 m
a Add 10 per cent for every additional meter depth of sinking over
the rate of sinking for the previous meter
b Add 5 per cent of cost for dewatering, if required
c Add 20 per cent of cost for Kentledge including supports, (a) (c ) Including (b)Including 5%
loading arrangement and Labour). 20% for for dewatering, if
Kentledge required

31st m 10% 129718.00 155662.00 163445.00

32nd 10% 142690.00 171228.00 179789.00

33rd m 10% 156959.00 188351.00 197769.00

34th m 10% 172655.00 207186.00 217545.00

35th m 10% 189921.00 227905.00 239300.00

36th m 10% 208913.00 250696.00 263231.00

37th m 10% 229804.00 275765.00 289553.00

38th m 10% 252784.00 303341.00 318508.00

39th m 10% 278062.00 333674.00 350358.00

40th m 10% 305868.00 367042.00 385394.00

Total Cost from 30m upto 40m 2067374 2480850 2604892

Avg Rate per metre 206737.00 248085.00 260489.00


12.17 C Soft Rock (11m dia well )
Unit = Running Meter.
Taking output = 0.50 m
Depth in soft rock strata upto 3m
Rate of sinking @ 0.06 m/hour
a) Labour
Mate day 0.95 329.34 312.87 L-12

Sinker ( skilled ) day 4.25 244.65 1039.76 L-15

Sinking helper (semi-skilled) day 18.00 176.43 3175.74 L-14

Diver day 1.50 294.05 441.08 L-07

b) Machinery
Hire & running charges of crane with grab bucket of 0.75 hour 8.00 1393.80 11150.38 P&M-075
cum capacity and accessories.
Air compressor with pneumatic breakers hour 4.50 334.04 1503.18 P&M-063

Consumables in sinking @ 10 per cent of (b) 1265.36

Add for dewatering @ 5 per cent of cost of (b), if required 695.95

c) Overhead charges @ 0.25 on (a+b) 4896.08

d) Contractor's profit @ 0.1 on (a+b+c) 2448.04

Cost for 0.5m = a+b+c+d 26928.42

Rate per metre = (a+b+c+d)/0.50 53856.84


say 53857.00
Ref. to Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
MoRTH Spec.
12.17 D Hard Rock (11m dia well )
Unit = Running Meter.
Taking output = 0.50 m
Depth in hard rock upto 3 m
Rate of sinking @ 0.05 m/hour
a) Material
Gelatine 80 per cent Kg 12.00 131.73 1580.81 M-110

Electric Detonators each. 48.00 4.61 221.31 M-100/100

b) Labour
Mate day 1.35 329.34 444.60 L-12

Driller day 2.00 294.05 588.10 L-06

Blaster day 0.25 352.86 88.22 L-03

Mazdoor day 26.00 152.91 3975.56 L-13

Mazdoor (Skilled) day 4.00 244.65 978.60 L-15

c) Machinery
Hire & running charges of crane with grab bucket of 0.75 hour 10.00 1393.80 13937.97 P&M-075
cum capacity and accessories.
Hire & running charges of compressor with pneumatic hour 3.50 334.04 1169.14 P&M-063
breaker/Jack hammer or drill
Dewatering @ 5 per cent of cost (c), if required. 755.36

Consumables in sinking @ 10 per cent of cost of (b+c). 2118.22

d) Overhead charges @ 0.25 on (a+b+c) 6464.47

e) Contractor's profit @ 0.1 on (a+b+c+d) 3232.24

Cost for 0.5m = a+b+c+d 35554.59

Rate per metre = (a+b+c+d)/0.50 71109.19


say 71109.00

71109.00
12.18 1200 Sinking of 12 m external diameter well ( other than
pneumatic method of sinking ) through all types of strata
namely sandy soil, clayey soil and rock as shown against
each case, complete as per drawing and technical
specifications. Depth of sinking is reckoned from bed level.

Unit = Running Meter


Taking output = 0.25 m
Diameter of well - 12 m.
A Sandy Soil
(i) I) Depth below bed level upto 3.0 M
Rate of sinking @ 0.05 m/hour
a) Labour
Mate day 0.22 329.34 72.45 L-12

Sinker ( skilled ) day 1.75 244.65 428.14 L-15

Sinking helper (semi-skilled) day 4.00 176.43 705.72 L-14

b) Machinery
Hire & running charges of crane with grab bucket of 0.75 hour 6.00 1393.80 8362.78 P&M-075
cum capacity and accessories.
Consumables in sinking @10 per cent of (b) 836.28

c) Overhead charges @ 0.25 on (a+b) 2601.34

d) Contractor's profit @ 0.1 on (a+b+c) 1300.67

Cost for 0.25m = a+b+c+d 14307.39

Rate per metre = (a+b+c+d)/0.25 57229.54


say 57230.00
Ref. to Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
MoRTH Spec.
12.18 A (ii) Beyond 3m upto 10m depth
Rate of sinking @ 0.038 m/hour
a) Labour
Mate day 0.37 329.34 121.85 L-12

Sinker day 2.50 244.65 611.62 L-15

Sinking helper (semi-skilled) day 4.75 176.43 838.04 L-14

b) Machinery
Hire & running charges of crane with grab bucket of 0.75 hour 6.50 1393.80 9059.68 P&M-075
cum capacity and accessories.
Consumables in sinking @10 per cent of (b) 905.97

c) Overhead charges @ 0.25 on (a+b) 2884.29

d) Contractor's profit @ 0.1 on (a+b+c) 1442.15

Cost for 0.25m = a+b+c+d 15863.61

Rate per metre = (a+b+c+d)/0.25 63454.43


say 63454.00
12.18 A (iii) Beyond 10m upto 20m
a Add 5 per cent for every additional meter depth of sinking over
the rate of sinking for the previous meter
11th m 5% 66627.00

12th m 5% 69958.00

13th m 5% 73456.00

14th m 5% 77129.00

15th m 5% 80985.00

16th m 5% 85034.00

17th m 5% 89286.00

18th m 5% 93750.00

19th m 5% 98438.00

20th m 5% 103360.00

Total Cost from 10m upto 20m 838023.00

Avg Rate per metre 83802.00


12.18 A (iv) Beyond 20m upto 30 m
a Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 20 per cent of cost for Kentledge including supports, (a) (b)Including
loading arrangement and Labour. 20% for
Kentledge
21st m 7.5% 111112.00 133334.00

22nd m 7.5% 119445.00 143334.00

23rd m 7.5% 128403.00 154084.00

24th m 7.5% 138033.00 165640.00

25th m 7.5% 148385.00 178062.00

26th m 7.5% 159514.00 191417.00

27th m 7.5% 171478.00 205774.00

28th m 7.5% 184339.00 221207.00

29th m 7.5% 198164.00 237797.00

30th m 7.5% 213026.00 255631.00

Total Cost from 20m upto 30m 1571899.00 1886280.00

Avg Rate per metre 157190.00 188628.00


Ref. to Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
MoRTH Spec.
12.18 A (v) Beyond 30m upto 40 m
a Add 10 per cent for every additional meter depth of sinking over
the rate of sinking for the previous meter
b Add 20 per cent of cost for Kentledge including supports, (a) (b)Including
loading arrangement, and Labour etc. 20% for
Kentledge
31st m 10% 234329.00 281195.00

32nd 10% 257762.00 309314.00

33rd m 10% 283538.00 340246.00

34th m 10% 311892.00 374270.00

35th m 10% 343081.00 411697.00

36th m 10% 377389.00 452867.00

37th m 10% 415128.00 498154.00

38th m 10% 456641.00 547969.00

39th m 10% 502305.00 602766.00

40th m 10% 552536.00 663043.00

Total Cost from 30m upto 40m 3734601 4481521

Avg Rate per metre 373460.00 448152.00


12.18 B Clayey Soil (12 m dia. Well )
Unit = Running Meter.
Taking output = 0.25 meter.
(i) Depth below bed level upto 3.0 M
Rate of sinking @ 0.04 m/hour
a) Labour
Mate day 0.30 329.34 98.80 L-12

Sinker ( skilled ) day 3.00 244.65 733.95 L-15

Sinking helper (semi-skilled) day 4.50 176.43 793.94 L-14

b) Machinery
Hire & running charges of crane with grab bucket of 0.75 hour 6.25 1393.80 8711.23 P&M-075
cum capacity and accessories.
Consumables in sinking @ 10 per cent of (b) 871.12

c) Overhead charges @ 0.25 on (a+b) 2802.26

d) Contractor's profit @ 0.1 on (a+b+c) 1401.13

Cost for 0.25m = a+b+c+d 15412.43

Rate per metre = (a+b+c+d)/0.25 61649.71


say 61650.00
12.18 B (ii) Beyond 3m upto 10m depth
Rate of sinking @ 0.03 m/hour
a) Labour
Mate day 0.48 329.34 158.08 L-12

Sinker day 3.75 244.65 917.44 L-15

Sinking helper (semi-skilled) day 6.00 176.43 1058.58 L-14

b) Machinery
Hire & running charges of crane with grab bucket of 0.75 hour 8.33 1393.80 11610.33 P&M-075
cum capacity and accessories.
Air compressor with pneumatic chisel attachment for cutting hour 4.50 334.04 1503.18 P&M-063
hard clay.
Consumables in sinking @ 10 per cent of (b) 1311.35

c) Overhead charges @ 0.25 on (a+b) 4139.74

d) Contractor's profit @ 0.1 on (a+b+c) 2069.87

Cost for 0.25m = a+b+c+d 22768.57

Rate per metre = (a+b+c+d)/0.25 91074.29


say 91074.00
Ref. to Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
MoRTH Spec.
12.18 B (iii) Beyond 10 m upto 20 m
a Add 5 per cent for every additional meter depth of sinking over
the rate of sinking for the previous meter
b Add for dewatering @ 5 per cent of cost, if required. (a)(b)Including
for dewatering
@ 5% of
cost, if
5% 95628.00 required
100409.00
11th m
12th m 5% 100409.00 105429.00

13th m 5% 105429.00 110700.00

14th m 5% 110700.00 116235.00

15th m 5% 116235.00 122047.00

16th m 5% 122047.00 128149.00

17th m 5% 128149.00 134556.00

18th m 5% 134556.00 141284.00

19th m 5% 141284.00 148348.00

20th m 5% 148348.00 155765.00

Total Cost from 10m upto 20m 1202785.00 1262922.00

Avg Rate per metre 120279.00 126292.00


12.18 B (iv) Beyond 20m upto 30 m
a Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 5 per cent of cost for dewatering on the cost, if required
c Add 25 per cent of cost for Kentledge including supports, (a) (c)Including (b)Including 5%
loading arrangement and Labour ). 25% for for dewatering, if
Kentledge required

21st m 7.5% 159474.00 199343.00 209310.00

22nd 7.5% 171435.00 214294.00 225009.00

23rd m 7.5% 184293.00 230366.00 241884.00

24th m 7.5% 198115.00 247644.00 260026.00

25th m 7.5% 212974.00 266218.00 279529.00

26th m 7.5% 228947.00 286184.00 300493.00

27th m 7.5% 246118.00 307648.00 323030.00

28th m 7.5% 264577.00 330721.00 347257.00

29th m 7.5% 284420.00 355525.00 373301.00

30th m 7.5% 305752.00 382190.00 401300.00

Total Cost from 20m upto 30m 2256105 2820133 2961139

Avg Rate per metre 225611.00 282013.00 296114.00


12.18 B (v) Beyond 30m upto 40 m
a Add 10 per cent for every additional meter depth of sinking over
the rate of sinking for the previous meter
b Add 5 per cent of cost for dewatering, if required
c Add 20 per cent of cost for Kentledge including supports, (a) (c ) Including (b)Including 5%
loading arrangement and Labour). 20% for for dewatering, if
Kentledge required

31st m 10% 336327.00 403592.00 423772.00

32nd 10% 369960.00 443952.00 466150.00

33rd m 10% 406956.00 488347.00 512764.00

34th m 10% 447652.00 537182.00 564041.00

35th m 10% 492417.00 590900.00 620445.00

36th m 10% 541659.00 649991.00 682491.00

37th m 10% 595825.00 714990.00 750740.00

38th m 10% 655408.00 786490.00 825815.00

39th m 10% 720949.00 865139.00 908396.00

40th m 10% 793044.00 951653.00 999236.00

Total Cost from 30m upto 40m 5360197 6432236 6753850

Avg Rate per metre 536020.00 643224.00 675385.00


Ref. to Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
MoRTH Spec.
12.18 C Soft Rock (12m dia well )
Unit = Running Meter
Taking output = 0.25 m
Depth in soft rock strata upto 3m
Rate of sinking @ 0.025 m/hour
a) Labour
Mate day 1.06 329.34 349.10 L-12

Sinker ( skilled ) day 4.50 244.65 1100.92 L-15

Sinking helper (semi-skilled) day 20.00 176.43 3528.60 L-14

Diver day 1.75 294.05 514.59 L-07

b) Machinery
Hire & running charges of crane with grab bucket of 0.75 hour 10.00 1393.80 13937.97 P&M-075
cum capacity and accessories.
Air compressor with pneumatic chisel attachment for cutting hour 4.75 334.04 1586.69 P&M-063
hard clay.
Consumables in sinking @ 10 per cent of (b) 1552.47

Add for dewatering @ 5 per cent, if required 853.86

c) Overhead charges @ 0.25 on (a+b) 5856.05

d) Contractor's profit @ 0.1 on (a+b+c) 2928.02

Cost for 0.25m = a+b+c+d 32208.27

Rate per metre = (a+b+c+d)/0.25 128833.06


say 128833.00
12.18 D Hard Rock (12m dia well )
Unit = Running Meter
Taking output = 0.25 m
(i) Depth in hard rock strata upto 3 m
Rate of sinking @ 0.020 m/hour
a) Material
Gelatine80 per cent Kg 14.00 131.73 1844.28 M-110

Electric detonator each. 56.00 4.61 258.20 M-100/100

b) Labour
Mate day 1.44 329.34 474.24 L-12

Driller day 2.00 294.05 588.10 L-06

Blaster day 0.25 352.86 88.22 L-03

Mazdoor day 28.00 152.91 4281.37 L-13

Mazdoor (Skilled) day 4.50 244.65 1100.92 L-15

c) Machinery
Hire & running charges of crane with grab bucket of 0.75 hour 12.50 1393.80 17422.46 P&M-075
cum capacity and accessories.
Hire & running charges of compressor with pneumatic hour 4.00 334.04 1336.16 P&M-063
breaker/Jack hammer or drill
Dewatering @ 5 per cent, if required. 937.93

Consumables in sinking @ 10 per cent of (c). 1969.66

d) Overhead charges @ 0.25 on (a+b+c) 7575.39

e) Contractor's profit @ 0.1 on (a+b+c+d) 3787.69

Cost for 0.25m = a+b+c+d+e 41664.62

Rate per metre = (a+b+c+d+e)/0.25 166658.49


say 166658.00

166658.00
Ref. to Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
MoRTH Spec.
12.19 1200 Sinking of Twin D Type well (other than pneumatic method
of sinking) through all types of strata namely sandy soil,
clayey soil and rock as shown against each case, complete
as per drawing and technical specifications. Depth of
sinking is reckoned from bed level.

Unit = Running Meter


Taking output = 1 m
Dimensions of well.
Overall length = 12 m
Overall width = 6 m
A Sandy Soil
(i) Depth from bed level upto 3.0 M
Rate of sinking @ 0.18 m/hour
a) Labour
Mate day 0.20 329.34 65.87 L-12

Sinker ( skilled ) day 1.25 244.65 305.81 L-15

Sinking helper (semi-skilled) day 3.75 176.43 661.61 L-14

b) Machinery
Hire & running charges of crane with grab bucket of 0.75 hour 5.50 1393.80 7665.88 P&M-075
cum capacity and accessories.
Consumables in sinking @10 per cent of (b) 766.59

c) Overhead charges @ 0.25 on (a+b) 2366.44

d) Contractor's profit @ 0.1 on (a+b+c) 1183.22

Rate per metre = (a+b+c+d) 13015.42


say 13015.00
12.19 A (ii) Beyond 3m upto 10m depth
Rate of sinking @ 0.17 m/hour
a) Labour
Mate day 0.30 329.34 98.80 L-12

Sinker day 1.50 244.65 366.97 L-15

Sinking helper (semi-skilled) day 4.00 176.43 705.72 L-14

b) Machinery
Hire & running charges of crane with grab bucket of 0.75 hour 5.88 1393.80 8195.53 P&M-075
cum capacity and accessories.
Consumables in sinking @10 per cent of (b) 819.55

c) Overhead charges @ 0.25 on (a+b) 2546.64

d) Contractor's profit @ 0.1 on (a+b+c) 1273.32

Rate per metre = (a+b+c+d) 14006.54


say 14007.00
12.19 A (iii) Beyond 10m upto 20m
a Add 5 per cent for every additional meter depth of sinking over
the rate of sinking for the previous meter
11th m 5% 14707.00

12th m 5% 15442.00

13th m 5% 16214.00

14th m 5% 17025.00

15th m 5% 17876.00

16th m 5% 18770.00

17th m 5% 19709.00

18th m 5% 20694.00

19th m 5% 21729.00

20th m 5% 22815.00

Total Cost from 10m upto 20m 184981.00

Avg Rate per metre 18498.00


Ref. to Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
MoRTH Spec.
12.19 A (iv) Beyond 20m upto 30 m
a Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 20 per cent of cost for Kentledge including supports, (a) (b)Including
loading arrangement and Labour. 20% for
Kentledge
21st m 7.5% 24526.00 29431.00

22nd m 7.5% 26365.00 31638.00

23rd m 7.5% 28342.00 34010.00

24th m 7.5% 30468.00 36562.00

25th m 7.5% 32753.00 39304.00

26th m 7.5% 35209.00 42251.00

27th m 7.5% 37850.00 45420.00

28th m 7.5% 40689.00 48827.00

29th m 7.5% 43741.00 52489.00

30th m 7.5% 47022.00 56426.00

Total Cost from 20m upto 30m 346965.00 416358.00

Avg Rate per metre 34697.00 41636.00


12.19 A (v) Beyond 30m upto 40 m
a Add 10 per cent for every additional meter depth of sinking over
the rate of sinking for the previous meter
b Add 20 per cent of cost for Kentledge including supports, (a) (b)Including
loading arrangement, and Labour etc. 20% for
Kentledge
31st m 10% 51724.00 62069.00

32nd 10% 56896.00 68275.00

33rd m 10% 62586.00 75103.00

34th m 10% 68845.00 82614.00

35th m 10% 75730.00 90876.00

36th m 10% 83303.00 99964.00

37th m 10% 91633.00 109960.00

38th m 10% 100796.00 120955.00

39th m 10% 110876.00 133051.00

40th m 10% 121964.00 146357.00

Total Cost from 30m upto 40m 824353.00 989224.00

Avg Rate per metre 82435.00 98922.00


12.19 B Clayey Soil (Twin D Type Well )
Unit = Running Meter
Taking output = 1 meter
(i) Depth below bed level upto 3.0 M
Rate of sinking @ 0.16 m/hour
a) Labour
Mate day 0.26 329.34 85.63 L-12

Sinker ( skilled ) day 2.50 244.65 611.62 L-15

Sinking helper (semi-skilled) day 4.00 176.43 705.72 L-14

b) Machinery
Hire & running charges of crane with grab bucket of 0.75 hour 6.25 1393.80 8711.23 P&M-075
cum capacity and accessories.
Consumables in sinking @ 10 per cent of (b) 871.12

c) Overhead charges @ 0.25 on (a+b) 2746.33

d) Contractor's profit @ 0.1 on (a+b+c) 1373.17

Rate per metre = (a+b+c+d) 15104.82


say 15105.00
Ref. to Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
MoRTH Spec.
12.19 B (ii) Beyond 3m upto 10m depth
Rate of sinking @ 0.15 m/hour
a) Labour
Mate day 0.45 329.34 148.20 L-12

Sinker day 3.25 244.65 795.11 L-15

Sinking helper (semi-skilled) day 6.00 176.43 1058.58 L-14

b) Machinery
Hire & running charges of crane with grab bucket of 0.75 hour 6.67 1393.80 9296.63 P&M-075
cum capacity and accessories.
Air compressor with pneumatic chisel attachment for cutting hour 4.50 334.04 1503.18 P&M-063
hard clay.
Consumables in sinking @ 10 per cent of (b) 1079.98

c) Overhead charges @ 0.25 on (a+b) 3470.42

d) Contractor's profit @ 0.1 on (a+b+c) 1735.21

Rate per metre = (a+b+c+d) 19087.31


say 19087.00
12.19 B (iii) Beyond 10 m upto 20 m
a Add 5 per cent for every additional meter depth of sinking over
the rate of sinking for the previous meter
b Add for dewatering @ 5 per cent of cost, if required. (a)(b)Including
for dewatering
@ 5% of
cost, if
11th m 5% 20042.00 required
21044.00

12th m 5% 21044.00 22096.00

13th m 5% 22096.00 23201.00

14th m 5% 23201.00 24361.00

15th m 5% 24361.00 25579.00

16th m 5% 25579.00 26858.00

17th m 5% 26858.00 28201.00

18th m 5% 28201.00 29611.00

19th m 5% 29611.00 31092.00

20th m 5% 31092.00 32647.00

Total Cost from 10m upto 20m 252085.00 264690.00

Avg Rate per metre 25209.00 26469.00


12.19 B (iv) Beyond 20m upto 30 m
a Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 5 per cent of cost for dewatering on the cost, if required
c Add 25 per cent of cost for Kentledge including supports, (a) (c)Including (b)Including 5%
loading arrangement and Labour ). 25% for for dewatering, if
Kentledge required

21st m 7.5% 33424.00 41780.00 43869.00

22nd 7.5% 35931.00 44914.00 47160.00

23rd m 7.5% 38626.00 48283.00 50697.00

24th m 7.5% 41523.00 51904.00 54499.00

25th m 7.5% 44637.00 55796.00 58586.00

26th m 7.5% 47985.00 59981.00 62980.00

27th m 7.5% 51584.00 64480.00 67704.00

28th m 7.5% 55453.00 69316.00 72782.00

29th m 7.5% 59612.00 74515.00 78241.00

30th m 7.5% 64083.00 80104.00 84109.00

Total Cost from 20m upto 30m 472858.00 591073.00 620627.00

Avg Rate per metre 47286.00 59107.00 62063.00


Ref. to Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
MoRTH Spec.
12.19 B (v) Beyond 30m upto 40 m
a Add 10 per cent for every additional meter depth of sinking over
the rate of sinking for the previous meter
b Add 5 per cent of cost for dewatering, if required
c Add 20 per cent of cost for Kentledge including supports, (a) (c ) Including (b)Including 5%
loading arrangement and Labour). 20% for for dewatering, if
Kentledge required

31st m 10% 70491.00 84589.00 88818.00

32nd 10% 77540.00 93048.00 97700.00

33rd m 10% 85294.00 102353.00 107471.00

34th m 10% 93823.00 112588.00 118217.00

35th m 10% 103205.00 123846.00 130038.00

36th m 10% 113526.00 136231.00 143043.00

37th m 10% 124879.00 149855.00 157348.00

38th m 10% 137367.00 164840.00 173082.00

39th m 10% 151104.00 181325.00 190391.00

40th m 10% 166214.00 199457.00 209430.00

Total Cost from 30m upto 40m 1123443.00 1348132.00 1415538.00

Avg Rate per metre 112344.00 134813.00 141554.00


12.19 C Soft Rock (Twin D Type Well )
Unit = Running Meter
Taking output = 1 m
Depth in soft rock strata upto 3m
Rate of sinking @ 0.12 m/hour
a) Labour
Mate day 0.86 329.34 283.23 L-12

Sinker ( skilled ) day 4.50 244.65 1100.92 L-15

Sinking helper (semi-skilled) day 15.00 176.43 2646.45 L-14

Diver day 1.50 294.05 441.08 L-07

b) Machinery
Hire & running charges of crane with grab bucket of 0.75 hour 8.33 1393.80 11610.33 P&M-075
cum capacity and accessories.
Air compressor with pneumatic breakers hour 6.00 334.04 2004.24 P&M-063

Consumables in sinking @ 10 per cent of (b) 1361.46

Add for dewatering @ 5 per cent, if required 748.80

c) Overhead charges @ 0.25 on (a+b) 5049.13

d) Contractor's profit @ 0.1 on (a+b+c) 2524.56

Rate per metre = (a+b+c+d) 27770.20


say 27770.00
Ref. to Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
MoRTH Spec.
12.19 D Hard Rock (Twin D Type Well )
Unit = Running Meter
Taking output = 1 m
Depth in hard rock strata upto 3 m
Rate of sinking @ 0.10 m/hour
a) Material
Geletine80 per cent Kg 10.00 131.73 1317.34 M-110

Electric detonators each. 40.00 4.61 184.43 M-100/100

b) Labour
Mate day 1.34 329.34 441.31 L-12

Driller day 2.00 294.05 588.10 L-06

Blaster day 0.25 352.86 88.22 L-03

Mazdoor day 25.00 152.91 3822.65 L-13

Mazdoor (Skilled) day 4.25 244.65 1039.76 L-15

c) Machinery
Hire & running charges of crane with grab bucket of 0.75 hour 10.00 1393.80 13937.97 P&M-075
cum capacity and accessories.
Hire & running charges of compressor with pneumatic hour 3.00 334.04 1002.12 P&M-063
breaker/Jack hammer or drill
Dewatering @ 5 per cent of cost of (b+c), if required. 1046.01

Consumables in sinking @ 10 per cent of (b). 1598.61

d) Overhead charges @ 0.25 on (a+b+c) 6266.63

e) Contractor's profit @ 0.1 on (a+b+c+d) 3133.31

Rate per metre = (a+b+c+d+e) 34466.46


say 34466.00

34466.00
Ref. to Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
MoRTH Spec.
12.21 1207 Sand Filling in Wells complete as per Drawing and
Technical Specifications.
Unit = 1 cum
Taking output = 1 cum
a) Material
Sand (assuming 20 per cent voids ) cum 1.20 1293.82 1552.58 M-006

b) Labour
Mate day 0.01 329.34 3.29 L-12

Mazdoor day 0.30 152.91 45.87 L-13

c) Overhead charges @ 0.25 on (a+b) 400.44

d) Contractor's profit @ 0.1 on (a+b+c) 200.22

Rate per cum (a+b+c+d) 2202.41


say 2202.00

2202.00
12.22 1200 & 1900 Providing Steel Liner 10 mm thick for Curbs and 6 mm thick
for Steining of Wells including Fabricating and Setting out
as per Detailed Drawing.
Unit = 1 MT
Taking output = 1 MT
a) Material
i) Structural steel including 5 per cent wastage tonne 1.05 60000.00 63000.00 M-185

b) Labour
Mate day 1.24 329.34 408.38 L-12

Fitter day 6.00 235.24 1411.44 L-08

Blacksmith day 5.00 317.57 1587.87 L-01

Welder day 5.00 352.86 1764.30 L-02

Mazdoor day 10.00 152.91 1529.06 L-13

Electrodes, cutting gas and other consumables @ 5 per 3150.00


cent on cost a (a) above.
c) Overhead charges @ 0.25 on (a+b) 18212.76

d) Contractor's profit @ 0.1 on (a+b+c) 9106.38

Rate for per MT (a+b+c+d) 100170.19


say 100170.00

100170.00
Ref. to Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
MoRTH Spec.
12.23 1100 & 1700 Bored cast-in-situ M35 grade R.C.C. Pile excluding
Reinforcement complete as per Drawing and Technical
Specifications and removal of excavated earth with all lifts
and lead upto 1000 m.
Pile diameter-750 mm
Unit = meter
Taking output = 15 m
a) Materials
PCC Grade M35 cum 6.62 9490.00 62823.80 Item 12.11
(C) iv
Rate for concrete may be adopted same as for bottom plug vide
item no. 12.11( C ) (IV)
Concrete to be cast with a tremie pipe 200mm dia.
b) Machinery( for boring and construction )
Hire and running charges of hydraulic piling rig with power hour 6.00 5486.97 32921.84 P&M-036
unit and complete accessories including shifting from one
bore location to another.
Hire and running charges of light crane for lowering hour 0.50 374.03 187.02 P&M-013
reinforcement cage
Hire and running charges of Bentonite pump hour 6.00 Rate included
in piling rig
Loader I cum bucket capacity. hour 0.30 803.34 241.00 P&M-017

Tipper 5.5 cum capacity for disposal of muck from pile bore hour 0.30 491.65 147.50 P&M-048
hole
Bentonite kg 300.00 18.53 5557.55 M-070

c) Labour
Mate/Supervisor day 0.14 329.34 46.11 L-12

Mazdoor day 3.50 152.91 535.17 L-13

d) Overhead charges @ 0.25 on (b+c) 9909.04

e) Contractor's profit @ 0.1 on (b+c+d) 4954.52

Cost for 15 m = a+b+c+d+d+e 117323.54

Rate per metre (a+b+c+d+e)/15 7821.57


say 7822.00

7822.00
Ref. to Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
MoRTH Spec.
12.24 1100,1600 & Bored cast-in-situ M35 grade R.C.C. Pile excluding
1700 Reinforcement complete as per Drawing and Technical
Specifications and removal of excavated earth with all lifts
and lead upto 1000 m.
Pile diameter-1000 mm
Unit = meter
Taking output = 10 m
a) Materials
PCC Grade M35 cum 7.85 9490.00 74496.50 Item 12.11
(C) iv
Rate for concrete may be adopted same as for bottom plug
vide item no. 12.11( C ) (IV)
Concrete to be cast with a tremie pipe 200mm dia.
b) Machinery( for boring and construction )
Hire and running charges of hydraulic piling rig with power hour 6.00 5486.97 32921.84 P&M-036
unit and complete accessories including shifting from one
bore location to another.
Hire and running charges of light crane for lowering hour 0.50 374.03 187.02 P&M-013
reinforcement cage
Hire and running charges of Bentonite pump hour 6.00 Rate included
in piling rig
Loader I cum bucket capacity. hour 0.40 803.34 321.34 P&M-017

Tipper 5.5 cum capacity for disposal of muck from pile bore hour 0.40 491.65 196.66 P&M-048
hole
Bentonite kg 350.00 18.53 6483.80 M-070

c) Labour
Mate/Supervisor day 0.16 329.34 52.69 L-12

Mazdoor day 4.00 152.91 611.62 L-13

d) Overhead charges @ 0.25 on (b+c) 10193.74

e) Contractor's profit @ 0.1 on (b+c+d) 5096.87

Cost for 10 m = a+b+c+d+d+e 130562.09

Rate per metre (a+b+c+d+e)/10 13056.21


say 13056.00

13056.00
Ref. to Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
MoRTH Spec.
12.25 1100 & 1700 Bored cast-in-situ M35 grade R.C.C. Pile excluding
Reinforcement complete as per Drawing and Technical
Specifications and removal of excavated earth with all lifts
and lead upto 1000 m.
Pile diameter-1200 mm
Unit = meter
Taking output = 9 m
a) Materials
PCC Grade M35 cum 10.17 9490.00 96513.30 Item 12.11
(C) iv
Rate for concrete may be adopted same as for bottom plug vide
item no. 12.11( C ) (IV)
Concrete to be cast with a tremie pipe 200mm dia.
b) Machinery( for boring and construction )
Hire and running charges of hydraulic piling rig with power hour 6.00 5486.97 32921.84 P&M-036
unit and complete accessories including shifting from one
bore location to another.
Hire and running charges of light crane for lowering hour 0.50 374.03 187.02 P&M-013
reinforcement cage
Hire and running charges of Bentonite pump hour 6.00 Rate included
in piling rig
Loader I cum bucket capacity. hour 0.50 803.34 401.67 P&M-017

Tipper 5.5 cum capacity for disposal of muck from pile bore hour 0.50 491.65 245.83 P&M-048
hole
Bentonite kg 385.00 18.53 7132.18 M-070

c) Labour
Mate/Supervisor day 0.18 329.34 59.28 L-12

Mazdoor day 4.50 152.91 688.08 L-13

d) Overhead charges @ 0.25 on (b+c) 10408.97

e) Contractor's profit @ 0.1 on (b+c+d) 5204.49

Cost for 9 m = a+b+c+d+d+e 153762.65

Rate per metre (a+b+c+d+e)/9 17084.74


say 17085.00

17085.00
Ref. to Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
MoRTH Spec.
12.26 1100 & 1700 Driven cast-in-place vertical M35 grade R.C.C. Pile
excluding Reinforcement complete as per Drawing and &
Technical Specification
Pile diameter - 750 mm
Unit = Running meter
Taking output = 40 metre
a) Materials
PCC Grade M35 cum 17.66 9490.00 167593.40 Item 12.11
(C) iv
Rate for concrete may be adopted same as for bottom plug vide
item no. 12.11( C ) (IV)
b) Materials Pile shoes
i) C.I. shoes for the pile Kg 160.00 98.80 15808.13 M-085

ii) M.S. clamps for shoe @ 35 Kg per pile of 15 m Kg 70.00 71.02 4971.33 M-130

iii) Steel helmet and cushion block on top of casing head Kg 50.00 58.81 2940.50 M-179
during driving
c) Machinery
Hire and running charges of piling rig Including double hour 6.00 1176.20 7057.20 P&M-085
acting pile driving hammer complete with power unit and
accessories..
Hiring and running charges for light crane 5 tonnes lifting hour 0.50 805.70 402.85 P&M-070
capacity for lowering reinforcement and handling steel
casing.
d) Labour
Mate/Supervisor day 0.12 329.34 39.52 L-12

Mazdoor day 3.00 152.91 458.72 L-13

e) Overhead charges @ 0.25 on (b+c+d) 7919.56

f) Contractor's profit @ 0.1 on (b+c+d+e) 3959.78

Cost for 40 m = a+b+c+d+e 211150.98

Rate per metre (a+b+c+d+e)/40 5278.77


say 5279.00

5279.00
Note 1.The quantity of concrete required to be removed above the
designed top level of concrete, if any, will be provided for in the
rate analysis.
2.In case steel lining is included in the design for driven cast-in-
situ pile and is planned to be retained, the same may be
included in the rate analysis. In case the temporary steel casing
used during casting is planned to be removed, an additional cost
@ 0.50 per cent of cost of concrete may be provided to cover its
usage.
Ref. to Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
MoRTH Spec.
12.27 1100 & 1700 Driven cast-in-place vertical M35 grade R.C.C. Pile
excluding Reinforcement complete as per Drawing and &
Technical Specification
Pile diameter - 1000 mm
Unit = Running meter
Taking output = 30 metre
a) Materials
PCC Grade M35 cum 23.55 9490.00 223489.50 Item 12.11
(C) iv
Rate for concrete may be adopted same as for bottom plug
vide item no. 12.11( C ) (IV)
b) Materials Pile shoes
i) C.I. shoes for the pile Kg 160.00 98.80 15808.13 M-085

ii) M.S. clamps for shoe @ 35 Kg per pile of 15 m Kg 70.00 71.02 4971.33 M-130

iii) Steel helmet and cushion block on top of casing head Kg 50.00 58.81 2940.50 M-179
during driving
c) Machinery
Hire and running charges of piling rig Including double hour 6.00 1176.20 7057.20 P&M-085
acting pile driving hammer complete with power unit and
accessories.
Hiring and running charges for light crane 5 tonnes lifting hour 0.50 805.70 402.85 P&M-070
capacity for lowering reinforcement and handling steel
casing.
Hire and running charges for light crane for lowering hour 0.50 374.03 187.02 P&M-013
reinforcement cage.
d) Labour
Mate/Supervisor day 0.16 329.34 52.69 L-12

Mazdoor day 4.00 152.91 611.62 L-13

e) Overhead charges @ 0.25 on (b+c+d) 8007.83

f) Contractor's profit @ 0.1 on (b+c+d+e) 4003.92

Cost for 30 m = a+b+c+d+e 267532.59

Rate per metre (a+b+c+d+e)/30 8917.75


say 8918.00

8918.00
Note 1.The quantity of concrete required to be removed above the
designed top level of concrete, if any, will be provided for in the
rate analysis.
2.In case steel lining is included in the design for driven cast-in-
situ pile and is planned to be retained, the same may be
included in the rate analysis. In case the temporary steel casing
used during casting is planned to be removed, an additional cost
@ 0.50 per cent of cost of concrete may be provided to cover its
usage.
Ref. to Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
MoRTH Spec.
12.28 1100 & 1700 Driven cast-in-place vertical M35 grade R.C.C. Pile
excluding Reinforcement complete as per Drawing and &
Technical Specification
Pile diameter - 1200 mm
Unit = Running meter
Taking output = 20 metre
a) Materials
PCC Grade M35 cum 22.61 9490.00 214568.90 Item 12.11
(C) iv
Rate for concrete may be adopted same as for bottom plug
vide item no. 12.11( C ) (IV)
b) Materials Pile shoes
i) C.I. shoes for the pile Kg 160.00 98.80 15808.13 M-085

ii) M.S. clamps for shoe @ 35 Kg per pile of 15 m Kg 70.00 71.02 4971.33 M-130

iii) Steel helmet on top of casing head during driving Kg 50.00 58.81 2940.50 M-179

c) Machinery
Hire and running charges of piling rig Including double hour 6.00 1176.20 7057.20 P&M-085
acting pile driving hammer complete with power unit and
accessories.
Hiring and running charges for light crane 5 tonnes lifting hour 0.50 805.70 402.85 P&M-070
capacity for lowering reinforcement and handling steel
casing.
d) Labour
Mate/Supervisor day 0.18 329.34 59.28 L-12

Mazdoor day 4.50 152.91 688.08 L-13

e) Overhead charges @ 0.25 on (b+c+d) 7981.84

f) Contractor's profit @ 0.1 on (b+c+d+e) 3990.92

Cost for 20 m = a+b+c+d+e 258469.02

Rate per metre (a+b+c+d+e)/20 12923.45


say 12923.00

12923.00
Note 1.The quantity of concrete required to be removed above the
designed top level of concrete, if any, will be provided for in the
rate analysis.
2.In case steel lining is included in the design for driven cast-in-
situ pile and is planned to be retained, the same may be
included in the rate analysis. In case the temporary steel casing
used during casting is planned to be removed, an additional cost
@ 0.50 per cent of cost of concrete may be provided to cover its
usage.
Ref. to Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
MoRTH Spec.
12.29 1100 & 1700 Driven precast vertical M35 grade R.C.C. Piles excluding
Reinforcement complete as per Drawing and & Technical
Specification
Pile Diameter = 500 mm
Unit = Running Meter
Taking output = 60 m
a) Materials
RCC Grade M35 cum 11.78 9053.00 106644.34 Item 12.11
(F) iv

Rate for concrete may be adopted same as for bottom plug


vide item no. 12.11( F ) (IV)
b ) Material Pile shoes
a) C.I Shoes Kg 240.00 98.80 23712.19 M-085

b) M.S. shoes Kg 105.00 77.19 8105.37 M-131

c) Steel helmet and cushion block on top of pile head Kg 30.00 58.81 1764.30 M-179
during driving.
c) Machinery
Crane20 t capacity hour 6.00 940.96 5645.76 P&M-073

Vibrating Pile driving hammer complete with power unit and hour 6.00 999.77 5998.62 P&M-090
accessories.
d) Labour
Mate/Supervisor day 0.12 329.34 39.52 L-12

Mazdoor day 3.00 152.91 458.72 L-13

Add 1 per cent of (a+b+c) for carriage of piles from 1523.69


casting yard to work site and stacking, and other
imponderables during installation.
e) Overhead charges @ 0.25 on (b+c+d) 11812.04

f) Contractor's profit @ 0.1 on (b+c+d+e) 5906.02

Cost for 60 m = a+b+c+d+e+f 171610.57

Rate per metre (a+b+c+d+e+f)/60 2860.18


say 2860.00

2860.00
Note The quantity of concrete required to be removed above the
designed top level of concrete, if any, will be provided for in the
rate analysis.
Ref. to Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
MoRTH Spec.
12.30 1100 & 1700 Driven precast vertical M35 grade R.C.C. Piles excluding
Reinforcement complete as per Drawing and & Technical
Specification
Pile Diameter = 750 mm
Unit = Running Meter
Taking output = 50 m
a) Materials
RCC Grade M35 cum 22.08 9053.00 199890.24 Item 12.11
(F) iv
Rate for concrete may be adopted same as for bottom plug
vide item no. 12.11( F ) (IV)
b ) Material Pile shoes
a) C.I. shoes Kg 160.00 98.80 15808.13 M-085

b) M.S. shoes Kg 70.00 77.19 5403.58 M-131

c) Steel helmet and cushion block on top of pile head Kg 40.00 58.81 2352.40 M-179
during driving.
c) Machinery
Crane 40 T capacity hour 6.00 993.89 5963.33 P&M-074

Vibrating Pile driving hammer complete with power unit and hour 6.00 999.77 5998.62 P&M-090
accessories.
d) Labour
Mate/Supervisor day 0.16 329.34 52.69 L-12

Mazdoor day 4.00 152.91 611.62 L-13

Add 1 per cent of (a+b+c) for carriage of piles from 2360.81


casting yard to work site and stacking, and other
imponderables during installation.
e) Overhead charges @ 0.25 on (b+c+d) 9637.80

f) Contractor's profit @ 0.1 on (b+c+d+e) 4818.90

Cost for 50 m = a+b+c+d+e+f 252898.12

Rate per metre (a+b+c+d+e+f)/50 5057.96


say 5058.00

5058.00
Note The quantity of concrete required to be removed above the
designed top level of concrete, if any, will be provided for in the
rate analysis.
Ref. to Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
MoRTH Spec.
12.31 1100 & 1700 Driven precast vertical M35 grade R.C.C. Piles excluding
Reinforcement complete as per Drawing and & Technical
Specification
Pile Diameter = 1000 mm
Unit = Running Meter
Taking output = 40 m
a) Materials
RCC Grade M35 cum 31.40 9053.00 284264.20 Item 12.11
(F) iv
Rate for concrete may be adopted same as for bottom plug
vide item no. 12.11( F ) (IV)
b ) Material Pile shoes
a) C.I. shoes for the pile Kg 160.00 98.80 15808.13 M-085

b) M.S. shoes @ 35 Kg per pile of 15 m Kg 70.00 77.19 5403.58 M-131

c) Steel helmet and cushion block on top of pile head Kg 50.00 58.81 2940.50 M-179
during driving.
c) Machinery
Crane 50 t capacity. hour 6.00 1336.16 8016.98 P&M-011

Vibrating Pile driving hammer complete with power unit and hour 6.00 999.77 5998.62 P&M-090
accessories.
d) Labour
Mate/Supervisor day 0.20 329.34 65.87 L-12

Mazdoor day 5.00 152.91 764.53 L-13

Add 1 per cent of (a+b+c) for carriage of piles from 3232.62


casting yard to work site and stacking, and other
imponderables during installation.
e) Overhead charges @ 0.25 on (b+c+d) 10557.71

f) Contractor's profit @ 0.1 on (b+c+d+e) 5278.85

Cost for 40 m = a+b+c+d+e+f 342331.59

Rate per metre (a+b+c+d+e+f)/40 8558.29


say 8558.00

8558.00
Note The quantity of concrete required to be removed above the
designed top level of concrete, if any, will be provided for in the
rate analysis.
Ref. to Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
MoRTH Spec.
12.32 1100&1700 Driven precast vertical M35 grade R.C.C. Piles excluding
Reinforcement complete as per Drawing and & Technical
Specification
Size of pile - 300 mm x 300 mm
Unit = Running Meter
Taking output = 60 m
a) Materials
RCC Grade M-35
Rate for concrete may be adopted same as for bottom plug cum 5.40 9053.00 48886.20 Item 12.11
vide item no. 12.11( F ) (IV) (F) iv

b ) Material Pile shoes


a) C I shoes kg 240.00 98.80 23712.19 M-085

b) M. S shoes kg 105.00 77.19 8105.37 M-131

c) Steel helmet and cushion block on top of pile head Kg 30.00 58.81 1764.30 M-179
during driving.
c) Machinery
Crane 10 tonne capacity hour 6.00 882.15 5292.90 P&M-071

Vibrating Pile driving hammer complete with power unit and hour 6.00 999.77 5998.62 P&M-090
accessories.
d ) Labour
Mate/Supervisor day 0.12 329.34 39.52 L-12

Mazdoor day 3.00 152.91 458.72 L-13

Add 1 per cent of (a+b+c) for carriage of piles from 942.58


casting yard to work site and stacking, and other
imponderables during installation.
e) Overhead charges @ 0.25 on (b+c+d) 11578.55

f) Contractor's profit @ 0.1 on (b+c+d+e) 5789.27

Cost for 60 m = a+b+c+d+e+f 112568.22

Rate per metre (a+b+c+d+e+f)/60 1876.14


say 1876.00

1876.00
Note The quantity of concrete required to be removed above the
designed top level of concrete, if any, will be provided for in the
rate analysis.
Ref. to Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
MoRTH Spec.
12.33 1100 &1700 Driven precast vertical M35 grade R.C.C. Piles excluding
Reinforcement complete as per Drawing and & Technical
Specification
Size of pile - 500 mm x 500 mm
Unit = Running Meter
Taking output = 50 m
a) Materials
RCC Grade M-35
Rate for concrete may be adopted same as for bottom plug cum 12.50 9053.00 113162.50 Item 12.11
vide item no. 12.11( F ) (IV) (F) iv

b ) Material Pile shoes


a) C I shoes kg 160.00 98.80 15808.13 M-085

b) M. S shoes kg 70.00 77.19 5403.58 M-131

c) Steel helmet and cushion block on top of pile head Kg 30.00 58.81 1764.30 M-179
during driving.
c) Machinery
Crane 20 tonne capacity hour 6.00 940.96 5645.76 P&M-073

Vibrating Pile driving hammer complete with power unit and hour 6.00 999.77 5998.62 P&M-090
accessories.
d ) Labour
Mate/Supervisor day 0.16 329.34 52.69 L-12

Mazdoor day 4.00 152.91 611.62 L-13

Add 1 per cent of (a+b+c) for carriage of piles from 1484.47


casting yard to work site and stacking, and other
imponderables during installation.
e) Overhead charges @ 0.25 on (b+c+d) 9192.29

f) Contractor's profit @ 0.1 on (b+c+d+e) 4596.15

Cost for 50 m = a+b+c+d+e+f 163720.12

Rate per metre (a+b+c+d+e+f)/50 3274.40


say 3274.00

3274.00
Note The quantity of concrete required to be removed above the
designed top level of concrete, if any, will be provided for in the
rate analysis.
Ref. to Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
MoRTH Spec.
12.34 1100 &1700 Driven precast vertical M35 grade R.C.C. Piles excluding
Reinforcement complete as per Drawing and & Technical
Specification
Size of pile - 750 mm x 750 mm
Unit = Running Meter
Taking output = 40 m
a) Materials
RCC Grade M-35
Rate for concrete may be adopted same as for bottom plug cum 22.50 9053.00 203692.50 Item 12.11
vide item no. 13.11( F ) (IV) (F) iv

b ) Material
Pile shoes
a) C I shoes kg 160.00 98.80 15808.13 M-085

b) M. S shoes kg 70.00 77.19 5403.58 M-131

c) Steel helmet and cushion block on top of pile head Kg 30.00 58.81 1764.30 M-179
during driving.
c) Machinery
Crane 20 tonne capacity hour 6.00 940.96 5645.76 P&M-073

Vibrating Pile driving hammer complete with power unit and hour 6.00 999.77 5998.62 P&M-090
accessories.
d ) Labour
Mate/Supervisor day 0.18 329.34 59.28 L-12

Mazdoor day 4.50 152.91 688.08 L-13

Add 1 per cent of (a+b+c) for carriage of piles from 2390.60


casting yard to work site and stacking, and other
imponderables during installation.
e) Overhead charges @ 0.25 on (b+c+d) 9439.59

f) Contractor's profit @ 0.1 on (b+c+d+e) 4719.79

Cost for 40 m = a+b+c+d+e+f 255610.23

Rate per metre (a+b+c+d+e+f)/40 6390.26


say 6390.00

6390.00
Note The quantity of concrete required to be removed above the
designed top level of concrete, if any, will be provided for in the
rate analysis.
12.35 1100, 1900 Driven Vertical Steel Piles complete as per Drawing and &
Technical Specification
Section of the pile - H Section steel column 400 x 250 mm
(ISHB Series)
Unit = Running Meter
Taking output = 70 m
a) Materials
Structural steel including 5 per cent wastage @ 82.20 kg/m tonnes 6.04 60000.00 362400.00 M-185

b) Machinery
Crane 10 T capacity hour 6.00 882.15 5292.90 P&M-071

Vibrating Pile driving hammer complete with power unit and hour 6.00 999.77 5998.62 P&M-090
other accessories.
c) Labour
Mate/Supervisor day 0.12 329.34 39.52 L-12

Mazdoor day 3.00 152.91 458.72 L-13

Add 0.5 per cent of (a+b+c) for providing steel helmet 1870.95
on top of pile head during driving, stacking of piles at site,
providing anti-corrosion treatment and other imponderables
during installation.
d) Overhead charges @ 0.25 on (a+b+c) 94015.18

e) Contractor's profit @ 0.1 on (a+b+c+d) 47007.59

Cost for 70 m = a+b+c+d+e 517083.47

Rate per metre (a+b+c+d+e)/70 7386.91


say 7387.00

7387.00
Ref. to Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
MoRTH Spec.
12.36 1100 &1900 Driven Vertical Steel Piles complete as per Drawing and &
Technical Specification
Section of the pile - H Section steel column 450 x 250 mm
(ISHB Series)
Unit = Running Meter
Taking output = 60 m
a) Materials
Structural steel including 5 per cent wastage @92.50 kg/m tonnes 5.83 60000.00 349800.00 M-185

b) Machinery
Crane 10 T capacity hour 6.00 882.15 5292.90 P&M-071

Vibrating Pile driving hammer complete with power unit and hour 6.00 999.77 5998.62 P&M-090
accessories.
c) Labour
Mate/Supervisor day 0.14 329.34 46.11 L-12

Mazdoor day 3.50 152.91 535.17 L-13

Add 0.5 per cent of (a+b+c) for providing steel helmet 1808.36
and cushion block on top of pile head during driving,
stacking of piles at site, providing anti-corrosive treatment
and other imponderables during installation.
d) Overhead charges @ 0.25 on (a+b+c) 90870.29

e) Contractor's profit @ 0.1 on (a+b+c+d) 45435.15

Cost for 60 m = a+b+c+d+e 499786.60

Rate per metre (a+b+c+d+e)/60 8329.78


say 8330.00

8330.00
12.37 1100 Pile Load Test on single Vertical Pile in accordance with
IS:2911(Part-IV)
Unit = 1 MT
Taking output = 1 MT
a) Initial and routine load test tonne 1.00 363.00 363.00

b) Lateral load test tonne 1.00 6050.00 6050.00

Note Although, this item is incidental to work and is not required to be 6413.00
included in BOQ of contract, the same is required to be added in
the estimate to assess cost of work.
Ref. to Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
MoRTH Spec.
12.38 1100, 1500 Cement Concrete for Reinforced Concrete in Pile Cap
&1700 complete as per Drawing and Technical Specification
A RCC Grade M20
Unit = cum
Taking output = 15 cum
(i) Using Concrete Mixer
a) Material
Cement tonne 5.12 8939.12 45768.29 M-086

Coarse sand cum 6.75 1176.20 7939.35 M-005

20 mm Aggregate cum 8.10 1529.06 12385.39 M-053

10 mm Aggregate cum 5.40 1529.06 8256.92 M-051

b) Labour
Mate day 0.90 329.34 296.40 L-12

Mason day 1.50 294.05 441.08 L-10

Mazdoor for concreting day 20.00 152.91 3058.12 L-13

Mazdoor for breaking pile head, bending bars, cleaning etc. day 1.00 152.91 152.91 L-13

c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 237.59 1425.55 P&M-009

Generator (capacity 33 KVA) hour 6.00 365.80 2194.79 P&M-079

Formwork @ 4 per cent on cost of concrete i.e. cost of a) 3276.75


Material, b) Labour and c) Machinery
d) Overhead charges @ 0.25 on (a+b+c) 21298.89

e) Contractor's profit @ 0.1 on (a+b+c+d) 10649.44

Cost for 15 cum = a+b+c+d+e 117143.89

Rate per metre (a+b+c+d+e)/15 7809.59


say 7810.00

7810.00
12.38A (ii) Using Batching Plant, Transit Mixer and Concrete Pump

a) Material
Cement tonne 5.12 8939.12 45768.29 M-086

Coarse sand cum 6.75 1176.20 7939.35 M-004

20 mm Aggregate cum 8.10 1529.06 12385.39 M-053

10 mm Aggregate cum 5.40 1529.06 8256.92 M-051

b) Labour
Mate day 0.16 329.34 52.69 L-12

Mason day 0.38 294.05 111.74 L-10

Mazdoor for concreting day 2.50 152.91 382.27 L-13

Mazdoor for breaking pile head, bending bars, cleaning etc. day 1.00 152.91 152.91 L-13

c) Machinery
Batching Plant @ 20 cum/hour hour 0.75 2301.82 1726.37 P&M-002

Generator 100 KVA hour 0.75 730.42 547.82 P&M-080

Loader (capacity 1 cum) hour 0.75 803.34 602.51 P&M-017

Transit Mixer ( capacity 4.0 cu.m )


Lead upto 1 Km hour 2.00 973.89 1947.79 P&M-049

Lead beyond 1 Km, L - lead in Kilometer tonne.km 37.5L 47.05 5292.90 Lead =3 km
& P&M-050
Concrete Pump hour 0.75 275.23 206.42 P&M-007

Formwork @ 4 per cent on cost of concrete i.e. cost of a) 3414.93


Material, b) Labour and c) Machinery
d) Overhead charges @ 0.25 on (a+b+c) 22197.07

e) Contractor's profit @ 0.1 on (a+b+c+d) 11098.54

Cost for 15 cum = a+b+c+d+e 122083.90

Rate per metre (a+b+c+d+e)/15 8138.93


say 8139.00

8139.00
Note The value of a, b and c may be taken as applicable i.e. either
using concrete mixer or batching plant.
Ref. to Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
MoRTH Spec.
12.38 B RCC Grade M25
Unit = cum
Taking output = 15 cum
(i) Using Concrete Mixer
a) Material
Cement tonne 5.99 8939.12 53545.33 M-086

Coarse sand cum 6.75 1176.20 7939.35 M-005

20 mm Aggregate cum 8.10 1529.06 12385.39 M-053

10 mm Aggregate cum 5.40 1529.06 8256.92 M-051

b) Labour
Mate day 0.90 329.34 296.40 L-12

Mason day 1.50 294.05 441.08 L-10

Mazdoor for concreting day 20.00 152.91 3058.12 L-13

Mazdoor for breaking pile head, bending bars, cleaning etc. day 1.00 152.91 152.91 L-13

c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 237.59 1425.55 P&M-009

Generator (capacity 33 KVA) hour 6.00 365.80 2194.79 P&M-079

Formwork @ 4 per cent on cost of concrete i.e. cost of a) 3587.83


Material, b) Labour and c) Machinery
d) Overhead charges @ 0.25 on (a+b+c) 23320.92

e) Contractor's profit @ 0.1 on (a+b+c+d) 11660.46

Cost for 15 cum = a+b+c+d+e 128265.05

Rate per metre (a+b+c+d+e)/15 8551.00


say 8551.00

8551.00
12.38B (ii) Using Batching Plant, Transit Mixer and Concrete Pump

a) Material
Cement tonne 5.99 8939.12 53545.33 M-086

Coarse sand cum 6.75 1176.20 7939.35 M-004

20 mm Aggregate cum 8.10 1529.06 12385.39 M-053

10 mm Aggregate cum 5.40 1529.06 8256.92 M-051

b) Labour
Mate day 0.16 329.34 52.69 L-12

Mason day 0.38 294.05 111.74 L-10

Mazdoor for concreting day 2.50 152.91 382.27 L-13

Mazdoor for breaking pile head, bending bars, cleaning etc. day 1.00 152.91 152.91 L-13

c) Machinery
Batching Plant @ 20 cum/hour hour 0.75 2301.82 1726.37 P&M-002

Generator 125 KVA hour 0.75 979.77 734.83 P&M-018

Loader (capacity 1 cum) hour 0.75 803.34 602.51 P&M-017

Transit Mixer ( capacity 4.0 cu.m )


Lead upto 1 Km hour 2.00 973.89 1947.79 P&M-049

Lead beyond 1 Km, L - lead in Kilometer tonne.km 37.5L 47.05 5292.90 Lead =3 km
& P&M-050
Concrete Pump hour 0.75 275.23 206.42 P&M-007

Formwork @ 4 per cent on cost of concrete i.e. cost of a) 3733.50


Material, b) Labour and c) Machinery
d) Overhead charges @ 0.25 on (a+b+c) 24267.73

e) Contractor's profit @ 0.1 on (a+b+c+d) 12133.86

Cost for 15 cum = a+b+c+d+e 133472.50

Rate per metre (a+b+c+d+e)/15 8898.17


say 8898.00

8898.00
Note The value of a, b and c may be taken as applicable i.e. either
using concrete mixer or batching plant.
Ref. to Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
MoRTH Spec.
12.38 C RCC Grade M30
Unit = cum
Taking output = 15 cum
(i) Using Concrete Mixer
a) Material
Cement tonne 6.10 8939.12 54528.63 M-086

Coarse sand cum 6.75 1176.20 7939.35 M-005

20 mm Aggregate cum 8.10 1529.06 12385.39 M-053

10 mm Aggregate cum 5.40 1529.06 8256.92 M-051

b) Labour
Mate day 0.90 329.34 296.40 L-12

Mason day 1.50 294.05 441.08 L-10

Mazdoor for concreting day 20.00 152.91 3058.12 L-13

Mazdoor for breaking pile head, bending bars, cleaning etc. day 1.00 152.91 152.91 L-13

c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 237.59 1425.55 P&M-009

Generator (capacity 33 KVA) hour 6.00 365.80 2194.79 P&M-079

Formwork @ 4 per cent on cost of concrete i.e. cost of a) 3627.17


Material, b) Labour and c) Machinery
d) Overhead charges @ 0.25 on (a+b+c) 23576.58

e) Contractor's profit @ 0.1 on (a+b+c+d) 11788.29

Cost for 15 cum = a+b+c+d+e 129671.17

Rate per metre (a+b+c+d+e)/15 8644.74


say 8645.00

8645.00
'12.38C (ii) Using Batching Plant, Transit Mixer and Concrete Pump

a) Material
Cement tonne 6.10 8939.12 54528.63 M-086

Coarse sand cum 6.75 1176.20 7939.35 M-004

20 mm Aggregate cum 8.10 1529.06 12385.39 M-053

10 mm Aggregate cum 5.40 1529.06 8256.92 M-051

b) Labour
Mate day 0.16 329.34 52.69 L-12

Mason day 0.38 294.05 111.74 L-10

Mazdoor for concreting day 2.50 152.91 382.27 L-13

Mazdoor for breaking pile head, bending bars, cleaning etc. day 1.00 152.91 152.91 L-13

c) Machinery
Batching Plant @ 20 cum/hour hour 0.75 2301.82 1726.37 P&M-002

Generator 100 KVA hour 0.75 730.42 547.82 P&M-080

Loader (capacity 1 cum) hour 0.75 803.34 602.51 P&M-017

Transit Mixer ( capacity 4.0 cu.m )


Lead upto 1 Km hour 2.00 973.89 1947.79 P&M-049

Lead beyond 1 Km, L - lead in Kilometer tonne.km 37.5L 47.05 5292.90 Lead =3 km
& P&M-050
Concrete Pump hour 0.75 275.23 206.42 P&M-007

Formwork @ 4 per cent on cost of concrete i.e. cost of a) 3765.35


Material, b) Labour and c) Machinery
d) Overhead charges @ 0.25 on (a+b+c) 24474.76

e) Contractor's profit @ 0.1 on (a+b+c+d) 12237.38

Cost for 15 cum = a+b+c+d+e 134611.19

Rate per metre (a+b+c+d+e)/15 8974.08


say 8974.00

8974.00
Note The value of a, b and c may be taken as applicable i.e. either
using concrete mixer or batching plant.
Ref. to Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
MoRTH Spec.
12.38 D RCC Grade M35
Unit = cum
Taking output = 15 cum
(i) Using Concrete Mixer
a) Material
Cement tonne 6.33 8939.12 56584.63 M-086

Coarse sand cum 6.75 1176.20 7939.35 M-005

20 mm Aggregate cum 8.10 1529.06 12385.39 M-053

10 mm Aggregate cum 5.40 1529.06 8256.92 M-051

b) Labour
Mate day 0.90 329.34 296.40 L-12

Mason day 1.50 294.05 441.08 L-10

Mazdoor day 20.00 152.91 3058.12 L-13

Mazdoor for breaking pile head, bending bars, cleaning etc. day 1.00 152.91 152.91 L-13

c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 237.59 1425.55 P&M-009

Generator (capacity 33 KVA) hour 6.00 365.80 2194.79 P&M-079

Formwork @ 4 per cent on cost of concrete i.e. cost of a) 3709.41


Material, b) Labour and c) Machinery
d) Overhead charges @ 0.25 on (a+b+c) 24111.14

e) Contractor's profit @ 0.1 on (a+b+c+d) 12055.57

Cost for 15 cum = a+b+c+d+e 132611.25

Rate per metre (a+b+c+d+e)/15 8840.75


say 8841.00

8841.00
'12.38D (ii) Using Batching Plant, Transit Mixer and Concrete Pump

a) Material
Cement tonne 6.33 8939.12 56584.63 M-086

Coarse sand cum 6.75 1176.20 7939.35 M-004

20 mm Aggregate cum 8.10 1529.06 12385.39 M-053

10 mm Aggregate cum 5.40 1529.06 8256.92 M-051

b) Labour
Mate day 0.16 329.34 52.69 L-12

Mason day 0.38 294.05 111.74 L-10

Mazdoor for concreting day 2.50 152.91 382.27 L-13

Mazdoor for breaking pile head, bending bars, cleaning etc. day 1.00 152.91 152.91 L-13

c) Machinery
Batching Plant @ 20 cum/hour hour 0.75 2301.82 1726.37 P&M-002

Generator 125 KVA hour 0.75 979.77 734.83 P&M-018

Loader (capacity 1 cum) hour 0.75 803.34 602.51 P&M-017

Transit Mixer ( capacity 4.0 cu.m )


Lead upto 1 Km hour 2.00 973.89 1947.79 P&M-049

Lead beyond 1 Km, L - lead in Kilometer tonne.km 37.5L 47.05 5292.90 Lead =3 km
& P&M-050
Concrete Pump hour 0.75 275.23 206.42 P&M-007

Formwork @ 4 per cent on cost of concrete i.e. cost of a) 3855.07


Material, b) Labour and c) Machinery
d) Overhead charges @ 0.25 on (a+b+c) 25057.94

e) Contractor's profit @ 0.1 on (a+b+c+d) 12528.97

Cost for 15 cum = a+b+c+d+e 137818.70

Rate per metre (a+b+c+d+e)/15 9187.91


say 9188.00

9188.00
Ref. to Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
MoRTH Spec.
12.39 1100&1700 Levelling Course for Pile cap
Providing and laying of PCC M15 levelling course 100mm
thick below the pile cap.
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 4.13 8939.12 36918.57 M-086

Coarse sand cum 6.75 1176.20 7939.35 M-005

40 mm aggregate cum 8.10 1411.44 11432.66 M-055

20 mm Aggregate cum 4.05 1529.06 6192.69 M-053

10 mm Aggregate cum 1.35 1529.06 2064.23 M-051

b) Labour
Mate day 0.86 329.34 283.23 L-12

Mason day 1.50 294.05 441.08 L-10

Mazdoor day 20.00 152.91 3058.12 L-13

c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 237.59 1425.55 P&M-009

Generator 33 KVA hour 6.00 365.80 2194.79 P&M-079

d) Overhead charges @ 0.25 on (a+b+c) 17987.57

e) Contractor's profit @ 0.1 on (a+b+c+d) 8993.78

Cost for 15 cum = a+b+c+d+e 98931.62

Rate per metre (a+b+c+d+e)/15 6595.44


say 6595.00

6595.00
12.40 1600 Supplying, Fitting and Placing un-coated HYSD bar
Reinforcement in Foundation complete as per Drawing and
Technical Specifications.
Unit = 1 MT
Taking output = 1 MT
a) Material
HYSD bars including5 per cent overlaps and wastage tonne 1.05 44000.00 46200.00 M-087

Binding wire Kg 6.00 92.63 555.75 M-071

b) Labour for cutting, bending, shifting to site, tying and


placing in position
Mate day 0.40 329.34 131.73 L-12

Blacksmith day 2.00 352.86 705.72 L-02

Mazdoor day 6.00 152.91 917.44 L-13

c) Overhead charges @ 0.25 on (a+b) 12127.66

d) Contractor's profit @ 0.1 on (a+b+c) 6063.83

Rate per MT (a+b+c+d) 66702.14


say 66702.00

66702.00
12.41 1600 Supplying, fitting and placing un-coated Mild steel
reinforcement complete in foundation as per drawing and
technical specification
Unit = 1 MT
Taking output = 1 MT
a) Material
MS bars including 5 per cent overlaps and wastage tonne 1.05 56457.60 59280.48 M-132

Binding wire Kg 6.00 92.63 555.75 M-071

b) Labour for straightening, cutting, bending, shifting to


site, tying and placing in position
Mate day 0.43 329.34 141.61 L-12

Blacksmith day 2.25 352.86 793.94 L-02

Mazdoor day 6.50 152.91 993.89 L-13

c) Overhead charges @ 0.25 on (a+b) 15441.42

d) Contractor's profit @ 0.1 on (a+b+c) 7720.71

Rate for per MT (a+b+c+d) 84927.80


say 84928.00
Ref. to Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
MoRTH Spec.
85526.00
CHAPTER-13
SUB-STRUCTURE
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
13.1 1300 & Brick masonry work in 1:3 in sub-structure complete
2200 excluding pointing and plastering, as per drawing and
Technical Specifications
Unit = cum
Taking output = 1 cum
a) Material
Bricks Ist class each 500.00 8.23 4116.70 M-084
Cement mortar 1:3 (Rate as in Item 12.6 A sub-analysis) cum 0.24 5945.00 1426.80 Item 12.6 (A)
b) Labour
Mate day 0.06 329.34 19.76 L-12
Mason day 0.80 352.86 282.29 L-11
Mazdoor day 0.80 152.91 122.32 L-13
Add for scaffolding @ 5 per cent of cost of material and 298.39
labour
c) Overhead charges @ 0.25 on (a+b) 1566.57
d) Contractor's profit @ 0.1 on (a+b+c) 783.28
Rate per cum (a+b+c+d) 8616.12
say 8616.00
8616.00
13.2 1300 & Pointing with cement mortar (1:3 ) on brick work in
2200 substructure as per Technical Specifications
Unit = 10 sqm
Taking output = 10 sqm
a) Material
Cement mortar 1:3 (Rate as in Item 12.6 ) cum 0.03 5945.00 178.35 Item 12.6 (A)

b) Labour
Mate day 0.04 329.34 13.17 L-12
Mason day 0.50 352.86 176.43 L-11
Mazdoor day 0.50 152.91 76.45 L-13
c) Overhead charges @ 0.25 on (a+b) 111.10
d) Contractor's profit @ 0.1 on (a+b+c) 55.55
Rate per 10 sqm (a+b+c+d) 611.06
say 611.00
611.00
Note Scaffolding is already included in item 13.1
13.3 1300 & Plastering with cement mortar (1:3 ) on brick work in sub-
2200 structure as per Technical Specifications
Unit = 10 sqm
Taking output = 10 sqm
a) Material
Cement mortar 1:3 (Rate as in Item 12.6) cum 0.144 5945.00 856.08 Item 12.6 (A)
b) Labour
Mate day 0.04 329.34 13.17 L-12
Mason day 0.50 352.86 176.43 L-11
Mazdoor day 0.50 152.91 76.45 L-13
c) Overhead charges @ 0.25 on (a+b) 280.53
d) Contractor's profit @ 0.1 on (a+b+c) 140.27
Rate per 10 sqm (a+b+c+d) 1542.94
say 1543.00
1543.00
Note 1.Scaffolding is already included in item no. 13.1
2.The number of masons and Mazdoors already catered in the
cement mortar have been taken into account while providing these
categories in brick masonry, pointing and plastering.
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
13.4 1400 & Stone masonry work in cement mortar 1:3 for substructure
2200 complete as per drawing and Technical Specifications

A Random Rubble Masonry


( coursed/uncoursed )
Unit = cum
Taking output = 1 cum
a) Material
Stone cum 1.00 802.76 802.76 M-153
Through and bond stone No 7.00 6.80 47.59 M-188
(7no.x0.24mx0.24mx0.39m = 0.16 cu.m)
Cement mortar 1:3 (Rate as in Item 12.6) cum 0.33 5945.00 1961.85 Item 12.6 (A)
b) Labour
Mate day 0.10 329.34 32.93 L-12
Mason day 1.20 352.86 423.43 L-11
Mazdoor day 1.20 152.91 183.49 L-13
Add for scaffolding @ 5 per cent of cost of a) Material and 172.60
b) Labour
c) Overhead charges @ 0.25 on (a+b) 906.16
d) Contractor's profit @ 0.1 on (a+b+c) 453.08
Rate per cum (a+b+c+d) 4983.89
say 4984.00
4984.00
13.4 B Coursed rubble masonry (first sort )
Unit = cum
Taking output = 1 cum
a) Material
Stone cum 1.10 802.76 883.03 M-153
Through and bond stone each 7.00 6.80 47.59 M-188
(7no.x0.24mx0.24mx0.39m = 0.16 cu.m)
Cement mortar 1:3 (Rate as in Item 12.6) cum 0.30 5945.00 1783.50 Item 12.6 (A)
b) Labour
Mate day 0.12 329.34 39.52 L-12
Mason day 1.50 352.86 529.29 L-11
Mazdoor day 1.50 152.91 229.36 L-13
Add for scaffolding @ 5 per cent of cost of material and 175.61
labour
c) Overhead charges @ 0.25 on (a+b) 921.98
d) Contractor's profit @ 0.1 on (a+b+c) 460.99
Rate per cum (a+b+c+d) 5070.87
say 5071.00
5071.00
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
13.4 C Ashlar masonry ( first sort )
Plain ashlar
Unit = cum
Taking output = 1 cum
a) Material
Stone cum 1.11 1074.46 1192.65 M-175
Through and bond stone each 7.00 6.80 47.59 M-188
(7no.x0.24mx0.24mx0.39m = 0.16 cu.m)
Cement mortar 1:3 (Rate as in Item 12.6) cum 0.33 5945.00 1961.85 Item 12.6 (A)
b) Labour for masonry work
Mate day 0.20 329.34 65.87 L-12
Mason day 2.50 352.86 882.15 L-11
Mazdoor day 2.50 152.91 382.27 L-13
Add for scaffolding @ 5 per cent of cost of a) Material and 226.62
b) Labour
c) Overhead charges @ 0.25 on (a+b) 1189.75
d) Contractor's profit @ 0.1 on (a+b+c) 594.87
Rate per cum (a+b+c+d) 6543.61
say 6544.00
6544.00
Note The labour already considered in the cement mortar have been
taken into account while providing these categories in the stone
masonry works.
13.5 1500, Plain/Reinforced cement concrete in sub-structure complete
1700 & as per drawing and Technical Specifications
2200
Unit = cum
Taking output = 1 cum
A PCC Grade M15
(p) Height upto 5m
Same as Item 12.8 (A) upto 5 m height, except for formwork which
shall be 10 per cent instead of 4 per cent of cost of material,
labour and machinery.
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) 4899.00 Item 12.8 (A)
of Item 12.8 (A)
d) formwork
Add 10 per cent of cost of material, labour and machinery 10.00 489.90
(a+b+c) for Formwork
e) Overhead charges @ 0.25 on (a+b+c+d) 1347.23
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 673.61
Rate per cum (a+b+c+d+e+f) 7409.74
say 7410.00
7410.00
13.5 B PCC Grade M20
(p) Height upto 5m
Same as Item 12.8 (B) upto 5 m height, except for formwork which
shall be 10 per cent instead of 4 per cent of cost of material,
labour and machinery.
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) 5438.00 Item 12.8 (B)
of Item 12.8 (B) PCC
d) formwork
Add 10 per cent of cost of material, labour and machinery 10.00 543.80
(a+b+c) for Formwork
e) Overhead charges @ 0.25 on (a+b+c+d) 1495.45
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 747.73
Rate per cum (a+b+c+d+e+f) 8224.98
say 8225.00
8225.00
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
13.5 C PCC Grade M25
(p) Height upto 5m
Same as Item 12.8 (D) upto 5 m height with the only change that
the provision of form work shall be 10 per cent instead of 3.75 per
cent of cost of material, labour and machinery.
Case I Using concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) 5933.00 Item 12.8 (D)
of Item 12.8 (D) Case I
d) formwork
Add 10 per cent of cost of material, labour and machinery 10.00 593.30
(a+b+c) for Formwork
e) Overhead charges @ 0.25 on (a+b+c+d) 1631.58
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 815.79
Rate per cum (a+b+c+d+e+f) 8973.66
say 8974.00
8974.00
13.5 C (p) Case II With Batching Plant, Transit Mixer and Concrete Pump

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) 5806.00 Item 12.8 (D)
of Item 12.8 (D) Case II
d) formwork
Add 10 per cent of cost of material, labour and machinery 10.00 580.60
(a+b+c) for Formwork
e) Overhead charges @ 0.25 on (a+b+c+d) 1596.65
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 798.33
Rate per cum (a+b+c+d+e+f) 8781.58
say 8782.00
8782.00
13.5 C (q) Height 5m to 10m
Same as Item 12.8 (D) with the following changes: (i) Add 2 per
cent of cost of material, Labour and machinery excluding form
work to cater for extra lift. (ii) The provision of form work shall be
12 per cent instead of 3.75 per cent of cost of material, labour
and machinery
Case I Using concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) 5933.00 Item 12.8 (D)
of Item 12.8 (D) Case I
d) formwork
Add 12 per cent of cost of material, labour and machinery 12.00 711.96
(a+b+c) for Formwork
Add 2 per cent of cost of material, Labour and machinery 2.00 118.66
excluding formwork to cater for extra lift
e) Overhead charges @ 0.25 on (a+b+c+d) 1690.91
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 845.45
Rate per cum (a+b+c+d+e+f) 9299.98
say 9300.00
9300.00
13.5 C (q) Case II With Batching Plant, Transit Mixer and Concrete Pump

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) 5806.00 Item 12.8 (D)
of Item 12.8 (D) Case II
d) formwork
Add 12 per cent of cost of material, labour and machinery 12.00 696.72
(a+b+c) for Formwork
Add 2 per cent of cost of material, Labour and machinery 2.00 116.12
excluding formwork to cater for extra lift
e) Overhead charges @ 0.25 on (a+b+c+d) 1654.71
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 827.36
Rate per cum (a+b+c+d+e+f) 9100.91
say 9101.00
9101.00
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
13.5 C (r) Height above 10m
Same as Item 12.8 (D) with the following changes: (i) Add 4 per
cent of cost of material, labour and machinery excluding form
work to cater for extra lift. (ii) The provision of form work shall be
15 per cent instead of 3.75 per cent of cost of material, labour
and machinery.
Case I Using concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) 5933.00 Item 12.8 (D)
of Item 12.8 (D) Case I
d) formwork
Add 15 per cent of cost of material, labour and machinery 15.00 889.95
(a+b+c) for Formwork
Add 4 per cent of cost of material, Labour and machinery 4.00 237.32
excluding formwork to cater for extra lift
e) Overhead charges @ 0.25 on (a+b+c+d) 1765.07
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 882.53
Rate per cum (a+b+c+d+e+f) 9707.87
say 9708.00
9708.00
13.5 C (r) Case II With Batching Plant, Transit Mixer and Concrete Pump

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) 5806.00 Item 12.8 (D)
of Item 12.8 (D) Case II
d) formwork
Add 15 per cent of cost of material, labour and machinery 15.00 870.90
(a+b+c) for Formwork
Add 4 per cent of cost of material, Labour and machinery 4.00 232.24
excluding formwork to cater for extra lift
e) Overhead charges @ 0.25 on (a+b+c+d) 1727.29
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 863.64
Rate per cum (a+b+c+d+e+f) 9500.07
say 9500.00
9500.00
13.5 D PCC Grade M30
(p) Height upto 5m
Same as Item 12.8 (F) upto 5 m height with the only change that
the provision of form work shall be 10 per cent instead of 3.50 per
cent of cost of material, labour and machinery.
Case I Using concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) 5986.00 Item 12.8 (F)
of Item 12.8 (F) Case I
d) formwork
Add 10 per cent of cost of material, labour and machinery 10.00 598.60
(a+b+c) for Formwork
e) Overhead charges @ 0.25 on (a+b+c+d) 1646.15
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 823.08
Rate per cum (a+b+c+d+e+f) 9053.83
say 9054.00
9054.00
13.5 D (p) Case II With Batching Plant, Transit Mixer and Concrete Pump

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) 5855.00 Item 12.8 (F)
of Item 12.8 (F) Case II
d) formwork
Add 10 per cent of cost of material, labour and machinery 10.00 585.50
(a+b+c) for Formwork
e) Overhead charges @ 0.25 on (a+b+c+d) 1610.13
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 805.06
Rate per cum (a+b+c+d+e+f) 8855.69
say 8856.00
8856.00
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
13.5 D (q) Height 5m to 10m
Same as Item 12.8 (F) with the following changes: (i) Add 2 per
cent of cost of material, Labour and machinery excluding form
work to cater for extra lift. (ii) The provision of form work shall be
12 per cent instead of 3.50 per cent of cost of material, labour
and machinery.
Case I Using concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) 5986.00 Item 12.8 (F)
of Item 12.8 (F) Case I
d) formwork
Add 12 per cent of cost of material, labour and machinery 12.00 718.32
(a+b+c) for Formwork
Add 2 per cent of cost of material, Labour and machinery 2.00 119.72
excluding formwork to cater for extra lift
e) Overhead charges @ 0.25 on (a+b+c+d) 1706.01
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 853.01
Rate per cum (a+b+c+d+e+f) 9383.06
say 9383.00
9383.00
13.5 D (q) Case II With Batching Plant, Transit Mixer and Concrete Pump

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) 5855.00 Item 12.8 (F)
of Item 12.8 (F) Case II
d) formwork
Add 12 per cent of cost of material, labour and machinery 12.00 702.60
(a+b+c) for Formwork
Add 2 per cent of cost of material, Labour and machinery 2.00 117.10
excluding formwork to cater for extra lift
e) Overhead charges @ 0.25 on (a+b+c+d) 1668.68
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 834.34
Rate per cum (a+b+c+d+e+f) 9177.71
say 9178.00
9178.00
13.5 D (r) Height above 10m
Same as Item 12.8 (F) with the following changes: (i) Add 4 per
cent of cost of material, labour and machinery excluding form
work to cater for extra lift. (ii) The provision of form work shall be
15 per cent instead of 3.50 per cent of cost of material, labour
and machinery
Case I Using concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) 5986.00 Item 12.8 (F)
of Item 12.8 (F) Case I
d) formwork
Add 15 per cent of cost of material, labour and machinery 15.00 897.90
(a+b+c) for Formwork
Add 4 per cent of cost of material, Labour and machinery 4.00 239.44
excluding formwork to cater for extra lift
e) Overhead charges @ 0.25 on (a+b+c+d) 1780.84
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 890.42
Rate per cum (a+b+c+d+e+f) 9794.59
say 9795.00
9795.00
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
13.5 D (r) Case II With Batching Plant, Transit Mixer and Concrete Pump

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) 5855.00 Item 12.8 (F)
of Item 12.8 (F) Case II
d) formwork
Add 15 per cent of cost of material, labour and machinery 15.00 878.25
(a+b+c) for Formwork
Add 4 per cent of cost of material, Labour and machinery 4.00 234.20
excluding formwork to cater for extra lift
e) Overhead charges @ 0.25 on (a+b+c+d) 1741.86
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 870.93
Rate per cum (a+b+c+d+e+f) 9580.24
say 9580.00
9580.00
13.5 E RCC Grade M20
(p) Height upto 5m
Same as Item 12.8 (C) upto 5 m height, except for formwork
which shall be 10 per cent instead of 4 per cent of cost of
material, labour and machinery.
Case I Using concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) 5510.00 Item 12.8 (C)
of Item 12.8 (C) Case I
d) formwork
Add 10 per cent of cost of material, labour and machinery 10.00 551.00
(a+b+c) for Formwork
e) Overhead charges @ 0.25 on (a+b+c+d) 1515.25
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 757.63
Rate per cum (a+b+c+d+e+f) 8333.88
say 8334.00
8334.00
13.5 E (p) Case II With Batching Plant, Transit Mixer and Concrete Pump

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) 5380.00 Item 12.8 (C)
of Item 12.8 (C) Case II
d) formwork
Add 10 per cent of cost of material, labour and machinery 10.00 538.00
(a+b+c) for Formwork
e) Overhead charges @ 0.25 on (a+b+c+d) 1479.50
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 739.75
Rate per cum (a+b+c+d+e+f) 8137.25
say 8137.00
8137.00
13.5 E (q) Height 5m to 10m
For height, upto 10m, add 2 per cent of cost as above excluding
formwork. For cost of formwork add 12 per cent of cost of
material, labour and machinery instead of 4 per cent .
Case I Using concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) 5510.00 Item 12.8 (C)
of Item 12.8 (C) Case I
d) formwork
Add 12 per cent of cost of material, labour and machinery 12.00 661.20
(a+b+c) for Formwork
Add 2 per cent of cost of material, Labour and machinery 2.00 110.20
excluding formwork to cater for extra lift
e) Overhead charges @ 0.25 on (a+b+c+d) 1570.35
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 785.18
Rate per cum (a+b+c+d+e+f) 8636.93
say 8637.00
8637.00
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
13.5 E (q) Case II With Batching Plant, Transit Mixer and Concrete Pump

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) 5380.00 Item 12.8 (C)
of Item 12.8 (C) Case II
d) formwork
Add 12 per cent of cost of material, labour and machinery 12.00 645.60
(a+b+c) for Formwork
Add 2 per cent of cost of material, Labour and machinery 2.00 107.60
excluding formwork to cater for extra lift
e) Overhead charges @ 0.25 on (a+b+c+d) 1533.30
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 766.65
Rate per cum (a+b+c+d+e+f) 8433.15
say 8433.00
8433.00
13.5 E (r) Height above 10m
Same as Item 12.8 (C) with the following changes: (i) Add 4 per
cent of cost of material, labour and machinery excluding form
work to cater for extra lift. (ii) The provision of form work shall be
15 per cent instead of 4 per cent of cost of material, labour and
machinery.
Case I Using concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) 5510.00 Item 12.8 (C)
of Item 12.8 (C) Case I
d) formwork
Add 15 per cent of cost of material, labour and machinery 15.00 826.50
(a+b+c) for Formwork
Add 4 per cent of cost of material, Labour and machinery 4.00 220.40
excluding formwork to cater for extra lift
e) Overhead charges @ 0.25 on (a+b+c+d) 1639.23
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 819.61
Rate per cum (a+b+c+d+e+f) 9015.74
say 9016.00
9016.00
13.5 E (r) Case II With Batching Plant, Transit Mixer and Concrete Pump

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) 5380.00 Item 12.8 (C)
of Item 12.8 (C) Case II
d) formwork
Add 15 per cent of cost of material, labour and machinery 15.00 807.00
(a+b+c) for Formwork
Add 4 per cent of cost of material, Labour and machinery 4.00 215.20
excluding formwork to cater for extra lift
e) Overhead charges @ 0.25 on (a+b+c+d) 1600.55
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 800.28
Rate per cum (a+b+c+d+e+f) 8803.03
say 8803.00
8803.00
13.5 F RCC Grade M25
(p) Height upto 5m
Same as Item 12.8 (E) upto 5m height, excluding formwork. For
cost of formwork, add 10 per cent of cost of material, labour and
machinery instead of 3.75 per cent .
Case I Using concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) 6011.00 Item 12.8 (E)
of Item 12.8 (E) Case I
d) formwork
Add 10 per cent of cost of material, labour and machinery 10.00 601.10
(a+b+c) for Formwork
e) Overhead charges @ 0.25 on (a+b+c+d) 1653.03
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 826.51
Rate per cum (a+b+c+d+e+f) 9091.64
say 9092.00
9092.00
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
13.5 F (p) Case II With Batching Plant, Transit Mixer and Concrete Pump

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) 6224.00 Item 12.8 (E)
of Item 12.8 (E) Case II
DIR used item
d) formwork
Add 10 per cent of cost of material, labour and machinery 10.00 622.40
(a+b+c) for Formwork
e) Overhead charges @ 0.25 on (a+b+c+d) 1711.60
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 855.80
Rate per cum (a+b+c+d+e+f) 9413.80
say 9414.00
9414.00
13.5 F (q) Height 5m to 10m
For height, upto 10m, add 1.8 per cent of cost as above excluding
formwork. For cost of formwork add 11.8 per cent of cost of
material, labour and machinery
13.5 F (q) Case II With Batching Plant, Transit Mixer and Concrete Pump

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) 6224.00 Item 12.8 (E)
of Item 12.8 (E) Case II
DIR used item
d) formwork
Add 11.8 per cent of cost of material, labour and machinery 11.80 734.43
(a+b+c) for Formwork
Add 1.8 per cent of cost of material, Labour and machinery 1.80 112.03
excluding formwork to cater for extra lift
e) Overhead charges @ 0.25 on (a+b+c+d) 1767.62
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 883.81
Rate per cum (a+b+c+d+e+f) 9721.89
say 9722.00
9722.00
13.5 F (r) Height above 10m
For height, above 10m, add 4 per cent of cost as above excluding
formwork. For cost of formwork add 15 per cent of cost of
material, labour and machinery
Case I Using concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) 6011.00 Item 12.8 (E)
of Item 12.8 (E) Case I
d) formwork
Add 15 per cent of cost of material, labour and machinery 15.00 901.65
(a+b+c) for Formwork
Add 4 per cent of cost of material, Labour and machinery 4.00 240.44
excluding formwork to cater for extra lift
e) Overhead charges @ 0.25 on (a+b+c+d) 1788.27
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 894.14
Rate per cum (a+b+c+d+e+f) 9835.50
say 9835.00
9835.00
13.5 F (r) Case II With Batching Plant, Transit Mixer and Concrete Pump
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) 6224.00 Item 12.8 (E)
of Item 12.8 (E) Case II
DIR used item
d) formwork
Add 15 per cent of cost of material, labour and machinery 15.00 933.60
(a+b+c) for Formwork
Add 4 per cent of cost of material, Labour and machinery 4.00 248.96
excluding formwork to cater for extra lift
e) Overhead charges @ 0.25 on (a+b+c+d) 1851.64
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 925.82
Rate per cum (a+b+c+d+e+f) 10184.02
say 10184.00
10184.00
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
13.5 G RCC Grade M30
(p) Height upto 5m
Same as Item 12.8 (G) upto 5m height, excluding formwork. For
cost of formwork, add 10 per cent of cost of material, labour and
machinery instead of 3.5 per cent .
13.5 G (p) Case II With Batching Plant, Transit Mixer and Concrete Pump

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) 6255.00 Item 12.8 (G)
of Item 12.8 (G) Case II
d) formwork
Add 10 per cent of cost of material, labour and machinery 10.00 625.50
(a+b+c) for Formwork
e) Overhead charges @ 0.25 on (a+b+c+d) 1720.13
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 860.06
Rate per cum (a+b+c+d+e+f) 9460.69
say 9461.00
9461.00
13.5 G (q) Height 5m to 10m
For height, upto 10m, add 1.6 per cent of cost as above excluding
formwork. For cost of formwork add 11.5 per cent of cost of
material, labour and machinery
13.5 G (q) Case II With Batching Plant, Transit Mixer and Concrete Pump

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) 6255.00 Item 12.8 (G)
of Item 12.8 (G) Case II
d) formwork
Add 11.5 per cent of cost of material, labour and machinery 11.50 719.33
(a+b+c) for Formwork
Add 1.6 per cent of cost of material, Labour and machinery 1.60 100.08
excluding formwork to cater for extra lift
e) Overhead charges @ 0.25 on (a+b+c+d) 1768.60
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 884.30
Rate per cum (a+b+c+d+e+f) 9727.31
say 9727.00
9727.00
13.5 G (r) Height above 10m
For height, above 10m, add 3.5 per cent of cost as above
excluding formwork. For cost of formwork add 14 per cent of cost
of material, labour and machinery
13.5 G (r) Case II With Batching Plant, Transit Mixer and Concrete Pump

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) 6255.00 Item 12.8 (G)
of Item 12.8 (G) Case II
d) formwork
Add 14 per cent of cost of material, labour and machinery 14.00 875.70
(a+b+c) for Formwork
Add 3.5 per cent of cost of material, Labour and machinery 3.50 218.93
excluding formwork to cater for extra lift
e) Overhead charges @ 0.25 on (a+b+c+d) 1837.41
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 918.70
Rate per cum (a+b+c+d+e+f) 10105.73
say 10106.00
10106.00
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
13.5 H RCC Grade M35
(p) Height upto 5m
Same as Item 12.8 (H) upto 5m height, excluding formwork. For
cost of formwork, add 10 per cent of cost of material, labour and
machinery instead of 3 per cent .
13.5 H (p) Case II With Batching Plant, Transit Mixer and Concrete Pump

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) 6674.00 Item 12.8 (H)
of Item 12.8 (H) Case II
DIR used item
d) formwork
Add 10 per cent of cost of material, labour and machinery 10.00 667.40
(a+b+c) for Formwork
e) Overhead charges @ 0.25 on (a+b+c+d) 1835.35
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 917.68
Rate per cum (a+b+c+d+e+f) 10094.43
say 10094.00
10094.00
13.5 H (q) Height 5m to 10m
For height, upto 10m, add 1.4 per cent of cost as above excluding
formwork. For cost of formwork add 11 per cent of cost of
material, labour and machinery .
13.5 H (q) Case II With Batching Plant, Transit Mixer and Concrete Pump

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) 6674.00 Item 12.8 (H)
of Item 12.8 (H) Case II
d) formwork
Add 11 per cent of cost of material, labour and machinery 11.00 734.14
(a+b+c) for Formwork
Add 1.4 per cent of cost of material, Labour and machinery 1.40 93.44
excluding formwork to cater for extra lift
e) Overhead charges @ 0.25 on (a+b+c+d) 1875.39
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 937.70
Rate per cum (a+b+c+d+e+f) 10314.67
say 10315.00
10315.00
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
13.5 H (r) Height above 10m
For height, above 10m, add 3 per cent of cost as above excluding
formwork. For cost of formwork add 13 per cent of cost of
material, labour and machinery
13.5 H (r) Case II With Batching Plant, Transit Mixer and Concrete Pump

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) 6674.00 Item 12.8 (H)
of Item 12.8 (H) Case II
d) formwork
Add 13 per cent of cost of material, labour and machinery 13.00 867.62
(a+b+c) for Formwork
Add 3 per cent of cost of material, Labour and machinery 3.00 200.22
excluding formwork to cater for extra lift
e) Overhead charges @ 0.25 on (a+b+c+d) 1935.46
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 967.73
Rate per cum (a+b+c+d+e+f) 10645.03
say 10645.00
10645.00
Note The basic components of this analysis are the same as those of
items 13.8 (A to H). The only changes are as under:
a) Ramps/Stairs: Extra expenditure on structures which are
more than 5 m high @ 2 per cent of cost for height upto 10 m and
4 per cent for heights above 10 m will be involved for approaching
the work spot by providing higher ramp/stair case for use by the
working parties.
b) The above mentioned percentages have been suitably
modified for different categories as cost for various categories
varies, whereas effort for access for same height will be similar. As
the cost of richer concrete is comparatively more, the percentage
to be added has been reduced to maintain the same cost for extra
efforts.
13.6 Section Supplying, fitting and placing HYSD bar reinforcement in sub-
1600 & structure complete as per drawing and Technical
2200 Specifications
Output: MT
Taking output = 1 MT
a) Material
HYSD bars including 5 per cent overlaps and wastage tonne 1.05 44000.00 46200.00 M-087
Binding wire kg 6.00 92.63 555.75 M-071
b) Labour for cutting, bending, shifting to site, tying and
placing in position
Mate day 0.34 329.34 111.97 L-12
Blacksmith day 2.00 352.86 705.72 L-02
Mazdoor day 6.50 152.91 993.89 L-13
c) Overhead charges @ 0.25 on (a+b) 12141.83
d) Contractor's profit @ 0.1 on (a+b+c) 6070.92
Rate for per MT (a+b+c+d) 66780.09
say 66780.00
66780.00
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
13.8 2706 & Providing weep holes in Brick masonry/Plain/ Reinforced
2200 concrete abutment, wing wall/ return wall with 100 mm dia AC
pipe, extending through the full width of the structure with
slope of 1V :20H towards drawing foce. Complete as per
drawing and Technical Specifications

Unit = Nos.
Taking output = 30 Nos.
a) Material
AC pipe 100 mm dia. (including wastage @ 5 per cent ) metre 31.50 1210.31 38124.76 M-056
Average length of weep hole is taken as one metre for the purpose
of estimating.
MS clamp each. 30.00 30.88 926.26 M-129
collar for AC pipe (average) taking 10% of above pipe rate each. 10.00 121.03 1210.31 M-056/10

Cement mortar 1:3 (Rate as in Item 12.6) cum 0.05 5945.00 297.25 Item 12.6 (A)
b) Labour
Mate day 0.03 329.34 9.88 L-12
Mason day 0.50 352.86 176.43 L-11
Mazdoor day 0.25 152.91 38.23 L-13
c) Overhead charges @ 0.25 on (a+b) 10195.78
d) Contractor's profit @ 0.1 on (a+b+c) 5097.89
Cost for 30 m = a+b+c+d 56076.78
Rate per No. (a+b+c+d)/30 1869.23
say 1869.00
1869.00
Note 1. In case of stone masonry, the size of the weep hole shall be
150 mm x 80 mm or circular with 150 mm diameter.
2. For structure in stone masonry, the weep holes shall be
deemed to be included in the item of stone masonry work and
shall not be paid separately.
13.9 710.1.4. Back filling behind abutment, wing wall and return wall
of complete as per drawing and Technical Specification
IRC:78
& 2200
Unit = cum
Taking output = 10 cum
A Granular material
a) Labour
Mate day 0.28 329.34 92.21 L-12
Mazdoor day 7.00 152.91 1070.34 L-13
b) Material
Granular material cum 12.00 978.88 11746.57 M-009
c) Machinery
Plate compactor/power rammer hour 2.50 256.41 641.03 P&M-086
Water Tanker hour 0.05 517.53 25.88 P&M-060
d) Overhead charges @ 0.25 on (a+b+c) 3394.01
e) Contractor's profit @ 0.1 on (a+b+c+d) 1697.00
Cost for 10 cum of granular backfill = a+b+c+d+e 18667.04
Rate per cum = (a+b+c+d+e)/10 1866.70
say 1867.00
1867.00
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
13.9 B Sandy material
a) Labour
Mate day 0.28 329.34 92.21 L-12
Mazdoor for filling, watering, ramming etc. day 7.00 152.91 1070.34 L-13
b) Material
Sand cum 12.00 1293.82 15525.84 M-006
c) Machinery
Plate compactor/power rammer hour 2.50 256.41 641.03 P&M-086
Water Tanker hour 0.06 517.53 31.05 P&M-060
d) Overhead charges @ 0.25 on (a+b+c) 4340.12
e) Contractor's profit @ 0.1 on (a+b+c+d) 2170.06
Cost for 10 cum of sandy backfill = a+b+c+d+e 23870.66
Rate per cum = (a+b+c+d+e)/10 2387.07
say 2387.00
2387.00
13.10 710.1.4. Providing and laying of Filter media with granular
of materials/stone crushed aggregates satisfying the
IRC:78 requirements laid down in clause 2504.2.2. of MoRTH
and specifications to a thickness of not less than 600 mm with
2200 smaller size towards the soil and bigger size towards the wall
and provided over the entire surface behind abutment, wing
wall and return wall to the full height compacted to a firm
condition complete as per drawing and Technical
Specification.
Unit = cum
Taking output = 10 cum.
a) Labour
Mate day 0.32 329.34 105.39 L-12
Mazdoor for filling, watering, ramming etc. day 7.00 152.91 1070.34 L-13
Mazdoor (Skilled) day 1.00 244.65 244.65 L-15
b) Material
Filter media of stone aggregate conforming to clause cum 12.00 1190.60 14287.16 M-012
2504.2.2. of MoRTH specifications.
c) Machinery
Water Tanker of 6 KL capacity hour 0.06 517.53 31.05 P&M-060
d) Overhead charges @ 0.25 on (a+b+c) 3934.65
e) Contractor's profit @ 0.1 on (a+b+c+d) 1967.32
cost for 10 cum of Fiter Media = a+b+c+d+e 21640.56
Rate per cum = (a+b+c+d+e)/10 2164.06
say 2164.00
2164.00
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
13.11 2000, Supplying, fitting and fixing in position true to line and level
1000 & cast steel rocker bearing conforming to IRC: 83(Pt.-1) section
2200 IX and clause 2003 of MoRTH specifications complete
including all accessories as per drawing and Technical
Specifications.
Unit: one tonne capacity
Considering a 250 tonne capacity bearing for this analysis
a) Labour
Mate day 0.06 329.34 19.76 L-12
Mazdoor (Skilled) day 0.50 244.65 122.32 L-15
Mazdoor day 1.00 152.91 152.91 L-13
b) Material
Cast steel rocker bearing assembly of 250 tonne design load each. 1.00 209951.70 209951.70 M-064
capacity duly painted complete with all its components as per
drawing and specifications
Add 1 per cent of cost of bearing assembly for foundation 2099.52
anchorage bolts, lifting arrangements, grease and other
consumables.
c) Overhead charges @ 0.25 on (a+b) 53086.55
d) Contractor's profit @ 0.1 on (a+b+c) 26543.28
cost for 250 tonnes capacity bearing = a+b+c+d 291976.04
Rate per tonne capacity = (a+b+c+d)/250 1167.90
say 1168.00
1168.00
13.12 2000 , Supplying, fitting and fixing in position true to line and level
1000 & forged steel roller bearing conforming to IRC: 83(Pt.-1)
2200 section IX and clause 2003 of MoRTH specifications complete
including all accessories as per drawing and Technical
Specifications.
Unit: one tonne capacity
Considering a 250 tonne capacity bearing for this analysis
a) Labour
Mate day 0.06 329.34 19.76 L-12
Mazdoor day 1.00 152.91 152.91 L-13
Mazdoor (Skilled) day 0.50 244.65 122.32 L-15
b) Material
Forged steel roller bearing of 250 tonne design load capacity each. 1.00 262439.63 262439.63 M-066
duly painted complete with all its components as per drawing
and specifications
Add 1 per cent of cost of bearing assembly for foundation 2624.40
anchorage bolts, lifting arrangements, grease and other
consumables.
c) Overhead charges @ 0.25 on (a+b) 66339.75
d) Contractor's profit @ 0.1 on (a+b+c) 33169.88
cost for 250 tonnes capacity bearing = a+b+c+d 364868.64
Rate per tonne capacity = (a+b+c+d)/250 1459.47
say 1459.00
1459.00
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
13.14 2000 & Supplying, fitting and fixing in position true to line and level
2200 elastomeric bearing conforming to IRC: 83 (Part-II) section IX
and clause 2005 of MoRTH specifications complete including
all accessories as per drawing and Technical Specifications.

Unit: one cubic centimetre


Considering an elastomeric bearing of size 500 x 400 x 96 mm for
this analysis.
Overall volume - 19200 cu.cm
Volume of 6 nos. 488 x 388 x 4 mm size reinforcing steel plates =
4545 cu.cm.
Hence volume of elastometer = 14655 cu.cm.
a) Labour
Mate day 0.06 329.34 19.76 L-12
Mazdoor day 1.00 152.91 152.91 L-13
Mazdoor (Skilled) day 0.50 244.65 122.32 L-15
b) Material
Elastomeric bearing assembly consisting of 7 layers of NOS 1.00 16937.28 16937.28 M-065
elastomer bonded to 6 nos. internal reinforcing steel
laminates by the process of vulcanisation, complete with all
components as per drawing and Technical Specifications.
Add 1 per cent of cost of bearing assembly for foundation 169.37
anchorage bolts and consumables.
c) Overhead charges @ 0.25 on (a+b) 4350.41
d) Contractor's profit @ 0.1 on (a+b+c) 2175.21
cost for 19200cc of elastomeric bearing = a+b+c+d 23927.26
Rate per cc of elastomeric bearing = (a+b+c+d)/19200 1.25
say 1.25
1.25

Non- Back filling behind abutment, wing wall and return wall
Sch complete as per drawing and Technical Specification
Unit = cum
Taking output = 10 cum
A Granular material
a) Labour
Mate day 0.28 329.34 92.21 L-12
Mazdoor day 7.00 152.91 1070.34 L-13
b) Material
Granular material cum 12.00 858.63 10303.51 M-009
c) Machinery
Plate compactor/power rammer hour 2.50 256.41 641.03 P&M-086
Water Tanker hour 0.05 517.53 25.88 P&M-060
d) Overhead charges @ 0.25 on (a+b+c) 3033.24
e) Contractor's profit @ 0.1 on (a+b+c+d) 1516.62
Cost for 10 cum of granular backfill = a+b+c+d+e 16682.84
Rate per cum = (a+b+c+d+e)/10 1668.28
say 1668.00
1668.00
CHAPTER-14
SUPER-STRUCTURE
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
14.1 1500 Furnishing and Placing Reinforced/ Prestressed cement
&1600 concrete in super-structure as per drawing and Technical
1700 Specification
A RCC Grade M20
Case I Using Concrete Mixer
Unit = 1 cum
Taking output = 15 cum
a) Material
Cement tonne 5.12 8939.12 45768.29 M-086
Coarse sand cum 6.75 1176.20 7939.35 M-005
20 mm Aggregate cum 8.10 1529.06 12385.39 M-053
10 mm Aggregate cum 5.40 1529.06 8256.92 M-051
b) Labour
Mate day 0.86 329.34 283.23 L-12
Mason day 1.50 352.86 529.29 L-11
Mazdoor day 20.00 152.91 3058.12 L-13
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 237.59 1425.55 P&M-009
Generator 33 KVA hour 6.00 365.80 2194.79 P&M-079
Basic Cost of Labour, Material & Machinery (a+b+c) for 15 81841.00
cum
For formwork and staging add the following:
14.1A (i) For solid slab super-structure, 20-30 per cent of (a+b+c)
Case I
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) for 15 81841.00
cum
d) Formwork and staging 20 per cent of (a+b+c) 20.00 16368.20
e) Overhead charges @ 0.25 on (a+b+c+d) 24552.30
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 12276.15
Cost for 15 cum = a+b+c+d+e+f 135037.65
Rate per cum = (a+b+c+d+e+f)/15 9002.51
say 9003.00
9003.00
14.1A (q) Height 5m to 10m
Case I (i)
Basic Cost of Labour, Material & Machinery (a+b+c) for 15 81841.00
cum
d) Formwork and staging 25 per cent of (a+b+c) 25.00 20460.25
e) Overhead charges @ 0.25 on (a+b+c+d) 25575.31
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 12787.66
Cost for 15 cum = a+b+c+d+e+f 140664.22
Rate per cum = (a+b+c+d+e+f)/15 9377.61
say 9378.00
9378.00
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
14.1A (r) Height above 10m
Case I (i)
Basic Cost of Labour, Material & Machinery (a+b+c) for 15 81841.00
cum
d) Formwork and staging 30 per cent of (a+b+c) 30.00 24552.30
e) Overhead charges @ 0.25 on (a+b+c+d) 26598.33
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 13299.16
Cost for 15 cum = a+b+c+d+e+f 146290.79
Rate per cum = (a+b+c+d+e+f)/15 9752.72
say 9753.00
9753.00
14.1A (ii) For T-beam & slab, 25-35 per cent of (a+b+c)
Case I
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) for 15 81841.00
cum
d) Formwork and staging 25 per cent of (a+b+c) 25.00 20460.25
e) Overhead charges @ 0.25 on (a+b+c+d) 25575.31
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 12787.66
Cost for 15 cum = a+b+c+d+e+f 140664.22
Rate per cum = (a+b+c+d+e+f)/15 9377.61
say 9378.00
9378.00
14.1A (q) Height 5m to 10m
Case I (ii)
Basic Cost of Labour, Material & Machinery (a+b+c) for 15 81841.00
cum
d) Formwork and staging 30 per cent of (a+b+c) 30.00 24552.30
e) Overhead charges @ 0.25 on (a+b+c+d) 26598.33
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 13299.16
Cost for 15 cum = a+b+c+d+e+f 146290.79
Rate per cum = (a+b+c+d+e+f)/15 9752.72
say 9753.00
9753.00
14.1A (r) Height above 10m
Case I (ii)
Basic Cost of Labour, Material & Machinery (a+b+c) for 15 81841.00
cum
d) Formwork and staging 35 per cent of (a+b+c) 35.00 28644.35
e) Overhead charges @ 0.25 on (a+b+c+d) 27621.34
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 13810.67
Cost for 15 cum = a+b+c+d+e+f 151917.36
Rate per cum = (a+b+c+d+e+f)/15 10127.82
say 10128.00
10128.00
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
14.1A Case II Using Batching Plant, Transit Mixer and Concrete Pump

Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 40.92 8939.12 365788.79 M-086
Coarse sand cum 54.00 1176.20 63514.80 M-004
20 mm Aggregate cum 64.80 1529.06 99083.09 M-053
10 mm Aggregate cum 43.20 1529.06 66055.39 M-051
b) Labour
Mate day 0.84 329.34 276.64 L-12
Mason day 3.00 352.86 1058.58 L-11
Mazdoor day 18.00 152.91 2752.31 L-13
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 2301.82 13810.94 P&M-002
Generator 100 KVA hour 6.00 730.42 4382.52 P&M-080
Loader hour 6.00 803.34 4820.07 P&M-017
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity lead upto1 Km hour 15.00 973.89 14608.40 P&M-049
Lead beyond 1 Km, L - lead in Kilometer tonne.k 300L 47.05 42343.20 Lead =3 km
m & P&M-050
Concrete Pump hour 6.00 275.23 1651.38 P&M-007
Basic Cost of Labour, Material & Machinery (a+b+c) for 680147.00
120 cum
For formwork and staging add the following:
14.1A (i) For solid slab super-structure, 20-30 per cent of (a+b+c)
Case II
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) for 120 680147.00
cum
d) Formwork and staging 20 per cent of (a+b+c) 20.00 136029.40
e) Overhead charges @ 0.25 on (a+b+c+d) 204044.10
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 102022.05
Cost for 120 cum = a+b+c+d+e+f 1122242.55
Rate per cum = (a+b+c+d+e+f)/120 9352.02
say 9352.00
9352.00
14.1A (q) Height 5m to 10m
Case II (i)
Basic Cost of Labour, Material & Machinery (a+b+c) for 120 680147.00
cum
d) Formwork and staging 25 per cent of (a+b+c) 25.00 170036.75
e) Overhead charges @ 0.25 on (a+b+c+d) 212545.94
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 106272.97
Cost for 120 cum = a+b+c+d+e+f 1169002.66
Rate per cum = (a+b+c+d+e+f)/120 9741.69
say 9742.00
9742.00
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
14.1A (r) Height above 10m
Case II (i)
Basic Cost of Labour, Material & Machinery (a+b+c) for 120 680147.00
cum
d) Formwork and staging 30 per cent of (a+b+c) 30.00 204044.10
e) Overhead charges @ 0.25 on (a+b+c+d) 221047.78
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 110523.89
Cost for 120 cum = a+b+c+d+e+f 1215762.76
Rate per cum = (a+b+c+d+e+f)/120 10131.36
say 10131.00
10131.00
14.1A (ii) For T-beam & slab, 25-35 per cent of (a+b+c)
Case II
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) for 120 680147.00
cum
d) Formwork and staging 25 per cent of (a+b+c) 25.00 170036.75
e) Overhead charges @ 0.25 on (a+b+c+d) 212545.94
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 106272.97
Cost for 120 cum = a+b+c+d+e+f 1169002.66
Rate per cum = (a+b+c+d+e+f)/120 9741.69
say 9742.00
9742.00
14.1A (q) Height 5m to 10m
Case II
(ii) Basic Cost of Labour, Material & Machinery (a+b+c) for 120 680147.00
cum
d) Formwork and staging 30 per cent of (a+b+c) 30.00 204044.10
e) Overhead charges @ 0.25 on (a+b+c+d) 221047.78
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 110523.89
Cost for 120 cum = a+b+c+d+e+f 1215762.76
Rate per cum = (a+b+c+d+e+f)/120 10131.36
say 10131.00
10131.00
14.1A (r) Height above 10m
Case II
(ii) Basic Cost of Labour, Material & Machinery (a+b+c) for 120 680147.00
cum
d) Formwork and staging 35 per cent of (a+b+c) 35.00 238051.45
e) Overhead charges @ 0.25 on (a+b+c+d) 229549.61
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 114774.81
Cost for 120 cum = a+b+c+d+e+f 1262522.87
Rate per cum = (a+b+c+d+e+f)/120 10521.02
say 10521.00
10521.00
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
14.1 B RCC Grade M25
14.1B Case II Using Batching Plant, Transit Mixer and Concrete Pump

Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 47.95 8939.12 428630.80 M-086
Coarse sand cum 54.20 1176.20 63750.04 M-004
20 mm Aggregate cum 64.80 1529.06 99083.09 M-053
10 mm Aggregate cum 43.20 1529.06 66055.39 M-051
b) Labour
Mate day 0.84 329.34 276.64 L-12
Mason day 3.00 352.86 1058.58 L-11
Mazdoor day 18.00 152.91 2752.31 L-13
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 2301.82 13810.94 P&M-002
Generator 100 KVA hour 6.00 730.42 4382.52 P&M-080
Loader hour 6.00 803.34 4820.07 P&M-017
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity lead upto1 Km hour 15.00 973.89 14608.40 P&M-049
Lead beyond 1 Km, L - lead in Kilometer tonne.k 300L 47.05 42343.20 Lead =3 km
m & P&M-050
Concrete Pump hour 6.00 275.23 1651.38 P&M-007
Basic Cost of Labour, Material & Machinery (a+b+c) for 743224.00
120 cum
For formwork and staging add the following:
14.1B (i) For solid slab super-structure, 20-30 per cent of (a+b+c)
Case II
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) for 120 743224.00
cum
d) Formwork and staging 20 per cent of (a+b+c) 20.00 148644.80
e) Overhead charges @ 0.25 on (a+b+c+d) 222967.20
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 111483.60
Cost for 120 cum = a+b+c+d+e+f 1226319.60
Rate per cum = (a+b+c+d+e+f)/120 10219.33
say 10219.00
10219.00
14.1B (q) Height 5m to 10m
Case II (i)
Basic Cost of Labour, Material & Machinery (a+b+c) for 120 743224.00
cum
d) Formwork and staging 25 per cent of (a+b+c) 25.00 185806.00
e) Overhead charges @ 0.25 on (a+b+c+d) 232257.50
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 116128.75
Cost for 120 cum = a+b+c+d+e+f 1277416.25
Rate per cum = (a+b+c+d+e+f)/120 10645.14
say 10645.00
10645.00
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
14.1B (ii) For T-beam & slab, 25-35 per cent of (a+b+c)
Case II
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) for 120 743224.00
cum
d) Formwork and staging 25 per cent of (a+b+c) 25.00 185806.00
e) Overhead charges @ 0.25 on (a+b+c+d) 232257.50
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 116128.75
Cost for 120 cum = a+b+c+d+e+f 1277416.25
Rate per cum = (a+b+c+d+e+f)/120 10645.14
say 10645.00
10645.00
14.1B (q) Height 5m to 10m
Case II
(ii) Basic Cost of Labour, Material & Machinery (a+b+c) for 120 743224.00
cum
d) Formwork and staging 30 per cent of (a+b+c) 30.00 222967.20
e) Overhead charges @ 0.25 on (a+b+c+d) 241547.80
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 120773.90
Cost for 120 cum = a+b+c+d+e+f 1328512.90
Rate per cum = (a+b+c+d+e+f)/120 11070.94
say 11071.00
11071.00
14.1B (r) Height above 10m
Case II
(ii) Basic Cost of Labour, Material & Machinery (a+b+c) for 120 743224.00
cum
d) Formwork and staging 35 per cent of (a+b+c) 35.00 260128.40
e) Overhead charges @ 0.25 on (a+b+c+d) 250838.10
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 125419.05
Cost for 120 cum = a+b+c+d+e+f 1379609.55
Rate per cum = (a+b+c+d+e+f)/120 11496.75
say 11497.00
11497.00
14.1 C RCC Grade M 30
Case I Using Concrete Mixer
Unit = 1 cum
Taking output = 15 cum
a) Material
Cement tonne 6.10 8939.12 54528.63 M-086
Coarse sand cum 6.75 1176.20 7939.35 M-005
20 mm Aggregate cum 8.10 1529.06 12385.39 M-053
10 mm Aggregate cum 5.40 1529.06 8256.92 M-051
b) Labour
Mate day 0.90 329.34 296.40 L-12
Mason day 1.50 352.86 529.29 L-11
Mazdoor day 21.00 152.91 3211.03 L-13
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 237.59 1425.55 P&M-009
Generator 33 KVA hour 6.00 365.80 2194.79 P&M-079
Basic Cost of Labour, Material & Machinery (a+b+c) for 15 90768.00
cum
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
For formwork and staging add the following:
14.1C (i) For solid slab super-structure, 20-30 per cent of (a+b+c)
Case I
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) for 15 90768.00
cum
d) Formwork and staging 20 per cent of (a+b+c) 20.00 18153.60
e) Overhead charges @ 0.25 on (a+b+c+d) 27230.40
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 13615.20
Cost for 15 cum = a+b+c+d+e+f 149767.20
Rate per cum = (a+b+c+d+e+f)/15 9984.48
say 9984.00
9984.00
14.1C (q) Height 5m to 10m
Case I (i)
Basic Cost of Labour, Material & Machinery (a+b+c) for 15 90768.00
cum
d) Formwork and staging 25 per cent of (a+b+c) 25.00 22692.00
e) Overhead charges @ 0.25 on (a+b+c+d) 28365.00
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 14182.50
Cost for 15 cum = a+b+c+d+e+f 156007.50
Rate per cum = (a+b+c+d+e+f)/15 10400.50
say 10401.00
10401.00
14.1C (r) Height above 10m
Case I (i)
Basic Cost of Labour, Material & Machinery (a+b+c) for 15 90768.00
cum
d) Formwork and staging 30 per cent of (a+b+c) 30.00 27230.40
e) Overhead charges @ 0.25 on (a+b+c+d) 29499.60
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 14749.80
Cost for 15 cum = a+b+c+d+e+f 162247.80
Rate per cum = (a+b+c+d+e+f)/15 10816.52
say 10817.00
10817.00
14.1C (ii) For T-beam & slab, 25-35 per cent of (a+b+c)
Case I
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) for 15 90768.00
cum
d) Formwork and staging 25 per cent of (a+b+c) 25.00 22692.00
e) Overhead charges @ 0.25 on (a+b+c+d) 28365.00
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 14182.50
Cost for 15 cum = a+b+c+d+e+f 156007.50
Rate per cum = (a+b+c+d+e+f)/15 10400.50
say 10401.00
10401.00
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
14.1C (q) Height 5m to 10m
Case I (ii)
Basic Cost of Labour, Material & Machinery (a+b+c) for 15 90768.00
cum
d) Formwork and staging 30 per cent of (a+b+c) 30.00 27230.40
e) Overhead charges @ 0.25 on (a+b+c+d) 29499.60
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 14749.80
Cost for 15 cum = a+b+c+d+e+f 162247.80
Rate per cum = (a+b+c+d+e+f)/15 10816.52
say 10817.00
10817.00
14.1C (r) Height above 10m
Case I (ii)
Basic Cost of Labour, Material & Machinery (a+b+c) for 15 90768.00
cum
d) Formwork and staging 35 per cent of (a+b+c) 35.00 31768.80
e) Overhead charges @ 0.25 on (a+b+c+d) 30634.20
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 15317.10
Cost for 15 cum = a+b+c+d+e+f 168488.10
Rate per cum = (a+b+c+d+e+f)/15 11232.54
say 11233.00
11233.00
14.1C Case II Using Batching Plant, Transit Mixer and Concrete Pump.

Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 48.79 8939.12 436139.66 M-086
Coarse sand cum 54.60 1176.20 64220.52 M-004
20 mm Aggregate cum 64.80 1529.06 99083.09 M-053
10 mm Aggregate cum 43.20 1529.06 66055.39 M-051
b) Labour
Mate day 0.88 329.34 289.82 L-12
Mason day 3.00 352.86 1058.58 L-11
Mazdoor day 19.00 152.91 2905.21 L-13
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 2301.82 13810.94 P&M-002
Generator 100 KVA hour 6.00 730.42 4382.52 P&M-080
Loader hour 6.00 803.34 4820.07 P&M-017
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity lead upto1 Km hour 15.00 973.89 14608.40 P&M-049
Lead beyond 1 Km, L - lead in Kilometer tonne.k 300L 47.05 42343.20 Lead =3 km
m & P&M-050
Concrete Pump hour 6.00 275.23 1651.38 P&M-007
Basic Cost of Labour, Material & Machinery (a+b+c) for 751369.00
120 cum
For formwork and staging add the following:
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
14.1C (i) For solid slab super-structure, 20-30 per cent of (a+b+c)
Case II
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) for 120 751369.00
cum
d) Formwork and staging 20 per cent of (a+b+c) 20.00 150273.80
e) Overhead charges @ 0.25 on (a+b+c+d) 225410.70
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 112705.35
Cost for 120 cum = a+b+c+d+e+f 1239758.85
Rate per cum = (a+b+c+d+e+f)/120 10331.32
say 10331.00
10331.00
14.1C (q) Height 5m to 10m
Case II (i)
Basic Cost of Labour, Material & Machinery (a+b+c) for 120 751369.00
cum
d) Formwork and staging 25 per cent of (a+b+c) 25.00 187842.25
e) Overhead charges @ 0.25 on (a+b+c+d) 234802.81
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 117401.41
Cost for 120 cum = a+b+c+d+e+f 1291415.47
Rate per cum = (a+b+c+d+e+f)/120 10761.80
say 10762.00
10762.00
14.1C (r) Height above 10m
Case II (i)
Basic Cost of Labour, Material & Machinery (a+b+c) for 120 751369.00
cum
d) Formwork and staging 30 per cent of (a+b+c) 30.00 225410.70
e) Overhead charges @ 0.25 on (a+b+c+d) 244194.93
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 122097.46
Cost for 120 cum = a+b+c+d+e+f 1343072.09
Rate per cum = (a+b+c+d+e+f)/120 11192.27
say 11192.00
11192.00
14.1C (ii) For T-beam & slab, 25-35 per cent of (a+b+c)
Case II
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) for 120 751369.00
cum
d) Formwork and staging 25 per cent of (a+b+c) 25.00 187842.25
e) Overhead charges @ 0.25 on (a+b+c+d) 234802.81
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 117401.41
Cost for 120 cum = a+b+c+d+e+f 1291415.47
Rate per cum = (a+b+c+d+e+f)/120 10761.80
say 10762.00
10762.00
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
14.1C (q) Height 5m to 10m
Case II
(ii) Basic Cost of Labour, Material & Machinery (a+b+c) for 120 751369.00
cum
d) Formwork and staging 30 per cent of (a+b+c) 30.00 225410.70
e) Overhead charges @ 0.25 on (a+b+c+d) 244194.93
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 122097.46
Cost for 120 cum = a+b+c+d+e+f 1343072.09
Rate per cum = (a+b+c+d+e+f)/120 11192.27
say 11192.00
11192.00
14.1C (r) Height above 10m
Case II
(ii) Basic Cost of Labour, Material & Machinery (a+b+c) for 120 751369.00
cum
d) Formwork and staging 35 per cent of (a+b+c) 35.00 262979.15
e) Overhead charges @ 0.25 on (a+b+c+d) 253587.04
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 126793.52
Cost for 120 cum = a+b+c+d+e+f 1394728.71
Rate per cum = (a+b+c+d+e+f)/120 11622.74
say 11623.00
11623.00
14.1 D RCC/PSC Grade M35
Case I Using Concrete Mixer.
Unit = 1 cum
Taking output = 15 cum
a) Material
Cement tonne 6.33 8939.12 56584.63 M-086
Coarse sand cum 6.75 1176.20 7939.35 M-005
20 mm Aggregate cum 8.10 1529.06 12385.39 M-053
10 mm Aggregate cum 5.40 1529.06 8256.92 M-051
b) Labour
Mate day 0.90 329.34 296.40 L-12
Mason day 1.50 352.86 529.29 L-11
Mazdoor day 21.00 152.91 3211.03 L-13
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 237.59 1425.55 P&M-009
Generator 33 KVA hour 6.00 365.80 2194.79 P&M-079
Basic Cost of Labour, Material & Machinery (a+b+c) for 15 92824.00
cum
For formwork and staging add the following:
14.1D (i) For solid slab super-structure, 18-28 per cent of (a+b+c)
Case I
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) for 15 92824.00
cum
d) Formwork and staging 18 per cent of (a+b+c) 18.00 16708.32
e) Overhead charges @ 0.25 on (a+b+c+d) 27383.08
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 13691.54
Cost for 15 cum = a+b+c+d+e+f 150606.94
Rate per cum = (a+b+c+d+e+f)/15 10040.46
say 10040.00
10040.00
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
14.1D (q) Height 5m to 10m
Case I (i)
Basic Cost of Labour, Material & Machinery (a+b+c) for 15 92824.00
cum
d) Formwork and staging 23 per cent of (a+b+c) 23.00 21349.52
e) Overhead charges @ 0.25 on (a+b+c+d) 28543.38
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 14271.69
Cost for 15 cum = a+b+c+d+e+f 156988.59
Rate per cum = (a+b+c+d+e+f)/15 10465.91
say 10466.00
10466.00
14.1D (r) Height above 10m
Case I (i)
Basic Cost of Labour, Material & Machinery (a+b+c) for 15 92824.00
cum
d) Formwork and staging 28 per cent of (a+b+c) 28.00 25990.72
e) Overhead charges @ 0.25 on (a+b+c+d) 29703.68
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 14851.84
Cost for 15 cum = a+b+c+d+e+f 163370.24
Rate per cum = (a+b+c+d+e+f)/15 10891.35
say 10891.00
10891.00
14.1D (ii) For T-beam & slab, 23-33 per cent of (a+b+c)
Case I
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) for 15 92824.00
cum
d) Formwork and staging 23 per cent of (a+b+c) 23.00 21349.52
e) Overhead charges @ 0.25 on (a+b+c+d) 28543.38
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 14271.69
Cost for 15 cum = a+b+c+d+e+f 156988.59
Rate per cum = (a+b+c+d+e+f)/15 10465.91
say 10466.00
10466.00
14.1D (q) Height 5m to 10m
Case I (ii)
Basic Cost of Labour, Material & Machinery (a+b+c) for 15 92824.00
cum
d) Formwork and staging 28 per cent of (a+b+c) 28.00 25990.72
e) Overhead charges @ 0.25 on (a+b+c+d) 29703.68
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 14851.84
Cost for 15 cum = a+b+c+d+e+f 163370.24
Rate per cum = (a+b+c+d+e+f)/15 10891.35
say 10891.00
10891.00
14.1D (r) Height above 10m
Case I (ii)
Basic Cost of Labour, Material & Machinery (a+b+c) for 15 92824.00
cum
d) Formwork and staging 33 per cent of (a+b+c) 33.00 30631.92
e) Overhead charges @ 0.25 on (a+b+c+d) 30863.98
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 15431.99
Cost for 15 cum = a+b+c+d+e+f 169751.89
Rate per cum = (a+b+c+d+e+f)/15 11316.79
say 11317.00
11317.00
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
14.1D (iii) For box girder and balanced cantilever, 38-58 per cent of
Case I cost of concrete.
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) for 15 92824.00
cum
d) Formwork and staging 38 per cent of (a+b+c) 38.00 35273.12
e) Overhead charges @ 0.25 on (a+b+c+d) 32024.28
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 16012.14
Cost for 15 cum = a+b+c+d+e+f 176133.54
Rate per cum = (a+b+c+d+e+f)/15 11742.24
say 11742.00
11742.00
14.1D (q) Height 5m to 10m
Case I
(iii) Basic Cost of Labour, Material & Machinery (a+b+c) for 15 92824.00
cum
d) Formwork and staging 48 per cent of (a+b+c) 48.00 44555.52
e) Overhead charges @ 0.25 on (a+b+c+d) 34344.88
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 17172.44
Cost for 15 cum = a+b+c+d+e+f 188896.84
Rate per cum = (a+b+c+d+e+f)/15 12593.12
say 12593.00
12593.00
14.1D (r) Height above 10m
Case I
(iii) Basic Cost of Labour, Material & Machinery (a+b+c) for 15 92824.00
cum
d) Formwork and staging 58 per cent of (a+b+c) 58.00 53837.92
e) Overhead charges @ 0.25 on (a+b+c+d) 36665.48
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 18332.74
Cost for 15 cum = a+b+c+d+e+f 201660.14
Rate per cum = (a+b+c+d+e+f)/15 13444.01
say 13444.00
13444.00
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Case II Using Batching Plant, Transit Mixer and Concrete Pump

Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 50.64 8939.12 452677.04 M-086
Coarse sand cum 54.00 1176.20 63514.80 M-004
20 mm Aggregate cum 64.80 1529.06 99083.09 M-053
10 mm Aggregate cum 43.20 1529.06 66055.39 M-051
b) Labour
Mate day 0.88 329.34 289.82 L-12
Mason day 3.00 352.86 1058.58 L-11
Mazdoor day 19.00 152.91 2905.21 L-13
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 2301.82 13810.94 P&M-002
Generator 100 KVA hour 6.00 730.42 4382.52 P&M-080
Loader hour 6.00 803.34 4820.07 P&M-017
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity lead upto1 Km hour 15.00 973.89 14608.40 P&M-049
Lead beyond 1 Km, L - lead in Kilometer tonne.k 300L 47.05 42343.20 Lead =3 km
m & P&M-050
Concrete Pump hour 6.00 275.23 1651.38 P&M-007
Basic Cost of Labour, Material & Machinery (a+b+c) for 767201.00
120 cum
For formwork and staging add the following:
14.1D (i) For solid slab super-structure, 18-28 per cent of (a+b+c)
Case II
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) for 120 767201.00
cum
d) Formwork and staging 18 per cent of (a+b+c) 18.00 138096.18
e) Overhead charges @ 0.25 on (a+b+c+d) 226324.30
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 113162.15
Cost for 120 cum = a+b+c+d+e+f 1244783.62
Rate per cum = (a+b+c+d+e+f)/120 10373.20
say 10373.00
10373.00
14.1D (q) Height 5m to 10m
Case II (i)
Basic Cost of Labour, Material & Machinery (a+b+c) for 120 767201.00
cum
d) Formwork and staging 23 per cent of (a+b+c) 23.00 176456.23
e) Overhead charges @ 0.25 on (a+b+c+d) 235914.31
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 117957.15
Cost for 120 cum = a+b+c+d+e+f 1297528.69
Rate per cum = (a+b+c+d+e+f)/120 10812.74
say 10813.00
10813.00
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
14.1D (r) Height above 10m
Case II (i)
Basic Cost of Labour, Material & Machinery (a+b+c) for 120 767201.00
cum
d) Formwork and staging 28 per cent of (a+b+c) 28.00 214816.28
e) Overhead charges @ 0.25 on (a+b+c+d) 245504.32
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 122752.16
Cost for 120 cum = a+b+c+d+e+f 1350273.76
Rate per cum = (a+b+c+d+e+f)/120 11252.28
say 11252.00
11252.00
14.1D (ii) For T-beam & slab, 23-33 per cent of (a+b+c)
Case II
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) for 120 767201.00
cum
d) Formwork and staging 23 per cent of (a+b+c) 23.00 176456.23
e) Overhead charges @ 0.25 on (a+b+c+d) 235914.31
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 117957.15
Cost for 120 cum = a+b+c+d+e+f 1297528.69
Rate per cum = (a+b+c+d+e+f)/120 10812.74
say 10813.00
10813.00
14.1D (q) Height 5m to 10m
Case II
(ii) Basic Cost of Labour, Material & Machinery (a+b+c) for 120 767201.00
cum
d) Formwork and staging 28 per cent of (a+b+c) 28.00 214816.28
e) Overhead charges @ 0.25 on (a+b+c+d) 245504.32
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 122752.16
Cost for 120 cum = a+b+c+d+e+f 1350273.76
Rate per cum = (a+b+c+d+e+f)/120 11252.28
say 11252.00
11252.00
14.1D (r) Height above 10m
Case II
(ii) Basic Cost of Labour, Material & Machinery (a+b+c) for 120 767201.00
cum
d) Formwork and staging 33 per cent of (a+b+c) 33.00 253176.33
e) Overhead charges @ 0.25 on (a+b+c+d) 255094.33
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 127547.17
Cost for 120 cum = a+b+c+d+e+f 1403018.83
Rate per cum = (a+b+c+d+e+f)/120 11691.82
say 11692.00
11692.00
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
14.1D (iii) For box girder and balanced cantilever, 38-58 per cent of
Case II cost of concrete.
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) for 120 767201.00
cum
d) Formwork and staging 38 per cent of (a+b+c) 38.00 291536.38
e) Overhead charges @ 0.25 on (a+b+c+d) 264684.35
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 132342.17
Cost for 120 cum = a+b+c+d+e+f 1455763.90
Rate per cum = (a+b+c+d+e+f)/120 12131.37
say 12131.00
12131.00
14.1D (q) Height 5m to 10m
Case II
(iii)
Basic Cost of Labour, Material & Machinery (a+b+c) for 120 767201.00
cum
d) Formwork and staging 48 per cent of (a+b+c) 48.00 368256.48
e) Overhead charges @ 0.25 on (a+b+c+d) 283864.37
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 141932.19
Cost for 120 cum = a+b+c+d+e+f 1561254.04
Rate per cum = (a+b+c+d+e+f)/120 13010.45
say 13010.00
13010.00
14.1D (r) Height above 10m
Case II
(iii)
Basic Cost of Labour, Material & Machinery (a+b+c) for 120 767201.00
cum
d) Formwork and staging 58 per cent of (a+b+c) 58.00 444976.58
e) Overhead charges @ 0.25 on (a+b+c+d) 303044.40
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 151522.20
Cost for 120 cum = a+b+c+d+e+f 1666744.17
Rate per cum = (a+b+c+d+e+f)/120 13889.53
say 13890.00
13890.00
14.1 E PSC Grade M-40
Case 1 Using concrete mixer.
Unit = 1 cum
Taking output = 15 cum
a) Material
Cement tonne 6.45 8939.12 57657.32 M-086
Coarse sand cum 6.75 1176.20 7939.35 M-005
20 mm Aggregate cum 8.10 1529.06 12385.39 M-053
10 mm Aggregate cum 5.40 1529.06 8256.92 M-051
Admixture @ 0.4 per cent of cement kg 25.80 166.73 4301.54 M-186
b) Labour
Mate day 0.96 329.34 316.16 L-12
Mason day 2.00 352.86 705.72 L-11
Mazdoor day 22.00 152.91 3363.93 L-13
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 237.59 1425.55 P&M-009
Generator 33 KVA hour 6.00 365.80 2194.79 P&M-079
Basic Cost of Labour, Material & Machinery (a+b+c) for 15 98547.00
cum
For formwork and staging add the following:
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
14.1E (i) For solid slab super-structure, 20-30 per cent of (a+b+c)
Case I
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) for 15 98547.00
cum
d) Formwork and staging 20 per cent of (a+b+c) 20.00 19709.40
e) Overhead charges @ 0.25 on (a+b+c+d) 29564.10
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 14782.05
Cost for 15 cum = a+b+c+d+e+f 162602.55
Rate per cum = (a+b+c+d+e+f)/15 10840.17
say 10840.00
10840.00
14.1E (q) Height 5m to 10m
Case I (i)
Basic Cost of Labour, Material & Machinery (a+b+c) for 15 98547.00
cum
d) Formwork and staging 25 per cent of (a+b+c) 25.00 24636.75
e) Overhead charges @ 0.25 on (a+b+c+d) 30795.94
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 15397.97
Cost for 15 cum = a+b+c+d+e+f 169377.66
Rate per cum = (a+b+c+d+e+f)/15 11291.84
say 11292.00
11292.00
14.1E (r) Height above 10m
Case I (i)
Basic Cost of Labour, Material & Machinery (a+b+c) for 15 98547.00
cum
d) Formwork and staging 30 per cent of (a+b+c) 30.00 29564.10
e) Overhead charges @ 0.25 on (a+b+c+d) 32027.78
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 16013.89
Cost for 15 cum = a+b+c+d+e+f 176152.76
Rate per cum = (a+b+c+d+e+f)/15 11743.52
say 11744.00
11744.00
14.1E (ii) For T-beam & slab, 25-35 per cent of (a+b+c)
Case I
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) for 15 98547.00
cum
d) Formwork and staging 25 per cent of (a+b+c) 25.00 24636.75
e) Overhead charges @ 0.25 on (a+b+c+d) 30795.94
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 15397.97
Cost for 15 cum = a+b+c+d+e+f 169377.66
Rate per cum = (a+b+c+d+e+f)/15 11291.84
say 11292.00
11292.00
14.1E (q) Height 5m to 10m
Case I (ii)
Basic Cost of Labour, Material & Machinery (a+b+c) for 15 98547.00
cum
d) Formwork and staging 30 per cent of (a+b+c) 30.00 29564.10
e) Overhead charges @ 0.25 on (a+b+c+d) 32027.78
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 16013.89
Cost for 15 cum = a+b+c+d+e+f 176152.76
Rate per cum = (a+b+c+d+e+f)/15 11743.52
say 11744.00
11744.00
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
14.1E (r) Height above 10m
Case I (ii)
Basic Cost of Labour, Material & Machinery (a+b+c) for 15 98547.00
cum
d) Formwork and staging 35 per cent of (a+b+c) 35.00 34491.45
e) Overhead charges @ 0.25 on (a+b+c+d) 33259.61
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 16629.81
Cost for 15 cum = a+b+c+d+e+f 182927.87
Rate per cum = (a+b+c+d+e+f)/15 12195.19
say 12195.00
12195.00
14.1E Case II Using Batching Plant, Transit Mixer and Concrete Pump

Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 51.60 8939.12 461258.59 M-086
Coarse sand cum 54.00 1176.20 63514.80 M-004
20 mm Aggregate cum 64.80 1529.06 99083.09 M-053
10 mm Aggregate cum 43.20 1529.06 66055.39 M-051
Admixture @ 0.4 per cent of cement kg 206.40 166.73 34412.32 M-186
b) Labour
Mate day 0.94 329.34 309.58 L-12
Mason day 3.50 352.86 1235.01 L-11
Mazdoor day 20.00 152.91 3058.12 L-13
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 2301.82 13810.94 P&M-002
Generator 100 KVA hour 6.00 730.42 4382.52 P&M-080
Loader hour 6.00 803.34 4820.07 P&M-017
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity lead upto1 Km hour 15.00 973.89 14608.40 P&M-049
Lead beyond 1 Km, L - lead in Kilometer tonne.k 300L 47.05 42343.20 Lead =3 km
m & P&M-050
Concrete Pump hour 6.00 275.23 1651.38 P&M-007
Basic Cost of Labour, Material & Machinery (a+b+c) for 120 810544.00
cum
For formwork and staging add the following:
14.1E (i) For solid/voided slab super-structure, 18-28 per cent of
Case II (a+b+c)
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) for 120 cum 810544.00

d) Formwork and staging 18 per cent of (a+b+c) 18.00 145897.92


e) Overhead charges @ 0.25 on (a+b+c+d) 239110.48
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 119555.24
Cost for 15 cum = a+b+c+d+e+f 1315107.64
Rate per cum = (a+b+c+d+e+f)/120 10959.23
say 10959.00
10959.00
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
14.1E (q) Height 5m to 10m
Case II (i)
Basic Cost of Labour, Material & Machinery (a+b+c) for 120 810544.00
cum
d) Formwork and staging 23 per cent of (a+b+c) 23.00 186425.12
e) Overhead charges @ 0.25 on (a+b+c+d) 249242.28
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 124621.14
Cost for 120 cum = a+b+c+d+e+f 1370832.54
Rate per cum = (a+b+c+d+e+f)/120 11423.60
say 11424.00
11424.00
14.1E (r) Height above 10m
Case II (i)
Basic Cost of Labour, Material & Machinery (a+b+c) for 120 810544.00
cum
d) Formwork and staging 28 per cent of (a+b+c) 28.00 226952.32
e) Overhead charges @ 0.25 on (a+b+c+d) 259374.08
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 129687.04
Cost for 120 cum = a+b+c+d+e+f 1426557.44
Rate per cum = (a+b+c+d+e+f)/120 11887.98
say 11888.00
11888.00
14.1E (ii) For T-beam & slab inclduing launching of precast girders by
Case II launching truss upto 40 m, 23-33 per cent of cost of
(p) concrete
Height (a+b+c)
upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) for 120 810544.00
cum
d) Formwork and staging 23 per cent of (a+b+c) 23.00 186425.12
e) Overhead charges @ 0.25 on (a+b+c+d) 249242.28
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 124621.14
Cost for 120 cum = a+b+c+d+e+f 1370832.54
Rate per cum = (a+b+c+d+e+f)/120 11423.60
say 11424.00
11424.00
14.1E (q) Height 5m to 10m
Case II
(ii) Basic Cost of Labour, Material & Machinery (a+b+c) for 120 810544.00
cum
d) Formwork and staging 28 per cent of (a+b+c) 28.00 226952.32
e) Overhead charges @ 0.25 on (a+b+c+d) 259374.08
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 129687.04
Cost for 120 cum = a+b+c+d+e+f 1426557.44
Rate per cum = (a+b+c+d+e+f)/120 11887.98
say 11888.00
11888.00
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
14.1E (r) Height above 10m
Case II
(ii) Basic Cost of Labour, Material & Machinery (a+b+c) for 120 810544.00
cum
d) Formwork and staging 33 per cent of (a+b+c) 33.00 267479.52
e) Overhead charges @ 0.25 on (a+b+c+d) 269505.88
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 134752.94
Cost for 120 cum = a+b+c+d+e+f 1482282.34
Rate per cum = (a+b+c+d+e+f)/120 12352.35
say 12352.00
12352.00
14.1E (iii) For cast-in-situ box girder, segment construction and
Case II balanced cantilever, 38-58 per cent of cost of concrete.
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) for 120 810544.00
cum
d) Formwork and staging 38 per cent of (a+b+c) 38.00 308006.72
e) Overhead charges @ 0.25 on (a+b+c+d) 279637.68
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 139818.84
Cost for 120 cum = a+b+c+d+e+f 1538007.24
Rate per cum = (a+b+c+d+e+f)/120 12816.73
say 12817.00
12817.00
14.1E (q) Height 5m to 10m
Case II
(iii)
Basic Cost of Labour, Material & Machinery (a+b+c) for 120 810544.00
cum
d) Formwork and staging 48 per cent of (a+b+c) 48.00 389061.12
e) Overhead charges @ 0.25 on (a+b+c+d) 299901.28
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 149950.64
Cost for 120 cum = a+b+c+d+e+f 1649457.04
Rate per cum = (a+b+c+d+e+f)/120 13745.48
say 13745.00
13745.00
14.1E (r) Height above 10m
Case II
(iii)
Basic Cost of Labour, Material & Machinery (a+b+c) for 120 810544.00
cum
d) Formwork and staging 58 per cent of (a+b+c) 58.00 470115.52
e) Overhead charges @ 0.25 on (a+b+c+d) 320164.88
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 160082.44
Cost for 120 cum = a+b+c+d+e+f 1760906.84
Rate per cum = (a+b+c+d+e+f)/120 14674.22
say 14674.00
14674.00
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
14.1F F PSC Grade M-45
Unit = 1 cum
Taking output = 120 cum
a) Material
Cement tonne 55.80 8939.12 498802.90 M-086
Coarse sand cum 54.00 1176.20 63514.80 M-004
20 mm Aggregate cum 64.80 1529.06 99083.09 M-053
10 mm Aggregate cum 43.20 1529.06 66055.39 M-051
Admixture @ 0.4 per cent of cement kg 223.20 166.73 37213.32 M-186
b) Labour
Mate day 0.94 329.34 309.58 L-12
Mason day 3.50 352.86 1235.01 L-11
Mazdoor day 20.00 152.91 3058.12 L-13
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 2301.82 13810.94 P&M-002
Generator 100 KVA hour 6.00 730.42 4382.52 P&M-080
Loader hour 6.00 803.34 4820.07 P&M-017
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity lead upto1 Km hour 15.00 973.89 14608.40 P&M-049
Lead beyond 1 Km, L - lead in Kilometer tonne.k 300L 47.05 42343.20 Lead =3 km
m & P&M-050
Concrete Pump hour 6.00 275.23 1651.38 P&M-007
Basic Cost of Labour, Material & Machinery (a+b+c) for 850889.00
120 cum
For formwork and staging add the following:
14.1F (i) For solid slab/voided slab super-structure, 16-26 per cent of
cost of concrete (a+b+c)
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) for 120 850889.00
cum
d) Formwork and staging 16 per cent of (a+b+c) 16.00 136142.24
e) Overhead charges @ 0.25 on (a+b+c+d) 246757.81
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 123378.91
Cost for 120 cum = a+b+c+d+e+f 1357167.96
Rate per cum = (a+b+c+d+e+f)/120 11309.73
say 11310.00
11310.00
14.1F (i) (q) Height 5m to 10m

Basic Cost of Labour, Material & Machinery (a+b+c) for 120 850889.00
cum
d) Formwork and staging 21 per cent of (a+b+c) 21.00 178686.69
e) Overhead charges @ 0.25 on (a+b+c+d) 257393.92
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 128696.96
Cost for 120 cum = a+b+c+d+e+f 1415666.57
Rate per cum = (a+b+c+d+e+f)/120 11797.22
say 11797.00
11797.00
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
14.1F (i) (r) Height above 10m

Basic Cost of Labour, Material & Machinery (a+b+c) for 120 850889.00
cum
d) Formwork and staging 26 per cent of (a+b+c) 26.00 221231.14
e) Overhead charges @ 0.25 on (a+b+c+d) 268030.04
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 134015.02
Cost for 120 cum = a+b+c+d+e+f 1474165.19
Rate per cum = (a+b+c+d+e+f)/120 12284.71
say 12285.00
12285.00
14.1F (ii) For T-beam & slab including launching of precast girders by
launching truss upto 40 m span, 21-31 per cent of cost of
concrete.
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) for 120 850889.00
cum
d) Formwork and staging 21 per cent of (a+b+c) 21.00 178686.69
e) Overhead charges @ 0.25 on (a+b+c+d) 257393.92
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 128696.96
Cost for 120 cum = a+b+c+d+e+f 1415666.57
Rate per cum = (a+b+c+d+e+f)/120 11797.22
say 11797.00
11797.00
14.1F (q) Height 5m to 10m
(ii)
Basic Cost of Labour, Material & Machinery (a+b+c) for 120 850889.00
cum
d) Formwork and staging 26 per cent of (a+b+c) 26.00 221231.14
e) Overhead charges @ 0.25 on (a+b+c+d) 268030.04
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 134015.02
Cost for 120 cum = a+b+c+d+e+f 1474165.19
Rate per cum = (a+b+c+d+e+f)/120 12284.71
say 12285.00
12285.00
14.1F (r) Height above 10m
(ii)
Basic Cost of Labour, Material & Machinery (a+b+c) for 120 850889.00
cum
d) Formwork and staging 31 per cent of (a+b+c) 31.00 263775.59
e) Overhead charges @ 0.25 on (a+b+c+d) 278666.15
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 139333.07
Cost for 120 cum = a+b+c+d+e+f 1532663.81
Rate per cum = (a+b+c+d+e+f)/120 12772.20
say 12772.00
12772.00
14.1F (iii) For cast-in-situ box girder, segmental construction and
balanced cantilever, 36-56 per cent of cost of concrete.

(p) Height upto 5m


Basic Cost of Labour, Material & Machinery (a+b+c) for 120 850889.00
cum
d) Formwork and staging 36 per cent of (a+b+c) 36.00 306320.04
e) Overhead charges @ 0.25 on (a+b+c+d) 289302.26
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 144651.13
Cost for 120 cum = a+b+c+d+e+f 1591162.43
Rate per cum = (a+b+c+d+e+f)/120 13259.69
say 13260.00
13260.00
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
14.1F (q) Height 5m to 10m
(iii)
Basic Cost of Labour, Material & Machinery (a+b+c) for 120 850889.00
cum
d) Formwork and staging 46 per cent of (a+b+c) 46.00 391408.94
e) Overhead charges @ 0.25 on (a+b+c+d) 310574.49
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 155287.24
Cost for 120 cum = a+b+c+d+e+f 1708159.67
Rate per cum = (a+b+c+d+e+f)/120 14234.66
say 14235.00
14235.00
14.1F (r) Height above 10m
(iii)
Basic Cost of Labour, Material & Machinery (a+b+c) for 120 850889.00
cum
d) Formwork and staging 56 per cent of (a+b+c) 56.00 476497.84
e) Overhead charges @ 0.25 on (a+b+c+d) 331846.71
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 165923.36
Cost for 120 cum = a+b+c+d+e+f 1825156.91
Rate per cum = (a+b+c+d+e+f)/120 15209.64
say 15210.00
15210.00
14.1 G PSC Grade M-50
Unit = 1 cum
Taking output = 120 cum
a) Material
Cement tonne 58.80 8939.12 525620.26 M-086
Coarse sand cum 54.00 1176.20 63514.80 M-004
20 mm Aggregate cum 64.80 1529.06 99083.09 M-053
10 mm Aggregate cum 43.20 1529.06 66055.39 M-051
Admixture @ 0.4 per cent of cement kg 235.20 166.73 39214.04 M-186
b) Labour
Mate day 0.94 329.34 309.58 L-12
Mason day 3.50 352.86 1235.01 L-11
Mazdoor day 20.00 152.91 3058.12 L-13
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 2301.82 13810.94 P&M-002
Generator 100 KVA hour 6.00 730.42 4382.52 P&M-080
Loader hour 6.00 803.34 4820.07 P&M-017
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity lead upto1 Km hour 15.00 973.89 14608.40 P&M-049
Lead beyond 1 Km, L - lead in Kilometer tonne.k 300L 47.05 42343.20 Lead =3 km
m & P&M-050
Concrete Pump hour 6.00 275.23 1651.38 P&M-007
Basic Cost of Labour, Material & Machinery (a+b+c) for 879707.00
120 cum
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
For formwork and staging add the following:
14.1G (i) For cast-in-situ box girder, segmental construction and
balanced cantilever, 35-55 per cent of cost of concrete

(p) Height upto 5m


Basic Cost of Labour, Material & Machinery (a+b+c) for 120 879707.00
cum
d) Formwork and staging 35 per cent of (a+b+c) 35.00 307897.45
e) Overhead charges @ 0.25 on (a+b+c+d) 296901.11
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 148450.56
Cost for 120 cum = a+b+c+d+e+f 1632956.12
Rate per cum = (a+b+c+d+e+f)/120 13607.97
say 13608.00
13608.00
14.1G (i) (q) Height 5m to 10m
Basic Cost of Labour, Material & Machinery (a+b+c) for 120 879707.00
cum
d) Formwork and staging 45 per cent of (a+b+c) 45.00 395868.15
e) Overhead charges @ 0.25 on (a+b+c+d) 318893.79
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 159446.89
Cost for 120 cum = a+b+c+d+e+f 1753915.83
Rate per cum = (a+b+c+d+e+f)/120 14615.97
say 14616.00
14616.00
14.1G (i) (r) Height above 10m
Basic Cost of Labour, Material & Machinery (a+b+c) for 120 879707.00
cum
d) Formwork and staging 55 per cent of (a+b+c) 55.00 483838.85
e) Overhead charges @ 0.25 on (a+b+c+d) 340886.46
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 170443.23
Cost for 120 cum = a+b+c+d+e+f 1874875.54
Rate per cum = (a+b+c+d+e+f)/120 15623.96
say 15624.00
15624.00
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
14.1 H PSC Grade M- 55
Unit = 1 cum
Taking output = 120 cum
a) Material
Cement tonne 63.50 8939.12 567634.12 M-086
Coarse sand cum 54.00 1176.20 63514.80 M-004
20 mm Aggregate cum 64.80 1529.06 99083.09 M-053
10 mm Aggregate cum 43.20 1529.06 66055.39 M-051
Admixture @ 0.4 per cent of cement kg 254.00 166.73 42348.49 M-186
b) Labour
Mate day 0.94 329.34 309.58 L-12
Mason day 3.50 352.86 1235.01 L-11
Mazdoor day 20.00 152.91 3058.12 L-13
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 2301.82 13810.94 P&M-002
Generator 100 KVA hour 6.00 730.42 4382.52 P&M-080
Loader hour 6.00 803.34 4820.07 P&M-017
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity lead upto1 Km hour 15.00 973.89 14608.40 P&M-049
Lead beyond 1 Km, L - lead in Kilometer tonne.k 300L 47.05 42343.20 Lead =3 km
m & P&M-050
Concrete Pump hour 6.00 275.23 1651.38 P&M-007
Basic Cost of Labour, Material & Machinery (a+b+c) for 924856.00
120 cum
For formwork and staging add the following:
14.1H (i) For cast-in-situ box girder, segmental construction and
balanced cantilever, 35-55 per cent of cost of concrete

(p) Height upto 5m


Basic Cost of Labour, Material & Machinery (a+b+c) for 120 924856.00
cum
d) Formwork and staging 35 per cent of (a+b+c) 35.00 323699.60
e) Overhead charges @ 0.25 on (a+b+c+d) 312138.90
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 156069.45
Cost for 120 cum = a+b+c+d+e+f 1716763.95
Rate per cum = (a+b+c+d+e+f)/120 14306.37
say 14306.00
14306.00
14.1H (i) (q) Height 5m to 10m

Basic Cost of Labour, Material & Machinery (a+b+c) for 120 924856.00
cum
d) Formwork and staging 45 per cent of (a+b+c) 45.00 416185.20
e) Overhead charges @ 0.25 on (a+b+c+d) 335260.30
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 167630.15
Cost for 120 cum = a+b+c+d+e+f 1843931.65
Rate per cum = (a+b+c+d+e+f)/120 15366.10
say 15366.00
15366.00
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
14.1H (i) (r) Height above 10m

Basic Cost of Labour, Material & Machinery (a+b+c) for 120 924856.00
cum
d) Formwork and staging 55 per cent of (a+b+c) 55.00 508670.80
e) Overhead charges @ 0.25 on (a+b+c+d) 358381.70
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 179190.85
Cost for 120 cum = a+b+c+d+e+f 1971099.35
Rate per cum = (a+b+c+d+e+f)/120 16425.83
say 16426.00
16426.00
Note 1.Where ever concrete is carried out using batching plant, transit
mixer, concrete pump, admixers conforming IS: 9103 @ 0.4 per
cent of weight of cement may be added for achieving desired
slump of concrete.
2. Cement provided for various components of the super structure
is for estimating purpose only. Actual quantity of cement will be
as per approved mix design. Similarly, the provision for coarse
and fine aggregates is for estimating purpose and the exact
quantity shall be as per the mix design.
3. The items like needle and surface vibrators are part of minor T
& P which is already covered under the overhead charges. As
such these items have not been added separately in the rate
analysis.
14.2 1600 Supplying, fitting and placing HYSD bar reinforcement in
super-structure complete as per drawing and technical
specifications
Unit = 1 MT
Taking output = 1 MT
a) Material
HYSD bars including 5 per cent for laps and wastage tonne 1.05 44000.00 46200.00 M-087
Binding wire Kg 8.00 92.63 741.01 M-071
b) Labour for cutting, bending, tying and placing in
position
Mate day 0.44 329.34 144.91 L-12
Blacksmith day 3.00 352.86 1058.58 L-02
Mazdoor day 8.00 152.91 1223.25 L-13
Basic Cost of Labour & Material (a+b) 49368.00
c) Overhead charges @ 0.25 on (a+b) 12341.94
d) Contractor's profit @ 0.1 on (a+b+c) 6170.97
Rate per MT = a+b+c+d 67880.65
say 67881.00
67881.00
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
14.3 1800 High tensile steel wires/strands including all accessories for
stressing, stressing operations and grouting complete as per
drawing and Technical Specifications

Unit = 1 MT
Taking output = 0.377 MT
Details of cost for 12T13 strand 40 m long cable (weight = 0.377
MT)
a) Material
H.T. Strand @ 9.42 kg/m including 2 per cent for wastage tonne 0.385 148201.20 57057.46 M-125
and extra length for jacking
Sheathing duct ID 66 mm along with 5 per cent extra length metre 42.00 99.98 4199.03 M-170
40 x 1.05 = 42 m.
Tube anchorage set complete with bearing plate, permanent each 2.00 2099.52 4199.03 M-193
wedges etc
Cement for grouting including 3 per cent wastage @ 3.00 tonne 0.125 8939.12 1117.39 M-086
kg/m = 3 x 1.03 x 40 = 123.60 kg (say, = 125 kg)
Add 0.50 per cent cost of material for Spacers, Insulation 332.86
tape and miscellaneous items
b) Labour
i) For making and fixing cables, anchorages
Mate day 0.16 329.34 52.69 L-12
Blacksmith day 1.00 352.86 352.86 L-02
Mazdoor day 3.00 152.91 458.72 L-13
ii) For prestressing
Mate/Supervisor day 0.05 329.34 16.47 L-12
Prestressing operator / Fitter day 0.25 235.24 58.81 L-08
Mazdoor day 1.00 152.91 152.91 L-13
iii) For grouting
Mate/Supervisor day 0.05 329.34 16.47 L-12
Mason day 0.25 352.86 88.22 L-11
Mazdoor day 1.00 152.91 152.91 L-13
c) Machinery
Stressing jack with pump hour 2.50 132.91 332.28 P&M-040
Grouting pump with agitator hour 1.00 419.90 419.90 M-117
Generator 33 KVA. hour 3.50 365.80 1280.29 P&M-079
d) Overhead charges @ 0.25 on (a+b+c) 17572.08
e) Contractor's profit @ 0.1 on (a+b+c+d) 8786.04
Cost for 0.377 MT (a+b+c+d+e) 96646.41
Rate per MT = (a+b+c+d+e)/0.377 256356.53
say 256357.00
256357.00
Note Cost of HT steel has been taken for delivery at site. Hence
carriage has not been considered.
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
14.4 2702 Providing and laying Cement concrete wearing coat M-30
grade including reinforcement complete as per drawing and
Technical Specifications
Unit = 1 cum
Taking output = 1 cum
a) Material
Cement concrete M30 Grade Refer relevant item of concrete cum 1.00 6261.00 6261.00 Item 14.1(C)
in Item 14.1 excluding formwork
HYSD bar reinforcement Rate as per item No 14.2(Excluding tonne 0.075 49368.00 3702.60 Item 14.2 A
OH & CP)
DIR used item
b) Labour
Mazdoor for cleaning deck slab concrete surface. day 0.15 152.91 22.94 L-13
c) Overhead charges @ 0.25 on (a+b) 2496.63
d) Contractor's profit @ 0.1 on (a+b+c) 1248.32
Rate per cum (a+b+c+d) 13731.49
say 13731.00
13731.00
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
14.5 515 & Mastic Asphalt
2702 Providing and laying 12 mm thick mastic asphalt wearing
course on top of deck slab excluding prime coat with paving
grade bitumen meeting the requirements given in table 500-
29, prepared by using mastic cooker and laid to required
level and slope after cleaning the surface, including
providing antiskid surface with bitumen precoated fine
grained hard stone chipping of 9.5 mm nominal size at the
rate of 0.005cum per 10 sqm and at an approximate spacing
of 10 cm center to center in both directions, pressed into
surface when the temperature of surfaces not less than 100
deg. C, protruding 1 mm to 4 mm over mastic surface, all
complete as per clause 515.

Unit = sqm
Taking output = 72.46 sqm (2 tonnes)(0.869 cum) assuming a
density of 2.3 tonnes/cum.
a) Labour
Mate day 0.49 329.34 161.37 L-12
Mazdoor day 11.00 152.91 1681.97 L-13
Mazdoor (Skilled) day 1.25 244.65 305.81 L-15
b) Machinery
Mechanical broom @ 1250 sqm per hour hour 0.06 396.38 23.78 P&M-031
Air compressor 250 cfm hour 0.06 334.04 20.04 P&M-001
Mastic cooker 1 tonne capacity hour 6.00 65.87 395.20 P&M-030
Bitumen boiler 1500 litres capacity hour 6.00 209.36 1256.18 P&M-005
Tractor for towing and positioning of mastic cooker and hour 1.00 379.91 379.91 P&M-053
bitumen boiler
c) Material
Base mastic (without coarse aggregates) = 60 per cent
Coarse aggregate(3.35mm to 9.5 mm size) = 40 per cent .
Proportion of material required for mastic asphalt with coarse
aggregates (based on mix design done by CRRI for a specific
case)
i) Bitumen 80/100 or 60/70 @ 10.2 per cent by weight of tonne 0.204 40000.00 8160.00 M-073
mix. 2 x 10.2/100 = 0.204
ii) Crusher stone dust @ 31.9 per cent by weight of mix = 2 cum 0.39 470.48 183.49 M-021
x 31.9/100 = 0.638 tonnes = 0.638/1.625 = 0.39
iii) Lime stone dust filler with calcium carbonate content not tonne 0.36 9571.33 3445.68 M-194
less than 80 per cent by weight @ 17.92 per cent by weight
of mix = 2 x 17.92/100 = 0.36
iv) Coarse aggregates 9.5 mm to 3.35 mm size @ 40 per cum 0.55 1529.06 840.98 M-051
cent by weight of mix = 2 x 40/100 = 0.8 MT = 0.8/1.456 =
0.55
v) Pre-coated stone chips of 9.5 mm nominal size for skid cum 0.036 8027.57 288.99 M-148
resistance = 72.46x0.005/10 = 0.036
vi) Bitumen for coating of chips @ 2 per cent by weight = kg 1.05 40.00 42.00 M-073/1000
0.036 x 1.456 x 2/100 = 0.001048MT = 1.05kg
d) Overhead charges @ 0.25 on (a+b+c) 4296.35
e) Contractor's profit @ 0.1 on (a+b+c+d) 2148.18
Cost for 72.46 sqm = a+b+c+d+e 23629.95
Rate per sqm = (a+b+c+d+e)/72.46 326.11
say 326.00
326.00
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Note 1.The rates for 6 mm or any other thickness may be worked out
on pro-rata basis.
2. Where tack coat is required to be provided before laying mastic
asphalt, the same is required to be measured and paid
separately.
3.The quantities of binder, filler and aggregates are for estimating
purpose. Exact quantities shall be as per mix design.

4.This rate analysis is based on design made by CRRI for a


specific case and is meant for estimating purposes only. Actual
design is required to be done for each case.
5.The quantity of bitumen works out 17 per cent of the mastic
asphalt blocks without aggregates and falls within the standards
laid down by MoRTH Specifications.
14.6 2703, Construction of precast RCC railing of M30 Grade, aggregate
1500, size not exceeding 12 mm, true to line and grade, tolerance
1600 & of vertical RCC post not to exceed 1 in 500, centre to centre
1700 spacing between vertical post not to exceed 2000 mm,
leaving adequate space between vertical post for expansion,
complete as per approved drawings and technical
specifications.
Unit = 1 RM
Taking output = 2 x 24 m span = 48 m
a) Material
i) M30 Grade Reinforced Cement Concrete cum 4.092 6261.00 25620.01 Item 14.1(C)
No. of vertical posts = (12 + 2)2 = 28 Nos., External area of DIR used
vertical post 0.25x0.275 = 0.069sqm, Concrete in Vertical item
posts = 0.069 x 28 = 1.932 cum, Hand rail in 3 tiers = 3 x 24
= 72 m, External area = 0.170 x 0.175 = 0.03 sqm, Concrete
in hand rails = 0.03 x 72 = 2.16 cum, Total Concrete = 1.932
+ 2.16 = 4.092 cum. (Refer MoRTH SD / 202).

Add 5 per cent of above cost for form work for casting in 1281.00
casting yard.
ii) HYSD bar reinforcement Rate as per item No tonne 0.865 49368.00 42703.32 Item 14.2 A
14.2(Excluding OH & CP)
DIR used item
Refer MoRTH SD / 202.
Add 5 per cent of (a) for handling and fixing of precast 3480.22
panels in position
b) Overhead charges @ 0.25 on (a) 18271.14
c) Contractor's profit @ 0.1 on (a+b) 9135.57
Rate for 48 m (a+b+c) 100491.26
Rate per metre (a+b+c)/48 2093.57
say 2094.00
2094.00
Note 1.Quantities of material have been adopted from standard plans
of MoRTH vide drawing no. SD/202.
2.48 m length is the total linear length adding both sides of 24 m
span.
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
14.7 2703, Construction of RCC railing of M30 Grade in-situ with 20 mm
1500, nominal size aggregate, true to line and grade, tolerance of
1600 & vertical RCC post not to exceed 1 in 500, centre to centre
1700 spacing between vertical post not to exceed 2000 mm,
leaving adequate space between vertical post for expansion,
complete as per approved drawings and technical
specifications.
Unit = 1 RM
Taking output = 2 x 24 m span = 48 m.
a) Material
i) M30 Grade Reinforced Cement Concrete cum 4.092 6261.00 25620.01 Item 14.1(C)

No. of vertical posts = (12 + 2)2 = 28 Nos., External area of


vertical post 0.25x0.275 = 0.069sqm, Concrete in vehicle
posts = 0.069 x 28 = 1.932 cum, Hand rail in 3 tiers = 3 x 24
= 72 m, External area = 0.170 x 0.175 = 0.03 sqm, Concrete
in hand rails = 0.03 x 72 = 2.16 cum, Total Concrete = 1.932
+ 2.16 = 4.092 cum. (Refer MoRTH SD / 202).

Add 12 per cent of above cost for form work. 3074.40


ii) HYSD bar reinforcement Rate as per item No tonne 0.865 49368.00 42703.32 Item 14.2 A
14.2(Excluding OH & CP)
refer MoRTH SD / 202.
b) Overhead charges @ 0.25 on (a) 17849.43
c) Contractor's profit @ 0.1 on (a+b) 8924.72
Rate for 48 m (a+b+c) 98171.88
Rate per metre (a+b+c)/48 2045.25
say 2045.00
2045.00
Note 1. Quantities of material have been adopted from standard plans
of MoRTH vide drawing no. SD/202.
2. 48 m length is the total linear length adding both sides of 24 m
span.
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
14.8 2703.2 & Providing, fitting and fixing mild steel railing complete as per
1900 drawing and Technical Specification
Unit = 1 RM
Taking output = 2 x 50 m span = 100 m
a) Material:
1) ISMC 100 = 2.806 x 1.05 = 2.946 MT tonne 2.946 60000.00 176760.00 M-185
2) MS Flat = 0.964 x 1.05 = 1.012 MT tonne 1.012 60000.00 60720.00 M-185
3) MS bars = 0.17 x 1.05 = 0.180 MT tonne 0.18 60000.00 10800.00 M-185
4) MS bolts, nuts and washers tonne 0.15 87685.71 13152.86 M-136*1000
Add @ 5 per cent of cost of material for painting one shop 13071.64
coat with red oxide primer and three coats of synthetic
enamel paint and consumables to safeguard against
weathering and corrosion.
Add for cost of concrete for fixing vertical posts in the 2614.33
performed recess @ 1 per cent of cost of material.
Add for electricity charges, welding and drilling equipment, 2614.33
electrodes and other consumables @ 1 per cent of cost of
material.
b) Labour
Mate day 2.80 329.34 922.14 L-12
Mazdoor (Skilled) day 30.00 244.65 7339.49 L-15
Mazdoor day 40.00 152.91 6116.24 L-13
c) Overhead charges @ 0.25 on (a+b) 73527.76
d) Contractor's profit @ 0.1 on (a+b+c) 36763.88
Cost for 100 m steel railing = a+b+c+d 404402.66
Rate per metre (a+b+c+d)/100 4044.03
say 4044.00
4044.00
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
14.9 2705 Drainage Spouts complete as per drawing and Technical
specification
Unit = 1 No.
Taking output = 1 No.
a) Material
Corrosion resistant Structural steel including 5 per cent Kg 4.00 65.21 260.83 M-094/1000
wastage
GI pipe 100mm dia metre 6.00 1210.31 7261.86 M-056
GI bolt 10 mm Dia each 6.00 14.82 88.92 M-116
Galvanised MS flat clamp each 2.00 494.00 988.01 M-107
b) Labour
For fabrication
Mate day 0.02 329.34 6.59 L-12
Skilled (Blacksmith, welder etc.) day 0.02 352.86 7.06 L-02
Mazdoor day 0.02 152.91 3.06 L-13
For fixing in position
Mate day 0.01 329.34 3.29 L-12
Mason day 0.01 352.86 3.53 L-11
Mazdoor day 0.20 152.91 30.58 L-13
Add @ 5 per cent of cost of material and labour for 432.69
electrodes, cutting gas, sealant, anti-corrosive bituminous
paint, mild steel grating etc.
c) Overhead charges @ 0.25 on (a+b) 2271.60
d) Contractor's profit @ 0.1 on (a+b+c) 1135.80
Rate per metre (a+b+c+d) 12493.82
say 12494.00
12494.00
Note 1. In case of viaducts in urban areas, the drainage spouts should
be connected with suitably located pipelines to discharge the
surface run-off to drains provided at ground level.

2. In case of bridges, sufficient length of G.I Pipe shall be


provided to ensure that there is no splashing of water from the
drainage spout on the structure.
14.10 2700 PCC M15 Grade leveling course below approach slab
complete as per drawing and Technical specification
Unit = 1 cum
Taking output = 1 cum
Material
Concrete, Rate as per item No. 12.8 (A) excluding formworks cum 1.00 6736.00 6736.00 Item 12.8 (A)

Rate per cum say 6736.00


6736.00
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
14.11 1500,160 Reinforced cement concrete approach slab including
0,1700 & reinforcement and formwork complete as per drawing and
2704 Technical specification
Unit = 1 cum
Taking output = 1 cum
a) Material
Cement concreteM30 Grade Refer relevant item of concrete cum 1.00 6255.00 6255.00 Item 12.8 (G)
in item 12.8(G)by using batching plant, excluding formwork
i.e. per cum basic cost (a+b+c) (Excluding OH & CP)

( Refer relevant item of concrete in item No. 13.8 (G) except 125.10
that form work may be added at the rate of 2 per cent of cost
against 3.5 per cent provided in the foundation concrete.

HYSD bar reinforcement Rate as per item No 14.2(Excluding tonne 0.05 49368.00 2468.40 Item 14.2 A
OH & CP)
b) Overhead charges @ 0.25 on (a) 2212.13
c) Contractor's profit @ 0.1 on(a+b) 1106.06
Rate per cum (a+b+c) 12166.69
say 12167.00
12167.00
Note The grade of reinforced cement concrete may be adopted as M30
for severe conditions and M25 for moderate conditions.
14.18 2605 Filler joint
(i) Providing & fixing 2 mm thick corrugated copper plate in
expansion joint complete as per drawing & Technical
Specification.
Unit = Running meter
Taking output = 12 m
a) Labour
Cutting, bending, carrying & fixing etc.
Mate day 0.04 329.34 13.17 L-12
Mazdoor day 0.50 152.91 76.45 L-13
Mazdoor (Skilled) day 0.50 244.65 122.32 L-15
b) Material
Copper plate - 12m long x 250 mm wide kg 55.00 314.93 17321.02 M-093
Area = 12 x 0.25 = 3 sqm
Weight = 3 x 0.002 x 8900 = 53.4 kg
Wastage @ 2.5 per cent = 1.33 kg/54.73 kg say = 55 kg.
c) Overhead charges @ 0.25 on (a+b) 4383.24
d) Contractor's profit @ 0.1 on (a+b+c) 2191.62
Cost for 12 m = (a+b+c+d) 24107.83
Rate per m = (a+b+c+d)/12 2008.99
say 2009.00
2009.00
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
14.18 (ii) Providing & fixing 20 mm thick compressible fibre board in
expansion joint complete as per drawing & Technical
Specification.
Unit = Running meter
Taking output = 12 m
a) Labour
For carrying, placing & fixing.
Mate day 0.01 329.34 2.63 L-12
Mazdoor day 0.10 152.91 15.29 L-13
Mazdoor (Skilled) day 0.10 244.65 24.46 L-15
b) Material
20 mm thick compressible fibre board 12 m long x 25 cm sqm 3.00 1976.02 5928.05 M-091
deep.
Area = 12 x 0.25 = 3 sqm
c) Overhead charges @ 0.25 on (a+b) 1492.61
d) Contractor's profit @ 0.1 on (a+b+c) 746.30
Cost for 12 m = (a+b+c+d) 8209.35
Rate per m = (a+b+c+d)/12 684.11
say 684.00
684.00
14.18 (iii) Providing and fixing in position 20 mm thick premoulded
joint filler in expansion joint for fixed ends of simply
supported spans not exceeding 10 m to cater for a horizontal
movement upto 20 mm, covered with sealant complete as per
drawing and technical specifications.

Unit = Running meter


Taking output = 12 m
a) Labour
Mate day 0.01 329.34 3.29 L-12
Mazdoor day 0.20 152.91 30.58 L-13
Mazdoor (Skilled) day 0.10 244.65 24.46 L-15
b) Material
Premoulded joint filler 12 m long,20 mm thick and 300 mm sqm 3.60 926.26 3334.53 M-147
deep.
c) Overhead charges @ 0.25 on (a+b) 848.22
d) Contractor's profit @ 0.1 on (a+b+c) 424.11
Cost for 12 m = (a+b+c+d) 4665.19
Rate per m = (a+b+c+d)/12 388.77
say 389.00
389.00
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
14.18 (iv) Providing and filling joint sealing compound as per drawings
and technical specifications with coarse sand and 6 per cent
bitumen by weight
Unit = Running meter
Taking output = 12 m
12m long x 100 mm wide x 10mm deep recess
a) Labour
Mate day 0.02 329.34 6.59 L-12
Mazdoor day 0.50 152.91 76.45 L-13
Mazdoor (Skilled) day 0.10 244.65 24.46 L-15
b) Material
Sand cum 0.012 1176.20 14.11 M-005
Volume 12 x 0.1 x 0.01 = 0.012 cum
Weight 0.012 x 1400 = 16.8kg
Bitumen cum 0.001 40000.00 40.00 M-073
16.8 x 0.06 = 1 kg
c) Overhead charges @ 0.25 on (a+b) 40.40
d) Contractor's profit @ 0.1 on (a+b+c) 20.20
Cost for 12 m = (a+b+c+d) 222.23
Rate per m = (a+b+c+d)/12 18.52
say 18.50
19.00
Note For arriving at the final rate of filler joints per m
length and per cm depth of joint filling compound,
the rates at Sl. No. i), ii), iii) & iv) shall be added
14.22 2607 Strip Seal Expansion Joint
Providing and laying of a strip seal expansion joint catering
to maximum horizontal movement upto 70 mm, complete as
per approved drawings and standard specifications to be
installed by the manufacturer/supplier or their authorised
representative ensuring compliance to the manufacturer's
instructions for installation.

Unit = Running meter


Taking output = 12 m
a) Labour
Mate day 0.05 329.34 16.47 L-12
Mazdoor day 1.00 152.91 152.91 L-13
Mazdoor (Skilled) day 0.25 244.65 61.16 L-15
b) Material
Supply of complete assembly of strip seal expansion joint metre 12.00 9997.70 119972.40 M-184
comprising of edge beams, anchorage, strip seal element
and complete accessories as per approved specifications
and drawings.
Add 5 per cent of cost of material for anchorage 6010.15
reinforcement, welding and other incidentals.
c) Overhead charges @ 0.25 on (a+b) 31553.27
d) Contractor's profit @ 0.1 on (a+b+c) 15776.64
Cost for 12 m = (a+b+c+d) 173542.99
Rate per m = (a+b+c+d)/12 14461.92
say 14462.00
14462.00
Note 1. The installation shall be done by the manufacturer or his
authorised representative to the satisfaction of the Engineer.
2. The concreting for joining the expansion joint assembly with
the deck has not been included in this analysis as the same is
catered in the quantities of RCC deck.
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Supply, fabrication, delivery at bridge site and erection of
structural steel works as per IS 2062, including two coats of
Rate Analysis performed on basis of sample analysis published in "Guidebook for Fabrication & Erection of Steel Structures" by Alok Baishya, BE(Civil), MBA and published by Institute for Steel

Non-Sch primer, one at shop and the other at site and two coats of
aluminium paints including all labour, material, consumables
etc.
Unit =1MT
Taking output = 1MT
a) Material
Structural Steel tonne 1.05 60000.00 63000.00
Permanent Bolts of tested quality kg 7.00 87.69 613.80
Electrode (@10 kg of weld metal (approx 275 nos. of 4mm
nos. 275.00 7.42 2040.50
electrode / ton of fabrication)
Electrode (@2 kg of weld metal (approx 275 nos. of 4mm
nos. 50.00 7.42 371.00
electrode / ton of erection)
DA Gas for fabrication cum 2.00 583.00 1166.00
DA Gas for erection cum 0.50 583.00 291.50
Oxygen for fabrication cum 6.00 100.70 604.20
Oxygen for erection cum 1.50 100.70 151.05
Red Lead Primer for fabrication l 1.50 127.20 190.80
Red Lead Primer for erection l 1.00 127.20 127.20
Paint l 2.00 185.25 370.50
Service bolts for erection kg 7.00 87.69 613.80
Development & Growth (INSDAG)

b) Labour
Marker for fabrication day 0.60 244.65 146.79
Fitter-I for fabrication day 0.90 235.24 211.72
Gas Cutter for fabrication day 0.90 244.65 220.18
Hammer man day 0.30 152.91 45.87
Welder-I for fabrication day 1.50 244.65 366.97
Foreman for fabrication day 0.90 176.43 158.79
Grinder for fabrication day 0.90 244.65 220.18
Work Supervisor for fabrication day 0.30 329.34 98.80
Unskilled for fabrication day 6.00 152.91 917.44
Painter for fabrication day 1.52 352.86 536.35
Painter for erection day 5.05 352.86 1781.94
Sarang for erection day 1.00 244.65 244.65
Riggers for erection day 8.00 176.43 1411.44
Welder for erection day 1.00 244.65 244.65
Gas Cutter for erection day 1.00 244.65 244.65
Fitter for erection day 1.00 235.24 235.24
Semi skilled for erection day 3.00 176.43 529.29
c) Machinery
Welding machine, grinding machine for fabrication LS 742.00 742.00
Tools, Zigs and fixtures for fabrication LS 212.00 212.00
Crane, inch, Welding generator, rectifier, transformer, etc. for
LS 742.00 742.00
erection
Tools, tackles, safety appliances, etc for erection LS 212.00 212.00
d)Overheads @ 0.25 on (a+b+c) 19765.83
e)Contractor’s profit @ 0.1 on (a+b+c+d) 9882.91
Rate for per MT (a+b+c+d+e) 108712.05
say 108712.00
CHAPTER - 15
RIVER TRAINING AND PROTECTION WORKS
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
15.1 2503 Providing and laying boulders apron on river bed for
protection against scour with stone boulders weighing not
less than 40 kg each complete as per drawing and Technical
specification.
A Boulder Laid Dry Without Wire Crates.
Unit = cum
Taking output = 1 cum
a) Material
Stone cum 1.00 858.63 858.63 M-003
Stone Spalls cum 0.20 969.66 193.93 M-008
b) Labour
Mate day 0.04 329.34 13.17 L-12
Mason day 0.35 352.86 123.50 L-11
Mazdoor * day 0.75 152.91 114.68 L-13
c) Overhead charges @ 0.25 on (a+b) 325.98
d) Contractor's profit @ 0.1 on (a+b+c) 162.99
Rate per cum = (a+b+c+d) 1792.88
say 1793.00
1793.00
* Including excavation for trimming for preparation of bed.
Note Nominal excavation required for preparation of bed has been
taken into account while making provision for labour.
15.2 2503 Boulder Apron Laid in Wire Crates
Providing and laying of boulder apron laid in wire crates made
with 4mm dia GI wire conforming to IS: 280 & IS:4826 in 100mm
x 100mm mesh (weaved diagonally) including 10 per cent extra
for laps and joints laid with stone boulders weighing not less than
40 kg each.
Unit = cum
Taking output = 3 mx1.5mx1.25m = 5.63 cum
a) Material
4mm GI wire crates woven in mesh size of 100 mm x 100 mm. sqm 22.00 355.07 7811.57 M-108
Stone cum 5.63 858.63 4834.06 M-003
Stone Spalls cum 1.13 969.66 1095.71 M-008
b) Labour
Mate day 0.18 329.34 59.28 L-12
Mazdoor (Skilled) day 1.50 244.65 366.97 L-15
Mazdoor day *3.00 152.91 458.7 L-13
c) Overhead charges @ 0.25 on (a+b) 3656.6
d) Contractor's profit @ 0.1 on (a+b+c) 1828.29
Cost for 5.63 cum = a+b+c+d 20111.19
Rate per cum = (a+b+c+d)/5.63 3572.15
say 3572.00
3572.00
* Including excavation for trimming for preparation of bed.
Note Readymade woven wire crate rolls have been considered in the
rate analysis. In case readymade rolls are not available, GI wire
4mm dia. @ 32 kg per 10 sqm may be provided. In that case 2
per cent of the cost of GI wire may be added for weaving the wire
crates.
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
15.3 2503 Cement Concrete Blocks (size 0.5 x 0.5 x 0.5 m)
Providing and laying of apron with cement concrete blocks of size
0.5x0.5x0.5 m cast in-situ and made with nominal mix of M-15
grade cement concrete with a minimum cement content of 250
kg/cum as per IRC: 21-2000.
Unit = cum
Taking out put = 1 cum
Concrete Grade M15 Rate as per item No. 12.8 (A) including OH cum 1.00 7004.00 7004.00 Item 12.8 (A)
& CP
Add 2 per cent of cost to account for excavation for preparation 140.08
of bed, nominal surface reinforcement and filling of granular
material in recesses between blocks.
Rate per cum 7144.08
say 7144.00
7144.00
15.4 2504 Providing and laying Pitching on slopes laid over prepared
filter media including boulder apron laid dry in front of toe of
embankment complete as per drawing and Technical
specifications
A Stone/Boulder
Unit = cum
Taking output = 1 cum
a) Material
Stone weighing not less than 40kg cum 1.00 858.63 858.63 M-003
Stone spalls of minimum 25 mm size cum 0.20 969.66 193.93 M-008
b) Labour
Mate day 0.04 329.34 13.17 L-12
Mason day 0.35 352.86 123.50 L-11
Mazdoor day 0.75 152.91 114.68 L-13
c) Overhead charges @ 0.25 on (a+b) 325.98
d) Contractor's profit @ 0.1 on (a+b+c) 162.99
Rate per cum = (a+b+c+d) 1792.88
say 1793.00
1793.00
15.4 B Cement Concrete Blocks of size 0.3x0.3 x0.3 m cast in
cement concrete of Grade M15
Unit = cum
Taking output = 1 cum
cum 1.00 7004.00 7004.00 Item 12.8 (A)
Concrete Grade M15 Rate as per item No. 12.8 (A)
Add 2 per cent of cost to account for nominal surface 140.08
reinforcement and filling of granular material in recesses between
blocks.
Rate per cum 7144.08
say 7144.00
7144.00
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
15.5 2504
Providing and laying Filter material underneath pitching in
slopes complete as per drawing and Technical specification

Unit = cum
Taking output = 1 cum
a) Material
Graded stone aggregate of required size cum 1.20 1190.60 1428.72 M-012
b) Labour
Mate day 0.05 329.34 16.47 L-12
Mazdoor (Skilled) day 0.25 244.65 61.16 L-15
Mazdoor * day 1.00 152.91 152.91 L-13
c) Overhead charges @ 0.25 on (a+b) 414.81
d) Contractor's profit @ 0.1 on (a+b+c) 207.41
Rate per cum = (a+b+c+d) 2281.47
say 2281.00
2281.00
Includes Mazdoor required for trimming of slope to proper profile
and preparation of bed.
15.6 700 &
Geotextile Filter
2504
Laying of a geotextile filter between pitching and embankment
slopes on which pitching is laid to prevent escape of the
embankment material through the voids of the stone
pitching/cement concrete blocks as well as to allow free
movement of water without creating any uplift head on the
pitching.
Unit = sqm
Taking output = 10 sqm.
a) Labour
Mate day 0.02 329.34 6.59 L-12
Mazdoor day 0.30 152.91 45.87 L-13
Mazdoor (Skilled) day 0.10 244.65 24.46 L-15
b) Material
Permeable synthetic geotextile including 5 per cent for overlap sqm 11.00 446.37 4910.05 M-187
and wastage
c) Overhead charges @ 0.25 on (a+b) 1246.74
d) Contractor's profit @ 0.1 on (a+b+c) 623.37
Cost for 10 sqm = a+b+c+d 6857.08
Rate per sqm = (a+b+c+d)/10 685.71
say 686.00
686.00
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
15.7 2504.4 Toe protection

A toe wall for toe protection can either be in dry rubble masonry in
case of dry rubble pitching or pitching with stones in wire crates
or it can be in PCC M15 nominal mix if cement concert block
have been used for pitching . Rates for toe wall can be adopted
from respective clauses depending upon approved design. The
rate for excavation for foundation, dry rubble masonry and PCC
M15 have been analysed and given in respective chapters.

15.8 2505
Providing and laying Flooring complete as per drawing and
Technical specifications laid over cement concert bedding.
A Rubble stone laid in cement mortar 1:3
Unit = cum
Taking output = 1 cum
a) Cement mortor 1:3 (Rate as in Item 12.6 sub-analysis) cum 0.33 5945.00 1961.85 Item 12.6 (A)
excluding OH & CP
b) Add for cement concrete bedding (M15 Nominal mix) cum 0.33 4899.00 1616.67 Item 12.8 (A)
vide Item 12.8 (A) excluding OH & CP . Quantity shall be
adopted as per design ( Assume Rubble stone Flooring
thickness 300mm and cement concrete bedding thickness
100mm)
Add 1 per cent of cost to account for excavation for preparation 35.79
of bed.
c) Material
Stone cum 1.00 858.63 858.63 M-003
Stone Spalls cum 0.20 969.66 193.93 M-008
d) Labour
Mate day 0.08 329.34 26.35 L-12
Mason day 0.50 352.86 176.43 L-11
Mazdoor (for laying stones, filling of quarry spalls) day 1.50 152.91 229.36 L-13
e) Overhead charges @ 0.25 on (a+c+d) 861.64
f) Contractor's profit @ 0.1 on (a+c+d+e) 430.82
Rate per cum = (a+b+c+d+e+f) 6391.45
say 6391.00
6391.00
* Includes cement mortar for laying and filling of joints.
15.8 B Cement Concrete blocks Grade M15
Concrete Grade M15 block. (Rate as per item No. 12.8 (A) cum 1.00 7004.00 7004.00 Item 12.8 (A)
including OH & CP.
Add for cement concrete bedding (M15 Nominal mix) vide Item cum 0.33 7004.00 2311.32 Item 12.8 (A)
12.8 (A) including OH & CP. Quantity shall be adopted as per
design ( Assume Cement Concrete blocks thickness 300mm and
cement concrete bedding thickness 100mm)
Add 1 per cent of cost to account for excavation for preparation 93.15
of bed.
Rate per cum 9408.47
say 9408.00
9408.00
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
15.9 2506 Dry Rubble Flooring
Construction of dry rubble flooring at cross drainage works for
relatively less important works.
Unit = cum
Taking output = 1 cum
a) Material
Stone cum 1.00 858.63 858.63 M-003
Stone Spalls cum 0.20 969.66 193.93 M-008
b) Labour
Mate day 0.10 329.34 32.93 L-12
Mason day 0.50 352.86 176.43 L-11
mazdoor day 1.50 152.91 229.36 L-13
Add 1 per cent of (b) for trimming and preparation of base. 4.39
c) Overhead charges @ 0.25 on (a+b) 373.92
d) Contractor's profit @ 0.1 on (a+b+c) 186.96
Rate per cum = (a+b+c+d) 2056.54
say 2057.00
2057.00
15.10 2507.2 Curtain wall complete as per drawing and Technical
specification
A Stone masonry in cement mortar (1:3)
cum 1.00 5309.00 5309.00 Item 12.7 (A )
Coursed rubble masonry (1st sort)

Rate same as per item No. 12.7 (A) including OH & CP


Rate per cum say 5309.00
or 5309.00

15.10 B Cement concrete Grade M15


Concrete Grade M15 Rate as per item No. 12.8 (A) including OH cum 1.00 7004.00 7004.00 Item 12.8 (A)
& CP
Rate per cum say 7004.00
7004.00
Note Other items like excavation for foundation, filling behind wall, filter
media, weep holes etc. shall be added separately as per
approved design.
15.11 2507.2 Flexible Apron :Construction of flexible apron 1 m thick
comprising of loose stone boulders weighing not less than
40 kg beyond curtain wall.
Unit = cum
Taking Output = 1 cum
a) Material
Stone cum 1.00 858.63 858.63 M-003
Stone Spalls cum 0.20 969.66 193.93 M-008
b) Labour
Mate day 0.05 329.34 16.47 L-12
Mason day 0.25 352.86 88.22 L-11
Mazdoor day 1.00 152.91 152.91 L-13
Add 1 per cent of cost of (a+b) for trimming and preparation of 13.10
bed.
c) Overhead charges @ 0.25 on (a+b) 330.81
d) Contractor's profit @ 0.1 on (a+b+c) 165.41
Rate per cum = (a+b+c+d) 1819.46
say 1819.00
1819.00
CHAPTER-16
REPAIR AND REHABILITATION
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
16.1 2809 Removal of existing cement concrete wearing coat including its disposal
complete as per Technical Specification without causing any detrimental
effect to any part of the bridge structure and removal of dismantled
material with all lifts and lead upto 1000 m
Unit = Sq m ( Thickness 75 mm)
Taking output = 10 sqm
a) Labour
Mate day 0.06 329.34 19.76 L-12
Mazdoor day 1.00 152.91 152.91 L-13
b) Machinery
Air Compressor 250 cfm with pneumatic breaker/jack hammer along with hour 1.00 334.04 334.04 P&M-001
accessories.
Tractor-trolley. hour 0.50 379.91 189.96 P&M-053
c) Overhead charges @ 0.3 on (a+b) 209.00
d) Contractor's profit @ 0.1 on (a+b+c) 90.57
Cost for 10 sqm = (a+d+c+d) 996.23
Rate per sqm = (a+b+c+d)/10 99.62
say 100.00
16.2 2809 Removal of existing asphaltic wearing coat comprising of 50 mm thick
asphaltic concert laid over 12 mm thick mastic asphalt including disposal
with all lift and lead upto 1000 m.

Unit = Sq m
Taking output = 10 sqm
a) Labour
Mate day 0.03 329.34 9.88 L-12
Mazdoor day 0.75 152.91 114.68 L-13
b) Machinery
Air Compressor 250 cfm with pneumatic breaker. hour 0.75 334.04 250.53 P&M-001
Tractor-trolley. hour 0.40 379.91 151.97 P&M-053
c) Overhead charges @ 0.3 on (a+b) 158.12
d) Contractor's profit @ 0.1 on (a+b+c) 68.52
Cost for 10 sqm = (a+d+c+d) 753.69
Rate per sqm = (a+b+c+d)/10 75.37
say 75.00
16.3 2807 Guniting concrete surface with cement mortar applied with compressor
after cleaning surface and spraying with epoxy complete as per Technical
Specification
Unit = Sq m
Taking output = 1 sqm
Assuming thickness 25 mm
a) Material
Cement kg 16.00 8.939 143.03 M-
Graded sand cum 0.04 1176.20 47.05 M-005
Wire mesh 50mm x 50mm size of 3mm wire kg 2.00 74.10 148.20 M-199
Epoxy kg 0.67 957.13 641.28 M-102
Accelerator compound for guniting @ 4 per cent of weight of cement kg 0.64 166.73 106.70 M-186

Add 2 per cent of cost of material for miscellaneous consumables like 21.73
nozzles, wire brush, cotton waste etc.
b) Labour
Mate day 0.01 329.34 3.29 L-12
Mason day 0.04 352.86 14.11 L-11
Mazdoor day 0.14 152.91 21.41 L-13
c) Machinery
Compressor with guniting equipment along with accessories hour 0.10 470.48 47.05 P&M-076

d) Overhead charges @ 0.3 on (a+b+c) 358.15


e) Contractor's profit @ 0.1 on (a+b+c+d) 155.20
Rate per sqm = (a+b+c+d+e) 1707.20
say 1707.00
1707.00
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
16.4 2800 Providing and inserting nipples with approved fixing compound after
drilling holes for grouting as per Technical Specifications including
subsequent cutting/removal and sealing of the hole as necessary of
nipples after completion of grouting with Cement/Epoxy

Unit = Number
Taking output = 1 No.
a) Material
Nipples each 1.00 33.72 33.72 M-135
Cement, fixing compound and consumables @ 15 per cent of cost of nipple 5.06

b) Labour
Mate day 0.01 329.34 3.29 L-12
Mazdoor (Skilled) labour for drilling day 0.08 244.65 19.57 L-15
Mazdoor (Skilled) labour for fixing nipple and sealing inlets day 0.08 244.65 19.57 L-15

Mazdoor for cutting and removing of nipples day 0.04 152.91 6.12 L-13
Add 10 per cent of labour cost for drilling holes etc 4.86
c) Overhead charges @ 0.3 on (a+b) 27.66
d) Contractor's profit @ 0.1 on (a+b+c) 11.98
Rate per No. = (a+b+c+d) 131.83
say 132.00
132.00
16.5 2806 Sealing of cracks/porous concrete by injection process through
nipples/Grouting complete as per Technical Specification.

A Cement Grout
Unit = kg
Taking output = 1 kg
a) Material
Cement including 10 per cent wastage kg 1.10 8.94 9.83 M-
Admixtures (anti shrinkage compound) @ 20 per cent of cost of cement 1.97
b) Labour
Mate day 0.08 329.34 26.35 L-12
Mazdoor (Skilled) day 0.10 244.65 24.46 L-15
Mazdoor day 0.10 152.91 15.29 L-13
c) Machinery
Grout pump with agitator and accessories hour 0.10 419.90 41.99 M-117
d) Overhead charges @ 0.3 on (a+b+c) 35.97
e) Contractor's profit @ 0.1 on (a+b+c+d) 15.59
Rate per kg = (a+b+c+d+e) 171.45
say 171.00
171.00
B Cement Mortar (1:1) Grouting
Unit = kg
Taking output = 1 kg
a) Material
Cement including 10 per cent wastage kg 0.55 8.94 4.92 M-
Sand including 10 per cent wastage kg 0.55 0.78 0.43 M-
Admixtures (anti shrinkage compound) @ 20 per cent of cost of cement 0.98

b) Labour
Mate day 0.08 329.34 26.35 L-12
Mazdoor (Skilled) day 0.10 244.65 24.46 L-15
Mazdoor day 0.10 152.91 15.29 L-13
c) Machinery
Grout pump with agitator and accessories hour 0.10 419.90 41.99 M-117
d) Overhead charges @ 0.3 on (a+b+c) 34.33
e) Contractor's profit @ 0.1 on (a+b+c+d) 14.88
Rate per kg = (a+b+c+d+e) 163.63
say 164.00
164.00
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
16.6 2800 Patching of damaged concrete surface with polymer concrete and curing
compounds, initiator and promoter, available in present formulations, to
be applied as per instructions of manufacturer and as approved by the
Engineer.

Unit = sqm
Taking output = 10 sqm for an average thickness of 25mm.

a) Labour
Mate day 0.06 329.34 19.76 L-12
Mazdoor (Skilled) day 0.75 244.65 183.49 L-15
Mazdoor day 0.75 152.91 114.68 L-13
b) Material
Pre-packed polymer concrete based on epoxy system complete with curing kg 315.00 98.80 31122.25 M-150
compound, intiator and promoter including 5 per cent wastage.

c) Machinery
Grout pump with agitator and accessories hour 2.00 419.90 839.81 M-117
d) Overhead charges @ 0.3 on (a+b+c) 9684.00
e) Contractor's profit @ 0.1 on (a+b+c+d) 4196.40
Cost for 10 sqm = a+b+c+d+e 46160.38
Rate per sqm = (a+b+c+d+e)/10 4616.04
say 4616.00
Note This item is a proprietory item available in market as pre-packed polymer
concrete and is required to be applied as per instructions of the manufacturer.

16.7 2803 Sealing of crack / porous concrete with Epoxy Grout by injection through
nipples complete as per clause 2803.1.

Unit = kg
Taking output = 1 kg
a) Material
Epoxy including 10 per cent wastage kg 1.10 957.13 1052.85 M-102
b) Labour
Mate day 0.08 329.34 26.35 L-12
Mazdoor (Skilled) day 0.10 244.65 24.46 L-15
Mazdoor day 0.10 152.91 15.29 L-13
c) Machinery
Epoxy Injection gun hour 0.10 352.86 35.29 P&M-078
d) Overhead charges @ 0.3 on (a+b+c) 346.27
e) Contractor's profit @ 0.1 on (a+b+c+d) 150.05
Rate per kg = (a+b+c+d+e) 1650.56
say 1651.00
1651.00
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
16.8 2804 Applying epoxy mortar over leached, honey combed and spalled concrete
surface and exposed steel reinforcement complete as per Technical
Specification

Unit = sqm
Taking output = 10 sqm
Assume average 10mm thickness of epoxy mortar
a) Material
Epoxy resin-hardener mix for prime coat kg 2.50 1327.64 3319.09 M-101
Epoxy mortar kg 2.20 679.26 1494.36 M-103
Epoxy resin -hardener mix for seal coat. kg 2.00 1327.64 2655.27 M-101
Add 3 per cent cost of material for other consumables like acetone etc and 224.06
to cover wastage.
b) Labour
Mate day 0.04 329.34 13.17 L-12
Mazdoor (Skilled) day 0.50 244.65 122.32 L-15
Mazdoor day 0.50 152.91 76.45 L-13
c) Overhead charges @ 0.3 on (a+b) 2371.42
d) Contractor's profit @ 0.1 on (a+b+c) 1027.62
Cost for 10 sqm = a+b+c+d 11303.77
Rate per sqm = (a+b+c+d)/10 1130.38
say 1130.00
1130.00
16.9 2807 Removal of defective concrete, cleaning the surface thoroughly, applying
the shotcrete mixture mechanically with compressed air under pressure,
comprising of cement, sand, coarse aggregates, water and quick setting
compound in the proportion as per clause 2807.1., sand and coarse
aggregates conforming to IS: 383 and table 1 of IS: 9012 respectively,
water cement ratio ranging from 0.35 to 0.50, density of gunite not less
than 2000 kg/cum, strength not less than 25 Mpa and workmanship
conforming to clause 2807.6.

unit: sqm
Taking output = 10 sqm, 40 mm average thickness.
a) Labour
Mate day 0.04 329.34 13.17 L-12
Mazdoor day 0.50 152.91 76.45 L-13
Mazdoor (Skilled) day 0.50 244.65 122.32 L-15
b) Machinery
Air compressor 250 cfm hour 1.00 334.04 334.04 P&M-001
Shotcreteing equipment hour 1.00 470.48 470.48 P&M-076
water tanker 6 KL capacity hour 0.02 517.53 10.35 P&M-060
c) Material
Cement kg 120.00 8.939 1072.69 M-
Sand cum 0.15 1176.20 176.43 M-005
Coarse aggregate of size 4.75mm cum 0.15 1566.98 235.05 M-024
Quick setting compound kg 2.50 43.23 108.06 M-152
Water KL 0.10 55.58 5.56 M-195
d) Overhead charges @ 0.3 on (a+b+c) 787.38
e) Contractor's profit @ 0.1 on (a+b+c+d) 341.20
Cost for 10 sqm = a+b+c+d+e 3753.20
Rate per sqm = (a+b+c+d+e)/10 375.32
say 375.00
375.00
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
16.10 2800 Applying pre-packed cement based polymer mortar of strength 45 Mpa at
28 days for replacement of spalled concrete

Unit = sqm
Taking output = 10 sqm
Assumed thickness - 10 mm
a) Material
Acrylic polymer bonding coat Litre 1.40 321.10 449.54 M-057
pre-packed cement based polymer mortar of strength 45 Mpa at 28 days kg 12.00 98.80 1185.61 M-150

Add 3 per cent of (a ) above for wastage. 49.05


b) Labour
Mate day 0.04 329.34 13.17 L-12
Mazdoor (Skilled) day 0.50 244.65 122.32 L-15
Mazdoor day 0.50 152.91 76.45 L-13
c) Overhead charges @ 0.3 on (a+b) 568.85
d) Contractor's profit @ 0.1 on (a+b+c) 246.50
Cost for 10 sqm = a+b+c+d 2711.51
Rate per sqm = (a+b+c+d)/10 271.15
say 271.00
271.00
16.11 2805 Eproxy bonding of new concrete to old concrete
Unit = sqm
Taking output = 10 sqm
a) Material
Epoxy resin with pot life not less than 60-90 minutes and satisfying testing kg 8.00 1327.64 10621.09 M-101
as per clause 2803.9
Add 3 per cent of (a ) above for wastage. 318.63
b) Labour
Mate day 0.04 329.34 13.17 L-12
Mazdoor (Skilled) day 0.50 244.65 122.32 L-15
Mazdoor day 0.50 152.91 76.45 L-13
c) Overhead charges @ 0.3 on (a+b) 3345.50
d) Contractor's profit @ 0.1 on (a+b+c) 1449.72
Cost for 10 sqm = a+b+c+d 15946.89
Rate per sqm = (a+b+c+d)/10 1594.69
say 1595.00
1595.00
16.17 Replacement of Expansion Joints complete as per drawings

Unit -1 RM
Taking output = 12 RM
a) Material
Epoxy for bonding new concrete to old concrete @ 0.8 kg/sqm kg 9.60 957.13 9188.47 M-102
M-30 grade cement concrete excluding OH & CP (Rate as per items 14.1 C cum 3.60 7514.00 27050.40 Item
(i) 14.1(C)
b) Labour
Removal of old expansion joint including breaking of concrete, cutting of lugs
and shifting of broken material etc.
Mate day 0.26 329.34 85.63 L-12
Mazdoor day 6.00 152.91 917.44 L-13
Mazdoor (Skilled) day 0.50 244.65 122.32 L-15
c) Overhead charges @ 0.3 on (a+b) 11209.28
d) Contractor's profit @ 0.1 on (a+b+c) 4857.35
Cost for replacement of 12 RM = a+b+c+d 53430.90
Rate per RM = (a+b+c+d)/12 4452.57
say 4453.00

4453.00
Note The rate for the installation of new expansion joints may be taken from the
chapter on superstructure. Broken concrete will have to be replaced which has
been included in this analysis.
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
16.18 Replacement of Damaged Concrete Railing.
Unit = RM
Taking output = 10 RM
a) Labour
Labour for dismantling old railing and disposal of dismantled material.

Mate day 0.20 329.34 65.87 L-12


Mazdoor day 5.00 152.91 764.53 L-13
b) Machinery
Tractor-trolley for disposal of dismantled material hour 1.00 379.91 379.91 P&M-053
c) Overhead charges @ 0.3 on (a+b) 363.09
d) Contractor's profit @ 0.1 on (a+b+c) 157.34
Cost for 10 m = a+b+c+d 1730.74
Rate per metre = (a+b+c+d)/10 173.07
say 173.00
Note The rate for the provision of new railing may be adopted from the chapter on
superstructure.
Non-Sch Reinforced Cement Concrete Crash Barrier
Provision of an Reinforced cement concrete crash barrier at the
edges of the road, approaches to bridge structures and medians,
constructed with M-40 grade concrete with HYSD reinforcement
conforming to IRC:21 and dowel bars 25 mm dia, 450 mm long at
expansion joints filled with pre-moulded asphalt filler board, keyed
to the structure on which it is built and installed as per design given
in the enclosure to MOST circular No. RW/NH - 33022/1/94-DO III
dated 24 June 1994 as per dimensions in the approved drawing
and at locations directed by the Engineer, all as specified
Unit = Linear metre
Taking output = 10 m
(i) a) M 40 grade concrete
M 40 grade concrete cum 3.000 6569.80 19709.40 Item 14.1(A)
b) Labour
Mate day 0.040 329.34 13.17 L-12
Mazdoor day 1.000 152.91 152.91 L-13
c) Material
HYSD steel reinforcement including dowel bars tonne 0.280 44000.00 12320.00 M-082
Pre-moulded asphalt filler board sqm 0.320 1049.76 335.92 M-144
d) Formwork @ 4 per cent on cost of concrete i.e. cost of 1301.26
material, labour and machinery
e) Overhead charges @ 0.25 on (a+b+c+d) 8132.85
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 4066.43
Cost for 10 metre = a+b+c+d+e 46031.93
Rate per metre = (a+b+c+d+e)/10 4603.19
say 4603.00
4603.00
Carriage of Material
Lead Charts Basic Rate of carriage of materials

Hauling Hauling
Lead Lead Loading Basic rate
Total Lead Charges on Charges on
Material Surfaced Unsurfaced and of carriage Unit
(km.) surfaced unsurfaced
Sl. No. Material Place Av.Lead (Km.) Road Road Unloading of materials
road road
1 2 3 4 5 6 7 9 10 11 12 13 14 15
1 Fine Sand Krishnai 51 To the Start Point Fine sand 58.000 57 4 1 4.8 92 per m3

2 Lime Bongaigaon 15 To the Start Point Lime 0.000 4 0 4.8 92 per m3

3 Moorum Krishnai 0 To the Start Point Moorum 0.000 4 1 4.8 92 per m3

4 Stone Metal Krishnai 0 To the Start Point Metal 9.986 8.986 4 1 4.8 92 162.89 per m3
5 Stone Boulder Krishnai 0 To the Start Point Boulder 9.986 8.986 4 1 4.8 112 180.04 per m3

6 Stone Chips, Aggregate Krishnai 0 To the Start Point Chips 9.986 8.986 4 1 4.8 92 157.19 per m3

7 Coarse Sand Krishnai 51 To the Start Point Coarse Sand 58.000 57 4 1 4.8 92 per m3

8 Cement Bongaigaon 0 To the Start Point Cement 0.000 0 4 0 4.8 162 162.00 per MT

9 Steel Bongaigaon 0 To the Start Point Steel 0.000 0 4 0 4.8 162 162.00 per MT

10 Tar, Bitumen Bongaigaon 0 To the Start Point Bitumen 0.000 0 4 0 4.8 162 162.00 per MT

Bitumen
11 Bitumen Emulsion Bongaigaon 0 To the Start Point 0.000 0 4 0 4.8 162 162.00 per MT
Emulsion
Structural
12 Structural Steel Bongaigaon 0 To the Start Point 0.000 0 4 0 4.8 162 162.00 per MT
Steel
13 Brick Local 0 to worksite Brick 0 0 4 0 4.8 162 per 1000
Finished Rate of Road Work
HAULAGE CALCULATION SHEET FOR ROAD WORKS
Item SOR Rate Stone chips /agg Stone Boulder Stone Metal Bitumen Bitumen Emulsion Lime/Filler/soil/pipe Sand Steel Cement Structural Steel Finished Labour Final Rate
Rate Cess (1%)
Sl. No. Cl No.
Quantity Carriage Quantity Carriage Quantity Carriage Quantity Carriage Quantity Carriage Quantity Carriage Quantity Carriage Quantity Carriage Quantity Carriage Quantity Carriage
Cost Cost Cost Cost Cost Cost Cost Cost Cost Cost

1 2.1 (i) Girth from 300 mm to 600 mm 162.00 162.00 1.62 163.62
2 2.1 (ii) Girth from 600 mm to 900 mm 315.00 315.00 3.15 318.15
3 2.1 (iii) Girth from 900 mm to 1800 mm 575.00 575.00 5.75 580.75
4 2.1 (iv) Girth above 1800 mm 1060.00 1060.00 10.60 1070.60
Clearing and Grubbing Road Land by
6 2.3 (ii) A Mechanical Means - In area of light jungle 45871.00 45871.00 458.71 46329.71

Dismantling of Structures - By Mechanical


Means -Prestressed / Reinforced cement
7 2.4 II. B 661.00 661.00 6.61 667.61
concrete grade M-20 & above

Dismantling Brick / Tile work -In cement


8 2.4 (ii) B mortar 216.00 216.00 2.16 218.16

Removing all type of Hume Pipes and


Stacking within a lead of 1000 metres
9 2.4 (IX) A including Earthwork and Dismantling of 102.00 102.00 1.02 103.02
Masonry Works - Up to 600 mm dia

Removing all type of Hume Pipes and


Stacking within a lead of 1000 metres
10 2.4 (IX) B including Earthwork and Dismantling of 139.00 139.00 1.39 140.39
Masonry Works - 600 mm to 900 mm dia

Removing all type of Hume Pipes and


Stacking within a lead of 1000 metres
11 2.4 (IX) C including Earthwork and Dismantling of 238.00 238.00 2.38 240.38
Masonry Works - above 900 mm dia

Dismantling of Flexible Pavements by


12 2.5 I (B) Manual Means - Granular courses 346.00 346.00 3.46 349.46

Dismantling of Flexible Pavements by


13 2.5 II (A) Mechanical Means - Bituminous course 240.00 240.00 2.40 242.40

Dismantling of Cement Concrete


2.6 Pavement 994.00 0.0000 0.00 0.000 0.00 0.000 0.00 994.00 9.94 1003.94

Dismantling Kilometre Stone - Ordinary


14 2.10 B KM Stone 144.00 0.0000 0.00 0.0000 0.00 0.0000 0.00 0.000 0.00 0.000 0.00 144.00 1.44 145.44

Excavation in Soil using Hydraulic


15 3.6 Excavator CK 90 and Tippers with Disposal 83.00 0.0000 0.00 0.0000 0.00 0.0000 0.00 0.000 0.00 0.000 0.00 83.00 0.83 83.83
upto 1000 metres.
Construction of Embankment with
16 3.16 Material obtained from Borrowpits 266.00 0.0000 0.00 0.0000 0.00 0.0000 0.00 0.000 0.00 0.000 0.00 266.00 2.66 268.66

Construction of Embankment with


17 3.16 Material obtained from Borrowpits with 266.00 0.0000 0.00 0.0000 0.00 0.0000 0.00 0.000 0.00 0.000 0.00 266.00 2.66 268.66
higher PI value
Construction of Embankment with
17 3.17 Material Deposited from Roadway Cutting 139.00 0.0000 0.00 0.0000 0.00 0.0000 0.00 0.000 0.00 0.000 0.00 139.00 1.39 140.39

Construction of Subgrade and Earthen


18 3.18 Shoulders 322.00 0.0000 0.00 0.0000 0.00 0.0000 0.00 0.000 0.00 0.000 0.00 322.00 3.22 325.22

19 3.22 Turfing with Sods 31.00 0.0000 0.00 0.0000 0.00 0.0000 0.00 0.000 0.00 0.000 0.00 31.00 0.31 31.31
20 3.15 Scarifying existing bituminous surface 4.20 0.0000 0.00 0.0000 0.00 0.0000 0.00 0.000 0.00 0.000 0.00 4.20 0.04 4.24
25 4.1A GSB Grading I (plant mix method) 2322.00 0.893 157.19 0.0000 0.00 0.0000 0.00 0.384 0.00 0.0000 0.00 0.000 0.00 0.000 0.00 2462.42 24.62 2487.05
Reuse of GSB Material obtained from
26 4.1 818.00 0.0000 0.00 0.0000 0.00 0.0000 0.00 0.000 0.00 0.000 0.00 818.00 8.18 826.18
Dismantling of Pavement Coarse
21 4.12 WMM 2350.00 0.924 157.19 0.0000 0.00 0.0000 0.00 0.396 0.00 0.0000 0.00 0.000 0.00 0.000 0.00 2495.24 24.95 2520.20
Construction of Median and Island with
22 4.14 259.00 0.0000 0.00 0.0000 0.00 0.0000 0.00 0.000 0.00 0.000 0.00 259.00 2.59 261.59
Soil Taken from Borrow Areas
Construction of Median and Island with
22 4.13 192.00 0.0000 0.00 0.0000 0.00 0.0000 0.00 0.000 0.00 0.000 0.00 192.00 1.92 193.92
Soil Taken from Roadway Cutting
HAULAGE CALCULATION SHEET FOR ROAD WORKS
Item SOR Rate Stone chips /agg Stone Boulder Stone Metal Bitumen Bitumen Emulsion Lime/Filler/soil/pipe Sand Steel Cement Structural Steel Finished Labour Final Rate
Rate Cess (1%)
Sl. No. Cl No.
Quantity Carriage Quantity Carriage Quantity Carriage Quantity Carriage Quantity Carriage Quantity Carriage Quantity Carriage Quantity Carriage Quantity Carriage Quantity Carriage
Cost Cost Cost Cost Cost Cost Cost Cost Cost Cost

23 4.15 Hard Shoulder 2322.00 0.893 157.19 0.0000 0.00 0.0000 0.00 0.384 0.00 0.0000 0.00 0.000 0.00 0.000 0.00 2462.42 24.62 2487.05
24 5.1 Prime Coat 25.00 0.0000 0.00 0.0006 162.00 0.0000 0.00 0.000 0.00 0.000 0.00 25.10 0.25 25.35
25 5.2 Tack Coat on Bitumeneous Surface 9.00 0.0000 0.00 0.0002 162.00 0.0000 0.00 0.000 0.00 0.000 0.00 9.03 0.09 9.12
26 5.2 Tack Coat on Granular Surface 17.10 0.0000 0.00 0.0004 162.00 0.0000 0.00 0.000 0.00 0.000 0.00 17.16 0.17 17.34
33 5.6 DBM (GR-I) 8408.00 0.000 157.19 0.1038 162.00 0.0000 0.00 0.0000 0.00 0.000 0.00 0.0000 0.00 0.000 0.00 0.000 0.00 8424.82 84.25 8509.06
27 5.6 DBM (GR-II) 8967.00 0.854 157.19 0.1038 162.00 0.0442 0.00 0.589 0.00 9118.11 91.18 9209.29
28 5.8 BC (GR-II) 10230.00 0.821 157.19 0.1272 162.00 0.0000 0.00 0.0451 0.00 0.642 0.00 0.0000 0.00 0.000 0.00 0.000 0.00 10379.61 103.80 10483.41
36 5.14 Mastic Asphalt (road) 1117.00 0.0201 162.00 0.0000 0.00 0.0000 0.00 0.000 0.00 0.000 0.00 1120.26 11.20 1131.46
29 6.1 DLC 4676.00 0.900 157.19 0.0000 0.00 0.0000 0.00 0.451 0.00 0.0000 0.00 0.150 162.00 0.000 0.00 4841.77 48.42 4890.19
30 6.2 PQC 9931.00 0.900 157.19 0.0000 0.00 0.0000 0.00 0.0101 162.00 0.394 162.00 0.000 0.00 10137.98 101.38 10239.36
31 8.1(B) Concrete M20 Kerb 362.00 0.061 157.19 0.0000 0.00 0.0000 0.00 0.030 0.00 0.0000 0.00 0.016 162.00 0.000 0.00 374.07 3.74 377.81
40 8.3 Printing Letter 0.30 0.0000 0.00 0.0000 0.00 0.0000 0.00 0.000 0.00 0.000 0.00 0.30 0.00 0.30
32 8.4 Retro-Refecltorised 0.00
33 (i) 90 cm equilateral triangle 2589.00 0.108 157.19 0.0000 0.00 0.0000 0.00 0.054 0.00 0.0190 162.00 0.033 162.00 0.000 0.00 2614.41 26.14 2640.55
34 (ii) 60 cm equilateral triangle 2447.00 0.108 157.19 0.0000 0.00 0.0000 0.00 0.054 0.00 0.0190 162.00 0.033 162.00 0.000 0.00 2472.41 24.72 2497.13
35 (iii) 60 cm circular 2540.00 0.108 157.19 0.0000 0.00 0.0000 0.00 0.054 0.00 0.0190 162.00 0.033 162.00 0.000 0.00 2565.41 25.65 2591.06
36 (iv) 80 mm x 60 mm rectangular 2684.00 0.108 157.19 0.0000 0.00 0.0000 0.00 0.054 0.00 0.0190 162.00 0.033 162.00 0.000 0.00 2709.41 27.09 2736.50
37 (v) 60 cm x 45 cm rectangular 2530.00 0.108 157.19 0.0000 0.00 0.0000 0.00 0.054 0.00 0.0190 162.00 0.033 162.00 0.000 0.00 2555.41 25.55 2580.96
38 (vi) 60 cm x 60 cm square 2596.00 0.108 157.19 0.00 0.00 0.054 0.00 0.0190 162.00 0.033 162.00 0.000 0.00 2621.41 26.21 2647.62
39 (vii) 90 cm high octagon 2825.00 0.108 157.19 0.00 0.00 0.054 0.00 0.0190 162.00 0.033 162.00 0.000 0.00 2850.41 28.50 2878.91
Overhead Signs - Truss and Vertical
49 8.7A 142869.00 0.0000 0.00 0.0000 0.00 1.0500 162.00 0.000 0.00 0.000 0.00 143039.10 1430.39 144469.49
Support
50 8.8 Painting Two Coats 58.00 0.0000 0.00 0.0000 0.00 0.0000 0.00 0.000 0.00 0.000 0.00 58.00 0.58 58.58
51 8.9 Printing On Steel Surface 52.00 0.0000 0.00 0.0000 0.00 0.0000 0.00 0.000 0.00 0.000 0.00 52.00 0.52 52.52
40 8.14 5th KM Post 3970.00 0.353 157.19 0.0000 0.00 0.0000 0.00 0.176 0.00 0.00368 162.00 0.115 162.00 0.000 0.00 4044.59 40.45 4085.04
41 8.14 Oridinary KM Post 2473.00 0.242 157.19 0.0000 0.00 0.0000 0.00 0.121 0.00 0.0019 162.00 0.074 162.00 0.000 0.00 2523.42 25.23 2548.65
54 8.22 RCC Crash Barrier 3624.00 0.270 157.19 0.0000 0.00 0.0000 0.00 0.135 0.00 0.0280 162.00 0.104 162.00 0.000 0.00 3687.85 36.88 3724.73
Direction and Place Identification signs
42 8.5 3335.00 0.120 157.19 0.0000 0.00 0.0000 0.00 0.060 0.00 0.0211 162.00 0.037 162.00 0.000 0.00 3363.23 33.63 3396.86
upto 0.9 sqm size board

Direction and Place Identification Signs


43 8.6 3831.00 0.144 157.19 0.0000 0.00 0.0000 0.00 0.072 0.00 0.0253 162.00 0.044 162.00 0.000 0.00 3864.88 38.65 3903.53
with size more than 0.9 sqm size Board.

Road Marking with Hot Applied


44 8.13 655.00 0.0000 0.00 0.0000 0.00 0.0000 0.00 0.000 0.00 0.000 0.00 655.00 6.55 661.55
Thermoplastic Compound
"THRIE" : Metal Beam Crash Barrier, Type-
58 8.23 B 5370.00 0.0000 0.00 0.0000 0.00 162.00 0.000 0.00 0.051 162.00 5378.22 53.78 5432.00
B
59 8.16 BOUNDARY PILLAR 636.00 0.020 157.19 0.010 0.00 0.0014 162.00 0.006 162.00 640.31 6.40 646.71
45 8.20 RAILING 2062.00 0.0099 162.00 0.018 162.00 2066.50 20.66 2087.16
50 8.23. A W- Metal beam crash barrier 3572.00 0.037 162.00 3577.98 35.78 3613.76
51 8.15 Road Delineators 1258.00 1258.00 12.58 1270.58
56 3.19 Compacting Original Ground 73.00 0.0000 0.00 0.0000 0.00 0.0000 0.00 0.000 0.00 0.000 0.00 73.00 0.73 73.73
75 Non-Sch Reinforced Cement Concrete Crash Barrier 4603.00 0.0280 162.00 0.1290 162.00 4628.43 46.28 4674.72
Construction of Median and Island with
192.00 192.00 1.92 193.92
Soil Taken from Roadway Cutting
Filling Pot-holes and Patch Repairs with
56 10.4 149.00 0.0015 162.00 0.0002 162.00 149.28 1.49 150.77
open-Graded Premix surfacing, 20mm.
Dismantling of Structures - Lime /Cement
Concrete(By Mechanical Means for items
57 2.4 (ii) B No. 202( b) & ( c)- Prestressed / 661.00 0.0000 0.00 0.0000 0.00 0.0000 0.00 0.000 0.00 0.000 0.00 661.00 6.61 667.61
Reinforced cement concrete grade M-20
& above
Dismantling of Flexible Pavements by
58 2.5 I (A) Manual Means - Bituminous courses 467.00 0.0000 0.00 0.0000 0.00 0.0000 0.00 0.000 0.00 0.000 0.00 467.00 4.67 471.67

Dismantling Kilometre Stone - 5th KM


59 2.10 A stone 255.00 0.0000 0.00 0.0000 0.00 0.0000 0.00 0.000 0.00 0.000 0.00 255.00 2.55 257.55

Excavation in Soil using Hydraulic


60 3.6 Excavator 83.00 0.0000 0.00 0.0000 0.00 0.0000 0.00 0.000 0.00 0.000 0.00 83.00 0.83 83.83
HAULAGE CALCULATION SHEET FOR ROAD WORKS
Item SOR Rate Stone chips /agg Stone Boulder Stone Metal Bitumen Bitumen Emulsion Lime/Filler/soil/pipe Sand Steel Cement Structural Steel Finished Labour Final Rate
Rate Cess (1%)
Sl. No. Cl No.
Quantity Carriage Quantity Carriage Quantity Carriage Quantity Carriage Quantity Carriage Quantity Carriage Quantity Carriage Quantity Carriage Quantity Carriage Quantity Carriage
Cost Cost Cost Cost Cost Cost Cost Cost Cost Cost

Granular Sub-base with Close Graded


62 4.1A Material (Table:- 400-1)-Plant Mix 2384.00 0.768 157.19 0.0000 0.00 0.0000 0.00 0.512 0.00 0.0000 0.00 0.000 0.00 0.000 0.00 2504.72 25.05 2529.77
Method( for grading- II Material)
Concrete M20 Kerb
63 8.1(A) 362.00 0.0000 0.00 0.0000 0.00 0.0000 0.00 0.016 162.00 0.000 0.00 364.56 3.65 368.21
Using Concrete Mixer
64 8.14 Hectometer stone (Precast) 635.00 0.0000 0.00 0.0000 0.00 0.0020 162.00 0.0132 162.00 0.000 0.00 637.46 6.37 643.84
65 8.27 Street Lighting (pole Height 6m) 28985.00 0.00 28985.00 289.85 29274.85
Excavation for Structures - Ordinary soil -
66 3.13 (I) A. 158.00 0.00 158.00 1.58 159.58
Manual Means (Depth upto 3 m)

67 7.5 Reinforced Earth Retaining Wall 0.00


(i) Facing elements of RCC 1529.00 0.0051 162.00 0.180 162.00 0.00 1558.98 15.59 1574.57
Assembling, joining and laying of
(ii) 0.00
reinforcing elements.
With reinforcing elements of synthetic
590.00 0.00 590.00 5.90 595.90
geogrids
PCC 1:3:6 in Foundation (Plain cement
concrete 1:3;6 mix with crushed stone
aggregate 40 mm niminal size
69 9.1 5237.00 0.920 157.19 0.460 0.00 0.2200 162.00 0.00 5417.26 54.17 5471.43
mechanically mixed, placed in foundation
and compacted by vibration including
curing forTreated
Cement 14 days)
Crushed Rock or
combination as per clause 403.2 and
table 400.4in Sub base/ Base (Providing,
laying and spreading Material on a
prepared sub grade, adding the designed
quantity of cement to the spread
70 4.6 Material, mixing in place with rotavator,
grading with the motor grader and
compacting with the road roller at OMC to
achieve the desired unconfined
compressive strength and to form a layer
of sub-base/base.)
(i) For Sub-Base course 3479.00 0.960 157.19 0.3200 0.00 0.040 162.00 3636.38 36.36 3672.75
(ii) For Base course 3073.00 0.480 157.19 0.8000 0.00 0.040 162.00 3154.93 31.55 3186.48
Surface Drains in Soil( Construction of
unlined surface drains of average cross
sectional area 0.40 sqm in soil to specified
lines, grades, levels and dimensions to the
71 3.24 69.00 69.00 0.69 69.69
requirement of clause 301 and 309.
Excavated material to be used in
embankment within a lead of 50 metres
(average lead 25 metres)

72 Non-Sch RAP 1858.00 0.370 157.19 0.037 162.00 1922.09 1922.09

73 8.7B Aluminium Alloy Plate for Over Head Sign 679.00 679.00 6.79 685.79
74 3.23 Seeding and Mulching 126.00 126.00 1.26 127.26
75 8.35 Road Stud 677.00 677.00 6.77 683.77
75 Non sche Utility Duct 835.00 835.00 8.35 843.35
76 4.1A GSB Grading III (plant mix method) 2235.00 0.608 157.190 0.000 0.000 0.000 0.000 0.000 0.000 0.672 0.000 0.000 0.000 0.000 0.000 0.000 0.000 2330.57 23.31 2353.88
77 Non-Sche Sand Pile 1320.00 0.1963 0.0000 1320.00 13.20 1333.20
Finished Rate of Structure Work
HAULAGE CALCULATION SHEET FOR MAJOR BRIDGES

Brick Stone Boulder Aggregate / Stone chips Bitumen Bitumen Emulsion Lime/Filler Sand Steel Cement Structural Steel
Sl. Finished Labour
Cl No. Item SOR Rate Final Rate
No. Carriage Carriage Carriage Carriage Carriage Carriage Carriage Carriage Carriage Carriage Rate Cess (1%)
Quantity Quantity Quantity Quantity Quantity Quantity Quantity Quantity Quantity Quantity
Cost Cost Cost Cost Cost Cost Cost Cost Cost Cost
Excavation for Structures (Ordinary soil)
1 12.1 A (i) with dewatering - Mechanical Means 80.00 0.0000 0.00 0.0000 0.00 0.0000 0.00 0.0000 0.00 0.0000 0.00 0.0000 0.00 80.00 0.80 80.80
Depth upto 3m
2 12.1A (ii) Depth 3m to 6m 103.00 0.0000 0.00 0.0000 0.00 0.0000 0.00 0.0000 0.00 0.0000 0.00 0.0000 0.00 103.00 1.03 104.03
3 12.1A (iii) Depth above 6m 137.00 137.00 1.37 138.37
4 12.3 Sand filling in foundation 2202.00 0.0000 0.00 0.0000 0.00 0.0000 0.00 1.2000 0.00 0.0000 0.00 0.0000 0.00 0.0000 0.00 2202.00 22.02 2224.02
5 12.5 Brick masonry work (1:3) 8390.32 500.00 0.00 0.00 0.1613 162.00 8416.45 84.16 8500.62
6 12.6 Cement Morter 1:6 4298.00 0.0000 0.00 0.0000 0.00 0.0000 0.00 1.3371 0.00 0.0000 0.00 0.2880 162.00 0.0000 0.00 4344.66 43.45 4388.10
7 12.6 Cement Morter 1:3 5945.00 0.0000 0.00 0.0000 0.00 0.0000 0.00 1.0500 0.00 0.0000 0.00 0.5100 162.00 0.0000 0.00 6027.62 60.28 6087.90
8 12.7 Stone Masonary 1:3 5321.00 0.0000 0.00 1.1000 112.00 0.790 157.19 0.0000 0.00 0.0000 0.00 0.3150 0.00 0.0000 0.00 0.1530 162.00 0.0000 0.00 5593.17 55.93 5649.10
9 12.8 A (I) PCC M15 7004.00 0.0000 0.00 0.900 157.19 0.0000 0.00 0.0000 0.00 0.4500 0.00 0.0000 0.00 0.2753 162.00 0.0000 0.00 7190.07 71.90 7261.97
10 12.8 B PCC M20 7776.00 0.0000 0.00 0.900 157.19 0.0000 0.00 0.0000 0.00 0.4500 0.00 0.0000 0.00 0.3440 162.00 0.0000 0.00 7973.20 79.73 8052.93
11 12.8 C RCC M20 (Batching plant) 8184.00 0.0000 0.00 0.900 157.19 0.0000 0.00 0.0000 0.00 0.4500 0.00 0.0000 0.00 0.3472 162.00 0.0000 0.00 8381.72 83.82 8465.53
12 12.8 E RCC M25(Batching plant) 8878.00 0.0000 0.00 0.900 157.19 0.0000 0.00 0.0000 0.00 0.4032 0.00 0.0000 0.00 0.0125 162.00 0.0000 0.00 9021.50 90.21 9111.71
13 12.8 F PCC M30 (Batching plant) 8820.00 0.0000 0.00 0.900 157.19 0.0000 0.00 0.0000 0.00 0.4500 0.00 0.0000 0.00 0.4050 162.00 0.0000 0.00 9027.08 90.27 9117.35
14 12.8 G RCC M30 (Batching plant) 8901.00 0.0000 0.00 0.900 157.19 0.0000 0.00 0.0000 0.00 0.4500 0.00 0.0000 0.00 0.4067 162.00 0.0000 0.00 9108.36 91.08 9199.44
15 12.8 H RCC M35 (Batching plant) 9053.00 0.0000 0.00 0.900 157.19 0.0000 0.00 0.0000 0.00 0.4500 0.00 0.0000 0.00 0.4220 162.00 0.0000 0.00 9262.84 92.63 9355.46
16 12.11 C PCC/RCC in Well Foundation BOTTOM 0.00 0.00
12.11 C (i)
17 PCC Grade M20 8809.00 0.0000 0.00 0.9000 157.19 0.0000 0.00 0.0000 0.00 0.4500 0.00 0.0000 0.00 0.3700 162.00 0.0000 0.00 9010.41 90.10 9100.52
Case-II
12.11 C (ii)
18 PCC Grade M25 9232.00 0.0000 0.00 0.9000 157.19 0.0000 0.00 0.0000 0.00 0.4500 0.00 0.0000 0.00 0.3990 162.00 0.0000 0.00 9438.11 94.38 9532.49
Case-II
12.11 C (iii)
19 PCC Grade M30 9313.00 0.0000 0.00 0.9000 157.19 0.0000 0.00 0.0000 0.00 0.4500 0.00 0.0000 0.00 0.4053 162.00 0.0000 0.00 9520.13 95.20 9615.33
Case-II
12.11 C (iv)
20 PCC Grade M35 9490.00 0.0000 0.00 0.9000 157.19 0.0000 0.00 0.0000 0.00 0.4500 0.00 0.0000 0.00 0.4190 162.00 0.0000 0.00 9699.35 96.99 9796.34
Case-II
21 12.22 Steel Liner 100170.00 0.0000 0.00 0.0000 0.00 0.0000 0.00 0.0000 0.00 0.0000 0.00 1.0500 162.00 100340.10 1003.40 101343.50
22 12.24 Board Cast in Situ RCC M35 (Dia 1000m) 13056.00 0.0000 0.00 0.7065 157.19 0.0000 0.00 0.0000 0.00 0.3533 0.00 0.0000 0.00 0.3289 162.00 0.0000 0.00 13220.34 132.20 13352.54

23 12.25 Board Cast in Situ RCC M35 (Dia 1200m) 17085.00 0.0000 0.00 1.0170 157.19 0.0000 0.00 0.0000 0.00 0.5085 0.00 0.0000 0.00 0.4735 162.00 0.0000 0.00 17321.57 173.22 17494.79

24 12.38 (B) (ii) RCC Pile Cap M25 8898.00 0.0000 0.00 0.9000 157.19 0.0000 0.00 0.0000 0.00 0.4500 0.00 0.0000 0.00 0.3993 162.00 0.0000 0.00 9104.16 91.04 9195.20
25 12.39 Levelling Course Pile Cap M15 6595.00 0.0000 0.00 0.9000 157.19 0.0000 0.00 0.0000 0.00 0.4500 0.00 0.0000 0.00 0.2753 162.00 0.0000 0.00 6781.07 67.81 6848.88
26 12.40 TMT Bar 66702.00 0.0000 0.00 0.0000 0.00 0.0000 0.00 1.0500 162.00 0.0000 0.00 0.0000 0.00 66872.10 668.72 67540.82
27 13.2 pointing 611.00 0.00 0.0032 0.00 0.0015 162.00 611.25 6.11 617.36
28 13.3 Plastering with cement mortar (1:3 ) 1543.00 0.0000 0.00 0.0000 0.00 0.0000 0.00 0.0151 0.00 0.0000 0.00 0.0073 162.00 0.0000 0.00 1544.19 15.44 1559.63
29 13.5 B (p) PCC Grade M20 Height upto 5 M 8225.00 0.0000 0.00 0.9000 157.19 0.0000 0.00 0.0000 0.00 0.4500 0.00 0.0000 0.00 0.3440 162.00 0.0000 0.00 8422.20 84.22 8506.42
13.5 E (p) RCC Grade M20 Height upto 5 M
30 8137.00 0.0000 0.00 0.9000 157.19 0.0000 0.00 0.0000 0.00 0.4500 0.00 0.0000 0.00 0.3472 162.00 0.0000 0.00 8334.72 83.35 8418.06
Case-II
13.5 E
31 RCC M20 (SUBSTRUCTURE)-5-10 M 8433.00 0.0000 0.00 0.9000 157.19 0.0000 0.00 0.0000 0.00 0.450 0.00 0.0000 0.00 0.3472 162.00 0.0000 0.00 8630.71 86.31 8717.02
(q)Case II
13.5 F (p)
32 RCC Substructure M25 Height 5M 9414.00 0.0000 0.00 0.9000 157.19 0.0000 0.00 0.0000 0.00 0.450 0.00 0.0000 0.00 0.4032 162.00 0.0000 0.00 9620.79 96.21 9717.00
Case II
13.5 F (q)
33 RCC Substructure M25 Height 5M-10M 9722.00 0.0000 0.00 0.9000 157.19 0.0000 0.00 0.0000 0.00 0.450 0.00 0.0000 0.00 0.4032 162.00 0.0000 0.00 9928.79 99.29 10028.08
Case II
13.5 F (r)
34 RCC Substructure M25 Height above10M 10184.00 0.9000 157.19 0.450 0.00 0.4032 162.00 10390.79 103.91 10494.70
Case II
13.5 H (p)
35 RCC M35 Height 5M 10094.00 0.0000 0.00 0.9000 157.19 0.0000 0.00 0.0000 0.00 0.450 0.00 0.0000 0.00 0.4220 162.00 0.0000 0.00 10303.84 103.04 10406.87
Case II

RCC M35 Height 5M to 10M 10315.00 0.9000 157.19 0.450 0.00 0.4220 162.00 10524.84 105.25 10630.08

36 13.6 TMT Bar 66780.00 0.0000 0.00 0.0000 0.00 0.0000 0.00 1.0500 162.00 0.0000 0.00 0.0000 0.00 66950.10 669.50 67619.60
37 13.8 Weep Hole 1869.00 0.0000 0.00 0.0000 0.00 0.0000 0.00 0.0018 0.00 0.0000 0.00 0.0009 162.00 0.0000 0.00 1869.15 18.69 1887.84

Back Filling In Abutment, Wing Wall,


38 13.9 A 1867.00 0.0000 0.00 1.2000 157.19 0.0000 0.00 0.0000 0.00 0.0000 0.00 0.0000 0.00 0.0000 0.00 2055.63 20.56 2076.18
Return Wall by Granular Material

Back Filling In Abutment, Wing Wall,


39 13.9 B 2387.00 0.0000 0.00 0.0000 0.00 0.0000 0.00 1.200 0.00 0.0000 0.00 0.0000 0.00 0.0000 0.00 2387.00 23.87 2410.87
Return Wall by Sandy Material

40 13.10 Filter Media 2164.00 0.0000 0.00 1.2000 157.19 0.0000 0.00 0.0000 0.00 0.0000 0.00 0.0000 0.00 0.0000 0.00 2352.63 23.53 2376.15
41 13.14 Elastomeric Bearing 1.25 0.0000 0.00 0.0000 0.00 0.0000 0.00 0.0000 0.00 0.0000 0.00 0.0000 0.00 1.25 0.01 1.26
42 13.16 POT-PTFE bearing 455.00 0.0000 0.00 0.0000 0.00 0.0000 0.00 0.0000 0.00 0.0000 0.00 0.0000 0.00 455.00 4.55 459.55
HAULAGE CALCULATION SHEET FOR MAJOR BRIDGES

Brick Stone Boulder Aggregate / Stone chips Bitumen Bitumen Emulsion Lime/Filler Sand Steel Cement Structural Steel
Sl. Finished Labour
Cl No. Item SOR Rate Final Rate
No. Carriage Carriage Carriage Carriage Carriage Carriage Carriage Carriage Carriage Carriage Rate Cess (1%)
Quantity Quantity Quantity Quantity Quantity Quantity Quantity Quantity Quantity Quantity
Cost Cost Cost Cost Cost Cost Cost Cost Cost Cost
14.1 A case -
43 RCC M25 Superstructure (height 5m) 10219.00 0.0000 0.00 0.9000 157.19 0.0000 0.00 0.0000 0.00 0.452 0.00 0.0000 0.00 0.3996 162.00 0.0000 0.00 10425.21 104.25 10529.46
II( i) a).
14.1 (B)
44 Case -II (ii) RCC T-Beam Height 5M (M25) 10645.00 0.0000 0.00 0.9000 157.19 0.0000 0.00 0.0000 0.00 0.452 0.00 0.0000 0.00 0.3996 162.00 0.0000 0.00 10851.21 108.51 10959.72
(p)
14.1 (B)
45 Case -II (ii) RCC T-Beam Height 10M 11071.00 0.0000 0.00 0.9000 157.19 0.0000 0.00 0.0000 0.00 0.452 0.00 0.0000 0.00 0.3996 162.00 0.0000 0.00 11277.21 112.77 11389.98
(q)
14.1 (B)
46 Case -II (ii) RCC T-Beam Height above 10M 11497.00 0.0000 0.00 0.9000 157.19 0.0000 0.00 0.0000 0.00 0.452 0.00 0.0000 0.00 0.3996 162.00 0.0000 0.00 11703.21 117.03 11820.24
('r)
14.1 (C)
47 Case -II (i) RCC M30 Solid Slab Height 5M 10331.00 0.0000 0.00 0.9000 157.19 0.0000 0.00 0.0000 0.00 0.455 0.00 0.0000 0.00 0.4066 162.00 0.0000 0.00 10538.34 105.38 10643.72
(p)
14.1 (C)
48 Case -II (i) RCC M30 Solid Slab Height 10M 10762.00 0.0000 0.00 0.9000 157.19 0.0000 0.00 0.0000 0.00 0.455 0.00 0.0000 0.00 0.4066 162.00 0.0000 0.00 10969.34 109.69 11079.03
(q)
14.1 (C)
49 Case -II (i) RCC M30 Solid Slab Height 15M 11192.00 0.0000 0.00 0.9000 157.19 0.0000 0.00 0.0000 0.00 0.455 0.00 0.0000 0.00 0.4066 162.00 0.0000 0.00 11399.34 113.99 11513.33
('r)
14.1 (C)
50 Case -II (i) RCC M30 T-Beam Height 5M 10762.00 0.0000 0.00 0.9000 157.19 0.0000 0.00 0.0000 0.00 0.4550 0.00 0.0000 0.00 0.4066 162.00 0.0000 0.00 10969.34 109.69 11079.03
(p)
14.1 (C)
51 Case -II (i) RCC M30 T-Beam Height 10M 11192.00 0.0000 0.00 0.9000 157.19 0.0000 0.00 0.0000 0.00 0.4550 0.00 0.0000 0.00 0.4066 162.00 0.0000 0.00 11399.34 113.99 11513.33
(q)
14.1 (C)
52 Case -II (i) RCC M30 T-Beam Height 15M 11623.00 0.0000 0.00 0.9000 157.19 0.0000 0.00 0.0000 0.00 0.4550 0.00 0.0000 0.00 0.4066 162.00 0.0000 0.00 11830.34 118.30 11948.64
('r)
53 14.2 Supplying, Fitting, Fixing TMT Bar 67881.00 0.0000 0.00 0.0000 0.00 0.0000 0.00 1.0500 162.00 0.0000 0.00 0.0000 0.00 68051.10 680.51 68731.61
54 14.5 Mastic Asphalt(FOR CD WORKS) 407.50 0.0000 0.00 0.0081 157.19 0.00283 162.00 0.0000 0.00 0.00497 0.00 0.0000 0.00 0.0000 0.00 0.0000 0.00 409.23 4.09 413.32
55 14.6 Precast RCC Railing 2094.00 0.0000 0.00 0.0767 157.19 0.0000 0.00 0.0000 0.00 0.039 0.00 0.0180 162.00 0.0347 162.00 0.0000 0.00 2114.60 21.15 2135.74
56 14.9 Drainage Spout 12494.00 0.0000 0.00 0.0000 0.00 0.0000 0.00 0.0000 0.00 0.0000 0.00 0.0000 0.00 12494.00 124.94 12618.94
57 14.10 PCC M15 Grade Levelling Course 6736.00 0.0000 0.00 0.9000 157.19 0.0000 0.00 0.0000 0.00 0.450 0.00 0.0000 0.00 0.2753 162.00 0.0000 0.00 6922.07 69.22 6991.29
58 14.11 RCC Approach Slab 12167.00 0.0000 0.00 0.9000 157.19 0.0000 0.00 0.0000 0.00 0.450 0.00 0.0500 162.00 0.4067 162.00 0.0000 0.00 12382.46 123.82 12506.28
59 14.22 Strip Seal Expansion Joint 14462.00 0.0000 0.00 0.0000 0.00 0.0000 0.00 0.0000 0.00 0.0000 0.00 0.0000 0.00 14462.00 144.62 14606.62
60 15.1 Lying Boulder 1793.00 0.0000 0.00 1.00 180.04 0.0000 0.00 0.0000 0.00 0.0000 0.00 0.0000 0.00 0.0000 0.00 1973.04 19.73 1992.77
61 15.4 A laying Pitching on slopes 1793.00 1.00 180.04 1973.04 19.73 1992.77
Providing and laying Filter material
62 15.5 underneath pitching in slopes complete as 2281.00 0.0000 0.00 1.2000 180.0425 0.0000 0.00 0.0000 0.00 0.0000 0.00 0.0000 0.00 0.0000 0.00 2497.05 24.97 2522.02
per drawing and Technical specification
63 15.8 (A) Laying Flooring by Rubble stone 6391.00 1.0000 180.04 0.3465 0.00 0.1683 162.00 6598.31 65.98 6664.29
64 15.8 (B) Laying Flooring 9408.00 0.0000 0.00 1.1970 157.19 0.0000 0.00 0.0000 0.00 0.599 0.00 0.0000 0.00 0.3662 162.00 0.0000 0.00 9655.48 96.55 9752.04
65 15.10 (B) Curtain Wall 7004.00 0.0000 0.00 0.9000 157.19 0.0000 0.00 0.0000 0.00 0.450 0.00 0.0000 0.00 0.2753 162.00 0.0000 0.00 7190.07 71.90 7261.97
66 15.11 Flexible Apron 1819.00 1.0000 180.04 1999.04 19.99 2019.03
Supplying, Febrication & Erection of
67 Non-Sch 108712.00 0.0000 0.00 0.0000 0.00 0.0000 0.00 0.0000 0.00 0.0000 0.00 1.0500 162.00 108882.10 1088.82 109970.92
Structural Steel
Removal of existing cement concrete
68 16.1 100.00 100.00 1.00 101.00
wearing coat
69 16.2 Removal of existing asphaltic wearing coat 75.00 75.00 0.75 75.75

Removal of defective concrete, cleaning


70 16.9 375.00 0.0150 157.19 0.0150 0.00 0.0120 162.00 379.30 3.79 383.09
the surface thoroughly
Applying pre-packed cement based
71 16.10 271.00 271.00 2.71 273.71
polymer mortar
Eproxy bonding of new concrete to old
72 16.11 1595.00 1595.00 15.95 1610.95
concrete
73 16.17 Replacement of Expansion Joints 4453.00 0.2700 157.19 0.1350 0.00 0.1220 162.00 4515.21 45.15 4560.36
Replacement of Damaged Concrete
74 16.18 173.00 173.00 1.73 174.73
Railing.
75 Non-Sch Reinforced Cement Concrete Crash Barrier 4603.00 0.270 157.19 0.1350 0.00 0.0280 162.00 0.1290 162.00 4670.88 46.71 4717.58
14.18 Filler joint 0.00 0.00 0.00
Providing & fixing 2 mm thick corrugated
76 14.18 (i) 2009.00 2009.00 20.09 2029.09
copper plate in expansion joint
HAULAGE CALCULATION SHEET FOR MAJOR BRIDGES

Brick Stone Boulder Aggregate / Stone chips Bitumen Bitumen Emulsion Lime/Filler Sand Steel Cement Structural Steel
Sl. Finished Labour
Cl No. Item SOR Rate Final Rate
No. Carriage Carriage Carriage Carriage Carriage Carriage Carriage Carriage Carriage Carriage Rate Cess (1%)
Quantity Quantity Quantity Quantity Quantity Quantity Quantity Quantity Quantity Quantity
Cost Cost Cost Cost Cost Cost Cost Cost Cost Cost
Providing & fixing 20 mm thick
77 14.18 (ii) compressible fibre board in expansion 684.00 684.00 6.84 690.84
joint
Providing and fixing in position 20 mm
78 14.18 (iii) 389.00 389.00 3.89 392.89
thick premoulded joint filler
Providing and filling joint sealing
79 14.18 (iv) 19.00 0.0001 162.00 0.0010 0.00 19.01 0.19 19.20
compound
80 15.2 Boulder Apron Laid in Wire Crates 3572.00 1.0000 180.04 3752.04 37.52 3789.56
13.5 G RCC Grade M30 0.00 0.00 0.00
81 13.5 G (p) Height upto 5m 9461.00 0.9000 157.19 0.4550 0.00 0.4067 162.00 9668.35 96.68 9765.03
82 13.5 G (q) Height 5m to 10m 9727.00 0.9000 157.19 0.4550 0.00 0.4067 162.00 9934.35 99.34 10033.69
83 13.5 G (r) Height above 10m 10106.00 0.9000 157.19 0.4550 0.00 0.4067 162.00 10313.35 103.13 10416.48
13.5 a (p) PCC Grade M15 Height upto 5 M 7410.00 0.0000 0.00 0.9000 157.19 0.0000 0.00 0.0000 0.00 0.4500 0.00 0.0000 0.00 0.2753 162.00 0.0000 0.00 7596.08 75.96 7672.04
Excavation for Structures (Ordinary soil)
12.1 I . B .
84 with dewatering - Mechanical Means 63.00 63.00 0.63 63.63
(b).(i)
Depth upto 3m

12.1 I . B .
85 Depth 3m to 6m 72.00 72.00 0.72 72.72
(b).(i)
Supplying, fitting and fixing in position
86 13.11 true to line and level cast steel rocker 1168.00 1168.00 11.68 1179.68
bearing
Supplying, fitting and fixing in position
87 13.12 true to line and level forged steel roller 1459.00 1459.00 14.59 1473.59
bearing
Curtain Wall-Stone masonry in cement
88 15.10(A) 5309.00 1.1000 180.04 0.7900 157.19 0.3150 0.00 0.1530 162.00 5656.01 56.56 5712.57
mortar (1:3)
14.1 (E)
89 Case -II (ii) PSC M40 T-Beam Height upto 5M 11424.00 0.9000 157.19 0.4500 0.00 0.4300 162.00 11635.13 116.35 11751.48
('p)

14.1 (F) (i)


90 PSC M45 For solid slab Height upto 5M 11310.00 0.9000 157.19 0.4500 0.00 0.4650 162.00 11526.80 115.27 11642.07
('p)

High tensile steel wires/strands including


all accessories for stressing, stressing
91 14.3 256357.00 0.3316 162.00 256410.71 2564.11 258974.82
operations and grouting complete as per
drawing and Technical Specifications

Providing and laying Cement concrete


92 14.4 wearing coat M-30 grade 13731.00 0.9000 157.19 0.4550 0.00 0.0750 162.00 0.4066 162.00 13950.49 139.50 14089.99

Pile load test on single vertical pile in


93 12.37 0.00
accordance with IS:2911(Part-IV)
i) Initial and Routine load test 363.00 363.00 3.63 366.63
ii Lateral load test 6050.00 6050.00 60.50 6110.50
14.1 (F) (i)
94 PSC M50 For solid slab Height upto 5M 13608.00 0.9000 157.19 0.4500 0.00 0.4650 162.00 13824.80 138.25 13963.05
('p)
Providing and laying Pitching on slopes laid
over prepared filter media including
boulder apron laid dry in front of toe of
95 15.4B embankment complete as per drawing 7144.00 0.9000 157.19 0.4500 0.00 0.2753 162.00 7330.07 73.30 7403.37
and Technical specifications ( Cement
Concrete Blocks of size 0.3x0.3 x0.3 m cast
in cement concrete of Grade M15)

PSC M40 (cast-in-situ box girder, segment


14.1E Case
96 construction and balanced cantilever) 12817.00 0.9000 157.19 0.4500 0.00 0.4300 162.00 13028.13 130.28 13158.41
II
Height upto 5M

PSC M40 (cast-in-situ box girder, segment


97 construction and balanced cantilever) 13745.00 0.9000 157.19 0.4500 0.00 0.4300 162.00 13956.13 139.56 14095.69
Height 5-10 M

97 12.38 (B) (ii) RCC Pile Cap M30 8974.00 0.0000 0.0000 0.0000 0.0000 0.9000 157.1904 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.4500 0.0000 0.0000 0.0000 0.3993 162.0000 0.0000 0.0000 9180.16 91.80 9271.96
14.1 (C)
98 Case -II (i) RCC M35 T-Beam Height 5M 10813.00 0.0000 0.00 0.9000 157.19 0.0000 0.00 0.0000 0.00 0.4500 0.00 0.0000 0.00 0.4220 162.00 0.0000 0.00 11022.84 110.23 11133.06
('r)
13.5 H (p)
99 RCC M35 Height 5M to 10M 10645.00 0.9000 157.19 0.450 0.00 0.4220 162.00 10854.84 108.55 10963.38
Case II
HAULAGE CALCULATION SHEET FOR MINOR BRIDGES & SMALL CULVERTS

Aggregate / Stone
Brick/pipe Stone Boulder Bitumen Bitumen Emulsion Lime/Filler Sand Steel Cement Structural Steel
chips Finished Labour
Sl. No. Cl No. Item SOR Rate Final Rate
Carriage Carriage Carriage Carriage Carriage Carriage Carriage Carriage Carriage Carriage Rate Cess (1%)
Quantity Quantity Quantity Quantity Quantity Quantity Quantity Quantity Quantity Quantity
Cost Cost Cost Cost Cost Cost Cost Cost Cost Cost
1 12.1 A (i) Excavation for Structures 76.80 0.0000 0.00 0.0000 0.00 0.0000 0.00 0.0000 0.00 0.0000 0.00 0.0000 0.00 76.80 0.77 77.57
2 12.1A (ii) Depth 3m to 6m 98.88 0.0000 0.00 0.0000 0.00 0.0000 0.00 0.0000 0.00 0.0000 0.00 0.0000 0.00 98.88 0.99 99.87
3 12.1A (iii) Depth above 6m 131.52 131.52 1.32 132.84
4 12.3 Sand filling in foundation 2113.92 0.0000 0.00 0.0000 0.00 0.0000 0.00 1.2000 0.00 0.0000 0.00 0.0000 0.00 0.0000 0.00 2113.92 21.14 2135.06
5 12.5 Brick masonry work (1:3) 8054.71 500.00 0.00 0.00 0.1613 162.00 8080.84 80.81 8161.65
6 12.6 Cement Morter 1:6 4126.08 0.0000 0.00 0.0000 0.00 0.0000 0.00 1.3371 0.00 0.0000 0.00 0.2880 162.00 0.0000 0.00 4172.74 41.73 4214.46
7 12.6 Cement Morter 1:3 5707.20 0.0000 0.00 0.0000 0.00 0.0000 0.00 1.0500 0.00 0.0000 0.00 0.5100 162.00 0.0000 0.00 5789.82 57.90 5847.72
8 12.7 Stone Masonary 1:3 (CR) 5108.16 0.0000 0.00 1.1000 112.00 0.790 157.19 0.0000 0.00 0.0000 0.00 0.3150 0.00 0.0000 0.00 0.1530 162.00 0.0000 0.00 5380.33 53.80 5434.13
9 12.8 A PCC M15 6723.84 0.0000 0.00 0.900 157.19 0.0000 0.00 0.0000 0.00 0.4500 0.00 0.0000 0.00 0.2753 162.00 0.0000 0.00 6909.91 69.10 6979.01
10 12.8 B PCC M20 7464.96 0.0000 0.00 0.900 157.19 0.0000 0.00 0.0000 0.00 0.4500 0.00 0.0000 0.00 0.3440 162.00 0.0000 0.00 7662.16 76.62 7738.78
11 12.8 C RCC M20 (Batching plant) 7856.64 0.0000 0.00 0.900 157.19 0.0000 0.00 0.0000 0.00 0.4500 0.00 0.0000 0.00 0.3472 162.00 0.0000 0.00 8054.36 80.54 8134.90
12 12.8 E RCC M25(Batching plant) 8522.88 0.0000 0.00 0.900 157.19 0.0000 0.00 0.0000 0.00 0.4032 0.00 0.0000 0.00 0.0125 162.00 0.0000 0.00 8666.38 86.66 8753.04
13 12.8 F PCC M30 (Batching plant) 8467.20 0.0000 0.00 0.900 157.19 0.0000 0.00 0.0000 0.00 0.4500 0.00 0.0000 0.00 0.4050 162.00 0.0000 0.00 8674.28 86.74 8761.02
14 12.8 G RCC M30 (Batching plant) 8544.96 0.0000 0.00 0.900 157.19 0.0000 0.00 0.0000 0.00 0.4500 0.00 0.0000 0.00 0.4067 162.00 0.0000 0.00 8752.32 87.52 8839.84
15 12.8 H RCC M35 (Batching plant) 8690.88 0.0000 0.00 0.900 157.19 0.0000 0.00 0.0000 0.00 0.4500 0.00 0.0000 0.00 0.4220 162.00 0.0000 0.00 8900.72 89.01 8989.72
16 12.11 C PCC/RCC in Well Foundation BOTTOM 0.00 0.00 0.00
12.11 C (i)
17 PCC Grade M20 8456.64 0.0000 0.00 0.9000 157.19 0.0000 0.00 0.0000 0.00 0.4500 0.00 0.0000 0.00 0.3700 162.00 0.0000 0.00 8658.05 86.58 8744.63
Case-II
12.11 C (ii)
18 PCC Grade M25 8862.72 0.0000 0.00 0.9000 157.19 0.0000 0.00 0.0000 0.00 0.4500 0.00 0.0000 0.00 0.3990 162.00 0.0000 0.00 9068.83 90.69 9159.52
Case-II
12.11 C (iii)
19 PCC Grade M30 8940.48 0.0000 0.00 0.9000 157.19 0.0000 0.00 0.0000 0.00 0.4500 0.00 0.0000 0.00 0.4053 162.00 0.0000 0.00 9147.61 91.48 9239.09
Case-II
12.11 C (iv)
20 PCC Grade M35 9110.40 0.0000 0.00 0.9000 157.19 0.0000 0.00 0.0000 0.00 0.4500 0.00 0.0000 0.00 0.4190 162.00 0.0000 0.00 9319.75 93.20 9412.95
Case-II
21 12.22 Steel Liner 96163.20 0.0000 0.00 0.0000 0.00 0.0000 0.00 0.0000 0.00 0.0000 0.00 1.0500 162.00 96333.30 963.33 97296.63

22 12.24 Board Cast in Situ RCC M35 (Dia 1000m) 12533.76 0.0000 0.00 0.7065 157.19 0.0000 0.00 0.0000 0.00 0.3533 0.00 0.0000 0.00 0.3289 162.00 0.0000 0.00 12698.10 126.98 12825.08

23 12.25 Board Cast in Situ RCC M35 (Dia 1200m) 16401.60 0.0000 0.00 1.0170 157.19 0.0000 0.00 0.0000 0.00 0.5085 0.00 0.0000 0.00 0.4735 162.00 0.0000 0.00 16638.17 166.38 16804.55

24 12.38 (B) (ii) RCC Pile Cap M25 8542.08 0.0000 0.00 0.9000 157.19 0.0000 0.00 0.0000 0.00 0.4500 0.00 0.0000 0.00 0.3993 162.00 0.0000 0.00 8748.24 87.48 8835.72

25 12.39 Levelling Course Pile Cap M15 6331.20 0.0000 0.00 0.9000 157.19 0.0000 0.00 0.0000 0.00 0.4500 0.00 0.0000 0.00 0.2753 162.00 0.0000 0.00 6517.27 65.17 6582.44
26 12.40 TMT Bar 64033.92 0.0000 0.00 0.0000 0.00 0.0000 0.00 1.0500 162.00 0.0000 0.00 0.0000 0.00 64204.02 642.04 64846.06
27 13.2 pointing 586.56 0.00 0.0032 0.00 0.0015 162.00 586.81 5.87 592.68
28 13.3 Plastering with cement mortar (1:3 ) 1481.28 0.0000 0.00 0.0000 0.00 0.0000 0.00 0.0151 0.00 0.0000 0.00 0.0073 162.00 0.0000 0.00 1482.47 14.82 1497.29
29 13.5 B (p) PCC Grade M20 Height upto 5 M 7896.00 0.0000 0.00 0.9000 157.19 0.0000 0.00 0.0000 0.00 0.4500 0.00 0.0000 0.00 0.3440 162.00 0.0000 0.00 8093.20 80.93 8174.13
13.5 E (p) RCC Grade M20 Height upto 5 M
30 7811.52 0.0000 0.00 0.9000 157.19 0.0000 0.00 0.0000 0.00 0.4500 0.00 0.0000 0.00 0.3472 162.00 0.0000 0.00 8009.24 80.09 8089.33
Case-II
13.5 E
31 RCC M20 (SUBSTRUCTURE)-5-10 M 8095.68 0.0000 0.00 0.9000 157.19 0.0000 0.00 0.0000 0.00 0.450 0.00 0.0000 0.00 0.3472 162.00 0.0000 0.00 8293.39 82.93 8376.33
(q)Case II
13.5 F (p)
32 RCC Substructure M25 Height 5M 9037.44 0.0000 0.00 0.9000 157.19 0.0000 0.00 0.0000 0.00 0.450 0.00 0.0000 0.00 0.4032 162.00 0.0000 0.00 9244.23 92.44 9336.67
Case II
13.5 F (q)
33 RCC Substructure M25 Height 5M-10M 9333.12 0.0000 0.00 0.9000 157.19 0.0000 0.00 0.0000 0.00 0.450 0.00 0.0000 0.00 0.4032 162.00 0.0000 0.00 9539.91 95.40 9635.31
Case II
13.5 F (r) RCC Substructure M25 Height
34 9776.64 0.9000 157.19 0.450 0.00 0.4032 162.00 9983.43 99.83 10083.26
Case II above10M
13.5 H (p)
35 RCC M35 Height 5M 9690.24 0.0000 0.00 0.9000 157.19 0.0000 0.00 0.0000 0.00 0.450 0.00 0.0000 0.00 0.4220 162.00 0.0000 0.00 9900.08 99.00 9999.08
Case II
36 13.6 TMT Bar 64108.80 0.0000 0.00 0.0000 0.00 0.0000 0.00 1.0500 162.00 0.0000 0.00 0.0000 0.00 64278.90 642.79 64921.69
37 13.8 Weep Hole 1794.24 0.0000 0.00 0.0000 0.00 0.0000 0.00 0.0018 0.00 0.0000 0.00 0.0009 162.00 0.0000 0.00 1794.39 17.94 1812.33
Back Filling In Abutment, Wing Wall,
38 13.9 A 1792.32 0.0000 0.00 1.2000 157.19 0.0000 0.00 0.0000 0.00 0.0000 0.00 0.0000 0.00 0.0000 0.00 1980.95 19.81 2000.76
Return Wall by Granular Material

Back Filling In Abutment, Wing Wall,


39 13.9 B 2291.52 0.0000 0.00 0.0000 0.00 0.0000 0.00 1.200 0.00 0.0000 0.00 0.0000 0.00 0.0000 0.00 2291.52 22.92 2314.44
Return Wall by Sandy Material

40 13.10 Filter Media 2077.44 0.0000 0.00 1.2000 157.19 0.0000 0.00 0.0000 0.00 0.0000 0.00 0.0000 0.00 0.0000 0.00 2266.07 22.66 2288.73
41 13.14 Elastomeric Bearing 1.20 0.0000 0.00 0.0000 0.00 0.0000 0.00 0.0000 0.00 0.0000 0.00 0.0000 0.00 1.20 0.01 1.21
42 13.16 POT-PTFE bearing 436.80 0.0000 0.00 0.0000 0.00 0.0000 0.00 0.0000 0.00 0.0000 0.00 0.0000 0.00 436.80 4.37 441.17
HAULAGE CALCULATION SHEET FOR MINOR BRIDGES & SMALL CULVERTS

Aggregate / Stone
Brick/pipe Stone Boulder Bitumen Bitumen Emulsion Lime/Filler Sand Steel Cement Structural Steel
chips Finished Labour
Sl. No. Cl No. Item SOR Rate Final Rate
Carriage Carriage Carriage Carriage Carriage Carriage Carriage Carriage Carriage Carriage Rate Cess (1%)
Quantity Quantity Quantity Quantity Quantity Quantity Quantity Quantity Quantity Quantity
Cost Cost Cost Cost Cost Cost Cost Cost Cost Cost
14.1 A case -
43 RCC M25 Superstructure (height 5m) 9810.24 0.0000 0.00 0.9000 157.19 0.0000 0.00 0.0000 0.00 0.452 0.00 0.0000 0.00 0.3996 162.00 0.0000 0.00 10016.45 100.16 10116.61
II( i) a).
14.1 (B)
44 Case -II (ii) RCC T-Beam Height 5M (M25) 10219.20 0.0000 0.00 0.9000 157.19 0.0000 0.00 0.0000 0.00 0.452 0.00 0.0000 0.00 0.3996 162.00 0.0000 0.00 10425.41 104.25 10529.66
(p)
14.1 (B)
45 Case -II (ii) RCC T-Beam Height 10M 10628.16 0.0000 0.00 0.9000 157.19 0.0000 0.00 0.0000 0.00 0.452 0.00 0.0000 0.00 0.3996 162.00 0.0000 0.00 10834.37 108.34 10942.71
(q)
14.1 (B)
46 Case -II (ii) RCC T-Beam Height above 10M 11037.12 0.0000 0.00 0.9000 157.19 0.0000 0.00 0.0000 0.00 0.452 0.00 0.0000 0.00 0.3996 162.00 0.0000 0.00 11243.33 112.43 11355.76
('r)
14.1 (C)
47 Case -II (i) RCC M30 Solid Slab Height 5M 9917.76 0.0000 0.00 0.9000 157.19 0.0000 0.00 0.0000 0.00 0.455 0.00 0.0000 0.00 0.4066 162.00 0.0000 0.00 10125.10 101.25 10226.35
(p)
14.1 (C)
48 Case -II (i) RCC M30 Solid Slab Height 10M 10331.52 0.0000 0.00 0.9000 157.19 0.0000 0.00 0.0000 0.00 0.455 0.00 0.0000 0.00 0.4066 162.00 0.0000 0.00 10538.86 105.39 10644.25
(q)
14.1 (C)
49 Case -II (i) RCC M30 Solid Slab Height 15M 10744.32 0.0000 0.00 0.9000 157.19 0.0000 0.00 0.0000 0.00 0.455 0.00 0.0000 0.00 0.4066 162.00 0.0000 0.00 10951.66 109.52 11061.18
('r)
14.1 (C)
50 Case -II (i) RCC M30 T-Beam Height 5M 10331.52 0.0000 0.00 0.9000 157.19 0.0000 0.00 0.0000 0.00 0.4550 0.00 0.0000 0.00 0.4066 162.00 0.0000 0.00 10538.86 105.39 10644.25
(p)
14.1 (C)
51 Case -II (i) RCC M30 T-Beam Height 10M 10744.32 0.0000 0.00 0.9000 157.19 0.0000 0.00 0.0000 0.00 0.4550 0.00 0.0000 0.00 0.4066 162.00 0.0000 0.00 10951.66 109.52 11061.18
(q)
14.1 (C)
52 Case -II (i) RCC M30 T-Beam Height 15M 11158.08 0.0000 0.00 0.9000 157.19 0.0000 0.00 0.0000 0.00 0.4550 0.00 0.0000 0.00 0.4066 162.00 0.0000 0.00 11365.42 113.65 11479.07
('r)
53 14.2 Supplying, Fitting, Fixing TMT Bar 65165.76 0.0000 0.00 0.0000 0.00 0.0000 0.00 1.0500 162.00 0.0000 0.00 0.0000 0.00 65335.86 653.36 65989.22
54 14.5 Mastic Asphalt(FOR CD WORKS) 391.20 0.0000 0.00 0.0081 157.19 0.00283 162.00 0.0000 0.00 0.00497 0.00 0.0000 0.00 0.0000 0.00 0.0000 0.00 392.93 3.93 396.86
55 14.6 Precast RCC Railing 2010.24 0.0000 0.00 0.0767 157.19 0.0000 0.00 0.0000 0.00 0.039 0.00 0.0180 162.00 0.0347 162.00 0.0000 0.00 2030.84 20.31 2051.15
56 14.9 Drainage Spout 11994.24 0.0000 0.00 0.0000 0.00 0.0000 0.00 0.0000 0.00 0.0000 0.00 0.0000 0.00 11994.24 119.94 12114.18
57 14.10 PCC M15 Grade Levelling Course 6466.56 0.0000 0.00 0.9000 157.19 0.0000 0.00 0.0000 0.00 0.450 0.00 0.0000 0.00 0.2753 162.00 0.0000 0.00 6652.63 66.53 6719.16
58 14.11 RCC Approach Slab 11680.32 0.0000 0.00 0.9000 157.19 0.0000 0.00 0.0000 0.00 0.450 0.00 0.0500 162.00 0.4067 162.00 0.0000 0.00 11895.78 118.96 12014.73
59 14.22 Strip Seal Expansion Joint 13883.52 0.0000 0.00 0.0000 0.00 0.0000 0.00 0.0000 0.00 0.0000 0.00 0.0000 0.00 13883.52 138.84 14022.36
60 15.1 Lying Boulder 1721.28 0.0000 0.00 1.00 180.04 0.0000 0.00 0.0000 0.00 0.0000 0.00 0.0000 0.00 0.0000 0.00 1901.32 19.01 1920.34
61 15.4 A laying Pitching on slopes 1721.28 1.00 180.04 1901.32 19.01 1920.34
Providing and laying Filter material
underneath pitching in slopes complete
62 15.5 2189.76 0.0000 0.00 1.2000 180.0425 0.0000 0.00 0.0000 0.00 0.0000 0.00 0.0000 0.00 0.0000 0.00 2405.81 24.06 2429.87
as per drawing and Technical
specification
63 15.8 (A) Laying Flooring by Rubble stone 6135.36 1.0000 180.04 0.3465 0.00 0.1683 162.00 6342.67 63.43 6406.09
64 15.8 (B) Laying Flooring 9031.68 0.0000 0.00 1.1970 157.19 0.0000 0.00 0.0000 0.00 0.599 0.00 0.0000 0.00 0.3662 162.00 0.0000 0.00 9279.16 92.79 9371.95
65 15.10 (B) Curtain Wall 6723.84 0.0000 0.00 0.9000 157.19 0.0000 0.00 0.0000 0.00 0.450 0.00 0.0000 0.00 0.2753 162.00 0.0000 0.00 6909.91 69.10 6979.01
66 15.11 Flexible Apron 1746.24 1.0000 180.04 1926.28 19.26 1945.55
Supplying, Febrication & Erection of
67 Non-Sch 104363.52 0.0000 0.00 0.0000 0.00 0.0000 0.00 0.0000 0.00 0.0000 0.00 1.0500 162.00 104533.62 1045.34 105578.96
Structural Steel
Reinforced Cement Concrete Crash
68 Non-Sch 4418.88 0.270 157.19 0.1350 0.00 0.0280 162.00 0.1290 162.00 4486.76 44.87 4531.62
Barrier
14.18 Filler joint 0.00 0.00 0.00
Providing & fixing 2 mm thick corrugated
69 14.18 (i) 1928.64 1928.64 19.29 1947.93
copper plate in expansion joint
Providing & fixing 20 mm thick
70 14.18 (ii) compressible fibre board in expansion 656.64 656.64 6.57 663.21
joint
Providing and fixing in position 20 mm
71 14.18 (iii) 373.44 373.44 3.73 377.17
thick premoulded joint filler
Providing and filling joint sealing
72 14.18 (iv) 18.24 0.0001 162.00 0.0010 0.00 18.25 0.18 18.44
compound
73 15.2 Boulder Apron Laid in Wire Crates 3429.12 1.0000 180.04 3609.16 36.09 3645.25
HAULAGE CALCULATION SHEET FOR MINOR BRIDGES & SMALL CULVERTS

Aggregate / Stone
Brick/pipe Stone Boulder Bitumen Bitumen Emulsion Lime/Filler Sand Steel Cement Structural Steel
chips Finished Labour
Sl. No. Cl No. Item SOR Rate Final Rate
Carriage Carriage Carriage Carriage Carriage Carriage Carriage Carriage Carriage Carriage Rate Cess (1%)
Quantity Quantity Quantity Quantity Quantity Quantity Quantity Quantity Quantity Quantity
Cost Cost Cost Cost Cost Cost Cost Cost Cost Cost

13.5 G RCC Grade M30 0.00 0.00 0.00


74 13.5 G (p) Height upto 5m 9082.56 0.9000 157.19 0.4550 0.00 0.4067 162.00 9289.91 92.90 9382.81
75 13.5 G (q) Height 5m to 10m 9337.92 0.9000 157.19 0.4550 0.00 0.4067 162.00 9545.27 95.45 9640.72
76 13.5 G (r) Height above 10m 9701.76 0.9000 157.19 0.4550 0.00 0.4067 162.00 9909.11 99.09 10008.20
13.5 a (p) PCC Grade M15 Height upto 5 M 7113.60 0.9000 157.19 0.4500 0.00 0.2753 162.00 7299.68 73.00 7372.67
Brick masonry work in 1:3 in sub-
13.1 8271.36 500.0 0.00 0.2520 0.00 0.1224 162.00 8291.19 82.91 8374.10
structure
Excavation for Structures (Ordinary soil)
12.1 I . B .
84 with dewatering - Mechanical Means 60.48 60.48 0.60 61.08
(b).(i)
Depth upto 3m

12.1 I . B .
85 Depth 3m to 6m 69.12 69.12 0.69 69.81
(b).(i)
Supplying, fitting and fixing in position
86 13.11 true to line and level cast steel rocker 1121.28 1121.28 11.21 1132.49
bearing
Supplying, fitting and fixing in position
87 13.12 true to line and level forged steel roller 1400.64 1400.64 14.01 1414.65
bearing
Curtain Wall-Stone masonry in cement
88 15.10(A) 5096.64 1.1000 180.04 0.7900 157.19 0.3150 0.00 0.1530 162.00 5443.65 54.44 5498.09
mortar (1:3)
14.1 (E)
89 Case -II (ii) PSC M40 T-Beam Height upto 5M 10967.04 0.9000 157.19 0.4500 0.00 0.4300 162.00 11178.17 111.78 11289.95
('p)
Removal of existing cement concrete
90 16.1 96.00 96.00 0.96 96.96
wearing coat
16.17 Replacement of Expansion Joints
91 4274.88 0.2700 157.19 0.1350 0.00 0.1220 162.00 4337.09 43.37 4380.46
complete as per drawings
16.18 Replacement of Damaged Concrete
92 166.08 166.08 1.66 167.74
Railing.
Providing and laying Cement concrete
93 14.4 13181.76 0.9000 157.19 0.4550 0.00 0.0750 162.00 0.4066 162.00 13401.25 134.01 13535.26
wearing coat M-30 grade
94 15.8 (A) Laying Flooring by Rubble stone 6135.36 1.0000 180.04 0.3465 0.00 0.1683 162.00 6342.67 63.43 6406.09

Back Filling In Abutment, Wing Wall,


95 Non-Sch 1601.28 1.2000 180.04 1817.33 18.17 1835.50
Return Wall by Granular Material

14.1 (F) (i)


90 PSC M45 For solid slab Height upto 5M 10857.60 0.9000 180.04 0.4300 0.00 0.4650 162.00 11094.97 110.95 11205.92
('p)

Removal of defective concrete, cleaning


70 16.9 360.00 0.0150 157.19 0.0150 0.00 0.0120 162.00 364.30 3.64 367.94
the surface thoroughly
Reinforced Cement Concrete Crash
75 Non-Sch 4418.88 0.270 180.04 0.1350 0.00 0.0280 162.00 0.1290 162.00 4492.93 44.93 4537.85
Barrier
Providing and laying Cement concrete
76 14.4 wearing coat M-30 grade 13181.76 0.9000 157.19 0.4550 0.00 0.0750 162.00 0.4066 162.00 13401.25 134.01 13535.26

High tensile steel wires/strands including


all accessories for stressing, stressing
77 14.3 246102.72 0.3316 162.00 246156.43 2461.56 248618.00
operations and grouting complete as per
drawing and Technical Specifications

78 12.38 (B) (ii) RCC Pile Cap M30 8615.04 0.0000 0.0000 0.0000 0.0000 0.9000 157.1904 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.4500 0.0000 0.0000 0.0000 0.3993 162.0000 0.0000 0.0000 8821.20 88.21 8909.41
Patching of damaged concrete surface
with polymer concrete and curing
compounds, initiator and promoter,
79 16.6 available in present formulations, to be 4431.36 4431.36 44.31 4475.67
applied as per instructions of
manufacturer and as approved by the
Engineer.
80 12.7 Stone Masonary 1:3 (RR) 4224.96 0.0000 0.00 1.1000 112.00 0.790 157.19 0.0000 0.00 0.0000 0.00 0.3150 0.00 0.0000 0.00 0.1581 162.00 0.0000 0.00 4497.95 44.98 4542.93
13.5 H (p)
81 RCC M35 Height 5M to 10M 9902.40 0.0000 0.0000 0.0000 0.0000 0.9000 157.1904 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.4500 0.0000 0.0000 0.0000 0.4220 162.0000 0.0000 0.0000 10112.24 101.12 10213.36
Case II
Volume-VII: Cost Estimates
Abstract of Cost
GENERAL ABSTRACT OF COST
Bilasipara-Jalukbari Road (PKG-5: Km 48.655 to Km 67.556 ) & (km 0.000 km to km1.071)
Length of Road (km) : 18.901
Length of CD & Bridge works (km) : 1.795
Length of Pavement excluding CD works (km) : 17.106

COST PER KM. OF


TOTAL COST % of Total Civil
Sl No DESCRIPTION OF WORKS TOTAL ROAD LENGTH
(IN Cr.) Works Cost
(IN Cr.)

A. ROAD WORKS
1 Site Clearance 1.11 0.06 0.26%
2 Earthwork, Erosion Control 33.82 1.79 8.00%
3 Sub-Base & Base Courses 48.16 2.55 11.40%
4 Bituminous surface 36.28 1.92 8.59%
5 Traffic signs, Road marking & other road appurtenances 8.42 0.45 1.99%
6 Drainage & Protection Works
a) RCC Cover Drain 5.46 0.29 1.29%
b) RE WALL 42.89 2.27 10.15%
c) RR Masonry Chute Drain 0.39 0.02 0.09%
d) Retaining Wall 3.93 0.21 0.93%
e) Toe Wall 2.03 0.11 0.48%
f) Ground Improvement Works (Sand Pile) 7.10 0.38 1.68%
7 Project Facilities
a) Bus Bay with passenger shelter 1.34 0.07 0.32%
8 Junction 1.37 0.07 0.32%
9 Service Road 6.55 0.35 1.55%
10 Utility Duct 4.46 0.24 1.06%
Total for Road Works= 203.31 10.78 48.12%
B. BRIDGES, CULVERTS & ROB
11 Major Bridges 12.58 0.67 2.98%
12 Minor Bridges 52.75 2.79 12.48%
13 ROB 117.29 6.21 27.76%
14 VUP 8.17 0.43 1.93%
15 Culvert 28.43 1.50 6.73%
16 Repairing & Rehabilitation of Bridges 0.004 0.0002 0.00%
Total for Structure Works= 219.22 11.60 51.88%
C. Cost of Civil Works in Cr. 422.53 22.35
Cost Put to the Tender 422.53
D. Maintenance for 5 years , i.e 2.5% on Civil cost ( C ) 10.56
E. GST @ 12% of ( C ) 50.70
F. Contingencies @ 2.8% of (C) 11.83
G. Supervision Consultancy Charges @ 3% of (C) 12.68
H. Agency Charges @ 3% of (C) 12.68

I. Escalation Cost @ 5% on ( C) during Construction Period(For 1 Years) 21.13

J. Total Centages and contigencies/GST ( J= D+E+F+G+H+I ) 119.58 6.33


Departmental Cost
a. LA Cost for Construction 45.73
b. Compensation for structures 25.17
c. Utility Shifting Cost 5.70
d. Environmental Mitigation Cost 1.54
K. Total Departmental Cost(K=a+b+c+d) 78.14
L. Total Capital Cost/(L=C+J+K) 620.25 32.82
Bill for Road Works
BILL OF QUANTITIES & COST ESTIMATE
BILL NO. 1. SITE CLEARANCE

SOR Ref.of
RATE AMOUNT
SL. NO. Item MoRT& DESCRIPTION UNIT QUANTITY
(INR) (INR)
No. H
Cutting of Trees, including Cutting of Trunks, Branches and Removal (Cutting of
trees, including cutting of trunks, branches and removal of stumps, roots, stacking
2.1
of serviceable material with all lifts and up to a lead of 1000 m and earth filling in
the depression/pit.)
1.1 201
(i) Girth from 300 mm to 600 mm Each 698 163.62 1,14,206.76
(ii) Girth from 600 mm to 900 mm Each 542 318.15 1,72,437.30
(iii) Girth from 900 mm to 1800 mm Each 287 580.75 1,66,675.25
(iv) Girth above 1800 mm Each 137 1,070.60 1,46,672.20
Clearing and Grubbing Road Land (Clearing and grubbing road land including
uprooting rank vegetation, grass, bushes, shrubs, saplings and trees girth up to 300
mm, removal of stumps of trees cut earlier and disposal of unserviceable materials
2.3 and stacking of serviceable material to be used or auctioned up to a lead of 1000
metres including removal and disposal of top organic soil not exceeding 150 mm in
thickness.)
(ii) By Mechanical Means
A In area of light jungle hectare 68.20 46,329.71 31,59,686.22
1.2 201 Dismantling of Structures (Dismantling of existing structures like culverts, bridges,
retaining walls and other structure comprising of masonry, cement concrete, wood
work, steel work, including T&P and scaffolding wherever necessary, sorting the
2.4 dismantled material, disposal of unserviceable material and stacking the
serviceable material with all lifts and lead of 1000 metres)

c. Prestressed / Reinforced cement concrete grade M-20 & above


2.4 (l) By Mechanical Means for items No. 202( b) & ( c)
.ii b Prestressed / Reinforced cement concrete grade M-20 & above cum 251.40 667.61 1,67,837.15
Dismantling of Flexible Pavements (Dismantling of flexible pavements and
disposal of dismantled materials up to a lead of 1000 metres, stacking serviceable
2.5
and unserviceable materials separately)
1.3 II. 202 By Mechanical Means
a. Bituminous courses cum 7575.00 242.40 18,36,180.00
2.5 I. Granular courses (manual means)
b. cum 15150.00 349.46 52,94,319.00
Total of Bill No.-1 1,10,58,013.88
BILL OF QUANTITIES & COST ESTIMATE
BILL NO. 2. EARTHWORK, EROSION CONTROLL AND DRAINAGES

SOR Item Ref.of RATE AMOUNT


SL. NO. DESCRIPTION UNIT QUANTITY
No. MoRT&H (INR) (INR)

Excavation in Soil using Hydraulic Excavator CK 90 and Tippers with disposal upto
1000 metres. (Excavation for roadwork in soil with hydraulic excavator of 0.9 cum
2.1 3.6 301 bucket capacity including cutting and loading in tippers, trimming bottom and side cum 279738.00 83.83 2,34,50,436.54
slopes, in accordance with requirements of lines, grades and cross sections, loading
and disposal of cut road within all lifts and lead upto 1000m)
Embankment Construction with Material Obtained from Borrow Pits (Construction
of embankment with approved material obtained from borrow pits with all lifts and
leads, transporting to site, spreading, grading to required slope and compacting to
2.2 3.16.A 305 meet requirement of table 300-2(including compensation of earth.) (Including cost
of testing oe materials at site and laboratory as directed by the deptt.)
from private land cum 751149.40 268.66 20,18,03,797.80
Construction of Embankment with Material Deposited from Roadway Cutting
(Construction of embankment with approved materials deposited at site from
2.3 3.17 305 cum 195816.60 140.39 2,74,90,692.47
roadway cutting and excavation from drain and foundation of other structures
graded and compacted to meet requirement of table 300-2)
Construction of Subgrade and Earthen Shoulders (Construction of subgrade and
earthen shoulders with approved material obtained from borrow pits with all lifts &
leads, transporting to site, spreading, grading to required slope and compacted to
2.4 3.18a 305 meet requirement of table No. 300-2) (including compensation of earth.)(a),(
Including cost of testing of naterials at site and laboratory as directed by the deptt.)
from private land cum 188384.78 325.22 6,12,66,498.15
Seeding and Mulching (Preparation of seed bed on previously laid top soil,
furnishing and placing of seeds, fertilizer, mulching material, applying bituminous
2.5 3.22 307 emulsion at the rate of 0.23 litres per sqm and laying and fixing jute netting, sqm 120666.87 127.26 1,53,56,065.88
including watering for 3 months all as per clause 308)
Construction of Median and Island with Soil Taken from Borrow Areas
(Construction of median and Island above road level with approved material
2.6 4.14 407 cum 25347.97 261.59 66,30,775.47
brought from borrow pits, spread, sloped and compacted as per clause 407)

Surface Drains in Soil (Mechanical means)


Construction of unlined surface drains of average cross sectional area 0.40 sqm in
2.7 3.24 A soil to specified lines, grades, levels and dimensions to the requirement of clause Rm 31423.780 69.69 21,89,923.23
301 and 309. Excavated material to be used in embankment within a lead of 50
metres (average lead 25 metres)
Total of Bill No.-2 33,81,88,189.54
BILL OF QUANTITIES & COST ESTIMATE
BILL NO. 3. SUB-BASES, BASES ( NON- BITUMINOUS) AND SHOULDERS

SOR Ref.of RATE AMOUNT


SL. NO. DESCRIPTION UNIT QUANTITY
Item No. MoRT&H (INR) (INR)

4.1 401 Granular Sub-Base with Close Graded Material (Table:- 400-1)
Plant Mix Method (Construction of granular sub-base by providing close graded Material,
mixing in a mechanical mix plant at OMC, carriage of mixed Material to work site,
spreading in uniform layers with motor grader on prepared surface and compacting with
vibratory power roller to achieve the desired density, complete as per clause 401( with an
initial lead of 5 km ) (Including cost of testing of materials at sitf and laboratory as directed
3.1
by the dept.)

(i) for grading- I Material cum 16274.51 2,487.05 4,04,75,520.10


for grading-III Material cum 6977.11 2,353.88 1,64,23,279.69
Wet Mix Macadam (Providing, laying, spreading and compacting graded stone aggregate
to wet mix macadam specification including premixing the Material with water at OMC in
mechanical mix plant carriage of mixed Material by tipper to site, laying in uniform layers
3.2 4.12 406 with paver in sub- base / base course on well prepared surface and compacting with cum 26200.99 2,520.20 6,60,31,735.00
vibratory roller to achieve the desired density. (including carriage up to initial lead of 5.0
km from quarry and carriage of mixed naterials up to 10.0 km initial lead from mixing
plant)

Cement Treated Crushed Rock or combination as per clause 403.2 and table 400.4in Sub
base/ Base ( Providing, laying and spreading Material on a prepared sub grade, adding the
designed quantity of cement to the spread Material, mixing in place with rotavator,
3.3 4.3 403
grading with the motor grader and compacting with the road roller at OMC to achieve the
desired unconfined compressive strength and to form a layer of sub-base/base.

(i) For Sub-Base course cum 66984.87 3,672.75 24,60,18,681.29


(ii) For Base course cum 25249.60 3,186.48 8,04,57,345.41
3.4 Non-Sch GSB Reuse cum 9090.00 826.18 75,09,976.20
3.5 Non-Sch RAP cum 7461.68 1,922.09 1,43,42,020.51
3.6 Non-Sch Geocell sqm 82874.05 100.00 82,87,405.00
3.7 Recycling of Existing Pavement(Including Plant & Machinery, Labour) Lumsum 21,00,000.00

Total of Bill No.-3 48,16,45,963.20


BILL OF QUANTITIES & COST ESTIMATE
BILL NO. 4. BITUMINOUS SURFACE COURSE

Ref.of RATE AMOUNT


SL.NO SOR Item No. DESCRIPTION UNIT QUANTITY
MoRT&H (INR) (INR)

Prime coat (Providing and applying primer coat with bitumen emulsion on
prepared surface of granular Base including clearing of road surface and
spraying primer at the rate of 1.0 kg/sqm using mechanical means.)(Including
4.1 5.1 A (i) 502
cost of testing of materials at sitfe and laboratory as directed by the depttt.)

with bitumen emulsion-CSS-1 h sqm 327150.89 25.35 82,93,275.06


Tack coat Providing and applying tack coat with bitumen emulsion using
emulsion pressure distributor at the rate of 0.20 kg per sqm on the prepared
5.2 bituminous/granular surface cleaned with mechanical broom.(Including cost of
testing of materials at sitfe and laboratory as directed by the depttt.)
4.2 503
(I) with bitumen emulsion-CSS-1 h
(a) Normal bituminious surface sqm 21543.00 9.12 1,96,472.16
( c) Granular surface treated with primer sqm 327150.89 17.34 56,72,796.43
Ref.of RATE AMOUNT
SL.NO SOR Item No. DESCRIPTION UNIT QUANTITY
MoRT&H (INR) (INR)

Dense Graded Bituminous Macadam (Providing and laying dense bituminous


macadam with 100-120 TPH batch type HMP producing an average output of 75
tonnes per hour using crushed aggregates of specified grading, premixed with
bituminous binder @ 4.0 to 4.5% by weight of total mix of mix and filler,
transporting the hot mix to work site, laying with a hydrostatic paver finisher
with sensor control to the required grade, level and alignment, rolling with
5.6 smooth wheeled, vibratory and tandem rollers to achieve the desired
compaction as per MoRTH specification clause No. 507 complete in all
4.3 507 respects.)(including carriage up to initial lead of 5.0 km from quarry and
carriage of mixed naterials up to 10.0 km initial lead from mixing
plant)(Including cost of testing of materials at sitfe and laboratory as directed
by the depttt.)

With hydrated lime/cement as filler(refer table 500-9 of MoRT&H


A.
specification)
(I) With 40/60 or VG -40 grade bitumen
(i) for Grading II ( 19 mm nominal size ) cum 21974.90 9,209.29 20,23,73,226.82
Bituminous Concrete (Providing and laying bituminous concrete with 100-120
TPH batch type hot mix plant producing an average output of 75 tonnes per
hour using crushed aggregates of specified grading, premixed with bituminous
binder @ 5.4 to 5.6 % of mix and filler, transporting the hot mix to work site,
laying with a hydrostatic paver finisher with sensor control to the required
grade, level and alignment, rolling with smooth wheeled, vibratory and tandem
5.6
rollers to achieve the desired compaction as per MORTH specification clause
No. 509 complete in all respects)(including carriage up to initial lead of 5.0 km
4.4 507
from quarry and carriage of mixed naterials up to 10.0 km initial lead from
mixing plant)(Including cost of testing of materials at sitfe and laboratory as
directed by the depttt.)

With hydrated lime/cement as filler(refer table 500-9 of MoRT&H


A.
specification)
(I) With 40/60 or VG -40 grade bitumen
(i) for Grading II ( 13 mm nominal size ) cum 13947.76 10,483.41 14,62,20,086.66

Total of Bill No.-4 36,27,55,857.13


BILL OF QUANTITIES & COST ESTIMATE
BILL NO.5 TRAFFIC SIGNS, ROAD MARKING AND OTHER ROAD APPURTENANCES

SOR Item Ref.of RATE AMOUNT


SL. NO. DESCRIPTION UNIT QUANTITY
No. MoRT&H (INR) (INR)

Cast in Situ Cement Concrete M20 kerb (Construction of cement concrete kerb with
top and bottom width 115 and 165 mm respectively, 250 mm high in M 20 grade PCC
on M-10 grade foundation 150 mm thick, foundation having 50 mm projection
5.1 8.1 408
beyond kerb stone, kerb stone laid with kerb laying machine, foundation concrete
laid manually, all complete as per clause 408)

B Using Concrete Batching and Mixing Plant metre 33180 377.81 1,25,35,735.80
Retro- reflectorised Traffic signs (Providing and fixing of retro- reflectorised
cautionary, mandatory and informatory sign as per IRC :67 made of encapsulated
lens type reflective sheeting vide clause 801.3, fixed over aluminium sheeting, 2.0
mm thick fixed on an angle iron of 25x25x4mm supported on a mild steel angle iron
8.4 post 75 mm x 75 mm x 6 mm firmly fixed to the ground by means of properly
designed foundation with M15 grade cement concrete 45 cm x 45 cm x 60 cm, 60 cm
5.2 below ground level as per approved drawing and signs(All steel work must be
Tata/Sail/or any other approved brand)

(i) 90 cm equilateral triangle each 91 2,640.55 2,40,290.05


( iii ) 60 cm circular each 10 2,591.06 25,910.60
( iv ) 80 mm x 60 mm rectangular each 8 2,736.50 21,892.00
( vii ) 90 cm high octagon each 25 2,878.91 71,972.75
Direction and Place Identification signs upto 0.9 sqm size board.(Providing and
erecting direction and place identification retro-reflectorised sign asper IRC:67 made
of encapsulated lens type reflective sheeting vide clause 801.3, fixed over aluminium
sheeting, 2 mm thick with area not exceeding 0.9 sqm fixed on an angle iron of
5.3 8.5 801 25x25x4mm supported on a mild steel angle iron post 75 mm x 75 mm x 6 mm sqm 15 3,396.86 50,952.90
firmly fixed to the ground by means of properly designed foundation with M15 grade
cement concrete 45 cm x 45 cm x 60 cm, 60 cm below ground level as per approved
drawing and signs(All steel work must be Tata/Sail/or any other approved brand)
SOR Item Ref.of RATE AMOUNT
SL. NO. DESCRIPTION UNIT QUANTITY
No. MoRT&H (INR) (INR)

804 Kilo Metre Stone (Reinforced cement concrete M15grade kilometre stone of
8.14 standard design as per IRC:8-1980, fixing in position including painting and printing
etc)
5.5
(i) 5th kilometre stone (precast) each 8 4,085.04 32,680.32
(ii) Ordinary Kilometer stone (Precast) each 22 2,548.65 56,070.30
(iii) Hectometer stone (Precast) each 58 643.84 37,342.72
Road Delineator
Providing metal tubular delineator (50mm dia & 1.25mm thick )with 15 cm reflector
made of heigh intensity grade retro reflectorised sheeting around the pipe at top
covered with wire mesh of 20cm length with 2 nos of similar reflective bends and
5.6 8.54 bottom fastner M.S.angle including firmly fixing the delineator to the ground by each 637 1,270.58 8,09,359.46
means of CC (M-15) foundation of size (25x25x25cm),25cm below ground to the true
line and level as directed by the deptt. With six months replacement warranty and
free maintenance.
b) 750 mm ht.
Boundary pillar (Reinforced cement concrete M15 grade boundary pillars of
5.7 8.16 806 standard design as per IRC:25-1967, fixed in position including finishing and lettering each 178 646.71 1,15,114.38
but excluding painting)
SOR Item Ref.of RATE AMOUNT
SL. NO. DESCRIPTION UNIT QUANTITY
No. MoRT&H (INR) (INR)

pole Height 6m:The materials of the pole as follows:Conforming to grade


S355JO,Base plate Fe 410 conforming to IS 226/IS 2062, Foundation Bolts:-6.8 Gr. As
per IS 1367, Plole sections:- The octagonal poles shall be in single piece with single
longitudinal welding join.Galvanization:-The pole shall be hot dip galvanized as per IS
2629/IS 2633/IS 4759 standards with average coating thickness of 65 micron.The
galvanizing shal be done in single dipping. Door opening:-The octagonal poles shall
have door of approxinate 500 mm length at the elevation of 500 mm from the base
plate.The door shall be vandal resistance and shall be weather proof to ensure saefty
of of inside connections.The door shall be flush with the exterior surface and shall
have suitable locking arrangement.The pole shall be adequately strengthened at the
location of the door compensate for the loss in the section.There shall also be
5.8 iv) suitable arrangement for the purpose of earthing,smart pack junction box with 6 each 185 29,274.85 54,15,847.25
MCB & Terminals for mounting inside base compartment of pole.Top dia(A/F) 70
Bottom Dia. (A/F) 130, Sheet thickness 3 mm, Base Plate Dimensions(LXBXT)
220x220x12, Foundation Bolt, Bolt size:-(noxdia) 4x20 dia, pitch circle dia.(PCD)
205,Bolt length 600,Projected Bolt Length 100, Anchor plate thickness:- 4 mm,Pole
Foundation :- The octagonal poles shall be bolted on a pre - cast foundation with a
set of four foundation bolts for greater rigidity. Foundation :- The foundation shall be
done with (i) Earth work:- 2.04 cubic Meters.(ii)RCC:- 1:1.5:3 proportion 0.65 cubic
meters. (iii0 Steel:-22.43 kg .(iv0 Shuttering:-4.32 square meters.=22.43 kg.
SOR Item Ref.of RATE AMOUNT
SL. NO. DESCRIPTION UNIT QUANTITY
No. MoRT&H (INR) (INR)

5.9 8.13 803 Road Marking with Hot Applied Thermoplastic Compound (Providing and laying of
hot applied thermoplastic compound 2.5 mm thick including reflectorising glass
beads @ 250 gms per sqm area, thickness of 2.5 mm is exclusive of surface applied sqm 13800.000 661.55 91,29,390.00
glass beads as per IRC:35 .The finished surface to be level, uniform and free from
streaks and holes.
5.10 8.35
Road Markers/Road Stud with Lense Reflector
Providing and fixing of road stud 100x 100 mm, die-cast in aluminium, resistant to
corrosive effect of salt and grit, fitted with lense reflectors, installed in concrete or nos 1188 683.77 8,12,318.76
asphaltic surface by drilling hole 30 mm upto a depth of 60 mm and bedded in a
suitable bituminous grout or epoxy mortar, all as per BS 873 part 4:1973

5.11 8.23 A W-Metal beam crash barrier


Providing and erecting a "W" metal beam crash barrier comprising of 3 mm thick
corrugated sheet metal beam rail, 70 cm above road/ground level, fixed on ISMC
series channel vertical post, 150 x 75 x 5 mm spaced 2 m centre to centre, 1.8 m
metre 15158.240 3,613.76 5,47,78,241.38
high, 1.1 m below ground/road level, all steel parts and fitments to be galvanised by
hot dip process, all fittings to conform to IS:1367 and IS:1364, metal beam rail to be
fixed on the vertical post with a spacer of channel section 150 x 75 x 5 mm, 330 mm
long complete as per clause 810

Total of Bill No.-5 8,41,56,539.85


BILL OF QUANTITIES & COST ESTIMATE
BILL NO. 6. DRAINAGE & PROTECTION WORK

SL. SOR Item Ref.of RATE AMOUNT


DESCRIPTION UNIT QUANTITY
NO. No. MoRT&H (INR) (INR)
RCC Cover Drain
Excavation for Structures (Earth work in excavation of foundation of
structures as per drawing and technical specification, including setting out,
construction of shoring and bracing, removal of stumps and other
deleterious matter, dressing of sides and bottom, backfilling the excavation
3.13 (I) . earth to the extent required and utilising the remaining earth locally for
6.1 304 cum 6725.51 61.08 4,10,794.15
A road work.)
i) Ordinary soil
A. a)Mechanical Means, with dewatering
upto 3 m depth
1500,1700 Plain/Reinforced cement concrete in open foundation complete as per
12.8 & 2100 drawing and technical specifications including steel shuttering forrmwork
6.2
A. Without plasticiser

(a) PCC Grade M15 cum 574.540 6,979.01 40,09,720.41


1500,1700 Plain/Reinforced cement concrete in sub-structure complete as per drawing
13.5 & 2200 and technical specifications
6.3 N(A).f. Without plasticiser
RCC Grade M25
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 2654.240 9,336.67 2,47,81,762.98
1600 & Reinforcement in Substructure :Supplying, fitting and placing un-coatedTMT
2300 bar reinforcement in foundation complete as per drawing and technical
13.6 (a) specifications
6.4 tonne 185.80 64,921.69 1,20,62,450.00
(i) a) From primary sources: TATA/SAIL/Esser Steel/Jindal steel/Shyam steel
i) TMT Corrosion Resistance Steel (CRS) reinforcement bar of Fe-500 N/mm2
2200 & Providing weep holes in Brick masonry/Plain/Reinforced concrete
2706 abutment, wing wall/return wall with 100 mm dia AC pipe, extending
6.5 13.8 through the full width of the structure with slope of 1V :20H towards each 7378.000 1,812.33 1,33,71,370.74
drawing foce. Complete as per drawing and Technical specifications

Total= 5,46,36,098.28
SL. SOR Item Ref.of RATE AMOUNT
DESCRIPTION UNIT QUANTITY
NO. No. MoRT&H (INR) (INR)
RR Masonry Chute Drain
Excavation for Structures (Earth work in excavation of foundation of
structures as per drawing and technical specification, including setting out,
construction of shoring and bracing, removal of stumps and other
deleterious matter, dressing of sides and bottom, backfilling the excavation
3.13 (I) B. earth to the extent required and utilising the remaining earth locally for
6.6 304 cum 711.900 61.08 43,482.85
(a) road work.)
i) Ordinary soil
A. a)Manual Means, with dewatering
upto 3 m depth
6.16 1500, 1700 Plain/Reinforced Cement Concrete in Open Foundation complete as per
& 2100 Drawing and Technical Specifications.
B Without plasticiser
PCC Grade M20 cum 457.890 7434.12 34,04,009.21
6.7 15.4 2504 Stone Pitching cum 203.400 2273.70 4,62,470.58
Total= 39,09,962.64
SL. SOR Item Ref.of RATE AMOUNT
DESCRIPTION UNIT QUANTITY
NO. No. MoRT&H (INR) (INR)
For RE Wall
6.6 3.18a 305 Embankment Filling by Subgrade Material cum 137609.47 325.22 4,47,53,351.83
6.7 Embankment Filling by Sand cum 137609.48 1,176.20 16,18,56,270.38
Reinforced Earth Stuctures (Reference to MORT&H's specifications 3100 ).
7.5 3100
With reinfocing element of synthetic geogrids
6.8
(i) Facing Element of RCC sqm 38734.10 1,574.57 6,09,89,551.84
(ii) With reinforcing element of synthetic geogrids sqm 38734.10 595.90 2,30,81,650.19
1500,1700 Plain/Reinforced cement concrete in open foundation complete as per
12.8 & 2100 drawing and technical specifications including steel shuttering forrmwork

6.9 A. Without plasticiser


(a) PCC Grade M15 cum 987.000 6,979.01 68,88,282.87
(E) RCC Grade M25
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 4146.139 8,753.04 3,62,91,320.51
12.4 0 1600 & Supplying, fitting and placing HYSD bar reinforcement in foundation
tonne 290.23 64,846.06 1,88,20,271.99
6.10 (a). (i) 2300
13.10 Filter Media cum 23237 2,288.73 5,31,83,219.01
Reinforced Cement Concrete Crash Barrier (Provision of an Reinforced
cement concrete crash barrier at the edges of the road, approaches to
bridge structures and medians, constructed with M-20 grade concrete with
HYSD reinforcement conforming to IRC:21 and dowel bars 25 mm dia, 450
mm long at expansion joints filled with pre-moulded asphalt filler board,
6.11 8.22 (ii) 809 keyed to the structure on which it is built and installed as per design given in metre 4936 4,674.72 2,30,74,417.92
the enclosure to MORT&H circular No. RW/NH - 33022/1/94-DO III dated
June 1994 as per dimensions in the approved drawing and at locations
directed by the Engineer, all as specified

Total= 42,89,38,336.54
SL. SOR Item Ref.of RATE AMOUNT
DESCRIPTION UNIT QUANTITY
NO. No. MoRT&H (INR) (INR)
For Retaining Wall
Excavation for Structures (Earth work in excavation of foundation of
structures as per drawing and technical specification, including setting out,
construction of shoring and bracing, removal of stumps and other
deleterious matter, dressing of sides and bottom, backfilling the excavation
3.13 (I) . earth to the extent required and utilising the remaining earth locally for
6.18 304 cum 2083.08 61.08 1,27,234.53
A road work.)
i) Ordinary soil
A. a)Mechanical Means, with dewatering
upto 3 m depth
12.7 1400 Stone masonry work in cement mortar 1:3 for foundation
6.20
B RR Masonry cum 1788.50 4,542.93 81,25,030.31
1500,1700 Plain/Reinforced cement concrete in open foundation complete as per
12.8 & 2100 drawing and technical specifications including steel shuttering forrmwork
6.21
A. Without plasticiser
(a) PCC Grade M15 cum 1009.980 6,979.01 70,48,660.52
1400 &
12.7 Stone masonry work in cement mortar 1:3 for substructure
2200
6.22
B RR Masonry cum 2503.90 4,542.93 1,13,75,042.43
CR Masonry cum 437.40 5,434.13 23,76,888.46
2200 & Providing weep holes in Brick masonry/Plain/Reinforced concrete
2706 abutment, wing wall/return wall with 100 mm dia AC pipe, extending
6.23 13.8 through the full width of the structure with slope of 1V :20H towards each 2104.12 1,812.33 38,13,359.80
drawing foce. Complete as per drawing and Technical specifications
710.1.4 of Providing and laying of Filter media with granular materials/stone crushed
IRC:78 & aggregates satisfying the requirements laid down in clause 2504.2.2. of
2200 MoRTH specifications to a thickness of not less than 600 mm with smaller
6.24 13.10 size towards the soil and bigger size towards the wall and provided over the Cum 2798.48 2,288.73 64,04,965.13
entire surface behind abutment, wing wall and return wall to the full height
compacted to a firm condition complete as per drawing and technical
specification.

Total= 3,92,71,181.18
SL. SOR Item Ref.of RATE AMOUNT
DESCRIPTION UNIT QUANTITY
NO. No. MoRT&H (INR) (INR)
Toe Wall
6. 24 Excavation for Structures (Earth work in excavation of foundation of
structures as per drawing and technical specification, including setting out,
construction of shoring and bracing, removal of stumps and other
deleterious matter, dressing of sides and bottom, backfilling the excavation
3.13 (I) . earth to the extent required and utilising the remaining earth locally for
304 cum 1426.53 61.08 87,132.45
A road work.)
i) Ordinary soil
A. a)Mechanical Means, with dewatering
upto 3 m depth

6.25 1500,1700 Plain/Reinforced cement concrete in open foundation complete as per


12.8 & 2100 drawing and technical specifications including steel shuttering forrmwork
A. Without plasticiser
(a) PCC Grade M15 cum 158.52 6979.01 11,06,312.67
6.26 13.5 F (p)
RCC Substructure M25 Height 5M cum 1435.84 8753.04 1,25,67,964.95
Case II
6.27 Supplying, Fitting and Placing un-coated HYSD bar Reinforcement in
12.4 Foundation complete as per Drawing and Technical Specifications. tonne 100.51 64846.06 65,17,677.49

Total= 2,02,79,087.56

Ground Improvement Works (Sand Pile)


6. 28 Non Sche Driven cast-in-place vertical Sand Pile complete as per Drawing and &
m 53220.00 1333.20 7,09,52,904.00
Technical Specification

Total= 7,09,52,904.00

Total of Bill No.-6 61,79,87,570.20


BILL OF QUANTITIES & COST ESTIMATE
BILL NO. 7. BUS- BAY WITH PASSENGER SHELTER & TRUCK LAY BYE

SOR Item Ref.of RATE AMOUNT


SL. NO. DESCRIPTION UNIT QUANTITY
No. MoRT&H (INR) (INR)

A. Bus Bay

Cement Treated Crushed Rock or combination as per clause 403.2 and


table 400.4in Sub base/ Base ( Providing, laying and spreading Material on a
prepared sub grade, adding the designed quantity of cement to the spread
7.1 4.3 403 Material, mixing in place with rotavator, grading with the motor grader and
compacting with the road roller at OMC to achieve the desired unconfined
compressive strength and to form a layer of sub-base/base.

(i) For Sub-Base course cum 1004.000 3,672.75 36,87,441.00


(ii) For Base course cum 502.000 3,186.48 15,99,612.96
Wet Mix Macadam (Providing, laying, spreading and compacting graded
stone aggregate to wet mix macadam specification including premixing the
Material with water at OMC in mechanical mix plant carriage of mixed
Material by tipper to site, laying in uniform layers with paver in sub- base /
7.2 4.12 406 base course on well prepared surface and compacting with vibratory roller cum 502.000 2,520.20 12,65,140.40
to achieve the desired density. (including carriage up to initial lead of 5.0 km
from quarry and carriage of mixed naterials up to 10.0 km initial lead from
mixing plant)

Providing and applying Primer coat over WMM layer using bitumen
7.3 5.1 A (i) 502 emulsion (Grade SS-1) @ 0.85Kg / sqm as per drawings and Technical sqm 5020.000 25.35 1,27,257.00
specifications clause 502 and as directed by the Engineer.
Tack coat Providing and applying tack coat with bitumen emulsion using
emulsion pressure distributor at the rate of 0.20 kg per sqm on the
5.2 prepared bituminous/granular surface cleaned with mechanical
7.4 503 broom.(Including cost of testing of materials at sitfe and laboratory as
directed by the depttt.)
(I) with bitumen emulsion-CSS-1 h
(c) Granular surface treated with primer sqm 5020.00 17.34 87,046.80
SOR Item Ref.of RATE AMOUNT
SL. NO. DESCRIPTION UNIT QUANTITY
No. MoRT&H (INR) (INR)

Construction of Subgrade and Earthen Shoulders (Construction of subgrade


and earthen shoulders with approved material obtained from borrow pits
with all lifts & leads, transporting to site, spreading, grading to required
7.5 3.18a 305 slope and compacted to meet requirement of table No. 300-2) (including
compensation of earth.)(a),( Including cost of testing of naterials at site and
laboratory as directed by the deptt.)

from private land cum 2510.00 325.22 8,16,302.20


SOR Item Ref.of RATE AMOUNT
SL. NO. DESCRIPTION UNIT QUANTITY
No. MoRT&H (INR) (INR)

Dense Graded Bituminous Macadam (Providing and laying dense


bituminous macadam with 100-120 TPH batch type HMP producing an
average output of 75 tonnes per hour using crushed aggregates of specified
grading, premixed with bituminous binder @ 4.0 to 4.5% by weight of total
mix of mix and filler, transporting the hot mix to work site, laying with a
hydrostatic paver finisher with sensor control to the required grade, level
7.6 5.6 A (I) 505 and alignment, rolling with smooth wheeled, vibratory and tandem rollers to
achieve the desired compaction as per MoRTH specification clause No. 507
complete in all respects.)(including carriage up to initial lead of 5.0 km from
quarry and carriage of mixed naterials up to 10.0 km initial lead from mixing
plant)(Including cost of testing of materials at sitfe and laboratory as
directed by the depttt.)

(ii) for Grading II (With 40/60 or VG -40 grade bitumen) (for Grading II ( 40
cum 301.200 9,209.29 27,73,838.15
mm nominal size )
Bituminous Concrete (Providing and laying bituminous concrete with 100-
120 TPH batch type hot mix plant producing an average output of 75 tonnes
per hour using crushed aggregates of specified grading, premixed with
bituminous binder @ 5.4 to 5.6 % of mix and filler, transporting the hot mix
to work site, laying with a hydrostatic paver finisher with sensor control to
the required grade, level and alignment, rolling with smooth wheeled,
5.8 A (I) 507 vibratory and tandem rollers to achieve the desired compaction as per
7.7 MORTH specification clause No. 509 complete in all respects)(including
carriage up to initial lead of 5.0 km from quarry and carriage of mixed
naterials up to 10.0 km initial lead from mixing plant)(Including cost of
testing of materials at sitfe and laboratory as directed by the depttt.)

(Ii) for Grading-I (19 mm nominal size) cum 200.800 10,483.41 21,05,068.73
Cast in Situ Cement Concrete M20 kerb (Construction of cement concrete
kerb with top and bottom width 115 and 165 mm respectively, 250 mm high
8.1 408 in M 20 grade PCC on M-10 grade foundation 150 mm thick, foundation
7.8 having 50 mm projection beyond kerb stone, kerb stone laid with kerb
laying machine, foundation concrete laid manually, all complete as per
clause 408)
A Using Concrete Mixer metre 252 377.81 95,208.12
SOR Item Ref.of RATE AMOUNT
SL. NO. DESCRIPTION UNIT QUANTITY
No. MoRT&H (INR) (INR)

Construction of Median and Island with Soil Taken from Roadway Cutting
(Construction of Median and Island above road level with approved material
7.9 4.13 407 deposited at site from roadway cutting and excavation for drain and cum 51 193.92 9,889.92
foundation of other structures, spread, graded and compacted as per clause
407)
SOR Item Ref.of RATE AMOUNT
SL. NO. DESCRIPTION UNIT QUANTITY
No. MoRT&H (INR) (INR)

Passenger Shelter
Excavation for Structures (Earth work in excavation of foundation of
structures as per drawing and technical specification, including setting out,
construction of shoring and bracing, removal of stumps and other
deleterious matter, dressing of sides and bottom, backfilling the excavation
3.13 (I) .
7. 10 304 earth to the extent required and utilising the remaining earth locally for cum 21.120 61.08 1,290.01
(A) road work.)
i) Ordinary soil
A. a)Manual Means, with dewatering
upto 3 m depth
1300 Brick masonry (Brick masonry work in cement mortar 1:3 in foundation
7.11 12.5 complete excluding pointing and plastering, as per drawing and technical cum 6.080 8,161.65 49,622.83
specifications
1300 Brick masonry (Brick masonry work in cement mortar 1:3 in Super Structure
7.12 12.5 complete excluding pointing and plastering, as per drawing and technical cum 17.520 8,161.65 1,42,992.11
specifications
1500, Plain/Reinforced cement concrete in open foundation -RCC M25-Without
7.13 12.8 C 1700 & plasticiser(With Batching Plant, Transit Mixer and Concrete Pump) cum 2.280 8,753.04 19,956.93
2100
Reinforcement in foundation-TMT Bar (From primary sources:
12.4 0 (a).
7.14 1600 TATA/SAIL/Esser Steel/Jindal steel/Shyam steel)-TMT Corrosion Resistance Tonne 0.160 64,846.06 10,375.37
(i)
Steel (CRS) reinforcement bar of Fe-500 N/mm2
Plain/Reinforced cement concrete in super-structure complete as per
1500,170 drawing and Technical Specifications section 1500,1700& 2200 and as
7.15 12.8 A (a) cum 4.040 6,979.01 28,195.20
0 & 2200 directed by the Engineer.
PCC M15
14.1 A Furnishing and Placing Reinforced/ Prestressed cement concrete in super-
1500
case -II( i) structure as per drawing and Technical Specification section 1500,1700 &
7.16 &1600,17 cum 14.720 10,116.61 1,48,916.50
a). 2300 and as directed by the Engineer.
00, 2300
RCC M25

Supplying, fitting and placing HYSD/TMT bar reinforcement in super-


1600 &
7.17 14.2 (a). (i structure complete as per drawing and technical specifications section 1600 Tonne 1.120 65,989.22 73,907.93
2300
& 2300 and as directed by the Engineer.

1300 & Plastering with cement mortar (1:3 ) on brick work in super-structure as per
7.18 13.3 2200 Technical specifications sqm 249.480 1,497.29 3,73,543.91

Total of Bus bay with passenger shelter= 1,34,15,606.07


SOR Item Ref.of RATE AMOUNT
SL. NO. DESCRIPTION UNIT QUANTITY
No. MoRT&H (INR) (INR)

Total of Bill No.-7 1,34,15,606.07


BILL OF QUANTITIES & COST ESTIMATE
BILL NO. 8. JUNCTION

SL. SOR Ref. Ref.of RATE AMOUNT


DESCRIPTION UNIT QUANTITY
NO. No MoRT&H (INR) (INR)
Cement Treated Crushed Rock or combination as per clause 403.2 and table
400.4in Sub base/ Base ( Providing, laying and spreading Material on a
prepared sub grade, adding the designed quantity of cement to the spread
8.1 4.3 403 Material, mixing in place with rotavator, grading with the motor grader and
compacting with the road roller at OMC to achieve the desired unconfined
compressive strength and to form a layer of sub-base/base.

(i) For Sub-Base course cum 1100.00 3,672.75 40,40,025.00


(ii) For Base course cum 550.00 3,186.48 17,52,564.00
5.1 A Prime coat
Prime coat (Providing and applying primer coat with bitumen emulsion on
prepared surface of granular Base including clearing of road surface and
8.2 502 spraying primer at the rate of 0.60 kg/sqm using mechanical
means.)(Including cost of testing of materials at sitfe and laboratory as
directed by the depttt.)
(i) with bitumen emulsion-CSS-1 h sqm 5500.00 25.35 1,39,425.00
Tack coat Providing and applying tack coat with bitumen emulsion using
emulsion pressure distributor at the rate of 0.20 kg per sqm on the prepared
5.2 (I) bituminous/granular surface cleaned with mechanical broom.(Including cost
8.3 503 of testing of materials at sitfe and laboratory as directed by the depttt.)

with bitumen emulsion-CSS-1 h


(b) Granular surface treated with primer sqm 5500.00 17.34 95,370.00
Wet Mix Macadam (Providing, laying, spreading and compacting graded
stone aggregate to wet mix macadam specification including premixing the
Material with water at OMC in mechanical mix plant carriage of mixed
Material by tipper to site, laying in uniform layers with paver in sub- base /
8.4 4.12 406 cum 550.00 2,520.20 13,86,110.00
base course on well prepared surface and compacting with vibratory roller to
achieve the desired density. (including carriage up to initial lead of 5.0 km
from quarry and carriage of mixed naterials up to 10.0 km initial lead from
mixing plant)
SL. SOR Ref. Ref.of RATE AMOUNT
DESCRIPTION UNIT QUANTITY
NO. No MoRT&H (INR) (INR)
Bituminous Concrete (Providing and laying bituminous concrete with 100-120
TPH batch type hot mix plant producing an average output of 75 tonnes per
hour using crushed aggregates of specified grading, premixed with
bituminous binder @ 5.4 to 5.6 % of mix and filler, transporting the hot mix
to work site, laying with a hydrostatic paver finisher with sensor control to
the required grade, level and alignment, rolling with smooth wheeled,
8.5 5.8 vibratory and tandem rollers to achieve the desired compaction as per
MORTH specification clause No. 509 complete in all respects)(including
carriage up to initial lead of 5.0 km from quarry and carriage of mixed
naterials up to 10.0 km initial lead from mixing plant)(Including cost of testing
of materials at sitfe and laboratory as directed by the depttt.)

With hydrated lime/cement as filler(refer table 500-9 of MoRT&H


A.
specification)
(I) With 40/60 or VG -40 grade bitumen
(ii) for GradingII(13 mm nominal size) cum 220.000 10,483.41 23,06,350.20
Dense Graded Bituminous Macadam (Providing and laying dense bituminous
macadam with 100-120 TPH batch type HMP producing an average output of 75
tonnes per hour using crushed aggregates of specified grading, premixed with
bituminous binder @ 4.0 to 4.5% by weight of total mix of mix and filler, transporting
the hot mix to work site, laying with a hydrostatic paver finisher with sensor control
to the required grade, level and alignment, rolling with smooth wheeled, vibratory
8.6 5.6
and tandem rollers to achieve the desired compaction as per MoRTH specification
clause No. 507 complete in all respects.)(including carriage up to initial lead of 5.0 km
from quarry and carriage of mixed naterials up to 10.0 km initial lead from mixing
plant)(Including cost of testing of materials at sitfe and laboratory as directed by the
depttt.)

With hydrated lime/cement as filler(refer table 500-9 of MoRT&H


A. specification)
(I) With 40/60 or VG -40 grade bitumen
(i) for Grading II ( 19 mm nominal size ) cum 330.00 9,209.29 30,39,065.70
Construction of Subgrade and Earthen Shoulders (Construction of subgrade
and earthen shoulders with approved material obtained from borrow pits
with all lifts & leads, transporting to site, spreading, grading to required slope
8.7 3.18a 305
and compacted to meet requirement of table No. 300-2) (including
compensation of earth.)(a),( Including cost of testing of naterials at site and
laboratory as directed by the deptt.)
from private land cum 2750.00 325.22 8,94,355.00
SL. SOR Ref. Ref.of RATE AMOUNT
DESCRIPTION UNIT QUANTITY
NO. No MoRT&H (INR) (INR)

Total of Bill No.-8 1,36,53,264.90


BILL OF QUANTITIES & COST ESTIMATE
BILL NO. 9. SERVICE ROAD

SL. SOR Ref. Ref.of RATE AMOUNT


DESCRIPTION UNIT QUANTITY
NO. No MoRT&H (INR) (INR)

Cement Treated Crushed Rock or combination as per clause 403.2 and table
400.4in Sub base/ Base ( Providing, laying and spreading Material on a
prepared sub grade, adding the designed quantity of cement to the spread
9.1 4.3 403 Material, mixing in place with rotavator, grading with the motor grader and
compacting with the road roller at OMC to achieve the desired unconfined
compressive strength and to form a layer of sub-base/base.

(i) For Sub-Base course cum 5778.00 3,672.75 2,12,21,149.50


(ii) For Base course cum 2889.00 3,186.48 92,05,740.72
4.1 401 Granular Sub-base with Close Graded Material (Table:- 400-1)

Construction of Subgrade and Earthen Shoulders (Construction of subgrade


and earthen shoulders with approved material obtained from borrow pits
with all lifts & leads, transporting to site, spreading, grading to required slope
9.2 3.18a 305 and compacted to meet requirement of table No. 300-2) (including
compensation of earth.)(a),( Including cost of testing of naterials at site and
laboratory as directed by the deptt.)
from private land cum 14445.00 325.22 46,97,802.90

9.3 5.1 A 502 Prime coat


Prime coat (Providing and applying primer coat with bitumen emulsion on
prepared surface of granular Base including clearing of road surface and
spraying primer at the rate of 0.60 kg/sqm using mechanical
means.)(Including cost of testing of materials at sitfe and laboratory as
directed by the depttt.)
(i) with bitumen emulsion-CSS-1 h sqm 28890.00 25.35 7,32,361.50
Tack coat Providing and applying tack coat with bitumen emulsion using
emulsion pressure distributor at the rate of 0.20 kg per sqm on the prepared
9.4 5.2 (I) 503 bituminous/granular surface cleaned with mechanical broom.(Including cost
of testing of materials at sitfe and laboratory as directed by the depttt.)

with bitumen emulsion-CSS-1 h


(b) Granular surface treated with primer sqm 28890.00 17.34 5,00,952.60
SL. SOR Ref. Ref.of RATE AMOUNT
DESCRIPTION UNIT QUANTITY
NO. No MoRT&H (INR) (INR)
Wet Mix Macadam (Providing, laying, spreading and compacting graded
stone aggregate to wet mix macadam specification including premixing the
Material with water at OMC in mechanical mix plant carriage of mixed
Material by tipper to site, laying in uniform layers with paver in sub- base /
9.5 4.12 406 base course on well prepared surface and compacting with vibratory roller to cum 2889.00 2,520.20 72,80,857.80
achieve the desired density. (including carriage up to initial lead of 5.0 km
from quarry and carriage of mixed naterials up to 10.0 km initial lead from
mixing plant)
Bituminous Concrete (Providing and laying bituminous concrete with 100-120
TPH batch type hot mix plant producing an average output of 75 tonnes per
hour using crushed aggregates of specified grading, premixed with
bituminous binder @ 5.4 to 5.6 % of mix and filler, transporting the hot mix
to work site, laying with a hydrostatic paver finisher with sensor control to
the required grade, level and alignment, rolling with smooth wheeled,
9.7 5.8 vibratory and tandem rollers to achieve the desired compaction as per
MORTH specification clause No. 509 complete in all respects)(including
carriage up to initial lead of 5.0 km from quarry and carriage of mixed
naterials up to 10.0 km initial lead from mixing plant)(Including cost of testing
of materials at sitfe and laboratory as directed by the depttt.)

for Grading-II (With 40/60 or VG -40 grade bitumen) (for Grading II ( 13


(ii) cum 1155.60 10,483.41 1,21,14,628.60
mm nominal size )
Reinforced Cement Concrete Crash Barrier (M20)
Provision of an Reinforced cement concrete crash barrier at the edges of the
road, approaches to bridge structures and medians, constructed with M-20
grade concrete with HYSD reinforcement conforming to IRC:21 and dowel
bars 25 mm dia, 450 mm long at expansion joints filled with pre-moulded
9.11 8.22 metre 2622.00 3,724.73 97,66,242.06
asphalt filler board, keyed to the structure on which it is built and installed as
per design given in the enclosure to MOST circular No. RW/NH - 33022/1/94-
DO III dated 24 June 1994 as per dimensions in the approved drawing and at
locations directed by the Engineer, all as specified

Total of Bill No.-9 6,55,19,735.68


BILL OF QUANTITIES & COST ESTIMATE
BILL NO. 10. UTILITY DUCT

SOR Item Ref.of RATE AMOUNT


SL. NO. DESCRIPTION UNIT QUANTITY
No. MoRT&H (INR) (INR)

1 Non-Sch Laying of utility duct of HDPE pipe ( Group of 3 pipes 90mm dia.) m 52880.49 843.35 4,45,96,761.24

Total Amount= 4,45,96,761.24


Bill for Structure Works
DETAILED COST ESTIMATES
BILL NO. 11 FOR MAJOR BRIDGES

Ref.of RATE AMOUNT


SL. NO. SOR Ref. No DESCRIPTION UNIT QUANTITY
MoRT&H (INR) (INR)

B.1 :: FOUNDATION
Excavation for Structures (Earth work in excavation of foundation of
structures as per drawing and technical specification, including setting out,
12.1 304 construction of shoring and bracing, removal of stumps and other
deleterious matter, dressing of sides and bottom and backfilling with
approved material.)
11.1
I. Ordinary soil
B. Mechanical Means
(b) with dewatering
(i) Depth upto 3 m cum 1795.340 63.63 1,14,237.48
(ii) Depth 3 m to 6 m cum 224.000 72.72 16,289.28
1500,170 Plain/Reinforced cement concrete in open foundation complete as per
12.8 0 &2100 drawing and technical specifications including steel shuttering forrmwork

11.2 A. Without plasticiser


(a) PCC Grade M15 cum 94.500 7,261.97 6,86,256.17
12.38 RCC Pile Cap M30
(A) III.(ii) Using Batching Plant, Transit Mixer and Concrete Pump cum 1061.740 9,271.96 98,44,410.81
1200 & Providing steel liner 10 mm thick for curbs and 6mm thick for steining of
11.3 12.22 1900 wells including fabricating and setting out as per detailed drawing tonne 9.590 1,01,343.50 9,71,884.17

1100 & Bored cast-in-situ M35 grade R.C.C. pile excluding reinforcement complete
1700 as per drawing and technical specifications and removal of excavated earth
11.4 12.25A metre 1734.000 17,494.79 3,03,35,965.86
with all lifts and lead upto 1000 m. (Pile diameter-1200 mm)

1600 Reinforcement in foundation :Supplying, fitting and placing un-


12.40 coatedTMT bar reinforcement in foundation complete as per drawing and
technical specifications
11.5 From primary sources: TATA/SAIL/Esser Steel/Jindal steel/Shyam steel
(a)
TMT Corrosion Resistance Steel (CRS) reinforcement bar of Fe-500 N/mm2
(i) tonne 320.977 67,540.82 2,16,79,049.78

TOTAL FOR B.1 :: FOUNDATION 6,36,48,093.55


Ref.of RATE AMOUNT
SL. NO. SOR Ref. No DESCRIPTION UNIT QUANTITY
MoRT&H (INR) (INR)

B.2 :: SUBSTRUCTURE
13.5 (N) .A 1500,170 Plain/Reinforced cement concrete in sub-structure complete as per drawing
.g.(i)-case II 0 &2200 and technical specifications
RCC Grade M30
Height upto 5m
With Batching Plant, Transit Mixer and Concrete Pump cum 456.81 9,765.03 44,60,763.35
11.6 13.5 (N) .A Height 5m to 10m
.g.(ii)-case II
With Batching Plant, Transit Mixer and Concrete Pump cum 186.16 10,033.69 18,67,871.73
h. RCC Grade M35
(i) Height 5m to 10m
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 42.060 10,630.08 4,47,101.16
1600 Supplying, fitting and placing TMT bar reinforcement in sub-structure
13.6 (a) (i)
&2200 complete as per drawing and technical specifications
From primary sources: TATA/SAIL/Esser Steel/Jindal steel/Shyam steel
11.7

TMT Corrosion Resistance Steel (CRS) reinforcement bar of Fe-500 N/mm2


tonne 95.904 67,619.60 64,84,990.12
2200 Providing weep holes in Brick masonry/Plain/Reinforced concrete
&2706 abutment, wing wall/return wall with 100 mm dia AC pipe, extending
11.8 13.8 through the full width of the structure with slope of 1V :20H towards each 378.000 1,887.84 7,13,603.52
drawing foce. Complete as per drawing and Technical specifications

710.1.4 of Back filling behind abutment, wing wall and return wall complete as per
13.9 IRC:78 & drawing and Technical specification
11.9 2200
A Granular material cum 245.700 2,076.18 5,10,117.43
B Sandy material cum 1019.540 2,410.87 24,57,978.40
Ref.of RATE AMOUNT
SL. NO. SOR Ref. No DESCRIPTION UNIT QUANTITY
MoRT&H (INR) (INR)

710.1.4 of Providing and laying of Filter media with granular materials/stone crushed
IRC:78 & aggregates satisfying the requirements laid down in clause 2504.2.2. of
2200 MoRTH specifications to a thickness of not less than 600 mm with smaller
size towards the soil and bigger size towards the wall and provided over the
11.10 13.10 cum 285.880 2,376.15 6,79,293.76
entire surface behind abutment, wing wall and return wall to the full height
compacted to a firm condition complete as per drawing and technical
specification.

2000 & Supplying, fitting and fixing in position true to line and level sliding plate
2200 bearing with PTFE surface sliding on stainless steel complete including all
tonne
11.11 13.13 accessories as per drawing and Technical Specifications and BS: 5400, 9600.000 459.55 44,11,680.00
capacity
section 9.1 & 9.2 (for PTFE) and clause 2004 of MoRTH Specifications.

2000 & Supplying, fitting and fixing in position true to line and level elastomeric
2200 bearing conforming to IRC: 83 (Part-II) section IX and clause 2005 of MoRTH cubic
11.12 13.14 639150.000 1.26 8,05,329.00
specifications complete including all accessories as per drawing and centimetre
Technical Specifications.

TOTAL FOR B.2 :: SUBSTRUCTURE 2,28,38,728.48

B.3 :: SUPERSTRUCTURE
1500 Furnishing and Placing Reinforced/Prestressed cement concrete in super-
14.1 A. III.case -
,1600 & structure as per drawing and Technical Specification
II(i) a
1700
RCC Grade M 30
Using Batching Plant, Transit Mixer and Concrete Pump.
11.13 For solid slab super-structure
Height upto 5m cum 15.250 10,643.72 1,62,316.73
14.1 A. VI .(i) PSC Grade M-45
a).
For solid slab/voided slab super-structure
Height upto 5m cum 891.960 11,642.07 1,03,84,260.76
High tensile steel wires/strands including all accessories for stressing,
11.14 14.3 stressing operations and grouting complete as per drawing and Technical tonne 44.000 2,58,974.82 1,13,94,892.08
Specifications
Supplying, Fitting, Fixing TMT Bar-From primary sources: TATA/SAIL/Esser
11.15 14.2 (a). (i) Steel/Jindal steel/Shyam steel (TMT Corrosion Resistance Steel (CRS) tonne 136.082 68,731.61 93,53,134.95
reinforcement bar of Fe-500 N/mm2
Ref.of RATE AMOUNT
SL. NO. SOR Ref. No DESCRIPTION UNIT QUANTITY
MoRT&H (INR) (INR)

515 & Mastic Asphalt


11.16 14.5
2702
Providing and laying 12 mm thick mastic asphalt wearing course on top of
deck slab excluding prime coat with paving grade bitumen meeting the
requirements given in table 500-29, prepared by using mastic cooker and
laid to required level and slope after cleaning the surface, including
providing antiskid surface with bitumen precoated fine grained hard stone
chipping of 9.5 mm nominal size at the rate of 0.005cum per 10 sqm and at sqm 1287.440 413.32 5,32,124.70
an approximate spacing of 10 cm center to center in both directions,
pressed into surface when the temperature of surfaces not less than 100
deg. C, protruding 1 mm to 4 mm over mastic surface, all complete as per
clause 515.

Providing and laying Bituminious wearing course comprising of tack coat


with bitumen emulsion CSS-1 h as per APWD SOR item no 5.2 & MoRT&H
Specification Nos 503,6mm thick mastic asphalt as per APWD SOR item no
14.5& MoRT&H Specification no 515 &2702 and 2 layer of 25 mm thick
11.17 5.8 (ii) cum 51.500 10,483.41 5,39,895.62
asphalt concrete including of close Graded Premix Surfacing (CGPS) material
with Type -a aggregate as per APWD SOR item no 5.11 & MoRT &H
Specification Nos 512 including all lead and lift as directed.

11.18 Tack coat Providing and applying tack coat with bitumen emulsion using
emulsion pressure distributor at the rate of 0.20 kg per sqm on the
5.2 prepared bituminous/granular surface cleaned with mechanical sqm 1,287.44 9.12 11,741.45
broom.(Including cost of testing of materials at sitfe and laboratory as
directed by the depttt.)
515 & Providing and laying Cement concrete wearing coat M-30 grade including
11.19 14. 4 2702 reinforcement complete as per drawing and Technical Specifications-With cum 15.250 14,089.99 2,14,872.35
batching plant
1500,160 Construction of precast RCC railing of M30 Grade, aggregate size not
0,1700 & exceeding 12 mm, true to line and grade, tolurence of vertical RCC post
2703 not to exceed 1 in 500, centre to centre spacing between vertical post not
11.20 14.6 metre 135.520 2,135.74 2,89,435.48
to exceed 2000 mm, leaving adequate space between vertical post for
expansion, complete as per approved drawings and technical
specifications.
2705 Drainage Spouts complete as per drawing and Technical specification
11.21 14.9 each 20.000 12,618.94 2,52,378.80
2700 PCC M15 Grade leveling course below approach slab complete as per
11.22 14.10 cum 24.670 6,991.29 1,72,475.12
drawing and Technical specification
Ref.of RATE AMOUNT
SL. NO. SOR Ref. No DESCRIPTION UNIT QUANTITY
MoRT&H (INR) (INR)

Reinforced Cement Concrete Crash Barrier (Provision of an Reinforced


cement concrete crash barrier at the edges of the road, approaches to
bridge structures and medians, constructed with M-40 grade concrete with
HYSD reinforcement conforming to IRC:21 and dowel bars 25 mm dia, 450
mm long at expansion joints filled with pre-moulded asphalt filler board,
11.23 8.22 (ii) 809 metre 271.04 4,717.58 12,78,652.88
keyed to the structure on which it is built and installed as per design given
in the enclosure to MORT&H circular No. RW/NH - 33022/1/94-DO III dated
June 1994 as per dimensions in the approved drawing and at locations
directed by the Engineer, all as specified)

1500,160 Reinforced cement concrete approach slab including reinforcement and


14.11(a) 0,1700 & formwork complete as per drawing and Technical specification
11.24
2704
With TATA make TMT CRS(Fe-500) grade rebar cum 50.610 12,506.28 6,32,942.83
14.18 2605 Filler joint
Providing & fixing 2 mm thick corrugated copper plate in expansion joint
(i) metre 48.200 2,029.09 97,802.14
complete as per drawing & Technical Specification.
Providing & fixing 20 mm thick compressible fibre board in expansion joint
(ii) metre 48.200 690.84 33,298.49
complete as per drawing & Technical Specification.
Providing and fixing in position 20 mm thick premoulded joint filler in
11.25 expansion joint for fixed ends of simply supported spans not exceeding 10 m
(iii) to cater for a horizontal movement upto 20 mm, covered with sealant metre 48.200 392.89 18,937.30
complete as per drawing and technical specifications.

Providing and filling joint sealing compound as per drawings and technical
(iv) specifications with coarse sand and 6% bitumen by weight metre 48.200 19.20 925.44

Strip Seal Expansion Joint (Providing and laying of a strip seal expansion
joint catering to maximum horizontal movement upto 70 mm, complete as
11.26 14.22 2607 per approved drawings and standard specifications to be installed by the metre 50.000 14,606.62 7,30,331.00
manufacturer/supplier or their authorised representative ensuring
compliance to the manufacturer's instructions for installation.)

TOTAL FOR B.3 :: SUPERSTUCTURE 3,61,00,418.12


Ref.of RATE AMOUNT
SL. NO. SOR Ref. No DESCRIPTION UNIT QUANTITY
MoRT&H (INR) (INR)

B.4 :: PROTECTION WORKS


2403 Providing and laying Pitching on slopes laid over prepared filter media
including boulder apron laid dry in front of toe of embankment complete as
15.4
11.27 per drawing and Technical specifications

A Stone/Boulder cum 820.670 1,992.77 16,35,406.56


2504 Providing and laying Filter material underneath pitching in slopes complete
11.28 15.5 cum 410.340 2,522.02 10,34,885.69
as per drawing and Technical specification
2505 Flexible Apron :Construction of flexible apron 1 m thick comprising of loose
11.29 15.11 stone boulders weighing not less than 40 kg beyond curtain wall. cum 193.240 2,019.03 3,90,157.36

TOTAL FOR B.4 :: PROTECTION WORKS 30,60,449.60

B.5::MISCELLANIOUS
803 Painting Two Coats on New Concrete Surfaces (Painting two coats after
11.30 8.8 filling the surface with synthetic enamel paint in all shades on new sqm 1068.820 58.58 62,611.48
plastered concrete surfaces)
11.31 8.4 (iv) Citizen information Board NH Project nos 2.00 2736.50 5,473.00
11.32 12.5 Brick work at median cum 8.76 8500.62 74,465.43

TOTAL FOR B.5 :: MISCELLANIOUS 1,42,549.91

Total of Bill No.11 12,57,90,239.65


DETAILED COST ESTIMATES
BILL NO. 12 FOR MINOR BRIDGES

Ref.of RATE AMOUNT


SL. NO. SOR Ref. No DESCRIPTION UNIT QUANTITY
MoRT&H (INR) (INR)

B.1 :: FOUNDATION
Excavation for Structures (Earth work in excavation of foundation of
structures as per drawing and technical specification, including setting out,
12.1 304 construction of shoring and bracing, removal of stumps and other
deleterious matter, dressing of sides and bottom and backfilling with
approved material.)
12.1
I. Ordinary soil
B. Mechanical Means
(b) with dewatering
(i) Depth upto 3 m cum 13913.804 61.08 8,49,855.16
(ii) Depth 3 m to 6 m cum 1141.843 69.81 79,712.06
1500,1700 Plain/Reinforced cement concrete in open foundation complete as per
12.8
&2100 drawing and technical specifications including steel shuttering forrmwork

12.2 A. Without plasticiser


PCC Grade M15 cum 705.777 6,979.01 49,25,628.09
(g) RCC Grade M30 (Pile Cap)
Case II Using Batching Plant, Transit Mixer and Concrete Pump cum 5004.060 8,909.41 4,45,83,222.20
1200 & Providing steel liner 10 mm thick for curbs and 6mm thick for steining of
12.3 12.22 tonne 0.000 97,296.63 0.00
1900 wells including fabricating and setting out as per detailed drawing
1100 & Bored cast-in-situ M35 grade R.C.C. pile excluding reinforcement complete
1700 as per drawing and technical specifications and removal of excavated earth
12.4 12.25A metre 7552.000 16,804.55 12,69,07,961.60
with all lifts and lead upto 1000 m. (Pile diameter-1200 mm)

1600 Reinforcement in foundation :Supplying, fitting and placing un-


12.4 0 (a).
coatedTMT bar reinforcement in foundation complete as per drawing and
(i)
technical specifications
12.5 From primary sources: TATA/SAIL/Esser Steel/Jindal steel/Shyam steel

TMT Corrosion Resistance Steel (CRS) reinforcement bar of Fe-500 N/mm2


tonne 1424.928 64,846.06 9,24,00,966.58

TOTAL FOR B.1 :: FOUNDATION 26,97,47,345.70


Ref.of RATE AMOUNT
SL. NO. SOR Ref. No DESCRIPTION UNIT QUANTITY
MoRT&H (INR) (INR)

B.2 :: SUBSTRUCTURE
1500,1700 Plain/Reinforced cement concrete in sub-structure complete as per drawing
13.5 (N) .A
12.6 &2200 and technical specifications
.g.(i)-case II
RCC Grade M30
Height upto 5m
With Batching Plant, Transit Mixer and Concrete Pump cum 3547.847 9,382.81 3,32,88,773.02
13.5 (N) .A Height 5m to 10m
.g.(ii)-case
II
With Batching Plant, Transit Mixer and Concrete Pump cum 797.690 9,640.72 76,90,305.94
RCC Grade M35 (Pedestals & RB)
13.5 (N) .A
12.7
.h.(i)-case II
Height 5m to 10m
With Batching Plant, Transit Mixer and Concrete Pump cum 133.160 10,213.36 13,60,011.02
1600 Supplying, fitting and placing TMT bar reinforcement in sub-structure
12.8 13.6 (a) (i
&2200 complete as per drawing and technical specifications
From primary sources: TATA/SAIL/Esser Steel/Jindal steel/Shyam steel

TMT Corrosion Resistance Steel (CRS) reinforcement bar of Fe-500 N/mm2


tonne 458.666 64,921.69 2,97,77,344.62
2200 Providing weep holes in Brick masonry/Plain/Reinforced concrete
&2706 abutment, wing wall/return wall with 100 mm dia AC pipe, extending
12.9 13.8 through the full width of the structure with slope of 1V :20H towards each 2168.000 1,812.33 39,29,131.44
drawing foce. Complete as per drawing and Technical specifications
Ref.of RATE AMOUNT
SL. NO. SOR Ref. No DESCRIPTION UNIT QUANTITY
MoRT&H (INR) (INR)

710.1.4 of Back filling behind abutment, wing wall and return wall complete as per
12.10 13.9 IRC:78 & drawing and Technical specification
2200
A Granular material cum 1447.601 2,000.76 28,96,302.18
B Sandy material cum 4905.052 2,314.44 1,13,52,447.94
710.1.4 of Providing and laying of Filter media with granular materials/stone crushed
IRC:78 & aggregates satisfying the requirements laid down in clause 2504.2.2. of
2200 MoRTH specifications to a thickness of not less than 600 mm with smaller
size towards the soil and bigger size towards the wall and provided over the
12.11 13.10 cum 1607.224 2,288.73 36,78,502.82
entire surface behind abutment, wing wall and return wall to the full height
compacted to a firm condition complete as per drawing and technical
specification.

2000 & Supplying, fitting and fixing in position true to line and level elastomeric
cubic
2200 bearing conforming to IRC: 83 (Part-II) section IX and clause 2005 of MoRTH
12.12 13.14 centimetr 1039200.000 1.21 12,57,432.00
specifications complete including all accessories as per drawing and
e
Technical Specifications.
2000 & Supplying, fitting and fixing in position true to line and level POT-PTFE
2200 bearing consisting of a metal piston supported by a disc or unreinforced
elastomer confined within a metal cylinder, sealing rings, dust seals, PTFE
surface sliding against stainless steel mating surface, completre assembly
tonne
12.13 13.16 to be of cast steel/fabricated structural steel, metal and elastomer 40800.000 441.17 1,79,99,736.00
capacity
elements to be as per IRC: 83 part-I & II respectively and other parts
conforming to BS: 5400, section 9.1 & 9.2 and clause 2006 of MoRTH
Specifications complete asper drawing and approved technical
specifications.

TOTAL FOR B.2 :: SUBSTRUCTURE 11,32,29,986.97


Ref.of RATE AMOUNT
SL. NO. SOR Ref. No DESCRIPTION UNIT QUANTITY
MoRT&H (INR) (INR)

B.3 :: SUPERSTRUCTURE
14.1 A. 1500 ,1600 Furnishing and Placing Reinforced/Prestressed cement concrete in super-
12.14 III.case -II(i) & 1700 structure as per drawing and Technical Specification
a
Without plasticiser
RCC Grade M 30
Using Batching Plant, Transit Mixer and Concrete Pump.
For T-Beam
Height upto 5m cum 3948.694 10,644.25 4,20,30,880.79
14.1 A. VI PSC Grade M-45
.(i) a)
For solid slab/voided slab super-structure
Height upto 5m cum 698.910 11,205.92 78,31,929.55
Reinforcement in Super Structure: Supplying, fitting and placing TMT bar
14.2 (a).
12.15 1600 reinforcement in super-structure including splicing complete as per
(i)
drawing and technical specifications
From primary sources: TATA/SAIL/Esser Steel/Jindal steel/Shyam steel

TMT Corrosion Resistance Steel (CRS) reinforcement bar of Fe-500 N/mm2


tonne
706.873 65,989.22 4,66,45,998.73
High tensile steel wires/strands including all accessories for stressing,
12.16 14.3 1800 stressing operations and grouting complete as per drawing and Technical tonne 29.000 2,48,618.00 72,09,922.00
Specifications
Ref.of RATE AMOUNT
SL. NO. SOR Ref. No DESCRIPTION UNIT QUANTITY
MoRT&H (INR) (INR)

Mastic Asphalt
12.17 14.5 (A) 515 & 2702
Providing and laying 12 mm thick mastic asphalt wearing course on top of
deck slab excluding prime coat with paving grade bitumen meeting the
requirements given in table 500-29, prepared by using mastic cooker and
laid to required level and slope after cleaning the surface, including
providing antiskid surface with bitumen precoated fine grained hard stone
chipping of 9.5 mm nominal size at the rate of 0.005cum per 10 sqm and at sqm 7217.810 396.86 28,64,460.08
an approximate spacing of 10 cm center to center in both directions,
pressed into surface when the temperature of surfaces not less than 100
deg. C, protruding 1 mm to 4 mm over mastic surface, all complete as per
clause 515.

Providing and laying Bituminious wearing course comprising of tack coat


with bitumen emulsion CSS-1 h as per APWD SOR item no 5.2 & MoRT&H
Specification Nos 503,6mm thick mastic asphalt as per APWD SOR item no
14.5& MoRT&H Specification no 515 &2702 and 2 layer of 25 mm thick
12.18 5.8 (ii) cum 288.720 10,483.41 30,26,770.14
asphalt concrete including of close Graded Premix Surfacing (CGPS) material
with Type -a aggregate as per APWD SOR item no 5.11 & MoRT &H
Specification Nos 512 including all lead and lift as directed.

Tack coat Providing and applying tack coat with bitumen emulsion using
emulsion pressure distributor at the rate of 0.20 kg per sqm on the
12.19 5.2 (I) (a) prepared bituminous/granular surface cleaned with mechanical sqm 7217.810 9.12 65,826.43
broom.(Including cost of testing of materials at sitfe and laboratory as
directed by the depttt.)

Providing and laying Cement concrete wearing coat M-30 grade including
12.20 14. 4 reinforcement complete as per drawing and Technical Specifications-With cum 79.239 13,535.26 10,72,517.08
batchimg plant
Drainage Spouts complete as per drawing and Technical specification
12.21 14.9 2705 each
110.000 12,114.18 13,32,559.80
PCC M15 Grade leveling course below approach slab complete as per
12.22 14.10 2700 cum 169.624 6,719.16
drawing and Technical specification 11,39,727.84
1500,1600, Reinforced cement concrete approach slab including reinforcement and
12.23 14.11 (a) 1700 & formwork complete as per drawing and Technical specification
2704
With TATA make TMT CRS(Fe-500) grade rebar cum 348.286 12,014.73 41,84,562.25
Ref.of RATE AMOUNT
SL. NO. SOR Ref. No DESCRIPTION UNIT QUANTITY
MoRT&H (INR) (INR)

12.24 14.18 2605 Filler joint


Providing & fixing 2 mm thick corrugated copper plate in expansion joint
(i) metre 372.720 1,947.93 7,26,032.47
complete as per drawing & Technical Specification.
Providing & fixing 20 mm thick compressible fibre board in expansion joint
(ii) metre 372.720 663.21 2,47,191.63
complete as per drawing & Technical Specification.
Providing and fixing in position 20 mm thick premoulded joint filler in
expansion joint for fixed ends of simply supported spans not exceeding 10 m
(iii) to cater for a horizontal movement upto 20 mm, covered with sealant metre 372.720 377.17 1,40,578.80
complete as per drawing and technical specifications.

Providing and filling joint sealing compound as per drawings and technical
(iv) specifications with coarse sand and 6% bitumen by weight metre 372.720 18.44 6,872.96

12.25 8.22 (ii) RCC Crash Barrier(M 40 grade concrete) metre 1540.380 4,531.62 69,80,416.82
12.26 14.6 Precast RCC Railing-With batching plant metre 704.190 2,051.15 14,44,399.32
Strip Seal Expansion Joint (Providing and laying of a strip seal expansion
joint catering to maximum horizontal movement upto 70 mm, complete as
per approved drawings and standard specifications to be installed by the
12.27 14.22 2607 metre 197.600 14,022.36 27,70,818.34
manufacturer/supplier or their authorised representative ensuring
compliance to the manufacturer's instructions for installation.)

12.28 HDPE Pipe metre 330.750 1,500.00 4,96,125.00

TOTAL FOR B.3 :: SUPERSTRUCTURE 13,02,17,590.01


Ref.of RATE AMOUNT
SL. NO. SOR Ref. No DESCRIPTION UNIT QUANTITY
MoRT&H (INR) (INR)

B.4 :: PROTECTION WORKS


Providing and laying Flooring complete as per drawing and Technical
12.29 2505 2403
specifications laid over cement concert bedding.
A Rubble stone laid in cement mortar 1:3 cum 179.699 6,406.09 11,51,166.69
2505 Boulder apron laid in wire crates (Providing and laying of boulder apron
laid in wire crates made with 4mm dia GI wire conforming to IS: 280 &
12.30 15.2 IS:4826 in 100mm x 100mm mesh (weaved diagonally) including 10% extra cum 1942.084 1,920.34 37,29,461.59
for laps and joints laid with stone boulders weighing not less than 40 kg
each.)
Providing and laying Filter material underneath pitching in slopes complete
12.31 15.5 2507.2 cum
as per drawing and Technical specification 971.040 2,429.87 23,59,500.96
Flexible Apron :Construction of flexible apron 750 mm thick comprising of
12.32 15.11 304 loose stone boulders weighing not less than 40 kg beyond curtain wall. cum 245.993 1,945.55 4,78,590.71

13.5 (N) .A 1500,1700 Plain/Reinforced cement concrete in sub-structure complete as per drawing
12.33
.b &2200 and technical specifications
12.8 A (a) PCC Grade M15 cum 286.334 6,979.01 19,98,324.71
12.34 15.10 (B) 2507.2 Curtain Wall-Cement concrete Grade M20 cum 249.202 7,738.78 19,28,516.36
12.1 I . Excavation for Structures
12.35 304 cum 1327.704 61.08
B. (b).(i) 81,096.16
12.36 15.11 304 Falling Apron on River Bed cum 990.140 1,945.55 19,26,366.88

TOTAL FOR B.4 :: PROTECTION WORKS 1,36,53,024.05

B.5:: MISCALLAENEOUS WORKS


Painting Two Coats on New Concrete Surfaces (Painting two coats after
12.37 8.8 803 filling the surface with synthetic enamel paint in all shades on new sqm 5740.870 58.58
plastered concrete surfaces) 3,36,300.16
12.38 8.4 (iv) Citizen information Board NH Project nos 12.000 2,736.50 32,838.00
12.39 12.5 Brick work at median cum 29.380 8,161.65 2,39,789.28

TOTAL FOR B.5:: MISCALLAENEOUS WORKS 6,08,927.44

Total of Bill No.12 52,74,56,874.17


DETAILED COST ESTIMATES
BILL NO. 13 FOR ROB

SOR Ref. Ref.of RATE AMOUNT


SL. NO. DESCRIPTION UNIT QUANTITY
No MoRT&H (INR) (INR)

B.1 :: FOUNDATION
Excavation for Structures (Earth work in excavation of foundation of structures as
per drawing and technical specification, including setting out, construction of
13.1 12.1 304 shoring and bracing, removal of stumps and other deleterious matter, dressing of
sides and bottom and backfilling with approved material.)

I. Ordinary soil
B. Mechanical Means
(b) with dewatering
(i) Depth upto 3 m cum 14123.630 63.63 8,98,686.58
(ii) Depth 3 m to 6 m cum 439.080 69.81 30,652.17
Bored cast-in-situ M35 grade R.C.C. pile excluding reinforcement complete as per
1100 & drawing and technical specifications and removal of excavated earth with all lifts
13.2 12.25A metre 10868.000 17,494.79 19,01,33,377.72
1700 and lead upto 1000 m. (Pile diameter-1200 mm)
RCC Pile Cap M30 -Using Batching Plant, Transit Mixer and Concrete Pump
12.38 (A)
13.3 cum 9552.150 9,271.96
III.(ii)
8,85,67,152.71
1100 & Levelling course for Pile cap
13.4 12.39 cum 1441.900 6,848.88
1700 98,75,400.07
Reinforcement in foundation :Supplying, fitting and placing un-coatedTMT bar
12.4 0 (a). reinforcement in foundation complete as per drawing and technical specifications
13.5 1600
(i)

From primary sources: TATA/SAIL/Esser Steel/Jindal steel/Shyam steel


TMT Corrosion Resistance Steel (CRS) reinforcement bar of Fe-500 N/mm2 tonne 2301.640 67,540.82 15,54,54,652.94
13.6 12.5 Brick masonry work (1:3) cum 140.220 8,500.62 11,91,956.94

TOTAL FOR B.1 :: FOUNDATION 44,61,51,879.14


SOR Ref. Ref.of RATE AMOUNT
SL. NO. DESCRIPTION UNIT QUANTITY
No MoRT&H (INR) (INR)

B.2 :: SUBSTRUCTURE
13.5 (N) 1500,1700 Plain/Reinforced cement concrete in sub-structure complete as per drawing and
13.7 .A .g.(i)- &2200 technical specifications
case II
Without plasticiser
RCC Grade M35
13.5 (N) .A
.h.(i)-case II
Height upto 5m
With Batching Plant, Transit Mixer and Concrete Pump cum 1806.290 10,406.87 1,87,97,825.21
(ii) Height 5m to 10m
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 3525.060 10,630.08 3,74,71,669.80
(iii) Height above 10m
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 1599.300 10,963.38 1,75,33,733.63
Supplying, fitting and placing TMT bar reinforcement in sub-structure complete as
13.8 13.6 (a) (i) 1600 &2200
per drawing and technical specifications
From primary sources: TATA/SAIL/Esser Steel/Jindal steel/Shyam steel
TMT Corrosion Resistance Steel (CRS) reinforcement bar of Fe-500 N/mm2 tonne 980.660 67,619.60 6,63,11,836.94
Pin Bearing tonne
13.9 3720.000 1,473.59
capacity 54,81,754.80
2000 & Supplying, fitting and fixing in position true to line and level sliding plate bearing
2200 with PTFE surface sliding on stainless steel complete including all accessories as per tonne
13.10 13.13 30720.000 459.55
drawing and Technical Specifications and BS: 5400, section 9.1 & 9.2 (for PTFE) capacity
and clause 2004 of MoRTH Specifications. 1,41,17,376.00
Metallic guide bearing tonne
13.11 3720.000 1,473.59
capacity 54,81,754.80
13.12 13.14 Elastomeric bearing CCUM 15872366.0 1.26 1,99,99,181.16
Reinforced/Prestressed cement concrete in super-structure -PSC M40
13.13 cum 74.020 11,751.48
Superstructure 8,69,844.55

TOTAL FOR B.2 :: SUBSTRUCTURE 18,60,64,976.90


SOR Ref. Ref.of RATE AMOUNT
SL. NO. DESCRIPTION UNIT QUANTITY
No MoRT&H (INR) (INR)

B.3 :: SUPERSTRUCTURE
14.1 A. 1500 ,1600 Furnishing and Placing Reinforced/Prestressed cement concrete in super-structure
13.14 III.case - & 1700 as per drawing and Technical Specification
II(i) a).
Without plasticiser
RCC/PSC Grade M35
Using Batching Plant, Transit Mixer and Concrete Pump
For solid slab super-structure
Height upto 5m cum 7921.880 11,133.06 8,81,94,765.35
VI. PSC Grade M-45
(i) For solid slab/voided slab super-structure
a) Height upto 5m cum 1803.100 11,642.07 2,09,91,816.42
Reinforcement in Super Structure: Supplying, fitting and placing TMT bar
14.2 (a).
13.15 1600 reinforcement in super-structure including splicing complete as per drawing and
(i)
technical specifications
From primary sources: TATA/SAIL/Esser Steel/Jindal steel/Shyam steel
TMT Corrosion Resistance Steel (CRS) reinforcement bar of Fe-500 N/mm2 tonne 1750.500 68,731.61 12,03,14,683.31
Supply, fabrication, delivery at bridge site and erection of structural steel works as
13.16 non sch per IS 2062, including two coats of primer, one at shop and the other at site and tonne 2115.520 1,09,970.92 23,26,45,680.68
two coats of aluminium paints including all labour, material, consumables etc.
SOR Ref. Ref.of RATE AMOUNT
SL. NO. DESCRIPTION UNIT QUANTITY
No MoRT&H (INR) (INR)

13.17 14.5 (A) 515 & 2702 Mastic Asphalt


Providing and laying 12 mm thick mastic asphalt wearing course on top of deck slab
excluding prime coat with paving grade bitumen meeting the requirements given in
table 500-29, prepared by using mastic cooker and laid to required level and slope
after cleaning the surface, including providing antiskid surface with bitumen
precoated fine grained hard stone chipping of 9.5 mm nominal size at the rate of sqm 17029.910 396.86 67,58,490.08
0.005cum per 10 sqm and at an approximate spacing of 10 cm center to center in
both directions, pressed into surface when the temperature of surfaces not less
than 100 deg. C, protruding 1 mm to 4 mm over mastic surface, all complete as
per clause 515.
Providing and laying Bituminious wearing course comprising of tack coat with
bitumen emulsion CSS-1 h as per APWD SOR item no 5.2 & MoRT&H Specification
Nos 503,6mm thick mastic asphalt as per APWD SOR item no 14.5& MoRT&H
13.18 5.8 (ii) Specification no 515 &2702 and 2 layer of 25 mm thick asphalt concrete including of cum 851.490 10,483.41 89,26,518.78
close Graded Premix Surfacing (CGPS) material with Type -a aggregate as per
APWD SOR item no 5.11 & MoRT &H Specification Nos 512 including all lead and
lift as directed.
Tack coat Providing and applying tack coat with bitumen emulsion using emulsion
pressure distributor at the rate of 0.20 kg per sqm on the prepared
13.19 5.2 bituminous/granular surface cleaned with mechanical broom.(Including cost of sqm 17029.910 9.12 1,55,312.78
testing of materials at sitfe and laboratory as directed by the depttt.)

Providing, fitting and fixing mild steel railing complete as per drawing and Technical
13.20 14.8 metre
1086.480 2,087.16 22,67,657.60
Specification
13.21 14.9 2705 Drainage Spouts complete as per drawing and Technical specification each 328.000 12,618.94 41,39,012.32
2700 PCC M15 Grade leveling course below approach slab complete as per drawing and
13.22 14.10 cum
11.630 6,991.29 81,308.70
Technical specification
Reinforced Cement Concrete Crash Barrier (Provision of an Reinforced cement
concrete crash barrier at the edges of the road, approaches to bridge structures
and medians, constructed with M-40 grade concrete with HYSD reinforcement
conforming to IRC:21 and dowel bars 25 mm dia, 450 mm long at expansion joints
13.23 8.22 (ii) 809 filled with pre-moulded asphalt filler board, keyed to the structure on which it is metre 3596.640 4,717.58 1,69,67,436.93
built and installed as per design given in the enclosure to MORT&H circular No.
RW/NH - 33022/1/94-DO III dated June 1994 as per dimensions in the approved
drawing and at locations directed by the Engineer, all as specified)
SOR Ref. Ref.of RATE AMOUNT
SL. NO. DESCRIPTION UNIT QUANTITY
No MoRT&H (INR) (INR)

13.24 14.18 2605 Filler joint


Providing & fixing 2 mm thick corrugated copper plate in expansion joint complete
(i) as per drawing & Technical Specification. metre 86.160 2,029.09 1,74,826.39
Providing & fixing 20 mm thick compressible fibre board in expansion joint
(ii) metre 86.160 690.84
complete as per drawing & Technical Specification. 59,522.77
Providing and fixing in position 20 mm thick premoulded joint filler in expansion
joint for fixed ends of simply supported spans not exceeding 10 m to cater for a
(iii) metre 86.160 392.89
horizontal movement upto 20 mm, covered with sealant complete as per drawing
and technical specifications. 33,851.40
Providing and filling joint sealing compound as per drawings and technical
(iv) metre 86.160 19.20
specifications with coarse sand and 6% bitumen by weight 1,654.27
Strip Seal Expansion Joint (Providing and laying of a strip seal expansion joint
catering to maximum horizontal movement upto 70 mm, complete as per
13.25 14.22 2607 approved drawings and standard specifications to be installed by the metre 766.040 14,606.62 1,11,89,255.18
manufacturer/supplier or their authorised representative ensuring compliance to
the manufacturer's instructions for installation.)
13.26 8.1 (A) RCC M30 Kerb M 24.580 377.81 9,286.57
Non- Reciever pipe for Drainage Spout
13.27 metre
400.000 150.00 60,000.00
Sch

TOTAL FOR B.3 :: SUPERSTRUCTURE 51,29,71,079.54


SOR Ref. Ref.of RATE AMOUNT
SL. NO. DESCRIPTION UNIT QUANTITY
No MoRT&H (INR) (INR)

B.4 :: MISCELLANEOUS
Painting Two Coats on New Concrete Surfaces (Painting two coats after filling the
13.28 8.8 803 surface with synthetic enamel paint in all shades on new plastered concrete sqm 11769.900 58.58 6,89,480.74
surfaces)
13.29 non sch Inspection ladder tonne 10.889 1,09,970.92 11,97,418.36
13.30 non sch Stair tonne 234.620 1,09,970.92 2,58,01,377.25

TOTAL FOR B.4 :: MISCELLANEOUS 2,76,88,276.35

Total of Bill No.13 Total= 1,17,28,76,211.93


DETAILED COST ESTIMATES
BILL NO. 14 FOR VUP

SOR Ref. Ref.of RATE AMOUNT


SL. NO. DESCRIPTION UNIT QUANTITY
No MoRT&H (INR) (INR)

B.1 :: FOUNDATION
Excavation for Structures (Earth work in excavation of foundation of structures as
per drawing and technical specification, including setting out, construction of
12.1 304 shoring and bracing, removal of stumps and other deleterious matter, dressing of
sides and bottom and backfilling with approved material.)
14.1
I. Ordinary soil
B. Mechanical Means
(b) with dewatering
(i) Depth upto 3 m cum 1089.350 61.08 66,537.50
1500,1700 Plain/Reinforced cement concrete in open foundation complete as per drawing
12.8
&2100 and technical specifications including steel shuttering forrmwork
A. Without plasticiser
14.2
PCC Grade M15 cum 67.950 6,979.01 4,74,223.73
(g) RCC Grade M30
Case II Using Batching Plant, Transit Mixer and Concrete Pump cum 591.940 8,909.41 52,73,836.16
1100 & Bored cast-in-situ M35 grade R.C.C. pile excluding reinforcement complete as per
14.3 12.25A 1700 drawing and technical specifications and removal of excavated earth with all lifts metre
and lead upto 1000 m. (Pile diameter-1200 mm)
1146.000 16,804.55 1,92,58,014.30
1600 Reinforcement in foundation :Supplying, fitting and placing un-coatedTMT bar
12.40(a). reinforcement in foundation complete as per drawing and technical specifications
(i)
14.4
From primary sources: TATA/SAIL/Esser Steel/Jindal steel/Shyam steel
TMT Corrosion Resistance Steel (CRS) reinforcement bar of Fe-500 N/mm2 tonne 190.795 64,846.06 1,23,72,304.02

TOTAL FOR B.1 :: FOUNDATION 3,74,44,915.70


SOR Ref. Ref.of RATE AMOUNT
SL. NO. DESCRIPTION UNIT QUANTITY
No MoRT&H (INR) (INR)

B.2 :: SUBSTRUCTURE
13.5 (N) 1500,1700 Plain/Reinforced cement concrete in sub-structure complete as per drawing and
14.5 .A .g.(i)- &2200 technical specifications
case II
Without plasticiser
RCC Grade M30
Height upto 5m
With Batching Plant, Transit Mixer and Concrete Pump cum 195.310 9,382.81 18,32,556.62
Height 5m to 10m
With Batching Plant, Transit Mixer and Concrete Pump cum 225.820 9,640.72 21,77,067.39
Height above 10m
With Batching Plant, Transit Mixer and Concrete Pump cum 132.230 10,008.20 13,23,384.29
RCC Grade M35 (Pedestals & RB)
Height 5m to 10m
With Batching Plant, Transit Mixer and Concrete Pump cum 39.610 10,213.36 4,04,551.19
1600 Supplying, fitting and placing TMT bar reinforcement in sub-structure complete as
14.6 13.6(a) (i)
per drawing and technical specifications
&2200
From primary sources: TATA/SAIL/Esser Steel/Jindal steel/Shyam steel
TMT Corrosion Resistance Steel (CRS) reinforcement bar of Fe-500 N/mm2 tonne 55.289 64,921.69 35,89,455.32
710.1.4 of Back filling behind abutment, wing wall and return wall complete as per drawing
14.7 13.9 IRC:78 & and Technical specification
2200
A Granular material cum 187.200 2,000.76 3,74,542.27
2000 & Supplying, fitting and fixing in position true to line and level elastomeric bearing
14.8 13.14 2200 conforming to IRC: 83 (Part-II) section IX and clause 2005 of MoRTH specifications cubic centimetre 207840.000 1.21 2,51,486.40
complete including all accessories as per drawing and Technical Specifications.

2000 & Supplying, fitting and fixing in position true to line and level sliding plate
2200 bearing with PTFE surface sliding on stainless steel complete including all
14.9 13.13 tonne capacity 9600.000 441.17 42,35,232.00
accessories as per drawing and Technical Specifications and BS: 5400,
section 9.1 & 9.2 (for PTFE) and clause 2004 of MoRTH Specifications.

TOTAL FOR B.2 :: SUBSTRUCTURE 1,41,88,275.48


SOR Ref. Ref.of RATE AMOUNT
SL. NO. DESCRIPTION UNIT QUANTITY
No MoRT&H (INR) (INR)

B.3 :: SUPERSTRUCTURE
14.1 A. 1500 ,1600 Furnishing and Placing Reinforced/Prestressed cement concrete in super-structure
14.10 III.case - & 1700 as per drawing and Technical Specification
II(i) a
Without plasticiser
RCC Grade M 30
Using Batching Plant, Transit Mixer and Concrete Pump.
For T-Beam
Height upto 5m cum 58.800 10,644.25 6,25,881.90
14.11 V. PSC Grade M-40
Case II Using Batching Plant, Transit Mixer and Concrete Pump
(ii) For T-beam & slab
a) Height upto 5m cum 288.670 11,289.95 32,59,069.87
14.1 A. VI PSC Grade M-45
14.12
.(i) a).
For solid slab/voided slab super-structure
Height upto 5m cum 545.370 11,205.92 61,11,372.59
Reinforcement in Super Structure: Supplying, fitting and placing TMT bar
14.2 (a).
14.13 1600 reinforcement in super-structure including splicing complete as per drawing and
(i)
technical specifications
From primary sources: TATA/SAIL/Esser Steel/Jindal steel/Shyam steel
TMT Corrosion Resistance Steel (CRS) reinforcement bar of Fe-500 N/mm2 tonne 133.926 65,989.22 88,37,672.28
High tensile steel wires/strands including all accessories for stressing, stressing
14.14 14.3 1800 operations and grouting complete as per drawing and Technical Specifications tonne 28.000 2,48,618.00 69,61,304.00
SOR Ref. Ref.of RATE AMOUNT
SL. NO. DESCRIPTION UNIT QUANTITY
No MoRT&H (INR) (INR)
Mastic Asphalt
14.15 14.5(A) 515 & 2702
Providing and laying 12 mm thick mastic asphalt wearing course on top of deck slab
excluding prime coat with paving grade bitumen meeting the requirements given in
table 500-29, prepared by using mastic cooker and laid to required level and slope
after cleaning the surface, including providing antiskid surface with bitumen
precoated fine grained hard stone chipping of 9.5 mm nominal size at the rate of sqm 1306.440 396.86 5,18,473.78
0.005cum per 10 sqm and at an approximate spacing of 10 cm center to center in
both directions, pressed into surface when the temperature of surfaces not less
than 100 deg. C, protruding 1 mm to 4 mm over mastic surface, all complete as
per clause 515.
Providing and laying Bituminious wearing course comprising of tack coat with
bitumen emulsion CSS-1 h as per APWD SOR item no 5.2 & MoRT&H Specification
Nos 503,6mm thick mastic asphalt as per APWD SOR item no 14.5& MoRT&H
14.16 5.8 (ii) Specification no 515 &2702 and 2 layer of 25 mm thick asphalt concrete including of cum 52.260 10,483.41 5,47,863.01
close Graded Premix Surfacing (CGPS) material with Type -a aggregate as per
APWD SOR item no 5.11 & MoRT &H Specification Nos 512 including all lead and
lift as directed.
Tack coat Providing and applying tack coat with bitumen emulsion using emulsion
pressure distributor at the rate of 0.20 kg per sqm on the prepared
14.17 5.2 (I) (a) bituminous/granular surface cleaned with mechanical broom.(Including cost of sqm 1306.440 9.12 11,914.73
testing of materials at sitfe and laboratory as directed by the depttt.)

14.18 14.9 2705 Drainage Spouts complete as per drawing and Technical specification each 20.000 12,114.18 2,42,283.60
PCC M15 Grade leveling course below approach slab complete as per drawing and
14.19 14.10 2700 cum 7.880 6,719.16 52,946.98
Technical specification
SOR Ref. Ref.of RATE AMOUNT
SL. NO. DESCRIPTION UNIT QUANTITY
No MoRT&H (INR) (INR)

14.20 14.18 2605 Filler joint


Providing & fixing 2 mm thick corrugated copper plate in expansion joint complete
(i) metre 42.000 1,947.93 81,813.06
as per drawing & Technical Specification.
Providing & fixing 20 mm thick compressible fibre board in expansion joint
(ii) metre 42.000 663.21 27,854.82
complete as per drawing & Technical Specification.
Providing and fixing in position 20 mm thick premoulded joint filler in expansion
(iii) joint for fixed ends of simply supported spans not exceeding 10 m to cater for a metre 42.000 377.17
horizontal movement upto 20 mm, covered with sealant complete as per drawing
and technical specifications. 15,841.14
Providing and filling joint sealing compound as per drawings and technical
(iv) metre 42.000 18.44 774.48
specifications with coarse sand and 6% bitumen by weight
8.22 (ii) RCC Crash Barrier(M 40 grade concrete) metre 275.040 4,531.62 12,46,376.76
Strip Seal Expansion Joint (Providing and laying of a strip seal expansion joint
catering to maximum horizontal movement upto 70 mm, complete as per
14.21 14.22 2607 approved drawings and standard specifications to be installed by the metre 63.000 14,022.36 8,83,408.68
manufacturer/supplier or their authorised representative ensuring compliance to
the manufacturer's instructions for installation.)
Non- Reciever pipe for Drainage Spout
14.22 metre 180.000 150.00 27,000.00
Sch

TOTAL FOR B.3 :: SUPERSTRUCTURE 2,94,51,851.68

B.4 :: MISCALLAENEOUS WORKS


Painting Two Coats on New Concrete Surfaces (Painting two coats after filling the
14.23 8.8 803 surface with synthetic enamel paint in all shades on new plastered concrete sqm 607.840 58.58 35,607.27
surfaces)
14.24 8.4 (iv) Citizen information Board NH Project nos 2.000 2,736.50 5,473.00
14.25 12.5 Brick masonry work (1:3) cum 68.250 8,161.65 5,57,032.61

TOTAL FOR B.4 :: MISCALLAENEOUS WORKS 5,98,112.88

Total of Bill No.14 8,16,83,155.74


DETAILED COST ESTIMATES
BILL NO. 15 FOR CULVERT

SOR Ref. Ref.of RATE AMOUNT


SL. NO. DESCRIPTION UNIT QUANTITY
No MoRT&H (INR) (INR)

B.1 :: FOUNDATION
Excavation for Structures (Earth work in excavation of foundation of structures as
per drawing and technical specification, including setting out, construction of
15.1 12.1 304 shoring and bracing, removal of stumps and other deleterious matter, dressing of
sides and bottom and backfilling with approved material.)

I. Ordinary soil
B. Mechanical Means
(b) with dewatering
(i) Depth upto 3 m cum 14419.358 61.08 8,80,734.41
1500,1700 Plain/Reinforced cement concrete in open foundation complete as per drawing
15.2 12.8
&2100 and technical specifications including steel shuttering forrmwork
A. Without plasticiser
PCC Grade M15 cum 1599.766 6,979.01 1,11,64,780.50

TOTAL FOR B.1 :: FOUNDATION 1,20,45,514.91


SOR Ref. Ref.of RATE AMOUNT
SL. NO. DESCRIPTION UNIT QUANTITY
No MoRT&H (INR) (INR)

B.2 :: SUBSTRUCTURE
13.5 (N) 1500,1700 Plain/Reinforced cement concrete in sub-structure complete as per drawing and
15.3 .A .g.(i)- &2200 technical specifications
case II
Without plasticiser
RCC Grade M30
Height upto 5m
With Batching Plant, Transit Mixer and Concrete Pump cum 6753.069 9,382.81 6,33,62,767.37
13.6 (a) 1600 Supplying, fitting and placing TMT bar reinforcement in sub-structure complete as
15.4 per drawing and technical specifications
(i) &2200
From primary sources: TATA/SAIL/Esser Steel/Jindal steel/Shyam steel
TMT Corrosion Resistance Steel (CRS) reinforcement bar of Fe-500 N/mm2 tonne 472.715 64,921.69 3,06,89,447.60
Providing weep holes in Brick masonry/Plain/Reinforced concrete abutment, wing
2200 wall/return wall with 100 mm dia AC pipe, extending through the full width of the
15.5 13.8 each 14184.000 1,812.33 2,57,06,088.72
&2706 structure with slope of 1V :20H towards drawing foce. Complete as per drawing and
Technical specifications
710.1.4 of Back filling behind abutment, wing wall and return wall complete as per drawing
15.6 13.9 IRC:78 & and Technical specification
2200
A Granular material cum 1218.757 2,000.76 24,38,440.26
B Sandy material cum 5723.432 2,314.44 1,32,46,539.77
Providing and laying of Filter media with granular materials/stone crushed
aggregates satisfying the requirements laid down in clause 2504.2.2. of MoRTH
710.1.4 of specifications to a thickness of not less than 600 mm with smaller size towards the
15.7 13.10 IRC:78 & soil and bigger size towards the wall and provided over the entire surface behind cum 7537.715 2,288.73 1,72,51,793.67
2200 abutment, wing wall and return wall to the full height compacted to a firm
condition complete as per drawing and technical specification.

TOTAL FOR B.2 :: SUBSTRUCTURE 15,26,95,077.39


SOR Ref. Ref.of RATE AMOUNT
SL. NO. DESCRIPTION UNIT QUANTITY
No MoRT&H (INR) (INR)

B.3 :: SUPERSTRUCTURE
14.1 A. 1500 ,1600 Furnishing and Placing Reinforced/Prestressed cement concrete in super-structure
15.8 III.case - & 1700 as per drawing and Technical Specification
II(i) a
Without plasticiser
RCC Grade M 30
Using Batching Plant, Transit Mixer and Concrete Pump.
For solid slab super-structure
Height upto 5m cum 1674.245 10,644.25 1,78,21,082.59
Reinforcement in Super Structure: Supplying, fitting and placing TMT bar
14.2 (a).
15.9 1600 reinforcement in super-structure including splicing complete as per drawing and
(i)
technical specifications
From primary sources: TATA/SAIL/Esser Steel/Jindal steel/Shyam steel
TMT Corrosion Resistance Steel (CRS) reinforcement bar of Fe-500 N/mm2 tonne 125.568 65,989.22 82,86,159.24
15.10 14.5 (A) 515 & 2702 Mastic Asphalt
Providing and laying 12 mm thick mastic asphalt wearing course on top of deck slab
excluding prime coat with paving grade bitumen meeting the requirements given in
table 500-29, prepared by using mastic cooker and laid to required level and slope
after cleaning the surface, including providing antiskid surface with bitumen
precoated fine grained hard stone chipping of 9.5 mm nominal size at the rate of sqm 7784.800 396.86 30,89,475.73
0.005cum per 10 sqm and at an approximate spacing of 10 cm center to center in
both directions, pressed into surface when the temperature of surfaces not less
than 100 deg. C, protruding 1 mm to 4 mm over mastic surface, all complete as
per clause 515.
Providing and laying Bituminious wearing course comprising of tack coat with
bitumen emulsion CSS-1 h as per APWD SOR item no 5.2 & MoRT&H Specification
Nos 503,6mm thick mastic asphalt as per APWD SOR item no 14.5& MoRT&H
15.11 5.8 (ii) Specification no 515 &2702 and 2 layer of 25 mm thick asphalt concrete including of cum 311.392 10,483.41 32,64,450.01
close Graded Premix Surfacing (CGPS) material with Type -a aggregate as per
APWD SOR item no 5.11 & MoRT &H Specification Nos 512 including all lead and
lift as directed.
Tack coat Providing and applying tack coat with bitumen emulsion using emulsion
pressure distributor at the rate of 0.20 kg per sqm on the prepared
15.12 5.2 (I) (a) bituminous/granular surface cleaned with mechanical broom.(Including cost of sqm 7784.800 9.12 70,997.38
testing of materials at sitfe and laboratory as directed by the depttt.)
SOR Ref. Ref.of RATE AMOUNT
SL. NO. DESCRIPTION UNIT QUANTITY
No MoRT&H (INR) (INR)

15.13 14.9 2705 Drainage Spouts complete as per drawing and Technical specification each 150.000 12,114.18 18,17,127.00
2700 PCC M15 Grade leveling course below approach slab complete as per drawing and
15.14 14.10 cum 907.451 6,719.16 60,97,306.71
Technical specification
Reinforced Cement Concrete Crash Barrier (Provision of an Reinforced cement
concrete crash barrier at the edges of the road, approaches to bridge structures
and medians, constructed with M-40 grade concrete with HYSD reinforcement
conforming to IRC:21 and dowel bars 25 mm dia, 450 mm long at expansion joints
15.15 8.22 (ii) 809 filled with pre-moulded asphalt filler board, keyed to the structure on which it is metre 1427.400 4,531.62 64,68,434.39
built and installed as per design given in the enclosure to MORT&H circular No.
RW/NH - 33022/1/94-DO III dated June 1994 as per dimensions in the approved
drawing and at locations directed by the Engineer, all as specified)
1500,1600, Reinforced cement concrete approach slab including reinforcement and formwork
15.16 14.11 1700 & complete as per drawing and Technical specification
2704
(a) With TATA make TMT CRS(Fe-500) grade rebar cum 1849.806 12,014.73 2,22,24,919.64
15.17 14.18 2605 Filler joint
Providing & fixing 2 mm thick corrugated copper plate in expansion joint complete
(i) metre 1778.840 1,947.93 34,65,055.80
as per drawing & Technical Specification.
Providing & fixing 20 mm thick compressible fibre board in expansion joint
(ii) metre 1778.840 663.21 11,79,744.48
complete as per drawing & Technical Specification.
Providing and fixing in position 20 mm thick premoulded joint filler in expansion
(iii) joint for fixed ends of simply supported spans not exceeding 10 m to cater for a metre 1778.840 377.17 6,70,925.08
horizontal movement upto 20 mm, covered with sealant complete as per drawing
and technical specifications.
Providing and filling joint sealing compound as per drawings and technical
(iv) metre 1778.840 18.44 32,801.81
specifications with coarse sand and 6% bitumen by weight

TOTAL FOR B.3 :: SUPERSTRUCTURE 7,44,88,479.85


SOR Ref. Ref.of RATE AMOUNT
SL. NO. DESCRIPTION UNIT QUANTITY
No MoRT&H (INR) (INR)

B.4 :: PROTECTION WORKS


Flexible Apron :Construction of flexible apron 1 m thick comprising of loose stone
15.18 15.11 2507.2 cum 3919.868 1,945.55 76,26,298.21
boulders weighing not less than 40 kg beyond curtain wall.
13.5 (N) 1500,1700 Plain/Reinforced cement concrete in sub-structure complete as per drawing and
15.19
.A .b &2200 technical specifications
PCC Grade M 15(Height upto 5m) cum 588.966 6,979.01 41,10,401.17
Providing and laying Flooring complete as per drawing and Technical
15.18 15.8.B 2505 cum 27.168 6,406.09 1,74,040.65
specification laid over cement concrete bedding-Grade M 15
Curtain Wall-Cement concrete Grade M20
15.20 15.10 (B) 2507.2 cum 4025.831 7,738.78 3,11,55,017.33
Painting Two Coats on New Concrete Surfaces (Painting two coats after filling the
15.21 8.8 803 surface with synthetic enamel paint in all shades on new plastered concrete 3850.532 58.58 2,25,564.16
surfaces) sqm
12.1 I . B. Excavation for Structures
15.21 304 cum 19278.573 61.08 11,77,535.25
(b).(i)
15.22 Guard Stone Nos 930.000 646.71 6,01,440.30

TOTAL FOR B.4 :: PROTECTION WORKS 4,50,70,297.08

Total of Bill No.15 28,42,99,369.23


DETAILED COST ESTIMATES
BILL NO. 16 : REPAIRING OF BRIDGE

SOR Ref. Ref.of RATE AMOUNT


SL. NO. DESCRIPTION UNIT QUANTITY
No MoRT&H (INR) (INR)

Painting Two Coats on New Concrete Surfaces (Painting two coats after
16.1 8.8 803 filling the surface with synthetic enamel paint in all shades on new sqm 649.302 58.58 38,036.11
plastered concrete surfaces)

Total of Bill No.16 38,036.11


Quantity Calculation for Road Works
Calculation of Quantities for Dismantling

Total
Chainage L B/H T Quantity
Sl. No. Brief Description Unit No. Quantity
(km) (m) (m) (m) (cum)
(cum)
Dismantling of Structures

B) RCC 49.015 4 7.50 0.80 4.00 96.00


Abutment and parapet for
(Bridges) 49.015 2 30.00 1.00 0.25 15.00
existing Slab culvert H=h, cum
(box & Slab
Length=L, and thickness=t.
Culvert)

B) RCC 49.015 1 26 9.0 0.60 140.40


For Slab cum
(Bridges)
TOTAL FOR DISMANTLING OF RCC = 251.40

SUMMARY OF DISMANTLING MATERIALS

TOTAL FOR DISMANTLING OF RCC= 251.40 cum


Calculation of Quantities for Dismantling of Existing Flexible Pavement

Avg. Avg. Quantity of


Avg. Quantity of
Net Length Bituminous Pavement Bituminous
TCS Type GSB thickness GSB material
(m) thickness width material
(m) (cum)
(m) (m) (cum)
TCS 1B 5740.00 0.100 0.200 10.0 5740.00 11480.00
TCS 1G 1285.00 0.100 0.200 10.0 1285.00 2570.00
TCS 1H 550.00 0.100 0.200 10.0 550.00 1100.00
Total = 7575.00 15150.00

Total Quantity of Bituminous Material= 7575.00 cum


Total Quantity of GSB Material= 15150.00 cum
Quantity of GSB material
9090 cum
for reuse (@ 60% ) =
Clearing and Grubbing Road Land

Width to be Area to be
Net Existing Road
cleared and cleared and
TCS Type Length Width
grubbed grubbed
(m) (m)
(m) (Ha)

TCS 1A 2154.3 10.0 35.0 5.4


TCS 1B 5523.7 10.0 45.0 19.3
TCS 1G 1175.9 10.0 45.0 4.1
TCS 1G 478.9 10.0 45.0 1.7
TCS 2 5746.1 0.0 45.0 25.9
TCS 6A 1003.3 0.0 45.0 4.5
TCS 6B 507.6 0.0 45.0 2.3
TCS 7 404.06 0.0 30.0 1.2
TCS 8 633.00 0.0 60.0 3.8
Total= 68.2

Total area of clearing & grubbing= 68.2 Ha


Trees to be cut within Corridor of Impact
Girth size of trees
300mm-600mm 600-900mm 900-1800mm > 1800mm
698 542 287 137
QUANTITY CALCULATION OF SEEDING & MULCHING

Mulching is provided on TCS 1A, TCS 1B, TCS 1E, TCS 1G, TCS 2

Length of Mulching for TCS 1A (Single side) = 2154.30 m


Length of Mulching for TCS 1B (Single side) = 5523.70 m
Length of Mulching for TCS 1G (Single side) = 1175.90 m
Length of Mulching for TCS 1H (Single side) = 478.90 m

Assume ht. of embankment = 1.0 m


Width of Turfing = 2.24 m

Length of Mulching for TCS 2 (both side)= 11492.20 m

Assume ht. of embankment = 3.0 m


Width of Turfing = 6.71 m

Length of Mulching for TCS 8 (both side)= 1266.00 m

Assume ht. of embankment = 8.0 m


Width of Turfing = 17.89 m

Quantity of Seeding & Mulching = 120666.87 sqm


QUANTITY CALCULATION OF CUTFILL

Earthwork - Cut Earthwork - Fill


Cut Area Fill Area
Chainage (m) Volume Volume
(sqm) (sqm)
(cum) (cum)
48655 24.1 0
48675 17.46 0.04
48700 17.61 0.92
48725 13.22 0.13
48750 15.05 0.19
48775 13.97 0.01
48800 17.51 0
48825 13.6 0
48850 16.34 0.02
48875 13.88 0
48900 15.76 0.01 Already considered Already
48925 12.1 0.04 in the Estimate of
considered in the
Estimate of Road
48950 11.83 0.69 Road Hapachara -
Hapachara -
48975 11.61 0.07 Tulungia Road
Tulungia Road
49000 12.05 0.13
49025 11.62 0.09
49050 8.75 1.87
49075 7.52 1.97
49100 6.39 3.14
49125 5.37 4.66
49150 4.55 4.73
49175 6.03 0.53
49200 10.88 0
49225 12.32 0 290.00 0.00
49250 1.53 22.29 173.13 278.63
49275 14.02 0 194.38 278.63
49300 12.06 0.01 326.00 0.13
49325 12.01 0 300.88 0.13
49350 11 0 287.63 0.00
49375 11.55 0 281.88 0.00
49400 10.3 0 273.13 0.00
49425 2.05 1.51 154.38 18.88
49450 0 16.19 25.63 221.25
QUANTITY CALCULATION OF CUTFILL

Earthwork - Cut Earthwork - Fill


Cut Area Fill Area
Chainage (m) Volume Volume
(sqm) (sqm)
(cum) (cum)
49475 0 28.7
49500 0 36.82
49525 0 56.26
49550 0 76.76
49575 0 99.42
49600 0 120.28
49625 0 137.35
49650 0 148.87
49675 0 170.74
49700 0 189
49725 0 196.96
49750 0 202.84
49775 0 206.69
49800 0 214.9
49825 0 218.94
49850 0 218.3
49875 0 233.95
49900 0 251.92
49925 0 261.94
49950 0 274.65
RE WALL RE WALL
49975 0 297.95
50000 0 270.5
50025 0 268
50050 0 269
50075 0 272.35
50100 0 220.89
50125 0 259.5
50150 0 251.36
50175 0 220.52
50200 0 187.57
50225 0 167.3
50250 0 147.42
50275 0 136.24
50300 0 116.66
50325 0 90.84
50350 0 66.26
50375 0 44.2
50400 0 27.71
50425 0 12.47
50450 3.08 6.59
50475 6.06 2.5 114.25 113.63
50500 9.29 6.15 191.88 108.13
50525 8.87 9.72 227.00 198.38
50550 9.42 10.26 228.63 249.75
50575 8.03 4.75 218.13 187.63
50600 9.09 6.86 214.00 145.13
50625 11.51 4.25 257.50 138.88
50650 9.18 2.83 258.63 88.50
50675 9.92 1.8 238.75 57.88
QUANTITY CALCULATION OF CUTFILL

Earthwork - Cut Earthwork - Fill


Cut Area Fill Area
Chainage (m) Volume Volume
(sqm) (sqm)
(cum) (cum)
50700 10.46 0 254.75 22.50
50725 12.34 0 285.00 0.00
50750 12.36 0 308.75 0.00
50775 7 4.41 242.00 55.13
50800 11.24 6.14 228.00 131.88
50825 11.2 4.7 280.50 135.50
50850 10.95 2.88 276.88 94.75
50875 9.54 4.94 256.13 97.75
50900 9.37 6.28 236.38 140.25
50925 9.16 9.77 231.63 200.63
50950 9.55 8.87 233.88 233.00
50975 10.01 7.56 244.50 205.38
51000 10.81 2.69 260.25 128.13
51025 15.58 0 329.88 33.63
51050 17.76 0 416.75 0.00
51075 19.75 0 468.88 0.00
51100 21.64 0 517.38 0.00
51125 13.35 2.09 437.38 26.13
51150 10.97 0.93 304.00 37.75
51175 10.17 0.83 264.25 22.00
51200 10.08 2.61 253.13 43.00
51225 8.5 7.51 232.25 126.50
51250 7.03 9.75 194.13 215.75
51275 5.52 11.97 156.88 271.50
51300 4.91 13.69 130.38 320.75
51325 5.96 9.83 135.88 294.00
51350 8.77 8.47 184.13 228.75
51375 10.71 9.28 243.50 221.88
51400 11.41 9.08 276.50 229.50
51425 12.23 0.28 295.50 117.00
51450 12.03 3.29 303.25 44.63
51475 12.86 0.51 311.13 47.50
51500 12.58 4.15 318.00 58.25
51525 14.58 0.02 339.50 52.13
51550 12.43 1.11 337.63 14.13
51575 14.38 0 335.13 13.88
51600 9.94 10.44 304.00 130.50
51625 8.8 11.77 234.25 277.63
51650 7.92 16.85 209.00 357.75
51675 6.95 20.1 185.88 461.88
51700 6.94 28.71 173.63 610.13
51725 5.44 20.61 154.75 616.50
51750 3.5 22.74 111.75 541.88
51775 4.77 26.63 103.38 617.13
51800 8.16 15.1 161.63 521.63
51825 0.03 95.33 102.38 1380.38
51850 6.76 21.23 84.88 1457.00
51875 6.27 18.68 162.88 498.88
51900 5.04 17.85 141.38 456.63
51925 3.52 4.97 107.00 285.25
QUANTITY CALCULATION OF CUTFILL

Earthwork - Cut Earthwork - Fill


Cut Area Fill Area
Chainage (m) Volume Volume
(sqm) (sqm)
(cum) (cum)
51950 3.11 4.26 82.88 115.38
51975 5.46 0 107.13 53.25
52000 4.58 6.31 125.50 78.88
52025 8.2 0.01 159.75 79.00
52050 12.22 0 255.25 0.13
52075 11.26 4.29 293.50 53.63
52100 11.85 6 288.88 128.63
52125 12.28 7.02 301.63 162.75
52150 11.73 7.17 300.13 177.38
52175 12.18 5.85 298.88 162.75
52200 12.12 5.1 303.75 136.88
52225 13.13 5.42 315.63 131.50
52250 13.14 4.86 328.38 128.50
52275 13.71 3.79 335.63 108.13
52300 13.76 1.6 343.38 67.38
52325 12.38 4.13 326.75 71.63
52350 10.88 4.47 290.75 107.50
52375 11.9 1.22 284.75 71.13
52400 11.22 3.77 289.00 62.38
52425 11.27 4.85 281.13 107.75
52450 11.44 5.19 283.88 125.50
52475 12.46 1.92 298.75 88.88
52500 13.08 1.51 319.25 42.88
52525 12.97 1.21 325.63 34.00
52550 11.98 3.91 311.88 64.00
52575 10.67 5.99 283.13 123.75
52600 10.12 6.9 259.88 161.13
52625 10.06 5.21 252.25 151.38
52650 10.02 4.74 251.00 124.38
52675 10.19 4.59 252.63 116.63
52700 8.89 4.66 238.50 115.63
52725 8.15 5.03 213.00 121.13
52750 8.91 2.02 213.25 88.13
52775 9.36 4.51 228.38 81.63
52800 10.25 7.86 245.13 154.63
52825 11.43 8.33 271.00 202.38
52850 11.11 7.86 281.75 202.38
52875 10.89 9.01 275.00 210.88
52900 11.89 11.99 284.75 262.50
52925 12.61 7.06 306.25 238.13
52950 14.32 3.24 336.63 128.75
52975 13.34 4.72 345.75 99.50
53000 11.58 5.11 311.50 122.88
53025 8.69 6.37 253.38 143.50
53050 7.21 14.22 198.75 257.38
53075 8.26 16.61 193.38 385.38
53100 10.31 14.33 232.13 386.75
53125 12.19 15.16 281.25 368.63
53150 10.94 15.74 289.13 386.25
QUANTITY CALCULATION OF CUTFILL

Earthwork - Cut Earthwork - Fill


Cut Area Fill Area
Chainage (m) Volume Volume
(sqm) (sqm)
(cum) (cum)
53175 7.38 12.12 229.00 348.25
53200 5.84 10.07 165.25 277.38
53225 6.34 7.22 152.25 216.13
53250 6.11 10.47 155.63 221.13
53275 6.36 13.6 155.88 300.88
53300 7.91 10.56 178.38 302.00
53325 10.07 8.95 224.75 243.88
53350 11.56 8.95 270.38 223.75
53375 11.43 8.21 287.38 214.50
53400 11.31 10.03 284.25 228.00
53425 10.47 6.51 272.25 206.75
53450 9.75 10.46 252.75 212.13
53475 10.42 7.6 252.13 225.75
53500 11.71 11.68 276.63 241.00
53525 12.72 8 305.38 246.00
53550 13.83 5.87 331.88 173.38
53575 14.19 6.28 350.25 151.88
53600 14.3 3.02 356.13 116.25
53625 13.28 3.39 344.75 80.13
53650 10.63 13.39 298.88 209.75
53675 9.94 12.26 257.13 320.63
53700 10.07 10.31 250.13 282.13
53725 12.06 9.24 276.63 244.38
53750 13.19 15.19 315.63 305.38
53775 12.43 9.51 320.25 308.75
53800 12.49 14.18 311.50 296.13
53825 12.05 10.61 306.75 309.88
53850 12.86 9.05 311.38 245.75
53875 13.57 11.72 330.38 259.63
53900 14.14 14.12 346.38 323.00
53925 14.16 12.92 353.75 338.00
53950 14.85 9.3 362.63 277.75
53975 16.49 7.63 391.75 211.63
54000 20.37 7.32 460.75 186.88
54025 14.11 11.26 431.00 232.25
54050 3.42 27.56 219.13 485.25
54075 0.85 34.87 53.38 780.38
54100 1.17 41.04 25.25 948.88
54125 2.6 43.47 47.13 1056.38
54150 4.49 45.89 88.63 1117.00
54175 6.96 18.82 143.13 808.88
54200 6.39 29.82 166.88 608.00
54225 6.3 24.42 158.63 678.00
54250 7.36 20.55 170.75 562.13
54275 9.29 20.18 208.13 509.13
54300 8.96 17.39 228.13 469.63
54325 0 78.9 112.00 1203.63
54350 0 127.35 0.00 2578.13
54375 11.19 9.09 139.88 1705.50
QUANTITY CALCULATION OF CUTFILL

Earthwork - Cut Earthwork - Fill


Cut Area Fill Area
Chainage (m) Volume Volume
(sqm) (sqm)
(cum) (cum)
54400 10.31 0.6 268.75 121.13
54425 9.93 0.59 253.00 14.88
54450 8.09 0.02 225.25 7.63
54475 4.03 1.07 151.50 13.63
54500 2.25 8.39 78.50 118.25
54525 2.2 6.8 55.63 189.88
54550 4.44 2.95 83.00 121.88
54575 4.77 0.38 115.13 41.63
54600 7.65 2.78 155.25 39.50
54625 12.04 0.01 246.13 34.88
54650 13.86 0.39 323.75 5.00
54675 17.28 0 389.25 4.88
54700 17.55 0 435.38 0.00
54725 13.69 0.02 390.50 0.25
54750 13.94 2.45 345.38 30.88
54775 13.95 3.42 348.63 73.38
54800 14.05 3.15 350.00 82.13
54825 12.73 2.63 334.75 72.25
54850 15 0 346.63 32.88
54875 12.7 0.89 346.25 11.13
54900 12.39 6.71 313.63 95.00
54925 12.92 0.04 316.38 84.38
54950 14.29 0 340.13 0.50
54975 13.84 0.16 351.63 2.00
55000 13.03 3.47 335.88 45.38
55025 15.09 5.98 351.50 118.13
55050 15.29 11.22 379.75 215.00
55075 16.93 6.11 402.75 216.63
55100 18.34 9.05 440.88 189.50
55125 16.14 6.5 431.00 194.38
55150 12.66 12.86 360.00 242.00
55175 10.27 18.96 286.63 397.75
55200 11.48 8.26 271.88 340.25
55225 13.89 2.47 317.13 134.13
55250 14.9 1.49 359.88 49.50
55275 13.53 0.27 355.38 22.00
55300 16.12 0.04 370.63 3.88
55325 15.3 0.02 392.75 0.75
55350 12.77 0.06 350.88 1.00
55375 17.89 0.02 383.25 1.00
55400 15.55 0 418.00 0.25
55425 10.65 1.93 327.50 24.13
55450 13.12 0 297.13 24.13
55475 16.95 0 375.88 0.00
55500 15.18 0 401.63 0.00
55525 14.93 0.31 376.38 3.88
55550 18.42 0 416.88 3.88
55575 18.06 0.01 456.00 0.13
55600 15.89 0.46 424.38 5.88
QUANTITY CALCULATION OF CUTFILL

Earthwork - Cut Earthwork - Fill


Cut Area Fill Area
Chainage (m) Volume Volume
(sqm) (sqm)
(cum) (cum)
55625 15.64 1.68 394.13 26.75
55650 15.81 0.92 393.13 32.50
55675 14.33 0.13 376.75 13.13
55700 13.01 4.46 341.75 57.38
55725 11.08 9.62 301.13 176.00
55750 9.62 15.51 258.75 314.13
55775 9.35 7.43 237.13 286.75
55800 13.67 3.32 287.75 134.38
55825 18.61 0 403.50 41.50
55850 13.02 21.01 395.38 262.63
55875 10.54 22.66 294.50 545.88
55900 10.12 30.21 258.25 660.88
55925 11.3 20.75 267.75 637.00
55950 9.97 17.5 265.88 478.13
55975 8.82 27.22 234.88 559.00
56000 9.85 9.81 233.38 462.88
56025 16.41 0.19 328.25 125.00
56050 16.06 0.58 405.88 9.63
56075 18.3 0 429.50 7.25
56100 22.01 0 503.88 0.00
56125 20.5 0 531.38 0.00
56150 12.97 6.04 418.38 75.50
56175 11.69 17.83 308.25 298.38
56200 11.79 18.39 293.50 452.75
56225 14.51 5.35 328.75 296.75
56250 15.53 2.39 375.50 96.75
56275 12.52 10.75 350.63 164.25
56300 9.51 24.09 275.38 435.50
56325 7.94 23.33 218.13 592.75
56350 7.12 19.55 188.25 536.00
56375 6.13 20.33 165.63 498.50
56400 5.63 21.88 147.00 527.63
56425 6.32 20.3 149.38 527.25
56450 7.37 15.29 171.13 444.88
56475 0.01 71.51 92.25 1085.00
56500 7.67 12.96 96.00 1055.88
56525 5.15 11.35 160.25 303.88
56550 2.85 12.01 100.00 292.00
56575 2.98 7.36 72.88 242.13
56600 4.25 6.64 90.38 175.00
56625 5.75 9.77 125.00 205.13
56650 6.79 6.02 156.75 197.38
56675 8.09 4.9 186.00 136.50
56700 9.13 3.72 215.25 107.75
56725 10.09 2.93 240.25 83.13
56750 7.34 6.23 217.88 114.50
56775 6.35 3.74 171.13 124.63
56800 3.19 6.03 119.25 122.13
56825 1.48 9.37 58.38 192.50
QUANTITY CALCULATION OF CUTFILL

Earthwork - Cut Earthwork - Fill


Cut Area Fill Area
Chainage (m) Volume Volume
(sqm) (sqm)
(cum) (cum)
56850 0.45 9.76 24.13 239.13
56875 0.01 26.8 5.75 457.00
56900 0.32 27.61 4.13 680.13
56925 2.35 14.64 33.38 528.13
56950 2.86 10.5 65.13 314.25
56975 1.78 15.53 58.00 325.38
57000 0 82.76 22.25 1228.63
57025 1.77 13.11 22.13 1198.38
57050 0.05 21.77 22.75 436.00
57075 0 27.39 0.63 614.50
57100 0 31.58 0.00 737.13
57125 0.01 29.24 0.13 760.25
57150 0.95 24.43 12.00 670.88
57175 2.2 23.29 39.38 596.50
57200 2.44 22.44 58.00 571.63
57225 5.4 9.81 98.00 403.13
57250 7.72 9.77 164.00 244.75
57275 9.32 10.48 213.00 253.13
57300 9.92 11.91 240.50 279.88
57325 10.74 7.32 258.25 240.38
57350 11.67 12.03 280.13 241.88
57375 11.91 12.92 294.75 311.88
57400 11.02 15.24 286.63 352.00
57425 11.15 13.55 277.13 359.88
57450 10.86 11.57 275.13 314.00
57475 12.37 7 290.38 232.13
57500 14.47 4.32 335.50 141.50
57525 17.56 5.56 400.38 123.50
57550 16.15 3.5 421.38 113.25
57575 13.66 6.32 372.63 122.75
57600 18.22 0 398.50 79.00
57625 15.3 0.9 419.00 11.25
57650 20.02 0 441.50 11.25
57675 25.51 0 569.13 0.00
57700 21.83 0 591.75 0.00
57725 14.9 4.13 459.13 51.63
57750 12.54 19.56 343.00 296.13
57775 12.85 17.17 317.38 459.13
57800 12.39 19.07 315.50 453.00
57825 12.36 15.99 309.38 438.25
57850 12.62 19.94 312.25 449.13
57875 11.78 19.89 305.00 497.88
57900 10.46 17.99 278.00 473.50
57925 10.69 19.91 264.38 473.75
57950 10.78 20.27 268.38 502.25
57975 10.93 16.15 271.38 455.25
58000 11.19 15.23 276.50 392.25
58025 10.71 19.22 273.75 430.63
58050 10.18 17.74 261.13 462.00
58075 10.32 16.74 256.25 431.00
QUANTITY CALCULATION OF CUTFILL

Earthwork - Cut Earthwork - Fill


Cut Area Fill Area
Chainage (m) Volume Volume
(sqm) (sqm)
(cum) (cum)
58100 12.52 8.70 285.50 318.00
58125 12.89 19.5 317.63 352.50
58150 14.92 16.8 347.63 453.75
58175 16.26 10.13 389.75 336.63
58200 15.60 17.23 398.25 342.00
58225 12.48 18.08 351.00 441.38
58250 11.32 20.22 297.50 478.75
58275 11.072 4.7545 279.90 312.18
58300 10.97 17.09 275.53 273.06
58325 11.03 13.72 275.00 385.13
58350 11.21 7.4 278.00 264.00
58375 11.56 9.44 284.63 210.50
58400 11.79 11.56 291.88 262.50
58425 11.74 4.4 294.13 199.50
58450 11.38 8.54 289.00 161.75
58475 11.52 6.64 286.25 189.75
58500 12.29 2.47 297.63 113.88
58525 11.61 23.32 298.75 322.38
58550 13.17 2.79 309.75 326.38
58575 11.87 14.76 313.00 219.38
58600 11.3 23.54 289.63 478.75
58625 10.86 18.45 277.00 524.88
58650 10.72 22.79 269.75 515.50
58675 10.49 22.79 265.13 569.75
58700 11.05 9 269.25 397.38
58725 9.49 28.35 256.75 466.88
58750 8.1725 33.3584 220.78 771.36
58775 8.39 35.06 207.03 855.23
58800 9.46 34.09 223.13 864.38
58825 10.9125 32.0641 254.66 826.93
58850 11.6599 31.2932 282.16 791.97
58875 11.2137 19.5613 285.92 635.68
58900 11.8 0.97 287.67 256.64
58925 10.79 5.98 282.38 86.88
58950 10.4124 24.6741 265.03 383.18
58975 12.02 29.71 280.41 679.80
59000 12.91 17.03 311.63 584.25
59025 22.74 0 445.63 212.88
59050 21.13 0 548.38 0.00
59075 17.73 0 485.75 0.00
59100 12.5 7.98 377.88 99.75
59125 11.44 23.1 299.25 388.50
59150 10.89 28.96 279.13 650.75
59175 12.01 0.5 286.25 368.25
59200 10.51 35.71 281.50 452.63
59225 9.79 20.57 253.75 703.50
59250 9.06 5.23 235.63 322.50
59275 9.82 10.46 236.00 196.13
59300 9.75 33.6 244.63 550.75
59325 9.88 11.95 245.38 569.38
QUANTITY CALCULATION OF CUTFILL

Earthwork - Cut Earthwork - Fill


Cut Area Fill Area
Chainage (m) Volume Volume
(sqm) (sqm)
(cum) (cum)
59350 10.23 22.77 251.38 434.00
59375 12.42 0 283.13 284.63
59400 10.31 16.9 284.13 211.25
59425 10.94 3.89 265.63 259.88
59450 10.13 25.3 263.38 364.88
59475 10.4 20.15 256.63 568.13
59500 10.11 26.1 256.38 578.13
59525 10.49 9.91 257.50 450.13
59550 11.33 20.07 272.75 374.75
59575 10.85 27.64 277.25 596.38
59600 9.37 31.71 252.75 741.88
59625 9.89 25.51 240.75 715.25
59650 9.4 27.03 241.13 656.75
59675 10.21 28.83 245.13 698.25
59700 12.2 25.45 280.13 678.50
59725 11.31 24.5 293.88 624.38
59750 11.34 25.3 283.13 622.50
59775 9.14 31.5 256.00 710.00
59800 8.65 28.53 222.38 750.38
59825 9.59 32.33 228.00 760.75
59850 7.39 33.73 212.25 825.75
59875 5.39 34.16 159.75 848.63
59900 4.8331 38.1029 127.79 903.29
59925 6.14 35.18 137.16 916.04
59950 5.2 32.7 141.75 848.50
59975 7.63 20.52 160.38 665.25
60000 4.81 14.27 155.50 434.88
60025 1.37 37.23 77.25 643.75
60050 0 42.2 17.13 992.88
60075 0 89.12 0.00 1641.50
60100 0 79.28 0.00 2105.00
60125 0 118.02 0.00 2466.25
60150 0 138.47 0.00 3206.13
60175 0.01 177.57 0.13 3950.50
60200 0 204.71 0.13 4778.50
60225 0 215.36 0.00 5250.88
60250 0 177.09 0.00 4905.63
60275 0 187.11 0.00 4552.50
60300 0 142.64
60325 0 333.58 Major Bridge Major Bridge
60350 0 161.02
60375 0 142 0.00 3787.75
60400 0 140.66 0.00 3533.25
60425 0 81.37 0.00 2775.38
60450 0 21.6 0.00 1287.13
60475 0.1 43.01 1.25 807.63
60500 0 79.22 1.25 1527.88
60525 0 72.6 0.00 1897.75
60550 0 60.53 0.00 1664.13
60575 0 46.51 0.00 1338.00
QUANTITY CALCULATION OF CUTFILL

Earthwork - Cut Earthwork - Fill


Cut Area Fill Area
Chainage (m) Volume Volume
(sqm) (sqm)
(cum) (cum)
60600 0 36.33 0.00 1035.50
60625 0 36.27 0.00 907.50
60650 0 44.86 0.00 1014.13
60675 0 52.75 0.00 1220.13
60700 0 59.8 0.00 1406.88
60725 0 65.04 0.00 1560.50
60750 0 75.87 0.00 1761.38
60775 0.01 86.15 0.13 2025.25
60800 0 94.21 0.13 2254.50
60825 0 98.99 0.00 2415.00
60850 0 108.3 0.00 2591.13
60875 0 112.12 0.00 2755.25
60900 0 119.73 0.00 2898.13
60925 0.34 192.12
60950 0 240.33 Major Bridge Major Bridge
60975 0.02 123.7
61000 0 125.19 0.25 3111.13
61025 0 124.31 0.00 3118.75
61050 0 122.58 0.00 3086.13
61075 0 115.07 0.00 2970.63
61100 0 105.79 0.00 2760.75
61125 0 96.2 0.00 2524.88
61150 0 98.78 0.00 2437.25
61175 0 89.12 0.00 2348.75
61200 0 70.43 0.00 1994.38
61225 0 63.48 0.00 1673.88
61250 0 62.44 0.00 1574.00
61275 0 61.27 0.00 1546.38
61300 0 69.15 0.00 1630.25
61325 0 66.5 0.00 1695.63
61350 0 72.57 0.00 1738.38
61375 0 74.83 0.00 1842.50
61400 0 75.81 0.00 1883.00
61425 0 79.16 0.00 1937.13
61450 0 78.55 0.00 1971.38
61475 0 75.96 0.00 1931.38
61500 0 74.15 0.00 1876.38
61525 0 75.51 0.00 1870.75
61550 0 77.36 0.00 1910.88
61575 0.01 76.04 0.13 1917.50
61600 8 10.74 100.13 1084.75
61625 0.14 24.02 101.75 434.50
61650 0 120.94 1.75 1812.00
61675 0 113.64 0.00 2932.25
61700 50.84 0.00 2056.00
61725 0.39 26.87 4.88 971.38
61750 1.32 12.81 21.38 496.00
61775 0.3 30.09 20.25 536.25
61800 0 98.56 3.75 1608.13
61825 0 131.73 0.00 2878.63
QUANTITY CALCULATION OF CUTFILL

Earthwork - Cut Earthwork - Fill


Cut Area Fill Area
Chainage (m) Volume Volume
(sqm) (sqm)
(cum) (cum)
61850 0 158.85 0.00 3632.25
61875 0 183.85 0.00 4283.75
61900 0 204.45 0.00 4853.75
61925 0 222.07 0.00 5331.50
61950 0 245.62 0.00 5846.13
61975 0 263.9 0.00 6369.00
62000 0 259.36 0.00 6540.75
62025 0 249.66
62050 0 367.21 Major Bridge Major Bridge
62075 0 365.92
62100 0 304.64 0.00 8382.00
62125 0 277.53 0.00 7277.13
62150 0 262.18 0.00 6746.38
62175 0 230.93 0.00 6163.88
62200 0 220.45 0.00 5642.25
62225 0 198.66 0.00 5238.88
62250 0 66.16 0.00 3310.25
62275 0.17 31.07 2.13 1215.38
62300 0 73.21 2.13 1303.50
62325 0 72.9 0.00 1826.38
62350 0 71.56 0.00 1805.75
62375 0 102.68 0.00 2178.00
62400 0 93.2 0.00 2448.50
62425 0 68.8 0.00 2025.00
62450 0 121.66 0.00 2380.75
62475 0 145.7 0.00 3342.00
62500 0 149.65 0.00 3691.88
62525 0.02 147.7 0.25 3716.88
62550 0 129 0.25 3458.75
62575 0 144.82 0.00 3422.75
62600 0 117.08 0.00 3273.75
62625 0 78.61 0.00 2446.13
62650 0 40.08 0.00 1483.63
62675 0.14 28.74 1.75 860.25
62700 0 68.04 1.75 1209.75
62725 0 77.67 0.00 1821.38
62750 0 69.15 0.00 1835.25
62775 0 97.4 0.00 2081.88
62800 0 128.9 0.00 2828.75
62825 0 104.52 0.00 2917.75
62850 0 85.74 0.00 2378.25
62875 0 81.7 0.00 2093.00
62900 0 64.77 0.00 1830.88
62925 0 91.43 0.00 1952.50
62950 0 113.06 0.00 2556.13
62975 0 109.02 0.00 2776.00
63000 0 103.72 0.00 2659.25
63025 0.01 110.1 0.13 2672.75
63050 0 126.54 0.13 2958.00
63075 0 39.31 0.00 2073.13
QUANTITY CALCULATION OF CUTFILL

Earthwork - Cut Earthwork - Fill


Cut Area Fill Area
Chainage (m) Volume Volume
(sqm) (sqm)
(cum) (cum)
63100 0 72.04 0.00 1391.88
63125 0.69 47.22 8.63 1490.75
63150 0 116.62 8.63 2048.00
63175 0 141.13 0.00 3221.88
63200 0 101.31 0.00 3030.50
63225 0 130.89 0.00 2902.50
63250 0 162.84 0.00 3671.63
63275 0 209.44 0.00 4653.50
63300 0 159.13 0.00 4607.13
63325 0 118.15 0.00 3466.00
63350 0 117.97 0.00 2951.50
63375 0 121.55 0.00 2994.00
63400 0 127.79 0.00 3116.75
63425 0 131.36 0.00 3239.38
63450 0 132.81 0.00 3302.13
63475 0 139.32 0.00 3401.63
63500 0 142.85 0.00 3527.13
63525 0 168.8 0.00 3895.63
63550 0 188.56 0.00 4467.00
63575 0 191.17 0.00 4746.63
63600 0 193.5 0.00 4808.38
63625 0 194.26 0.00 4847.00
63650 0 192.06 0.00 4829.00
63675 0 190.3 0.00 4779.50
63700 0 206.68 0.00 4962.25
63725 0 217.01 0.00 5296.13
63750 0 221.52 0.00 5481.63
63775 210.54 0.00 5400.75
63800 0 202.5 0.00 5163.00
63825 197.11 0.00 4995.13
63850 0 199.41 0.00 4956.50
63875 0 181.41 0.00 4760.25
63900 0 173.88 0.00 4441.13
63925 0.01 148.04 0.13 4024.00
63950 0 127.49 0.13 3444.13
63975 4.15 83.36 51.88 2635.63
64000 0 111.43 51.88 2434.88
64025 0 55.56 0.00 2087.38
64050 7.84 15.56 98.00 889.00
64075 9.8 10.46 220.50 325.25
64100 0 47.29 122.50 721.88
64125 0.13 113.7 1.63 2012.38
64150 0 265.57 1.63 4740.88
64175 0.33 330.3 4.13 7448.38
64200 0 72.76 4.13 5038.25
QUANTITY CALCULATION OF CUTFILL

Earthwork - Cut Earthwork - Fill


Cut Area Fill Area
Chainage (m) Volume Volume
(sqm) (sqm)
(cum) (cum)
64225 0 74.29 0.00 1838.13
64250 0 100.81
64275 0 134.7
64300 0 161.46
64325 0 111.87
64350 0 127.53
64375 0 139.26
64400 0 149.84
64425 0 170.43
64450 0 179.79
64475 0 231.02
64500 0 157.97
64525 0 60.49
64550 0 112.91
64575 0 239.91
64600 0 293.51
64625 0 298.27
64650 0 254.11
64675 0 216.02
64700 0 243.78
64725 0 286.08
64750 0 278.12
64775 0 218.94
64800 0 287.91
RE WALL RE WALL
64825 0 297.37
64850 0 295.29
64875 0 276.72
64900 0 266.18
64925 0 273.79
64950 0 304.39
64975 0 288.1
65000 0 221.76
65025 0 143.78
65050 0 265.8
65075 0 286.22
65100 0 282.87
65125 0 251.35
65150 0 41.87
65175 1.94 45.31
65200 5.41 77.93
65225 39.63 0
65250 19.58 0
65275 0 166.07
65300 0 314.65
65325 0 263.51
65350 0 125.34
65375 53.38 0
65400 70.08 0 1543.25 0.00
65425 108.66 0 2234.25 0.00
65450 156.4 0 3313.25 0.00
QUANTITY CALCULATION OF CUTFILL

Earthwork - Cut Earthwork - Fill


Cut Area Fill Area
Chainage (m) Volume Volume
(sqm) (sqm)
(cum) (cum)
65475 94.76 4.45 3139.50 55.63
65500 86.12 0.06 2261.00 56.38
65525 140.49 0.01 2832.63 0.88
65550 0 54.08 1756.13 676.13
65575 0 168.01 0.00 2776.13
65600 0 161.77 0.00 4122.25
65625 0 152.79 0.00 3932.00
65650 142.81 0.00 3695.00
65675 0.04 137.22 0.50 3500.38
65700 0 108.62 0.50 3073.00
65725 0.01 94.87 0.13 2543.63
65750 0 99.35 0.13 2427.75
65775 0 121.19 0.00 2756.75
65800 0 109.53 0.00 2884.00
65825 0 107.07 0.00 2707.50
65850 0 117.92 0.00 2812.38
65875 0 114.88 0.00 2910.00
65900 0 88.7 0.00 2544.75
65925 0.01 73 0.13 2021.25
65950 0 102.64 0.13 2195.50
65975 2.25 138.07 28.13 3008.88
66000 0 109.39 28.13 3093.25
66025 0.08 208.39 1.00 3972.25
66050 5.14 202.78 65.25 5139.63
66075 369.91 171.54 4688.13 4679.00
66100 0 179.75 4623.88 4391.13
66125 0.03 189.24 0.38 4612.38
66150 0 154.91 0.38 4301.88
66175 0 88.7 0.00 3045.13
66200 33.89 67.85 423.63 1956.88
66225 126.39 45.2 2003.50 1413.13
66250 129.85 33.02 3203.00 977.75
66275 2.45 44.79 1653.75 972.63
66300 67.73 37.71 877.25 1031.25
66325 66.98 30.34 1683.88 850.63
66350 0 50.87 837.25 1015.13
66375 0 69.63 0.00 1506.25
66400 1.17 58.5 14.63 1601.63
66425 353.77 0 4436.75 731.25
66450 570.7 0 11555.88 0.00
66475 739.04 0 16371.75 0.00
66500 836.62 0 19695.75 0.00
66525 779.42 0 20200.50 0.00
66550 489.3 0 15859.00 0.00
66575 389.22 0.03 10981.50 0.38
66600 364.04 0 9415.75 0.38
66625 84.23 31.83 5603.38 397.88
66650 144.24 35.82 2855.88 845.63
66675 266.76 23.55 5137.50 742.13
66700 274.23 22.87 6762.38 580.25
QUANTITY CALCULATION OF CUTFILL

Earthwork - Cut Earthwork - Fill


Cut Area Fill Area
Chainage (m) Volume Volume
(sqm) (sqm)
(cum) (cum)
66725 214.9 22.51 6114.13 567.25
66750 318.9 0 6672.50 281.38
66775 674.38 0 12416.00 0.00
66800 379.84 0 13177.75 0.00
66825 88.07 6.56 5848.88 82.00
66850 67.12 14.17 1939.88 259.13
66875 5.42 70.58 906.75 1059.38
66900 0 219.97 67.75 3631.88
66925 0 237.24 0.00 5715.13
66950 0 259.46 0.00 6208.75
66975 0 302.03 0.00 7018.63
67000 0 314.79 0.00 7710.25
67025 0 330.31
67050 0 353.51 Major Bridge Major Bridge
67075 0 360.07
67100 0 353.58 0.00 8920.63
67125 0 346.08 0.00 8745.75
67150 0 356.68 0.00 8784.50
67175 0 374.39 0.00 9138.38
67200 0 355.9 0.00 9128.63
67225 0 314.89
67250 0 273.02
67275 0 141.15
67300 0 137.31
67325 0 99.37
67350 0 99.55
67375 0 113.09
RE WALL RE WALL
67400 0 116.75
67425 0 120.79
67450 0 143.53
67475 0 151.56
67500 0 155.39
67525 0 161.41
67543 0 168.38
QUANTITY CALCULATION OF CUTFILL

Earthwork - Cut Earthwork - Fill


Cut Area Fill Area
Chainage (m) Volume Volume
(sqm) (sqm)
(cum) (cum)
Cutfill For 2 lane portion and Bridge Appraoch
0 0 161.41
25 0 168.38
50 0 173.65
75 0 182.36
100 0 185.89
125 0 143.44
150 0 153.69
175 0 179.05
200 0 202.9
225 0 227.36
RE WALL RE WALL
250 0 215.12
275 0 231.71
300 0 228.05
325 0 236.3
350 0 246.03
375 0 267.9
400 0 292.04
425 0 302.19
450 0 320.41
475 0 338.52
500 0 37.59 0.00 4701.38
525 0 57.35 0.00 1186.75
550 0 96.58 0.00 1924.13
575 0 107.12 0.00 2546.25
600 0 95 0.00 2526.50
625 0 123.88 0.00 2736.00
650 0 147.98 0.00 3398.25
675 0 170.18 0.00 3977.00
700 0 198.66 0.00 4610.50
725 0 227.46 0.00 5326.50
750 0 254.99 0.00 6030.63
775 0 283.15 0.00 6726.75
800 0 313.92 0.00 7463.38
825 0 345.9 0.00 8247.75
850 0 376.82 0.00 9034.00
875 0 410.42 0.00 9840.50
900 0 477.48 0.00 11098.75
925 0 530.92 0.00 12605.00
950 0 548.95 0.00 13498.38
975 0 562.24 0.00 13889.88
1000 0 554.35 0.00 13957.38
1025 0 559.53 0.00 13923.50
1050 0 569.71 0.00 14115.50
1071 0 573.03 0.00 11998.77
Total = 279738 946966

Total Earthwork in cutting = 279738.00


Embankment Filling Volume = 946966.00
Embankment Filling from cuBng material (70% of cuBng material)= 195816.60
QUANTITY CALCULATION OF CUTFILL

Earthwork - Cut Earthwork - Fill


Cut Area Fill Area
Chainage (m) Volume Volume
(sqm) (sqm)
(cum) (cum)
Borrow area Soil is required for Embankment Filling purpose = 751149.40
Borrow area Soil is required for Median Filling purpose = 25347.97
QUANTITY CALCULATION OF FLEXIBLE PAVEMENT (Existing Portion)

Design Length= 19972 m 19.972 Km


Total Length of Flexible Pavement= 9815 m 9.815 Km
Length of CD= 0.482 Km
Length of road excluding CD= 9.333 Km
Pavement Thickness Pavement Thickness Pavement Thickness
(overlay portion):- ( Reconstruction portion):- ( Widening portion):

Thickness Thickness Thickness


Layer Layer Layer
(m) (m) (m)
BC 0.040 BC 0.04 BC 0.040
DBM 0.050 DBM 0.06 DBM-I 0.100
DBM for Profile Corrective
Course 0.050 RAP 0.110 WMM-I 0.125
GSB
(Drainage Layer) 0.150 WMM-II 0.125
GSB (Separation
Layer) 0.150 GSB 0.200
Subgrade 0.500 Subgrade 0.500

Quantity Calculation For TCS-1A (4 LANE DIVIDED CARRIAGEWAY WITH PAVED SHOULDER IN RURAL AREA ECCENTRIC WIDENING AND
OVERLAY OVER EXISTING PAVEMENT)
Chainage
Length CD Length Net Length
From To
55065 56270 1205 28.5 1176.5
57310 58345 1035 57.2 977.8

Total Length= 2240 85.7 2154.3 m

Width of Flexible Pavement= 7.0 m


Width of Kerb Shyness = 0.5 m
Width of Paved Shoulder = 2.5 m
Width of BC= 10.00 m
Width of DBM= 10.00 m

Quantity of Tack coat (Bituminous Layer) = 21543.00 sqm


Quantity of BC= 861.72 cum
Quantity of DBM= 1077.15 cum
Quantity of DBM (for PCC) = 1077.15 cum
Quantity Calculation For TCS-1B (4 LANE DIVIDED CARRIAGEWAY WITH PAVED SHOULDER IN RURAL AREA)
(RECONSTRUCTION OVER EXISTING PAVEMENT WITH PARTIAL GRANULAR LAYER SCARIFICATION)

Chainage
Length CD Length Net Length
From To
50445 54045 3600 168.7 3431.3
56270 56445 175 9.54 165.46
56995 57310 315 19.04 295.96
58345 59995 1650 19.04 1630.96

Total Length= 5740 216.32 5523.68 m

Width of Existing Pavement= 10.0 m


Width of Flexible Pavement= 7.0 m
Width of Kerb Shyness = 0.5 m
Width of Paved Shoulder = 2.5 m
Width of Earthen Shoulder = 1.5 m
Width of BC= 10.00 m
Width of DBM= 10.00 m
Width of RAP = 10.125 m
Width of GSB (Drainage Layer) = 12.07 m
Width of GSB (Separation Layer) = 12.37 m
Width of Geocell= 12.37 m

Quantity of Prime coat= 55236.80 sqm


Quantity of Tack coat (Granular Layer) = 55236.80 sqm
Quantity of BC= 2209.47 cum
Quantity of DBM= 3314.21 cum
Quantity of RAP = 6152.00 cum
Quantity of Geocell = 68327.92 sqm
Quantity of GSB (Drainage Layer) = 10000.62 cum
Quantity of GSB (Separation Layer) = 10249.19 cum

Quantity Calculation For TCS-1G (4 LANE DIVIDED CARRIAGEWAY WITH PAVED SHOULDER IN RURAL AREA)
(RECONSTRUCTION OVER EXISTING PAVEMENT WITH PARTIAL GRANULAR LAYER SCARIFICATION)

Chainage
Length CD Length Net Length
From To
49205 49470 265 42.54 222.46
54045 55065 1020 66.54 953.46

Total Length= 1285 109.08 1175.92 m

Width of Existing Pavement= 10.0 m


Width of Flexible Pavement= 7.0 m
Width of Kerb Shyness = 0.5 m
Width of Paved Shoulder = 2.5 m
Width of Earthen Shoulder = 1.5 m
Width of BC= 10.00 m
Width of DBM= 10.00 m
Width of RAP = 10.125 m
Width of GSB (Drainage Layer) = 12.07 m
Width of GSB (Separation Layer) = 12.37 m
Width of Geocell= 12.37 m

Quantity of Prime coat= 11759.20 sqm


Quantity of Tack coat (Granular Layer) = 11759.20 sqm
Quantity of BC= 470.37 cum
Quantity of DBM= 705.55 cum
Quantity of RAP = 1309.68 cum
Quantity of Geocell = 14546.13 sqm
Quantity of GSB (Drainage Layer) = 2129.00 cum
Quantity of GSB (Separation Layer) = 2181.92 cum
Quantity Calculation For TCS- 1H (4 LANE DIVIDED CARRIAGEWAY WITH PAVED SHOULDER IN RURAL AREA)
(RECONSTRUCTION OVER EXISTING PAVEMENT WITH PARTIAL GRANULAR LAYER SCARIFICATION)
Chainage
Length CD Length Net Length
From To
56445 56995 550 71.13 478.87

Total Length= 550 71.13 478.87 m

Width of Existing Pavement= 10.0 m


Width of Flexible Pavement= 7.0 m
Width of Kerb Shyness = 0.5 m
Width of Paved Shoulder = 2.5 m
Width of Earthen Shoulder = 1.5 m
Width of BC= 10.00 m
Width of DBM= 10.00 m
Width of WMM I = 10.125 m
Width of WMM II = 10.250 m
Width of GSB (Drainage Layer) = 12.480 m

Quantity of Prime coat= 4788.70 sqm


Quantity of Tack coat (granular)= 4788.70 sqm
Quantity of BC= 191.55 cum
Quantity of DBM= 478.87 cum
Quantity of WMM= 1219.62 cum
Quantity of GSB (Drainage Layer) = 1195.26 cum

Total Quantity:
Unit Road Part Total
Total Quantity of Prime coat= sqm 71784.70 71784.70

Total Quantity of Tack coat


sqm 71784.70 71784.70
(Granular Layer)=
Total Quantity of Tack coat
sqm 21543.00 21543.00
(Bituminous Layer)=
Total Quantity of BC= cum 3733.11 3733.11
Total Quantity of DBM= cum 6652.93 6652.93
Total Quantity of WMM= cum 1219.62 1219.62
Total Quantity of RAP= cum 7461.68 7461.68
Total Quantity of GSB
cum 13324.88 13324.88
(Drainage Layer) =
Total Quantity of GSB
cum 12431.11 12431.11
(Separation Layer) =
Total Quantity of Geocell= sqm 82874.05 82874.05

From Chainage 48.655 km to 49.205 km (550m length) already considered in the Estimate of Road Hapachara - Tulungia
Road. For this, Road part length of 550 m is not considered for Estimate Purpose.
QUANTITY CALCULATION OF FLEXIBLE PAVEMENT (Widening Portion)

Design Length= 19972 m 19.972 Km


Total Length of Flexible Pavement= 19422.00 m 19.42 Km
Pavement Thickness:-
Thickness
Layer
(m) Length of CD= 1.795 Km
BC 0.040 Length of road excluding CD= 17.627 Km
DBM 0.060 Road Part Not Considered = 0.550 Km
WMM 0.100
CT Base 0.100
CT Sub Base 0.200
SUBGRADE 0.500

Quantity Calculation For TCS-1A (4 LANE DIVIDED CARRIAGEWAY WITH PAVED SHOULDER IN RURAL AREA ECCENTRIC WIDENING AND
OVERLAY OVER EXISTING PAVEMENT WITHOUT TOE WALL)
Chainage
Length CD Length Net Length
From To
55065 56270 1205 28.5 1176.5
57310 58345 1035 57.2 977.8

Total Length= 2240 85.7 2154.3 m

Width of Flexible Pavement= 7.0 m


Width of Kerb Shyness = 0.5 m
Width of Median = 1.5 m
Width of Paved Shoulder = 2.5 m
Width of Earthen Shoulder = 1.5 m
Width of BC= 10.00 m
Width of DBM= 10.00 m
Width of WMM = 10.125 m
Width of CT Base = 10.250 m
Width of CT Sub Base = 13.80 m
Width of Subgrade= 14.50 m

Quantity of Prime coat= 21543.00 sqm


Quantity of Tack coat (Granular Layer)= 21543.00 sqm
Quantity of BC= 861.72 cum
Quantity of DBM= 1292.58 cum
Quantity of WMM= 2181.23 cum
Quantity of CT base= 2208.16 cum
Quantity of CT Sub base= 5945.87 cum
Quantity of Subgrade= 15618.675 cum
Quantity Calculation For TCS-1B (4 LANE DIVIDED CARRIAGEWAY WITH PAVED SHOULDER IN RURAL AREA)
(RECONSTRUCTION OVER EXISTING PAVEMENT WITH PARTIAL GRANULAR LAYER SCARIFICATION)

Chainage
Length CD Length Net Length
From To
50445 54045 3600 168.7 3431.3
56270 56445 175 9.54 165.46
56995 57310 315 19.04 295.96
58345 59995 1650 19.04 1630.96

Total Length= 5740 216.32 5523.68 m

Width of Flexible Pavement= 7.0 m


Width of Kerb Shyness = 0.5 m
Width of Median = 1.5 m
Width of Paved Shoulder = 2.5 m
Width of Earthen Shoulder = 1.5 m
Width of BC= 10.00 m
Width of DBM= 10.00 m
Width of WMM = 10.125 m
Width of CT Base = 10.250 m
Width of CT Sub Base = 13.80 m
Width of Subgrade= 14.50 m

Quantity of Prime coat= 55236.80 sqm


Quantity of Tack coat (Granular Layer)= 55236.80 sqm
Quantity of BC= 2209.47 cum
Quantity of DBM= 3314.21 cum
Quantity of WMM= 5592.73 cum
Quantity of CT base= 5661.77 cum
Quantity of CT Sub base= 15245.36 cum
Quantity of Subgrade= 40046.68 cum

Quantity Calculation For TCS-1G (4 LANE DIVIDED CARRIAGEWAY WITH PAVED SHOULDER IN RURAL AREA)
(RECONSTRUCTION OVER EXISTING PAVEMENT WITH PARTIAL GRANULAR LAYER SCARIFICATION)

Chainage
Length CD Length Net Length
From To
49205 49470 265 42.54 222.46
54045 55065 1020 66.54 953.46

Total Length= 1285 109.08 1175.92 m

Width of Flexible Pavement= 7.0 m


Width of Kerb Shyness = 0.5 m
Width of Median = 1.5 m
Width of Paved Shoulder = 2.5 m
Width of Earthen Shoulder = 1.5 m
Width of BC= 10.00 m
Width of DBM= 10.00 m
Width of WMM = 10.125 m
Width of CT Base = 10.250 m
Width of CT Sub Base = 13.80 m
Width of Subgrade= 14.50 m

Quantity of Prime coat= 11759.20 sqm


Quantity of Tack coat (Granular Layer)= 11759.20 sqm
Quantity of BC= 470.37 cum
Quantity of DBM= 705.55 cum
Quantity of WMM= 1190.62 cum
Quantity of CT base= 1205.32 cum
Quantity of CT Sub base= 3245.54 cum
Quantity of Subgrade= 8525.42 cum
Quantity Calculation For TCS-1H (4 LANE DIVIDED CARRIAGEWAY WITH PAVED SHOULDER IN RURAL AREA)
(RECONSTRUCTION OVER EXISTING PAVEMENT WITH PARTIAL GRANULAR LAYER SCARIFICATION)

Chainage
Length CD Length Net Length
From To
56445 56995 550 71.13 478.87

Total Length= 550 71.13 478.87 m

Width of Flexible Pavement= 7.0 m


Width of Kerb Shyness = 0.5 m
Width of Median = 1.5 m
Width of Paved Shoulder = 2.5 m
Width of Earthen Shoulder = 1.5 m
Width of BC= 10.00 m
Width of DBM= 10.00 m
Width of WMM = 10.125 m
Width of CT Base = 10.250 m
Width of CT Sub Base = 13.80 m
Width of Subgrade= 14.50 m

Quantity of Prime coat= 4788.70 sqm


Quantity of Tack coat (Granular Layer)= 4788.70 sqm
Quantity of BC= 191.55 cum
Quantity of DBM= 287.32 cum
Quantity of WMM= 484.86 cum
Quantity of CT base= 490.84 cum
Quantity of CT Sub base= 1321.68 cum
Quantity of Subgrade= 3471.808 cum

Quantity Calculation For TCS-2 (4 LANE DIVIDED CARRIAGEWAY WITH PAVED SHOULDER IN BYPASS STRETCH)

Chainage
Length CD Length Net Length
From To
59995 64245 4250 277.38 3972.62
65380 67220 1840 66.5 1773.5

Total Length= 6090 343.88 5746.12 m

Width of Flexible Pavement= 14.0 m


Width of Kerb Shyness (@0.5m each side)= 1.0 m
Width of Median = 4.0 m
Width of Paved Shoulder (@2.5m each side)= 5.0 m
Width of Earthen Shoulder (@1.5m each side)= 3.0 m
Width of BC= 20.00 m
Width of DBM= 20.00 m
Width of WMM = 20.250 m
Width of CT Base = 20.500 m
Width of CT Sub Base = 28.60 m
Width of Subgrade= 30.00 m

Quantity of Prime coat= 114922.40 sqm


Quantity of Tack coat (Granular Layer)= 114922.40 sqm
Quantity of BC= 4596.90 cum
Quantity of DBM= 6895.34 cum
Quantity of WMM= 11635.89 cum
Quantity of CT base= 11779.55 cum
Quantity of CT Sub base= 32867.81 cum
Quantity of Subgrade= 86191.80 cum
Quantity Calculation For TCS-6A (4 LANE DIVIDED CARRIAGEWAY WITH PAVED SHOULDER IN VUP/ROB APPROACHES WITH BOTH SIDE
SERVICE ROAD IN BUILT UP/ RURAL AREA FOLLOWS EXISTING 2-LANE ROAD) (CONCENTRIC WIDENING)

Chainage
Length CD Length Net Length
From To
49470 50445 975 273.80 701.2
67220 67556 336 33.94 302.06

Total Length= 1311 307.74 1003.26 m

Width of Flexible Pavement (@9.5m each side)= 19.0 m


Width of Median= 4.0 m

Width of BC= 19.00 m


Width of DBM= 19.00 m
Width of WMM = 16.00 m
Width of CT Base = 16.00 m
Width of CT Sub Base = 16.00 m
Width of Subgrade= 22.26 m

Quantity of Prime coat= 19061.94 sqm


Quantity of Tack coat (Granular Layer)= 19061.94 sqm
Quantity of BC= 762.48 cum
Quantity of DBM= 1143.72 cum
Quantity of WMM= 1605.22 cum
Quantity of CT base= 1605.22 cum
Quantity of CT Sub base= 3210.43 cum
Quantity of Subgrade= 11166.28 cum

Quantity Calculation For TCS-6B (4 LANE DIVIDED CARRIAGEWAY WITH PAVED SHOULDER IN VUP/ROB APPROACHES WITHOUT BOTH
SIDE SERVICE ROAD IN BUILT UP/ RURAL AREA FOLLOWS EXISTING 2-LANE ROAD) (CONCENTRIC WIDENING)
Chainage
Length CD Length Net Length
From To
64245 65380 1135 627.38 507.62

Total Length= 1135 627.38 507.62 m

Width of Flexible Pavement (@9.5m each side)= 19.0 m


Width of Median= 4.0 m

Width of BC= 19.00 m


Width of DBM= 19.00 m
Width of WMM = 16.00 m
Width of CT Base = 16.00 m
Width of CT Sub Base = 16.00 m
Width of Subgrade= 22.26 m

Quantity of Prime coat= 9644.78 sqm


Quantity of Tack coat (Granular Layer)= 9644.78 sqm
Quantity of BC= 385.79 cum
Quantity of DBM= 578.69 cum
Quantity of WMM= 812.19 cum
Quantity of CT base= 812.19 cum
Quantity of CT Sub base= 1624.38 cum
Quantity of Subgrade= 5649.81 cum
Estimate For 2-Lane Portion
Quantity Calculation For TCS-7 (2 LANE CARRIAGEWAY WITH PAVED SHOULDER IN VUP/ROB APPROACHES WITHOUT SERVICE ROAD IN
BUILT UP/ RURAL AREA)
Chainage
Length CD Length Net Length
From To
0 438 438 33.94 404.06

Total Length= 438 33.94 404.06 m

Width of Flexible Pavement = 9.5 m

Width of BC= 9.50 m


Width of DBM= 9.50 m
Width of WMM = 6.50 m
Width of CT Base = 6.50 m
Width of CT Sub Base = 6.50 m
Width of Subgrade= 8.76 m

Quantity of Prime coat= 3838.57 sqm


Quantity of Tack coat (Granular Layer)= 3838.57 sqm
Quantity of BC= 153.54 cum
Quantity of DBM= 230.31 cum
Quantity of WMM= 262.64 cum
Quantity of CT base= 262.64 cum
Quantity of CT Sub base= 525.28 cum
Quantity of Subgrade= 1769.78 cum

Quantity Calculation For TCS-8 (2 LANE CARRIAGEWAY WITH PAVED SHOULDER IN BYPASS STRETCH)

Chainage
Length CD Length Net Length
From To
438 1071 633 0 633

Total Length= 633 0 633 m

Width of Flexible Pavement= 7.0 m


Width of Kerb Shyness (@0.5m each side)= 1.0 m
Width of Paved Shoulder (@2.0m each side)= 4.0 m
Width of Earthen Shoulder (@1.5m each side)= 3.0 m
Width of BC= 12.00 m
Width of DBM= 12.00 m
Width of WMM = 12.125 m
Width of CT Base = 12.250 m
Width of CT Sub Base = 16.60 m
Width of Subgrade= 18.00 m

Quantity of Prime coat= 7596.00 sqm


Quantity of Tack coat (Granular Layer)= 7596.00 sqm
Quantity of BC= 303.84 cum
Quantity of DBM= 455.76 cum
Quantity of WMM= 767.51 cum
Quantity of CT base= 775.43 cum
Quantity of CT Sub base= 2101.56 cum
Quantity of Subgrade= 5697.00 cum
Quantity Calculation For Proposed Clover Leaf

Total Length= 830 m

Width of Flexible Pavement = 8.0 m

Width of BC= 8.00 m


Width of DBM= 8.00 m
Width of WMM = 5.00 m
Width of CT Base = 5.00 m
Width of CT Sub Base = 5.00 m
Width of Subgrade= 7.26 m

Quantity of Prime coat= 6640.00 sqm


Quantity of Tack coat (Granular Layer)= 6640.00 sqm
Quantity of BC= 265.60 cum
Quantity of DBM= 398.40 cum
Quantity of WMM= 415.00 cum
Quantity of CT base= 415.00 cum
Quantity of CT Sub base= 830.00 cum
Quantity of Subgrade= 3012.90 cum

Total Quantity:
Unit Road Part Total
Total Quantity of Prime coat= sqm 255031.39 255031.39

Total Quantity of Tack coat


sqm 255031.39 255031.39
(Granular Layer)=
Total Quantity of BC= cum 10201.26 10201.26
Total Quantity of DBM= cum 15301.88 15301.88
Total Quantity of WMM= cum 24947.89 24947.89
Total Quantity of CT base= cum 25216.12 25216.12
Total Quantity of CT Sub base= cum 66917.91 66917.91
Total Quantity of Subgrade= cum 181150.15 181150.15

From Chainage 48.655 km to 49.205 km (550m length) already considered in the Estimate of Road Hapachara - Tulungia
Road. For this, Road part length of 550 m is not considered for Estimate Purpose.
QUANTITY CALCULATION OF SHOULDER FOR MAIN ROAD

For TCS 2, TCS 8 (Both Side Earthen Shoulder)

DBM Side Offset of


Total Length BC Thickness
CT base WMM (m) Thickness each Pavement
(m) (m)
(m) Layer (m)

6379.12 0.100 0.100 0.060 0.040 0.125

Shoulder Thickness (Crust Thickness of Shoulder Portion)= 0.300 m


Top Width of Shoulder= 1.50 m
Bottom Width of Shoulder= 2.1 m
Avg. Width of Shoulder= 1.8 m

Quantity of Shoulder (cum)=


=2x (1.8 X 0.3 X 6379.12) - 2X(0.1x0.125x6379.12)-2 X (0.1x 0.25x6379.12)
6411.02
Quantity of Hard Shoulder= 2870.60 cum
Quantity of Earthen Shoulder= 3540.42 cum

For TCS 1A, TCS 1B, TCS 1G, TCS 1H (Single Side Earthen Shoulder-Widening Portion)
.
Total Length DBM BC Thickness Side Offset of
CT base WMM (m)
(m) Thickness (m) each Pavement
9332.77 0.100 0.100 0.060 0.040 0.125

Shoulder Thickness (Crust Thickness of Shoulder Portion)= 0.300 m


Top Width of Shoulder= 1.50 m
Bottom Width of Shoulder= 2.1 m
Avg. Width of Shoulder= 1.8 m

Quantity of Shoulder (cum)=


= (1.8 X 0.3 X 9332.77) - (0.1x0.125x9332.77) - (0.1x 0.25x9332.77)
4689.72
Quantity of Hard Shoulder= 2099.87 cum
Quantity of Earthen Shoulder= 2589.85 cum
For TCS 1B, TCS 1G (Single Side Earthen Shoulder-Existing portion)

Total Length DBM BC Thickness Side Offset of


RAP (m)
(m) Thickness (m) each Pavement
6699.60 0.110 0.060 0.040 0.125

Shoulder Thickness (Crust Thickness of Shoulder Portion)= 0.210 m


Top Width of Shoulder= 1.50 m
Bottom Width of Shoulder= 1.92 m
Avg. Width of Shoulder= 1.71 m

Quantity of Shoulder (cum)=


= (1.71 X 0.21 X 6699.6) - (x0.125x6699.6) - (0.11x 0.25x6699.6)
2221.59
Quantity of Hard Shoulder= 1507.41 cum
Quantity of Earthen Shoulder= 714.18 cum

For TCS 1H (Single Side Earthen Shoulder-Existing portion)

Total Length DBM BC Thickness Side Offset of


WMM (m) WMM (m)
(m) Thickness (m) each Pavement
478.87 0.125 0.125 0.100 0.040 0.125

Shoulder Thickness (Crust Thickness of Shoulder Portion)= 0.390 m


Top Width of Shoulder= 1.50 m
Bottom Width of Shoulder= 2.28 m
Avg. Width of Shoulder= 1.89 m

Quantity of Shoulder (cum)=


= (1.89 X 0.39 X 478.87) - (0.125x0.125x478.87) - (0.125x 0.25x478.87)
330.53
Quantity of Hard Shoulder= 107.75 cum
Quantity of Earthen Shoulder= 222.78 cum

Quantity summary of Shoulder::


Total Quantity of Hard Shoulder= 6585.63 cum
Total Quantity of Earthen Shoulder= 7067.23 cum
Calculation of Extra Widening
For 0.6m EXTRA WIDENING

START END CHORD LENGTH OF


HIP/CURVE RADIUS
ELEMENT LENGTH EXTRA
NO. (m)
(m) WIDENING(m)
CHAINAGE (m) CHAINAGE (m)
Transition 53043.478 53133.478 90 45.00
1 Arc 53133.478 53202.641 69.163 69.16 250
Transition 53202.641 53292.641 90 45.00
Transition 53891.218 53981.218 90 45.00
2 Arc 53981.218 54168.119 186.9 186.90 250
Transition 54168.119 54258.119 90 45.00
Transition 54980.064 55070.064 90 45.00
3 Arc 55070.064 55101.913 31.849 31.85 250
Transition 55101.913 55191.913 90 45.00
Total Length of 0.6m Extra Widening= 558 m

Total Length of 0.6m Extra Widening= 558 m


Total Area of Extra Widening= 334.8 sqm
Layer Thickness:-
Pavement Thickness (m)
Subgrade 0.500
CT Sub Base 0.200
CT Base 0.100
WMM 0.100
DBM 0.060
BC 0.040

Quantity Summary Of Extra Widening::


Total Quantity of Subgrade= 167.400 cum
Total Quantity of CT Sub Base = 66.96 cum
Total Quantity of CT Base = 33.48 cum
Total Quantity of WMM= 33.48 cum
Total Quantity of DBM= 20.09 cum
Total Quantity of BC= 13.39 cum
Total Quantity of Tack Coat (Granular Layer)= 334.80 sqm
Total Quantity of Prime Coat= 334.80 sqm
Summary of Flexible Pavement
Total Quantity:
Road Part
(Ch. 48.455 Km to Ch. 67.556 Km) & (Ch. 0.000 Km to Ch. 1.071 Km)
Re-use
Unit Total
Extra Shoulder Material
Existing Portion Widening Portion
Widening (Main Road)

Total Quantity of Prime coat= sqm 71784.70 255031.39 334.80 327150.89

Total Quantity of Tack coat


sqm 21543.00 21543.00
(Bituminous Layer)=

Total Quantity of Tack coat


sqm 71784.70 255031.39 334.80 327150.89
(Granular Layer)=

Total Quantity of BC= cum 3733.11 10201.26 13.39 13947.76

Total Quantity of DBM= cum 6652.93 15301.88 20.09 21974.90

Total Quantity of WMM= cum 1219.62 24947.89 33.48 26200.99

Total Quantity of CT base= cum 25216.12 33.48 25249.60

Total Quantity of CT sub base= cum 66917.91 66.96 66984.87

Total Quantity of GSB


cum 13324.88 6585.63 3636 16274.51
(Drainage/Filter Layer) =
Total Quantity of GSB
cum 12431.11 5454 6977.11
(Separation Layer) =

Total Quantity of RAP= cum 7461.68 7575 7461.68

Total Quantity of Geocell= sqm 82874.05 82874.05

Total Quantity of Subgrade= cum 0.00 181150.15 167.40 7067.23 188384.78


Quantity calculation for Service Road

Pavement Layer thickness (TCS 6A): Pavement Layer thickness (TCS 4A):
Pavement
Pavement layer Thickness (m)
layer
BC 0.040 BC
WMM 0.100 DBM
CT base 0.100 WMM
CT sub base 0.200 GSB
Subgrade 0.500 Subgrade

Carriageway Width of
Shoulder Width of BC Width of CT base CT sub base
TCS Type width Subgrade
width(m) (m) WMM (m) (m) (m)
(m) (m)
TCS 6A 15 0 15 15 15 15 15

Prime Coat Tack Coat BC WMM CT base CT sub base Subgrade


TCS Type Length(m)
(sqm) (sqm) (cum) (cum) (cum) (cum) (cum)
TCS 6A 1311 19665.00 19665.00 786.60 1966.50 1966.50 3933.00 9832.50
Total 1311 19665.00 19665.00 786.60 1966.50 1966.50 3933.00 9832.50

Service Road at Clover Leaf Location:

Service Road for Carriageway Width of


Shoulder Width of BC Width of CT base CT sub base
Clover Leaf width Subgrade
width(m) (m) WMM (m) (m) (m)
(m) (m)
9 0 9 9 9 9 9

Prime Coat Tack Coat BC WMM CT base CT sub base Subgrade


Length(m)
(sqm) (sqm) (cum) (cum) (cum) (cum) (cum)
1025 9225.00 9225.00 369.00 922.50 922.50 1845.00 4612.50
Total 1025 9225.00 9225.00 369.00 922.50 922.50 1845.00 4612.50

Quantity Summary::

Total Quantity of Prime coat= 28890.00


Total Quantity of Tack coat (Granular Layer)= 28890.00
Total Quantity of BC= 1155.60
Total Quantity of WMM= 2889.00
Total Quantity of CT Base 2889.00
Total Quantity of CT Sub Base 5778.00
Total Quantity of Subgrade= 14445.00
Total Quantity of RCC Crash Barrier (M20) = 2622.00
Quantity Calculation For Drain (Service Road)
Cover Drain (1.5 m Width)

Chainage(m)
CD Length TCS Type Side Net Length(m)
From To
49470 50445 TCS 6A Both 1950
67220 67556 TCS 6A Both 672
Total Length= 2622 m

Outfall of 10 m length in 2
20 m
location =
Total length of drain = 2642 m

1.50 m

0.15 m
0.25 m FRL
0.90 m
0.15 m

0.20 m
0.10 m
Quantity Calculation for Covered Side Drain : 1.70 m
Length Width Thickness Quantity
Item Component Nos
(m) (m) (m) (cum)
Earthwork 1 2642 1.800 1.100 5231.160
PCC
1 2642 1.700 0.100 449.140
(M15)

RCC Side wall 2 2642 0.900 0.150 713.340


(M25)-substructure Bottom slab 1 2642 1.500 0.200 792.600
Total = 1505.940

Reinforcement in ton (@ 70 kg/cum of RCC) 105.416


Total (in ton) = 105.416

RCC-M25 cover 1 2642 1.500 0.150 594.450


Total = 594.450

Reinforcement in ton (@ 70 kg/cum of RCC) 41.612


Total (in ton) = 41.612

Weep holes
no of weep holes in horizontal (per meter) X (2642 + 1) X2 = 5286
(PVC pipe 50 mm dia)
Total = 5286

Quantity Summary :
Total Quantity of earthwork = 5231.16 cum
Total Quantity of PCC M15 = 449.14 cum
Total Quantity of RCC M25 (sub-structure) = 2100.39 cum
Total Quantity of Steel (sub-structure)= 147.03 t
Weep-hole= 5286 no.

Cover Drain (1.0m Width)

Service Road at Clover Leaf Location:


CD Length TCS Type Side Net Length(m)

1025 Single 1025.00


Total Length= 1025 m

Outfall of 10 m length in 2
20 m
location =
Total length of drain = 1045 m

1.00 m

0.15 m
0.25 m FRL
0.90 m
0.10 m

0.20 m
0.10 m
Quantity Calculation for Covered Side Drain : 1.20 m
Length Width Thickness Quantity
Item Component Nos
(m) (m) (m) (cum)
Earthwork 1 1045 1.300 1.100 1494.350
PCC
1 1045 1.200 0.100 125.400
(M15)
RCC Side wall 2 1045 0.900 0.100 188.100
(M25)-substructure Bottom slab 1 1045 1.000 0.200 209.000
Total = 397.100

Reinforcement in ton (@ 70 kg/cum of RCC) 27.797


Total (in ton) = 27.797

RCC-M25 cover 1 1045 1.000 0.150 156.750


Dudection
(super-structure)
forPolyelasto
Total = 156.750

Reinforcement in ton (@ 70 kg/cum of RCC) 10.973


Total (in ton) = 10.973

Weep holes
no of weep holes in horizontal (per meter) X (1045 + 1) X2 = 2092
(PVC pipe 50 mm dia)
Total = 2092

Quantity Summary :
Total Quantity of earthwork = 1494.35 cum
Total Quantity of PCC M15 = 125.40 cum
Total Quantity of RCC M25 (sub-structure) = 553.85 cum
Total Quantity of Steel (sub-structure)= 38.77 t
Weep-hole= 2092 no.

Total Quantity Summary :


Total Quantity of earthwork = 6725.51 cum
Total Quantity of PCC M15 = 574.54 cum
Total Quantity of RCC M25 (sub-structure) = 2654.24 cum
Total Quantity of Steel (sub-structure)= 185.80 t
Weep-hole= 7378.00 no.
CALCULATION FOR BUS -BAY WITH PASSENGER SHELTER

Chainage of Bus bay With Passenger Shelter: Thickness of Layer: Chainage of Passenger Shelter:
Chainage(km) Side Layer Thickness Chainage(km) Side
57.400 Both Subgrade 500 Both
65.700 Both CT sub base 200
CT base 100
WMM 100
DBM 60
BC 40

Total Number of Busbay = 4 Nos


Total Number of Passenger Shelter = 4 Nos

Area required for Busbay = 0.5x100x10+30x10+0.5x100x10 = 1300 sqm


Area of Kerb = 30x1.5 = 45.00 sqm
Deducting area for kerb, Total area = 1255 sqm

Subgrade 4x1255x0.5 = 2510 cum


CT sub base 4x1255x0.2 = 1004 cum
CT base 4x1255x0.1 = 502 cum
WMM Quantity = 4x1255x0.1 = 502 cum
DBM Quantity = 4x1255x0.06 = 301.2 cum
BC Quantity = 4x1255x0.04 = 200.8 cum
Prime coat Quantity = 4x1255 = 5020 sqm
Tack coat Quantity (Granular)= 1x4x1255 = 5020 sqm
Kerb Length = 252 m
Earthwork for Median = 51.246 cum
Drawing of Passenger Shelter (Not to Scale):- x
0.25 2.625 0.25 2.625 0.25

0.25
0.50
0.75 0.25 1.25
1.5 5.00
0.2 0.125
0.1
0.75 0.25
Foundation

x Plan
0.45
0.35 0.25
0.1 0.1
0.15 0.1
0.05
0.45 0.45
0.9
2.15 2.1
0.075
0.25 0.525

GL
0.25 0.3
0.15
0.1 th PCC over 0.5
0.075 th B.F.S
Section at X-X
Thickness
Total
Component Description Unit Nos Length Width (w) /height Quantity
Quantity
(t)
Foundation
Column cum 6 0.85 0.85 0.75 3.25
Earthwork For Brick Wall cum 1 13.50 0.50 0.30 2.03
Total = 5.28 21.12
Lower Portion cum 1 13.50 0.50 0.15 1.01
Brick Masonry (1:4) Upper Portion cum 1 13.50 0.25 0.15 0.51
Total = 1.52 6.08
Column cum 6 0.75 0.75 0.10 0.34
6 0.56 0.06 0.20 0.06
RCC (M-20)
6 0.25 0.25 0.45 0.17
Total = 0.57 2.28
Column ton (@ 75 kg/cum of RCC) 0.04
Reinforcement
Total = 0.04 0.16
Super structure
Lower Portion of
Side Wall & Back cum 1 13.50 0.25 0.25 0.84
wall
Upper Portion of
cum 1 3.00 0.125 1.88 0.71
Side Wall
Brick Masonry
Upper Portion of
cum 1 5.25 0.125 1.60 1.05
back wall
Railing cum 1 9.75 0.125 0.45 0.55
Seating bench cum 3 0.50 0.250 0.525 0.20
Deduction for Window 2 1.25 0.125 0.90 0.28
Plinth soling Sqm 1 5.75 1.75 0.075 0.75
Total = 4.38 17.52
Floor cum 1 5.75 1.75 0.10 1.01
PCC (M15)
Total = 1.01 4.04
Front column cum 3 0.25 0.25 2.65 0.50
Back column cum 3 0.25 0.25 2.10 0.39
Side beam (RB2) cum 2 1.53 0.35 0.25 0.27
Side beam (RB1) cum 4 3.00 0.35 0.25 1.05
RCC M25 Roof slab cum 1 5.25 1.53 0.10 0.80
Front Chajja cum 1 5.25 0.68 0.10 0.36
Back Chajja cum 1 5.25 0.45 0.05 0.12
Seating bench cum 1 5.00 0.50 0.075 0.19
Total = 3.68 14.72
Reinforcement ton (@ 75 kg/cum of RCC) 0.28
Total = 0.28 1.12
Side wall
sqm 4 2.00 3.83 30.64
(Both Side)
Backwall
sqm 2 6.00 2.35 28.20
Plastering (Both Side)
Roof sqm 1 5.25 1.53 8.03
Dudection for Window 4 1.25 0.90 4.50
Total = 62.37 249.48
Summary of Quantity of Busbay with Passenger Shelter:
DESCRIPTION QUANTITY UNIT
Road part
Subgrade 2510.00 cum
CT sub base 1004.00 cum
CT base 502.00 cum
WMM 502.00 cum
DBM 301.20 cum
BC 200.80 cum
Prime coat 5020.00 sqm
Tack coat (Granular)= 5020.00 sqm
Kerb 252.00 m
Earthwork (median) 51.25 cum
Foundation
Earthwork 21.12 cum
Brick Masonry (1:4) 6.08 cum
RCC (M-25) 2.28 cum
Reinforcement 0.16 ton
Super structure
Brick Masonry 17.52 cum
PCC (M15) 4.04 cum
RCC (M-25) 14.72 cum
Reinforcement 1.12 ton
Plastering 249.48 sqm
Quantity Calculation For Junction Road
Thickness
Pavement Layer
(m)
BC 0.040
DBM 0.060
WMM 0.100
CT base 0.100
CT sub base 0.200
Subgrade 0.500

Quantity Calculation for Major junction:


CT sub
Area per Total Prime Coat Tack Coat BC DBM WMM CT base Subgrade
Type of junction No base
junction(sqm) area(sqm) (sqm) (sqm) (cum) (cum) (cum) (cum) (cum)
(cum)
Major junction (3
1 2000.000 2000.000 2000.00 2000.000 80.000 120.000 200.000 200.000 400.000 1000.000
Legged)

Quantity Calculation for Minor junction:


CT sub
Area per Total Prime Coat Tack Coat BC DBM WMM CT base Subgrade
Type of junction No base
junction(sqm) area(sqm) (sqm) (sqm) (cum) (cum) (cum) (cum) (cum)
(cum)
Minor junction (4
5 300.000 1500.000 1500.00 1500.000 60.000 90.000 150.000 150.000 300.000 750.000
Legged)
Minor junction (3
10 200.000 2000.000 2000.00 2000.000 80.000 120.000 200.000 200.000 400.000 1000.000
Legged)

Total Quantity of CT sub base= 1100.00 cum


Total Quantity of CT base= 550.00 cum
Total Quantity of WMM= 550.00 cum
Total Quantity of DBM= 330.00 cum
Total Quantity of BC= 220.00 cum
Total Quantity of Tack Coat (Granular surface)= 5500.00 sqm
Total Quantity of Prime Coat= 5500.00 sqm
Total Quantity of Subgrade= 2750.00 cum
CALCULATION FOR DELINEATOR
In Horizontal Curves (radius 1000 m or less)

START END Spacing Nos in Nos in 1.8s 3s 6s


HIP / CURVE RADIUS 1.8s end 3s end of 6s end of
ELEMENT on Curve Length outside inner beginning beginning beginning
NO. CHAINAGE CHAINAGE (m) of curve curve curve
(S) curve (s) curve (2s) of curve of curve of curve
(m) (m)

2 Arc 50599.051 50656.158 600 38 57.107 4 2 2 2 2 2 2 2


3 Arc 51666.690 51688.980 600 38 22.290 2 2 2 2 2 2 2 2
4 Arc 53133.478 53202.641 250 20 69.163 8 4 2 2 2 2 2 2
5 Arc 53981.218 54168.119 250 20 186.901 20 10 2 2 2 2 2 2
6 Arc 55070.064 55101.913 250 20 31.849 4 2 2 2 2 2 2 2
7 Arc 56911.071 56925.947 500 35 14.876 2 2 2 0 2 0 2 0
8 Arc 57045.283 57157.127 500 35 111.844 8 4 0 2 2 2 0 2
9 Arc 59812.394 60247.183 800 45 434.789 20 10 2 2 2 2 2 2
10 Arc 62186.655 62413.048 500 35 226.393 14 8 2 0 2 0 2 0
11 Arc 62528.186 62928.421 600 38 400.235 22 12 0 2 2 2 0 2
12 Arc 66861.408 66966.515 500 35 105.107 8 4 2 0 2 0 2 0
For 2-Lane Portion
13 Arc 631.074 928.363 500 35 297.289 18 10 0 0 2 0 0 0
TOTAL = 1957.8 130 70 18 16 24 16 18 16

Total no. of delineator = 308 nos.


CALCULATION FOR ROAD STUD

START END START CH. END CH. Spacing Total On


Transition HAND OF Total On
SL. No. Description of section CHAINAGE CHAINAGE Length Radius on Curve Median
length Road Stud Road stud ARC shoulder
(m) (m) (S) (nos)

Horizontal curve :: 50599.051 50656.158 80 50499.051 50756.158 257.11 600 18 Right 30 30


Curve radii upto 450 , 51666.690 51688.980 80 51566.690 51788.98 222.29 600 18 Left 26 26
spacing =9m. 53133.478 53202.641 90 53023.478 53312.641 289.16 250 9 Left 66 66
Curve radii 451 to 750 , 53981.218 54168.119 90 53871.218 54278.119 406.90 250 9 Right 92 92
spacing =18m. 55070.064 55101.913 90 54960.064 55211.913 251.85 250 9 Left 56 56
Curve radii 751 to 2000m 56911.071 56925.947 45 56846.071 56990.947 144.88 500 18 Right 18 18
& critical sections, 57045.283 57157.127 45 56980.283 57222.127 241.84 500 18 Right 28 28
1
spacing =27m 59812.394 60247.183 30 59762.394 60297.183 534.79 800 27 Right 40 40
61209.511 61959.164 30 61159.511 62009.164 849.65 1100 27 Left 64 64
62186.655 62413.048 45 62121.655 62478.048 356.39 500 18 Left 40 40
62528.186 62928.421 40 62468.186 62988.421 520.24 600 18 Right 58 58
66861.408 66966.515 45 66796.408 67031.515 235.11 500 18 Right 28 28
For 2-Lane Portion
631.074 928.363 45 566.074 993.363 427.29 500 18 Left 48 48
Total= 594 594

Total no. of Road stud = 1188 nos.


Quantity Calculation for Traffic sign
IRC-67 2012
Sl No Type Dimension Chainage / Location No Remarks
Specification
900 mm
1 Right Hand Side Curve fig 15.02 7 location 14 @ 2 per location
Tringular
900 mm
2 Left Hand Side Curve fig 15.01 6 location 12 @ 2 per location
Tringular
900 mm
3 School fig 15.34 2 location 4 @ 2 per location
Tringular
900 mm
4 Side road left fig 15.10 9 location 18 @ 2 per location
Tringular
900 mm
5 Side road right fig 15.09 2 location 4 @ 2 per location
Tringular
900 mm
6 Cross Road fig 15.14 5 nos 10 @ 2 per location
Tringular
800x600 2 Nos
7 Bus Stop fig 17.35 8 @ 2 per location
rectangular
8 Direction Sign <.0.9 sqm 21
900 mm
9 Stop Sign fig 14.01 22
Octagonal
600mm
10 Horn prohibited fig 14.18 School ( 2 location) 4
Cicular
Hazard Marker fig 15.76 & fig 900x300 mm
11 Culvert,Bridge, VUP & ROB Location 316 @ 4 per structure
(one way) 15.77 rectangular
Object Marker fig 15.76 & fig 900x300 mm
12 Busbay 8 @ 2per location
(one way) 15.77 rectangular
900 mm
19 Pedestrian Crossing Fig 15.33 18
Tringular
SUMMARY
90 cm equilateral triangle 91
Stop Sign (90 cm high octagon) 25
60 cm circular 10
80 cm x 60 cm rectangular 8
Direction Sign <.0.9 sqm 25
Object
329
marker(900X300mm)

Calculation for Kilometre Stone :

Item No. Calculation Backup

5 th Kilometer Stone 8 Total Length /5

Kilometer stones 22 (Total Length ) - No.of km 5th Stones


(Total Lengthx5) - No.of km 5th Stones - No.of km
Hectometer stones 58
Stones

Boundary stones 178 (Total Lengthx5x2) + 2x1


Quantity Calculation for Road Marking

Effective Length of road (m) 17626.83

Length of Road for 4 Lane Portion= 16589.77 m


Length of Road for 2 Lane Portion= 1037.06 m

Lane Marking (Center Line):


Items NO. Length (m) Width (m) Area (sqm) Remarks
Lane marking in 4 lane portion
2 16589.77 0.15 1990.77 @3m Marking per 7.5m Length
excluding junction
Lane marking in 2 lane portion
1 1037.06 0.15 62.22 @3m Marking per 7.5m Length
excluding junction
Sub total= 2052.99 sqm

Total
Lane marking in Mainline, Junction 2054.990
(in sqm)=

Edge Line Marking (Main line):


Items Effective Length (m) Width (m) Area (sqm) Remarks
Edge Line marking (For 4 Lane portion) 66359.08 0.15 9953.86 Continuous line
Edge Line marking (For 2 Lane portion) 2074.12 0.15 311.12 Continious line
Sub total= 10264.98

Total
Total Edge Line Marking on project Road = 10264.98
(in sqm)=

Pedestarian Marking:
Marking per junction Individual
Location No. Total Area (sqm)
(nos) Area(sqm)

Bus Stop(both side) 4 20 1.5 120

Schools 2 20 1.5 60
Total (in sqm) = 210

(i) Lane marking, edge marking sqm 12530

(ii) Lettering sqm 1253

Total = 13783
Say 13800

Total area of painting = 13800 sqm


Quantity Calculation for W-Metal Beam Crash Barrier

Description No Length(m) Remarks


@ 50m length at the approach of
Major Bridge 1 200
the structure at 4 side
@ 50m length at the approach of
Minor Bridge 9 1800
the structure at 4 side
@ 50m length at the approach of
ROB 2 400
the structure at 4 side
Total langth= 2400 m

W-Beam crash barrier above 3m high embankment

Chainage(km)
Side Length (m)
TCS Type Length
TCS 2 5746.12 Both 11492.24
TCS 8 633.00 Both 1266
Total= 12758.24

Total Length of W- Beam


15158.24 m
crash barrier=
CALCULATION FOR STREET LIGHTING

Proposed Street light location (Median & Service Road):

TCS Type Length Length (m)

TCS 6A 1311.00 3933.00


Total = 3933

Busbay & Passenger Shelter location= 920 m


Bridge approach= 2400.00 m
Bridge Portion= 1795.17 m
Total length = 9048 m

Assuming , street lights @= 50 m interval

for 9048 m 181 nos

Total nos of street light= 185 nos


Quantity Calculation of Toe Wall

Toe wall for 0.6m height


Top Width of Wall: 250 mm 250
Thickness of PCC: 100 mm
Depth Below Ground Level: 900 mm
Height: 1500 mm
Width at bottom: 850 mm 600
height above groundlevel : 600 mm
g.l
1500 m
Per metre Quantity 1h in 2.5v
900
Excavation: 0.765 cum
PCC: 0.085 cum
RCC M25 : 0.770 cum
850

Chainage
Total Earth
PCC M15 RCC M25
Sl. No. CD length Net length side Length Work
from to (cum) (cum)
(m) (cum)

1 62575 62635 60.00 LHS 60.00 45.90 5.10 46.20


2 63845 63945 100.00 LHS 100.00 76.50 8.50 77.00
Toe wall for 1.0m height 250
Top Width of Wall: 250 mm
Thickness of PCC: 100 mm
Depth Below Ground Level: 2000 mm
Height: 3000 mm 1000
Width at bottom: 1500 mm
height above groundlevel : 1000 mm g.l
3000
1h in 2.5v
Per metre Quantity 2000

Excavation: 3 cum
PCC: 0.15 cum
Brickwork: 2.538 cum 1500
Pointing of exposed surface: 2.25 sqm

CHAINAGE Total Earth Brick


PCC M15
Sl. No. CD length Length SIDE Length Work work
FROM TO (cum)
(m) (cum) (cum)
56825 57145 32.39 320 LHS 287.61 220.02 24.45 221.46
58720 58845 125 LHS 125.00 95.63 10.63 96.25
59120 59345 225 LHS 225.00 172.13 19.13 173.25
60175 60285 110 LHS 110.00 84.15 9.35 84.70
1
61845 62015 170 LHS 170.00 130.05 14.45 130.90
62015 62195 67.88 180 RHS 112.12 85.77 9.53 86.33
62245 62470 225 RHS 225.00 172.13 19.13 173.25
62945 63170 225 Both 450.00 344.25 38.25 346.50

Quantity summary ::

Earthwork = 1426.53 cum


PCC M15 = 158.52 cum
RCC M25 = 1435.84 cum
Steel 100.51 t
QUANTITY CALCULATION RETAINING WALL

RETAINING WALL HIGHT 2m

Chainage
side Hight CD Length Length
From To
55840 55985 RHS 2.0 145
61845 62015 RHS 2.0 170
62015 62195 LHS 2.0 67.88 112.12
62635 62845 LHS 2.0 210
63170 63845 Both 2.0 1350
66970 67095 Both 2.0 66.5 117

Length of 2.0m Retaining Wall = 2104.12 m

450

600 Parapet wall of C.R.M. 1:4


Road Level
s lo p
e1
in 3

H1

Random Rubble Masonry (1:3)

600 mm Filter Media


B3
600
B1

H2

B2

PCC M15 n6
1i
300 mm thick
150

Hight (H1) T B1 B2 B3 H2
2 0.6 1.27 1.288 1.1 0.212
Unit
Quantity Total
Item Calculation Unit
Quantity
For 2m
Earth Work in Excavation= 1/2x[(H2+0.6+0.3)+(0.6+0.3)]x(0.15+B3+0.3) cum 0.99 2083.08
PCC M15 in Foundation = 0.3x(0.15+B2+0.15) cum 0.48 1009.98
RR Masonry (1:3) =
[1/2x(B3+B1)x0.6]+[1/2xH2xB1] 0.85
(Foundation) cum 1788.50
RR Masonry (1:3) = 1/2x(B3+T)x(H1-0.6) cum 1.19 2503.90
Parapet wall @ 2m length &
0.6m Gap (2x0.45x0.6) cum 0.54 437.40
CR Masonry (1:3)
Weepholes (1/1) x (H1/1)X(B2+T)/2 nos 2.00 2104.12
Filter Media 0.6 x (H1+H2) cum 1.33 2798.48

Quantity Summary
Earthwork in Ordinary Soil = 2083.08 cum
PCC M15 in Foundation = 1009.98 cum
RR Masonry (Foundation)= 1788.50 cum
RR Masonry (1:3) = 2503.90 cum
CR Masonry (1:3) = 437.40 cum
Weepholes= 2104.12 nos
Filter Media= 2798.48 cum
QUANTITY CALCULATION FOR RE WALL

RE Wall Facing Element

Chainage (km) Total Net Length Height Quantity


CD Length Unit Nos
Length (m) (m) (sqm)
From To
49.470 50.445 975 273.800 sqm 2 701.20 7.00 9816.8
67.220 67.556 336 33.940 sqm 2 302.06 8.90 5376.7
64.245 65.380 1135 627.380 sqm 2 508 9.2 9347.2
0.000 0.438 438 33.940 sqm 2 404 7.3 5898.4
Length of Clover Leaf 553 sqm 2 553 7.5 8295.0
Total = 38734.1
Total Quantity of Facing Element= 38734.1 sqm

Backfilling Behind the facing Elements of RE Wall

Chainage (km) Total Net Length Breadth Height Quantity


CD Length Unit Nos
From To Length (m) (m) (m) (cum)
49.470 50.445 975 273.80 sqm 1 701.20 22.4 6.50 102094.72
67.220 67.556 336 33.94 sqm 1 302.06 22.4 8.40 56835.61
64.245 65.380 1135 627.38 sqm 1 508 22.4 5.40 61447.68
0.000 0.438 438 33.94 sqm 1 404 10.5 5.50 23331
Length of Clover Leaf 553 0.00 sqm 1 553 7.4 7.70 31509.94
Total = 275218.95

Total Quantity of Backfilling Material= 275218.95 cum

Filter Media

Chainage (km) Total Net Length Breadth Height Quantity


CD Length Unit Nos
From To Length (m) (m) (m) (cum)
49.470 50.445 975 273.8 cum 2 701.2 0.6 7.00 5890.1
67.220 67.556 336 33.94 cum 2 302.06 0.6 8.90 3226.0
64.245 65.380 1135 627.38 cum 2 507.62 0.6 9.20 5604.1
0.000 0.438 438 33.94 cum 2 404.06 0.6 7.30 3539.6
Length of Clover Leaf 553 0 cum 2 553 0.6 7.50 4977.0
Total = 23236.8

Total Quantity of Filter Media= 23236.8 cum

RCC Crash Barrier

Chainage (km) Total Net Length Quantity


CD Length Unit Nos
From To Length (m) (cum)
49.470 50.445 975 273.8 m 2 701.2 1402.4
67.220 67.556 336 33.94 m 2 302.06 604.12
64.245 65.380 1135 627.38 m 2 507.62 1015.24
0.000 0.438 438 33.94 m 2 404.06 808.12
Length of Clover Leaf 553 0 m 2 553 1106
Total = 4935.88

Total Quantity of Crash Barrier= 4935.88 m


Friction slab for RCC Crash Barrier

Chainage (km) Total Net Length Quantity


CD Length Unit Nos Area (sqm)
From To Length (m) (cum)
49.470 50.445 975 273.8 cum 2 701.2 0.84 1178.016
67.220 67.556 336 33.94 cum 2 302.06 0.84 507.4608
64.245 65.38 1135 627.38 cum 2 507.62 0.84 852.8016
0 0.438 438 33.94 cum 2 404.06 0.84 678.8208
Length of Clover Leaf 553 0 cum 2 553 0.84 929.04
Total = 4146.1392

Total Quantity of Friction slab for RCC Crash Barrier= 4146.1392 Cum

Steel Reinforcement @ 70kg / cum= 290.229744 ton

PCC M15 under friction slab for RCC Crash Barrier

Chainage (km) Total Net Length Breadth Height Quantity


CD Length Unit Nos
From To Length (m) (m) (m) (cum)
49.470 50.445 975 273.8 cum 2 701.2 2 0.1 280.48
67.220 67.556 336 33.94 cum 2 302.06 2 0.1 120.824
64.245 65.38 1135 627.38 cum 2 507.62 2 0.1 203.048
0 0.438 438 33.94 cum 2 404.06 2 0.1 161.624
Length of Clover Leaf 553 0 cum 2 553 2 0.1 221.2
Total = 987.176

Total Quantity of PCC M15 under friction slab for RCC Crash Barrier= 987 Cum
Quantity Calculation For Median
Length Calculation of Median:
Median Kerb Width
Earthwork
TCS Type Length (m) Width (One side) Depth (m)
(cum)
(m) (m)

TCS 1A 2154.30 1.5 0.165 1701.36


TCS 1B 5523.68 1.5 0.165 4362.33
TCS 1G 1175.92 1.5 0.165 928.68
TCS 1H 478.87 1.5 0.165 0.675 378.19
TCS 2 5746.12 4.0 0.165 14234.58
TCS 6A 1003.26 4.0 0.165 2485.33
TCS 6B 507.62 4.0 0.165 1257.50
Total= 16590 25347.97

Earthwork Quantity for Median= 25347.97 cum


Length of Kerb = 33180 m
Quantity Calculation of Unlined Drain

Length of Unlined Drain= 31423.78 m


Quantity Calculation for Utility Duct

Length of Road= 17.6268 km

Provided Duct in Median and Both side of the Road

The total Length of Duct= 52.8805 km


52880.5 m
Guard Stone For Culvert

Guard Stone for Culvert, taking 10 Nos Guard Stone


Both Side For 31 nos Culvert = 310 Nos
Taking Approach Road for Culvert (10m Both Side)= 620 m
Taking 2.0m C/C Both Side Guard Stone = 620.0 Nos

Total Nos of Guard Stone = 930.00 Nos


Quantity Calculation For Chute Drain

For RR Masonry Chute drain:


CHAINAGE (M) CD
Side Length(m)
From To Length (m)
61645 64245 Both 125.30 4949.40
65380 67220 Both 66.50 3547.00
Total= 8496.4 m

Taking 50 m interval for Chute Drain and height of Embankment is 5 m we get,

Total Length of Drain= 849.64 m

For RR Masonry Chute drain:


CHAINAGE (M) CD
Side Length(m)
From To Length (m)
438 1071 Both 0 1266.00
Total= 1266 m

No of Catch Pit drain to be Provided = 2 Nos


So, Total Length = 2532 m

Taking 50 m interval for Chute Drain and height of Embankment is 10 m we get,

Total Length of Drain= 506.40 m

Thickness/
Item Unit Nos Length Width Quantity
Depth
Earth Work Cum 1 1356 0.70 0.75 711.90
Stone Pitching Cum 1 1356 1.00 0.15 203.40
Side Portion Cum 7 221 0.15 0.6 139.23
(PCC M20)
(side wall)
Cum 2 1356 0.15 0.45 183.06
(PCC M20)
PCC M20
Cum 1 1356 1.00 0.10 135.6
(Bottom)

Earthwork in Ordinary Soil = 711.90 cum


PCC M20 = 457.89 cum
Stone Pitching = 203.40 cum
Quantity Calculation for Sand Piling

Location above 8m height Where Sand Pile Required:

Chainage CD length Net length Avg Width No of Sand Pile taking 2 m C/C Distance Total
Depth (m)
from to (m) (m) (m) LengthWise WidthWise Length (m)
For 2-Lane Portion
0 300 33.94 266.06 12.00 134.00 7.00 10.00 9380.000
625 1171 546.00 30.00 274.00 16.00 10.00 43840.000
Total = 812.06 53220.00

So, Total Length Of Sand Pile = 53220.00 m


Quantity Calculation for Structure Works
Major Bridge
JOB NO : 4146 (PACKAGE-5)
Summary sheet of Major Bridge(Quantities & amount)
Chainage (Km) 62+041

2 x 30m_PSC T Total Quantity


Span(m)
Girder
Sl No. Description Unit
A. Foundation
Item no 1(a) Excavation (upto 3 m depth) cum 1795.340 1795.340
Item no 1(b) Excavation (3 m to 6 m depth) cum 224.000 224.000
Item no 2 R.C.C M30 (Pile Cap) cum 1061.740 1061.740
Item no 3 P.C.C (M-15) cum 94.500 94.500
Item no 4 Bored cast-in-situ M35 grade R.C.C. Piles m 1734.000 1734.000
Item no 5 steel liner 6mm thick ton 9.590 9.590
Item no 6 Steel (Foundation) ton 320.977 320.977
B. Sub-Structure
Item no 1(a) R.C.C M30 (Substructure) upto 5m cum 456.810 456.810
Item no 1(b) R.C.C M30 (Substructure) from 5m to 10m cum 186.160 186.160
Item no 2 R.C.C. M35 for Pedestals & RB cum 42.060 42.060
Item no 3 Steel (Substructure) ton 95.904 95.904
Item no 4 Weep Holes each 378.000 378.000
Item no 5 Backfilling - Granular Material cum 245.700 245.700
Item no 6 Backfilling - Sandy Material cum 1019.540 1019.540
Item no 7 Filter Media cum 285.880 285.880
Item no 8 Elastomeric Bearing cc 639150.000 639150.000
Item no 9 POT cum PTFE Bearing ton 9600.000 9600.000
C. Super-Structure
Item no 1(a) R.C.C M30 (Superstructure) upto 5m cum 15.250 15.250
Item no 1(e) R.C.C M45(Superstructure) upto 5m cum 344.930 344.930
Item no 1(f) P.S.C M45(Superstructure) upto 5m cum 547.030 547.030
Item no 2(a) Steel (Superstructure) ton 136.082 136.082
Item no 3(a) Bituminous Concrete Wearing Coat(65mm) cum 51.500 51.500
Item no 3(b) Mastic Asphalt sqm 1287.440 1287.440
Item no 3(c) Tack Coat sqm 1287.440 1287.440
Item no 2(b) PSC Steel ton 44.000 44.000
Item no 3(d) Cement Concrete Wearing Course cum 15.250 15.250
Item no 4 RCC railing metre 135.520 135.520
Item no 5 Crash Barrier metre 271.040 271.040
Item no 6 Drainage Spout each 20.000 20.000
Item no 8 PCC below approach slab cum 24.670 24.670
Item no 9 R.C.C. Approach Slab with steel (M30) cum 50.610 50.610
Item no 10 Strip Seal Expansion Joint metre 50.000 50.000
Item no 11 Filler Joint
(i) copper plate metre 48.200 48.200
(ii) fibre board metre 48.200 48.200
(iii) 20mm thick premoulded joint filler metre 48.200 48.200
(iv) joint sealing compound metre 48.200 48.200
D. Protection Work
Item no 1a Boulder Pitching cum 820.670 820.670
Item no 1b Filter Media cum 410.340 410.340
Item no 2 Falling Apron on River Bed cum 193.240 193.240
E. Miscelleaneous
Item no 1a Painting sqm 1068.820 1068.820
Item no 2 Citizen Information Board NH project no 2.000 2.000
Brick work at median cum 4.740 4.740
Brick Flat Soling (BFS) below brick wall at median cum 4.020 4.020
QUANTITY CALCULATION OF BRIDGE AT CH._ 62.041 KM ON BILASIPURA-GUWAHATI STRETCH
BHARATMALA LOT-I PKG-IA IN THE STATE OF ASSAM

2 No. X 30 M SPAN CH._ 62.041 KM


Length
Item Sl No. Description Unit nos. Breadth (m) Height (m) Quantity
(m)

FOUNDATION
1.1 Excavation upto 3m depth
Abutment-1 cum 2 13.60 9.70 3.00 791.52
Pier-1 cum 2 9.70 9.70 2.15 404.59
Abutment-2 cum 2 13.60 9.70 2.25 593.64
Return wall I at median (A1 side) cum 1 2.00 1.30 1.87 4.86
Return wall I at median (A2 side) cum 1 2.00 1.30 0.28 0.73
Total 1795.34

1.2 Excavation 3.0m to 6.0m depth


Abutment-1 cum 2 13.60 9.70 0.849 224.00
Total 224.00

2 Pile cap RCC M30


Abutment cum 4 12.60 8.700 1.80 789.26
Pier cum 2 8.70 8.700 1.80 272.48
Total= 1061.74

3 Bored Cast-in-situ Pile M35 (dia.=1.2m)


Abutment-1 m 24 26.000 624.00
Pier-1 m 18 27.000 486.00
Abutment-2 m 24 26.000 624.00
Total= 1734.00

4 PCC M-15 levelling course


Below Pile-cap for Abutment cum 4 12.90 9.00 0.15 69.66
Below Pile-cap for Pier cum 2 9.00 9.00 0.15 24.30
Below Brick wall at median cum 2 2.98 0.90 0.10 0.54
Total= 94.50

5 Steel Liner(1.2m dia pile)


Pier-1 tonne 18 3.77 0.006 3.00 9.59
Total= 9.59

6 HYSD Bars
90kg/cum for pile cap & @ 130kg/m
T Total= 320.977
for pile

7 BFS below brick wall at median


cum 2 2.98 0.90 0.75 4.023
Total= 4.02
QUANTITY CALCULATION OF BRIDGE AT CH._ 62.041 KM ON BILASIPURA-GUWAHATI STRETCH
BHARATMALA LOT-I PKG-IA IN THE STATE OF ASSAM

2 No. X 30 M SPAN CH._ 62.041 KM


Length
Item Sl No. Description Unit nos. Breadth (m) Height (m) Quantity
(m)
SUBSTRUCTURE
8 RCC M-30 upto 5.0m height
Abutment wall cum 4 12.50 1.200 4.600 276.00
Abutment cap cum 4 12.80 2.120 0.400 43.42
Pier shaft (straight portion) cum 2 7.00 1.200 5.000 84.00
Pier shaft (circular portion) cum 4 0.57 5.000 11.40
Return Wall-I upto abutment cap cum 4 3.75 0.450 4.576 30.89
Return Wall-I above abutment cap cum 4 2.83 0.450 0.424 2.16
Return Wall-I at median cum 2 0.30 2.980 5.000 8.94
Total= 456.81

9 RCC M-30 height above 5.0m upto 10.0m


Pier shaft (straight portion) cum 2 7.00 1.200 0.850 14.28
Pier shaft (circular portion) cum 4 0.57 0.850 1.94
Pier cap(Trapizoidal portion) cum 2 10.40 2.250 0.700 32.76
Pier cap(Rectangular portion) cum 2 12.60 3.300 0.700 58.21
Dirt Wall cum 4 12.80 0.400 2.394 49.03
Bracket cum 4 12.35 0.180 8.89
Return Wall-I above abutment cap cum 4 2.83 0.450 2.850 14.52
Return wall extra fins rectangular
cum 4 0.30 2.500 1.000 3.00
portion
Return wall extra fins triangular
cum 4 0.30 2.081 2.50
portion
Return Wall at median cum 2 2.98 0.300 0.575 1.03
Total= 186.160

10 RCC M-35 for Pedestal & Seismic Arrestor Blocks height upto 5.0m
cum 4 0.80 0.800 0.150 0.38
Pedestal at Abutment & Pier POT cum 4 0.80 0.800 0.197 0.50
bearing cum 4 0.80 0.800 0.272 0.70
cum 4 0.80 0.800 0.347 0.89
cum 4 0.80 0.800 0.150 0.38
Pedestal at Abutment & Pier for POT cum 4 0.80 0.800 0.197 0.50
cum PTFE bearing cum 4 0.80 0.800 0.272 0.70
cum 4 0.800 0.800 0.347 0.89
Total= 4.94
Block RB2 cum 16 0.700 0.550 1.400 8.62
Block RB1 cum 16 1.299 0.800 16.63
Block RB3 cum 8 1.060 1.000 1.400 11.87
Total= 42.06

11 HYSD Bars
@ 120 kg/cum T 95.904
Total= 95.904
QUANTITY CALCULATION OF BRIDGE AT CH._ 62.041 KM ON BILASIPURA-GUWAHATI STRETCH
BHARATMALA LOT-I PKG-IA IN THE STATE OF ASSAM

2 No. X 30 M SPAN CH._ 62.041 KM


Length
Item Sl No. Description Unit nos. Breadth (m) Height (m) Quantity
(m)
12 Weep holes
Spacing for weep holes = 2 m in horizontal and 1 m in vertical direction
No of weep holes in horizontal direction per abutment = 12.05/2+1 = 8
No of weep holes in vertical direction per abutment = 4.6/1+1 = 6
No of weep holes in horizental direction per return wall = (3.29)/2+1 = 3
No of weep holes in vertical direction per return wall = (7.85-0.3-0.15)/1+1 = 9
No of weep holes in horizental direction per return wall at median = (2.98)/2+1 = 3
No of weep holes in vertical direction per return wall at median= (5.575)/1+1 = 7
No of weep holes in horizental direction per return wall extra fin = (2.5)/2+1 = 3
No of weep holes in vertical direction per return wall extra fin = (1.8325)/2+1 = 3
Total no of Weep holes per abutment = 8 x 6 48
Total no of Weep holes per return wall = 3 x 9 27
Total no of Weep holes per return wall at median= 7 x 3 21
Total no of Weep holes per return wall extra fin portion = 3 x 3 9
Total no of weep holes = 48 x 4 + 27 x 4 + 21 x 2 + 9 x 4 Total 378.00

13.1 Backfilling - Granular Material


Abutment cum 4 22.30 1.950 173.94
Pier cum 2 18.40 1.950 71.76
Total 245.70

13.2 Backfilling - Sandy Material


Behind Abutment & Return wall-I cum 4 11.45 3.15 7.544 1088.37
Behind Return wall at median cum 2 3.00 4.650 8.113 226.35
Deduct for filter media cum -285.88
Deduct for Brick wall cum -9.30
Total 1019.54

14 Filter media
Behind Abutment cum 4 12.050 0.60 7.544 218.17
Behind Return wall-I cum 4 2.690 0.60 7.400 47.77
Behind Return at median cum 2 2.980 0.60 5.575 19.94
Total 285.88

15 POT & POT cum PTFE Bearing


ton 32 300.00 9600.00
Total 9600.00

16 Elastomeric Bearing
Bearing B2 cucm 16 37.00 54.50 9.80 316187
Bearing B3 cucm 32 27.00 42.00 8.90 322963
Total 639150
QUANTITY CALCULATION OF BRIDGE AT CH._ 62.041 KM ON BILASIPURA-GUWAHATI STRETCH
BHARATMALA LOT-I PKG-IA IN THE STATE OF ASSAM

2 No. X 30 M SPAN CH._ 62.041 KM


Length
Item Sl No. Description Unit nos. Breadth (m) Height (m) Quantity
(m)
SUPERSTRUCTURE

17 PSC M-45 Girder portion


Long Girder middle portion cum 4 21.600 3.744 323.48

Long Girder end straight portion cum 8 1.950 6.272 97.84

Long Girder varying portion cum 8 1.600 5.008 64.10

End Cross Girder (portion in between


cum 8 0.400 9.513 30.44
the long girder)

End Cross Girder (rectangular part) cum 8 0.400 0.520 1.66


IntermediateCross Girder (portion in
cum 8 0.300 11.408 27.38
between the long girder)
Intermediate Cross Girder (triangular
cum 8 0.300 0.888 2.13
part)
Total 547.03

18 R.C.C. Deck slab (M45)


Deck Slab cum 4 28.70 12.500 0.225 322.88
Cantilever portion of Deck Slab cum 8 0.630 12.500 0.350 22.05
Total 344.93

19 Kerb (M30)
cum 2 67.76 0.50 0.225 15.25
Total 15.25

20 PSC Steel
@11 Ton per span TON 2 22.00 44.00
Total 44.00

21 Superstructure Steel (HYSD Bars)


@ 150 kg/cum TON 136.082
Total= 136.082

22 RCC M30 Railing


m 2 67.76 135.52
Total= 135.52

23 RCC M40 Crash Barrier


m 4 67.76 271.04
Total= 271.04

24 Drainage Spout nos. 20 Total 20.00

25 M15 PCC below Approach Slab


cum 4 3.370 12.200 0.15 24.67
Total 24.67
QUANTITY CALCULATION OF BRIDGE AT CH._ 62.041 KM ON BILASIPURA-GUWAHATI STRETCH
BHARATMALA LOT-I PKG-IA IN THE STATE OF ASSAM

2 No. X 30 M SPAN CH._ 62.041 KM


Length
Item Sl No. Description Unit nos. Breadth (m) Height (m) Quantity
(m)
26 Approach Slab(M30)
Approach Slab cum 4 3.500 12.050 0.300 50.61
Total 50.61

27 Bituminus concrete wearing course


cum 2 67.76 9.50 0.040 51.50
Total= 51.50

28 Mastic asphalt
sqm 2 67.76 9.50 1287.44
Total= 1287.44

29 Tack coat
sqm 2 67.76 9.50 1287.44
Total= 1287.44

30 Cement Concrete wearing coarse(75mm)


cum 2 67.76 1.50 0.075 15.25
Total= 15.25

31 Filler joint
Providing & fixing 2 mm thick
corrugated copper plate in expansion m 4 12.05 48.20
joint
Providing & fixing 20 mm thick
compressible fibre board in expansion m 4 12.05 48.20
joint
Providing and fixing in position 20 mm
m 4 12.05 48.20
thick premoulded joint filler
Providing and filling joint sealing
m 4 12.05 48.20
compound

32 Strip Seal Expansion Joint


m 4 12.500 50.00
Total 50.00

33 Brick work at median


Above the abutment cap cum 2 2.380 0.250 2.513 2.99
Below the abutment cap cum 2 2.380 0.368 1.75
Total 4.74
QUANTITY CALCULATION OF BRIDGE AT CH._ 62.041 KM ON BILASIPURA-GUWAHATI STRETCH
BHARATMALA LOT-I PKG-IA IN THE STATE OF ASSAM

2 No. X 30 M SPAN CH._ 62.041 KM


Length
Item Sl No. Description Unit nos. Breadth (m) Height (m) Quantity
(m)
PROTECTION WORK

Pitching with Stone Blanket (A1


34 cum 2 500.34 0.30 300.204
side)
Pitching with Stone Blanket (A2
cum 2 697.82 0.30 418.692
side)
In front of abutments cum 2 28.00 6.058 0.30 101.774
Total 820.67

35 Floor Protection
A1 & A2 side (Straight part) cum 4 10.00 0.601 24.040
A1 & A2 side (Curved part) cum 4 17.00 1.127 76.636
Infront of the abutment and return
cum 2 28.00 1.653 92.568
wall at median
Total 193.24

36 Filter material below stone pitching


A1 side cum 2 500.34 0.15 150.102
A2 side cum 2 697.82 0.15 209.346
In front of abutments cum 2 28.00 6.058 0.15 50.887
Total= 410.34

MISCELLANNEOUS
37 Painting
Kerb below railing sqm 2 0.950 67.76 128.74
Railing(Post) sqm 80 1.03 1.10 90.64
Railing(Beam) sqm 6 0.69 67.76 280.53
Crash Barrier sqm 4 2.099 67.76 568.91
Total 1068.820

38 Citizen information Board NH Project no Total 2.000


Minor Bridge
JOB NO : 4146 (PACKAGE-5)
Summary sheet of Minor Bridges (Quantities & amount)

CHAINAGE 49+236 51+819 54+332 56+461 KM 56+985 KM


3X8.0X4.0 1X13.0 M + 1
Span RCC BOX 3X8.8X4.0 X13.5 M + 1 X13.0 1X21M INTEGRAL 1X24M INTEGRAL
Arrangement with both side RCC BOX M VOIDED SLAB VOIDED SLAB
Service Road INTEGRAL SLAB
ITEM NO. Description Unit
A. Foundation
Item no 1(a) Excavation (upto 3 m depth) cum 4028.530 945.674 804.200 505.860 313.150
Item no 1(b) Excavation (3 m to 6 m depth) cum 157.173 54.200 37.340
Item no 2 R.C.C M30 (Pile Cap) cum 425.960 231.340 231.340
Item no 3 P.C.C (M-15) cum 193.175 63.963 38.560 20.900 20.900
Item no 4 Bored cast-in-situ M35 grade R.C.C. Piles m 504.000 288.000 400.000
Item no 5 steel liner 6mm thick ton 0.000
Item no 6 Steel (Foundation) ton 103.860 58.260 72.820
B. Sub-Structure
Item no 1(a) R.C.C M30 (Substructure) upto 5m cum 1169.284 410.453 179.740 100.530 109.940
Item no 1(b) R.C.C M30 (Substructure) from 5m to 10m cum 1.380
Item no 2 R.C.C. M35 for Pedestals & RB cum
Item no 3 Steel (Substructure) ton 81.850 28.732 21.950 12.060 13.190
Item no 4 Weep Holes each 372.000 180.000 116.000 120.000 120.000
Item no 5 Backfilling - Granular Material cum 71.996 49.115 138.550 72.930 72.930
Item no 6 Backfilling - Sandy Material cum 380.017 258.985 144.700 130.060 127.220
Item no 7 Filter Media cum 276.961 103.643 65.950 69.950 71.630
Item no 8 Elastomeric Bearing cc
Item no 9 POT cum PTFE Bearing ton
CHAINAGE 49+236 51+819 54+332 56+461 KM 56+985 KM
3X8.0X4.0 1X13.0 M + 1
Span RCC BOX 3X8.8X4.0 X13.5 M + 1 X13.0 1X21M INTEGRAL 1X24M INTEGRAL
Arrangement with both side RCC BOX M VOIDED SLAB VOIDED SLAB
Service Road INTEGRAL SLAB
ITEM NO. Description Unit
C. Super-Structure
Item no 1(a) R.C.C M30 (Superstructure) upto 5m cum 662.950 221.903 340.130 240.370 289.030
Item no 1(e) R.C.C M45(Superstructure) upto 5m cum
Item no 1(f) P.S.C M45(Superstructure) upto 5m cum
Item no 2(a) Steel (Superstructure) ton 49.721 16.643 51.020 40.860 49.140
Item no 2(b) PSC Steel ton
Item no 3(a) Bituminous Concrete Wearing Coat(65mm) cum 46.200 13.490 18.050 11.100 12.290
Item no 3(b) Mastic Asphalt sqm 1155.000 337.250 451.250 277.400 307.330
Item no 3(c) Tack Coat sqm 1155.000 337.250 451.250 277.400 307.330
Item no 3(d) Cement Concrete Wearing Course cum 7.425 3.994 5.340 3.290 3.640
Item no 4 RCC railing metre 66.000 35.500 47.500 29.200 32.350
Item no 5 Crash Barrier metre 264.000 71.000 95.000 58.400 64.700
Item no 6 Drainage Spout each 24.000 6.000 6.000 2.000 2.000
Item no 7 HDPE Pipe m 153.900 176.850
Item no 8 PCC below approach slab cum 21.767 12.567 12.360 12.360 12.360
Item no 9 R.C.C. Approach Slab with steel (M30) cum 44.268 25.788 25.370 25.370 25.370
Item no 10 Strip Seal Expansion Joint metre
Item no 11 Filler Joint
(i) copper plate metre 84.320 24.560 24.160 24.160 24.160
(ii) fibre board metre 84.320 24.560 24.160 24.160 24.160
(iii) 20mm thick premoulded joint filler metre 84.320 24.560 24.160 24.160 24.160
(iv) joint sealing compound metre 84.320 24.560 24.160 24.160 24.160
D. Protection Work
Item no 1a Boulder Pitching cum 66.924 172.218 272.152
Item no 1b Filter Media cum 33.460 86.110 136.080
Item no 2 Falling Apron on River Bed cum 149.180 167.780
Item no 3 PCC(M 15) Toe Wall cum 31.180 0.000
300 mm thick Rubble stone flooring laid over
Item no 4 cum 75.996 103.703
100mm thick cement concrete bedding
Item no 5 750 mm thick Flexible apron cum 121.635 124.358
Item no 6 Curtain Wall- PCC (M-20) cum 119.998 129.203
Item no 7 Excavation in soil cum 660.489 667.215
Item no 9 PCC M15 cum 59.691 72.183
E. Miscelleaneous
Item no 1a Painting sqm 822.690 366.480 371.000 230.380 254.150
Item no 2 Citizen Information Board NH project no 2.000 2.000
Brick work at median cum 0.740 1.600 1.720
Brick flat soling (BFS) for brick wall at median cum
CHAINAGE 60+315 KM 60+930 KM 64+159 KM 67+046 KM

Span Total Quantity


3 X 18m_RCC T- 3 x 18m_RCC 1 x 40m_PSC 3 x 18m_RCC
Arrangement
beam T-girder T-girder T-girder
ITEM NO. Description Unit
A. Foundation
Item no 1(a) Excavation (upto 3 m depth) cum 2120.960 2257.610 1159.310 1778.510 13913.804
Item no 1(b) Excavation (3 m to 6 m depth) cum 126.380 310.030 298.140 158.580 1141.843
Item no 2 R.C.C M30 (Pile Cap) cum 1108.720 1108.720 789.260 1108.720 5004.060
Item no 3 P.C.C (M-15) cum 99.360 99.360 70.200 99.360 705.777
Item no 4 Bored cast-in-situ M35 grade R.C.C. Piles m 1488.000 1488.000 1440.000 1944.000 7552.000
Item no 5 steel liner 6mm thick ton 0.000 0.000
Item no 6 Steel (Foundation) ton 293.225 293.225 251.033 352.505 1424.928
B. Sub-Structure
Item no 1(a) R.C.C M30 (Substructure) upto 5m cum 384.570 384.520 382.610 426.200 3547.847
Item no 1(b) R.C.C M30 (Substructure) from 5m to 10m cum 184.050 177.430 89.130 345.700 797.690
Item no 2 R.C.C. M35 for Pedestals & RB cum 37.820 37.820 19.700 37.820 133.160
Item no 3 Steel (Substructure) ton 72.773 71.972 58.973 97.166 458.666
Item no 4 Weep Holes each 266.000 266.000 340.000 388.000 2168.000
Item no 5 Backfilling - Granular Material cum 289.380 289.380 173.940 289.380 1447.601
Item no 6 Backfilling - Sandy Material cum 758.540 765.320 1222.840 1117.370 4905.052
Item no 7 Filter Media cum 217.700 219.670 300.600 281.120 1607.224
Item no 8 Elastomeric Bearing cc 311760.000 311760.000 103920.000 311760.000 1039200.000
Item no 9 POT cum PTFE Bearing ton 12000.000 12000.000 4800.000 12000.000 40800.000
CHAINAGE 60+315 KM 60+930 KM 64+159 KM 67+046 KM

Span Total Quantity


3 X 18m_RCC T- 3 x 18m_RCC 1 x 40m_PSC 3 x 18m_RCC
Arrangement
beam T-girder T-girder T-girder
ITEM NO. Description Unit
C. Super-Structure
Item no 1(a) R.C.C M30 (Superstructure) upto 5m cum 727.930 727.930 10.760 727.690 3948.694
Item no 1(e) R.C.C M45(Superstructure) upto 5m cum 228.080 228.080
Item no 1(f) P.S.C M45(Superstructure) upto 5m cum 470.830 470.830
Item no 2(a) Steel (Superstructure) ton 131.027 131.027 106.451 130.984 706.873
Item no 2(b) PSC Steel ton 29.000 29.000
Item no 3(a) Bituminous Concrete Wearing Coat(65mm) cum 50.420 50.420 36.330 50.420 288.720
Item no 3(b) Mastic Asphalt sqm 1260.460 1260.460 908.200 1260.460 7217.810
Item no 3(c) Tack Coat sqm 1260.460 1260.460 908.200 1260.460 7217.810
Item no 3(d) Cement Concrete Wearing Course cum 14.930 14.930 10.760 14.930 79.239
Item no 4 RCC railing metre 132.680 132.680 95.600 132.680 704.190
Item no 5 Crash Barrier metre 265.360 265.360 191.200 265.360 1540.380
Item no 6 Drainage Spout each 20.000 20.000 12.000 18.000 110.000
Item no 7 HDPE Pipe m 330.750
Item no 8 PCC below approach slab cum 24.730 24.730 24.320 24.430 169.624
Item no 9 R.C.C. Approach Slab with steel (M30) cum 50.740 50.740 50.530 50.110 348.286
Item no 10 Strip Seal Expansion Joint metre 50.000 50.000 47.600 50.000 197.600
Item no 11 Filler Joint
(i) copper plate metre 48.320 48.320 47.600 47.120 372.720
(ii) fibre board metre 48.320 48.320 47.600 47.120 372.720
(iii) 20mm thick premoulded joint filler metre 48.320 48.320 47.600 47.120 372.720
(iv) joint sealing compound metre 48.320 48.320 47.600 47.120 372.720
D. Protection Work
Item no 1a Boulder Pitching cum 216.060 200.080 550.200 464.450 1942.084
Item no 1b Filter Media cum 108.030 100.040 275.100 232.220 971.040
Item no 2 Falling Apron on River Bed cum 176.900 173.480 102.570 220.230 990.140
Item no 3 PCC(M 15) Toe Wall cum 0.000 0.000 123.280 154.460
300 mm thick Rubble stone flooring laid over
Item no 4 cum 179.699
100mm thick cement concrete bedding
Item no 5 750 mm thick Flexible apron cum 245.993
Item no 6 Curtain Wall- PCC (M-20) cum 249.202
Item no 7 Excavation in soil cum 1327.704
Item no 9 PCC M15 cum 131.874
E. Miscelleaneous
Item no 1a Painting sqm 970.160 970.160 785.690 970.160 5740.870
Item no 2 Citizen Information Board NH project no 2.000 2.000 2.000 2.000 12.000
Brick work at median cum 5.530 5.530 7.130 5.530 27.780
Brick flat soling (BFS) for brick wall at median cum 0.400 0.400 0.400 0.400 1.600
QUANTITY CALCULATION OF BRIDGE AT CH._49.236 KM ON BILASIPURA-GUWAHATI STRETCH
BHARATMALA IN THE STATE OF ASSAM

Box Size:- 3 cell of 8 m x 4 m_SR


CH._49.236 KM with Rigid & Flexible Apron

Breadth
Item No. Description Unit nos Length (m) Height (m) Quantity
(m)

A. FOUNDATION
Item no 1 Excavation(up to 3m)
Box Bridge cum 1 27.000 46.100 2.958 3682.030
Return Wall II cum 4 5.500 5.250 3.000 346.500
` Total 4028.530

Item no 1(b) Excavation(above 3m)


Shear Key cum 2 27.000 1.550 0.600 50.220
Return Wall cum 4 5.500 5.250 0.926 106.953
Total 157.173

Item no 2 PCC-M15
Box Bridge cum 1 26.000 43.300 0.150 168.870
Shear Key cum 2 26.300 1.299 0.150 10.245
Return Wall II cum 4 5.150 4.550 0.150 14.060
Total 193.175

B. SUBSTRUCTURE

Item no 1(a) RCC-M30 (upto 5m)


Bottom Slab cum 1 26.000 45.040 0.600 702.624
Box Side Wall cum 2 45.040 0.600 4.219 228.015
Box middle Wall cum 2 45.040 0.400 4.219 152.010
Base slab of return wall II cum 4 5.000 4.250 0.400 34.000
Return wall II cum 4 5.000 0.325 4.750 30.875
Shear key cum 2 26.000 0.360 18.720
Haunch cum 6 45.040 0.011 3.040
Total= 1169.284

Item no 2 Substructure Steel (HYSD Bars)

70 kg/cum of Concrete ton 1 81.850 81.850

Total 81.850

Item no 3 Weep holes


Spacing for weep holes = 2 m in horizontal and 1 m in vertical direction
No of weep holes in horizontal direction per side wall =44.37/2+1 = 23
No of weep holes in vertical direction per side wall =4.32/1+1 = 6
No of weep holes in horizontal direction per return wall =5/2+1 = 4
No of weep holes in vertical direction per return wall =4.3/1 +1= 6
Total no of Weep holes per side wall = 23 x 6 138
Total no of Weep holes per return wall = 4 x 6 24
Total no of weep holes = 138 x 2 + 24 x 4 372

Item no 4 Backfilling - Sandy Material


Behind Side Wall & cum 2 40.040 3.500 1.850 518.518
return wall
Behind Return wall II cum 4 2.300 3.500 4.300 138.460
Deduct for filter media cum 276.961
Total 380.017
QUANTITY CALCULATION OF BRIDGE AT CH._49.236 KM ON BILASIPURA-GUWAHATI STRETCH
BHARATMALA IN THE STATE OF ASSAM

Box Size:- 3 cell of 8 m x 4 m_SR


CH._49.236 KM with Rigid & Flexible Apron

Breadth
Item No. Description Unit nos Length (m) Height (m) Quantity
(m)

Item no 5 Backfilling - Granular Material


Box cum 1 73.660 0.600 44.196
Shear key cum 2 13.000 0.600 15.600
Return Wall cum 4 7.625 0.400 12.200
Total 71.996

Item no 6 Filter media


Behind Side Wall cum 2 44.640 0.600 4.319 231.347
Behind Return Wall cum 4 4.420 0.600 4.300 45.614
Total 276.961

C. SUPERSTRUCTURE

Item no 1 RCC-M30(up to 5m)


Box Bridge cum 1 26.000 45.040 0.550 644.072
(+)Haunch cum 6 45.040 0.011 3.040
Kerb cum 2 33.000 0.300 0.225 4.455
Rectangular part of bracket cum 2 42.160 0.300 0.300 7.589
Triangular part of bracket cum 2 42.160 0.045 3.794
Total 662.950

Item no 2 Superstructure Steel (HYSD Bars)


75 kg/cum of concrete ton 1 49.721 49.721
Total 49.721

Item no 3(a) Wearing Course (Bituminous Concrete)


cum 2 33.000 17.500 0.040 46.200
Total 46.200

Item no 3(b) Wearing Course (Cement Concrete)


cum 2 33.000 1.500 0.075 7.425
Total 7.425

Item no 3(c) Wearing Course (Mastic Asphalt)


sqm 2 33.000 17.500 1155.000
Total 1155.000

Item no 3(d) Tack Coat


sqm 2 33.000 17.500 1155.000
Total 1155.000

Item no 4 Crash Barrier m 8 33.000 264.000


Total 264.000

Item no 5 Railing m 2 33.000 66.000


Total 66.000

Item no 6 Drainage Spout nos. 24 24

Item no 7 PCC below Approach Slab


cum 2 3.370 10.730 0.150 10.848
cum 2 3.370 10.800 0.150 10.919
Total 21.767
QUANTITY CALCULATION OF BRIDGE AT CH._49.236 KM ON BILASIPURA-GUWAHATI STRETCH
BHARATMALA IN THE STATE OF ASSAM

Box Size:- 3 cell of 8 m x 4 m_SR


CH._49.236 KM with Rigid & Flexible Apron

Breadth
Item No. Description Unit nos Length (m) Height (m) Quantity
(m)

Item no 8 Approach Slab


cum 2 3.500 10.580 0.300 22.218
cum 2 3.500 10.500 0.300 22.050
Total 44.268

Item no 9 Filler Joint


(i) copper plate m 4 21.080 84.320
(ii) fiber board m 4 21.080 84.320
(iii) 20mm thick
m 4 21.080 84.320
premoulded joint filler
(iv) joint sealing m 4 21.080 84.320

D. PROTECTION WORK

Item no 1 Rigid Appron


Up stream cum 1 36.040 3.000 0.300 32.436
Down stream cum 1 36.040 5.000 0.300 54.060
Deduction due to
cum 4 5.000 1.750 0.300 -10.500
return wall ll foundation
Total 75.996

Item no 2 Flexible Appron


Up stream cum 1 36.040 1.500 0.750 40.545
Down stream cum 1 36.040 3.000 0.750 81.090
Total 121.635

Item no 3 PCC M20 Curtain Wall


Up stream side cum 1 38.540 1.480 57.039
Down stream side cum 1 42.540 1.480 62.959
Total 119.998

Item no 4 PCC (M-15)


Below Curtain Wall (Up
cum 1 38.540 1.600 0.150 9.250
stream side)
Below Curtain Wall (Down
cum 1 42.540 1.950 0.150 12.443
stream side)
Rigid apron
cum 1 36.040 3.000 0.150 16.218
(Up stream side)
Rigid apron
cum 1 36.040 5.000 0.150 27.030
(Down stream side)
Deduction due to
cum 4 5.000 1.750 0.150 -5.250
return wall ll foundation
Total 59.691
QUANTITY CALCULATION OF BRIDGE AT CH._49.236 KM ON BILASIPURA-GUWAHATI STRETCH
BHARATMALA IN THE STATE OF ASSAM

Box Size:- 3 cell of 8 m x 4 m_SR


CH._49.236 KM with Rigid & Flexible Apron

Breadth
Item No. Description Unit nos Length (m) Height (m) Quantity
(m)

Item no 5 Excavation in Soil


Curtain Wall (upstream) cum 1 38.540 2.600 2.150 215.439
Curtain Wall (downstream) cum 1 42.540 2.950 2.650 332.556
Flexible apron up stream cum 1 36.040 1.500 0.750 40.545
Flexible apron down stream cum 1 36.040 3.000 0.750 81.090
Rigid apron up stream cum 1 36.040 3.000 0.450 48.654
Rigid apron down stream cum 1 36.040 5.000 0.450 81.090
Deduction due to Curtain
cum 1 36.040 1.300 0.750 -35.139
Wall (up stream)
Deduction due to Curtain
cum 1 36.040 1.475 0.750 -39.869
Wall(down stream)
Deduction due to Curtain
cum 1 38.540 1.300 0.450 -22.546
Wall (up stream)
Deduction due to Curtain
cum 1 38.540 1.475 0.450 -25.581
Wall(down stream)
Deduction due to
cum 4 5.000 1.750 0.450 -15.750
return wall ll foundation
Total 660.489

MISCELLANEOUS
Item no 1 Painting
Kerb below railing. sqm 2 0.750 33.00 49.50
Railing(Post) sqm 46 1.05 1.10 53.13
Railing(Beam) sqm 6 0.69 33.00 136.62
Crash Barrier sqm 8 2.210 33.00 583.44
Total 822.690
QUANTITY CALCULATION OF BRIDGE AT CH._51.819KM ON BILASIPURA-GUWAHATI STRETCH
BHARATMALA IN THE STATE OF ASSAM

Box Size:- 3 cell of 8.8 m x 4 m


CH._51.819KM Additional 2 lane bridge
with Rigid & Flexible Apron
Length Breadth Height
Item No. Description Unit nos Quantity
(m) (m) (m)

A. FOUNDATION
Item no 1 Excavation(up to 3m)
Box Bridge cum 1 29.500 13.500 1.880 748.693
Shear Key cum 2 29.500 1.500 0.550 48.675
Return Wall II cum 2 5.500 5.350 2.369 139.396
Return wall at median cum 2 2.500 1.650 1.080 8.910
` Total= 945.674

Item no 2 PCC-M15
Box Bridge cum 1 28.500 10.800 0.150 46.170
Shear Key cum 2 28.800 1.228 0.150 10.608
Return Wall II cum 2 5.150 4.650 0.150 7.184
Total= 63.963

B. SUBSTRUCTURE

Item no 1 (a) RCC-M30 (upto 5m)


Bottom Slab cum 1 28.500 12.500 0.650 231.563
Box Side Wall cum 2 12.500 0.650 4.119 66.930
Box middle Wall cum 2 12.500 0.400 4.119 41.188
Base slab of return wall II cum 2 5.000 4.350 0.400 17.400
Return wall(at median) cum 2 2.980 0.650 4.838 18.740
Return wall II cum 2 5.000 0.325 4.850 15.763
Shear key cum 2 28.500 0.316 18.026
Haunch cum 6 12.500 0.011 0.844
Total= 410.453

Item no 2 Substructure Steel (HYSD Bars)

70 kg/cum of Concrete ton 1 28.732 28.732

Total 28.732

Item no 3 Weep holes


Spacing for weep holes = 2 m in horizontal and 1 m in vertical direction
No of weep holes in horizontal direction per side wall =12.5/2+1 = 8
No of weep holes in vertical direction per side wall =4.1/1+1 = 6
No of weep holes in horizontal direction per return wall =5/2+1 = 4
No of weep holes in vertical direction per return wall =4.4/1 +1= 6
No of weep holes in horizontal direction per return wall at median
3
=3/2+1 =
No of weep holes in vertical direction per return wall at median =4.8/1
6
+1=
Total no of Weep holes per side wall = 8 x 6 48
Total no of Weep holes per return wall = 4 x 6 24
Total no of Weep holes per return wall at median = 3 x 6 18
Total no of weep holes = 48 x 2 + 24 x 2 + 18 x 2 180
QUANTITY CALCULATION OF BRIDGE AT CH._51.819KM ON BILASIPURA-GUWAHATI STRETCH
BHARATMALA IN THE STATE OF ASSAM

Box Size:- 3 cell of 8.8 m x 4 m


CH._51.819KM Additional 2 lane bridge
with Rigid & Flexible Apron
Length Breadth Height
Item No. Description Unit nos Quantity
(m) (m) (m)

Item no 4 Backfilling - Sandy Material


Behind Side Wall & cum 2 10.000 3.520 3.031 213.406
Behind Return wall II cum 2 2.300 3.500 4.400 70.840
Return wall(at median) cum 2 2.980 3.500 3.758 78.382
Deduct for filter media cum 103.643
Total 258.985

Item no 5 Backfilling - Granular Material


Box cum 1 42.000 0.650 27.300
Shear key cum 2 14.250 0.550 15.675
Return Wall cum 2 7.675 0.400 6.140
Total 49.115

Item no 6 Filter media


Behind Side Wall cum 2 12.300 0.600 4.269 63.007
Behind Return Wall cum 2 4.420 0.600 4.400 23.338
Return wall(at median) cum 2 2.980 0.600 4.838 17.299
Total 103.643

C. SUPERSTRUCTURE

Item no 1 RCC-M30(up to 5m)


Box Bridge cum 1 28.500 12.500 0.600 213.750
(+)Haunch cum 6 12.500 0.011 0.844
Kerb cum 1 35.500 0.500 0.225 3.994
Rectangular part of bracket cum 2 12.280 0.300 0.300 2.210
Triangular part of bracket cum 2 12.280 0.045 1.105
Total 221.903

Item no 2 Superstructure Steel (HYSD Bars)


75 kg/cum of concrete ton 1 16.643 16.643
Total 16.643

Item no 3(a) Wearing Course (Bituminous Concrete)


cum 1 35.500 9.500 0.040 13.490
Total 13.490

Item no 3(b) Wearing Course (Cement Concrete)


cum 1 35.500 1.500 0.075 3.994
Total 3.994

Item no 3(c) Wearing Course (Mastic Asphalt)


sqm 1 35.500 9.500 337.250
Total 337.250

Item no 3(d) Tack Coat


sqm 1 35.500 9.500 337.250
Total 337.250

Item no 4 Crash Barrier m 2 35.500 71.000


Total 71.000
QUANTITY CALCULATION OF BRIDGE AT CH._51.819KM ON BILASIPURA-GUWAHATI STRETCH
BHARATMALA IN THE STATE OF ASSAM

Box Size:- 3 cell of 8.8 m x 4 m


CH._51.819KM Additional 2 lane bridge
with Rigid & Flexible Apron
Length Breadth Height
Item No. Description Unit nos Quantity
(m) (m) (m)

Item no 5 Railing m 1 35.500 35.500


Total 35.500

Item no 6 Drainage Spout nos. 6 6

Item no 7 PCC below Approach Slab


cum 2 3.370 12.430 0.150 12.567
Total 12.567

Item no 8 Approach Slab


cum 2 3.500 12.280 0.300 25.788
Total 25.788

Item no 9 Filler Joint


(i) copper plate m 2 12.280 24.560
(ii) fibar board m 2 12.280 24.560
(iii) 20mm thick premoulded
m 2 12.280 24.560
joint filler
(iv) joint sealing compound m 2 12.280 24.560

D. PROTECTION WORK

Item no 1 300 mm thick Rigid Apron


Up stream cum 1 38.540 3.000 0.300 34.686
Down stream cum 1 33.500 5.000 0.300 50.250
at median cum 1 2.980 27.200 0.300 24.317
Deduction due to
cum 2 5.000 1.850 0.300 -5.550
return wall ll foundation
Total 103.703

Item no 2 Flexible Apron


Up stream cum 1 38.540 1.500 0.750 43.358
Down stream cum 1 36.000 3.000 0.750 81.000
Total 124.358

Item no 3 PCC M20 Curtain Wall


Up stream side cum 1 40.840 1.480 60.443
Down stream side cum 1 36.000 1.910 68.760
Total 129.203

Item no 4 PCC (M-15)


Below Curtain Wall
Up stream side cum 1 40.840 1.600 0.150 9.802
Down stream side cum 1 36.000 1.950 0.150 10.530
Below Rigid Appron
Up stream side cum 1 38.540 3.000 0.150 17.343
Down stream side cum 1 33.500 5.000 0.150 25.125
at median cum 1 2.980 27.200 0.150 12.158
Deduction due to return wall ll
cum 2 5.000 1.850 0.150 -2.775
foundation
Total 72.183
QUANTITY CALCULATION OF BRIDGE AT CH._51.819KM ON BILASIPURA-GUWAHATI STRETCH
BHARATMALA IN THE STATE OF ASSAM

Box Size:- 3 cell of 8.8 m x 4 m


CH._51.819KM Additional 2 lane bridge
with Rigid & Flexible Apron
Length Breadth Height
Item No. Description Unit nos Quantity
(m) (m) (m)

Item no 5 Excavation in Soil


Curtain Wall (up stream) cum 1 40.840 2.600 2.150 228.296
Curtain Wall (down stream) cum 1 36.000 2.950 2.650 281.430
Rigid appron up stream cum 1 38.540 3.000 0.450 52.029
Rigid appron down stream cum 1 33.500 5.000 0.450 75.375
at median cum 1 2.980 27.200 0.450 36.475
Flexible appron up stream cum 1 38.540 1.500 0.750 43.358
Flexible appron down stream cum 1 36.000 3.000 0.750 81.000
Deduction due to Curtain Wall
cum 1 40.840 1.300 0.450 -23.891
(up stream)
Deduction due to Curtain
cum 1 36.000 1.475 0.450 -23.895
Wall(down stream)
Deduction due to Curtain Wall
cum 1 38.540 1.300 0.750 -37.577
(up stream)
Deduction due to Curtain
cum 1 33.500 1.475 0.750 -37.059
Wall(down stream)
Deduction due to
cum 2 5.000 1.850 0.450 -8.325
return wall ll foundation
Total 667.215

MISCELLANNEOUS
Item no 1 Painting
Kerb below railing. sqm 1 0.950 35.50 33.73
Railing(Post) sqm 25 1.05 1.10 28.88
Railing(Beam) sqm 6 0.69 35.50 146.97
Crash Barrier sqm 2 2.210 35.50 156.91
Total 366.480
QUANTITY ESTIMATE OF SIMPLY SUPPORTED INTEGRAL SLAB BRIDGE

1 no x 13.0 M + 1 no x 13.5 M + 1 no x 13.0 M


CHAINAGE - 54.332 KM

Length Height
Item No. Description Unit nos Breadth (m) Quantity
(m) (m)

FOUNDATION
1 Excavation upto 3.0m depth
Abutment-1 cum 1 13.60 6.100 2.95 244.73
Pier-1 cum 1 11.60 6.100 3.00 212.28
Pier-2 cum 1 11.60 6.100 1.99 140.81
Abutment-2 cum 1 13.60 6.100 2.43 201.59
Return Wall (at median) A1 side cum 1 2.50 1.30 0.997 3.24
Return Wall (at median) A2 side cum 1 2.50 1.30 0.478 1.55
Total 804.20

2 Excavation 3.0m to 6.0m depth


Pier-1 cum 1 11.60 6.100 0.766 54.20
Total 54.20

3 Bored Cast-in-situ Piles M-35 (Dia-1.2 m)


Abutment-1 metre 6 22.00 132.00
Pier-1 metre 6 20.00 120.00
Pier-2 metre 6 20.00 120.00
Abutment-2 metre 6 22.00 132.00
Total 504.00

4 Levelling Course for Pile Cap (PCC M-15)


Abutment-1 cum 1 12.900 5.400 0.15 10.45
Pier-1 cum 1 10.900 5.400 0.15 8.83
Pier-2 cum 1 10.900 5.400 0.15 8.83
Abutment-2 cum 1 12.900 5.400 0.15 10.45
Total 38.56

5 RCC M-30
Pile Cap (Abutment-1) cum 1 12.600 5.100 1.80 115.67
Pier-1 cum 1 10.600 5.100 1.80 97.31
Pier-2 cum 1 10.600 5.100 1.80 97.31
Pile Cap (Abutment-2) cum 1 12.600 5.100 1.80 115.67
Total 425.96

6 HYSD Bars

@ 90 kg/cum of cocrete volume


Tonne 103.86
for pile cap & @ 130Kg/m run pile

Total 103.86
QUANTITY ESTIMATE OF SIMPLY SUPPORTED INTEGRAL SLAB BRIDGE

1 no x 13.0 M + 1 no x 13.5 M + 1 no x 13.0 M


CHAINAGE - 54.332 KM

Length Height
Item No. Description Unit nos Breadth (m) Quantity
(m) (m)

SUBSTRUCTURE

8 RCC M-30 upto 5 m


Abutment-1 & 2 cum 2 12.500 1.100 2.857 78.57
Pier (Straight part) cum 2 8.700 0.900 5.000 78.30
Pier (Circular part) cum 2 0.636 5.000 6.36
Bracket cum 2 12.100 0.180 4.36
Return Wall-I cum 2 2.050 0.400 3.738 6.13
Return Wall-I (at median) cum 2 2.980 0.300 2.988 5.34
Return Wall I extra fin
cum 1 0.300 0.811 0.24
portion(triangular)
Return Wall I extra fin
cum 1 0.300 1.470 1.000 0.44
portion(rectangular)
Total 179.74

9 RCC M-30 5 m to 10 m
Pier (Straight part) cum 2 8.700 0.900 0.082 1.28
Pier (Circular part) cum 2 0.636 0.082 0.10
Total 1.38

10 HYSD Bars
@ 120 kg/cum of concrete
t 21.95
volume
Total 21.95

11 Weep holes
Spacing for weep holes = 2 m in horizontal and 1 m in vertical direction
No of weep holes in horizontal direction per abutment = 12.1/2+1 = 8
No of weep holes in vertical direction per abutment = 2.857+1 = 4
No of weep holes in horizontal direction per return wall =(2.05)/2+1 = 3
No of weep holes in vertical direction per return wall =(3.738-0.3-0.15)/1+1 = 5
No of weep holes in horizontal direction per return wall I (at median)
2
=(2.98)/2+1 =
No of weep holes in vertical direction per return wall I (at median) =(2.988)/1+1
4
=
No of weep holes in horizontal direction per return wall extra fin portion
1
=(1.47)/2+1 =
No of weep holes in vertical direction per return wall extra fin portion
3
=(1.5065)/1+1 =
Total no of Weep holes per abutment = 8 x 4 32
Total no of Weep holes per return wall = 3 x 5 15
Total no of Weep holes per return wall I (at median) = 2 x 4 8
Total no of Weep holes per return wall extra fin portion = 2 x 4 3
Total no of weep holes = 32 x 2 + 15 x 2 + 8 x 2 + 3 x 2 Total 116.00
QUANTITY ESTIMATE OF SIMPLY SUPPORTED INTEGRAL SLAB BRIDGE

1 no x 13.0 M + 1 no x 13.5 M + 1 no x 13.0 M


CHAINAGE - 54.332 KM

Length Height
Item No. Description Unit nos Breadth (m) Quantity
(m) (m)

12 Backfilling - Granular Material

Abutment cum 2 18.70 1.950 72.93


Pier cum 2 16.70 1.950 65.13
Total 138.55

13 Backfilling - Sandy Material


Behind Abutment & Return wall cum 2 12.100 2.050 3.407 169.02
Behind Return wall (at median) cum 2 2.980 2.050 3.407 41.63
Deduct for filter media cum -65.95
Total 144.70

14 Filter media
Behind Abutment cum 2 12.100 0.600 3.407 49.47
Behind Return wall-I cum 2 1.450 0.600 3.288 5.72
Behind Return wall (at median) cum 2 3.000 0.600 2.988 10.76
Total 65.95

SUPERSTRUCTURE

15 RCC M-30 - For Solid slab superstructure


At support cum 2 10.50 0.450 1.001 9.46
Varying Portion cum 2 10.50 2.925 0.801 49.20
At mid span cum 1 10.50 6.750 0.600 42.53
For 13.5 m span 0.813
cum 1 6.75 5.49
Cantilever portion
cum 2 3.375 2.000 0.507 6.84
Kerb cum 1 13.50 0.500 0.225 1.52
Total 115.04
cum 2 10.50 0.45 1.001 9.46
At support
cum 2 12.50 0.50 1.026 12.83
cum 2 10.50 2.80 0.801 47.10
Varying Portion
cum 2 10.50 2.75 0.813 46.95
For 13.0 m span At mid span cum 2 10.50 6.50 0.60 81.90
cum 2 6.50 0.813 10.57
Cantilever portion cum 2 3.25 2.00 0.51 6.63
cum 2 2.80 2.00 0.52 5.82
Kerb cum 2 17.00 0.50 0.225 3.83
Total 225.09
Total quantity 340.13
QUANTITY ESTIMATE OF SIMPLY SUPPORTED INTEGRAL SLAB BRIDGE

1 no x 13.0 M + 1 no x 13.5 M + 1 no x 13.0 M


CHAINAGE - 54.332 KM

Length Height
Item No. Description Unit nos Breadth (m) Quantity
(m) (m)
16 HYSD Bars

@ 150 kg/cum of cocrete volume t 51.02

Total 51.02

17 RCC M30 Railing rm 1 47.50 47.50


Total 47.50

18 Crash Barrier RCC M40


m 2 47.50 95.00
Total 95.00

19 Drainage Spout nos. 6 Total 6.00

20 PCC below Approach Slab


cum 2 12.230 3.370 0.150 12.36
Total 12.36

21 Approach Slab RCC M30


Approach Slab cum 2 12.080 3.500 0.300 25.37
Total 25.37

22 Bitumenous concrete Wearing Coat


cum 1 47.50 9.50 0.040 18.05
Total 18.05

23 Mastic asphalt
sqm 1 47.50 9.50 451.25
Total 451.25

24 Tack coat
sqm 1 47.50 9.50 451.25
Total 451.25

25 Cement concrete wearing course on footpath


cum 1 47.50 1.50 0.075 5.34
Total 5.34
QUANTITY ESTIMATE OF SIMPLY SUPPORTED INTEGRAL SLAB BRIDGE

1 no x 13.0 M + 1 no x 13.5 M + 1 no x 13.0 M


CHAINAGE - 54.332 KM

Length Height
Item No. Description Unit nos Breadth (m) Quantity
(m) (m)
26 Filler joint
Providing & fixing 2 mm thick
corrugated copper plate in m 2 12.08 24.16
expansion joint
Providing & fixing 20 mm thick
compressible fibre board in m 2 12.08 24.16
expansion joint
Providing and fixing in position 20
m 2 12.08 24.16
mm thick premoulded joint filler

Providing and filling joint sealing


m 2 12.08 24.16
compound

27 Brick work at median


cum 2 3.00 0.125 0.988 0.74
Total 0.74

PROTECTION WORK

28 Pitching with Stone Blanket

A1 side cum 2 47.12 0.30 28.272

A2 side cum 2 64.42 0.30 38.652

Total 66.924

29 Toe Wall cum 4 0.433 18.00 31.176


Total 31.176

30 Filter Blanket below pitching


A1 side cum 2 47.12 0.15 14.136
A2 side cum 2 64.42 0.15 19.326
Total 33.462

Miscelaneous
31 Paint for concrete surface
Kerb below railing sqm 1 0.950 47.50 45.13
Railing(Post) sqm 26 1.05 1.10 30.03
Railing(Beam) sqm 3 0.69 47.50 98.33
Crash Barrier sqm 2 2.079 47.50 197.51
Total 371.000
QUANTITY CALCULATION OF BRIDGE AT CH._56.461 KM ON BILASIPURA-GUWAHATI STRETCH BHARATMALA
IN THE STATE OF ASSAM

CHAINAGE - 56.461 KM 1 no x 21.0 M RCC Integral Voided Slab

Length Height
Item No. Description Unit nos Breadth (m) Quantity
(m) (m)

FOUNDATION
1 Excavation upto 3.0m depth
Abutment-1 cum 1 13.60 6.100 3.00 248.88
Abutment-2 cum 1 13.60 6.100 3.00 248.88
Return wall @ median (Abutment -A1) cum 1 2.50 1.300 1.38 4.49
Return wall @ median (Abutment -A2) cum 1 2.50 1.300 1.11 3.61
Total 505.86

2 Excavation 3.0m to 6.0m depth


Abutment-1 cum 1 13.60 6.100 0.36 29.87
Abutment-2 cum 1 13.60 6.100 0.09 7.47
Total 37.34

3 Bored Cast-in-situ Piles M-35 (Dia-1.2 m)


Abutment-1 metre 6 24.00 144.00
Abutment-2 metre 6 24.00 144.00
Total 288.00

4 Levelling Course for Pile Cap (PCC M-15)


Abutment-1 cum 1 12.900 5.400 0.15 10.45
Abutment-2 cum 1 12.900 5.400 0.15 10.45
Total 20.90

5 RCC M-30
Pile Cap (Abutment-1) cum 1 12.600 5.100 1.80 115.67
Pile Cap (Abutment-2) cum 1 12.600 5.100 1.80 115.67
Total 231.34

6 HYSD Bars
@ 90 kg/cum of cocrete volume for
Tonne 58.26
pile cap & @ 130Kg/m run pile
Total 58.26
QUANTITY CALCULATION OF BRIDGE AT CH._56.461 KM ON BILASIPURA-GUWAHATI STRETCH BHARATMALA
IN THE STATE OF ASSAM

CHAINAGE - 56.461 KM 1 no x 21.0 M RCC Integral Voided Slab

Length Height
Item No. Description Unit nos Breadth (m) Quantity
(m) (m)
SUBSTRUCTURE

7 RCC M-30 upto 5 m


Abutment-1 & 2 cum 2 12.500 1.200 2.787 83.61
Return Wall-I cum 2 1.950 0.400 3.868 6.03
Return Wall-I (Fin portion) cum 2 2.186 0.300 1.31
Return Wall (at median) cum 2 2.980 0.300 2.918 5.22
Bracket cum 2 12.100 0.180 4.36
Total 100.53

8 HYSD Bars

@ 120 kg/cum of cocrete volume t 12.06

Total 12.06

9 Weep holes
Spacing for weep holes = 2 m in horizontal and 1 m in vertical direction
No of weep holes in horizontal direction per abutment = 12.1/2+1 = 8
No of weep holes in vertical direction per abutment = 2.787/1+1 = 4
No of weep holes in horizontal direction per return wall I =(1.95)/2+1 = 2
No of weep holes in vertical direction per return wall I =(3.868-0.3-0.15)/1+1 = 5

No of weep holes in horizontal direction per return wall I fin portion =(1.57)/2+1 = 2

No of weep holes in vertical direction per return wall I fin portion =(1.3925)/1+1 = 3

No of weep holes in horizontal direction per return wall (at median) =(2.98)/2+1 = 3

No of weep holes in vertical direction per return wall (at median) =(2.918)/1+1 = 4

Total no of Weep holes per abutment = 8 x 4 32


Total no of Weep holes per return wall = 2 x 5 10
Total no of Weep holes per return wall fin portion= 2 x 3 6
Total no of Weep holes per return wall I (at median) = 3 x 4 12
Total no of weep holes = 32 x 2 + 6 x 2 + 10 x 2 + 12 x 2 Total 120.00

10 Backfilling - Granular Material

Abutment cum 2 18.70 1.950 72.93


Total 72.93
QUANTITY CALCULATION OF BRIDGE AT CH._56.461 KM ON BILASIPURA-GUWAHATI STRETCH BHARATMALA
IN THE STATE OF ASSAM

CHAINAGE - 56.461 KM 1 no x 21.0 M RCC Integral Voided Slab

Length Height
Item No. Description Unit nos Breadth (m) Quantity
(m) (m)
11 Backfilling - Sandy Material
Behind Abutment & Return wall cum 2 11.500 1.950 3.537 158.63
Behind Return wall I (at median) cum 2 3.000 1.950 3.537 41.38
Deduct for filter media cum -69.95
Total 130.06

12 Filter media
Behind Abutment cum 2 12.100 0.600 3.537 51.36
Behind Return wall-I cum 2 1.350 0.600 3.418 5.54
Behind Return Wall-I (Fin portion) cum 2 2.186 0.600 2.62
Behind Return wall I (at median) cum 2 2.980 0.600 2.918 10.43
Total 69.95

SUPERSTRUCTURE

13 RCC M-30 - For Voided Slab Superstructure


At support cum 2 12.5 1.200 1.226 36.78
Varrying Portion cum 2 12.500 4.650 1.038 120.67
At mid span cum 1 10.500 10.456 109.79
Deduction for voids volume cum 9 0.196 17.100 -30.16
Kerb cum 1 29.20 0.500 0.225 3.29
Total 240.37

14 HDPE Pipe
m 9 17.10 153.90
Total 153.90

15 HYSD Bars
@ 170 kg/cum of concrete volume t 40.86
Total 40.86

16 RCC M30 Railing rm 1 29.20 29.20


Total 29.20

17 Crash Barrier RCC M40


m 2 29.20 58.40
Total 58.40

18 Drainage Spout nos. 2 Total 2.00


QUANTITY CALCULATION OF BRIDGE AT CH._56.461 KM ON BILASIPURA-GUWAHATI STRETCH BHARATMALA
IN THE STATE OF ASSAM

CHAINAGE - 56.461 KM 1 no x 21.0 M RCC Integral Voided Slab

Length Height
Item No. Description Unit nos Breadth (m) Quantity
(m) (m)
19 PCC below Approach Slab
cum 2 12.230 3.370 0.150 12.36
Total 12.36

20 Approach Slab RCC M30


Approach Slab cum 2 12.080 3.500 0.300 25.37
Total 25.37

21 Bitumenous concrete Wearing Coat


cum 1 29.20 9.50 0.040 11.10
Total 11.10

22 Mastic asphalt
sqm 1 29.20 9.50 277.40
Total 277.40

23 Tack coat
sqm 1 29.20 9.50 277.40
Total 277.40

24 Cement concrete wearing course on footpath


cum 1 29.20 1.50 0.075 3.29
Total 3.29

25 Filler joint

Providing & fixing 2 mm thick corrugated


m 2 12.08 24.16
copper plate in expansion joint
Providing & fixing 20 mm thick
compressible fibre board in expansion m 2 12.08 24.16
joint
Providing and fixing in position 20 mm
m 2 12.08 24.16
thick premoulded joint filler

Providing and filling joint sealing


m 2 12.08 24.16
compound

26 Brick Work cum 2 2.98 0.125 2.153 1.60


Total 1.600
QUANTITY CALCULATION OF BRIDGE AT CH._56.461 KM ON BILASIPURA-GUWAHATI STRETCH BHARATMALA
IN THE STATE OF ASSAM

CHAINAGE - 56.461 KM 1 no x 21.0 M RCC Integral Voided Slab

Length Height
Item No. Description Unit nos Breadth (m) Quantity
(m) (m)
PROTECTION WORK

27 Pitching with Stone Blanket

A1 side cum 2 108.44 0.30 65.064

A2 side cum 2 121.84 0.30 73.104

In front of abutment cum 2 25.000 2.270 0.30 34.050

Total 172.218

28 Floor Protection(A-1 & A-2 side)

In front of abutment A1 & A2 cum 2 25.000 1.653 82.650

Abutment A1 & A2 (circular portion) cum 4 9.425 1.127 42.488

Abutment A1 & A2 (straight portion) cum 4 10.000 0.601 24.040

Total= 149.178

29 Filter Blanket below pitching


A1 side cum 2 108.44 0.15 32.532
A2 side cum 2 121.84 0.15 36.552
In front of abutment cum 2 25.000 2.270 0.15 17.025
Total= 86.109

MISCELLANEOUS
30 Paint for concrete surface
Kerb below railing sqm 1 0.950 29.20 27.74
Railing(Post) sqm 18 1.05 1.10 20.79
Railing(Beam) sqm 3 0.69 29.20 60.44
Crash Barrier sqm 2 2.079 29.20 121.41
Total 230.380
QUANTITY CALCULATION OF BRIDGE AT CH._56.985 KM ON BILASIPURA-GUWAHATI STRETCH BHARATMALA
IN THE STATE OF ASSAM

CHAINAGE - 56.985 KM 1 no x 24.0 M RCC Integral Voided Slab

Length Height
Item No. Description Unit nos Breadth (m) Quantity
(m) (m)

FOUNDATION
1 Excavation upto 3.0m depth
Abutment-1 cum 1 13.60 6.100 2.10 174.22
Abutment-2 cum 1 13.60 6.100 1.67 138.54
Return wall @ median (Abutment -A1) cum 1 2.50 1.300 0.12 0.39
Total 313.15

2 Bored Cast-in-situ Piles M-35 (Dia-1.2 m)


Abutment-1 metre 8 25.00 200.00
Abutment-2 metre 8 25.00 200.00
Total 400.00

3 Levelling Course for Pile Cap (PCC M-15)


Abutment-1 cum 1 12.900 5.400 0.15 10.45
Abutment-2 cum 1 12.900 5.400 0.15 10.45
Total 20.90

4 RCC M-30
Pile Cap (Abutment-1) cum 1 12.600 5.100 1.80 115.67
Pile Cap (Abutment-2) cum 1 12.600 5.100 1.80 115.67
Total 231.34

5 HYSD Bars
@ 90 kg/cum of cocrete volume for
Tonne 72.82
pile cap & @ 130Kg/m run pile
Total 72.82
QUANTITY CALCULATION OF BRIDGE AT CH._56.985 KM ON BILASIPURA-GUWAHATI STRETCH BHARATMALA
IN THE STATE OF ASSAM

CHAINAGE - 56.985 KM 1 no x 24.0 M RCC Integral Voided Slab

Length Height
Item No. Description Unit nos Breadth (m) Quantity
(m) (m)
SUBSTRUCTURE

6 RCC M-30 upto 5 m


Abutment-1 & 2 cum 2 12.500 1.350 2.757 93.05
Return Wall-I cum 2 1.875 0.400 3.988 5.98
Return Wall-I (Fin portion) cum 2 2.322 0.300 1.39
Return Wall (at median) cum 2 2.980 0.300 2.888 5.16
Bracket cum 2 12.100 0.180 4.36
Total 109.94

7 HYSD Bars

@ 120 kg/cum of cocrete volume t 13.19

Total 13.19

8 Weep holes
Spacing for weep holes = 2 m in horizontal and 1 m in vertical direction
No of weep holes in horizontal direction per abutment = 12.1/2+1 = 8
No of weep holes in vertical direction per abutment = 2.757/1+1 = 4
No of weep holes in horizontal direction per return wall I =(1.875)/2+1 = 2
No of weep holes in vertical direction per return wall I =(3.988-0.3-0.15)/1+1 = 5
No of weep holes in horizontal direction per return wall I fin portion =(1.645)/2+1
2
=

No of weep holes in vertical direction per return wall I fin portion =(1.4115)/1+1 = 3

No of weep holes in horizontal direction per return wall (at median) =(2.98)/2+1 = 3

No of weep holes in vertical direction per return wall (at median) =(2.888)/1+1 = 4

Total no of Weep holes per abutment = 8 x 4 32


Total no of Weep holes per return wall = 2 x 5 10
Total no of Weep holes per return wall fin portion= 2 x 3 6
Total no of Weep holes per return wall I (at median) = 3 x 4 12
Total no of weep holes = 32 x 2 + 6 x 2 + 10 x 2 + 12 x 2 Total 120.00
QUANTITY CALCULATION OF BRIDGE AT CH._56.985 KM ON BILASIPURA-GUWAHATI STRETCH BHARATMALA
IN THE STATE OF ASSAM

CHAINAGE - 56.985 KM 1 no x 24.0 M RCC Integral Voided Slab

Length Height
Item No. Description Unit nos Breadth (m) Quantity
(m) (m)
9 Backfilling - Granular Material

Abutment cum 2 18.70 1.950 72.93


Total 72.93

10 Backfilling - Sandy Material


Behind Abutment & Return wall cum 2 11.500 1.875 3.657 157.71
Behind Return wall I (at median) cum 2 3.000 1.875 3.657 41.14
Deduct for filter media cum -71.63
Total 127.22

11 Filter media
Behind Abutment cum 2 12.100 0.600 3.657 53.10
Behind Return wall-I cum 2 1.275 0.600 3.538 5.41
Return Wall-I (Fin portion) cum 2 2.322 0.600 2.79
Behind Return wall I (at median) cum 2 2.980 0.600 2.888 10.33
Total 71.63

SUPERSTRUCTURE

12 RCC M-30 - For Voided Slab Superstructure


At support cum 2 12.5 1.350 1.376 46.44
Varrying Portion cum 2 12.500 5.325 1.113 148.17
At mid span cum 1 12.000 10.453 125.44
Deduction for voids volume cum 9 0.196 19.650 -34.66
Kerb cum 1 32.35 0.500 0.225 3.64
Total 289.03

13 HDPE Pipe
m 9 19.65 176.85
Total 176.85

14 HYSD Bars
@ 170 kg/cum of concrete volume t 49.14
Total 49.14

15 RCC M30 Railing rm 1 32.35 32.35


Total 32.35

16 Crash Barrier RCC M40


m 2 32.35 64.70
Total 64.70
QUANTITY CALCULATION OF BRIDGE AT CH._56.985 KM ON BILASIPURA-GUWAHATI STRETCH BHARATMALA
IN THE STATE OF ASSAM

CHAINAGE - 56.985 KM 1 no x 24.0 M RCC Integral Voided Slab

Length Height
Item No. Description Unit nos Breadth (m) Quantity
(m) (m)

17 Drainage Spout nos. 2 Total 2.00

18 PCC below Approach Slab


cum 2 12.230 3.370 0.150 12.36
Total 12.36

19 Approach Slab RCC M30


Approach Slab cum 2 12.080 3.500 0.300 25.37
Total 25.37

20 Bitumenous concrete Wearing Coat


cum 1 32.35 9.50 0.040 12.29
Total 12.29

21 Mastic asphalt
sqm 1 32.35 9.50 307.33
Total 307.33

22 Tack coat
sqm 1 32.35 9.50 307.33
Total 307.33

23 Cement concrete wearing course on footpath


cum 1 32.35 1.50 0.075 3.64
Total 3.64

24 Filler joint

Providing & fixing 2 mm thick corrugated


m 2 12.08 24.16
copper plate in expansion joint
Providing & fixing 20 mm thick
compressible fibre board in expansion m 2 12.08 24.16
joint
Providing and fixing in position 20 mm
m 2 12.08 24.16
thick premoulded joint filler

Providing and filling joint sealing


m 2 12.08 24.16
compound

25 Brick Work cum 2 2.98 0.125 2.303 1.72


Total 1.720
QUANTITY CALCULATION OF BRIDGE AT CH._56.985 KM ON BILASIPURA-GUWAHATI STRETCH BHARATMALA
IN THE STATE OF ASSAM

CHAINAGE - 56.985 KM 1 no x 24.0 M RCC Integral Voided Slab

Length Height
Item No. Description Unit nos Breadth (m) Quantity
(m) (m)

PROTECTION WORK

26 Pitching with Stone Blanket

A1 side cum 2 182.29 0.30 109.374

A2 side cum 2 204.36 0.30 122.616

In front of abutment cum 2 24.200 2.766 0.30 40.162

Total 272.152

27 Floor Protection(A-1 & A-2 side)

In front of abutment A1 & A2 cum 2 24.200 1.653 80.005

Abutment A1 & A2 (circular portion) cum 4 14.137 1.127 63.730

Abutment A1 & A2 (straight portion) cum 4 10.000 0.601 24.040

Total= 167.775

28 Filter Blanket below pitching


A1 side cum 2 182.29 0.15 54.687
A2 side cum 2 204.36 0.15 61.308
In front of abutment cum 2 24.200 2.766 0.15 20.081
Total= 136.076

MISCELLANEOUS
29 Paint for concrete surface
Kerb below railing sqm 1 0.950 32.35 30.73
Railing(Post) sqm 19 1.05 1.10 21.95
Railing(Beam) sqm 3 0.69 32.35 66.96
Crash Barrier sqm 2 2.079 32.35 134.51
Total 254.150
QUANTITY CALCULATION OF BRIDGE AT CH._60.315 KM ON BILASIPURA-GUWAHATI STRETCH BHARATMALA IN
THE STATE OF ASSAM

3 No. X 18 M SPAN CH._60.315 KM


Length Height
Item Sl No. Description Unit nos. Breadth (m) Quantity
(m) (m)

FOUNDATION
1.1 Excavation upto 3m depth
Abutment-1 cum 2 13.60 9.70 3.00 791.52
Pier-1 cum 2 9.70 6.10 2.21 261.53
Pier-2 cum 2 9.70 6.10 2.28 269.82
Abutment-2 cum 2 13.60 9.70 3.00 791.52
Return wall-I at Abutment-1 (at median) cum 1 2.00 1.30 1.14 2.96
Return wall-I at Abutment-2 (at median) cum 1 2.00 1.30 1.39 3.61
Total 2120.960

1.2 Excavation 3.0m to 6.0m depth


Abutment-1 cum 2 13.60 9.70 0.119 31.40
Abutment-2 cum 2 13.60 9.70 0.360 94.98
Total 126.38

2 Pile cap RCC M30


Abutment cum 4 12.60 8.700 1.80 789.26
Pier cum 4 8.70 5.100 1.80 319.46
Total= 1108.720

3 Bored Cast-in-situ Pile M35 (dia.=1.2m)


Abutment-1 m 24 20.000 480.00
Pier-1 m 12 22.000 264.00
Pier-2 m 12 22.000 264.00
Abutment-2 m 24 20.000 480.00
Total= 1488.000

4 PCC M-15 levelling course


Below Pile-cap for Abutment cum 4 12.90 9.00 0.15 69.66
Below Pile-cap for Pier cum 4 9.00 5.40 0.15 29.16
Below brick wall at median cum 2 2.98 0.90 0.10 0.54
Total= 99.360

5 HYSD Bars
90kg/cum for pile cap & @ 130kg/m for
T Total= 293.225
pile

6 Brick Flat Soling (BFS) below brick wall at median


cum 2 2.98 0.90 0.075 0.40
Total= 0.40
SUBSTRUCTURE
7 RCC M-30 upto 5.0m height
Abutment wall cum 4 12.50 1.200 2.850 171.00
Abutment cap cum 4 12.50 1.790 1.000 89.50
Pier shaft cum portion)
(circular 4 3.14 5.000 62.80
Dirt Wall cum 4 12.50 0.400 1.150 23.00
Bracket cum 4 12.10 0.045 2.18
Return Wall-I upto abutment cap cum 4 3.75 0.400 2.825 16.95
Return Wall-I above abutment cap cum 4 3.16 0.400 2.175 11.00
Return wall at median cum 2 2.980 0.300 3.825 6.84
Return wall extra finch triangular portion cum 4 0.30 1.080 1.30
Total= 384.570
QUANTITY CALCULATION OF BRIDGE AT CH._60.315 KM ON BILASIPURA-GUWAHATI STRETCH BHARATMALA IN
THE STATE OF ASSAM

3 No. X 18 M SPAN CH._60.315 KM


Length Height
Item Sl No. Description Unit nos. Breadth (m) Quantity
(m) (m)
8 RCC M-30 height above 5.0m upto 10.0m
Pier shaft cum portion)
(circular 4 3.14 0.800 10.05
Pier cap(Trapizoidal portion) cum 4 7.25 2.700 0.700 54.81
Pier cap(Rectangular portion) cum 4 11.50 2.700 0.700 86.94
Dirt Wall cum 4 12.50 0.400 0.969 19.38
Bracket cum 4 12.10 0.135 6.53
Return Wall-I above abutment cap cum 4 3.16 0.400 0.826 4.18
Return wall extra fin rectangular portion cum 4 0.30 1.800 1.000 2.16
Total= 184.050

9 RCC M-35 for Pedestal & Seismic Arrestor Blocks height upto 5.0m
cum 6 0.80 0.800 0.150 0.58
cum 6 0.80 0.800 0.215 0.83
Pedestal at POT cum PTFE bearing
cum 6 0.80 0.800 0.288 1.11
cum 6 0.80 0.800 0.361 1.39
cum 6 0.80 0.800 0.150 0.58
cum 6 0.80 0.800 0.215 0.83
Pedestal at POT bearing
cum 6 0.80 0.800 0.288 1.11
cum 6 0.80 0.800 0.361 1.39
Total= 7.820

Block RB2 cum 16 0.340 0.700 1.060 4.04


Block RB1 cum 12 0.800 0.889 8.53
Block RB1 (a) cum 12 0.800 1.069 10.26
Block RB3 cum 16 0.640 0.700 1.060 7.17
Total= 37.820

10 HYSD Bars
@ 120 kg/cum T 72.773
Total= 72.773

11 Weep holes
Spacing for weep holes = 2 m in horizontal and 1 m in vertical direction
No of weep holes in horizontal direction per abutment = 12.1/2+1 = 8
No of weep holes in vertical direction per abutment = 2.85+1 = 4
No of weep holes in horizontal direction per return wall = (3.75)/2+1 = 3
No of weep holes in vertical direction per return wall = (5.826)/1+1 = 7
No of weep holes in horizontal direction per return wall at median= (2.98)/2+1 = 3
No of weep holes in vertical direction per return wall at median = (3.825)/1+1 = 5
No of weep holes in horizontal direction per return wall extra fin= (1.8)/2+1 = 2
No of weep holes in vertical direction per return wall extra fin = (1.6)/1+1 = 3
Total no of Weep holes per abutment = 8 x 4 32
Total no of Weep holes per return wall = 3 x 7 21
Total no of Weep holes per return wall at median= 3 x 5 15
Total no of Weep holes per return wall extra fin= 2 x 3 6
Total no of weep holes = 32 x 4 + 21 x 4 + 15 x 2 + 6 x 4 Total 266.000

12 Backfilling - Granular Material


Abutment cum 4 22.30 1.950 173.94
Pier cum 4 14.80 1.950 115.44
Total 289.380

13 Backfilling - Sandy Material


Behind Abutment & Return wall-I cum 4 11.50 3.15 5.519 799.70
Behind Return wall at median cum 2 3.00 5.010 6.088 183.01
Deduct for filter media cum -217.70
Deduct for brick wall at median cum -6.470
Total 758.540
QUANTITY CALCULATION OF BRIDGE AT CH._60.315 KM ON BILASIPURA-GUWAHATI STRETCH BHARATMALA IN
THE STATE OF ASSAM

3 No. X 18 M SPAN CH._60.315 KM


Length Height
Item Sl No. Description Unit nos. Breadth (m) Quantity
(m) (m)

14 Filter media
Behind Abutment cum 4 12.100 0.60 5.519 160.27
Behind Return wall-I cum 4 2.855 0.60 5.376 36.84
Behind return wall-I extra fin portion cum 4 2.880 0.600 6.91
Behind Return wall at median cum 2 2.980 0.60 3.825 13.68
Total 217.700

15 POT cum PTFE Bearing


ton 48 250.00 12000.00
Total 12000.000

16 Elastomeric Bearing
Bearing B2 cucm 24 35.00 42.50 4.80 171360
Bearing B3 cucm 48 25.00 30.00 3.90 140400
Total 311760.000
SUPERSTRUCTURE

17 RCC M-30
For T-Girder & Slab
Long Girder middle straight portion With
cum 6 14.260 5.607 479.73
Deck slab
Long Girder end straight portion with
Deck slab cum 12 1.000 6.812 81.74
Long Girder end varying portion With
Deck slab cum 12 1.200 6.210 89.42
Cantilever portion of Deck Slab cum 12 0.420 12.500 0.350 22.05
End Cross Girder cum 12 0.300 7.140 25.70
IntermediateCross Girder cum 6 0.300 7.980 14.36
Kerb cum 2 66.340 0.500 0.225 14.93
Total 727.930

18 HYSD Bars
@ 180 kg/cum T 131.027
Total= 131.027

19 RCC M30 Railing


m 2 66.34 132.68
Total= 132.680

20 RCC M40 Crash Barrier


m 4 66.34 265.36
Total= 265.360

21 Drainage Spout nos. 20 Total 20.000

22 M15 PCC below Approach Slab


cum 4 3.370 12.230 0.15 24.73
Total 24.730

23 Approach Slab(M30)
Approach Slab cum 4 3.500 12.080 0.300 50.74
Total 50.740

24 Bituminous concrete wearing course


cum 2 66.34 9.50 0.040 50.42
Total= 50.420
QUANTITY CALCULATION OF BRIDGE AT CH._60.315 KM ON BILASIPURA-GUWAHATI STRETCH BHARATMALA IN
THE STATE OF ASSAM

3 No. X 18 M SPAN CH._60.315 KM


Length Height
Item Sl No. Description Unit nos. Breadth (m) Quantity
(m) (m)

25 Mastic asphalt
sqm 2 66.34 9.50 1260.46
Total= 1260.460

26 Tack coat
sqm 2 66.34 9.50 1260.46
Total= 1260.460

27 Cement Concrete wearing coarse(75mm)


cum 2 66.34 1.50 0.075 14.93
Total= 14.930

28 Filler joint
Providing & fixing 2 mm thick corrugated
m 4 12.08 48.32
copper plate in expansion joint
Providing & fixing 20 mm thick
compressible fibre board in expansion m 4 12.08 48.32
joint
Providing and fixing in position 20 mm
m 4 12.08 48.32
thick premoulded joint filler
Providing and filling joint sealing
m 4 12.08 48.32
compound

29 Strip Seal Expansion Joint


m 4 12.500 50.00
Total 50.000

30 Brick work at median

Above abutment cap level cum 2 2.980 0.250 2.238 3.33

Below abutment cap level cum 2 2.980 0.369 2.20


Total 5.530
QUANTITY CALCULATION OF BRIDGE AT CH._60.315 KM ON BILASIPURA-GUWAHATI STRETCH BHARATMALA IN
THE STATE OF ASSAM

3 No. X 18 M SPAN CH._60.315 KM


Length Height
Item Sl No. Description Unit nos. Breadth (m) Quantity
(m) (m)
PROTECTION WORK
31 Pitching with Stone Blanket
Pitching with Stone Blanket (A1 side) cum 2 180.69 0.30 108.414
Pitching with Stone Blanket (A2 side) cum 2 168.35 0.30 101.010
In front of abutment cum 2 28.00 0.395 0.30 6.636
Total 216.060

32 Floor Protection
Abutment (straight portion) cum 4 10.00 0.601 24.040
Abutment A1 (curve portion) cum 2 13.72 1.127 30.925
Abutment A2 (curve portion) cum 2 13.03 1.127 29.370
In front of abutment cum 2 28.00 1.653 92.568
Total 176.903

33 Filter Blanket below pitching


A1 side cum 2 180.69 0.15 54.207
A2 side cum 2 168.35 0.15 50.505
In front of abutment cum 2 28.00 0.395 0.15 3.318
Total= 108.030

MISCELLANEOUS
34 Painting
Kerb below railing sqm 2 0.950 66.34 126.05
Railing(Post) sqm 78 0.90 1.10 77.22
Railing(Beam) sqm 6 0.54 66.34 214.94
Crash Barrier sqm 4 2.080 66.34 551.95
Total 970.160

35 Citizen information Board NH Project no Total 2.000


QUANTITY CALCULATION OF BRIDGE AT CH._60.930 KM ON BILASIPURA-GUWAHATI STRETCH BHARATMALA
LOT-I PKG-IA IN THE STATE OF ASSAM

3 No. X 18 M SPAN CH._60.930 KM


Length Height
Item Sl No. Description Unit nos. Breadth (m) Quantity
(m) (m)

FOUNDATION
1.1 Excavation upto 3m depth
Abutment-1 cum 2 13.60 9.70 3.00 791.52
Pier-1 cum 2 9.70 6.10 2.63 311.23
Pier-2 cum 2 9.70 6.10 3.00 355.02
Abutment-2 cum 2 13.60 9.70 3.00 791.52
Return wall-I at Abutment-1 (at median) cum 1 2.00 1.30 1.42 3.69
Return wall-I at Abutment-2 (at median) cum 1 2.00 1.30 1.78 4.63
Total 2257.610

1.2 Excavation 3.0m to 6.0m depth


Abutment-1 cum 2 13.60 9.70 0.391 103.16
Pier-2 cum 2 9.70 6.10 0.076 8.99
Abutment-2 cum 2 13.60 9.70 0.750 197.88
Total 310.03

2 Pile cap RCC M30


Abutment cum 4 12.60 8.700 1.80 789.26
Pier cum 4 8.70 5.100 1.80 319.46
Total= 1108.720

3 Bored Cast-in-situ Pile M35 (dia.=1.2m)


Abutment-1 m 24 20.000 480.00
Pier-1 m 12 22.000 264.00
Pier-2 m 12 22.000 264.00
Abutment-2 m 24 20.000 480.00
Total= 1488.000

4 PCC M-15 levelling course


Below Pile-cap for Abutment cum 4 12.90 9.00 0.15 69.66
Below Pile-cap for Pier cum 4 9.00 5.40 0.15 29.16
Below brick wall at median cum 2 2.98 0.90 0.10 0.54
Total= 99.360

5 HYSD Bars
90kg/cum for pile cap & @ 130kg/m for
T Total= 293.225
pile

6 Brick Flat Soling (BFS) below brick wall at median


cum 2 2.98 0.90 0.075 0.40
Total= 0.40
SUBSTRUCTURE
7 RCC M-30 upto 5.0m height
Abutment wall cum 4 12.50 1.200 2.900 174.00
Abutment cap cum 4 12.50 1.790 1.000 89.50
Pier shaft cum portion)
(circular 4 3.14 5.000 62.80
Dirt Wall cum 4 12.50 0.400 1.100 22.00
Return Wall-I upto abutment cap cum 4 3.75 0.400 2.875 17.25
Return Wall-I above abutment cap cum 4 3.16 0.400 2.125 10.74
Return wall at median cum 2 2.980 0.300 3.875 6.93
Return wall extra finch triangular portion cum 4 0.30 1.080 1.30
Total= 384.520
QUANTITY CALCULATION OF BRIDGE AT CH._60.930 KM ON BILASIPURA-GUWAHATI STRETCH BHARATMALA
LOT-I PKG-IA IN THE STATE OF ASSAM

3 No. X 18 M SPAN CH._60.930 KM


Length Height
Item Sl No. Description Unit nos. Breadth (m) Quantity
(m) (m)
8 RCC M-30 height above 5.0m upto 10.0m
Pier cap(Trapizoidal portion) cum 4 7.25 2.700 0.700 54.81
Pier cap(Rectangular portion) cum 4 11.50 2.700 0.700 86.94
Dirt Wall cum 4 12.50 0.400 1.019 20.38
Bracket cum 4 12.10 0.180 8.71
Return Wall-I above abutment cap cum 4 3.16 0.400 0.876 4.43
Return wall extra fin rectangular portion cum 4 0.30 1.800 1.000 2.16
Total= 177.430

9 RCC M-35 for Pedestal & Seismic Arrestor Blocks height upto 5.0m
cum 6 0.80 0.800 0.150 0.58
cum 6 0.80 0.800 0.215 0.83
Pedestal at POT cum PTFE bearing
cum 6 0.80 0.800 0.288 1.11
cum 6 0.80 0.800 0.361 1.39
cum 6 0.80 0.800 0.150 0.58
cum 6 0.80 0.800 0.215 0.83
Pedestal at POT bearing
cum 6 0.80 0.800 0.288 1.11
cum 6 0.80 0.800 0.361 1.39
Total= 7.820

Block RB2 cum 16 0.340 0.700 1.060 4.04


Block RB1 cum 12 0.800 0.889 8.53
Block RB1 (a) cum 12 0.800 1.069 10.26
Block RB3 cum 16 0.640 0.700 1.060 7.17
Total= 37.820

10 HYSD Bars
@ 120 kg/cum T 71.972
Total= 71.972

11 Weep holes
Spacing for weep holes = 2 m in horizontal and 1 m in vertical direction
No of weep holes in horizontal direction per abutment = 12.1/2+1 = 8
No of weep holes in vertical direction per abutment = 2.9+1 = 4
No of weep holes in horizontal direction per return wall = (3.75)/2+1 = 3
No of weep holes in vertical direction per return wall = (5.876)/1+1 = 7
No of weep holes in horizontal direction per return wall at median= (2.98)/2+1 = 3
No of weep holes in vertical direction per return wall at median = (3.875)/1+1 = 5
No of weep holes in horizontal direction per return wall extra fin= (1.8)/2+1 = 2
No of weep holes in vertical direction per return wall extra fin = (1.6)/1+1 = 3
Total no of Weep holes per abutment = 8 x 4 32
Total no of Weep holes per return wall = 3 x 7 21
Total no of Weep holes per return wall at median= 3 x 5 15
Total no of Weep holes per return wall extra fin= 2 x 3 6
Total no of weep holes = 32 x 4 + 21 x 4 + 15 x 2 + 6 x 4 Total 266.000

12 Backfilling - Granular Material


Abutment cum 4 22.30 1.950 173.94
Pier cum 4 14.80 1.950 115.44
Total 289.380

13 Backfilling - Sandy Material


Behind Abutment & Return wall-I cum 4 11.50 3.15 5.569 806.95
Behind Return wall at median cum 2 3.00 5.010 6.138 184.51
Deduct for filter media cum -219.67
Deduct for brick wall at median cum -6.470
Total 765.320
QUANTITY CALCULATION OF BRIDGE AT CH._60.930 KM ON BILASIPURA-GUWAHATI STRETCH BHARATMALA
LOT-I PKG-IA IN THE STATE OF ASSAM

3 No. X 18 M SPAN CH._60.930 KM


Length Height
Item Sl No. Description Unit nos. Breadth (m) Quantity
(m) (m)
14 Filter media
Behind Abutment cum 4 12.100 0.60 5.569 161.72
Behind Return wall-I cum 4 2.855 0.60 5.426 37.18
Behind return wall-I extra fin portion cum 4 2.880 0.600 6.91
Behind Return wall at median cum 2 2.980 0.60 3.875 13.86
Total 219.670

15 POT cum PTFE Bearing


ton 48 250.00 12000.00
Total 12000.000

16 Elastomeric Bearing
Bearing B2 cucm 24 35.00 42.50 4.80 171360
Bearing B3 cucm 48 25.00 30.00 3.90 140400
Total 311760.000
SUPERSTRUCTURE

17 RCC M-30
For T-Girder & Slab
Long Girder middle straight portion With
cum 6 14.260 5.607 479.73
Deck slab
Long Girder end straight portion with
Deck slab cum 12 1.000 6.812 81.74
Long Girder end varying portion With
Deck slab cum 12 1.200 6.210 89.42
Cantilever portion of Deck Slab cum 12 0.420 12.500 0.350 22.05
End Cross Girder cum 12 0.300 7.140 25.70
IntermediateCross Girder cum 6 0.300 7.980 14.36
Kerb cum 2 66.340 0.500 0.225 14.93
Total 727.930

18 HYSD Bars
@ 180 kg/cum T 131.027
Total= 131.027

19 RCC M30 Railing


m 2 66.34 132.68
Total= 132.680

20 RCC M40 Crash Barrier


m 4 66.34 265.36
Total= 265.360

21 Drainage Spout nos. 20 Total 20.000

22 M15 PCC below Approach Slab


cum 4 3.370 12.230 0.15 24.73
Total 24.730

23 Approach Slab(M30)
Approach Slab cum 4 3.500 12.080 0.300 50.74
Total 50.740

24 Bituminous concrete wearing course


cum 2 66.34 9.50 0.040 50.42
Total= 50.420
QUANTITY CALCULATION OF BRIDGE AT CH._60.930 KM ON BILASIPURA-GUWAHATI STRETCH BHARATMALA
LOT-I PKG-IA IN THE STATE OF ASSAM

3 No. X 18 M SPAN CH._60.930 KM


Length Height
Item Sl No. Description Unit nos. Breadth (m) Quantity
(m) (m)
25 Mastic asphalt
sqm 2 66.34 9.50 1260.46
Total= 1260.460

26 Tack coat
sqm 2 66.34 9.50 1260.46
Total= 1260.460

27 Cement Concrete wearing coarse(75mm)


cum 2 66.34 1.50 0.075 14.93
Total= 14.930

28 Filler joint
Providing & fixing 2 mm thick corrugated
m 4 12.08 48.32
copper plate in expansion joint
Providing & fixing 20 mm thick
compressible fibre board in expansion m 4 12.08 48.32
joint
Providing and fixing in position 20 mm
m 4 12.08 48.32
thick premoulded joint filler
Providing and filling joint sealing
m 4 12.08 48.32
compound

29 Strip Seal Expansion Joint


m 4 12.500 50.00
Total 50.000

30 Brick work at median

Above abutment cap level cum 2 2.980 0.250 2.238 3.33

Below abutment cap level cum 2 2.980 0.369 2.20


Total 5.530
QUANTITY CALCULATION OF BRIDGE AT CH._60.930 KM ON BILASIPURA-GUWAHATI STRETCH BHARATMALA
LOT-I PKG-IA IN THE STATE OF ASSAM

3 No. X 18 M SPAN CH._60.930 KM


Length Height
Item Sl No. Description Unit nos. Breadth (m) Quantity
(m) (m)
PROTECTION WORK
31 Pitching with Stone Blanket
Pitching with Stone Blanket (A1 side) cum 2 169.81 0.30 101.886
Pitching with Stone Blanket (A2 side) cum 2 152.59 0.30 91.554
In front of abutment cum 2 28.00 0.395 0.30 6.636
Total 200.076

32 Floor Protection
Abutment (straight portion) cum 4 10.00 0.601 24.040
Abutment A1 (curve portion) cum 2 13.11 1.127 29.550
Abutment A2 (curve portion) cum 2 12.12 1.127 27.318
In front of abutment cum 2 28.00 1.653 92.568
Total 173.476

33 Filter Blanket below pitching


A1 side cum 2 169.81 0.15 50.943
A2 side cum 2 152.59 0.15 45.777
In front of abutment cum 2 28.00 0.395 0.15 3.318
Total= 100.038

MISCELLANEOUS
34 Painting
Kerb below railing sqm 2 0.950 66.34 126.05
Railing(Post) sqm 78 0.90 1.10 77.22
Railing(Beam) sqm 6 0.54 66.34 214.94
Crash Barrier sqm 4 2.080 66.34 551.95
Total 970.160

35 Citizen information Board NH Project no Total 2.000


QUANTITY CALCULATION OF BRIDGE AT CH._64.159 KM ON BILASIPURA-GUWAHATI STRETCH BHARATMALA
LOT-I PKG-IA IN THE STATE OF ASSAM

1 No. X 40 M SPAN CH._64.159 KM


Length
Item Sl No. Description Unit nos. Breadth (m) Height (m) Quantity
(m)

FOUNDATION
1.1 Excavation upto 3m depth
Abutment-1 cum 2 13.60 9.70 3.00 791.52
Abutment-2 cum 2 13.60 9.70 1.36 358.82
Return wall-I at Abutment-1(median side) cum 1 3.00 1.30 2.18 8.50

Return wall-I at Abutment-2(median side) cum 1 3.00 1.30 0.12 0.47


Total 1159.31

1.2 Excavation 3.0m to 6.0m depth


Abutment-1 cum 2 13.60 9.70 1.130 298.14
Total 298.14

2 Pile cap RCC M30


Abutment cum 4 12.60 8.700 1.80 789.26
Total= 789.26

3 Bored Cast-in-situ Pile M35 (dia.=1.2m)


Abutment-1 m 24 30.000 720.00
Abutment-2 m 24 30.000 720.00
Total= 1440.00

4 PCC M-15 levelling course


Below Pile-cap for Abutment cum 4 12.90 9.00 0.15 69.66
Below brick wall at median cum 4 1.49 0.90 0.10 0.54
Total= 70.20

5 HYSD Bars
90kg/cum for pile cap & @ 125kg/m for
T Total= 251.033
pile

6 Brick Flat Soling (BFS) below brick wall at median


cum 4 1.49 0.90 0.075 0.40
Total= 0.40

SUBSTRUCTURE
7 RCC M-30 upto 5.0m height
Abutment wall cum 4 12.50 1.200 3.900 234.00
Abutment cap cum 4 12.50 2.120 1.000 106.00
Dirt Wall cum 4 12.50 0.400 0.100 2.00
Return Wall-I upto abutment cap cum 4 3.75 0.450 3.876 26.16
Return Wall-I above abutment cap cum 4 2.83 0.450 1.124 5.73

Return Wall-I(median ) cum 4 1.49 0.300 4.875 8.72

Total= 382.61

8 RCC M-30 height above 5.0m upto 10.0m


Dirt Wall cum 4 12.50 0.400 3.093 61.86
Bracket cum 4 12.50 0.180 9.00
Return Wall-I above abutment cap cum 4 2.83 0.450 2.950 15.03
Return Wall-I(median ) cum 4 1.49 0.300 0.025 0.04
Return wall extra fins rectangular portion cum 4 0.30 1.700 1.000 2.04
Return wall extra fins triangular portion cum 4 0.30 0.963 1.16

Total= 89.130
QUANTITY CALCULATION OF BRIDGE AT CH._64.159 KM ON BILASIPURA-GUWAHATI STRETCH BHARATMALA
LOT-I PKG-IA IN THE STATE OF ASSAM

1 No. X 40 M SPAN CH._64.159 KM


Length
Item Sl No. Description Unit nos. Breadth (m) Height (m) Quantity
(m)

9 RCC M-35 for Pedestal & Seismic Arrestor Blocks height upto 5.0m
cum 4 0.80 0.80 0.150 0.38
cum 4 0.80 0.80 0.213 0.55
Pedestal at Abutment
cum 4 0.80 0.80 0.288 0.74
cum 4 0.80 0.80 0.363 0.93
Total= 2.60
Block RB2 cum 16 0.740 0.530 1.400 8.79
Block RB1 cum 8 0.800 1.299 8.31
Total= 19.70

10 HYSD Bars
@ 120 kg/cum T 58.973
Total= 58.973

11 Weep holes
Spacing for weep holes = 2 m in horizontal and 1 m in vertical direction
No of weep holes in horizontal direction per abutment = 12.05/2+1 = 8
No of weep holes in vertical direction per abutment = 3.9/1+1 = 5
No of weep holes in horizontal direction per return wall = (3.75)/2+1 = 3
No of weep holes in vertical direction per return wall = (7.95-0.3-0.15)/1+1 = 9
No of weep holes in horizontal direction per return wall fins= (1.7)/2+1 = 2
No of weep holes in vertical direction per return wall fins = (1.5665)/1+1 = 3
No of weep holes in horizontal direction per return wall at median= (1.49)/2+1 = 2
No of weep holes in vertical direction per return wall at median= (4.9)/1+1 = 6
Total no of Weep holes per abutment = 8 x 5 40
Total no of Weep holes per return wall = 3 x 9 27
Total no of Weep holes per return wall fins = 3 x 2 6
Total no of Weep holes per return wall at median = 2 x 6 12
Total no of weep holes = 40 x 4 + 27 x 4 + 6 x 4 + 12 x 4 Total 340.00

12.1 Backfilling - Granular Material


Behind Abutment cum 4 22.30 1.950 173.94
Total 173.94

12.2 Backfilling - Sandy Material


Behind Abutment & Return wall-I cum 4 13.55 3.75 7.500 1524.38
Deduct for filter media cum -300.60
Deduct for brick wall at median cum -0.940
Total 1222.84

13 Filter media
Behind Abutment cum 4 13.550 0.60 7.500 243.90
Behind Return wall-I cum 4 3.150 0.60 7.500 56.70
Total 300.60

14 POT & POT cum PTFE Bearing


ton 16 300.00 4800.00
Total 4800.00

15 Elastomeric Bearing
Bearing B2 cucm 8 35.00 42.50 4.80 57120
Bearing B3 cucm 16 25.00 30.00 3.90 46800
Total 103920
QUANTITY CALCULATION OF BRIDGE AT CH._64.159 KM ON BILASIPURA-GUWAHATI STRETCH BHARATMALA
LOT-I PKG-IA IN THE STATE OF ASSAM

1 No. X 40 M SPAN CH._64.159 KM


Length
Item Sl No. Description Unit nos. Breadth (m) Height (m) Quantity
(m)
SUPERSTRUCTURE

16 PSC M-45 Girder portion


Long Girder middle portion cum 2 31.600 4.704 297.29

Long Girder straight portion cum 4 1.950 8.992 70.14

Long Girder varying portion cum 4 1.600 6.848 43.83

End Cross Girder (portion in between the


cum 4 0.400 14.595 23.35
long girder)

End Cross Girder (rectangular part) cum 4 0.400 0.840 1.34


Intermediate Cross Girder (portion in
cum 6 0.300 17.889 32.20
between the long girder)
Intermediate Cross Girder (Trapezoidal
cum 6 0.300 1.488 2.68
part)
Total 470.83

17 R.C.C. Deck slab (M45)


Deck Slab cum 2 38.20 12.50 0.225 214.88
Cantilever portion of Deck Slab cum 4 0.880 12.50 0.300 13.20
Total 228.08

18 Kerb(M30)
cum 2 47.80 0.50 0.225 10.76
Total 10.76

19 PSC Steel
@14.5ton/span TON 2 14.50 29.00
Total 29.00

20 Superstructure Steel (HYSD Bars)


@ 150 kg/cum TON 106.451
Total= 106.451

21 RCC M30 Railing


m 2 47.80 95.60
Total= 95.60

22 RCC M40 Crash Barrier


m 4 47.80 191.20
Total= 191.20

23 Drainage Spout nos. 12 Total 12.00

24 M15 PCC below Approach Slab


cum 4 3.370 12.030 0.15 24.32
Total 24.32

25 Approach Slab(M30)
Approach Slab cum 4 3.500 12.030 0.300 50.53
Total 50.53

26 Bituminous concrete wearing course


cum 2 47.80 9.50 0.040 36.33
Total= 36.33
QUANTITY CALCULATION OF BRIDGE AT CH._64.159 KM ON BILASIPURA-GUWAHATI STRETCH BHARATMALA
LOT-I PKG-IA IN THE STATE OF ASSAM

1 No. X 40 M SPAN CH._64.159 KM


Length
Item Sl No. Description Unit nos. Breadth (m) Height (m) Quantity
(m)
27 Mastic asphalt
sqm 2 47.80 9.50 908.20
Total= 908.20

28 Tack coat
sqm 2 47.80 9.50 908.20
Total= 908.20

29 Cement Concrete wearing coarse(75mm)


cum 2 47.80 1.50 0.075 10.76
Total= 10.76

30 Filler joint
Providing & fixing 2 mm thick corrugated
m 4 11.90 47.60
copper plate in expansion joint
Providing & fixing 20 mm thick
compressible fibre board in expansion m 4 11.90 47.60
joint
Providing and fixing in position 20 mm
m 4 11.90 47.60
thick premoulded joint filler
Providing and filling joint sealing
m 4 11.90 47.60
compound

31 Strip Seal Expansion Joint


m 4 11.900 47.60
Total 47.60

32 Brick work at median

Above abutment cap level cum 4 1.490 0.250 3.312 4.93

Below abutment cap level cum 4 1.49 0.369 2.20


Total 7.130
QUANTITY CALCULATION OF BRIDGE AT CH._64.159 KM ON BILASIPURA-GUWAHATI STRETCH BHARATMALA
LOT-I PKG-IA IN THE STATE OF ASSAM

1 No. X 40 M SPAN CH._64.159 KM


Length
Item Sl No. Description Unit nos. Breadth (m) Height (m) Quantity
(m)
PROTECTION WORK

33 Pitching with Stone Blanket (A1 side) cum 2 345.79 0.30 207.474
Pitching with Stone Blanket (A2 side) cum 2 571.21 0.30 342.726
Total 550.20

34 Toe Wall
A1 side cum 2 0.610 34.54 42.139
A2 side cum 2 0.610 66.51 81.142
Total 123.28

35 Floor Protection
A1 side cum 2 16.74 0.526 17.610
A1 side (Infront of abutment) cum 2 14.10 1.052 29.666
A2 side cum 2 24.36 0.526 25.627
A2 side (Infront of abutment) cum 2 14.10 1.052 29.666
Total 102.57

36 Filter material below stone pitching


A1 side cum 2 345.79 0.15 103.737
A2 side cum 2 571.21 0.15 171.363
Total= 275.10

MISCELLANEOUS
37 Painting
Kerb below railing sqm 2 0.950 47.80 90.82
Railing(Post) sqm 56 1.05 1.10 64.68
Railing(Beam) sqm 6 0.69 47.80 197.89
Crash Barrier sqm 4 2.261 47.80 432.30
Total 785.690

38 Citizen information Board NH Project no Total 2.000


QUANTITY CALCULATION OF BRIDGE AT CH._67.046 KM ON BILASIPURA-GUWAHATI STRETCH BHARATMALA
LOT-I PKG-IA IN THE STATE OF ASSAM

3 No. X 18 M SPAN CH._67.046 KM


Length Height
Item Sl No. Description Unit nos. Breadth (m) Quantity
(m) (m)

FOUNDATION
1.1 Excavation upto 3m depth
Abutment-1 cum 2 13.60 9.70 1.79 472.27
Pier-1 cum 2 9.70 6.10 1.98 234.31
Pier-2 cum 2 9.70 6.10 3.00 355.02
Abutment-2 cum 2 13.60 9.70 2.71 715.01
Return wall-I at Abutment-2 (at median) cum 1 2.00 1.30 0.73 1.90
Total 1778.510

1.2 Excavation 3.0m to 6.0m depth


Pier-2 cum 2 9.70 6.10 1.340 158.58
Total 158.580

2 Pile cap RCC M30


Abutment cum 4 12.60 8.700 1.80 789.26
Pier cum 4 8.70 5.100 1.80 319.46
Total= 1108.720

3 Bored Cast-in-situ Pile M35 (dia.=1.2m)


Abutment-1 m 24 27.000 648.00
Pier-1 m 12 27.000 324.00
Pier-2 m 12 27.000 324.00
Abutment-2 m 24 27.000 648.00
Total= 1944.000

4 PCC M-15 levelling course


Below Pile-cap for Abutment cum 4 12.90 9.00 0.15 69.66
Below Pile-cap for Pier cum 4 9.00 5.40 0.15 29.16
Below brick wall at median cum 2 2.98 0.90 0.10 0.54
Total= 99.360

5 HYSD Bars
90kg/cum for pile cap & @ 130kg/m for
T Total= 352.505
pile

6 Brick Flat Soling (BFS) below brick wall at median


cum 2 2.98 0.90 0.075 0.40
Total= 0.40
SUBSTRUCTURE
7 RCC M-30 upto 5.0m height
Abutment wall cum 4 12.50 1.200 5.000 300.00
Pier shaft cum portion)
(circular 4 3.80 5.000 76.00
Return Wall-I upto abutment cap cum 2 3.75 0.550 5.000 20.63
Return Wall-I(another side) upto
cum 2 3.75 0.550 5.000 20.63
abutment cap
Return wall at median cum 2 2.980 0.300 5.000 8.94
Total= 426.200
QUANTITY CALCULATION OF BRIDGE AT CH._67.046 KM ON BILASIPURA-GUWAHATI STRETCH BHARATMALA
LOT-I PKG-IA IN THE STATE OF ASSAM

3 No. X 18 M SPAN CH._67.046 KM


Length Height
Item Sl No. Description Unit nos. Breadth (m) Quantity
(m) (m)
8 RCC M-30 height above 5.0m upto 10.0m
Abutment wall cum 2 12.50 1.200 0.350 10.50
Abutment cap cum 4 12.50 1.790 1.000 89.50
Pier shaft cum portion)
(circular 4 3.80 1.700 25.84
Pier cap(Trapizoidal portion) cum 4 7.25 2.700 0.700 54.81
Pier cap(Rectangular portion) cum 4 11.50 2.700 0.700 86.94
Dirt Wall cum 4 12.50 0.400 2.119 42.38
Bracket cum 4 11.95 0.180 8.60
Return Wall-I upto abutment cap cum 2 3.75 0.550 0.325 1.34
Return Wall-I above abutment cap cum 2 3.16 0.550 3.001 10.43
Return Wall-I(another side) upto
cum 2 3.75 0.550 0.325 1.34
abutment cap
Return Wall-I(another side) above
cum 2 3.16 0.550 3.001 10.43
abutment cap
Return wall extra fin rectangular portion cum 4 0.30 0.800 1.000 0.96
Return wall extra fin triangular portion cum 4 0.30 0.213 0.26
Return wall at median cum 2 2.98 0.300 1.325 2.37
Total= 345.700

9 RCC M-35 for Pedestal & Seismic Arrestor Blocks height upto 5.0m
cum 6 0.80 0.800 0.150 0.58
cum 6 0.80 0.800 0.215 0.83
Pedestal at POT cum PTFE bearing
cum 6 0.80 0.800 0.288 1.11
cum 6 0.80 0.800 0.361 1.39
cum 6 0.80 0.800 0.150 0.58
cum 6 0.80 0.800 0.215 0.83
Pedestal at POT bearing
cum 6 0.80 0.800 0.288 1.11
cum 6 0.80 0.800 0.361 1.39
Total= 7.820

Block RB2 cum 16 0.340 0.700 1.060 4.04


Block RB1 cum 12 0.800 0.889 8.53
Block RB1 (a) cum 12 0.800 1.069 10.26
Block RB3 cum 16 0.640 0.700 1.060 7.17
Total= 37.820

10 HYSD Bars
@ 120 kg/cum T 97.166
Total= 97.166

11 Weep holes
Spacing for weep holes = 2 m in horizontal and 1 m in vertical direction
No of weep holes in horizontal direction per abutment = 11.95/2+1 = 7
No of weep holes in vertical direction per abutment = 5.35+1 = 7
No of weep holes in horizontal direction per return wall = (3.75)/2+1 = 3
No of weep holes in vertical direction per return wall = (8.326)/1+1 = 10
No of weep holes in horizontal direction per return wall at median= (2.98)/2+1 = 3
No of weep holes in vertical direction per return wall at median = (6.325)/1+1 = 8
No of weep holes in horizontal direction per return wall extra fin= (0.8)/2+1 = 2
No of weep holes in vertical direction per return wall extra fin = (1.2665)/1+1 = 3
Total no of Weep holes per abutment = 7 x 7 49
Total no of Weep holes per return wall = 3 x 10 30
Total no of Weep holes per return wall at median= 3 x 8 24
Total no of Weep holes per return wall extra fin= 2 x 3 6
Total no of weep holes = 49 x 4 + 30 x 4 + 24 x 2 + 6 x 4 Total 388.000
QUANTITY CALCULATION OF BRIDGE AT CH._67.046 KM ON BILASIPURA-GUWAHATI STRETCH BHARATMALA
LOT-I PKG-IA IN THE STATE OF ASSAM

3 No. X 18 M SPAN CH._67.046 KM


Length Height
Item Sl No. Description Unit nos. Breadth (m) Quantity
(m) (m)
12 Backfilling - Granular Material
Abutment cum 4 22.30 1.950 173.94
Pier cum 4 14.80 1.950 115.44
Total 289.380

13 Backfilling - Sandy Material


Behind Abutment & Return wall-I cum 4 11.35 3.15 8.019 1146.80
Behind Return wall at median cum 2 3.00 5.010 8.588 258.16
Deduct for filter media cum -281.12
Deduct for brick wall at median cum -6.470
Total 1117.370

14 Filter media
Behind Abutment cum 4 11.950 0.60 8.019 229.98
Behind Return wall-I cum 2 2.855 0.60 7.876 26.98
Behind return wall-I extra fin portion cum 2 1.280 0.600 1.54
Behind Return wall at median cum 2 2.980 0.60 6.325 22.62
Total 281.120

15 POT cum PTFE Bearing


ton 48 250.00 12000.00
Total 12000.000

16 Elastomeric Bearing
Bearing B2 cucm 24 35.00 42.50 4.80 171360
Bearing B3 cucm 48 25.00 30.00 3.90 140400
Total 311760.000
SUPERSTRUCTURE

17 RCC M-30
For T-Girder & Slab
Long Girder middle straight portion With
cum 6 14.260 5.607 479.73
Deck slab
Long Girder end straight portion with
Deck slab cum 12 1.000 6.812 81.74
Long Girder end varying portion With
Deck slab cum 12 1.200 6.210 89.42
Cantilever portion of Deck Slab cum 12 0.420 12.500 0.350 22.05
End Cross Girder cum 12 0.300 7.071 25.46
IntermediateCross Girder cum 6 0.300 7.977 14.36
Kerb cum 2 66.340 0.500 0.225 14.93
Total 727.690

18 HYSD Bars
@ 180 kg/cum T 130.984
Total= 130.984

19 RCC M30 Railing


m 2 66.34 132.68
Total= 132.680

20 RCC M40 Crash Barrier


m 4 66.34 265.36
Total= 265.360

21 Drainage Spout nos. 18 Total 18.000


QUANTITY CALCULATION OF BRIDGE AT CH._67.046 KM ON BILASIPURA-GUWAHATI STRETCH BHARATMALA
LOT-I PKG-IA IN THE STATE OF ASSAM

3 No. X 18 M SPAN CH._67.046 KM


Length Height
Item Sl No. Description Unit nos. Breadth (m) Quantity
(m) (m)
22 M15 PCC below Approach Slab
cum 4 3.370 12.080 0.15 24.43
Total 24.430

23 Approach Slab(M30)
Approach Slab cum 4 3.500 11.930 0.300 50.11
Total 50.110

24 Bituminous concrete wearing course


cum 2 66.34 9.50 0.040 50.42
Total= 50.420

25 Mastic asphalt
sqm 2 66.34 9.50 1260.46
Total= 1260.460

26 Tack coat
sqm 2 66.34 9.50 1260.46
Total= 1260.460

27 Cement Concrete wearing coarse(75mm)


cum 2 66.34 1.50 0.075 14.93
Total= 14.930

28 Filler joint
Providing & fixing 2 mm thick corrugated
m 4 11.78 47.12
copper plate in expansion joint
Providing & fixing 20 mm thick
compressible fibre board in expansion m 4 11.78 47.12
joint
Providing and fixing in position 20 mm
m 4 11.78 47.12
thick premoulded joint filler
Providing and filling joint sealing
m 4 11.78 47.12
compound

29 Strip Seal Expansion Joint


m 4 12.500 50.00
Total 50.000

30 Brick work at median

Above abutment cap level cum 2 2.980 0.250 2.238 3.33

Below abutment cap level cum 2 2.980 0.369 2.20


Total 5.530
QUANTITY CALCULATION OF BRIDGE AT CH._67.046 KM ON BILASIPURA-GUWAHATI STRETCH BHARATMALA
LOT-I PKG-IA IN THE STATE OF ASSAM

3 No. X 18 M SPAN CH._67.046 KM


Length Height
Item Sl No. Description Unit nos. Breadth (m) Quantity
(m) (m)
PROTECTION WORK
31 Pitching with Stone Blanket
Pitching with Stone Blanket (A1 side) cum 2 413.14 0.30 247.884
Pitching with Stone Blanket (A2 side) cum 2 349.88 0.30 209.928
In front of abutment cum 2 28.00 0.395 0.30 6.636
Total 464.448

32 Floor Protection
Abutment (straight portion) cum 4 10.00 0.601 24.040
Abutment A1 (curve portion) cum 2 24.25 1.127 54.660
Abutment A2 (curve portion) cum 2 21.72 1.127 48.957
In front of abutment cum 2 28.00 1.653 92.568
Total 220.225

33 Filter Blanket below pitching


A1 side cum 2 413.14 0.15 123.942
A2 side cum 2 349.88 0.15 104.964
In front of abutment cum 2 28.00 0.395 0.15 3.318
Total= 232.224

MISCELLANEOUS
34 Painting
Kerb below railing sqm 2 0.950 66.34 126.05
Railing(Post) sqm 78 0.90 1.10 77.22
Railing(Beam) sqm 6 0.54 66.34 214.94
Crash Barrier sqm 4 2.080 66.34 551.95
Total 970.160

35 Citizen information Board NH Project no Total 2.000


ROB
JOB NO : 4146 (PACKAGE-5)
Summary sheet of ROB (Quantities & amount)

CHAINAGE 49+989 Km 64.763 Km

7 x 24+(3 x 36m)+
1 x 24+
SPAN 12 x 24+1x18
(24+3X36+24)+ TOTAL QTY
ARRANGEMENT Composite girder(ROB)
3 x 24
T-Beam(Via duct)
ITEM NO. Description Unit
FOUNDATION
1 Excavation upto 3.0m depth CUM 3952.390 10171.240 14,123.63
2 Excavation 3.0m to 6.0m depth CUM 96.760 342.320 439.08
3 Bored Cast-in-situ Pile M35 M 4912.000 5956.000 10,868.00
4 RCC M35 Pile Cap CUM 3214.720 6337.430 9,552.15
5 Brick foundation for approach slab CUM 71.760 68.460 140.22
6 Levelling Course for Foundation slab CUM 859.350 582.550 1,441.90
7 Steel Reinforcement TON 968.520 1333.120 2,301.64
SUBSTRUCTURE
8 RCC M35 upto 5 m CUM 637.200 1169.090 1,806.29
9 RCC M35 5 m to 10 m CUM 1358.000 1731.910 3,089.91
10 RCC M35 above 10 m CUM 355.060 1244.240 1,599.30
11
RCC M40 above 5 m for pedestal CUM 31.340 42.680 74.02
12 RCC M35 above 5 m for REACTION
CUM 72.530 362.620 435.15
BLOCK
13 Steel Reinforcement TON 343.580 637.080 980.66
14 POT CUM PTFE Bearing TON CAPACITY 5120.000 25600.000 30,720.00
16 Metallic guide bearing TON CAPACITY 2280.000 1440.000 3,720.00
17 Elastomeric bearing CCUM 5250269.000 10622097.000 1,58,72,366.00
18 Pin bearing TON CAPACITY 2280.000 1440.000 3,720.00
SUPERSTRUCTURE
18 RCC M35 CUM 1394.370 6527.510 7,921.88
19 RCC M45 CUM 1064.310 738.790 1,803.10
21 Steel Reinforcement TON 442.570 1307.930 1,750.50
23 Supply, fabrication, delivery at bridge
site and erection of structural steel 1232.530 882.990 2,115.52
works TON
24 Bituminas Concrete Wearing Coat CUM 257.470 594.020 851.49
25 Tack Coat SQM 5149.550 11880.360 17,029.91
26 Mastic Asphalt SQM 5149.550 11880.360 17,029.91
27 PCC M15 below approach slab CUM 5.960 5.670 11.63
28 RCC M30 approach slab CUM 0.00
29 RCC M30 Kerb M 14.540 10.040 24.58
30 Crash Barrier RCC M40 M 1098.880 2497.760 3,596.64
31 Steel railing M 599.680 486.800 1,086.48
32 Drainage Spout NO. 92.000 236.000 328.00
33 Strip Seal Expansion Joint M 246.040 520.000 766.04
34 Receiver Pipe for drainage spout M 240.000 160.000 400.00
35 Filler joint 0.00
Providing & fixing 2 mm thick
corrugated copper plate in expansion 44.160 42.000 86.16
joint M
Providing & fixing 20 mm thick
compressible fibre board in expansion 44.160 42.000 86.16
joint M
Providing and fixing in position 20 mm
M 44.160 42.000 86.16
thick premoulded joint filler
Providing and filling joint sealing
44.160 42.000 86.16
compound M
Miscellaneous
36 Paint for concrete surface SQM 4036.520 7733.380 11,769.90
37 Stair TON 201.100 33.520 234.62
38 Inspection ladder TON 9.333 1.556 10.89
ESTIMATE OF QUANTITY OF ROB

Chainage:- 49.989 KM ROB

Length Height
BOQ Sl No. Description Unit nos Breadth (m) Quantity
(m) (m)

FOUNDATION

1 Excavation upto 3.0m depth


Pier 3 cum 2 13.30 9.70 1.75 451.54
Pier 4 cum 2 13.30 9.70 1.54 397.35
Pier 5 cum 2 13.30 9.70 1.67 430.89
Pier 6 cum 2 13.30 9.70 3.00 774.06
Total 2053.84

1(ii) Excavation 3.0m to 6.0m depth


Pier 6 cum 2 13.30 9.70 0.375 96.76
Total 96.76

2 Bored Cast-in-situ Pile M35


m 96 24.00 2304.00
Total 2304.00

3 RCC M35 Pile Cap


Pile cap for Pier 3 & Pier 6 cum 4 12.30 8.70 1.80 770.47
Pile cap for Pier 4 & Pier 5 cum 4 12.30 8.70 1.80 770.47
Total= 1540.94

4 Levelling Course for Foundation slab M15 below pile cap


Pile cap for Pier 3 & Pier 6 cum 4 12.60 9.000 0.15 68.04
Pile cap for Pier 4 & Pier 5 cum 4 12.60 9.000 0.15 68.04
Total= 136.08

5 Steel Reinforcement
@ 90 kg/cum for pile cap & @ 125
t 426.68
kg/m for pile
Total= 426.68

SUBSTRUCTURE

6 RCC M35 upto 5 m(ROB Portion)


Pier 3 circular portion cum 8 1.77 5.000 70.80
Pier 4 circular portion cum 8 1.77 5.000 70.80
Pier 5 circular portion cum 8 1.77 5.000 70.80
Pier 6 circular portion cum 8 1.77 5.000 70.80
Total= 283.20

7 RCC M35 5 m to 10 m
Pier 3 circular portion cum 8 1.77 2.500 35.40
Pier 4 circular portion cum 8 1.77 3.000 42.48
Pier 5 circular portion cum 8 1.77 4.500 63.72
Pier 6 circular portion cum 8 1.77 4.000 56.64
Pier 3 cap rectangular portion cum 2 2.84 12.800 1.000 72.70
Pier 4 cap rectangular portion cum 2 2.84 12.800 1.000 72.70
Pier 3 cap trapezoidal portion cum 2 2.21 11.950 1.000 52.82
Pier 4 cap trapezoidal portion cum 2 2.21 11.950 1.000 52.82
Pier 5 cap trapezoidal portion cum 2 2.21 11.950 0.500 26.41
Pier 6 cap trapezoidal portion cum 2 2.21 11.950 1.000 52.82
Extra cap part in P3 & P6 cum 4 1.42 12.80 0.361 26.25
Inspection polatform for P3 & P4 cum 4 32.28 1.20 0.200 30.99
Total= 585.75
ESTIMATE OF QUANTITY OF ROB

Chainage:- 49.989 KM ROB

Length Height
BOQ Sl No. Description Unit nos Breadth (m) Quantity
(m) (m)

8 RCC M35 above 10 m(ROB Portion)


Pier 5 cap rectangular portion cum 2 2.84 12.80 1.000 72.70
Pier 6 cap rectangular portion cum 2 2.84 12.80 1.000 72.70
Pier 5 cap trapezoidal portion cum 2 2.21 11.95 0.500 26.41
Inspection polatform for P5 & P6 cum 4 32.28 1.200 0.200 30.99
Total= 202.80

9 RCC M40 upto 5 m for pedestal


cum 8 0.900 0.650 0.150 0.70
cum 8 0.900 0.650 0.213 1.00
Pedestal below 24m RDSO Span cum 8 0.900 0.650 0.276 1.29
cum 8 0.900 0.650 0.339 1.59
cum 8 0.900 0.650 0.402 1.88
cum 12 1.050 0.650 0.150 1.23
cum 12 1.050 0.650 0.213 1.74
Pedestal below 36m RDSO Span cum 12 1.050 0.650 0.276 2.26
cum 12 1.050 0.650 0.339 2.78
cum 12 1.050 0.650 0.402 3.29
Metallic guide bearing(24m span) cum 4 0.880 1.015 0.365 1.30
Pin bearing (24m span) cum 4 0.880 1.015 0.365 1.30
Metallic guide bearing(36m span) cum 6 1.070 1.325 0.441 3.75
Pin bearing (36m span) cum 6 1.070 1.325 0.441 2.13
Total = 26.24

10 Steel Reinforcement
@ 140kg/cum t 153.72
Total = 153.72

11 Elastomeric Bearing
for 36 m span (Composite) cc 60 35.00 75.00 14.90 2346750.00
for 24 m span (Composite) cc 40 35.00 60.00 14.90 1251600.00
Total = 3598350.00

12 Metallic guide bearing


one tonne
for 36 m span (Composite) 6 240.00 1440.0
capacity
one tonne
for 24 m span (Composite) 4 210.000 840.00
capacity
Total 2280

13 Pin bearing
one tonne
for 36 m span (Composite) 6 240.00 1440.00
capacity
one tonne
for 24 m span (Composite) 4 210.00 840.00
capacity
Total 2280.00
ESTIMATE OF QUANTITY OF ROB

Chainage:- 49.989 KM ROB

Length Height
BOQ Sl No. Description Unit nos Breadth (m) Quantity
(m) (m)

SUPERSTRUCTURE

14 RCC M45 (ROB Portion)


For 36.0 m RDSO superstructure 3.31
cum 6 37.20 738.79
deck
For 24.0 m RDSO superstructure 3.25
cum 4 25.04 325.52
deck
Total 1064.31

15 Steel Reinforcement
@ 180kg/cum t 191.58
Total= 191.58

16 Supply, fabrication, delivery at bridge site and erection of structural steel works
For 36 m span t 6 147.165 882.99
For 24 m span t 4 87.386 349.54
Total= 1232.53

17 Bituminous Concrete Wearing Coat


For 36 m span cum 6 8.94 37.20 0.050 99.77
For 24 m span cum 4 8.94 25.00 0.050 44.70
Total= 144.47

18 Mastic Asphalt
For 36 m span sqm 6 8.94 37.20 1995.41
For 24 m span sqm 4 8.94 25.00 894.00
Total= 2889.41

19 Tack Coat
For 36 m span sqm 6 8.94 37.20 1995.41
For 24 m span sqm 4 8.94 25.00 894.00
Total= 2889.41

20 RCC M30 Kerb cum 2 161.60 0.30 0.150 14.54


Total 14.54

21 Crash Barrier RCC M40


m 4 161.60 646.40
Total 646.40

Steel railing for inspection


22
Platform
Steel railing for P3 & P4 m 4 34.56 138.24
Steel railing for P5 & P6 m 4 34.56 138.24
Steel railing for footpath m 2 161.60 323.20
Total 599.68

23 Drainage Spout nos. 52 Total 52.00

24 Strip Seal Expansion Joint


m 12 13.143 157.72
Total 157.72

25 Receiver Pipe for drainage spout


For 36 span m 12 20.00 240.00
Total 240.00

Miscallaeneous

27 Paint for concrete surface


For ROB portion (kerb) sqm 2 161.60 0.600 934.05
For ROB portion (crash barrier) sqm 4 161.60 2.890 1868.10
Total= 2802.15
ESTIMATE OF QUANTITY OF VIADUCT

Chainage:- 49.989 KM Viaduct


Length Height
BOQ Sl No. Description Unit nos Breadth (m) Quantity
(m) (m)

FOUNDATION

29 Excavation upto 3.0m depth


Pier 1 cum 2 13.30 6.10 2.04 331.01
Pier 2 cum 2 13.30 9.70 1.60 412.83
Pier 7 cum 2 13.30 9.70 1.18 304.46
Pier 8 cum 2 13.30 6.10 1.52 246.64
Pier 9 cum 2 13.30 6.10 1.80 292.07
Pier 10 cum 2 13.30 6.10 1.92 311.54
Total 1898.55

30 Bored Cast-in-situ Pile M35


Pier-1,8,9,10 m 64 22.00 1408.00
Pier-2 & 7 m 48 25.00 1200.00
Total 2608.00

31 RCC M35 Pile Cap(Viaduct Portion)


Pile cap for P1,P8,P9,P10 cum 8 12.30 5.10 1.80 903.31
Pile cap for P2 & P7 cum 4 12.30 8.70 1.80 770.47
Total= 1673.78

32 Levelling Course for Foundation slab M15 below pile cap


Pile cap for P1,P8,P9,P10 cum 8 12.60 5.40 0.15 81.65
Pile cap for P2 & P7 cum 4 12.60 9.00 1.15 521.64
Below brick foundation cum 4 11.34 2.300 1.15 119.98
Total= 723.27

33 Steel Reinforcement
@ 90 kg/cum for pile cap & @
t 541.84
130 kg/m for pile
Total= 541.84

34 Brick foundation for Solid slab


cum 4 11.04 1.625 71.76
Total= 71.76
ESTIMATE OF QUANTITY OF VIADUCT

Chainage:- 49.989 KM Viaduct


Length Height
BOQ Sl No. Description Unit nos Breadth (m) Quantity
(m) (m)
SUBSTRUCTURE
35 RCC M30 upto 5 m
Pier 1 circular portion cum 6 1.77 5.000 53.10
Pier 2 circular portion cum 8 1.77 5.000 70.80
Pier 7 circular portion cum 8 1.77 5.000 70.80
Pier 8 circular portion cum 6 1.77 5.000 53.10
Pier 9 circular portion cum 6 1.77 5.000 53.10
Pier 10 circular portion cum 6 1.77 5.000 53.10
Total= 354.00

36 RCC M30 5 m to 10 m
Pier 1 circular portion cum 6 1.77 1.000 10.62
Pier 2 circular portion cum 8 1.77 1.500 21.24
Pier 7 circular portion cum 8 1.77 3.700 52.39
Pier 8 circular portion cum 6 1.77 3.700 39.29
Pier 9 circular portion cum 6 1.77 3.700 39.29
Pier 10 circular portion cum 6 1.77 3.300 35.05
Pier 1 cap rectangular portion cum 2 2.04 10.90 1.000 44.47
Pier 2 cap rectangular portion cum 2 3.00 12.80 1.000 76.80
Pier 7 cap rectangular portion cum 2 3.00 12.80 0.300 23.04
Pier 8 cap rectangular portion cum 2 2.79 10.90 0.300 18.25
Pier 9 cap rectangular portion cum 2 2.79 10.90 0.300 18.25
Pier 10 cap rectangular portion cum 2 2.04 10.90 0.700 31.13
Pier 1 cap trapezoidal portion cum 2 1.81 9.20 1.000 33.30
Pier 2 cap trapezoidal portion cum 2 2.29 11.95 1.000 54.73
Pier 7 cap trapezoidal portion cum 2 2.29 11.95 1.000 54.73
Pier 8 cap trapezoidal portion cum 2 2.18 9.20 1.000 40.11
Pier 9 cap trapezoidal portion cum 2 2.18 9.20 1.000 40.11
Pier 10 cap trapezoidal portion cum 2 1.81 9.20 1.000 33.30
Extra cap part in P2 & P7 cum 4 1.16 12.80 0.778 46.21
Dirt Wall cum 4 11.46 0.400 2.819 51.69
Bracket cum 4 11.46 0.180 8.25
Total= 772.25

37 RCC M30 above 10m


Pier 7 cap rectangular portion cum 2 3.00 12.800 0.700 53.76
Pier 8 cap rectangular portion cum 2 2.79 10.900 0.700 42.58
Pier 9 cap rectangular portion cum 2 2.79 10.900 0.700 42.58
Pier 10 cap rectangular portion cum 2 2.04 10.900 0.300 13.34
Total= 152.26
38 RCC M40 above 5 m for pedestal
cum 8 0.800 0.800 0.150 0.77
cum 8 0.800 0.800 0.216 1.11
Pedestal below 24m RCC Span
cum 8 0.800 0.800 0.282 1.44
cum 8 0.800 0.800 0.348 1.78
Total= 5.10

39 RCC M35 above 10m for Reaction Block


Reaction block 1 (RB1) cum 32 0.800 0.873 22.35
Reaction block 2 (RB2) cum 64 0.800 0.700 1.400 50.18
Total= 72.53
ESTIMATE OF QUANTITY OF VIADUCT

Chainage:- 49.989 KM Viaduct


Length Height
BOQ Sl No. Description Unit nos Breadth (m) Quantity
(m) (m)
40 Steel Reinforcement
@ 140kg/cum t 189.86
Total= 189.86

41 Pot cum PTFE Bearing


one tonne
for 24 m span 32 160.000 5120.00
capacity
Total 5120.00

42 Elastomeric Bearing
Bearing B2 cc 32 54.80 37.00 9.80 635855
Bearing B3 cc 64 42.00 42.00 9.00 1016064
Total 1651919

SUPERSTRUCTURE

43 RCC M35
Deck Slab_T Beam_24(End) cum 8 2.000 7.81 124.96
Deck Slab_T Beam_24(Middle) cum 8 20.260 5.87 951.41
Deck Slab_T Beam_24(Varrying) cum 8 2.400 6.84 131.33
Cantilever of Deck cum 16 0.600 11.04 0.468 49.60
T beam cross girder middle cum 8 0.300 11.373 27.30
T beam cross girder end cum 16 0.300 9.990 47.95
Solid Slab in Approach cum 4 11.040 4.000 0.350 61.82
Total 1394.37

44 Steel Reinforcement
@ 180kg/cum t 250.99
Total= 250.99

45 Bituminous Concrete Wearing Coat


For 24 m span with dirt wall cum 8 9.99 26.28 0.050 105.01
For solid slab cum 4 9.99 4.00 0.050 7.99
Total= 113.00

46 Mastic Asphalt
For 24 m span with dirt wall sqm 8 9.99 26.28 2100.30
For solid slab sqm 4 9.99 4.00 159.84
Total= 2260.14

47 Tack coat
For 24 m span with dirt wall sqm 8 9.99 26.28 2100.30
For solid slab sqm 4 9.99 4.00 159.84
Total= 2260.14

48 PCC M15 below solid slab


cum 4 11.04 0.90 0.15 5.96
Total= 5.96

49 Crash Barrier RCC M40 m 4 113.12 452.48


Total 452.48
ESTIMATE OF QUANTITY OF VIADUCT

Chainage:- 49.989 KM Viaduct


Length Height
BOQ Sl No. Description Unit nos Breadth (m) Quantity
(m) (m)
50 Drainage Spout nos. 40 Total 40.00

51 Strip Seal Expansion Joint m 8 11.04 88.32


Total 88.32

52 Filler joint
Providing & fixing 2 mm thick
corrugated copper plate in m 4 11.04 44.16
expansion joint
Providing & fixing 20 mm thick
compressible fibre board in m 4 11.04 44.16
expansion joint
Providing and fixing in position 20
m 4 11.04 44.16
mm thick premoulded joint filler
Providing and filling joint sealing
m 4 11.04 44.16
compound

Miscallaeneous

53 Paint for concrete surface


For Viaduct portion (crash
sqm 4 113.12 2.728 1234.37
barrier)
Total= 1234.37
MEASUREMENT SHEET
STRUCTURAL STEEL WORKS FOR STAIRCASE

Volume
Length Breadth Thickne (m3) / Unit Total
Sl. No. Description Nos.
(m) (m) ss (m) Length Weight Weight (kg)
(m)
28 Stair
Stair Columns (ISMB 250) 4 11.000 47.55 2092.20
Stair Case inclined beam (ISMC 200) 8 5.000 28.21 1128.40
Floor Beams 1 (ISMC 200) 5 10.500 28.21 1481.03
Floor Beams 2 (ISMC 200) 10 4.500 28.21 1269.45
Gratings (4 X 1.5) 5 4.200 2.000 40 1680.00
Stair Gratings (1.6 X 0.3) 74 1.800 0.300 40 1598.40
Railing for various platform & Stair (32NB) 300 3.1 930.00
Railing for various platform & Stair (40NB) 250 3.56 890.00
15 % extra for Int. X Frames, Splices, Nuts,
2010.97
Bolts, Gusset plate
10% Wastage Due to Non Avaiability of
1340.65
required legth of member
GRAND TOTAL for 1 stair = 16758.10
GRAND TOTAL for 12 stair = 201097.20
GRAND TOTAL for 4 stair (in ton) = 201.10

29 Inspection ladder
Inclined member (ISMC 200) 2 3.831 28.21 216.15
Stair Gratings (1.6 X 0.3) 26 1.800 0.300 40 561.60
GRAND TOTAL for 1 Ladder = 777.75
No of ladder = 12 Total in tonne = 9.333
ESTIMATE OF QUANTITY OF ROB

Chainage:- 64.763 KM ROB

Length Height
BOQ Sl No. Description Unit nos Breadth (m) Quantity
(m) (m)

FOUNDATION

1 Excavation upto 3.0m depth


Pier 8 cum 2 9.70 13.30 2.19 565.06
Pier 9 cum 2 9.70 13.30 2.22 572.80
Pier 10 cum 2 9.70 13.30 2.22 572.80
Pier 11 cum 2 9.70 13.30 3.00 774.06
Total 2484.72

1(ii) Excavation 3.0m to 6.0m depth


Pier 11 cum 2 9.70 13.30 0.099 25.54
Total 25.54

2 Bored Cast-in-situ Pile M35


m 96 24.00 2304.00
Total 2304.00

3 RCC M35 Pile Cap


Pile cap for Pier 8,Pier 9,Pier 10 &
cum 8 8.70 12.30 1.80 1540.94
Pier 11
Total= 1540.94

4 Levelling Course for Foundation slab M15 below pile cap


Pile cap for Pier 8,Pier 9,Pier 10 &
cum 8 9.00 12.600 0.15 136.08
Pier 11
Total= 136.08

5 Steel Reinforcement
@ 90 kg/cum for pile cap & @ 125
t 426.68
kg/m for pile
Total= 426.68

SUBSTRUCTURE

6 RCC M35 upto 5 m(ROB Portion)


Pier 8 circular portion cum 2 3.58 5.000 35.80
Pier 9 circular portion cum 2 3.58 5.000 35.80
Pier 10 circular portion cum 2 3.58 5.000 35.80
Pier 11 circular portion cum 2 3.58 5.000 35.80
Total= 143.20

7 RCC M35 5 m to 10 m
Pier 8 circular portion cum 2 3.58 5.000 35.80
Pier 9 circular portion cum 2 3.58 5.000 35.80
Pier 10 circular portion cum 2 3.58 5.000 35.80
Pier 11 circular portion cum 2 3.58 5.000 35.80
Total= 143.20
ESTIMATE OF QUANTITY OF ROB

Chainage:- 64.763 KM ROB

Length Height
BOQ Sl No. Description Unit nos Breadth (m) Quantity
(m) (m)

8 RCC M35 above 10 m(ROB Portion)


Pier 8 circular portion cum 2 3.58 1.600 11.46
Pier 9 circular portion cum 2 3.58 0.400 2.86
Pier 10 circular portion cum 2 3.58 0.400 2.86
Pier 11 circular portion cum 2 3.58 1.600 11.46
Pier 8 cap rectangular portion cum 2 2.90 12.00 1.000 69.60
Pier 9 cap rectangular portion cum 2 2.70 12.00 1.000 64.80
Pier 10 cap rectangular portion cum 2 2.70 12.00 1.000 64.80
Pier 11 cap rectangular portion cum 2 2.90 12.00 1.000 69.60
Pier 8 cap trapezoidal portion cum 2 2.45 7.00 1.000 34.30
Pier 9 cap trapezoidal portion cum 2 2.35 7.00 1.000 32.90
Pier 10 cap trapezoidal portion cum 2 2.35 7.00 1.000 32.90
Pier 11 cap trapezoidal portion cum 2 2.45 7.00 1.000 34.30
Extra part of pier cap of Pier 8 &
cum 4 1.27 12.00 0.417 25.42
Pier 11
Inspection polatform for P8 & P11 cum 4 29.30 1.200 0.200 28.13

Inspection polatform for P9 & P10 cum 4 31.50 1.200 0.200 30.24
Total= 515.63

9 RCC M35 above 10 m for pedestal


cum 12 1.050 0.650 0.150 1.23
cum 12 1.050 0.650 0.213 1.74
Pedestal below 36m RDSO Span cum 12 1.050 0.650 0.276 2.26
cum 12 1.050 0.650 0.339 2.78
cum 12 1.050 0.650 0.402 3.29
Metallic guide bearing(36m span) cum 6 1.070 1.325 0.441 3.75
Pin bearing (36m span) cum 6 1.070 1.325 0.441 2.13
Total = 17.18

10 Steel Reinforcement
@ 140kg/cum t 114.69
Total = 114.69

11 Elastomeric Bearing
for 36 m span (Composite) cc 60 35.00 75.00 15.00 2362500.00
Total = 2362500.00

12 Metallic guide bearing


one tonne
for 36 m span (Composite) 6 240.00 1440.0
capacity
Total 1440

13 Pin bearing
one tonne
for 36 m span (Composite) 6 240.00 1440.00
capacity
Total 1440.00
ESTIMATE OF QUANTITY OF ROB

Chainage:- 64.763 KM ROB

Length Height
BOQ Sl No. Description Unit nos Breadth (m) Quantity
(m) (m)

SUPERSTRUCTURE

14 RCC M45 (ROB Portion)


For 36.0 m RDSO superstructure 3.31
cum 6 37.20 738.79
deck
Total 738.79

15 Steel Reinforcement
@ 180kg/cum t 132.98
Total= 132.98

16 Supply, fabrication, delivery at bridge site and erection of structural steel works
For 36 m span t 6 147.165 882.99
Total= 882.99

17 Bituminas Concrete Wearing Coat


For 36 m span cum 6 9.50 37.20 0.050 106.02
Total= 106.02

18 Mastic Asphalt
For 36 m span sqm 6 9.50 37.20 2120.40
Total= 2120.40

19 Tack Coat
For 36 m span sqm 6 9.50 37.20 2120.40
Total= 2120.40

20 RCC M30 Kerb cum 2 111.60 0.30 0.150 10.04


Total 10.04

21 Crash Barrier RCC M40


m 4 111.60 446.40
Total 446.40

Steel railing for inspection


22
Platform
Steel railing for P8 & P11 m 4 31.70 126.80
Steel railing for P9 & P10 m 4 34.20 136.80
Steel railing for footpath m 2 111.60 223.20
Total 486.80

23 Drainage Spout nos. 36 Total 36.00

24 Strip Seal Expansion Joint


m 8 12.500 100.00
Total 100.00

25 Receiver Pipe for drainage spout


For 36 span m 8 20.00 160.00
Total 160.00

Miscallaeneous

26 Paint for concrete surface


For ROB portion (kerb) sqm 2 111.60 0.600 756.87
For ROB portion (crash barrier) sqm 4 111.60 3.391 1513.74
Total= 2270.61
ESTIMATE OF QUANTITY OF VIADUCT

Chainage:- 64.763 KM Viaduct


Length Height
BOQ Sl No. Description Unit nos Breadth (m) Quantity
(m) (m)

FOUNDATION

29 Excavation upto 3.0m depth


Pier 1 cum 2 6.10 13.30 1.31 212.56
Pier 2 cum 2 6.10 13.30 2.68 434.86
Pier 3 cum 2 6.10 13.30 1.50 243.39
Pier 4 cum 2 9.70 9.70 2.27 427.17
Pier 5 cum 2 9.70 9.70 2.07 389.53
Pier 6 cum 2 9.70 9.70 1.41 265.33
Pier 7 cum 2 9.70 9.70 2.91 547.60
Pier 12 cum 2 9.70 9.70 2.06 387.65
Pier 13 cum 2 9.70 9.70 3.00 564.54
Pier 14 cum 2 6.10 13.30 2.19 355.35
Pier 15 cum 2 6.10 13.30 2.67 433.23
Pier 16 cum 2 6.10 13.30 2.45 397.54
Pier 17 cum 2 6.10 13.30 2.74 444.59
Pier 18 cum 2 6.10 13.30 1.99 322.90
Pier 19 cum 2 6.10 13.30 2.68 434.86
Pier 20 cum 2 6.10 13.30 3.00 486.78
Pier 21 cum 2 6.10 13.30 1.98 321.27
Pier 22 cum 2 6.10 13.30 2.24 363.46
Pier 23 cum 2 6.10 13.30 2.01 326.14
Pier 24 cum 2 6.10 13.30 2.02 327.77
Total 7686.52

29(ii) Excavation 3.0m to 6.0m depth


Pier 13 cum 2 9.70 9.70 1.448 272.48
Pier 20 cum 2 6.10 13.30 0.273 44.30
Total 316.78

30 Bored Cast-in-situ Pile M35


m 166 22.00 3652.00
Total 3652.00

31 RCC M35 Pile Cap(Viaduct Portion)


Pile cap for P1 to P3 & P14 to
cum 28 5.10 12.30 1.80 3161.59
P24
Pile cap for P4 to P7 & P12 to
cum 12 8.70 8.70 1.80 1634.90
P13
Total= 4796.49

32 Levelling Course for Foundation slab M15 below pile cap


Pile cap for P1 to P3 & P14 to
cum 28 5.40 12.60 0.15 285.77
P24
Pile cap for P4 to P7 & P12 to
cum 12 9.00 9.00 0.15 145.80
P13
Below brick foundation cum 4 10.80 2.300 0.15 14.90
Total= 446.47

33 Steel Reinforcement
@ 90 kg/cum for pile cap & @
t 906.44
130 kg/m for pile
Total= 906.44

34 Brick foundation for Solid slab


cum 4 10.50 1.63 68.46
Total= 68.46
ESTIMATE OF QUANTITY OF VIADUCT

Chainage:- 64.763 KM Viaduct


Length Height
BOQ Sl No. Description Unit nos Breadth (m) Quantity
(m) (m)
SUBSTRUCTURE
35 RCC M35 upto 5 m
Pier 1 circular portion cum 6 1.77 3.500 37.17
Pier 2 circular portion cum 6 1.77 5.000 53.10
Pier 3 circular portion cum 6 1.77 5.000 53.10
Pier 4 circular portion cum 2 3.58 5.000 35.80
Pier 5 circular portion cum 2 3.58 5.000 35.80
Pier 6 circular portion cum 2 3.58 5.000 35.80
Pier 7 circular portion cum 2 3.58 5.000 35.80
Pier 12 circular portion cum 2 3.58 5.000 35.80
Pier 13 circular portion cum 2 3.58 5.000 35.80
Pier 14 circular portion cum 6 1.77 5.000 53.10
Pier 15 circular portion cum 6 1.77 4.000 42.48
Pier 16 circular portion cum 6 1.77 5.000 53.10
Pier 17 circular portion cum 6 1.77 5.000 53.10
Pier 18 circular portion cum 6 1.77 5.000 53.10
Pier 19 circular portion cum 6 1.77 4.900 52.04
Pier 20 circular portion cum 6 1.77 5.000 53.10
Pier 21 circular portion cum 6 1.77 5.000 53.10
Pier 22 circular portion cum 6 1.77 5.000 53.10
Pier 23 circular portion cum 6 1.77 5.000 53.10
Pier 24 circular portion cum 6 1.77 5.000 53.10
Pier 1 cap rectangular portion cum 2 1.94 10.90 0.500 21.15
Pier 1 cap trapezoidal portion cum 2 1.72 9.20 1.000 31.65
Pier 15 cap trapezoidal portion cum 2 2.10 9.20 1.000 38.64
Pier 19 cap trapezoidal portion cum 2 2.10 9.20 0.100 3.86
Total= 1025.89
ESTIMATE OF QUANTITY OF VIADUCT

Chainage:- 64.763 KM Viaduct


Length Height
BOQ Sl No. Description Unit nos Breadth (m) Quantity
(m) (m)
36 RCC M35 5 m to 10 m
Pier 2 circular portion cum 6 1.77 2.100 22.30
Pier 3 circular portion cum 6 1.77 3.400 36.11
Pier 4 circular portion cum 2 3.58 5.000 35.80
Pier 5 circular portion cum 2 3.58 5.000 35.80
Pier 6 circular portion cum 2 3.58 5.000 35.80
Pier 7 circular portion cum 2 3.58 5.000 35.80
Pier 12 circular portion cum 2 3.58 5.000 35.80
Pier 13 circular portion cum 2 3.58 5.000 35.80
Pier 14 circular portion cum 6 1.77 0.300 3.19
Pier 15 circular portion cum 6 1.77 0.000 0.00
Pier 16 circular portion cum 6 1.77 0.300 3.19
Pier 17 circular portion cum 6 1.77 0.300 3.19
Pier 18 circular portion cum 6 1.77 0.100 1.06
Pier 19 circular portion cum 6 1.77 0.000 0.00
Pier 20 circular portion cum 6 1.77 2.600 27.61
Pier 21 circular portion cum 6 1.77 3.300 35.05
Pier 22 circular portion cum 6 1.77 4.000 42.48
Pier 23 circular portion cum 6 1.77 4.300 45.67
Pier 24 circular portion cum 6 1.77 1.800 19.12
Pier 1 cap rectangular portion cum 2 1.94 10.90 0.500 21.15
Pier 2 cap rectangular portion cum 2 2.70 10.90 1.000 58.86
Pier 3 cap rectangular portion cum 2 2.70 10.90 0.600 35.32
Pier 14 cap rectangular portion cum 2 2.70 10.90 1.000 58.86
Pier 15 cap rectangular portion cum 2 2.70 10.90 1.000 58.86
Pier 16 cap rectangular portion cum 2 2.70 10.90 1.000 58.86
Pier 17 cap rectangular portion cum 2 2.70 10.90 1.000 58.86
Pier 18 cap rectangular portion cum 2 2.70 10.90 1.000 58.86
Pier 19 cap rectangular portion cum 2 2.70 10.90 1.000 58.86
Pier 20 cap rectangular portion cum 2 2.70 10.90 1.000 58.86
Pier 21 cap rectangular portion cum 2 2.70 10.90 0.700 41.20
Pier 24 cap rectangular portion cum 2 1.94 10.90 1.000 42.29
Pier 2 cap trapezoidal portion cum 2 2.10 9.20 1.000 38.64
Pier 3 cap trapezoidal portion cum 2 2.10 9.20 1.000 38.64
Pier 14 cap trapezoidal portion cum 2 2.10 9.20 1.000 38.64
Pier 16 cap trapezoidal portion cum 2 2.10 9.20 1.000 38.64
Pier 17 cap trapezoidal portion cum 2 2.10 9.20 1.000 38.64
Pier 18 cap trapezoidal portion cum 2 2.10 9.20 1.000 38.64
Pier 19 cap trapezoidal portion cum 2 2.10 9.20 0.900 34.78
Pier 20 cap trapezoidal portion cum 2 2.10 9.20 1.000 38.64
Pier 21 cap trapezoidal portion cum 2 2.10 9.20 1.000 38.64
Pier 22 cap trapezoidal portion cum 2 2.10 9.20 1.000 38.64
Pier 23 cap trapezoidal portion cum 2 2.10 9.20 0.700 27.05
Pier 24 cap trapezoidal portion cum 2 1.72 9.20 1.000 31.65
Extra cap part in P18 & P19 cum 4 1.00 10.90 0.593 25.85
Dirt Wall cum 4 10.90 0.400 2.819 49.16
Bracket cum 4 10.90 0.180 7.85
Total= 1588.71
ESTIMATE OF QUANTITY OF VIADUCT

Chainage:- 64.763 KM Viaduct


Length Height
BOQ Sl No. Description Unit nos Breadth (m) Quantity
(m) (m)
37 RCC M35 above 10m
Pier 5 circular portion cum 2 3.58 1.450 10.38
Pier 7 circular portion cum 2 3.58 1.600 11.46
Pier 3 cap rectangular portion cum 2 2.70 10.900 0.400 23.54
Pier 4 cap rectangular portion cum 2 2.70 10.900 1.000 58.86
Pier 5 cap rectangular portion cum 2 2.70 10.900 1.000 58.86
Pier 6 cap rectangular portion cum 2 2.70 10.900 1.000 58.86
Pier 7 cap rectangular portion cum 2 2.70 10.900 1.000 58.86
Pier 12 cap rectangular portion cum 2 2.70 10.900 1.000 58.86
Pier 13 cap rectangular portion cum 2 2.70 10.900 1.000 58.86
Pier 21 cap rectangular portion cum 2 2.70 10.900 0.300 17.66
Pier 22 cap rectangular portion cum 2 2.70 10.900 1.000 58.86
Pier 23 cap rectangular portion cum 2 2.70 10.900 1.000 58.86
Pier 4 cap trapezoidal portion cum 2 2.35 6.450 1.000 30.32
Pier 5 cap trapezoidal portion cum 2 2.35 6.450 1.000 30.32
Pier 6 cap trapezoidal portion cum 2 2.35 6.450 1.000 30.32
Pier 7 cap trapezoidal portion cum 2 2.35 6.450 1.000 30.32
Pier 12 cap trapezoidal portion cum 2 2.35 6.450 1.000 30.32
Pier 13 cap trapezoidal portion cum 2 2.35 6.450 1.000 30.32
Pier 23 cap trapezoidal portion cum 2 2.10 9.200 0.300 11.59
Total= 728.61
38 RCC M40 above 5 m for pedestal
cum 40 0.800 0.800 0.150 3.84
Pedestal below 24m & 18m RCC cum 40 0.800 0.800 0.216 5.53
Span cum 40 0.800 0.800 0.282 7.22
cum 40 0.800 0.800 0.348 8.91
Total= 25.50

39 RCC M35 above 5m for Reaction Block


Reaction block 1 (RB1) cum 160 0.800 0.873 111.74
Reaction block 2 (RB2) cum 320 0.800 0.700 1.400 250.88
Total= 362.62

40 Steel Reinforcement
@ 140kg/cum t 522.39
Total= 522.39

41 Pot cum PTFE Bearing


one tonne
for 24 m & 18 m span 160 160.000 25600.00
capacity
Total 25600.00

42 Elastomeric Bearing
Bearing B2 cc 160 54.80 37.00 9.80 3179277
Bearing B3 cc 320 42.00 42.00 9.00 5080320
Total 8259597
ESTIMATE OF QUANTITY OF VIADUCT

Chainage:- 64.763 KM Viaduct


Length Height
BOQ Sl No. Description Unit nos Breadth (m) Quantity
(m) (m)
SUPERSTRUCTURE

43 RCC M35
Deck Slab_T Beam_24(End) cum 38 2.000 7.81 593.56
Deck Slab_T Beam_24(Middle) cum 38 20.260 5.87 4519.20
Deck Slab_T Beam_24(Varrying) cum 38 2.400 6.84 623.81
T beam cross girder middle_24 cum 38 0.300 11.373 129.65
T beam cross girder end_24 cum 76 0.300 9.990 227.77
Deck Slab_T Beam_18(End) cum 2 2.000 6.313 25.25
Deck Slab_T Beam_18(Middle) cum 2 14.260 5.087 145.08
Deck Slab_T Beam_18(Varrying) cum 2 2.400 5.70 27.36
T beam cross girder middle_18 cum 2 0.300 7.188 4.31
T beam cross girder end_18 cum 4 0.300 6.345 7.61
Cantilever of Deck cum 80 0.420 10.50 0.468 165.11
Solid Slab in Approach cum 4 10.500 4.000 0.350 58.80
Total 6527.51

44 Steel Reinforcement
@ 180kg/cum t 1174.95
Total= 1174.95

45 Bituminas Concrete Wearing Coat


For 24 m & 18 m span with dirt
cum 2 9.50 504.84 0.050 479.60
wall
For solid slab cum 4 10.50 4.00 0.050 8.40
Total= 488.00

46 Mastic Asphalt
For 24 m & 18 m span with dirt
sqm 2 9.50 504.84 9591.96
wall
For solid slab sqm 4 10.50 4.00 168.00
Total= 9759.96

47 Tack coat
For 24 m & 18 m span with dirt
sqm 2 9.50 504.84 9591.96
wall
For solid slab sqm 4 10.50 4.00 168.00
Total= 9759.96

48 PCC M15 below solid slab


cum 4 10.50 0.90 0.15 5.67
Total= 5.67

49 Crash Barrier RCC M40 m 4 512.84 2051.36


Total 2051.36
ESTIMATE OF QUANTITY OF VIADUCT

Chainage:- 64.763 KM Viaduct


Length Height
BOQ Sl No. Description Unit nos Breadth (m) Quantity
(m) (m)

50 Drainage Spout nos. 200 Total 200.00

51 Strip Seal Expansion Joint m 40 10.50 420.00


Total 420.00

52 Filler joint
Providing & fixing 2 mm thick
corrugated copper plate in m 4 10.50 42.00
expansion joint
Providing & fixing 20 mm thick
compressible fibre board in m 4 10.50 42.00
expansion joint
Providing and fixing in position 20
m 4 10.50 42.00
mm thick premoulded joint filler

Providing and filling joint sealing


m 4 10.50 42.00
compound

Miscallaeneous

53 Paint for concrete surface


For Viaduct portion (crash
sqm 4 512.84 2.663 5462.77
barrier)
Total= 5462.77
MEASUREMENT SHEET
STRUCTURAL STEEL WORKS FOR STAIRCASE

Volume
Length Breadth Thickne (m3) / Unit Total
Sl. No. Description Nos.
(m) (m) ss (m) Length Weight Weight (kg)
(m)
27 Stair
Stair Columns (ISMB 250) 4 11.000 47.55 2092.20
Stair Case inclined beam (ISMC 200) 8 5.000 28.21 1128.40
Floor Beams 1 (ISMC 200) 5 10.500 28.21 1481.03
Floor Beams 2 (ISMC 200) 10 4.500 28.21 1269.45
Gratings (4 X 1.5) 5 4.200 2.000 40 1680.00
Stair Gratings (1.6 X 0.3) 74 1.800 0.300 40 1598.40
Railing for various platform & Stair (32NB) 300 3.1 930.00
Railing for various platform & Stair (40NB) 250 3.56 890.00
15 % extra for Int. X Frames, Splices, Nuts,
2010.97
Bolts, Gusset plate
10% Wastage Due to Non Avaiability of
1340.65
required legth of member
GRAND TOTAL for 1 stair = 16758.10
GRAND TOTAL for 2 stair = 33516.20
GRAND TOTAL for 2 stair (in ton) = 33.52

28 Inspection ladder
Inclined member (ISMC 200) 2 3.831 28.21 216.15
Stair Gratings (1.6 X 0.3) 26 1.800 0.300 40 561.60
GRAND TOTAL for 1 Ladder = 777.75
No of ladder = 2 Total in tonne = 1.5555
VUP, LVUP & PUP
JOB NO : 4146 (PACKAGE-5)
Summary sheet of VUP,LVUP,PUP (Quantities & amount)

CHAINAGE 67+556 km

Span Total Quantity


Arrangement 2 x 30m_PSC

ITEM NO. Description Unit


A. Foundation
Item no 1(a) Excavation (upto 3 m depth) cum 1089.350 1089.350
Item no 2 R.C.C M30 (Pile Cap) cum 591.940 591.940
Item no 3 P.C.C (M-15) cum 67.950 67.950
Item no 4 Bored cast-in-situ M35 grade R.C.C. Piles m 1146.000 1146.000
Item no 6 Steel (Foundation) ton 190.795 190.795
B. Sub-Structure
Item no 1(a) R.C.C M30 (Substructure) upto 5m cum 195.310 195.310
Item no 1(b) R.C.C M30 (Substructure) from 5m to 10m cum 225.820 225.820
Item no 1(c) R.C.C M30 (Substructure) above 10m cum 132.230 132.230
Item no 2 R.C.C. M35 for Pedestals & RB cum 39.610 39.610
Item no 3 Steel (Substructure) ton 55.289 55.289
Item no 5 Backfilling - Granular Material cum 187.200 187.200
Item no 8 Elastomeric Bearing cc 207840.000 207840.000
Item no 9 POT cum PTFE Bearing ton 9600.000 9600.000
C. Super Structure
Item no 1(a) R.C.C M30 (Superstructure) upto 5m cum 58.800 58.800
Item no 1(d) R.C.C M40(Superstructure) upto 5m cum 288.670 288.670
Item no 1(e) P.S.C M45(Superstructure) upto 5m cum 545.370 545.370
Item no 2(a) Steel (Superstructure) ton 133.926 133.926
Item no 2(b) PSC Steel ton 28.000 28.000
Item no 3(a) Bituminous Concrete Wearing Coat(40mm) cum 52.260 52.260
Item no 3(b) Mastic Asphalt (12mm) sqm 1306.440 1306.440
Item no 3(c) Tack Coat sqm 1306.440 1306.440
Item no 5 Crash Barrier metre 275.040 275.040
Item no 6 Drainage Spout each 20.000 20.000
Item no 7 Reciever pipe for Drainage Spout m 180.000 180.000
Item no 8 PCC below approach slab cum 7.880 7.880
Item no 10 Strip Seal Expansion Joint metre 63.000 63.000
(i) copper plate metre 42.000 42.000
(ii) fibre board metre 42.000 42.000
(iii) 20mm thick premoulded joint filler metre 42.000 42.000
(iv) joint sealing compound metre 42.000 42.000
E. MISCELLANNEOUS
Item no 1a Painting sqm 607.840 607.840
Item no 2 Citizen Information Board NH project no 2.000 2.000
Brick foundation cum 68.250 68.250
QUANTITY CALCULATION OF BRIDGE AT CH._67.556 KM ON BILASIPURA-GUWAHATI STRETCH
BHARATMALA IN THE STATE OF ASSAM

2 No. X 30 M SPAN CH._67.556 KM


Item Sl No. Description Unit nos. Length Breadth (m) Height Quantity
(m) (m)

FOUNDATION
1 Excavation upto 3m depth
Abutment-1 & 1A cum 2 9.70 6.10 2.77 327.80
Pier-1 & 1A cum 2 9.70 9.70 2.72 511.85
Abutment-2 & 2A cum 2 9.70 6.10 2.11 249.70
Total 1089.35

2 Pile cap RCC M30


Abutment cum 4 8.70 5.100 1.80 319.46
Pier cum 2 8.70 8.700 1.80 272.48
Total= 591.94

3 Bored Cast-in-situ Pile M35 (dia.=1.2m)


Abutment-1 & 1A m 12 29.000 348.00
Pier-1 & 1A m 18 25.000 450.00
Abutment-2 & 2A m 12 29.000 348.00
Total= 1146.00

4 PCC M-15 levelling course


Below Pile-cap for Abutment cum 4 9.00 5.40 0.15 29.16
Below Pile-cap for Pier cum 2 9.00 9.00 0.15 24.30
Below brick foundation cum 4 10.50 2.300 0.15 14.49
Total= 67.95

5 HYSD Bars
90kg/cum for pile cap & @ 120kg/m
T Total= 190.795
for pile

6 Brick foundation
Solid Slab cum 4 10.50 1.625 68.250
Total 68.250

SUBSTRUCTURE
7 RCC M-30 upto 5.0m height
Abutment wall (straight portion) cum 4 5.20 1.200 5.000 124.80
Pier shaft (straight portion) cum 2 5.20 1.000 4.600 47.84
Pier shaft (semi circular portion) cum 4 0.39 4.600 7.18
Pier cap(Trapezoidal Portion) cum 2 8.80 2.200 0.400 15.49
Total= 195.31

8 RCC M-30 height above 5.0m upto 10.0m


Abutment wall (straight portion) cum 4 5.20 1.200 4.400 109.82
Abutment cap (Trapizoidal portion) cum 4 9.85 2.120 0.600 50.12
Pier cap(Rectangular portion) cum 2 11.40 3.400 0.700 54.26
Pier cap(Trapizoidal portion) cum 2 8.80 2.200 0.300 11.62
Total= 225.820

9 RCC M-30 height above 10.0m


Abutment cap (Rectangular portion) cum 4 11.40 2.120 0.700 67.67
Abutment cap (Trapizoidal portion) cum 4 9.85 2.120 0.100 8.35
Dirt Wall cum 4 11.40 0.40 2.389 43.58
Bracket cum 4 11.40 0.277 12.63
Total= 132.230
QUANTITY CALCULATION OF BRIDGE AT CH._67.556 KM ON BILASIPURA-GUWAHATI STRETCH
BHARATMALA IN THE STATE OF ASSAM

2 No. X 30 M SPAN CH._67.556 KM


Item Sl No. Description Unit nos. Length Breadth (m) Height Quantity
(m) (m)
10 RCC M-35 for Pedestal & Seismic Arrestor Blocks height above 5.0m
cum 8 0.80 0.80 0.150 0.77
cum 8 0.80 0.80 0.215 1.10
Pedestal at Abutment & Pier
cum 8 0.80 0.80 0.280 1.43
cum 8 0.80 0.80 0.345 1.77
Total= 5.07
Block RB2 cum 16 0.740 0.550 1.400 9.12
Block RB1 cum 16 0.800 1.299 16.63
Block RB3 cum 8 1.060 0.740 1.400 8.79
Total= 39.61

11 HYSD Bars
@ 120 kg/cum T 55.289
Total= 55.289

12 Backfilling - Granular Material


In Foundation trench (for Abutment) cum 4 14.80 1.950 115.44
In Foundation trench (for pier) cum 2 18.40 1.950 71.76
Total 187.20

13 POT & POT cum PTFE Bearing


ton 32 300.00 9600.00
Total 9600.00

14 Elastomeric Bearing
Bearing B2 cucm 16 35.00 42.50 4.80 114240
Bearing B3 cucm 32 25.00 30.00 3.90 93600
Total 207840
SUPERSTRUCTURE

15 PSC M-45 Girder portion


Long Girder middle portion cum 4 21.600 3.840 331.78

Long Girder straight portion cum 8 1.950 6.288 98.09

Long Girder varying portion cum 8 1.600 5.064 64.82

End Cross Girder (portion in between


cum 8 0.400 7.599 24.32
the long girder)

End Cross Girder (trapezoidal part) cum 8 0.400 0.516 1.65


Intermediate Cross Girder (portion in
cum 8 0.300 9.435 22.64
between the long girder)
Intermediate Cross Girder
cum 8 0.300 0.864 2.07
(trapezoidal part)
Total 545.37

16 R.C.C. Deck slab (M40)


Deck Slab cum 4 28.20 10.50 0.225 266.49
Cantilever portion of Deck Slab cum 8 0.880 10.50 0.300 22.18
Total 288.67

17 PSC Steel
@7 ton/span TON 4 7.00 28.00
Total 28.00
QUANTITY CALCULATION OF BRIDGE AT CH._67.556 KM ON BILASIPURA-GUWAHATI STRETCH
BHARATMALA IN THE STATE OF ASSAM

2 No. X 30 M SPAN CH._67.556 KM


Item Sl No. Description Unit nos. Length Breadth (m) Height Quantity
(m) (m)
18 Superstructure Steel (HYSD Bars)
@ 150 kg/cum TON 133.926
Total= 133.926

19 RCC M40 Crash Barrier


m 4 68.76 275.04
Total= 275.04

20 Drainage Spout nos. 20 Total 20.00

21 Reciever Pipe
m 4 45.00 180.00
Total 180.00

22 M15 PCC below Solid Slab


cum 4 1.250 10.500 0.15 7.88
Total 7.88

23 Solid Slab(M30)
Solid Slab cum 4 4.000 10.500 0.350 58.80
Total 58.80

24 Bituminous concrete wearing course


cum 2 68.76 9.50 0.040 52.26
Total= 52.26

25 Mastic asphalt
sqm 2 68.76 9.50 1306.44
Total= 1306.44

26 Tack coat
sqm 2 68.76 9.50 1306.44
Total= 1306.44

27 Filler joint
Providing & fixing 2 mm thick
corrugated copper plate in expansion m 4 10.50 42.00
joint
Providing & fixing 20 mm thick
compressible fibre board in m 4 10.50 42.00
expansion joint
Providing and fixing in position 20
m 4 10.50 42.00
mm thick premoulded joint filler
Providing and filling joint sealing
m 4 10.50 42.00
compound

28 Strip Seal Expansion Joint


m 6 10.500 63.00
Total 63.00

MISCELLANEOUS
29 Painting
Crash Barrier sqm 4 2.210 68.76 607.84
Total 607.840

30 Citizen information Board NH Project no Total 2.000


Culvert
JOB NO : 4146 (PACKAGE-5)
Summary sheet of Culverts (Quantities & amount)
TYPE 1 2 3 4 5 6 7

TW-41.0M TW-18.50 M
TW-24.5M FA TW-24.5 M TW-24 M TW-24.5 M TW-26.0 M FA & NC
Span (m) x FA NC FA FA & NC FA & NC FA & NC EC upto 3m
Height (m) = NC With Service SE EC upto 3m EC upto 3m EC upto 3m With Service Road
2x2x1cell Road 2x2x1cell 2x2x1cell 2x2x1cell 2x2x1cell (in RE Wall)
2x2x1cell 2x2x1cell

No. of Culverts = 18 1 1 1 20 1 1
ITEM NO. Description Unit QUANTITY QUANTITY QUANTITY QUANTITY QUANTITY QUANTITY QUANTITY
A. Foundation
Item no 1(a) Excavation (upto 3 m depth) cum 236.51 276.030 275.59 146.74 151.68 144.04 83.43
Item no 2 P.C.C (M-15) cum 18.58 27.144 17.87 25.05 26.03 24.51 13.28
B. SubStructure
Item no 1(a) R.C.C M30 (Substructure) upto 5m cum 71.79 107.159 78.00 95.17 98.97 93.10 53.10
Item no 3 Steel (Substructure) ton 5.03 7.501 5.46 6.66 6.93 6.52 3.72
Item no 4 Weep Holes each 152.00 180.000 152.00 238.00 248.00 228.00 124.00
Item no 5 Backfilling - Granular Material cum 24.17 28.425 14.25 12.83 12.83 12.83 9.19
Item no 6 Backfilling - Sandy Material cum 92.49 104.081 62.19 62.20
Item no 7 Filter Media cum 69.02 118.119 78.23 123.08 128.53 120.11 56.92
TYPE 1 2 3 4 5 6 7

TW-41.0M TW-18.50 M
TW-24.5M FA TW-24.5 M TW-24 M TW-24.5 M TW-26.0 M FA & NC
Span (m) x FA NC FA FA & NC FA & NC FA & NC EC upto 3m
Height (m) = NC With Service SE EC upto 3m EC upto 3m EC upto 3m With Service Road
2x2x1cell Road 2x2x1cell 2x2x1cell 2x2x1cell 2x2x1cell (in RE Wall)
2x2x1cell 2x2x1cell

No. of Culverts = 18 1 1 1 20 1 1
ITEM NO. Description Unit QUANTITY QUANTITY QUANTITY QUANTITY QUANTITY QUANTITY QUANTITY
C. Super Structure
Item no 1(a) R.C.C M30 (Superstructure) upto 5m cum 22.48 37.618 22.48 24.18 25.39 23.52 11.98
Item no 2 Steel (Superstructure) ton 1.69 2.821 1.69 1.81 1.90 1.76 0.90
Item no 3(a) Bituminous Concrete Wearing Coat(40mm) cum 8.36 12.920 8.36 2.66
Item no 3(b) Mastic Asphalt (12mm) sqm 209.00 323.000 209.00 66.50
Item no 3(c) Tack Coat sqm 209.00 323.000 209.00 66.50
Item no 4 Crash Barrier metre 38.00 76.000 38.00 19.00
Item no 5 Drainage Spout each 4.00 8.000 4.00 2.00
Item no 6 PCC below approach slab cum 23.62 40.804 24.16 7.85
Item no 7 R.C.C. Approach Slab with steel cum 49.06 84.756 50.19 16.30
Item no 8 Filler Joint
(i) copper plate metre 46.72 82.000 49.00 16.00
(ii) fibre board metre 46.72 82.000 49.00 16.00
(iii) 20mm thick premoulded joint filler metre 46.72 82.000 49.00 16.00
(iv) joint sealing compound metre 46.72 82.000 49.00 16.00
D. Protection Work
300 mm thick Rubble stone flooring laid over 100mm thick
Item no 1 cum
cement concrete bedding
Item no 2 750 mm thick Flexible apron cum 57.12 58.275 43.125 57.315 57.32 57.32 60.05
Item no 3 Curtain Wall- PCC (M-20) cum 58.92 59.598 48.75 58.92 58.92 58.92 61.40
Item no 4 PCC M15 cum 8.70 8.801 7.19 8.70 8.70 8.70 9.03
Item no 5 Excavation cum 278.72 288.366 263.89 280.13 280.13 280.13 282.43
E. Miscellaneous
Item no 1 Painting sqm 99.18 198.36 99.18 4.25 4.25 4.25 49.59
JOB NO : 4146 (PACKAGE-5)
Summary sheet of Culverts (Quantities & amount)
TYPE 8 9 10 11 12 13 14

TW-40.00 M
FA & NC TW-24.5 M TW-24.5M TW-41M TW-24.5 M TW-24.5 M TW-24.5 M Total Quantity
Span (m) x EC upto 4m FA & SE FA FA FA F&R A FA & NC
Height (m) = With Service Road EC upto 3m NC NC SE SE EC upto 5m
(in RE Wall) 2x2x1cell 2x3x1cell 2x3x1cell 2x3x1cell 2x3x1cell 2x3x1cell
2x2x1cell

No. of Culverts = 1 3 10 1 3 1 4 66
ITEM NO. Description Unit QUANTITY QUANTITY QUANTITY QUANTITY QUANTITY QUANTITY QUANTITY
A. Foundation
Item no 1(a) Excavation (upto 3 m depth) cum 160.41 142.28 247.79 339.18 438.97 467.58 253.48 14419.358
Item no 2 P.C.C (M-15) cum 27.60 25.03 23.05 31.81 25.75 25.75 42.18 1599.766
B. SubStructure
Item no 1(a) R.C.C M30 (Substructure) upto 5m cum 107.51 95.78 109.73 158.83 128.66 130.96 221.75 6753.069
Item no 3 Steel (Substructure) ton 7.53 6.70 7.68 11.12 9.01 9.17 15.52 472.715
Item no 4 Weep Holes each 258.00 276.00 210.00 300.00 210.00 210.00 310.00 14184.000
Item no 5 Backfilling - Granular Material cum 12.83 10.03 17.69 22.97 32.18 32.18 19.54 1218.757
Item no 6 Backfilling - Sandy Material cum 116.29 233.00 428.22 236.58 245.94 5723.432
Item no 7 Filter Media cum 121.95 123.95 115.69 179.77 121.79 126.47 226.51 7537.715
TYPE 8 9 10 11 12 13 14

TW-40.00 M
FA & NC TW-24.5 M TW-24.5M TW-41M TW-24.5 M TW-24.5 M TW-24.5 M Total Quantity
Span (m) x EC upto 4m FA & SE FA FA FA F&R A FA & NC
Height (m) = With Service Road EC upto 3m NC NC SE SE EC upto 5m
(in RE Wall) 2x2x1cell 2x3x1cell 2x3x1cell 2x3x1cell 2x3x1cell 2x3x1cell
2x2x1cell

No. of Culverts = 1 3 10 1 3 1 4 66
ITEM NO. Description Unit QUANTITY QUANTITY QUANTITY QUANTITY QUANTITY QUANTITY QUANTITY
C. Super Structure
Item no 1(a) R.C.C M30 (Superstructure) upto 5m cum 25.90 24.37 23.97 40.11 23.97 23.97 41.85 1674.245
Item no 2 Steel (Superstructure) ton 1.94 1.83 1.80 3.01 1.80 1.80 3.14 125.568
Item no 3(a) Bituminous Concrete Wearing Coat(40mm) cum 5.32 8.40 14.12 8.40 8.40 311.392
Item no 3(b) Mastic Asphalt (12mm) sqm 133.00 209.88 352.98 209.88 209.88 7784.800
Item no 3(c) Tack Coat sqm 133.00 209.88 352.98 209.88 209.88 7784.800
Item no 4 Crash Barrier metre 38.00 38.16 38.16 38.16 38.16 1427.400
Item no 5 Drainage Spout each 4.00 4.00 4.00 4.00 4.00 150.000
Item no 6 PCC below approach slab cum 32.59 24.16 40.84 23.62 23.62 907.451
Item no 7 R.C.C. Approach Slab with steel cum 32.59 50.19 84.84 49.06 49.06 1849.806
Item no 8 Filler Joint
(i) copper plate metre 32.00 49.00 82.00 46.72 46.72 1778.840
(ii) fibre board metre 32.00 49.00 82.00 46.72 46.72 1778.840
(iii) 20mm thick premoulded joint filler metre 32.00 49.00 82.00 46.72 46.72 1778.840
(iv) joint sealing compound metre 32.00 49.00 82.00 46.72 46.72 1778.840
D. Protection Work
300 mm thick Rubble stone flooring laid over 100mm thick
Item no 1 cum 27.17 27.168
cement concrete bedding
Item no 2 750 mm thick Flexible apron cum 57.32 56.34 66.795 66.795 60.195 41.6475 71.505 3919.868
Item no 3 Curtain Wall- PCC (M-20) cum 58.92 58.92 68.55 68.55 61.77 57.95 66.58 4025.831
Item no 4 PCC M15 cum 8.70 8.70 9.62 9.62 9.12 8.57 9.84 588.966
Item no 5 Excavation cum 278.19 278.96 320.85 320.85 311.07 358.31 332.02 19278.573
E. Miscellaneous
Item no 1 Painting sqm 99.18 4.25 99.60 99.60 99.60 99.60 4.69 3850.532
ESTIMATE OF QUANTITY OF BOX CULVERT

Box Size:- 1 cell of 2 m x 2 m


with Flexible Apron NC

Item No. Description Unit nos Length (m) Breadth (m) Height (m) Quantity

A. FOUNDATION
1 Excavation(up to 3m)
Box Bridge cum 1 4.500 25.500 1.367 156.863
Shear Key cum 2 4.500 1.800 0.900 14.580
Return Wall-II cum 4 3.400 3.500 1.367 65.069
` Total 236.512

2 PCC-M15
Box Bridge cum 1 3.500 22.100 0.150 11.603
Shear Key cum 2 3.700 1.673 0.150 1.857
Return Wall-II cum 4 3.050 2.800 0.150 5.124
Total 18.583

B. SUBSTRUCTURE
3 RCC-M30 (upto 5m)
Bottom Slab cum 1 3.500 24.500 0.300 25.725
Box Side Wall cum 2 24.500 0.250 2.138 26.184
Base slab of return wall II cum 4 2.900 2.500 0.250 7.250
Return wall I cum 4 0.500 0.300 2.250 1.350
Return wall II cum 4 2.900 0.225 2.300 6.003
Shear key cum 2 3.500 0.675 4.725
Haunch cum 2 24.500 0.011 0.551
Total= 71.789

4 Substructure Steel (HYSD Bars)


70 kg/cum of Concrete ton 1 5.025 5.025
Total 5.025

5 Weep holes
Spacing for weep holes = 2 m in horizontal and 1 m in vertical direction
No of weep holes in horizontal direction per side wall =23.9/2+1 = 13
No of weep holes in vertical direction per side wall =2.1/1+1 = 4
No of weep holes in horizontal direction per return wall =3.4/2+1 = 3
No of weep holes in vertical direction per return wall =2.3/1 +1= 4
Total no of Weep holes per side wall= 13 x 4 52
Total no of Weep holes per return wall = 3 x 4 12
Total no of weep holes = 52 x 2 + 12 x 4 152

6 Backfilling - Granular Material


Box cum 1 29.000 0.450 13.050
Shear key cum 2 1.750 1.050 3.675
Return Wall-II cum 4 4.650 0.400 7.440
Total 24.165

7 Backfilling - Sandy Material


Behind the side wall and return
cum 2 23.900 3.400 0.994 161.504
wall
Deduct for the filter media cum 69.019
Total 92.485

8 Filter media
Behind Abutment cum 2 23.900 0.600 1.938 55.568
Behind Return Wall cum 4 2.820 0.600 1.988 13.451
Total 69.019
ESTIMATE OF QUANTITY OF BOX CULVERT

Box Size:- 1 cell of 2 m x 2 m


with Flexible Apron NC

Item No. Description Unit nos Length (m) Breadth (m) Height (m) Quantity

C. SUPERSTRUCTURE

9 RCC-M30(up to 5m)
Box Bridge cum 1 2.500 24.500 0.250 15.313
(+)Haunch cum 2 24.500 0.011 0.551
Rectangular part of bracket cum 2 24.500 0.300 0.300 4.410
Triangular part of bracket cum 2 24.500 0.045 2.205
Total 22.479

10 Superstructure Steel (HYSD Bars)


75 kg/cum of concrete ton 1 1.686 1.686
Total 1.686

11 Bituminous Concrete Wearing Coat(40mm)


cum 1 9.500 22.000 0.040 8.360
Total 8.360

12 Mastic Asphalt
sqm 1 9.500 22.000 209.000
Total 209.000

13 Tack Coat
sqm 1 9.500 22.000 209.000
Total 209.000

14 Crash Barrier R.C.C. M40 m 4 9.500 38.000


Total 38.000

15 Drainage Spout nos. 4 4

16 PCC below Approach Slab


cum 2 3.370 23.360 0.150 23.617
Total 23.617

17 Approach Slab
cum 2 3.500 23.360 0.300 49.056
Total 49.056

18 Filler Joint
(i) copper plate m 2 23.360 46.720
(ii) fibar board m 2 23.360 46.720
(iii) 20mm thick premoulded
m 2 23.360 46.720
joint filler
(iv) joint sealing compound m 2 23.360 46.720
ESTIMATE OF QUANTITY OF BOX CULVERT

Box Size:- 1 cell of 2 m x 2 m


with Flexible Apron NC

Item No. Description Unit nos Length (m) Breadth (m) Height (m) Quantity

19 750 mm thick Flexible apron


Upstream cum 1 9.300 3.000 0.750 20.925
Downstream cum 1 9.300 6.000 0.750 41.850
Deduction due to return wall ll
4 2.900 0.650 0.750 5.655
foundation
Total 57.120

20 Curtain Wall- PCC (M-20)


Downstream side cum 1 21.300 1.910 40.683
Upstream side cum 1 15.300 1.480 22.644
Deduction due to return wall ll
cum 2 0.650 1.910 2.483
foundation (D/S)
Deduction due to return wall ll
cum 2 0.650 1.480 1.924
foundation (U/S)
Total 58.920

21 Excavation in Soil
Curtain Wall (downstream) cum 1 21.300 2.850 2.650 160.868
Curtain Wall (upstream) cum 1 15.300 2.500 2.150 82.238
Flexible appron(downstream) cum 1 8.300 2.000 0.750 12.450
Flexible appron(upstream) cum 1 8.300 5.000 0.750 31.125
Deduction due to return wall ll
cum 4 3.400 0.650 0.900 7.956
foundation
Total 278.725

22 PCC (M-15)
Below Curtain Wall
Downstream side cum 1 21.300 1.850 0.150 5.911
Upstream side 1 15.300 1.500 0.150 3.443
Deduction due to return wall ll
cum 4 0.650 1.675 0.150 0.653
foundation
Total 8.700

E. MISCELLANEOUS WORK

23 Painting
Crash Barrier sqm 4 9.50 2.610 99.18
Total 99.18
QUANTITY ESTIMATE OF BOX CULVERT

Box Size:- 1 cell of 2 m x 2 m


with Flexible Apron
With Service road_NC
Item No. Description Unit nos Length (m) Breadth (m) Height (m) Quantity

A. FOUNDATION
1.(a) Excavation(up to 3m)
Box Bridge cum 1 4.500 42.000 0.950 179.550
Shear Key cum 2 4.500 1.800 0.900 14.580
Return Wall-II (Service Road) cum 4 3.000 3.500 1.950 81.900
` Total 276.030

2 PCC-M15
Box Bridge cum 1 3.500 38.600 0.150 20.265
Shear Key cum 2 3.700 1.673 0.150 1.857
Return Wall-II (Service Road) cum 4 3.100 2.700 0.150 5.022
Total 27.144

B. SUBSTRUCTURE
3 RCC-M30 (upto 5m)
Bottom Slab cum 1 3.500 41.000 0.300 43.050
Box Side Wall (Main structure) cum 2 24.000 0.250 2.306 27.675
Box Side Wall (Service Road) cum 2 17.000 0.250 2.094 17.797
Return wall I (Service Road) cum 4 0.500 0.300 2.250 1.350
Base slab of return wall II(Service
cum 4 3.000 2.500 0.250 7.500
Road)
Return wall II (Service Road) cum 4 2.000 0.225 2.300 4.140
Shear key cum 2 3.500 0.675 4.725
Haunch cum 2 41.000 0.011 0.923
Total= 107.159

4 Substructure Steel (HYSD Bars)


70 kg/cum of Concrete ton 1 7.501 7.501
Total 7.501

5 Weep holes
Spacing for weep holes = 2 m in horizontal and 1 m in vertical direction
No of weep holes in horizontal direction per side wall =40.4/2+1 = 22
No of weep holes in vertical direction per side wall =1.9/1+1 = 3
No of weep holes in horizontal direction per return wall (service road) =3.5/2+1 = 3
No of weep holes in vertical direction per return wall (service road) =2.3/1 +1= 4
Total no of Weep holes per side wall = 22 x 3 66
Total no of Weep holes per return wall (service road) = 3 x 4 12
Total no of weep holes = 66 x 2 + 12 x 4 180

6 Backfilling - Granular Material


Box cum 1 45.500 0.450 20.475
Shear key cum 2 1.750 0.900 3.150
At Return wall II (Service Road) cum 4 3.000 0.400 4.800
Total 28.425

7 Backfilling - Sandy Material


Behind the side wall and return
cum 2 40.40 2.500 1.100 222.200
wall
Deduct for the filter media cum -118.119
Total 104.081

8 Filter media
Behind side wall cum 2 40.400 0.600 2.106 102.111
Behind Return Wall cum 4 2.900 0.600 2.300 16.008
Total 118.119
QUANTITY ESTIMATE OF BOX CULVERT

Box Size:- 1 cell of 2 m x 2 m


with Flexible Apron
With Service road_NC
Item No. Description Unit nos Length (m) Breadth (m) Height (m) Quantity

C. SUPERSTRUCTURE

9 RCC-M30(up to 5m)
Box Bridge cum 1 2.500 41.000 0.250 25.625
Rectangular part of bracket cum 2 41.000 0.300 0.300 7.380
Triangular part of bracket cum 2 41.000 0.045 3.690
(+)Haunch cum 2 41.000 0.011 0.923
Total 37.618

10 Superstructure Steel (HYSD Bars)


75 kg/cum of concrete ton 1 2.821 2.821
Total 2.821

11 Bituminous concrete wearing course


For Main structure cum 2 9.500 9.500 0.040 7.220
For Service Road cum 2 9.500 7.500 0.040 5.700
Total 12.920

12 Mastic Asphalt
For Main structure sqm 2 9.500 9.500 180.500
For Service Road sqm 2 9.500 7.500 142.500
Total 323.000

13 Tack Coat
For Main structure sqm 2 9.500 9.500 180.500
For Service Road sqm 2 9.500 7.500 142.500
Total 323.000

14 Crash Barrier R.C.C. M40 m 8 9.500 76.000


Total 76.000

15 Drainage Spout nos. 8 8

16 PCC below Approach Slab


cum 2 3.370 40.360 0.150 40.804
Total 40.804

17 Approach Slab
cum 2 3.500 40.360 0.300 84.756
Total 84.756

18 Filler Joint
(i) copper plate m 2 41.000 82.000
(ii) fibar board m 2 41.000 82.000
(iii) 20mm thick premoulded
m 2 41.000 82.000
joint filler
(iv) joint sealing compound m 2 41.000 82.000
QUANTITY ESTIMATE OF BOX CULVERT

Box Size:- 1 cell of 2 m x 2 m


with Flexible Apron
With Service road_NC
Item No. Description Unit nos Length (m) Breadth (m) Height (m) Quantity

D. PROTECTION WORK
19 750 mm thick Flexible appron
Upstream cum 1 9.500 3.000 0.750 21.375
Downstream cum 1 9.500 6.000 0.750 42.750
Deduction for Return wall 2 cum 4 3.000 0.650 0.750 -5.850
Total 58.275

20 Curtain Wall- PCC (M-20)


Downstream side cum 1 20.200 1.910 38.582
Upstream side cum 1 14.200 1.480 21.016
Total 59.598

21 Excavation in Soil
Curtain Wall (downstream) cum 1 21.500 2.850 2.650 162.379
Curtain Wall (upstream) cum 1 15.500 2.500 2.150 83.313
Flexible apron(downstream) cum 1 8.500 2.000 0.750 12.750
Flexible apron(upstream) cum 1 8.500 5.000 0.750 31.875
Deduction for Return wall 2 cum 4 3.000 0.650 0.250 -1.950
Total 288.366

22 PCC (M-15)
Below Curtain Wall
Downstream side cum 1 20.200 1.850 0.150 5.606
Upstream side cum 1 14.200 1.500 0.150 3.195
Total 8.801

E. MISCELLANEOUS WORK

23 Painting
Crash Barrier sqm 8 9.50 2.610 198.36
Total 198.36
ESTIMATE OF QUANTITY OF BOX CULVERT

Box Size:- 1 cell of 2 m x 2 m


with Flexible Apron
with SE
Item No. Description Unit nos Length (m) Breadth (m) Height (m) Quantity

A. FOUNDATION
1 Excavation(up to 3m)
Box Bridge cum 1 4.500 25.500 1.750 200.813
Shear Key cum 2 4.500 1.800 0.900 14.580
Return Wall-II cum 4 2.000 4.300 1.750 60.200
` Total 275.593

2 PCC-M15
Box Bridge cum 1 3.500 22.100 0.150 11.603
Shear Key cum 2 3.700 1.673 0.150 1.857
Return Wall-II cum 4 2.100 3.500 0.150 4.410
Total 17.869

B. SUBSTRUCTURE
3 RCC-M30 (upto 5m)
Bottom Slab cum 1 3.500 24.500 0.300 25.725
Box Side Wall cum 2 24.500 0.250 2.550 31.238
Base slab of return wall II cum 4 2.000 3.300 0.300 7.920
Return wall I cum 4 0.500 0.300 2.800 1.680
Return wall II cum 4 2.000 0.275 2.800 6.160
Shear key cum 2 3.500 0.675 4.725
Haunch cum 2 24.500 0.011 0.551
Total= 77.999

4 Substructure Steel (HYSD Bars)


70 kg/cum of Concrete ton 1 5.460 5.460
Total 5.460

5 Weep holes
Spacing for weep holes = 2 m in horizontal and 1 m in vertical direction
No of weep holes in horizontal direction per side wall =23.9/2+1 = 13
No of weep holes in vertical direction per side wall=2.8/1+1 = 4
No of weep holes in horizontal direction per return wall =3/2+1 = 3
No of weep holes in vertical direction per return wall =2.8/1 +1= 4
Total no of Weep holes per side wall = 13 x 4 52
Total no of Weep holes per return wall = 3 x 4 12
Total no of weep holes = 52 x 2 + 12 x 4 152

6 Backfilling - Granular Material


Box cum 1 29.000 0.300 8.700
Shear key cum 2 1.750 0.900 3.150
Return Wall-II cum 4 2.000 0.300 2.400
Total 14.250

7 Backfilling - Sandy Material


Behind the side wall and return
cum 2 23.90 2.500 1.175 140.413
wall
Deduct for the filter media cum 78.227
Total 62.186

8 Filter media
Behind Abutment cum 2 23.900 0.600 2.350 67.398
Behind Return Wall cum 4 1.920 0.600 2.350 10.829
Total 78.227
ESTIMATE OF QUANTITY OF BOX CULVERT

Box Size:- 1 cell of 2 m x 2 m


with Flexible Apron
with SE
Item No. Description Unit nos Length (m) Breadth (m) Height (m) Quantity

C. SUPERSTRUCTURE

9 RCC-M30(up to 5m)
Box Bridge cum 1 2.500 24.500 0.250 15.313
(+)Haunch cum 2 24.500 0.011 0.551
Rectangular part of bracket cum 2 24.500 0.300 0.300 4.410
Triangular part of bracket cum 2 24.500 0.045 2.205
Total 22.479

10 Superstructure Steel (HYSD Bars)


75 kg/cum of concrete ton 1 1.686 1.686
Total 1.686

11 Bituminous conceret wearing course


cum 1 9.500 22.000 0.040 8.360
Total 8.360

12 Mastic Asphalt
sqm 1 9.500 22.000 209.000
Total 209.000

13 Tack Coat
sqm 1 9.500 22.000 209.000
Total 209.000

14 Crash Barrier R.C.C. M40 m 4 9.500 38.000


Total 38.000

15 Drainage Spout nos. 4 4

16 PCC below Approach Slab


cum 2 3.370 23.900 0.150 24.163
Total 24.163

17 Approach Slab
cum 2 3.500 23.900 0.300 50.190
Total 50.190

18 Filler Joint
(i) copper plate m 2 24.500 49.000
(ii) fibar board m 2 24.500 49.000
(iii) 20mm thick premoulded
m 2 24.500 49.000
joint filler
(iv) joint sealing compound m 2 24.500 49.000
ESTIMATE OF QUANTITY OF BOX CULVERT

Box Size:- 1 cell of 2 m x 2 m


with Flexible Apron
with SE
Item No. Description Unit nos Length (m) Breadth (m) Height (m) Quantity

D. PROTECTION WORK

750 mm thick Flexible appron


19 Upstream cum 1 7.500 3.000 0.750 16.875
Downstream cum 1 7.500 6.000 0.750 33.750
Deduction for Return wall cum 4 2.000 1.250 0.750 -7.500
Total 43.125

Curtain Wall- PCC (M-20)


20 Downstream side cum 1 19.500 1.910 37.245
Upstream side cum 1 13.500 1.480 19.980
Deduction due to return wall ll
cum 2 1.250 1.910 4.775
foundation (D/S)
Deduction due to return wall ll
cum 2 1.250 1.480 3.700
foundation (U/S)
Total 48.750

21 Excavation in Soil
Curtain Wall (downstream) cum 1 20.500 2.850 2.650 154.826
Curtain Wall (upstream) cum 1 14.500 2.500 2.150 77.938
Flexible appron(downstream) cum 1 6.500 2.000 0.750 9.750
Flexible appron(upstream) cum 1 6.500 5.000 0.750 24.375
Deduction for Return wall cum 4 2.000 1.250 0.300 -3.000
Total 263.889

22 PCC (M-15)
Below Curtain Wall
Downstream side cum 1 19.500 1.850 0.150 5.411
Upstream side cum 1 13.500 1.500 0.150 3.038
Deduction due to return wall ll cum 4 1.250 1.675 0.150 1.256
Total 7.193

E. MISCELLANEOUS WORK

23 Painting
Crash Barrier sqm 4 9.50 2.610 99.18
Total 99.18
QUANTITY ESTIMATE OF BOX CULVERT

Box Size:- 1 cell of 2 m x 2 m


with Flexible Apron_EC

Item No. Description Unit nos Length (m) Breadth (m) Height (m) Quantity

A. FOUNDATION
1.(a) Excavation(up to 3m)
Box Bridge cum 1 3.700 36.072 0.750 100.100
Shear Key cum 2 3.700 1.800 0.900 11.988
Return Wall-II (Main structure) cum 4 3.300 3.500 0.750 34.650
` Total 146.738

2 PCC-M15
Box Bridge cum 1 3.700 32.672 0.150 18.133
Shear Key cum 2 3.900 1.673 0.150 1.957
Return Wall-II (Main structure) cum 4 2.950 2.800 0.150 4.956
Total 25.046

B. SUBSTRUCTURE
3 RCC-M30 (upto 5m)
Bottom Slab cum 1 3.700 35.072 0.300 38.930
Box Side Wall (Main structure) cum 2 35.072 0.250 2.000 35.072
Return wall I (Main structure) cum 4 0.600 0.300 2.550 1.836
Base slab of return wall II (Main
cum 4 2.800 2.500 0.250 7.000
structure)
Return wall II (Main structure) cum 4 2.800 0.225 2.600 6.552
Shear key cum 2 3.700 0.675 4.995
Haunch cum 2 35.072 0.011 0.789
Total= 95.174

4 Substructure Steel (HYSD Bars)


70 kg/cum of Concrete ton 1 6.662 6.662
Total 6.662

5 Weep holes
Spacing for weep holes = 2 m in horizontal and 1 m in vertical direction
No of weep holes in horizontal direction per side wall =34.5/2+1 = 19
No of weep holes in vertical direction per side wall =3.1/1+1 = 5
No of weep holes in horizontal direction per return wall (main str.)=3.4/2+1 = 3
No of weep holes in vertical direction per return wall (main str.)=2.6/1 +1= 4
Total no of Weep holes per side wall = 19 x 5 95
Total no of Weep holes per return wall (main str.) = 3 x 4 12
Total no of weep holes = 95 x 2 + 12 x 4 + 0 x 4 238

6 Backfilling - Granular Material


Box cum 1 3.700 0.450 1.665
Shear key cum 2 1.850 1.050 3.885
At Return wall II (Main structure) cum 4 4.550 0.400 7.280
Total 12.830

7 Filter media
Behind side wall cum 2 34.472 0.600 2.550 105.484
Behind Return Wall cum 4 2.820 0.600 2.600 17.597
Total 123.081
QUANTITY ESTIMATE OF BOX CULVERT

Box Size:- 1 cell of 2 m x 2 m


with Flexible Apron_EC

Item No. Description Unit nos Length (m) Breadth (m) Height (m) Quantity

C. SUPERSTRUCTURE

8 RCC-M30(up to 5m)
Box Bridge cum 1 2.500 35.072 0.263 23.016
Kerb over Top Slab cum 2 2.500 0.250 0.300 0.375
(+)Haunch cum 2 35.072 0.011 0.789
Total 24.180

9 Superstructure Steel (HYSD Bars)


75 kg/cum of concrete ton 1 1.814 1.814
Total 1.814

D. PROTECTION WORK
10 750 mm thick Flexible apron
Upstream cum 1 9.300 3.000 0.750 20.925
Downstream cum 1 9.300 6.000 0.750 41.850
Deduction for Return wall 2 cum 4 2.800 0.650 0.750 5.460
Total 57.315

11 Curtain Wall- PCC (M-20)


Downstream side cum 1 21.300 1.910 40.683
Upstream side cum 1 15.300 1.480 22.644
Deduction due to return wall ll
cum 2 0.650 1.910 2.483
foundation (D/S)
Deduction due to return wall ll
cum 2 0.650 1.480 1.924
foundation (U/S)
Total 58.920

12 Excavation in Soil
Curtain Wall (downstream) cum 1 21.300 2.850 2.650 160.868
Curtain Wall (upstream) cum 1 15.300 2.500 2.150 82.238
Flexible apron(downstream) cum 1 8.300 2.000 0.750 12.450
Flexible apron(upstream) cum 1 8.300 5.000 0.750 31.125
Deduction for Return wall 2 cum 4 2.800 0.650 0.900 6.552
Total 280.129

13 PCC (M-15)
Below Curtain Wall
Downstream side cum 1 21.300 1.850 0.150 5.911
Upstream side cum 1 15.300 1.500 0.150 3.443
Deduction due to return wall ll cum 4 0.650 1.675 0.150 0.653
Total 8.700

E. MISCELLANEOUS WORK

14 Painting
Kerb sqm 2 2.50 0.850 4.25
Total 4.250
QUANTITY ESTIMATE OF BOX CULVERT

Box Size:- 1 cell of 2 m x 2 m


with Flexible Apron_EC

Item No. Description Unit nos Length (m) Breadth (m) Height (m) Quantity

A. FOUNDATION
1.(a) Excavation(up to 3m)
Box Bridge cum 1 3.700 37.852 0.750 105.039
Shear Key cum 2 3.700 1.800 0.900 11.988
Return Wall-II (Main structure) cum 4 3.300 3.500 0.750 34.650
` Total 151.677

2 PCC-M15
Box Bridge cum 1 3.700 34.452 0.150 19.121
Shear Key cum 2 3.900 1.673 0.150 1.957
Return Wall-II (Main structure) cum 4 2.950 2.800 0.150 4.956
Total 26.034

B. SUBSTRUCTURE
3 RCC-M30 (upto 5m)
Bottom Slab cum 1 3.700 36.852 0.300 40.906
Box Side Wall (Main structure) cum 2 36.852 0.250 2.000 36.852
Return wall I (Main structure) cum 4 0.600 0.300 2.550 1.836
Base slab of return wall II (Main
cum 4 2.800 2.500 0.250 7.000
structure)
Return wall II (Main structure) cum 4 2.800 0.225 2.600 6.552
Shear key cum 2 3.700 0.675 4.995
Haunch cum 2 36.852 0.011 0.829
Total= 98.970

4 Substructure Steel (HYSD Bars)


70 kg/cum of Concrete ton 1 6.928 6.928
Total 6.928

5 Weep holes
Spacing for weep holes = 2 m in horizontal and 1 m in vertical direction
No of weep holes in horizontal direction per side wall =36.3/2+1 = 20
No of weep holes in vertical direction per side wall =3.1/1+1 = 5
No of weep holes in horizontal direction per return wall (main str.)=3.4/2+1 = 3
No of weep holes in vertical direction per return wall (main str.)=2.6/1 +1= 4
Total no of Weep holes per side wall = 20 x 5 100
Total no of Weep holes per return wall (main str.) = 3 x 4 12
Total no of weep holes = 100 x 2 + 12 x 4 + 0 x 4 248

6 Backfilling - Granular Material


Box cum 1 3.700 0.450 1.665
Shear key cum 2 1.850 1.050 3.885
At Return wall II (Main structure) cum 4 4.550 0.400 7.280
Total 12.830

7 Filter media
Behind side wall cum 2 36.252 0.600 2.550 110.931
Behind Return Wall cum 4 2.820 0.600 2.600 17.597
Total 128.528
QUANTITY ESTIMATE OF BOX CULVERT

Box Size:- 1 cell of 2 m x 2 m


with Flexible Apron_EC

Item No. Description Unit nos Length (m) Breadth (m) Height (m) Quantity

C. SUPERSTRUCTURE

8 RCC-M30(up to 5m)
Box Bridge cum 1 2.500 36.852 0.263 24.184
Kerb over Top Slab cum 2 2.500 0.250 0.300 0.375
(+)Haunch cum 2 36.852 0.011 0.829
Total 25.388

9 Superstructure Steel (HYSD Bars)


75 kg/cum of concrete ton 1 1.904 1.904
Total 1.904

D. PROTECTION WORK
10 750 mm thick Flexible apron
Upstream cum 1 9.300 3.000 0.750 20.925
Downstream cum 1 9.300 6.000 0.750 41.850
Deduction for Return wall 2 cum 4 2.800 0.650 0.750 5.460
Total 57.315

11 Curtain Wall- PCC (M-20)


Downstream side cum 1 21.300 1.910 40.683
Upstream side cum 1 15.300 1.480 22.644
Deduction due to return wall ll
cum 2 0.650 1.910 2.483
foundation (D/S)
Deduction due to return wall ll
cum 2 0.650 1.480 1.924
foundation (U/S)
Total 58.920

12 Excavation in Soil
Curtain Wall (downstream) cum 1 21.300 2.850 2.650 160.868
Curtain Wall (upstream) cum 1 15.300 2.500 2.150 82.238
Flexible apron(downstream) cum 1 8.300 2.000 0.750 12.450
Flexible apron(upstream) cum 1 8.300 5.000 0.750 31.125
Deduction for Return wall 2 cum 4 2.800 0.650 0.900 6.552
Total 280.129

13 PCC (M-15)
Below Curtain Wall
Downstream side cum 1 21.300 1.850 0.150 5.911
Upstream side cum 1 15.300 1.500 0.150 3.443
Deduction due to return wall ll cum 4 0.650 1.675 0.150 0.653
Total 8.700

E. MISCELLANEOUS WORK

14 Painting
Kerb sqm 2 2.50 0.850 4.25
Total 4.250
QUANTITY ESTIMATE OF BOX CULVERT

Box Size:- 1 cell of 2 m x 2 m


with Flexible Apron_EC

Item No. Description Unit nos Length (m) Breadth (m) Height (m) Quantity

A. FOUNDATION
1.(a) Excavation(up to 3m)
Box Bridge cum 1 3.700 35.100 0.750 97.402
Shear Key cum 2 3.700 1.800 0.900 11.988
Return Wall-II (Main structure) cum 4 3.300 3.500 0.750 34.650
` Total 144.041

2 PCC-M15
Box Bridge cum 1 3.700 31.700 0.150 17.594
Shear Key cum 2 3.900 1.673 0.150 1.957
Return Wall-II (Main structure) cum 4 2.950 2.800 0.150 4.956
Total 24.507

B. SUBSTRUCTURE
3 RCC-M30 (upto 5m)
Bottom Slab cum 1 3.700 34.100 0.300 37.851
Box Side Wall (Main structure) cum 2 34.100 0.250 2.000 34.100
Return wall I (Main structure) cum 4 0.600 0.300 2.550 1.836
Base slab of return wall II (Main
cum 4 2.800 2.500 0.250 7.000
structure)
Return wall II (Main structure) cum 4 2.800 0.225 2.600 6.552
Shear key cum 2 3.700 0.675 4.995
Haunch cum 2 34.100 0.011 0.767
Total= 93.101

4 Substructure Steel (HYSD Bars)


70 kg/cum of Concrete ton 1 6.517 6.517
Total 6.517

5 Weep holes
Spacing for weep holes = 2 m in horizontal and 1 m in vertical direction
No of weep holes in horizontal direction per side wall =33.5/2+1 = 18
No of weep holes in vertical direction per side wall =3.1/1+1 = 5
No of weep holes in horizontal direction per return wall (main str.)=3.4/2+1 = 3
No of weep holes in vertical direction per return wall (main str.)=2.6/1 +1= 4
Total no of Weep holes per side wall = 18 x 5 90
Total no of Weep holes per return wall (main str.) = 3 x 4 12
Total no of weep holes = 90 x 2 + 12 x 4 + 0 x 4 228

6 Backfilling - Granular Material


Box cum 1 3.700 0.450 1.665
Shear key cum 2 1.850 1.050 3.885
At Return wall II (Main structure) cum 4 4.550 0.400 7.280
Total 12.830

7 Filter media
Behind side wall cum 2 33.500 0.600 2.550 102.510
Behind Return Wall cum 4 2.820 0.600 2.600 17.597
Total 120.107
QUANTITY ESTIMATE OF BOX CULVERT

Box Size:- 1 cell of 2 m x 2 m


with Flexible Apron_EC

Item No. Description Unit nos Length (m) Breadth (m) Height (m) Quantity

C. SUPERSTRUCTURE

8 RCC-M30(up to 5m)
Box Bridge cum 1 2.500 34.100 0.263 22.378
Kerb over Top Slab cum 2 2.500 0.250 0.300 0.375
(+)Haunch cum 2 34.100 0.011 0.767
Total 23.520

9 Superstructure Steel (HYSD Bars)


75 kg/cum of concrete ton 1 1.764 1.764
Total 1.764

D. PROTECTION WORK
10 750 mm thick Flexible apron
Upstream cum 1 9.300 3.000 0.750 20.925
Downstream cum 1 9.300 6.000 0.750 41.850
Deduction for Return wall 2 cum 4 2.800 0.650 0.750 5.460
Total 57.315

11 Curtain Wall- PCC (M-20)


Downstream side cum 1 21.300 1.910 40.683
Upstream side cum 1 15.300 1.480 22.644
Deduction due to return wall ll
cum 2 0.650 1.910 2.483
foundation (D/S)
Deduction due to return wall ll
cum 2 0.650 1.480 1.924
foundation (U/S)
Total 58.920

12 Excavation in Soil
Curtain Wall (downstream) cum 1 21.300 2.850 2.650 160.868
Curtain Wall (upstream) cum 1 15.300 2.500 2.150 82.238
Flexible apron(downstream) cum 1 8.300 2.000 0.750 12.450
Flexible apron(upstream) cum 1 8.300 5.000 0.750 31.125
Deduction for Return wall 2 cum 4 2.800 0.650 0.900 6.552
Total 280.129

13 PCC (M-15)
Below Curtain Wall
Downstream side cum 1 21.300 1.850 0.150 5.911
Upstream side cum 1 15.300 1.500 0.150 3.443
Deduction due to return wall ll cum 4 0.650 1.675 0.150 0.653
Total 8.700

E. MISCELLANEOUS WORK

14 Painting
Kerb sqm 2 2.50 0.850 4.25
Total 4.250
QUANTITY ESTIMATE OF BOX CULVERT

Box Size:- 1 cell of 2 m x 2 m


with Flexible Apron
& Earth Cushion
Item No. Description Unit nos Length (m) Breadth (m) Height (m) Quantity

A. FOUNDATION
1.(a) Excavation(up to 3m)
Box Bridge cum 1 3.700 19.500 0.750 54.112
Shear Key cum 2 3.700 1.800 0.900 11.988
Return Wall-II (Service Road) cum 2 3.300 3.500 0.750 17.325
` Total 83.425

2 PCC-M15
Box Bridge cum 1 3.700 16.100 0.150 8.936
Shear Key cum 2 3.900 1.673 0.150 1.957
Return Wall-II (Service Road) cum 2 2.950 2.700 0.150 2.390
Total 13.282

B. SUBSTRUCTURE
3 RCC-M30 (upto 5m)
Bottom Slab cum 1 3.700 18.500 0.300 20.535
Box Side Wall (Main structure) cum 2 10.500 0.250 2.175 11.419
Box Side Wall (Service Road) cum 2 8.000 0.250 2.088 8.350
Return wall I (Service Road) cum 2 0.600 0.300 2.250 0.810
Base slab of return wall II(Service
cum 2 2.800 2.500 0.250 3.500
Road)
Return wall II (Service Road) cum 2 2.800 0.225 2.300 2.898
Shear key cum 2 3.700 0.675 4.995
Haunch cum 2 26.500 0.011 0.596
Total= 53.103

4 Substructure Steel (HYSD Bars)


70 kg/cum of Concrete ton 1 3.717 3.717
Total 3.717

5 Weep holes
Spacing for weep holes = 2 m in horizontal and 1 m in vertical direction
No of weep holes in horizontal direction per side wall =17.9/2+1 = 10
No of weep holes in vertical direction per side wall =3.9/1+1 = 5
No of weep holes in horizontal direction per return wall (service road) =3.4/2+1 = 3
No of weep holes in vertical direction per return wall (service road) =2.3/1 +1= 4
Total no of Weep holes per side wall = 10 x 5 50
Total no of Weep holes per return wall (service road) = 3 x 4 12
Total no of weep holes = 50 x 2 + 12 x 2 124

6 Backfilling - Granular Material


Box cum 1 3.700 0.450 1.665
Shear key cum 2 1.850 1.050 3.885
At Return wall II (Service Road) cum 2 4.550 0.400 3.640
Total 9.190

7 Backfilling - Sandy Material


Behind the side wall and return
cum 2 7.70 3.400 2.275 119.119
wall
Deduct for the filter media cum -56.923
Total 62.196

8 Filter media
Behind side wall cum 2 18.200 0.600 2.250 49.140
Behind Return Wall cum 2 2.820 0.600 2.300 7.783
Total 56.923
QUANTITY ESTIMATE OF BOX CULVERT

Box Size:- 1 cell of 2 m x 2 m


with Flexible Apron
& Earth Cushion
Item No. Description Unit nos Length (m) Breadth (m) Height (m) Quantity

C. SUPERSTRUCTURE

9 RCC-M30(up to 5m)
Box Bridge cum 1 2.500 18.500 0.250 11.563
(+)Haunch cum 2 18.500 0.011 0.416
Rectangular part of bracket cum 2 8.000 0.300 0.300 1.440
Triangular part of bracket cum 2 8.000 0.045 0.720
Total 11.979

10 Superstructure Steel (HYSD Bars)


75 kg/cum of concrete ton 1 0.898 0.898
Total 0.898

11 Bituminous concrete wearing course


For Service Road cum 1 9.500 7.000 0.040 2.660
Total 2.660

12 Mastic Asphalt
For Service Road sqm 1 9.500 7.000 66.500
Total 66.500

13 Tack Coat
For Service Road sqm 1 9.500 7.000 66.500
Total 66.500

14 Crash Barrier R.C.C. M40 m 2 9.500 19.000


Total 19.000

15 Drainage Spout nos. 2 2

16 PCC below Approach Slab


cum 2 3.370 7.760 0.150 7.845
Total 7.845

17 Approach Slab
cum 2 3.500 7.760 0.300 16.296
Total 16.296
18 Filler Joint
(i) copper plate m 2 8.000 16.000
(ii) fibar board m 2 8.000 16.000
(iii) 20mm thick premoulded
m 2 8.000 16.000
joint filler
(iv) joint sealing compound m 2 8.000 16.000
QUANTITY ESTIMATE OF BOX CULVERT

Box Size:- 1 cell of 2 m x 2 m


with Flexible Apron
& Earth Cushion
Item No. Description Unit nos Length (m) Breadth (m) Height (m) Quantity

D. PROTECTION WORK
19 750 mm thick Flexible apron
Upstream cum 1 9.300 3.000 0.750 20.925
Downstream cum 1 9.300 6.000 0.750 41.850
Deduction for Return wall 2 cum 2 2.800 0.650 0.750 2.730
Total 60.045

20 Curtain Wall- PCC (M-20)


Downstream side cum 1 21.300 1.910 40.683
Upstream side cum 1 15.300 1.480 22.644
Deduction due to return wall ll
cum 2 0.650 1.480 1.924
foundation (U/S)
Total 61.403

21 Excavation in Soil
Curtain Wall (downstream) cum 1 21.300 2.850 2.650 160.868
Curtain Wall (upstream) cum 1 15.300 2.500 2.150 82.238
Flexible apron(downstream) cum 1 8.300 2.000 0.750 12.450
Flexible apron(upstream) cum 1 8.300 5.000 0.750 31.125
Deduction for Return wall 2 cum 2 3.630 0.650 0.900 4.247
Total 282.434

22 PCC (M-15)
Below Curtain Wall
Downstream side cum 1 21.300 1.850 0.150 5.911
Upstream side cum 1 15.300 1.500 0.150 3.443
Deduction due to return wall ll cum 2 0.650 1.675 0.150 0.327
Total 9.027
E. MISCELLANEOUS WORK

23 Painting
Crash Barrier sqm 2 9.50 2.610 49.59
Total 49.59
QUANTITY ESTIMATE OF BOX CULVERT

Box Size:- 1 cell of 2 m x 2 m


with Flexible Apron
& Earth Cushion
Item No. Description Unit nos Length (m) Breadth (m) Height (m) Quantity

A. FOUNDATION
1.(a) Excavation(up to 3m)
Box Bridge cum 1 3.700 41.000 0.750 113.775
Shear Key cum 2 3.700 1.800 0.900 11.988
Return Wall-II (Service Road) cum 4 3.300 3.500 0.750 34.650
` Total 160.413

2 PCC-M15
Box Bridge cum 1 3.700 37.600 0.150 20.868
Shear Key cum 2 3.900 1.673 0.150 1.957
Return Wall-II (Service Road) cum 4 2.950 2.700 0.150 4.779
Total 27.604

B. SUBSTRUCTURE
3 RCC-M30 (upto 5m)
Bottom Slab cum 1 3.700 40.000 0.300 44.400
Box Side Wall (Main structure) cum 2 24.000 0.250 2.175 26.100
Box Side Wall (Service Road) cum 4 8.000 0.250 2.088 16.700
Return wall I (Service Road) cum 4 0.600 0.300 2.250 1.620
Base slab of return wall II(Service
cum 4 2.800 2.500 0.250 7.000
Road)
Return wall II (Service Road) cum 4 2.800 0.225 2.300 5.796
Shear key cum 2 3.700 0.675 4.995
Haunch cum 2 40.000 0.011 0.900
Total= 107.511

4 Substructure Steel (HYSD Bars)


70 kg/cum of Concrete ton 1 7.526 7.526
Total 7.526

5 Weep holes
Spacing for weep holes = 2 m in horizontal and 1 m in vertical direction
No of weep holes in horizontal direction per side wall =39.4/2+1 = 21
No of weep holes in vertical direction per side wall =3.9/1+1 = 5
No of weep holes in horizontal direction per return wall (service road) =3.4/2+1 = 3
No of weep holes in vertical direction per return wall (service road) =2.3/1 +1= 4
Total no of Weep holes per side wall = 21 x 5 105
Total no of Weep holes per return wall (service road) = 3 x 4 12
Total no of weep holes = 105 x 2 + 12 x 4 258

6 Backfilling - Granular Material


Box cum 1 3.700 0.450 1.665
Shear key cum 2 1.850 1.050 3.885
At Return wall II (Service Road) cum 4 4.550 0.400 7.280
Total 12.830

7 Backfilling - Sandy Material


Behind the side wall and return
cum 2 15.40 3.400 2.275 238.238
wall
Deduct for the filter media cum -121.946
Total 116.292

8 Filter media
Behind side wall cum 2 39.400 0.600 2.250 106.380
Behind Return Wall cum 4 2.820 0.600 2.300 15.566
Total 121.946
QUANTITY ESTIMATE OF BOX CULVERT

Box Size:- 1 cell of 2 m x 2 m


with Flexible Apron
& Earth Cushion
Item No. Description Unit nos Length (m) Breadth (m) Height (m) Quantity

C. SUPERSTRUCTURE

9 RCC-M30(up to 5m)
Box Bridge cum 1 2.500 40.000 0.250 25.000
(+)Haunch cum 2 40.000 0.011 0.900
Rectangular part of bracket cum 4 8.000 0.300 0.300 2.880
Triangular part of bracket cum 4 8.000 0.045 1.440
Total 25.900

10 Superstructure Steel (HYSD Bars)


75 kg/cum of concrete ton 1 1.943 1.943
Total 1.943

11 Bituminous concrete wearing course


For Service Road cum 2 9.500 7.000 0.040 5.320
Total 5.320

12 Mastic Asphalt
For Service Road sqm 2 9.500 7.000 133.000
Total 133.000

13 Tack Coat
For Service Road sqm 2 9.500 7.000 133.000
Total 133.000

14 Crash Barrier R.C.C. M40 m 4 9.500 38.000


Total 38.000

15 Drainage Spout nos. 4 4

16 PCC below Approach Slab


cum 4 3.370 7.760 0.150 15.691
Total 15.691

17 Approach Slab
cum 4 3.500 7.760 0.300 32.592
Total 32.592
18 Filler Joint
(i) copper plate m 4 8.000 32.000
(ii) fibar board m 4 8.000 32.000
(iii) 20mm thick premoulded
m 4 8.000 32.000
joint filler
(iv) joint sealing compound m 4 8.000 32.000
QUANTITY ESTIMATE OF BOX CULVERT

Box Size:- 1 cell of 2 m x 2 m


with Flexible Apron
& Earth Cushion
Item No. Description Unit nos Length (m) Breadth (m) Height (m) Quantity

D. PROTECTION WORK
19 750 mm thick Flexible apron
Upstream cum 1 9.300 3.000 0.750 20.925
Downstream cum 1 9.300 6.000 0.750 41.850
Deduction for Return wall 2 cum 4 2.800 0.650 0.750 5.460
Total 57.315

20 Curtain Wall- PCC (M-20)


Downstream side cum 1 21.300 1.910 40.683
Upstream side cum 1 15.300 1.480 22.644
Deduction due to return wall ll
cum 2 0.650 1.910 2.483
foundation (D/S)
Deduction due to return wall ll
cum 2 0.650 1.480 1.924
foundation (U/S)
Total 58.920

21 Excavation in Soil
Curtain Wall (downstream) cum 1 21.300 2.850 2.650 160.868
Curtain Wall (upstream) cum 1 15.300 2.500 2.150 82.238
Flexible apron(downstream) cum 1 8.300 2.000 0.750 12.450
Flexible apron(upstream) cum 1 8.300 5.000 0.750 31.125
Deduction for Return wall 2 cum 4 3.630 0.650 0.900 8.494
Total 278.187

22 PCC (M-15)
Below Curtain Wall
Downstream side cum 1 21.300 1.850 0.150 5.911
Upstream side cum 1 15.300 1.500 0.150 3.443
Deduction due to return wall ll cum 4 0.650 1.675 0.150 0.653
Total 8.700
E. MISCELLANEOUS WORK

23 Painting
Crash Barrier sqm 4 9.50 2.610 99.18
Total 99.18
QUANTITY ESTIMATE OF BOX CULVERT

Box Size:- 1 cell of 2 m x 2 m


with Flexible Apron_EC
SE
Item No. Description Unit nos Length (m) Breadth (m) Height (m) Quantity

A. FOUNDATION
1.(a) Excavation(up to 3m)
Box Bridge cum 1 3.700 36.356 0.750 100.888
Shear Key cum 2 3.700 1.800 0.900 11.988
Return Wall-II (Main structure) cum 4 2.800 3.500 0.750 29.400
` Total 142.276

2 PCC-M15
Box Bridge cum 1 3.700 32.956 0.150 18.291
Shear Key cum 2 3.900 1.673 0.150 1.957
Return Wall-II (Main structure) cum 4 2.950 2.700 0.150 4.779
Total 25.027

B. SUBSTRUCTURE
3 RCC-M30 (upto 5m)
Bottom Slab cum 1 3.700 35.356 0.300 39.245
Box Side Wall (Main structure) cum 2 35.356 0.250 2.000 35.356
Return wall I (Main structure) cum 4 0.600 0.300 2.550 1.836
Base slab of return wall II (Main
cum 4 2.800 2.500 0.250 7.000
structure)
Return wall II (Main structure) cum 4 2.800 0.225 2.600 6.552
Shear key cum 2 3.700 0.675 4.995
Haunch cum 2 35.356 0.011 0.796
Total= 95.780

4 Substructure Steel (HYSD Bars)


70 kg/cum of Concrete ton 1 6.705 6.705
Total 6.705

5 Weep holes
Spacing for weep holes = 2 m in horizontal and 1 m in vertical direction
No of weep holes in horizontal direction per side wall =34.8/2+1 = 19
No of weep holes in vertical direction per side wall =4.2/1+1 = 6
No of weep holes in horizontal direction per return wall (main str.)=3.4/2+1 = 3
No of weep holes in vertical direction per return wall (main str.)=2.6/1 +1= 4
Total no of Weep holes per side wall = 19 x 6 114
Total no of Weep holes per return wall (main str.) = 3 x 4 12
Total no of weep holes = 114 x 2 + 12 x 4 + 0 x 4 276

6 Backfilling - Granular Material


Box cum 1 3.700 0.450 1.665
Shear key cum 2 1.850 1.050 3.885
At Return wall II (Main structure) cum 4 2.800 0.400 4.480
Total 10.030

7 Filter media
Behind side wall cum 2 34.756 0.600 2.550 106.353
Behind Return Wall cum 4 2.820 0.600 2.600 17.597
Total 123.950
QUANTITY ESTIMATE OF BOX CULVERT

Box Size:- 1 cell of 2 m x 2 m


with Flexible Apron_EC
SE
Item No. Description Unit nos Length (m) Breadth (m) Height (m) Quantity

C. SUPERSTRUCTURE

8 RCC-M30(up to 5m)
Box Bridge cum 1 2.500 35.356 0.263 23.202
Kerb over Top Slab cum 2 2.500 0.250 0.300 0.375
(+)Haunch cum 2 35.356 0.011 0.796
Total 24.373

9 Superstructure Steel (HYSD Bars)


75 kg/cum of concrete ton 1 1.828 1.828
Total 1.828

D. PROTECTION WORK
10 750 mm thick Flexible appron
Upstream cum 1 9.300 3.000 0.750 20.925
Downstream cum 1 9.300 6.000 0.750 41.850
Deduction for Return wall 2 cum 4 3.300 0.650 0.750 6.435
Total 56.340

11 Curtain Wall- PCC (M-20)


Downstream side cum 1 21.300 1.910 40.683
Upstream side cum 1 15.300 1.480 22.644
Deduction due to return wall ll
cum 2 0.650 1.910 2.483
foundation (D/S)
Deduction due to return wall ll
cum 2 0.650 1.480 1.924
foundation (U/S)
Total 58.920

12 Excavation in Soil
Curtain Wall (downstream) cum 1 21.300 2.850 2.650 160.868
Curtain Wall (upstream) cum 1 15.300 2.500 2.150 82.238
Flexible apron(downstream) cum 1 8.300 2.000 0.750 12.450
Flexible apron(upstream) cum 1 8.300 5.000 0.750 31.125
Deduction for Return wall 2 cum 4 3.300 0.650 0.900 7.722
Total 278.959

13 PCC (M-15)
Below Curtain Wall
Downstream side cum 1 21.300 1.850 0.150 5.911
Upstream side cum 1 15.300 1.500 0.150 3.443
Deduction due to return wall ll cum 4 0.650 1.675 0.150 0.653
Total 8.700

E. MISCELLANEOUS WORK

14 Painting
Kerb sqm 2 2.50 0.850 4.25
Total 4.250
ESTIMATE OF QUANTITY OF BOX CULVERT

Box Size:- 1 cell of 2 m x 3 m


with Flexible Apron NC

Item No. Description Unit nos Length (m) Breadth (m) Height (m) Quantity

A. FOUNDATION
1 Excavation(up to 3m)
Box Bridge cum 1 4.540 25.500 1.220 141.239
Shear Key cum 2 4.540 1.780 0.880 14.223
Return Wall-II cum 4 4.400 4.300 1.220 92.330
` Total 247.792

2 PCC-M15
Box Bridge cum 1 3.540 22.140 0.150 11.756
Shear Key cum 2 3.740 1.645 0.150 1.845
Return Wall-II cum 4 4.500 3.500 0.150 9.450
Total 23.051

B. SUBSTRUCTURE
3 RCC-M30 (upto 5m)
Bottom Slab cum 1 3.540 24.500 0.320 27.754
Box Side Wall cum 2 24.500 0.270 3.138 41.509
Base slab of return wall II cum 4 4.400 3.300 0.300 17.424
Return wall I cum 4 0.500 0.300 3.270 1.962
Return wall II cum 4 4.400 0.275 3.290 15.924
Shear key cum 2 3.540 0.651 4.610
Haunch cum 2 24.500 0.011 0.551
Total= 109.734

4 Substructure Steel (HYSD Bars)


70 kg/cum of Concrete ton 1 7.681 7.681
Total 7.681

5 Weep holes
Spacing for weep holes = 2 m in horizontal and 1 m in vertical direction
No of weep holes in horizontal direction per side wall =23.9/2+1 = 13
No of weep holes in vertical direction per side wall =3.1/1+1 = 5
No of weep holes in horizontal direction per return wall =4.9/2+1 = 4
No of weep holes in vertical direction per return wall =3.3/1 +1= 5
Total no of Weep holes per side wall= 13 x 5 65
Total no of Weep holes per return wall = 4 x 5 20
Total no of weep holes = 65 x 2 + 20 x 4 210

6 Backfilling - Granular Material


Box cum 1 29.040 0.320 9.293
Shear key cum 2 1.770 0.880 3.115
Return Wall-II cum 4 4.400 0.300 5.280
Total 17.688

7 Backfilling - Sandy Material


Behind the side wall and return
cum 2 23.900 4.900 1.489 348.695
wall
Deduct for the filter media cum 115.692
Total 233.003

8 Filter media
Behind Abutment cum 2 23.900 0.600 2.958 84.821
Behind Return Wall cum 4 4.320 0.600 2.978 30.871
Total 115.692
ESTIMATE OF QUANTITY OF BOX CULVERT

Box Size:- 1 cell of 2 m x 3 m


with Flexible Apron NC

Item No. Description Unit nos Length (m) Breadth (m) Height (m) Quantity

C. SUPERSTRUCTURE

9 RCC-M30(up to 5m)
Box Bridge cum 1 2.540 24.500 0.270 16.802
(+)Haunch cum 2 24.500 0.011 0.551
Rectangular part of bracket cum 2 24.500 0.300 0.300 4.410
Triangular part of bracket cum 2 24.500 0.045 2.205
Total 23.968

10 Superstructure Steel (HYSD Bars)


75 kg/cum of concrete ton 1 1.798 1.798
Total 1.798

11 Bituminous Concrete Wearing Coat(40mm)


cum 1 9.540 22.000 0.040 8.395
Total 8.395

12 Mastic Asphalt
sqm 1 9.540 22.000 209.880
Total 209.880

13 Tack Coat
sqm 1 9.540 22.000 209.880
Total 209.880

14 Crash Barrier R.C.C. M40 m 4 9.540 38.160


Total 38.160

15 Drainage Spout nos. 4 4

16 PCC below Approach Slab


cum 2 3.370 23.900 0.150 24.163
Total 24.163

17 Approach Slab
cum 2 3.500 23.900 0.300 50.190
Total 50.190

18 Filler Joint
(i) copper plate m 2 24.500 49.000
(ii) fibar board m 2 24.500 49.000
(iii) 20mm thick premoulded
m 2 24.500 49.000
joint filler
(iv) joint sealing compound m 2 24.500 49.000
ESTIMATE OF QUANTITY OF BOX CULVERT

Box Size:- 1 cell of 2 m x 3 m


with Flexible Apron NC

Item No. Description Unit nos Length (m) Breadth (m) Height (m) Quantity

19 750 mm thick Flexible appron


Upstream cum 1 12.340 3.000 0.750 27.765
Downstream cum 1 12.340 6.000 0.750 55.530
Deduction due to return wall ll
4 4.400 1.250 0.750 16.500
foundation
Total 66.795

20 Curtain Wall- PCC (M-20)


Downstream side cum 1 25.340 1.910 48.399
Upstream side cum 1 19.340 1.480 28.623
Deduction due to return wall ll
cum 2 1.250 1.910 4.775
foundation (D/S)
Deduction due to return wall ll
cum 2 1.250 1.480 3.700
foundation (U/S)
Total 68.548

21 Excavation in Soil
Curtain Wall (downstream) cum 1 25.340 2.850 2.650 191.380
Curtain Wall (upstream) cum 1 19.340 2.500 2.150 103.953
Flexible appron(downstream) cum 1 11.340 2.000 0.750 17.010
Flexible appron(upstream) cum 1 11.340 5.000 0.750 42.525
Deduction due to return wall ll
cum 4 5.400 1.750 0.900 34.020
foundation
Total 320.848

22 PCC (M-15)
Below Curtain Wall
Downstream side cum 1 24.340 1.850 0.150 6.754
Upstream side 1 18.340 1.500 0.150 4.127
Deduction due to return wall ll
cum 4 1.250 1.675 0.150 1.256
foundation
Total 9.625

E. MISCELLANEOUS WORK

23 Painting
Crash Barrier sqm 4 9.54 2.610 99.60
Total 99.60
ESTIMATE OF QUANTITY OF BOX CULVERT

Box Size:- 1 cell of 2 m x 3 m


with Flexible Apron NC

Item No. Description Unit nos Length (m) Breadth (m) Height (m) Quantity

A. FOUNDATION
1 Excavation(up to 3m)
Box Bridge cum 1 4.540 42.000 1.220 232.630
Shear Key cum 2 4.540 1.780 0.880 14.223
Return Wall-II cum 4 4.400 4.300 1.220 92.330
` Total 339.182

2 PCC-M15
Box Bridge cum 1 3.540 38.640 0.150 20.518
Shear Key cum 2 3.740 1.645 0.150 1.845
Return Wall-II cum 4 4.500 3.500 0.150 9.450
Total 31.813

B. SUBSTRUCTURE
3 RCC-M30 (upto 5m)
Bottom Slab cum 1 3.540 41.000 0.320 46.445
Box Side Wall cum 2 41.000 0.270 3.231 71.540
Base slab of return wall II cum 4 4.400 3.300 0.300 17.424
Return wall I cum 4 0.500 0.300 3.270 1.962
Return wall II cum 4 4.400 0.275 3.290 15.924
Shear key cum 2 3.540 0.651 4.610
Haunch cum 2 41.000 0.011 0.923
Total= 158.827

4 Substructure Steel (HYSD Bars)


70 kg/cum of Concrete ton 1 11.118 11.118
Total 11.118

5 Weep holes
Spacing for weep holes = 2 m in horizontal and 1 m in vertical direction
No of weep holes in horizontal direction per side wall =40.4/2+1 = 22
No of weep holes in vertical direction per side wall =3.2/1+1 = 5
No of weep holes in horizontal direction per return wall =4.9/2+1 = 4
No of weep holes in vertical direction per return wall =3.3/1 +1= 5
Total no of Weep holes per side wall= 22 x 5 110
Total no of Weep holes per return wall = 4 x 5 20
Total no of weep holes = 110 x 2 + 20 x 4 300

6 Backfilling - Granular Material


Box cum 1 45.540 0.320 14.573
Shear key cum 2 1.770 0.880 3.115
Return Wall-II cum 4 4.400 0.300 5.280
Total 22.968

7 Backfilling - Sandy Material


Behind the side wall and return
cum 2 40.400 4.900 1.536 607.985
wall
Deduct for the filter media cum 179.767
Total 428.217

8 Filter media
Behind Abutment cum 2 40.400 0.600 3.051 147.925
Behind Return Wall cum 4 4.320 0.600 3.071 31.843
Total 179.767
ESTIMATE OF QUANTITY OF BOX CULVERT

Box Size:- 1 cell of 2 m x 3 m


with Flexible Apron NC

Item No. Description Unit nos Length (m) Breadth (m) Height (m) Quantity

C. SUPERSTRUCTURE

9 RCC-M30(up to 5m)
Box Bridge cum 1 2.540 41.000 0.270 28.118
(+)Haunch cum 2 41.000 0.011 0.923
Rectangular part of bracket cum 2 41.000 0.300 0.300 7.380
Triangular part of bracket cum 2 41.000 0.045 3.690
Total 40.110

10 Superstructure Steel (HYSD Bars)


75 kg/cum of concrete ton 1 3.008 3.008
Total 3.008

11 Bituminous Concrete Wearing Coat(40mm)


cum 1 9.540 37.000 0.040 14.119
Total 14.119

12 Mastic Asphalt
sqm 1 9.540 37.000 352.980
Total 352.980

13 Tack Coat
sqm 1 9.540 37.000 352.980
Total 352.980

14 Crash Barrier R.C.C. M40 m 4 9.540 38.160


Total 38.160

15 Drainage Spout nos. 4 4

16 PCC below Approach Slab


cum 2 3.370 40.400 0.150 40.844
Total 40.844

17 Approach Slab
cum 2 3.500 40.400 0.300 84.840
Total 84.840

18 Filler Joint
(i) copper plate m 2 41.000 82.000
(ii) fibar board m 2 41.000 82.000
(iii) 20mm thick premoulded
m 2 41.000 82.000
joint filler
(iv) joint sealing compound m 2 41.000 82.000
ESTIMATE OF QUANTITY OF BOX CULVERT

Box Size:- 1 cell of 2 m x 3 m


with Flexible Apron NC

Item No. Description Unit nos Length (m) Breadth (m) Height (m) Quantity

19 750 mm thick Flexible appron


Upstream cum 1 12.340 3.000 0.750 27.765
Downstream cum 1 12.340 6.000 0.750 55.530
Deduction due to return wall ll
4 4.400 1.250 0.750 16.500
foundation
Total 66.795

20 Curtain Wall- PCC (M-20)


Downstream side cum 1 25.340 1.910 48.399
Upstream side cum 1 19.340 1.480 28.623
Deduction due to return wall ll
cum 2 1.250 1.910 4.775
foundation (D/S)
Deduction due to return wall ll
cum 2 1.250 1.480 3.700
foundation (U/S)
Total 68.548

21 Excavation in Soil
Curtain Wall (downstream) cum 1 25.340 2.850 2.650 191.380
Curtain Wall (upstream) cum 1 19.340 2.500 2.150 103.953
Flexible appron(downstream) cum 1 11.340 2.000 0.750 17.010
Flexible appron(upstream) cum 1 11.340 5.000 0.750 42.525
Deduction due to return wall ll
cum 4 5.400 1.750 0.900 34.020
foundation
Total 320.848

22 PCC (M-15)
Below Curtain Wall
Downstream side cum 1 24.340 1.850 0.150 6.754
Upstream side 1 18.340 1.500 0.150 4.127
Deduction due to return wall ll
cum 4 1.250 1.675 0.150 1.256
foundation
Total 9.625

E. MISCELLANEOUS WORK

23 Painting
Crash Barrier sqm 4 9.54 2.610 99.60
Total 99.60
ESTIMATE OF QUANTITY OF BOX CULVERT

Box Size:- 1 cell of 2 m x 3 m


with Flexible Apron
with 2.83%(L),3.17%(R) SE
Item No. Description Unit nos Length (m) Breadth (m) Height (m) Quantity

A. FOUNDATION
1 Excavation(up to 3m)
Box Bridge cum 1 4.540 25.500 1.960 226.909
Shear Key cum 2 4.540 1.780 0.880 14.223
Return Wall-II cum 4 4.900 5.150 1.960 197.842
` Total 438.975

2 PCC-M15
Box Bridge cum 1 3.540 22.140 0.150 11.756
Shear Key cum 2 3.740 1.645 0.150 1.845
Return Wall-II cum 4 4.550 4.450 0.150 12.149
Total 25.750

B. SUBSTRUCTURE
3 RCC-M30 (upto 5m)
Bottom Slab cum 1 3.540 24.500 0.320 27.754
Box Side Wall cum 2 24.500 0.270 3.320 43.925
Base slab of return wall II cum 4 4.450 4.150 0.400 29.548
Return wall I cum 4 0.500 0.300 3.596 2.158
Return wall II cum 4 4.400 0.325 3.516 20.112
Shear key cum 2 3.540 0.651 4.610
Haunch cum 2 24.500 0.011 0.551
Total= 128.658

4 Substructure Steel (HYSD Bars)


70 kg/cum of Concrete ton 1 9.006 9.006
Total 9.006

5 Weep holes
Spacing for weep holes = 2 m in horizontal and 1 m in vertical direction
No of weep holes in horizontal direction per side wall =23.9/2+1 = 13
No of weep holes in vertical direction per side wall=3.6/1+1 = 5
No of weep holes in horizontal direction per return wall =4.5/2+1 = 4
No of weep holes in vertical direction per return wall =3.5/1 +1= 5
Total no of Weep holes per side wall = 13 x 5 65
Total no of Weep holes per return wall = 4 x 5 20
Total no of weep holes = 65 x 2 + 20 x 4 210

6 Backfilling - Granular Material


Box cum 1 29.040 0.470 13.649
Shear key cum 2 1.770 1.030 3.646
Return Wall-II cum 4 6.768 0.550 14.889
Total 32.184

7 Backfilling - Sandy Material


Behind the side wall and return
cum 2 23.90 4.900 1.530 358.368
wall
Deduct for the filter media cum 121.785
Total 236.583

8 Filter media
Behind Abutment cum 2 23.900 0.600 3.140 90.058
Behind Return Wall cum 4 4.320 0.600 3.060 31.727
Total 121.785
ESTIMATE OF QUANTITY OF BOX CULVERT

Box Size:- 1 cell of 2 m x 3 m


with Flexible Apron
with 2.83%(L),3.17%(R) SE
Item No. Description Unit nos Length (m) Breadth (m) Height (m) Quantity

C. SUPERSTRUCTURE

9 RCC-M30(up to 5m)
Box Bridge cum 1 2.540 24.500 0.270 16.802
(+)Haunch cum 2 24.500 0.011 0.551
Rectangular part of bracket cum 2 24.500 0.300 0.300 4.410
Triangular part of bracket cum 2 24.500 0.045 2.205
Total 23.968

10 Superstructure Steel (HYSD Bars)


75 kg/cum of concrete ton 1 1.798 1.798
Total 1.798

11 Bituminous conceret wearing course


cum 1 9.540 22.000 0.040 8.395
Total 8.395

12 Mastic Asphalt
sqm 1 9.540 22.000 209.880
Total 209.880

13 Tack Coat
sqm 1 9.540 22.000 209.880
Total 209.880

14 Crash Barrier R.C.C. M40 m 4 9.540 38.160


Total 38.160

15 Drainage Spout nos. 4 4

16 PCC below Approach Slab


cum 2 3.370 23.360 0.150 23.617
Total 23.617

17 Approach Slab
cum 2 3.500 23.360 0.300 49.056
Total 49.056

18 Filler Joint
(i) copper plate m 2 23.360 46.720
(ii) fibar board m 2 23.360 46.720
(iii) 20mm thick premoulded
m 2 23.360 46.720
joint filler
(iv) joint sealing compound m 2 23.360 46.720
ESTIMATE OF QUANTITY OF BOX CULVERT

Box Size:- 1 cell of 2 m x 3 m


with Flexible Apron
with 2.83%(L),3.17%(R) SE
Item No. Description Unit nos Length (m) Breadth (m) Height (m) Quantity

D. PROTECTION WORK

750 mm thick Flexible apron


19 Upstream cum 1 12.340 3.000 0.750 27.765
Downstream cum 1 12.340 6.000 0.750 55.530
Deduction for Return wall cum 4 4.400 1.750 0.750 -23.100
Total 60.195

Curtain Wall- PCC (M-20)


20 Downstream side cum 1 24.340 1.910 46.489
Upstream side cum 1 18.340 1.480 27.143
Deduction due to return wall ll
cum 2 1.750 1.910 6.685
foundation (D/S)
Deduction due to return wall ll
cum 2 1.750 1.480 5.180
foundation (U/S)
Total 61.768

21 Excavation in Soil
Curtain Wall (downstream) cum 1 24.340 2.850 2.650 183.828
Curtain Wall (upstream) cum 1 18.340 2.500 2.150 98.578
Flexible apron(downstream) cum 1 11.340 2.000 0.750 17.010
Flexible apron(upstream) cum 1 11.340 5.000 0.750 42.525
Deduction for Return wall cum 4 4.900 1.750 0.900 -30.870
Total 311.070

22 PCC (M-15)
Below Curtain Wall
Downstream side cum 1 24.340 1.850 0.150 6.754
Upstream side cum 1 18.340 1.500 0.150 4.127
Deduction due to return wall ll cum 4 1.750 1.675 0.150 1.759
Total 9.122

E. MISCELLANEOUS WORK

23 Painting
Crash Barrier sqm 4 9.54 2.610 99.60
Total 99.60
ESTIMATE OF QUANTITY OF BOX CULVERT

Box Size:- 1 cell of 2 m x 3 m


with Flexible & Rigid Apron
with 4% SE
Item No. Description Unit nos Length (m) Breadth (m) Height (m) Quantity

A. FOUNDATION
1 Excavation(up to 3m)
Box Bridge cum 1 4.540 25.500 2.092 242.191
Shear Key cum 2 4.540 1.780 0.880 14.223
Return Wall-II cum 4 4.900 5.150 2.092 211.166
` Total 467.580

2 PCC-M15
Box Bridge cum 1 3.540 22.140 0.150 11.756
Shear Key cum 2 3.740 1.645 0.150 1.845
Return Wall-II cum 4 4.550 4.450 0.150 12.149
Total 25.750

B. SUBSTRUCTURE
3 RCC-M30 (upto 5m)
Bottom Slab cum 1 3.540 24.500 0.320 27.754
Box Side Wall cum 2 24.500 0.270 3.440 45.511
Base slab of return wall II cum 4 4.450 4.150 0.400 29.548
Return wall I cum 4 0.500 0.300 3.710 2.226
Return wall II cum 4 4.400 0.325 3.630 20.764
Shear key cum 2 3.540 0.651 4.610
Haunch cum 2 24.500 0.011 0.551
Total= 130.964

4 Substructure Steel (HYSD Bars)


70 kg/cum of Concrete ton 1 9.167 9.167
Total 9.167

5 Weep holes
Spacing for weep holes = 2 m in horizontal and 1 m in vertical direction
No of weep holes in horizontal direction per side wall =23.9/2+1 = 13
No of weep holes in vertical direction per side wall=3.7/1+1 = 5
No of weep holes in horizontal direction per return wall =4.5/2+1 = 4
No of weep holes in vertical direction per return wall =3.6/1 +1= 5
Total no of Weep holes per side wall = 13 x 5 65
Total no of Weep holes per return wall = 4 x 5 20
Total no of weep holes = 65 x 2 + 20 x 4 210

6 Backfilling - Granular Material


Box cum 1 29.040 0.470 13.649
Shear key cum 2 1.770 1.030 3.646
Return Wall-II cum 4 6.768 0.550 14.889
Total 32.184

7 Backfilling - Sandy Material


Behind the side wall and return
cum 2 23.90 4.900 1.590 372.410
wall
Deduct for the filter media cum 126.467
Total 245.943

8 Filter media
Behind Abutment cum 2 23.900 0.600 3.260 93.497
Behind Return Wall cum 4 4.320 0.600 3.180 32.970
Total 126.467
ESTIMATE OF QUANTITY OF BOX CULVERT

Box Size:- 1 cell of 2 m x 3 m


with Flexible & Rigid Apron
with 4% SE
Item No. Description Unit nos Length (m) Breadth (m) Height (m) Quantity

C. SUPERSTRUCTURE

9 RCC-M30(up to 5m)
Box Bridge cum 1 2.540 24.500 0.270 16.802
(+)Haunch cum 2 24.500 0.011 0.551
Rectangular part of bracket cum 2 24.500 0.300 0.300 4.410
Triangular part of bracket cum 2 24.500 0.045 2.205
Total 23.968

10 Superstructure Steel (HYSD Bars)


75 kg/cum of concrete ton 1 1.798 1.798
Total 1.798

11 Bituminous conceret wearing course


cum 1 9.540 22.000 0.040 8.395
Total 8.395

12 Mastic Asphalt
sqm 1 9.540 22.000 209.880
Total 209.880

13 Tack Coat
sqm 1 9.540 22.000 209.880
Total 209.880

14 Crash Barrier R.C.C. M40 m 4 9.540 38.160


Total 38.160

15 Drainage Spout nos. 4 4

16 PCC below Approach Slab


cum 2 3.370 23.360 0.150 23.617
Total 23.617

17 Approach Slab
cum 2 3.500 23.360 0.300 49.056
Total 49.056

18 Filler Joint
(i) copper plate m 2 23.360 46.720
(ii) fibar board m 2 23.360 46.720
(iii) 20mm thick premoulded
m 2 23.360 46.720
joint filler
(iv) joint sealing compound m 2 23.360 46.720
ESTIMATE OF QUANTITY OF BOX CULVERT

Box Size:- 1 cell of 2 m x 3 m


with Flexible & Rigid Apron
with 4% SE
Item No. Description Unit nos Length (m) Breadth (m) Height (m) Quantity

D. PROTECTION WORK
19 300 mm thick Rigid appron (over 100mm thick PCC)
Upstream cum 1 12.340 3.000 0.400 14.808
Downstream cum 1 12.340 5.000 0.400 24.680
Deduction due to return wall ll
cum 4 4.400 1.750 0.400 12.320
foundation
Total 27.168

750 mm thick Flexible apron


20 Upstream cum 1 12.340 1.500 0.750 13.883
Downstream cum 1 12.340 3.000 0.750 27.765
Total 41.648

Curtain Wall- PCC (M-20)


21 Downstream side cum 1 22.340 1.910 42.669
Upstream side cum 1 18.340 1.480 27.143
Deduction due to return wall ll
cum 2 1.750 1.910 6.685
foundation (D/S)
Deduction due to return wall ll
cum 2 1.750 1.480 5.180
foundation (U/S)
Total 57.948

22 Excavation in Soil
Curtain Wall (downstream) cum 1 22.340 2.850 2.650 168.723
Curtain Wall (upstream) cum 1 18.340 2.500 2.150 98.578
Flexible apron(downstream) cum 1 11.340 1.575 0.750 13.395
Flexible apron(upstream) cum 1 11.340 0.250 0.750 2.126
Rigid appron(downstream) cum 1 11.840 3.575 0.400 16.931
Rigid appron(upstream) cum 1 11.840 1.750 0.400 8.288
Deduction for Return wall cum 4 4.900 1.750 0.900 -30.870
Total 358.307

23 PCC (M-15)
Below Curtain Wall
Downstream side cum 1 22.340 1.850 0.150 6.199
Upstream side cum 1 18.340 1.500 0.150 4.127
Deduction due to return wall ll cum 4 1.750 1.675 0.150 1.759
Total 8.567

E. MISCELLANEOUS WORK

24 Painting
Crash Barrier sqm 4 9.54 2.610 99.60
Total 99.60
QUANTITY ESTIMATE OF BOX CULVERT

Box Size:- 1 cell of 2 m x 3 m


with Flexible Apron_EC

Item No. Description Unit nos Length (m) Breadth (m) Height (m) Quantity

A. FOUNDATION
1.(a) Excavation(up to 3m)
Box Bridge cum 1 4.960 44.904 0.800 178.179
Shear Key cum 2 4.960 1.750 0.850 14.756
Return Wall-II (Main structure) cum 4 4.400 4.300 0.800 60.544
` Total 253.479

2 PCC-M15
Box Bridge cum 1 4.960 41.604 0.150 30.953
Shear Key cum 2 5.160 1.602 0.150 2.480
Return Wall-II (Main structure) cum 4 4.050 3.600 0.150 8.748
Total 42.181

B. SUBSTRUCTURE
3 RCC-M30 (upto 5m)
Bottom Slab cum 1 4.960 43.904 0.350 76.217
Box Side Wall (Main structure) cum 2 43.904 0.380 3.000 100.101
Return wall I (Main structure) cum 4 1.100 0.300 3.620 4.778
Base slab of return wall II (Main
cum 4 3.900 3.300 0.350 18.018
structure)
Return wall II (Main structure) cum 4 3.900 0.275 3.620 15.530
Shear key cum 2 4.960 0.616 6.113
Haunch cum 2 43.904 0.011 0.988
Total= 221.746

4 Substructure Steel (HYSD Bars)


70 kg/cum of Concrete ton 1 15.522 15.522
Total 15.522

5 Weep holes
Spacing for weep holes = 2 m in horizontal and 1 m in vertical direction
No of weep holes in horizontal direction per side wall =43.3/2+1 = 23
No of weep holes in vertical direction per side wall =3/1+1 = 5
No of weep holes in horizontal direction per return wall (main str.)=5/2+1 = 4
No of weep holes in vertical direction per return wall (main str.)=3.6/1 +1= 5
Total no of Weep holes per side wall = 23 x 5 115
Total no of Weep holes per return wall (main str.) = 4 x 5 20
Total no of weep holes = 115 x 2 + 20 x 4 + 0 x 4 310

6 Backfilling - Granular Material


Box cum 1 4.960 0.500 2.480
Shear key cum 2 2.480 1.000 4.960
At Return wall II (Main structure) cum 4 6.050 0.500 12.100
Total 19.540

7 Filter media
Behind side wall cum 2 43.304 0.600 3.620 188.113
Behind Return Wall cum 4 4.420 0.600 3.620 38.401
Total 226.514
QUANTITY ESTIMATE OF BOX CULVERT

Box Size:- 1 cell of 2 m x 3 m


with Flexible Apron_EC

Item No. Description Unit nos Length (m) Breadth (m) Height (m) Quantity

C. SUPERSTRUCTURE

8 RCC-M30(up to 5m)
Box Bridge cum 1 2.760 43.904 0.334 40.448
Kerb over Top Slab cum 2 2.760 0.250 0.300 0.414
(+)Haunch cum 2 43.904 0.011 0.988
Total 41.850

9 Superstructure Steel (HYSD Bars)


75 kg/cum of concrete ton 1 3.139 3.139
Total 3.139

D. PROTECTION WORK
10 750 mm thick Flexible apron
Upstream cum 1 12.760 3.000 0.750 28.710
Downstream cum 1 12.760 6.000 0.750 57.420
Deduction for Return wall 2 cum 4 3.900 1.250 0.750 14.625
Total 71.505

11 Curtain Wall- PCC (M-20)


Downstream side cum 1 24.760 1.910 47.292
Upstream side cum 1 18.760 1.480 27.765
Deduction due to return wall ll
cum 2 1.250 1.910 4.775
foundation (D/S)
Deduction due to return wall ll
cum 2 1.250 1.480 3.700
foundation (U/S)
Total 66.581

12 Excavation in Soil
Curtain Wall (downstream) cum 1 24.760 2.850 2.650 187.000
Curtain Wall (upstream) cum 1 18.760 2.500 2.150 100.835
Flexible apron(downstream) cum 1 11.760 2.000 0.750 17.640
Flexible apron(upstream) cum 1 11.760 5.000 0.750 44.100
Deduction for Return wall 2 cum 4 3.900 1.250 0.900 17.550
Total 332.025

13 PCC (M-15)
Below Curtain Wall
Downstream side cum 1 24.760 1.850 0.150 6.871
Upstream side cum 1 18.760 1.500 0.150 4.221
Deduction due to return wall ll cum 4 1.250 1.675 0.150 1.256
Total 9.836

E. MISCELLANEOUS WORK

14 Painting
Kerb sqm 2 2.76 0.850 4.69
Total 4.692
REPAIR & REHABILITATION OF BRIDGE
JOB NO : 4146 (PACKAGE-5)
QTY. REPAIR & REHABILITATION

ITEM
Description Unit TOTAL
NO.
CH._51.819 KM CH._54.332 KM 3 X CH._56.461 KM 2 X CH._56.985 KM 2 X
3 X 8.6 m_RCC T 12.1 m_RCC T 10 m_RCC T Girder 11 m_RCC T Girder
Girder Bridge Girder Bridge Bridge Bridge
7 Painting on concrete surface sqm 17.304 279.618 164.880 187.500 649.30
ESTIMATE OF QUANTITY FOR REPAIRING , REHABILITATION AND PROTECTION WORK OF
BRIDGE

Chainage= 51.819 Km SPAN ARRANGEMENT - 3 X 8.6 M

Length Breadth Height


Item No. Description Unit nos Quantity
(m) (m) (m)

1 Patching of damaged concrete surface


Substructure(30 % of surface area) sqm 2 8.240 3.500 17.304
Total 17.304
ESTIMATE OF QUANTITY FOR REPAIRING , REHABILITATION AND PROTECTION WORK OF
BRIDGE

Chainage= 54.332 Km SPAN ARRANGEMENT - 3 X 12.1 M

Length Breadth Height


Item No. Description Unit nos Quantity
(m) (m) (m)

1 Painting on concrete surface


Kerb below railing sqm 2 43.300 1.350 116.910
Railing post sqm 60 0.800 0.900 43.200
Railing beam sqm 4 0.690 43.300 119.508
Total= 279.618
ESTIMATE OF QUANTITY FOR REPAIRING , REHABILITATION AND PROTECTION WORK OF
BRIDGE

Chainage= 56.461 Km SPAN ARRANGEMENT - 2 X 10 M

Length Breadth Height


Item No. Description Unit nos Quantity
(m) (m) (m)

1 Painting on concrete surface


Kerb below railing sqm 2 28.000 1.050 58.800
Railing post sqm 40 0.800 0.900 28.800
Railing beam sqm 4 0.690 28.000 77.280
Total= 164.880
ESTIMATE OF QUANTITY FOR REPAIRING , REHABILITATION AND PROTECTION WORK OF
BRIDGE

Chainage= 56.985 Km SPAN ARRANGEMENT - 2 X 11 M

Length Breadth Height


Item No. Description Unit nos Quantity
(m) (m) (m)

1 Painting on concrete surface


Kerb below railing sqm 2 30.000 1.185 71.100
Railing post sqm 42 1.000 0.800 33.600
Railing beam sqm 4 0.690 30.000 82.800
Total= 187.500
Volume-VIII: Bill of Quantites
BILL OF QUANTITIES & COST ESTIMATE
BILL NO. 1. SITE CLEARANCE

SOR Ref.of
RATE AMOUNT
SL. NO. Item MoRT& DESCRIPTION UNIT QUANTITY
(INR) (INR)
No. H
Cutting of Trees, including Cutting of Trunks, Branches and Removal (Cutting of
trees, including cutting of trunks, branches and removal of stumps, roots, stacking
2.1
of serviceable material with all lifts and up to a lead of 1000 m and earth filling in
the depression/pit.)
1.1 201
(i) Girth from 300 mm to 600 mm Each 698
(ii) Girth from 600 mm to 900 mm Each 542
(iii) Girth from 900 mm to 1800 mm Each 287
(iv) Girth above 1800 mm Each 137
Clearing and Grubbing Road Land (Clearing and grubbing road land including
uprooting rank vegetation, grass, bushes, shrubs, saplings and trees girth up to 300
mm, removal of stumps of trees cut earlier and disposal of unserviceable materials
2.3 and stacking of serviceable material to be used or auctioned up to a lead of 1000
metres including removal and disposal of top organic soil not exceeding 150 mm in
thickness.)
(ii) By Mechanical Means
A In area of light jungle hectare 68.20
1.2 201 Dismantling of Structures (Dismantling of existing structures like culverts, bridges,
retaining walls and other structure comprising of masonry, cement concrete, wood
work, steel work, including T&P and scaffolding wherever necessary, sorting the
2.4 dismantled material, disposal of unserviceable material and stacking the
serviceable material with all lifts and lead of 1000 metres)

c. Prestressed / Reinforced cement concrete grade M-20 & above


2.4 (l) By Mechanical Means for items No. 202( b) & ( c)
.ii b Prestressed / Reinforced cement concrete grade M-20 & above cum 251.40
Dismantling of Flexible Pavements (Dismantling of flexible pavements and
disposal of dismantled materials up to a lead of 1000 metres, stacking serviceable
2.5
and unserviceable materials separately)
1.3 II. 202 By Mechanical Means
a. Bituminous courses cum 7575.00
2.5 I. Granular courses (manual means)
b. cum 15150.00
Total of Bill No.-1
BILL OF QUANTITIES & COST ESTIMATE
BILL NO. 2. EARTHWORK, EROSION CONTROLL AND DRAINAGES

SOR Item Ref.of RATE AMOUNT


SL. NO. DESCRIPTION UNIT QUANTITY
No. MoRT&H (INR) (INR)

Excavation in Soil using Hydraulic Excavator CK 90 and Tippers with disposal upto
1000 metres. (Excavation for roadwork in soil with hydraulic excavator of 0.9 cum
2.1 3.6 301 bucket capacity including cutting and loading in tippers, trimming bottom and side cum 279738.00
slopes, in accordance with requirements of lines, grades and cross sections, loading
and disposal of cut road within all lifts and lead upto 1000m)
Embankment Construction with Material Obtained from Borrow Pits (Construction
of embankment with approved material obtained from borrow pits with all lifts and
leads, transporting to site, spreading, grading to required slope and compacting to
2.2 3.16.A 305 meet requirement of table 300-2(including compensation of earth.) (Including cost
of testing oe materials at site and laboratory as directed by the deptt.)
from private land cum 751149.40
Construction of Embankment with Material Deposited from Roadway Cutting
(Construction of embankment with approved materials deposited at site from
2.3 3.17 305 cum 195816.60
roadway cutting and excavation from drain and foundation of other structures
graded and compacted to meet requirement of table 300-2)
Construction of Subgrade and Earthen Shoulders (Construction of subgrade and
earthen shoulders with approved material obtained from borrow pits with all lifts &
leads, transporting to site, spreading, grading to required slope and compacted to
2.4 3.18a 305 meet requirement of table No. 300-2) (including compensation of earth.)(a),(
Including cost of testing of naterials at site and laboratory as directed by the deptt.)
from private land cum 188384.78
Seeding and Mulching (Preparation of seed bed on previously laid top soil,
furnishing and placing of seeds, fertilizer, mulching material, applying bituminous
2.5 3.22 307 emulsion at the rate of 0.23 litres per sqm and laying and fixing jute netting, sqm 120666.87
including watering for 3 months all as per clause 308)
Construction of Median and Island with Soil Taken from Borrow Areas
(Construction of median and Island above road level with approved material
2.6 4.14 407 cum 25347.97
brought from borrow pits, spread, sloped and compacted as per clause 407)

Surface Drains in Soil (Mechanical means)


Construction of unlined surface drains of average cross sectional area 0.40 sqm in
2.7 3.24 A soil to specified lines, grades, levels and dimensions to the requirement of clause Rm 31423.780
301 and 309. Excavated material to be used in embankment within a lead of 50
metres (average lead 25 metres)
Total of Bill No.-2
BILL OF QUANTITIES & COST ESTIMATE
BILL NO. 3. SUB-BASES, BASES ( NON- BITUMINOUS) AND SHOULDERS

SOR Ref.of RATE AMOUNT


SL. NO. DESCRIPTION UNIT QUANTITY
Item No. MoRT&H (INR) (INR)

4.1 401 Granular Sub-Base with Close Graded Material (Table:- 400-1)
Plant Mix Method (Construction of granular sub-base by providing close graded Material,
mixing in a mechanical mix plant at OMC, carriage of mixed Material to work site,
spreading in uniform layers with motor grader on prepared surface and compacting with
vibratory power roller to achieve the desired density, complete as per clause 401( with an
initial lead of 5 km ) (Including cost of testing of materials at sitf and laboratory as directed
3.1
by the dept.)

(i) for grading- I Material cum 16274.51


for grading-III Material cum 6977.11
Wet Mix Macadam (Providing, laying, spreading and compacting graded stone aggregate
to wet mix macadam specification including premixing the Material with water at OMC in
mechanical mix plant carriage of mixed Material by tipper to site, laying in uniform layers
3.2 4.12 406 with paver in sub- base / base course on well prepared surface and compacting with cum 26200.99
vibratory roller to achieve the desired density. (including carriage up to initial lead of 5.0
km from quarry and carriage of mixed naterials up to 10.0 km initial lead from mixing
plant)

Cement Treated Crushed Rock or combination as per clause 403.2 and table 400.4in Sub
base/ Base ( Providing, laying and spreading Material on a prepared sub grade, adding the
designed quantity of cement to the spread Material, mixing in place with rotavator,
3.3 4.3 403
grading with the motor grader and compacting with the road roller at OMC to achieve the
desired unconfined compressive strength and to form a layer of sub-base/base.

(i) For Sub-Base course cum 66984.87


(ii) For Base course cum 25249.60
3.4 Non-Sch GSB Reuse cum 9090.00
3.5 Non-Sch RAP cum 7461.68
3.6 Non-Sch Geocell sqm 82874.05
3.7 Recycling of Existing Pavement(Including Plant & Machinery, Labour) Lumsum

Total of Bill No.-3


BILL OF QUANTITIES & COST ESTIMATE
BILL NO. 4. BITUMINOUS SURFACE COURSE

Ref.of RATE AMOUNT


SL.NO SOR Item No. DESCRIPTION UNIT QUANTITY
MoRT&H (INR) (INR)

Prime coat (Providing and applying primer coat with bitumen emulsion on
prepared surface of granular Base including clearing of road surface and
spraying primer at the rate of 1.0 kg/sqm using mechanical means.)(Including
4.1 5.1 A (i) 502
cost of testing of materials at sitfe and laboratory as directed by the depttt.)

with bitumen emulsion-CSS-1 h sqm 327150.89


Tack coat Providing and applying tack coat with bitumen emulsion using
emulsion pressure distributor at the rate of 0.20 kg per sqm on the prepared
5.2 bituminous/granular surface cleaned with mechanical broom.(Including cost of
testing of materials at sitfe and laboratory as directed by the depttt.)
4.2 503
(I) with bitumen emulsion-CSS-1 h
(a) Normal bituminious surface sqm 21543.00
( c) Granular surface treated with primer sqm 327150.89
Ref.of RATE AMOUNT
SL.NO SOR Item No. DESCRIPTION UNIT QUANTITY
MoRT&H (INR) (INR)

Dense Graded Bituminous Macadam (Providing and laying dense bituminous


macadam with 100-120 TPH batch type HMP producing an average output of 75
tonnes per hour using crushed aggregates of specified grading, premixed with
bituminous binder @ 4.0 to 4.5% by weight of total mix of mix and filler,
transporting the hot mix to work site, laying with a hydrostatic paver finisher
with sensor control to the required grade, level and alignment, rolling with
5.6 smooth wheeled, vibratory and tandem rollers to achieve the desired
compaction as per MoRTH specification clause No. 507 complete in all
4.3 507 respects.)(including carriage up to initial lead of 5.0 km from quarry and
carriage of mixed naterials up to 10.0 km initial lead from mixing
plant)(Including cost of testing of materials at sitfe and laboratory as directed
by the depttt.)

With hydrated lime/cement as filler(refer table 500-9 of MoRT&H


A.
specification)
(I) With 40/60 or VG -40 grade bitumen
(i) for Grading II ( 19 mm nominal size ) cum 21974.90
Bituminous Concrete (Providing and laying bituminous concrete with 100-120
TPH batch type hot mix plant producing an average output of 75 tonnes per
hour using crushed aggregates of specified grading, premixed with bituminous
binder @ 5.4 to 5.6 % of mix and filler, transporting the hot mix to work site,
laying with a hydrostatic paver finisher with sensor control to the required
grade, level and alignment, rolling with smooth wheeled, vibratory and tandem
5.6
rollers to achieve the desired compaction as per MORTH specification clause
No. 509 complete in all respects)(including carriage up to initial lead of 5.0 km
4.4 507
from quarry and carriage of mixed naterials up to 10.0 km initial lead from
mixing plant)(Including cost of testing of materials at sitfe and laboratory as
directed by the depttt.)

With hydrated lime/cement as filler(refer table 500-9 of MoRT&H


A.
specification)
(I) With 40/60 or VG -40 grade bitumen
(i) for Grading II ( 13 mm nominal size ) cum 13947.76

Total of Bill No.-4


BILL OF QUANTITIES & COST ESTIMATE
BILL NO.5 TRAFFIC SIGNS, ROAD MARKING AND OTHER ROAD APPURTENANCES

SOR Item Ref.of RATE AMOUNT


SL. NO. DESCRIPTION UNIT QUANTITY
No. MoRT&H (INR) (INR)

Cast in Situ Cement Concrete M20 kerb (Construction of cement concrete kerb with
top and bottom width 115 and 165 mm respectively, 250 mm high in M 20 grade PCC
on M-10 grade foundation 150 mm thick, foundation having 50 mm projection
5.1 8.1 408
beyond kerb stone, kerb stone laid with kerb laying machine, foundation concrete
laid manually, all complete as per clause 408)

B Using Concrete Batching and Mixing Plant metre 33180


Retro- reflectorised Traffic signs (Providing and fixing of retro- reflectorised
cautionary, mandatory and informatory sign as per IRC :67 made of encapsulated
lens type reflective sheeting vide clause 801.3, fixed over aluminium sheeting, 2.0
mm thick fixed on an angle iron of 25x25x4mm supported on a mild steel angle iron
8.4 post 75 mm x 75 mm x 6 mm firmly fixed to the ground by means of properly
designed foundation with M15 grade cement concrete 45 cm x 45 cm x 60 cm, 60 cm
5.2 below ground level as per approved drawing and signs(All steel work must be
Tata/Sail/or any other approved brand)

(i) 90 cm equilateral triangle each 91


( iii ) 60 cm circular each 10
( iv ) 80 mm x 60 mm rectangular each 8
( vii ) 90 cm high octagon each 25
Direction and Place Identification signs upto 0.9 sqm size board.(Providing and
erecting direction and place identification retro-reflectorised sign asper IRC:67 made
of encapsulated lens type reflective sheeting vide clause 801.3, fixed over aluminium
sheeting, 2 mm thick with area not exceeding 0.9 sqm fixed on an angle iron of
5.3 8.5 801 25x25x4mm supported on a mild steel angle iron post 75 mm x 75 mm x 6 mm sqm 15
firmly fixed to the ground by means of properly designed foundation with M15 grade
cement concrete 45 cm x 45 cm x 60 cm, 60 cm below ground level as per approved
drawing and signs(All steel work must be Tata/Sail/or any other approved brand)
SOR Item Ref.of RATE AMOUNT
SL. NO. DESCRIPTION UNIT QUANTITY
No. MoRT&H (INR) (INR)

804 Kilo Metre Stone (Reinforced cement concrete M15grade kilometre stone of
8.14 standard design as per IRC:8-1980, fixing in position including painting and printing
etc)
5.5
(i) 5th kilometre stone (precast) each 8
(ii) Ordinary Kilometer stone (Precast) each 22
(iii) Hectometer stone (Precast) each 58
Road Delineator
Providing metal tubular delineator (50mm dia & 1.25mm thick )with 15 cm reflector
made of heigh intensity grade retro reflectorised sheeting around the pipe at top
covered with wire mesh of 20cm length with 2 nos of similar reflective bends and
5.6 8.54 bottom fastner M.S.angle including firmly fixing the delineator to the ground by each 637
means of CC (M-15) foundation of size (25x25x25cm),25cm below ground to the true
line and level as directed by the deptt. With six months replacement warranty and
free maintenance.
b) 750 mm ht.
Boundary pillar (Reinforced cement concrete M15 grade boundary pillars of
5.7 8.16 806 standard design as per IRC:25-1967, fixed in position including finishing and lettering each 178
but excluding painting)
SOR Item Ref.of RATE AMOUNT
SL. NO. DESCRIPTION UNIT QUANTITY
No. MoRT&H (INR) (INR)

pole Height 6m:The materials of the pole as follows:Conforming to grade


S355JO,Base plate Fe 410 conforming to IS 226/IS 2062, Foundation Bolts:-6.8 Gr. As
per IS 1367, Plole sections:- The octagonal poles shall be in single piece with single
longitudinal welding join.Galvanization:-The pole shall be hot dip galvanized as per IS
2629/IS 2633/IS 4759 standards with average coating thickness of 65 micron.The
galvanizing shal be done in single dipping. Door opening:-The octagonal poles shall
have door of approxinate 500 mm length at the elevation of 500 mm from the base
plate.The door shall be vandal resistance and shall be weather proof to ensure saefty
of of inside connections.The door shall be flush with the exterior surface and shall
have suitable locking arrangement.The pole shall be adequately strengthened at the
location of the door compensate for the loss in the section.There shall also be
5.8 iv) suitable arrangement for the purpose of earthing,smart pack junction box with 6 each 185
MCB & Terminals for mounting inside base compartment of pole.Top dia(A/F) 70
Bottom Dia. (A/F) 130, Sheet thickness 3 mm, Base Plate Dimensions(LXBXT)
220x220x12, Foundation Bolt, Bolt size:-(noxdia) 4x20 dia, pitch circle dia.(PCD)
205,Bolt length 600,Projected Bolt Length 100, Anchor plate thickness:- 4 mm,Pole
Foundation :- The octagonal poles shall be bolted on a pre - cast foundation with a
set of four foundation bolts for greater rigidity. Foundation :- The foundation shall be
done with (i) Earth work:- 2.04 cubic Meters.(ii)RCC:- 1:1.5:3 proportion 0.65 cubic
meters. (iii0 Steel:-22.43 kg .(iv0 Shuttering:-4.32 square meters.=22.43 kg.
SOR Item Ref.of RATE AMOUNT
SL. NO. DESCRIPTION UNIT QUANTITY
No. MoRT&H (INR) (INR)

5.9 8.13 803 Road Marking with Hot Applied Thermoplastic Compound (Providing and laying of
hot applied thermoplastic compound 2.5 mm thick including reflectorising glass
beads @ 250 gms per sqm area, thickness of 2.5 mm is exclusive of surface applied sqm 13800.000
glass beads as per IRC:35 .The finished surface to be level, uniform and free from
streaks and holes.
5.10 8.35
Road Markers/Road Stud with Lense Reflector
Providing and fixing of road stud 100x 100 mm, die-cast in aluminium, resistant to
corrosive effect of salt and grit, fitted with lense reflectors, installed in concrete or nos 1188
asphaltic surface by drilling hole 30 mm upto a depth of 60 mm and bedded in a
suitable bituminous grout or epoxy mortar, all as per BS 873 part 4:1973

5.11 8.23 A W-Metal beam crash barrier


Providing and erecting a "W" metal beam crash barrier comprising of 3 mm thick
corrugated sheet metal beam rail, 70 cm above road/ground level, fixed on ISMC
series channel vertical post, 150 x 75 x 5 mm spaced 2 m centre to centre, 1.8 m
metre 15158.240
high, 1.1 m below ground/road level, all steel parts and fitments to be galvanised by
hot dip process, all fittings to conform to IS:1367 and IS:1364, metal beam rail to be
fixed on the vertical post with a spacer of channel section 150 x 75 x 5 mm, 330 mm
long complete as per clause 810

Total of Bill No.-5


BILL OF QUANTITIES & COST ESTIMATE
BILL NO. 6. DRAINAGE & PROTECTION WORK

SL. SOR Item Ref.of RATE AMOUNT


DESCRIPTION UNIT QUANTITY
NO. No. MoRT&H (INR) (INR)
RCC Cover Drain
Excavation for Structures (Earth work in excavation of foundation of
structures as per drawing and technical specification, including setting out,
construction of shoring and bracing, removal of stumps and other
deleterious matter, dressing of sides and bottom, backfilling the excavation
3.13 (I) . earth to the extent required and utilising the remaining earth locally for
6.1 304 cum 6725.51
A road work.)
i) Ordinary soil
A. a)Mechanical Means, with dewatering
upto 3 m depth
1500,1700 Plain/Reinforced cement concrete in open foundation complete as per
12.8 & 2100 drawing and technical specifications including steel shuttering forrmwork
6.2
A. Without plasticiser

(a) PCC Grade M15 cum 574.540


1500,1700 Plain/Reinforced cement concrete in sub-structure complete as per drawing
13.5 & 2200 and technical specifications
6.3 N(A).f. Without plasticiser
RCC Grade M25
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 2654.240
1600 & Reinforcement in Substructure :Supplying, fitting and placing un-coatedTMT
2300 bar reinforcement in foundation complete as per drawing and technical
13.6 (a) specifications
6.4 tonne 185.80
(i) a) From primary sources: TATA/SAIL/Esser Steel/Jindal steel/Shyam steel
i) TMT Corrosion Resistance Steel (CRS) reinforcement bar of Fe-500 N/mm2
2200 & Providing weep holes in Brick masonry/Plain/Reinforced concrete
2706 abutment, wing wall/return wall with 100 mm dia AC pipe, extending
6.5 13.8 through the full width of the structure with slope of 1V :20H towards each 7378.000
drawing foce. Complete as per drawing and Technical specifications
SL. SOR Item Ref.of RATE AMOUNT
DESCRIPTION UNIT QUANTITY
NO. No. MoRT&H (INR) (INR)
RR Masonry Chute Drain
Excavation for Structures (Earth work in excavation of foundation of
structures as per drawing and technical specification, including setting out,
construction of shoring and bracing, removal of stumps and other
deleterious matter, dressing of sides and bottom, backfilling the excavation
3.13 (I) B. earth to the extent required and utilising the remaining earth locally for
6.6 304 cum 711.900
(a) road work.)
i) Ordinary soil
A. a)Manual Means, with dewatering
upto 3 m depth
6.16 1500, 1700 Plain/Reinforced Cement Concrete in Open Foundation complete as per
& 2100 Drawing and Technical Specifications.
B Without plasticiser
PCC Grade M20 cum 457.890
6.7 15.4 2504 Stone Pitching cum 203.400
SL. SOR Item Ref.of RATE AMOUNT
DESCRIPTION UNIT QUANTITY
NO. No. MoRT&H (INR) (INR)
For RE Wall
6.6 3.18a 305 Embankment Filling by Subgrade Material cum 137609.47
6.7 Embankment Filling by Sand cum 137609.48
Reinforced Earth Stuctures (Reference to MORT&H's specifications 3100 ).
7.5 3100
With reinfocing element of synthetic geogrids
6.8
(i) Facing Element of RCC sqm 38734.10
(ii) With reinforcing element of synthetic geogrids sqm 38734.10
1500,1700 Plain/Reinforced cement concrete in open foundation complete as per
12.8 & 2100 drawing and technical specifications including steel shuttering forrmwork

6.9 A. Without plasticiser


(a) PCC Grade M15 cum 987.000
(E) RCC Grade M25
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 4146.139
12.4 0 1600 & Supplying, fitting and placing HYSD bar reinforcement in foundation
tonne 290.23
6.10 (a). (i) 2300
13.10 Filter Media cum 23237
Reinforced Cement Concrete Crash Barrier (Provision of an Reinforced
cement concrete crash barrier at the edges of the road, approaches to
bridge structures and medians, constructed with M-20 grade concrete with
HYSD reinforcement conforming to IRC:21 and dowel bars 25 mm dia, 450
mm long at expansion joints filled with pre-moulded asphalt filler board,
6.11 8.22 (ii) 809 keyed to the structure on which it is built and installed as per design given in metre 4936
the enclosure to MORT&H circular No. RW/NH - 33022/1/94-DO III dated
June 1994 as per dimensions in the approved drawing and at locations
directed by the Engineer, all as specified
SL. SOR Item Ref.of RATE AMOUNT
DESCRIPTION UNIT QUANTITY
NO. No. MoRT&H (INR) (INR)
For Retaining Wall
Excavation for Structures (Earth work in excavation of foundation of
structures as per drawing and technical specification, including setting out,
construction of shoring and bracing, removal of stumps and other
deleterious matter, dressing of sides and bottom, backfilling the excavation
3.13 (I) . earth to the extent required and utilising the remaining earth locally for
6.18 304 cum 2083.08
A road work.)
i) Ordinary soil
A. a)Mechanical Means, with dewatering
upto 3 m depth
12.7 1400 Stone masonry work in cement mortar 1:3 for foundation
6.20
B RR Masonry cum 1788.50
1500,1700 Plain/Reinforced cement concrete in open foundation complete as per
12.8 & 2100 drawing and technical specifications including steel shuttering forrmwork
6.21
A. Without plasticiser
(a) PCC Grade M15 cum 1009.980
1400 &
12.7 Stone masonry work in cement mortar 1:3 for substructure
2200
6.22
B RR Masonry cum 2503.90
CR Masonry cum 437.40
2200 & Providing weep holes in Brick masonry/Plain/Reinforced concrete
2706 abutment, wing wall/return wall with 100 mm dia AC pipe, extending
6.23 13.8 through the full width of the structure with slope of 1V :20H towards each 2104.12
drawing foce. Complete as per drawing and Technical specifications
710.1.4 of Providing and laying of Filter media with granular materials/stone crushed
IRC:78 & aggregates satisfying the requirements laid down in clause 2504.2.2. of
2200 MoRTH specifications to a thickness of not less than 600 mm with smaller
6.24 13.10 size towards the soil and bigger size towards the wall and provided over the Cum 2798.48
entire surface behind abutment, wing wall and return wall to the full height
compacted to a firm condition complete as per drawing and technical
specification.
SL. SOR Item Ref.of RATE AMOUNT
DESCRIPTION UNIT QUANTITY
NO. No. MoRT&H (INR) (INR)
Toe Wall
6. 24 Excavation for Structures (Earth work in excavation of foundation of
structures as per drawing and technical specification, including setting out,
construction of shoring and bracing, removal of stumps and other
deleterious matter, dressing of sides and bottom, backfilling the excavation
3.13 (I) . earth to the extent required and utilising the remaining earth locally for
304 cum 1426.53
A road work.)
i) Ordinary soil
A. a)Mechanical Means, with dewatering
upto 3 m depth

6.25 1500,1700 Plain/Reinforced cement concrete in open foundation complete as per


12.8 & 2100 drawing and technical specifications including steel shuttering forrmwork
A. Without plasticiser
(a) PCC Grade M15 cum 158.52
6.26 13.5 F (p)
RCC Substructure M25 Height 5M cum 1435.84
Case II
6.27 Supplying, Fitting and Placing un-coated HYSD bar Reinforcement in
12.4 Foundation complete as per Drawing and Technical Specifications. tonne 100.51

Ground Improvement Works (Sand Pile)


6. 28 Non Sche Driven cast-in-place vertical Sand Pile complete as per Drawing and &
m 53220.00
Technical Specification

Total of Bill No.-6


BILL OF QUANTITIES & COST ESTIMATE
BILL NO. 7. BUS- BAY WITH PASSENGER SHELTER & TRUCK LAY BYE

SOR Item Ref.of RATE AMOUNT


SL. NO. DESCRIPTION UNIT QUANTITY
No. MoRT&H (INR) (INR)

A. Bus Bay

Cement Treated Crushed Rock or combination as per clause 403.2 and table
400.4in Sub base/ Base ( Providing, laying and spreading Material on a
prepared sub grade, adding the designed quantity of cement to the spread
7.1 4.3 403 Material, mixing in place with rotavator, grading with the motor grader and
compacting with the road roller at OMC to achieve the desired unconfined
compressive strength and to form a layer of sub-base/base.

(i) For Sub-Base course cum 1004.000


(ii) For Base course cum 502.000
Wet Mix Macadam (Providing, laying, spreading and compacting graded
stone aggregate to wet mix macadam specification including premixing the
Material with water at OMC in mechanical mix plant carriage of mixed
Material by tipper to site, laying in uniform layers with paver in sub- base /
7.2 4.12 406 base course on well prepared surface and compacting with vibratory roller to cum 502.000
achieve the desired density. (including carriage up to initial lead of 5.0 km
from quarry and carriage of mixed naterials up to 10.0 km initial lead from
mixing plant)

Providing and applying Primer coat over WMM layer using bitumen emulsion
7.3 5.1 A (i) 502 (Grade SS-1) @ 0.85Kg / sqm as per drawings and Technical specifications sqm 5020.000
clause 502 and as directed by the Engineer.
Tack coat Providing and applying tack coat with bitumen emulsion using
emulsion pressure distributor at the rate of 0.20 kg per sqm on the prepared
5.2 bituminous/granular surface cleaned with mechanical broom.(Including cost
7.4 503 of testing of materials at sitfe and laboratory as directed by the depttt.)

(I) with bitumen emulsion-CSS-1 h


(c) Granular surface treated with primer sqm 5020.00
Construction of Subgrade and Earthen Shoulders (Construction of subgrade
and earthen shoulders with approved material obtained from borrow pits
with all lifts & leads, transporting to site, spreading, grading to required slope
7.5 3.18a 305 and compacted to meet requirement of table No. 300-2) (including
compensation of earth.)(a),( Including cost of testing of naterials at site and
laboratory as directed by the deptt.)
SOR Item Ref.of RATE AMOUNT
SL. NO. DESCRIPTION UNIT QUANTITY
No. MoRT&H (INR) (INR)

from private land cum 2510.00


SOR Item Ref.of RATE AMOUNT
SL. NO. DESCRIPTION UNIT QUANTITY
No. MoRT&H (INR) (INR)

Dense Graded Bituminous Macadam (Providing and laying dense bituminous


macadam with 100-120 TPH batch type HMP producing an average output of
75 tonnes per hour using crushed aggregates of specified grading, premixed
with bituminous binder @ 4.0 to 4.5% by weight of total mix of mix and filler,
transporting the hot mix to work site, laying with a hydrostatic paver finisher
with sensor control to the required grade, level and alignment, rolling with
7.6 5.6 A (I) 505 smooth wheeled, vibratory and tandem rollers to achieve the desired
compaction as per MoRTH specification clause No. 507 complete in all
respects.)(including carriage up to initial lead of 5.0 km from quarry and
carriage of mixed naterials up to 10.0 km initial lead from mixing
plant)(Including cost of testing of materials at sitfe and laboratory as directed
by the depttt.)

(ii) for Grading II (With 40/60 or VG -40 grade bitumen) (for Grading II ( 40 mm
cum 301.200
nominal size )
Bituminous Concrete (Providing and laying bituminous concrete with 100-
120 TPH batch type hot mix plant producing an average output of 75 tonnes
per hour using crushed aggregates of specified grading, premixed with
bituminous binder @ 5.4 to 5.6 % of mix and filler, transporting the hot mix
to work site, laying with a hydrostatic paver finisher with sensor control to
the required grade, level and alignment, rolling with smooth wheeled,
5.8 A (I) 507 vibratory and tandem rollers to achieve the desired compaction as per
7.7 MORTH specification clause No. 509 complete in all respects)(including
carriage up to initial lead of 5.0 km from quarry and carriage of mixed
naterials up to 10.0 km initial lead from mixing plant)(Including cost of testing
of materials at sitfe and laboratory as directed by the depttt.)

(Ii) for Grading-I (19 mm nominal size) cum 200.800


Cast in Situ Cement Concrete M20 kerb (Construction of cement concrete
kerb with top and bottom width 115 and 165 mm respectively, 250 mm high
8.1 408 in M 20 grade PCC on M-10 grade foundation 150 mm thick, foundation
7.8 having 50 mm projection beyond kerb stone, kerb stone laid with kerb laying
machine, foundation concrete laid manually, all complete as per clause 408)
A Using Concrete Mixer metre 252
Construction of Median and Island with Soil Taken from Roadway Cutting
(Construction of Median and Island above road level with approved material
7.9 4.13 407 deposited at site from roadway cutting and excavation for drain and cum 51
foundation of other structures, spread, graded and compacted as per clause
407)
SOR Item Ref.of RATE AMOUNT
SL. NO. DESCRIPTION UNIT QUANTITY
No. MoRT&H (INR) (INR)

Passenger Shelter
Excavation for Structures (Earth work in excavation of foundation of
structures as per drawing and technical specification, including setting out,
construction of shoring and bracing, removal of stumps and other deleterious
matter, dressing of sides and bottom, backfilling the excavation earth to the
3.13 (I) .
7. 10 304 extent required and utilising the remaining earth locally for road work.) cum 21.120
(A)
i) Ordinary soil
A. a)Manual Means, with dewatering
upto 3 m depth

1300 Brick masonry (Brick masonry work in cement mortar 1:3 in foundation
7.11 12.5 complete excluding pointing and plastering, as per drawing and technical cum 6.080
specifications
1300 Brick masonry (Brick masonry work in cement mortar 1:3 in Super Structure
7.12 12.5 complete excluding pointing and plastering, as per drawing and technical cum 17.520
specifications
1500, Plain/Reinforced cement concrete in open foundation -RCC M25-Without
7.13 12.8 C 1700 & plasticiser(With Batching Plant, Transit Mixer and Concrete Pump) cum 2.280
2100
Reinforcement in foundation-TMT Bar (From primary sources:
12.4 0 (a).
7.14 1600 TATA/SAIL/Esser Steel/Jindal steel/Shyam steel)-TMT Corrosion Resistance Tonne 0.160
(i)
Steel (CRS) reinforcement bar of Fe-500 N/mm2
Plain/Reinforced cement concrete in super-structure complete as per
1500,1700 drawing and Technical Specifications section 1500,1700& 2200 and as
7.15 12.8 A (a) cum 4.040
& 2200 directed by the Engineer.
PCC M15
14.1 A Furnishing and Placing Reinforced/ Prestressed cement concrete in super-
1500
case -II( i) structure as per drawing and Technical Specification section 1500,1700 &
7.16 &1600,17 cum 14.720
a). 2300 and as directed by the Engineer.
00, 2300
RCC M25

Supplying, fitting and placing HYSD/TMT bar reinforcement in super-structure


1600 &
7.17 14.2 (a). (i complete as per drawing and technical specifications section 1600 & 2300 Tonne 1.120
2300
and as directed by the Engineer.

1300 & Plastering with cement mortar (1:3 ) on brick work in super-structure as per
7.18 13.3 2200 Technical specifications sqm 249.480

Total of Bus bay with passenger shelter=

Total of Bill No.-7


BILL OF QUANTITIES & COST ESTIMATE
BILL NO. 8. JUNCTION

SL. SOR Ref. Ref.of RATE AMOUNT


DESCRIPTION UNIT QUANTITY
NO. No MoRT&H (INR) (INR)
Cement Treated Crushed Rock or combination as per clause 403.2 and table
400.4in Sub base/ Base ( Providing, laying and spreading Material on a
prepared sub grade, adding the designed quantity of cement to the spread
8.1 4.3 403 Material, mixing in place with rotavator, grading with the motor grader and
compacting with the road roller at OMC to achieve the desired unconfined
compressive strength and to form a layer of sub-base/base.

(i) For Sub-Base course cum 1100.00


(ii) For Base course cum 550.00
5.1 A Prime coat
Prime coat (Providing and applying primer coat with bitumen emulsion on
prepared surface of granular Base including clearing of road surface and
8.2 502 spraying primer at the rate of 0.60 kg/sqm using mechanical means.)(Including
cost of testing of materials at sitfe and laboratory as directed by the depttt.)

(i) with bitumen emulsion-CSS-1 h sqm 5500.00


Tack coat Providing and applying tack coat with bitumen emulsion using
emulsion pressure distributor at the rate of 0.20 kg per sqm on the prepared
5.2 (I) bituminous/granular surface cleaned with mechanical broom.(Including cost of
8.3 503 testing of materials at sitfe and laboratory as directed by the depttt.)

with bitumen emulsion-CSS-1 h


(b) Granular surface treated with primer sqm 5500.00
Wet Mix Macadam (Providing, laying, spreading and compacting graded stone
aggregate to wet mix macadam specification including premixing the Material
with water at OMC in mechanical mix plant carriage of mixed Material by tipper
to site, laying in uniform layers with paver in sub- base / base course on well
8.4 4.12 406 cum 550.00
prepared surface and compacting with vibratory roller to achieve the desired
density. (including carriage up to initial lead of 5.0 km from quarry and carriage
of mixed naterials up to 10.0 km initial lead from mixing plant)
SL. SOR Ref. Ref.of RATE AMOUNT
DESCRIPTION UNIT QUANTITY
NO. No MoRT&H (INR) (INR)
Bituminous Concrete (Providing and laying bituminous concrete with 100-120
TPH batch type hot mix plant producing an average output of 75 tonnes per
hour using crushed aggregates of specified grading, premixed with bituminous
binder @ 5.4 to 5.6 % of mix and filler, transporting the hot mix to work site,
laying with a hydrostatic paver finisher with sensor control to the required
grade, level and alignment, rolling with smooth wheeled, vibratory and tandem
8.5 5.8 rollers to achieve the desired compaction as per MORTH specification clause
No. 509 complete in all respects)(including carriage up to initial lead of 5.0 km
from quarry and carriage of mixed naterials up to 10.0 km initial lead from
mixing plant)(Including cost of testing of materials at sitfe and laboratory as
directed by the depttt.)

With hydrated lime/cement as filler(refer table 500-9 of MoRT&H


A.
specification)
(I) With 40/60 or VG -40 grade bitumen
(ii) for GradingII(13 mm nominal size) cum 220.000
Dense Graded Bituminous Macadam (Providing and laying dense bituminous
macadam with 100-120 TPH batch type HMP producing an average output of 75
tonnes per hour using crushed aggregates of specified grading, premixed with
bituminous binder @ 4.0 to 4.5% by weight of total mix of mix and filler, transporting
the hot mix to work site, laying with a hydrostatic paver finisher with sensor control to
the required grade, level and alignment, rolling with smooth wheeled, vibratory and
8.6 5.6
tandem rollers to achieve the desired compaction as per MoRTH specification clause
No. 507 complete in all respects.)(including carriage up to initial lead of 5.0 km from
quarry and carriage of mixed naterials up to 10.0 km initial lead from mixing
plant)(Including cost of testing of materials at sitfe and laboratory as directed by the
depttt.)

With hydrated lime/cement as filler(refer table 500-9 of MoRT&H


A. specification)
(I) With 40/60 or VG -40 grade bitumen
(i) for Grading II ( 19 mm nominal size ) cum 330.00
Construction of Subgrade and Earthen Shoulders (Construction of subgrade
and earthen shoulders with approved material obtained from borrow pits with
all lifts & leads, transporting to site, spreading, grading to required slope and
8.7 3.18a 305
compacted to meet requirement of table No. 300-2) (including compensation of
earth.)(a),( Including cost of testing of naterials at site and laboratory as
directed by the deptt.)
from private land cum 2750.00

Total of Bill No.-8


BILL OF QUANTITIES & COST ESTIMATE
BILL NO. 9. SERVICE ROAD

SL. SOR Ref. Ref.of RATE AMOUNT


DESCRIPTION UNIT QUANTITY
NO. No MoRT&H (INR) (INR)

Cement Treated Crushed Rock or combination as per clause 403.2 and table
400.4in Sub base/ Base ( Providing, laying and spreading Material on a
prepared sub grade, adding the designed quantity of cement to the spread
9.1 4.3 403 Material, mixing in place with rotavator, grading with the motor grader and
compacting with the road roller at OMC to achieve the desired unconfined
compressive strength and to form a layer of sub-base/base.

(i) For Sub-Base course cum 5778.00


(ii) For Base course cum 2889.00
4.1 401 Granular Sub-base with Close Graded Material (Table:- 400-1)

Construction of Subgrade and Earthen Shoulders (Construction of subgrade


and earthen shoulders with approved material obtained from borrow pits
with all lifts & leads, transporting to site, spreading, grading to required slope
9.2 3.18a 305 and compacted to meet requirement of table No. 300-2) (including
compensation of earth.)(a),( Including cost of testing of naterials at site and
laboratory as directed by the deptt.)
from private land cum 14445.00

9.3 5.1 A 502 Prime coat


Prime coat (Providing and applying primer coat with bitumen emulsion on
prepared surface of granular Base including clearing of road surface and
spraying primer at the rate of 0.60 kg/sqm using mechanical
means.)(Including cost of testing of materials at sitfe and laboratory as
directed by the depttt.)
(i) with bitumen emulsion-CSS-1 h sqm 28890.00
Tack coat Providing and applying tack coat with bitumen emulsion using
emulsion pressure distributor at the rate of 0.20 kg per sqm on the prepared
9.4 5.2 (I) 503 bituminous/granular surface cleaned with mechanical broom.(Including cost
of testing of materials at sitfe and laboratory as directed by the depttt.)

with bitumen emulsion-CSS-1 h


(b) Granular surface treated with primer sqm 28890.00
SL. SOR Ref. Ref.of RATE AMOUNT
DESCRIPTION UNIT QUANTITY
NO. No MoRT&H (INR) (INR)
Wet Mix Macadam (Providing, laying, spreading and compacting graded
stone aggregate to wet mix macadam specification including premixing the
Material with water at OMC in mechanical mix plant carriage of mixed
Material by tipper to site, laying in uniform layers with paver in sub- base /
9.5 4.12 406 base course on well prepared surface and compacting with vibratory roller to cum 2889.00
achieve the desired density. (including carriage up to initial lead of 5.0 km
from quarry and carriage of mixed naterials up to 10.0 km initial lead from
mixing plant)
Bituminous Concrete (Providing and laying bituminous concrete with 100-120
TPH batch type hot mix plant producing an average output of 75 tonnes per
hour using crushed aggregates of specified grading, premixed with
bituminous binder @ 5.4 to 5.6 % of mix and filler, transporting the hot mix
to work site, laying with a hydrostatic paver finisher with sensor control to
the required grade, level and alignment, rolling with smooth wheeled,
9.7 5.8 vibratory and tandem rollers to achieve the desired compaction as per
MORTH specification clause No. 509 complete in all respects)(including
carriage up to initial lead of 5.0 km from quarry and carriage of mixed
naterials up to 10.0 km initial lead from mixing plant)(Including cost of testing
of materials at sitfe and laboratory as directed by the depttt.)

for Grading-II (With 40/60 or VG -40 grade bitumen) (for Grading II ( 13


(ii) cum 1155.60
mm nominal size )
Reinforced Cement Concrete Crash Barrier (M20)
Provision of an Reinforced cement concrete crash barrier at the edges of the
road, approaches to bridge structures and medians, constructed with M-20
grade concrete with HYSD reinforcement conforming to IRC:21 and dowel
bars 25 mm dia, 450 mm long at expansion joints filled with pre-moulded
9.11 8.22 metre 2622.00
asphalt filler board, keyed to the structure on which it is built and installed as
per design given in the enclosure to MOST circular No. RW/NH - 33022/1/94-
DO III dated 24 June 1994 as per dimensions in the approved drawing and at
locations directed by the Engineer, all as specified

Total of Bill No.-9


BILL OF QUANTITIES & COST ESTIMATE
BILL NO. 10. UTILITY DUCT

SOR Item Ref.of RATE AMOUNT


SL. NO. DESCRIPTION UNIT QUANTITY
No. MoRT&H (INR) (INR)

1 Non-Sch Laying of utility duct of HDPE pipe ( Group of 3 pipes 90mm dia.) m 52880.49
DETAILED COST ESTIMATES
BILL NO. 11 FOR MAJOR BRIDGES

Ref.of RATE AMOUNT


SL. NO. SOR Ref. No DESCRIPTION UNIT QUANTITY
MoRT&H (INR) (INR)

B.1 :: FOUNDATION
Excavation for Structures (Earth work in excavation of foundation of
structures as per drawing and technical specification, including setting out,
12.1 304 construction of shoring and bracing, removal of stumps and other
deleterious matter, dressing of sides and bottom and backfilling with
approved material.)
11.1
I. Ordinary soil
B. Mechanical Means
(b) with dewatering
(i) Depth upto 3 m cum 1795.340
(ii) Depth 3 m to 6 m cum 224.000
1500,170 Plain/Reinforced cement concrete in open foundation complete as per
12.8 0 &2100 drawing and technical specifications including steel shuttering forrmwork

11.2 A. Without plasticiser


(a) PCC Grade M15 cum 94.500
12.38 RCC Pile Cap M30
(A) III.(ii) Using Batching Plant, Transit Mixer and Concrete Pump cum 1061.740
1200 & Providing steel liner 10 mm thick for curbs and 6mm thick for steining of
11.3 12.22 1900 wells including fabricating and setting out as per detailed drawing tonne 9.590

1100 & Bored cast-in-situ M35 grade R.C.C. pile excluding reinforcement complete
1700 as per drawing and technical specifications and removal of excavated earth
11.4 12.25A metre 1734.000
with all lifts and lead upto 1000 m. (Pile diameter-1200 mm)

1600 Reinforcement in foundation :Supplying, fitting and placing un-


12.40 coatedTMT bar reinforcement in foundation complete as per drawing and
technical specifications
11.5 From primary sources: TATA/SAIL/Esser Steel/Jindal steel/Shyam steel
(a)
TMT Corrosion Resistance Steel (CRS) reinforcement bar of Fe-500 N/mm2
(i) tonne 320.977

TOTAL FOR B.1 :: FOUNDATION


Ref.of RATE AMOUNT
SL. NO. SOR Ref. No DESCRIPTION UNIT QUANTITY
MoRT&H (INR) (INR)

B.2 :: SUBSTRUCTURE
13.5 (N) .A 1500,170 Plain/Reinforced cement concrete in sub-structure complete as per drawing
.g.(i)-case II 0 &2200 and technical specifications
RCC Grade M30
Height upto 5m
With Batching Plant, Transit Mixer and Concrete Pump cum 456.81
11.6 13.5 (N) .A Height 5m to 10m
.g.(ii)-case II
With Batching Plant, Transit Mixer and Concrete Pump cum 186.16
h. RCC Grade M35
(i) Height 5m to 10m
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 42.060
1600 Supplying, fitting and placing TMT bar reinforcement in sub-structure
13.6 (a) (i)
&2200 complete as per drawing and technical specifications
From primary sources: TATA/SAIL/Esser Steel/Jindal steel/Shyam steel
11.7

TMT Corrosion Resistance Steel (CRS) reinforcement bar of Fe-500 N/mm2


tonne 95.904
2200 Providing weep holes in Brick masonry/Plain/Reinforced concrete
&2706 abutment, wing wall/return wall with 100 mm dia AC pipe, extending
11.8 13.8 through the full width of the structure with slope of 1V :20H towards each 378.000
drawing foce. Complete as per drawing and Technical specifications

710.1.4 of Back filling behind abutment, wing wall and return wall complete as per
13.9 IRC:78 & drawing and Technical specification
11.9 2200
A Granular material cum 245.700
B Sandy material cum 1019.540
Ref.of RATE AMOUNT
SL. NO. SOR Ref. No DESCRIPTION UNIT QUANTITY
MoRT&H (INR) (INR)

710.1.4 of Providing and laying of Filter media with granular materials/stone crushed
IRC:78 & aggregates satisfying the requirements laid down in clause 2504.2.2. of
2200 MoRTH specifications to a thickness of not less than 600 mm with smaller
size towards the soil and bigger size towards the wall and provided over the
11.10 13.10 cum 285.880
entire surface behind abutment, wing wall and return wall to the full height
compacted to a firm condition complete as per drawing and technical
specification.

2000 & Supplying, fitting and fixing in position true to line and level sliding plate
2200 bearing with PTFE surface sliding on stainless steel complete including all
tonne
11.11 13.13 accessories as per drawing and Technical Specifications and BS: 5400, 9600.000
capacity
section 9.1 & 9.2 (for PTFE) and clause 2004 of MoRTH Specifications.

2000 & Supplying, fitting and fixing in position true to line and level elastomeric
2200 bearing conforming to IRC: 83 (Part-II) section IX and clause 2005 of MoRTH cubic
11.12 13.14 639150.000
specifications complete including all accessories as per drawing and centimetre
Technical Specifications.

TOTAL FOR B.2 :: SUBSTRUCTURE

B.3 :: SUPERSTRUCTURE
1500 Furnishing and Placing Reinforced/Prestressed cement concrete in super-
14.1 A. III.case -
,1600 & structure as per drawing and Technical Specification
II(i) a
1700
RCC Grade M 30
Using Batching Plant, Transit Mixer and Concrete Pump.
11.13 For solid slab super-structure
Height upto 5m cum 15.250
14.1 A. VI .(i) PSC Grade M-45
a).
For solid slab/voided slab super-structure
Height upto 5m cum 891.960
High tensile steel wires/strands including all accessories for stressing,
11.14 14.3 stressing operations and grouting complete as per drawing and Technical tonne 44.000
Specifications
Supplying, Fitting, Fixing TMT Bar-From primary sources: TATA/SAIL/Esser
11.15 14.2 (a). (i) Steel/Jindal steel/Shyam steel (TMT Corrosion Resistance Steel (CRS) tonne 136.082
reinforcement bar of Fe-500 N/mm2
Ref.of RATE AMOUNT
SL. NO. SOR Ref. No DESCRIPTION UNIT QUANTITY
MoRT&H (INR) (INR)

515 & Mastic Asphalt


11.16 14.5
2702
Providing and laying 12 mm thick mastic asphalt wearing course on top of
deck slab excluding prime coat with paving grade bitumen meeting the
requirements given in table 500-29, prepared by using mastic cooker and
laid to required level and slope after cleaning the surface, including
providing antiskid surface with bitumen precoated fine grained hard stone
chipping of 9.5 mm nominal size at the rate of 0.005cum per 10 sqm and at sqm 1287.440
an approximate spacing of 10 cm center to center in both directions,
pressed into surface when the temperature of surfaces not less than 100
deg. C, protruding 1 mm to 4 mm over mastic surface, all complete as per
clause 515.

Providing and laying Bituminious wearing course comprising of tack coat


with bitumen emulsion CSS-1 h as per APWD SOR item no 5.2 & MoRT&H
Specification Nos 503,6mm thick mastic asphalt as per APWD SOR item no
14.5& MoRT&H Specification no 515 &2702 and 2 layer of 25 mm thick
11.17 5.8 (ii) cum 51.500
asphalt concrete including of close Graded Premix Surfacing (CGPS) material
with Type -a aggregate as per APWD SOR item no 5.11 & MoRT &H
Specification Nos 512 including all lead and lift as directed.

11.18 Tack coat Providing and applying tack coat with bitumen emulsion using
emulsion pressure distributor at the rate of 0.20 kg per sqm on the
5.2 prepared bituminous/granular surface cleaned with mechanical sqm 1,287.44
broom.(Including cost of testing of materials at sitfe and laboratory as
directed by the depttt.)
515 & Providing and laying Cement concrete wearing coat M-30 grade including
11.19 14. 4 2702 reinforcement complete as per drawing and Technical Specifications-With cum 15.250
batching plant
1500,160 Construction of precast RCC railing of M30 Grade, aggregate size not
0,1700 & exceeding 12 mm, true to line and grade, tolurence of vertical RCC post
2703 not to exceed 1 in 500, centre to centre spacing between vertical post not
11.20 14.6 metre 135.520
to exceed 2000 mm, leaving adequate space between vertical post for
expansion, complete as per approved drawings and technical
specifications.
2705 Drainage Spouts complete as per drawing and Technical specification
11.21 14.9 each 20.000
2700 PCC M15 Grade leveling course below approach slab complete as per
11.22 14.10 cum 24.670
drawing and Technical specification
Ref.of RATE AMOUNT
SL. NO. SOR Ref. No DESCRIPTION UNIT QUANTITY
MoRT&H (INR) (INR)

Reinforced Cement Concrete Crash Barrier (Provision of an Reinforced


cement concrete crash barrier at the edges of the road, approaches to
bridge structures and medians, constructed with M-40 grade concrete with
HYSD reinforcement conforming to IRC:21 and dowel bars 25 mm dia, 450
mm long at expansion joints filled with pre-moulded asphalt filler board,
11.23 8.22 (ii) 809 metre 271.04
keyed to the structure on which it is built and installed as per design given
in the enclosure to MORT&H circular No. RW/NH - 33022/1/94-DO III dated
June 1994 as per dimensions in the approved drawing and at locations
directed by the Engineer, all as specified)

1500,160 Reinforced cement concrete approach slab including reinforcement and


14.11(a) 0,1700 & formwork complete as per drawing and Technical specification
11.24
2704
With TATA make TMT CRS(Fe-500) grade rebar cum 50.610
14.18 2605 Filler joint
Providing & fixing 2 mm thick corrugated copper plate in expansion joint
(i) metre 48.200
complete as per drawing & Technical Specification.
Providing & fixing 20 mm thick compressible fibre board in expansion joint
(ii) metre 48.200
complete as per drawing & Technical Specification.
Providing and fixing in position 20 mm thick premoulded joint filler in
11.25 expansion joint for fixed ends of simply supported spans not exceeding 10 m
(iii) to cater for a horizontal movement upto 20 mm, covered with sealant metre 48.200
complete as per drawing and technical specifications.

Providing and filling joint sealing compound as per drawings and technical
(iv) specifications with coarse sand and 6% bitumen by weight metre 48.200

Strip Seal Expansion Joint (Providing and laying of a strip seal expansion
joint catering to maximum horizontal movement upto 70 mm, complete as
11.26 14.22 2607 per approved drawings and standard specifications to be installed by the metre 50.000
manufacturer/supplier or their authorised representative ensuring
compliance to the manufacturer's instructions for installation.)

TOTAL FOR B.3 :: SUPERSTUCTURE


Ref.of RATE AMOUNT
SL. NO. SOR Ref. No DESCRIPTION UNIT QUANTITY
MoRT&H (INR) (INR)

B.4 :: PROTECTION WORKS


2403 Providing and laying Pitching on slopes laid over prepared filter media
including boulder apron laid dry in front of toe of embankment complete as
15.4
11.27 per drawing and Technical specifications

A Stone/Boulder cum 820.670


2504 Providing and laying Filter material underneath pitching in slopes complete
11.28 15.5 cum 410.340
as per drawing and Technical specification
2505 Flexible Apron :Construction of flexible apron 1 m thick comprising of loose
11.29 15.11 stone boulders weighing not less than 40 kg beyond curtain wall. cum 193.240

TOTAL FOR B.4 :: PROTECTION WORKS

B.5::MISCELLANIOUS
803 Painting Two Coats on New Concrete Surfaces (Painting two coats after
11.30 8.8 filling the surface with synthetic enamel paint in all shades on new sqm 1068.820
plastered concrete surfaces)
11.31 8.4 (iv) Citizen information Board NH Project nos 2.00
11.32 12.5 Brick work at median cum 8.76

TOTAL FOR B.5 :: MISCELLANIOUS

Total of Bill No.11


DETAILED COST ESTIMATES
BILL NO. 12 FOR MINOR BRIDGES

Ref.of RATE AMOUNT


SL. NO. SOR Ref. No DESCRIPTION UNIT QUANTITY
MoRT&H (INR) (INR)

B.1 :: FOUNDATION
Excavation for Structures (Earth work in excavation of foundation of
structures as per drawing and technical specification, including setting out,
12.1 304 construction of shoring and bracing, removal of stumps and other
deleterious matter, dressing of sides and bottom and backfilling with
approved material.)
12.1
I. Ordinary soil
B. Mechanical Means
(b) with dewatering
(i) Depth upto 3 m cum 13913.804
(ii) Depth 3 m to 6 m cum 1141.843
1500,1700 Plain/Reinforced cement concrete in open foundation complete as per
12.8
&2100 drawing and technical specifications including steel shuttering forrmwork

12.2 A. Without plasticiser


PCC Grade M15 cum 705.777
(g) RCC Grade M30 (Pile Cap)
Case II Using Batching Plant, Transit Mixer and Concrete Pump cum 5004.060
1200 & Providing steel liner 10 mm thick for curbs and 6mm thick for steining of
12.3 12.22 tonne 0.000
1900 wells including fabricating and setting out as per detailed drawing
1100 & Bored cast-in-situ M35 grade R.C.C. pile excluding reinforcement complete
1700 as per drawing and technical specifications and removal of excavated earth
12.4 12.25A metre 7552.000
with all lifts and lead upto 1000 m. (Pile diameter-1200 mm)

1600 Reinforcement in foundation :Supplying, fitting and placing un-


12.4 0 (a).
coatedTMT bar reinforcement in foundation complete as per drawing and
(i)
technical specifications
12.5 From primary sources: TATA/SAIL/Esser Steel/Jindal steel/Shyam steel

TMT Corrosion Resistance Steel (CRS) reinforcement bar of Fe-500 N/mm2


tonne 1424.928

TOTAL FOR B.1 :: FOUNDATION


Ref.of RATE AMOUNT
SL. NO. SOR Ref. No DESCRIPTION UNIT QUANTITY
MoRT&H (INR) (INR)

B.2 :: SUBSTRUCTURE
1500,1700 Plain/Reinforced cement concrete in sub-structure complete as per drawing
13.5 (N) .A
12.6 &2200 and technical specifications
.g.(i)-case II
RCC Grade M30
Height upto 5m
With Batching Plant, Transit Mixer and Concrete Pump cum 3547.847
13.5 (N) .A Height 5m to 10m
.g.(ii)-case
II
With Batching Plant, Transit Mixer and Concrete Pump cum 797.690
RCC Grade M35 (Pedestals & RB)
13.5 (N) .A
12.7
.h.(i)-case II
Height 5m to 10m
With Batching Plant, Transit Mixer and Concrete Pump cum 133.160
1600 Supplying, fitting and placing TMT bar reinforcement in sub-structure
12.8 13.6 (a) (i
&2200 complete as per drawing and technical specifications
From primary sources: TATA/SAIL/Esser Steel/Jindal steel/Shyam steel

TMT Corrosion Resistance Steel (CRS) reinforcement bar of Fe-500 N/mm2


tonne 458.666
2200 Providing weep holes in Brick masonry/Plain/Reinforced concrete
&2706 abutment, wing wall/return wall with 100 mm dia AC pipe, extending
12.9 13.8 through the full width of the structure with slope of 1V :20H towards each 2168.000
drawing foce. Complete as per drawing and Technical specifications
Ref.of RATE AMOUNT
SL. NO. SOR Ref. No DESCRIPTION UNIT QUANTITY
MoRT&H (INR) (INR)

710.1.4 of Back filling behind abutment, wing wall and return wall complete as per
12.10 13.9 IRC:78 & drawing and Technical specification
2200
A Granular material cum 1447.601
B Sandy material cum 4905.052
710.1.4 of Providing and laying of Filter media with granular materials/stone crushed
IRC:78 & aggregates satisfying the requirements laid down in clause 2504.2.2. of
2200 MoRTH specifications to a thickness of not less than 600 mm with smaller
size towards the soil and bigger size towards the wall and provided over the
12.11 13.10 cum 1607.224
entire surface behind abutment, wing wall and return wall to the full height
compacted to a firm condition complete as per drawing and technical
specification.

2000 & Supplying, fitting and fixing in position true to line and level elastomeric
cubic
2200 bearing conforming to IRC: 83 (Part-II) section IX and clause 2005 of MoRTH
12.12 13.14 centimetr 1039200.000
specifications complete including all accessories as per drawing and
e
Technical Specifications.
2000 & Supplying, fitting and fixing in position true to line and level POT-PTFE
2200 bearing consisting of a metal piston supported by a disc or unreinforced
elastomer confined within a metal cylinder, sealing rings, dust seals, PTFE
surface sliding against stainless steel mating surface, completre assembly
tonne
12.13 13.16 to be of cast steel/fabricated structural steel, metal and elastomer 40800.000
capacity
elements to be as per IRC: 83 part-I & II respectively and other parts
conforming to BS: 5400, section 9.1 & 9.2 and clause 2006 of MoRTH
Specifications complete asper drawing and approved technical
specifications.

TOTAL FOR B.2 :: SUBSTRUCTURE


Ref.of RATE AMOUNT
SL. NO. SOR Ref. No DESCRIPTION UNIT QUANTITY
MoRT&H (INR) (INR)

B.3 :: SUPERSTRUCTURE
14.1 A. 1500 ,1600 Furnishing and Placing Reinforced/Prestressed cement concrete in super-
12.14 III.case -II(i) & 1700 structure as per drawing and Technical Specification
a
Without plasticiser
RCC Grade M 30
Using Batching Plant, Transit Mixer and Concrete Pump.
For T-Beam
Height upto 5m cum 3948.694
14.1 A. VI PSC Grade M-45
.(i) a)
For solid slab/voided slab super-structure
Height upto 5m cum 698.910
Reinforcement in Super Structure: Supplying, fitting and placing TMT bar
14.2 (a).
12.15 1600 reinforcement in super-structure including splicing complete as per
(i)
drawing and technical specifications
From primary sources: TATA/SAIL/Esser Steel/Jindal steel/Shyam steel

TMT Corrosion Resistance Steel (CRS) reinforcement bar of Fe-500 N/mm2


tonne
706.873
High tensile steel wires/strands including all accessories for stressing,
12.16 14.3 1800 stressing operations and grouting complete as per drawing and Technical tonne 29.000
Specifications
Ref.of RATE AMOUNT
SL. NO. SOR Ref. No DESCRIPTION UNIT QUANTITY
MoRT&H (INR) (INR)

Mastic Asphalt
12.17 14.5 (A) 515 & 2702
Providing and laying 12 mm thick mastic asphalt wearing course on top of
deck slab excluding prime coat with paving grade bitumen meeting the
requirements given in table 500-29, prepared by using mastic cooker and
laid to required level and slope after cleaning the surface, including
providing antiskid surface with bitumen precoated fine grained hard stone
chipping of 9.5 mm nominal size at the rate of 0.005cum per 10 sqm and at sqm 7217.810
an approximate spacing of 10 cm center to center in both directions,
pressed into surface when the temperature of surfaces not less than 100
deg. C, protruding 1 mm to 4 mm over mastic surface, all complete as per
clause 515.

Providing and laying Bituminious wearing course comprising of tack coat


with bitumen emulsion CSS-1 h as per APWD SOR item no 5.2 & MoRT&H
Specification Nos 503,6mm thick mastic asphalt as per APWD SOR item no
14.5& MoRT&H Specification no 515 &2702 and 2 layer of 25 mm thick
12.18 5.8 (ii) cum 288.720
asphalt concrete including of close Graded Premix Surfacing (CGPS) material
with Type -a aggregate as per APWD SOR item no 5.11 & MoRT &H
Specification Nos 512 including all lead and lift as directed.

Tack coat Providing and applying tack coat with bitumen emulsion using
emulsion pressure distributor at the rate of 0.20 kg per sqm on the
12.19 5.2 (I) (a) prepared bituminous/granular surface cleaned with mechanical sqm 7217.810
broom.(Including cost of testing of materials at sitfe and laboratory as
directed by the depttt.)

Providing and laying Cement concrete wearing coat M-30 grade including
12.20 14. 4 reinforcement complete as per drawing and Technical Specifications-With cum 79.239
batchimg plant
Drainage Spouts complete as per drawing and Technical specification
12.21 14.9 2705 each
110.000
PCC M15 Grade leveling course below approach slab complete as per
12.22 14.10 2700 cum 169.624
drawing and Technical specification
1500,1600, Reinforced cement concrete approach slab including reinforcement and
12.23 14.11 (a) 1700 & formwork complete as per drawing and Technical specification
2704
With TATA make TMT CRS(Fe-500) grade rebar cum 348.286
Ref.of RATE AMOUNT
SL. NO. SOR Ref. No DESCRIPTION UNIT QUANTITY
MoRT&H (INR) (INR)

12.24 14.18 2605 Filler joint


Providing & fixing 2 mm thick corrugated copper plate in expansion joint
(i) metre 372.720
complete as per drawing & Technical Specification.
Providing & fixing 20 mm thick compressible fibre board in expansion joint
(ii) metre 372.720
complete as per drawing & Technical Specification.
Providing and fixing in position 20 mm thick premoulded joint filler in
expansion joint for fixed ends of simply supported spans not exceeding 10 m
(iii) to cater for a horizontal movement upto 20 mm, covered with sealant metre 372.720
complete as per drawing and technical specifications.

Providing and filling joint sealing compound as per drawings and technical
(iv) specifications with coarse sand and 6% bitumen by weight metre 372.720

12.25 8.22 (ii) RCC Crash Barrier(M 40 grade concrete) metre 1540.380
12.26 14.6 Precast RCC Railing-With batching plant metre 704.190
Strip Seal Expansion Joint (Providing and laying of a strip seal expansion
joint catering to maximum horizontal movement upto 70 mm, complete as
per approved drawings and standard specifications to be installed by the
12.27 14.22 2607 metre 197.600
manufacturer/supplier or their authorised representative ensuring
compliance to the manufacturer's instructions for installation.)

12.28 HDPE Pipe metre 330.750

TOTAL FOR B.3 :: SUPERSTRUCTURE


Ref.of RATE AMOUNT
SL. NO. SOR Ref. No DESCRIPTION UNIT QUANTITY
MoRT&H (INR) (INR)

B.4 :: PROTECTION WORKS


Providing and laying Flooring complete as per drawing and Technical
12.29 2505 2403
specifications laid over cement concert bedding.
A Rubble stone laid in cement mortar 1:3 cum 179.699
2505 Boulder apron laid in wire crates (Providing and laying of boulder apron
laid in wire crates made with 4mm dia GI wire conforming to IS: 280 &
12.30 15.2 IS:4826 in 100mm x 100mm mesh (weaved diagonally) including 10% extra cum 1942.084
for laps and joints laid with stone boulders weighing not less than 40 kg
each.)
Providing and laying Filter material underneath pitching in slopes complete
12.31 15.5 2507.2 cum
as per drawing and Technical specification 971.040
Flexible Apron :Construction of flexible apron 750 mm thick comprising of
12.32 15.11 304 loose stone boulders weighing not less than 40 kg beyond curtain wall. cum 245.993

13.5 (N) .A 1500,1700 Plain/Reinforced cement concrete in sub-structure complete as per drawing
12.33
.b &2200 and technical specifications
12.8 A (a) PCC Grade M15 cum 286.334
12.34 15.10 (B) 2507.2 Curtain Wall-Cement concrete Grade M20 cum 249.202

12.1 I . Excavation for Structures


12.35 304 cum 1327.704
B. (b).(i)
12.36 15.11 304 Falling Apron on River Bed cum 990.140

TOTAL FOR B.4 :: PROTECTION WORKS

B.5:: MISCALLAENEOUS WORKS


Painting Two Coats on New Concrete Surfaces (Painting two coats after
12.37 8.8 803 filling the surface with synthetic enamel paint in all shades on new sqm 5740.870
plastered concrete surfaces)
12.38 8.4 (iv) Citizen information Board NH Project nos 12.000
12.39 12.5 Brick work at median cum 29.380

TOTAL FOR B.5:: MISCALLAENEOUS WORKS

Total of Bill No.12


DETAILED COST ESTIMATES
BILL NO. 13 FOR ROB

SOR Ref. Ref.of RATE AMOUNT


SL. NO. DESCRIPTION UNIT QUANTITY
No MoRT&H (INR) (INR)

B.1 :: FOUNDATION
Excavation for Structures (Earth work in excavation of foundation of structures as
per drawing and technical specification, including setting out, construction of
13.1 12.1 304 shoring and bracing, removal of stumps and other deleterious matter, dressing of
sides and bottom and backfilling with approved material.)

I. Ordinary soil
B. Mechanical Means
(b) with dewatering
(i) Depth upto 3 m cum 14123.630
(ii) Depth 3 m to 6 m cum 439.080
Bored cast-in-situ M35 grade R.C.C. pile excluding reinforcement complete as per
1100 & drawing and technical specifications and removal of excavated earth with all lifts
13.2 12.25A metre 10868.000
1700 and lead upto 1000 m. (Pile diameter-1200 mm)
RCC Pile Cap M30 -Using Batching Plant, Transit Mixer and Concrete Pump
12.38 (A)
13.3 cum 9552.150
III.(ii)
1100 & Levelling course for Pile cap
13.4 12.39 cum 1441.900
1700
Reinforcement in foundation :Supplying, fitting and placing un-coatedTMT bar
12.4 0 (a). reinforcement in foundation complete as per drawing and technical specifications
13.5 1600
(i)

From primary sources: TATA/SAIL/Esser Steel/Jindal steel/Shyam steel


TMT Corrosion Resistance Steel (CRS) reinforcement bar of Fe-500 N/mm2 tonne 2301.640
13.6 12.5 Brick masonry work (1:3) cum 140.220

TOTAL FOR B.1 :: FOUNDATION


SOR Ref. Ref.of RATE AMOUNT
SL. NO. DESCRIPTION UNIT QUANTITY
No MoRT&H (INR) (INR)

B.2 :: SUBSTRUCTURE
13.5 (N) 1500,1700 Plain/Reinforced cement concrete in sub-structure complete as per drawing and
13.7 .A .g.(i)- &2200 technical specifications
case II
Without plasticiser
RCC Grade M35
13.5 (N) .A
.h.(i)-case II
Height upto 5m
With Batching Plant, Transit Mixer and Concrete Pump cum 1806.290
(ii) Height 5m to 10m
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 3525.060
(iii) Height above 10m
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 1599.300
Supplying, fitting and placing TMT bar reinforcement in sub-structure complete as
13.8 13.6 (a) (i) 1600 &2200
per drawing and technical specifications
From primary sources: TATA/SAIL/Esser Steel/Jindal steel/Shyam steel
TMT Corrosion Resistance Steel (CRS) reinforcement bar of Fe-500 N/mm2 tonne 980.660
Pin Bearing tonne
13.9 3720.000
capacity
2000 & Supplying, fitting and fixing in position true to line and level sliding plate bearing
2200 with PTFE surface sliding on stainless steel complete including all accessories as per tonne
13.10 13.13 30720.000
drawing and Technical Specifications and BS: 5400, section 9.1 & 9.2 (for PTFE) capacity
and clause 2004 of MoRTH Specifications.
Metallic guide bearing tonne
13.11 3720.000
capacity
13.12 13.14 Elastomeric bearing CCUM 15872366.0
Reinforced/Prestressed cement concrete in super-structure -PSC M40
13.13 cum 74.020
Superstructure

TOTAL FOR B.2 :: SUBSTRUCTURE


SOR Ref. Ref.of RATE AMOUNT
SL. NO. DESCRIPTION UNIT QUANTITY
No MoRT&H (INR) (INR)

B.3 :: SUPERSTRUCTURE
14.1 A. 1500 ,1600 Furnishing and Placing Reinforced/Prestressed cement concrete in super-structure
13.14 III.case - & 1700 as per drawing and Technical Specification
II(i) a).
Without plasticiser
RCC/PSC Grade M35
Using Batching Plant, Transit Mixer and Concrete Pump
For solid slab super-structure
Height upto 5m cum 7921.880
VI. PSC Grade M-45
(i) For solid slab/voided slab super-structure
a) Height upto 5m cum 1803.100
Reinforcement in Super Structure: Supplying, fitting and placing TMT bar
14.2 (a).
13.15 1600 reinforcement in super-structure including splicing complete as per drawing and
(i)
technical specifications
From primary sources: TATA/SAIL/Esser Steel/Jindal steel/Shyam steel
TMT Corrosion Resistance Steel (CRS) reinforcement bar of Fe-500 N/mm2 tonne 1750.500
Supply, fabrication, delivery at bridge site and erection of structural steel works as
13.16 non sch per IS 2062, including two coats of primer, one at shop and the other at site and tonne 2115.520
two coats of aluminium paints including all labour, material, consumables etc.
SOR Ref. Ref.of RATE AMOUNT
SL. NO. DESCRIPTION UNIT QUANTITY
No MoRT&H (INR) (INR)

13.17 14.5 (A) 515 & 2702 Mastic Asphalt


Providing and laying 12 mm thick mastic asphalt wearing course on top of deck slab
excluding prime coat with paving grade bitumen meeting the requirements given in
table 500-29, prepared by using mastic cooker and laid to required level and slope
after cleaning the surface, including providing antiskid surface with bitumen
precoated fine grained hard stone chipping of 9.5 mm nominal size at the rate of sqm 17029.910
0.005cum per 10 sqm and at an approximate spacing of 10 cm center to center in
both directions, pressed into surface when the temperature of surfaces not less
than 100 deg. C, protruding 1 mm to 4 mm over mastic surface, all complete as
per clause 515.
Providing and laying Bituminious wearing course comprising of tack coat with
bitumen emulsion CSS-1 h as per APWD SOR item no 5.2 & MoRT&H Specification
Nos 503,6mm thick mastic asphalt as per APWD SOR item no 14.5& MoRT&H
13.18 5.8 (ii) Specification no 515 &2702 and 2 layer of 25 mm thick asphalt concrete including of cum 851.490
close Graded Premix Surfacing (CGPS) material with Type -a aggregate as per
APWD SOR item no 5.11 & MoRT &H Specification Nos 512 including all lead and
lift as directed.
Tack coat Providing and applying tack coat with bitumen emulsion using emulsion
pressure distributor at the rate of 0.20 kg per sqm on the prepared
13.19 5.2 bituminous/granular surface cleaned with mechanical broom.(Including cost of sqm 17029.910
testing of materials at sitfe and laboratory as directed by the depttt.)

Providing, fitting and fixing mild steel railing complete as per drawing and Technical
13.20 14.8 metre
1086.480
Specification
13.21 14.9 2705 Drainage Spouts complete as per drawing and Technical specification each 328.000
2700 PCC M15 Grade leveling course below approach slab complete as per drawing and
13.22 14.10 cum
11.630
Technical specification
Reinforced Cement Concrete Crash Barrier (Provision of an Reinforced cement
concrete crash barrier at the edges of the road, approaches to bridge structures
and medians, constructed with M-40 grade concrete with HYSD reinforcement
conforming to IRC:21 and dowel bars 25 mm dia, 450 mm long at expansion joints
13.23 8.22 (ii) 809 filled with pre-moulded asphalt filler board, keyed to the structure on which it is metre 3596.640
built and installed as per design given in the enclosure to MORT&H circular No.
RW/NH - 33022/1/94-DO III dated June 1994 as per dimensions in the approved
drawing and at locations directed by the Engineer, all as specified)
SOR Ref. Ref.of RATE AMOUNT
SL. NO. DESCRIPTION UNIT QUANTITY
No MoRT&H (INR) (INR)

13.24 14.18 2605 Filler joint


Providing & fixing 2 mm thick corrugated copper plate in expansion joint complete
(i) as per drawing & Technical Specification. metre 86.160
Providing & fixing 20 mm thick compressible fibre board in expansion joint
(ii) metre 86.160
complete as per drawing & Technical Specification.
Providing and fixing in position 20 mm thick premoulded joint filler in expansion
joint for fixed ends of simply supported spans not exceeding 10 m to cater for a
(iii) metre 86.160
horizontal movement upto 20 mm, covered with sealant complete as per drawing
and technical specifications.
Providing and filling joint sealing compound as per drawings and technical
(iv) metre 86.160
specifications with coarse sand and 6% bitumen by weight
Strip Seal Expansion Joint (Providing and laying of a strip seal expansion joint
catering to maximum horizontal movement upto 70 mm, complete as per
13.25 14.22 2607 approved drawings and standard specifications to be installed by the metre 766.040
manufacturer/supplier or their authorised representative ensuring compliance to
the manufacturer's instructions for installation.)
13.26 8.1 (A) RCC M30 Kerb M 24.580
Non- Reciever pipe for Drainage Spout
13.27 metre
400.000
Sch

TOTAL FOR B.3 :: SUPERSTRUCTURE


SOR Ref. Ref.of RATE AMOUNT
SL. NO. DESCRIPTION UNIT QUANTITY
No MoRT&H (INR) (INR)

B.4 :: MISCELLANEOUS
Painting Two Coats on New Concrete Surfaces (Painting two coats after filling the
13.28 8.8 803 surface with synthetic enamel paint in all shades on new plastered concrete sqm 11769.900
surfaces)
13.29 non sch Inspection ladder tonne 10.889
13.30 non sch Stair tonne 234.620

TOTAL FOR B.4 :: MISCELLANEOUS

Total of Bill No.13 Total=


DETAILED COST ESTIMATES
BILL NO. 14 FOR VUP

SOR Ref. Ref.of RATE AMOUNT


SL. NO. DESCRIPTION UNIT QUANTITY
No MoRT&H (INR) (INR)

B.1 :: FOUNDATION
Excavation for Structures (Earth work in excavation of foundation of structures as
per drawing and technical specification, including setting out, construction of
12.1 304 shoring and bracing, removal of stumps and other deleterious matter, dressing of
sides and bottom and backfilling with approved material.)
14.1
I. Ordinary soil
B. Mechanical Means
(b) with dewatering
(i) Depth upto 3 m cum 1089.350
1500,1700 Plain/Reinforced cement concrete in open foundation complete as per drawing
12.8
&2100 and technical specifications including steel shuttering forrmwork
A. Without plasticiser
14.2
PCC Grade M15 cum 67.950
(g) RCC Grade M30
Case II Using Batching Plant, Transit Mixer and Concrete Pump cum 591.940
1100 & Bored cast-in-situ M35 grade R.C.C. pile excluding reinforcement complete as per
14.3 12.25A 1700 drawing and technical specifications and removal of excavated earth with all lifts metre
and lead upto 1000 m. (Pile diameter-1200 mm)
1146.000
1600 Reinforcement in foundation :Supplying, fitting and placing un-coatedTMT bar
12.40(a). reinforcement in foundation complete as per drawing and technical specifications
(i)
14.4
From primary sources: TATA/SAIL/Esser Steel/Jindal steel/Shyam steel
TMT Corrosion Resistance Steel (CRS) reinforcement bar of Fe-500 N/mm2 tonne 190.795

TOTAL FOR B.1 :: FOUNDATION


SOR Ref. Ref.of RATE AMOUNT
SL. NO. DESCRIPTION UNIT QUANTITY
No MoRT&H (INR) (INR)

B.2 :: SUBSTRUCTURE
13.5 (N) 1500,1700 Plain/Reinforced cement concrete in sub-structure complete as per drawing and
14.5 .A .g.(i)- &2200 technical specifications
case II
Without plasticiser
RCC Grade M30
Height upto 5m
With Batching Plant, Transit Mixer and Concrete Pump cum 195.310
Height 5m to 10m
With Batching Plant, Transit Mixer and Concrete Pump cum 225.820
Height above 10m
With Batching Plant, Transit Mixer and Concrete Pump cum 132.230
RCC Grade M35 (Pedestals & RB)
Height 5m to 10m
With Batching Plant, Transit Mixer and Concrete Pump cum 39.610
1600 Supplying, fitting and placing TMT bar reinforcement in sub-structure complete as
14.6 13.6(a) (i)
per drawing and technical specifications
&2200
From primary sources: TATA/SAIL/Esser Steel/Jindal steel/Shyam steel
TMT Corrosion Resistance Steel (CRS) reinforcement bar of Fe-500 N/mm2 tonne 55.289
710.1.4 of Back filling behind abutment, wing wall and return wall complete as per drawing
14.7 13.9 IRC:78 & and Technical specification
2200
A Granular material cum 187.200
2000 & Supplying, fitting and fixing in position true to line and level elastomeric bearing
14.8 13.14 2200 conforming to IRC: 83 (Part-II) section IX and clause 2005 of MoRTH specifications cubic centimetre 207840.000
complete including all accessories as per drawing and Technical Specifications.

2000 & Supplying, fitting and fixing in position true to line and level sliding plate
2200 bearing with PTFE surface sliding on stainless steel complete including all
14.9 13.13 tonne capacity 9600.000
accessories as per drawing and Technical Specifications and BS: 5400,
section 9.1 & 9.2 (for PTFE) and clause 2004 of MoRTH Specifications.

TOTAL FOR B.2 :: SUBSTRUCTURE


SOR Ref. Ref.of RATE AMOUNT
SL. NO. DESCRIPTION UNIT QUANTITY
No MoRT&H (INR) (INR)

B.3 :: SUPERSTRUCTURE
14.1 A. 1500 ,1600 Furnishing and Placing Reinforced/Prestressed cement concrete in super-structure
14.10 III.case - & 1700 as per drawing and Technical Specification
II(i) a
Without plasticiser
RCC Grade M 30
Using Batching Plant, Transit Mixer and Concrete Pump.
For T-Beam
Height upto 5m cum 58.800
14.11 V. PSC Grade M-40
Case II Using Batching Plant, Transit Mixer and Concrete Pump
(ii) For T-beam & slab
a) Height upto 5m cum 288.670
14.1 A. VI PSC Grade M-45
14.12
.(i) a).
For solid slab/voided slab super-structure
Height upto 5m cum 545.370
Reinforcement in Super Structure: Supplying, fitting and placing TMT bar
14.2 (a).
14.13 1600 reinforcement in super-structure including splicing complete as per drawing and
(i)
technical specifications
From primary sources: TATA/SAIL/Esser Steel/Jindal steel/Shyam steel
TMT Corrosion Resistance Steel (CRS) reinforcement bar of Fe-500 N/mm2 tonne 133.926
High tensile steel wires/strands including all accessories for stressing, stressing
14.14 14.3 1800 operations and grouting complete as per drawing and Technical Specifications tonne 28.000
SOR Ref. Ref.of RATE AMOUNT
SL. NO. DESCRIPTION UNIT QUANTITY
No MoRT&H (INR) (INR)
Mastic Asphalt
14.15 14.5(A) 515 & 2702
Providing and laying 12 mm thick mastic asphalt wearing course on top of deck slab
excluding prime coat with paving grade bitumen meeting the requirements given in
table 500-29, prepared by using mastic cooker and laid to required level and slope
after cleaning the surface, including providing antiskid surface with bitumen
precoated fine grained hard stone chipping of 9.5 mm nominal size at the rate of sqm 1306.440
0.005cum per 10 sqm and at an approximate spacing of 10 cm center to center in
both directions, pressed into surface when the temperature of surfaces not less
than 100 deg. C, protruding 1 mm to 4 mm over mastic surface, all complete as
per clause 515.
Providing and laying Bituminious wearing course comprising of tack coat with
bitumen emulsion CSS-1 h as per APWD SOR item no 5.2 & MoRT&H Specification
Nos 503,6mm thick mastic asphalt as per APWD SOR item no 14.5& MoRT&H
14.16 5.8 (ii) Specification no 515 &2702 and 2 layer of 25 mm thick asphalt concrete including of cum 52.260
close Graded Premix Surfacing (CGPS) material with Type -a aggregate as per
APWD SOR item no 5.11 & MoRT &H Specification Nos 512 including all lead and
lift as directed.
Tack coat Providing and applying tack coat with bitumen emulsion using emulsion
pressure distributor at the rate of 0.20 kg per sqm on the prepared
14.17 5.2 (I) (a) bituminous/granular surface cleaned with mechanical broom.(Including cost of sqm 1306.440
testing of materials at sitfe and laboratory as directed by the depttt.)

14.18 14.9 2705 Drainage Spouts complete as per drawing and Technical specification each 20.000
PCC M15 Grade leveling course below approach slab complete as per drawing and
14.19 14.10 2700 cum 7.880
Technical specification
SOR Ref. Ref.of RATE AMOUNT
SL. NO. DESCRIPTION UNIT QUANTITY
No MoRT&H (INR) (INR)

14.20 14.18 2605 Filler joint


Providing & fixing 2 mm thick corrugated copper plate in expansion joint complete
(i) metre 42.000
as per drawing & Technical Specification.
Providing & fixing 20 mm thick compressible fibre board in expansion joint
(ii) metre 42.000
complete as per drawing & Technical Specification.
Providing and fixing in position 20 mm thick premoulded joint filler in expansion
(iii) joint for fixed ends of simply supported spans not exceeding 10 m to cater for a metre 42.000
horizontal movement upto 20 mm, covered with sealant complete as per drawing
and technical specifications.
Providing and filling joint sealing compound as per drawings and technical
(iv) metre 42.000
specifications with coarse sand and 6% bitumen by weight
8.22 (ii) RCC Crash Barrier(M 40 grade concrete) metre 275.040
Strip Seal Expansion Joint (Providing and laying of a strip seal expansion joint
catering to maximum horizontal movement upto 70 mm, complete as per
14.21 14.22 2607 approved drawings and standard specifications to be installed by the metre 63.000
manufacturer/supplier or their authorised representative ensuring compliance to
the manufacturer's instructions for installation.)
Non- Reciever pipe for Drainage Spout
14.22 metre 180.000
Sch

TOTAL FOR B.3 :: SUPERSTRUCTURE

B.4 :: MISCALLAENEOUS WORKS


Painting Two Coats on New Concrete Surfaces (Painting two coats after filling the
14.23 8.8 803 surface with synthetic enamel paint in all shades on new plastered concrete sqm 607.840
surfaces)
14.24 8.4 (iv) Citizen information Board NH Project nos 2.000
14.25 12.5 Brick masonry work (1:3) cum 68.250

TOTAL FOR B.4 :: MISCALLAENEOUS WORKS

Total of Bill No.14


DETAILED COST ESTIMATES
BILL NO. 15 FOR CULVERT

SOR Ref. Ref.of RATE AMOUNT


SL. NO. DESCRIPTION UNIT QUANTITY
No MoRT&H (INR) (INR)

B.1 :: FOUNDATION
Excavation for Structures (Earth work in excavation of foundation of structures as
per drawing and technical specification, including setting out, construction of
15.1 12.1 304 shoring and bracing, removal of stumps and other deleterious matter, dressing of
sides and bottom and backfilling with approved material.)

I. Ordinary soil
B. Mechanical Means
(b) with dewatering
(i) Depth upto 3 m cum 14419.358
1500,1700 Plain/Reinforced cement concrete in open foundation complete as per drawing
15.2 12.8
&2100 and technical specifications including steel shuttering forrmwork
A. Without plasticiser
PCC Grade M15 cum 1599.766

TOTAL FOR B.1 :: FOUNDATION


SOR Ref. Ref.of RATE AMOUNT
SL. NO. DESCRIPTION UNIT QUANTITY
No MoRT&H (INR) (INR)

B.2 :: SUBSTRUCTURE
13.5 (N) 1500,1700 Plain/Reinforced cement concrete in sub-structure complete as per drawing and
15.3 .A .g.(i)- &2200 technical specifications
case II
Without plasticiser
RCC Grade M30
Height upto 5m
With Batching Plant, Transit Mixer and Concrete Pump cum 6753.069
13.6 (a) 1600 Supplying, fitting and placing TMT bar reinforcement in sub-structure complete as
15.4 per drawing and technical specifications
(i) &2200
From primary sources: TATA/SAIL/Esser Steel/Jindal steel/Shyam steel
TMT Corrosion Resistance Steel (CRS) reinforcement bar of Fe-500 N/mm2 tonne 472.715
Providing weep holes in Brick masonry/Plain/Reinforced concrete abutment, wing
2200 wall/return wall with 100 mm dia AC pipe, extending through the full width of the
15.5 13.8 each 14184.000
&2706 structure with slope of 1V :20H towards drawing foce. Complete as per drawing and
Technical specifications
710.1.4 of Back filling behind abutment, wing wall and return wall complete as per drawing
15.6 13.9 IRC:78 & and Technical specification
2200
A Granular material cum 1218.757
B Sandy material cum 5723.432
Providing and laying of Filter media with granular materials/stone crushed
aggregates satisfying the requirements laid down in clause 2504.2.2. of MoRTH
710.1.4 of specifications to a thickness of not less than 600 mm with smaller size towards the
15.7 13.10 IRC:78 & soil and bigger size towards the wall and provided over the entire surface behind cum 7537.715
2200 abutment, wing wall and return wall to the full height compacted to a firm
condition complete as per drawing and technical specification.

TOTAL FOR B.2 :: SUBSTRUCTURE


SOR Ref. Ref.of RATE AMOUNT
SL. NO. DESCRIPTION UNIT QUANTITY
No MoRT&H (INR) (INR)

B.3 :: SUPERSTRUCTURE
14.1 A. 1500 ,1600 Furnishing and Placing Reinforced/Prestressed cement concrete in super-structure
15.8 III.case - & 1700 as per drawing and Technical Specification
II(i) a
Without plasticiser
RCC Grade M 30
Using Batching Plant, Transit Mixer and Concrete Pump.
For solid slab super-structure
Height upto 5m cum 1674.245
Reinforcement in Super Structure: Supplying, fitting and placing TMT bar
14.2 (a).
15.9 1600 reinforcement in super-structure including splicing complete as per drawing and
(i)
technical specifications
From primary sources: TATA/SAIL/Esser Steel/Jindal steel/Shyam steel
TMT Corrosion Resistance Steel (CRS) reinforcement bar of Fe-500 N/mm2 tonne 125.568
15.10 14.5 (A) 515 & 2702 Mastic Asphalt
Providing and laying 12 mm thick mastic asphalt wearing course on top of deck slab
excluding prime coat with paving grade bitumen meeting the requirements given in
table 500-29, prepared by using mastic cooker and laid to required level and slope
after cleaning the surface, including providing antiskid surface with bitumen
precoated fine grained hard stone chipping of 9.5 mm nominal size at the rate of sqm 7784.800
0.005cum per 10 sqm and at an approximate spacing of 10 cm center to center in
both directions, pressed into surface when the temperature of surfaces not less
than 100 deg. C, protruding 1 mm to 4 mm over mastic surface, all complete as
per clause 515.
Providing and laying Bituminious wearing course comprising of tack coat with
bitumen emulsion CSS-1 h as per APWD SOR item no 5.2 & MoRT&H Specification
Nos 503,6mm thick mastic asphalt as per APWD SOR item no 14.5& MoRT&H
15.11 5.8 (ii) Specification no 515 &2702 and 2 layer of 25 mm thick asphalt concrete including of cum 311.392
close Graded Premix Surfacing (CGPS) material with Type -a aggregate as per
APWD SOR item no 5.11 & MoRT &H Specification Nos 512 including all lead and
lift as directed.
Tack coat Providing and applying tack coat with bitumen emulsion using emulsion
pressure distributor at the rate of 0.20 kg per sqm on the prepared
15.12 5.2 (I) (a) bituminous/granular surface cleaned with mechanical broom.(Including cost of sqm 7784.800
testing of materials at sitfe and laboratory as directed by the depttt.)
SOR Ref. Ref.of RATE AMOUNT
SL. NO. DESCRIPTION UNIT QUANTITY
No MoRT&H (INR) (INR)

15.13 14.9 2705 Drainage Spouts complete as per drawing and Technical specification each 150.000
2700 PCC M15 Grade leveling course below approach slab complete as per drawing and
15.14 14.10 cum 907.451
Technical specification
Reinforced Cement Concrete Crash Barrier (Provision of an Reinforced cement
concrete crash barrier at the edges of the road, approaches to bridge structures
and medians, constructed with M-40 grade concrete with HYSD reinforcement
conforming to IRC:21 and dowel bars 25 mm dia, 450 mm long at expansion joints
15.15 8.22 (ii) 809 filled with pre-moulded asphalt filler board, keyed to the structure on which it is metre 1427.400
built and installed as per design given in the enclosure to MORT&H circular No.
RW/NH - 33022/1/94-DO III dated June 1994 as per dimensions in the approved
drawing and at locations directed by the Engineer, all as specified)
1500,1600, Reinforced cement concrete approach slab including reinforcement and formwork
15.16 14.11 1700 & complete as per drawing and Technical specification
2704
(a) With TATA make TMT CRS(Fe-500) grade rebar cum 1849.806
15.17 14.18 2605 Filler joint
Providing & fixing 2 mm thick corrugated copper plate in expansion joint complete
(i) metre 1778.840
as per drawing & Technical Specification.
Providing & fixing 20 mm thick compressible fibre board in expansion joint
(ii) metre 1778.840
complete as per drawing & Technical Specification.
Providing and fixing in position 20 mm thick premoulded joint filler in expansion
(iii) joint for fixed ends of simply supported spans not exceeding 10 m to cater for a metre 1778.840
horizontal movement upto 20 mm, covered with sealant complete as per drawing
and technical specifications.
Providing and filling joint sealing compound as per drawings and technical
(iv) metre 1778.840
specifications with coarse sand and 6% bitumen by weight

TOTAL FOR B.3 :: SUPERSTRUCTURE


SOR Ref. Ref.of RATE AMOUNT
SL. NO. DESCRIPTION UNIT QUANTITY
No MoRT&H (INR) (INR)

B.4 :: PROTECTION WORKS


Flexible Apron :Construction of flexible apron 1 m thick comprising of loose stone
15.18 15.11 2507.2 cum 3919.868
boulders weighing not less than 40 kg beyond curtain wall.
13.5 (N) 1500,1700 Plain/Reinforced cement concrete in sub-structure complete as per drawing and
15.19
.A .b &2200 technical specifications
PCC Grade M 15(Height upto 5m) cum 588.966
Providing and laying Flooring complete as per drawing and Technical
15.18 15.8.B 2505 cum 27.168
specification laid over cement concrete bedding-Grade M 15
Curtain Wall-Cement concrete Grade M20
15.20 15.10 (B) 2507.2 cum 4025.831
Painting Two Coats on New Concrete Surfaces (Painting two coats after filling the
15.21 8.8 803 surface with synthetic enamel paint in all shades on new plastered concrete 3850.532
surfaces) sqm
12.1 I . B. Excavation for Structures
15.21 304 cum 19278.573
(b).(i)
15.22 Guard Stone Nos 930.000

TOTAL FOR B.4 :: PROTECTION WORKS

Total of Bill No.15


DETAILED COST ESTIMATES
BILL NO. 16 : REPAIRING OF BRIDGE

SOR Ref. Ref.of RATE AMOUNT


SL. NO. DESCRIPTION UNIT QUANTITY
No MoRT&H (INR) (INR)

Painting Two Coats on New Concrete Surfaces (Painting two coats after
16.1 8.8 803 filling the surface with synthetic enamel paint in all shades on new sqm 649.302
plastered concrete surfaces)

Total of Bill No.16

You might also like