You are on page 1of 1

Konsorsium PP – Betasurya

Tatagraha ENGINEERING PROGRESS CALCULATION REPORT


Jl. TB. Simatupang No. 57 Pasar Rebo Jakarta
Telp. 021-840 3902 Fax. 021-840 3992 PROYEK PLTGU TANJUNG UNCANG 100-120 MW
epc@pt-pp.com
BATAM

I. OVERALL FOR ENGINEERING

Weight PROGRESS (%) PROGRESS EARNED (%)


No Description Factor Level Previous Previous
This Week Cumulative This Week Cumulative
2(%) Week Week
1 Design Basis 5.00% 100.000% 0.000% 100.000% 5.000% 0.000% 5.000%
2 Manufacture Design 45.00% 100.000% 0.00% 100.000% 45.000% 0.000% 45.000%
3 Mechanical BOP Design 20.00% 98.054% 0.000% 98.054% 19.611% 0.000% 19.611%
4 Electrical & Instrument BOP Design 20.00% 89.843% 0.000% 89.843% 17.969% 0.000% 17.969%
5 Civil, Structure & Architechtural 10.00% 99.625% 0.000% 99.625% 9.962% 0.000% 9.962%
TOTAL 100.00% 97.542% 0.000% 97.542%

You might also like