Professional Documents
Culture Documents
Contract Package Description Contract Amount Rel. Weight Previous Week Weighted %
CP-01A Civil & Structural Works 380,000,000.00 53.56% 91.86% 48.85%
CP-02-4 Plumbing & Sanitary Works 24,700,000.00 3.48% 30.67% 1.06%
CP-03-1 Exterior AAC Walls 29,000,000.00 4.09% 32.93% 1.34%
CP-02-5 Fire Protection Works 16,800,000.00 2.37% 40.92% 0.96%
CP-02-8 Mechanical Works 60,000,000.00 11.28% 24.17% 2.03%
CP-02-9 Electrical Works 80,000,000.00 8.46% 30.90% 3.46%
CP-02-10 Electronics Works 34,500,000.00 4.86% 17.32% 0.84%
CP-03-3A Interior AAC Walls 56,500,000.00 7.96% 4.59% 0.36%
CP-03-2 Exterior Glass & Glazing 28,000,000.00 3.95% 20.50% 0.80%
Civil Works for Change of
CP-02-11
Elevation 5,127,927.19 0.72% 6.19% 0.04%
3. Update On Billings.
4. Updates of Awarded Contracts
5. Updates of Procurement
6. Look-Ahead Schedule & Milestone Dates
7. Presentation of Revised Quotation of Banitrade for SUPPLY AND INSTALLATION OF BRAND-
NEW DISTRIBUTION TRANSFORMER 1.5MVA 3PHASE.
8. Presentation of Revised Quotation of Kintar Power for Supply of Electrical Panels.
9. Presentation of Revised Quotation of GenDiesel for GENSET.
US OF ACCOMPLISHMENT– CIVIL & STRUCTURAL WORKS - RRSAGARAY ECS
Site Offices
Fire Pro
Phase 2 Phase 3 AC
Location of Conference Installation of MEPF Laying of rebars and C ES
& Sample Room concreting 2F-RD S
Installation of MEPF
Bun ECS
se
kho u
RRS
Office
il RRSECS se,
Phase 4 & 5 Temfac
ACCE
ou
& Wareh
ho p Glass
Erection is Going on. M e c h. S se
O ffi ce
S
unkhou
Elect. B ffice
S
M e c h. and O
use
Bunkho
Spurway Temfacil
STEEL ERECTION – PHASE 3
COMPLETED
Phase 4
Phase 2 Phase 3
Phase 1 Phase 6 Phase 6
Completed Completed
Completed
Phase 5
ERECTION IS
GOING-0N
1 103.58594 Metric Tons 5.55% 8-Feb-21 Issued Issued Issued Done Done Installed 103.58594
2 106.61831 Metric Tons 5.72% 10-Feb-21 Issued Issued Issued Done Done Installed 210.20425
3 119.26694 Metric Tons 6.39% 25-Feb-21 Issued Issued Issued Done Done Installed 329.47118
4 133.84113 Metric Tons 7.17% 20-Mar-21 Issued Issued Issued Done Done Installed 463.31231
5 51.93006 Metric Tons 2.78% 18-Mar-21 Issued Issued Issued Done Done Installed 515.24237
6 138.53309 Metric Tons 7.43% 7-Apr-21 Issued Issued Issued Done Done Installed 653.77546
7 117.00135 Metric Tons 6.27% 5-Apr-21 Issued Issued Issued Done Done Installed 770.77681
8 261.29903 Metric Tons 14.01% 4-May-21 Issued Issued Issued Done Done Installed 1,032.07584
9 195.68156 Metric Tons 10.49% 10-May-21 Issued Issued Issued Done Done Installed 1,227.75740
10 163.79140 Metric Tons 8.78% 25-Jun-21 Issued Issued Issued Done Done Installed 1,391.54880
On-going
11 139.49624 Metric Tons 7.48% 27-Jul-21 Issued Issued Issued Done Done 1,531.04504
installation
On-going
12 160.00674 Metric Tons 8.58% 12-Jul-2-2 Issued Issued Issued Done Done 1,691.05178
installation
1 3.75707 Metric Tons 7.48% 8-Feb-21 Issued Issued Issued Done Done Installed 3.75707
2 3.86706 Metric Tons 7.70% 10-Feb-21 Issued Issued Issued Done Done Installed 7.62413
3 4.32582 Metric Tons 8.61% 25-Feb-21 Issued Issued Issued Done Done Installed 11.94996
4 4.85443 Metric Tons 9.67% 20-Mar-21 Issued Issued Issued Done Done Installed 16.80439
5 1.88351 Metric Tons 3.75% 18-Mar-21 Issued Issued Issued Done Done Installed 18.68790
6 5.02461 Metric Tons 10.01% 7-Apr-21 Issued Issued Issued Done Done Installed 23.71251
On-going
7 4.24365 Metric Tons 8.45% 5-Apr-21 Issued Issued Issued Done Done 27.95616
installation
On-going
8 9.47734 Metric Tons 18.87% 4-May-21 Issued Issued Issued Done Done 37.43350
installation
On-going
9 7.09739 Metric Tons 14.13% 10-May-21 Issued Issued Issued Done Done 44.53089
installation
On-going
10 5.68511 Metric Tons 11.32% 25-Jun-21 Issued Issued Issued Done Done 50.21600
installation
8 9,404.010 m2 37.04% 4-May-21 Issued Issued Issued Done Done Installed 9,404.010
Installed
9 8,426.890 m2 33.19% 10-May-21 Issued Issued Issued Done Done 17,830.900
10 6,055.900 m2 23.85% 25-Jun-21 Issued Issued Issued Done Done Installed 23,886.800
On-going
8 31,960.000 pcs 66.25% 4-May-21 Issued Issued Issued Done Done 31,960.000
installation
On-going
Remaining 16,283.050 pcs 33.75% 12-Jul-22 Issued Issued Issued Done Done 48,243.050
Unloading
Remaining Remaining
Item Description In (BOX) Meters Out (BOX) Meters Remarks
(BOX) (Meters)
3.5mm
1 THHN/THWN 23 3,450 23 3450 23 0.00 Complete qty.
(BLACK)
3.5mm
2 THHN/THWN 74 11,100 24 3600 50 7500 Complete qty.
(RED)
3.5mm
3 THHN/THWN 74 11,100 24 3600 50 7500 Complete qty.
(BLUE)
3.5mm
4 THHN/THWN 74 11,100 24 3600 7500 Complete qty.
50
(YELLOW)
3.5mm
5 THHN/THWN 134 20,100 24 3600 110 16,500 Complete qty.
(WHITE)
2.00 mm TW
6 171 25,650 20 3000 151 22,650 Complete qty.
(GREEN)
3.5mm
7 THHN/THWN 1 180 180 Complete qty.
(WHITE ROLL)
100mm2 (19X6mm)
8 1 1,500 1,500 Complete qty.
Comp. BS CU
LIVERY OF MATERIALS FOR CHANGE OF ELEVATION
Actual
Actual
Area BOQ This Actual Total Percentage Remaining Remarks
Previous
Week
10Ǿ Rebar 3-Oct-20 Davao Diamond Industrial Supply 275.00 480.00 395.00 547.00 PASSED
12Ǿ Rebar 4-Oct-20 Davao Diamond Industrial Supply 275.00 480.00 429.00 548.00 PASSED
20Ǿ Rebar 5-Oct-20 Davao Diamond Industrial Supply 415.00 550.00 446.00 576.00 PASSED
25Ǿ Rebar 6-Oct-20 Davao Diamond Industrial Supply 415.00 550.00 460.00 621.00 PASSED
28Ǿ Rebar 7-Oct-20 Davao Diamond Industrial Supply 415.00 550.00 487.00 640.00 PASSED
32Ǿ Rebar 8-Oct-20 Davao Diamond Industrial Supply 415.00 550.00 495.00 674.00 PASSED
28Ǿ Rebar 26-Nov-20 Davao Diamond Industrial Supply 415.00 550.00 487.00 650.00 PASSED
28Ǿ Rebar 2-Dec-20 Davao Diamond Industrial Supply 415.00 550.00 490.00 656.00 PASSED
10Ǿ Rebar 8-Dec-20 Davao Diamond Industrial Supply 275.00 480.00 427.00 579.00 PASSED
12Ǿ Rebar 8-Dec-20 Davao Diamond Industrial Supply 275.00 480.00 398.00 548.00 PASSED
20Ǿ Rebar 8-Dec-20 Davao Diamond Industrial Supply 415.00 550.00 557.00 678.00 PASSED
25Ǿ Rebar 8-Dec-20 Davao Diamond Industrial Supply 415.00 550.00 505.00 646.00 PASSED
28Ǿ Rebar 8-Dec-20 Davao Diamond Industrial Supply 415.00 550.00 490.00 643.00 PASSED
10Ǿ Rebar 8-Mar-21 Davao Diamond Industrial Supply 275.00 480.00 382.00 573.00 PASSED
12Ǿ Rebar 8-Mar-21 Davao Diamond Industrial Supply 275.00 480.00 380.00 548.00 PASSED
25Ǿ Rebar 8-Mar-21 Davao Diamond Industrial Supply 415.00 550.00 485.00 611.00 PASSED
32Ǿ Rebar 8-Mar-21 Davao Diamond Industrial Supply 415.00 550.00 472.00 699.00 PASSED
25 mm Ø Anchor Bolt 5-Nov-20 Davao Diamond Industrial Supply 830.00 953.00 PASSED
25 mm Ø Anchor Bolt 11-Feb-21 Davao Diamond Industrial Supply 830.00 1,010.00 PASSED
10Ǿ Rebar Davao Diamond Industrial Supply
09-Feb-22 275.00 480.00 420.00 586.00 PASSED
LITY ASSURANCE – DIMENSIONAL & TENSILE TESTING FOR BOLTS
k s l d Tensile Strength
REQUIRED
22.10 - 22.90 54 - 55 99.83 - 100.2 35.48 - 36 800 MPa
SAMPLE DATE DELIVERED SUPPLIER REMARKS
mm mm mm mm 115,940 psi
Aspire Steel
Sample 2 M36X100 8-Feb-21 22.65 54.68 99.68 35.65 890 PASSED
Vietnam
Aspire Steel
RESULTS
Sample 2 M36X100 8-Feb-21 22.75 54.69 99.98 35.74 920 PASSED
Vietnam
Aspire Steel
Sample 3 M36X100 8-Feb-21 22.62 54.72 99.95 35.58 880 PASSED
Vietnam
Aspire Steel
Sample 4 M36X100 8-Feb-21 22.64 54.58 99.68 35.69 895 PASSED
Vietnam
k s l d Tensile Strength
REQUIRED
SAMPLE DATE DELIVERED SUPPLIER 22.10 - 22.90 54 - 55 119.3 - 120.7 35.48 - 36 800 MPa REMARKS
mm mm mm mm 115,940 psi
Aspire Steel
Sample1 M36X120 10-Feb-21 22.62 54.65 119.68 35.63 885 PASSED
Vietnam
Aspire Steel
RESULTS
Sample 2 M36X120 10-Feb-21 22.75 54.62 119.98 35.72 910 PASSED
Vietnam
Aspire Steel
Sample 3 M36X120 10-Feb-21 22.66 54.75 119.95 35.59 890 PASSED
Vietnam
Aspire Steel
Sample 4 M36X120 10-Feb-21 22.68 54.62 119.68 35.71 900 PASSED
Vietnam k s l d Tensile Strength
REQUIRED
SAMPLE DATE DELIVERED SUPPLIER 22.10 - 22.90 54 - 55 129.3 - 130.7 35.48 - 36 800 MPa REMARKS
mm mm mm mm 115,940 psi
Aspire Steel
Sample1 M36X130 25-Feb-21 22.63 54.68 129.68 35.55 900 PASSED
Vietnam
Aspire Steel
RESULTS
Sample 2 M36X130 25-Feb-21 22.76 54.62 129.98 35.61 910 PASSED
Vietnam
Aspire Steel
Sample 3 M36X130 25-Feb-21 22.63 54.7 129.95 35.58 895 PASSED
Vietnam
Aspire Steel
Sample 4 M36X130 25-Feb-21 22.64 54.56 129.68 35.57 900 PASSED
Vietnam
k = thickness of Hexa Nut / s = width of hexa nut / l = length of bolt / d = diameter of bolt
ALITY ASSURANCE –TORQUE TESTING OF BOLTS
Present Week
Previous Week
OGRESS PHOTOS – CIVIL /STRUCTURAL – LEFT SIDE VIEWS
OGRESS PHOTOS – CIVIL /STRUCTURAL – OTHER VIEWS
GRESS PHOTOS – CIVIL /STRUCTURAL – STEEL ERECTION AT PHASE4 @ THE TOP
GRESS PHOTOS – CIVIL /STRUCTURAL – STEEL ERECTION AT PHASE 4 & 5
OGRESS PHOTOS – CIVIL /STRUCTURAL – VIEW FROM THE TOP
OGRESS PHOTOS - PHASE 3 - 6F STEEL DECKING WORKS
OGRESS PHOTOS - PHASE 3 - 7F STEEL DECKING WORKS
OGRESS PHOTOS - PHASE 3 – ROOF DECK STEEL DECKING WORKS
ROGRESS PHOTOS – CIVL / STRUCTURAL – SUSPENDED SLABS – Phase 1
OGRESS PHOTOS – CIVL / STRUCTURAL – SUSPENDED SLABS – Phase 2
PHASE 2- RD
OGRESS PHOTOS – CIVL / STRUCTURAL – SUSPENDED SLABS – Phase 3
PHASE 3- 2F PHASE 3- 3F
PHASE 3- 4F PHASE 3- 5F
PROGRESS PHOTOS - EXTERNAL AAC WALLS – Phase 1 to 2
Complete Steel Erection for Building Superstructure October 31, 2021 Delayed at 85.01%
Plumbing and Sanitary Works (Started 6-1-21) August 20, 2022 31.50%
Exterior AAC Walls (Started 8-9-21) August 20, 2022 33.00%
Fire Protection Works (Started 7-1-21) August 20, 2022 42.00%
Mechanical Works (Started 8-16-21) August 20, 2022 31.50%
Electrical Works (Started 8-30-21) August 20, 2022 25.00%
Electronics / Auxiliary Works (Started 10-25-21) August 20, 2022 18.00%
Exterior Glazing, Windows and Doors (Started 8-9-21) August 20, 2022 23.00%
Interior AAC, Drywall, Ceiling & Vinyl Floor August 20, 2022 5.00%
OSM Lighting Fixtures & Wiring Devices (NOA 9-13-21) August 20, 2022 Start deliveries
Award Other Basic Architectural & Other Packages Until August to September 2022
MEPF and Medical Equipment Testing & Commissioning September 15 to October 15, 2022
Project Completion for 1st Priority (GF – 5F) December 31, 2022
September 21, 2020 to December 31, 2022 / 619 Calendar
Overall Schedule
Days
EVISED PROJECTED OVERALL SCHEDULE
THANK YOU and GOD BLESS.