ACE MEDICAL CENTER GENSAN

Progress Report as of August 13,2022


SUMMARY OF DISCUSSIONS FROM PREVIOUS MEETING

1. Status of On-going Work Packages

Contract Package Description Contract Amount Rel. Weight Previous Week Weighted %
CP-01A Civil & Structural Works 380,000,000.00 53.56% 91.86% 48.85%
CP-02-4 Plumbing & Sanitary Works 24,700,000.00 3.48% 30.67% 1.06%
CP-03-1 Exterior AAC Walls 29,000,000.00 4.09% 32.93% 1.34%
CP-02-5 Fire Protection Works 16,800,000.00 2.37% 40.92% 0.96%
CP-02-8 Mechanical Works 60,000,000.00 11.28% 24.17% 2.03%
CP-02-9 Electrical Works 80,000,000.00 8.46% 30.90% 3.46%
CP-02-10 Electronics Works 34,500,000.00 4.86% 17.32% 0.84%
CP-03-3A Interior AAC Walls 56,500,000.00 7.96% 4.59% 0.36%
CP-03-2 Exterior Glass & Glazing 28,000,000.00 3.95% 20.50% 0.80%
Civil Works for Change of
CP-02-11
Elevation 5,127,927.19 0.72% 6.19% 0.04%

Total 714,627,927.19 100.00% 59.74%


Variance 0.440%
2. Status of Steel Shipments

• ON GOING INSTALLATION FOR PHASE4 & 5.

3. Status of Awarded Contracts


• 30 Contracts awarded to date
• Total Contract Amount = PHP. 930,686,976.26
• Value of Accomplishment =PHP. 447,255,407.66
AGENDA FOR TODAY’S MEETING

1. Updates of On-going Works


• Civil & Structural Works
• Plumbing & Sanitary Works
• Exterior AAC Walls
• Fire Protection Works
• Electrical Works
• Mechanical Works
• Electronics Works
• Interior AAC Walls
• Exterior Glass & Glazing Works
• Monitoring Sheets
• Quality Control
• Health & Safety
2. Progress Photos
• On-going Works

3. Update On Billings.
4. Updates of Awarded Contracts
5. Updates of Procurement
6. Look-Ahead Schedule & Milestone Dates
7. Presentation of Revised Quotation of Banitrade for SUPPLY AND INSTALLATION OF BRAND-
NEW DISTRIBUTION TRANSFORMER 1.5MVA 3PHASE.
8. Presentation of Revised Quotation of Kintar Power for Supply of Electrical Panels.
9. Presentation of Revised Quotation of GenDiesel for GENSET.
US OF ACCOMPLISHMENT– CIVIL & STRUCTURAL WORKS - RRSAGARAY ECS

Target Accomplishment this Week= 92.00%


US OF ACCOMPLISHMENT– PLUMBING & SANITARY WORKS – RRSAGARAY ECS

Target Accomplishment this Week= 30.50%


TUS OF ACCOMPLISHMENT– EXTERIOR AAC WALLS – RRSAGARAY ECS

Target Accomplishment this Week=32.50%


TUS OF ACCOMPLISHMENT– FIRE PROTECTION WORKS – RPR 1030 CORP.

Target Accomplishment this Week= 41.00%


US OF ACCOMPLISHMENT– ELECTRICAL WORKS – JFS ELECTRICAL CORP.

Target Accomplishment this Week=24.50%


STATUS OF ACCOMPLISHMENT– MECHANICAL WORKS – BRUN
AIRCONDITION INC.

Target Accomplishment this Week= 31.00%


STATUS OF ACCOMPLISHMENT– ELECTRONICS / AUXILIARY WORKS –
SYCHRONIZED

Target Accomplishment this Week= 17.50%


STATUS OF ACCOMPLISHMENT– INTERIOR AAC WALLS- SPURWAY
ENTERPRISES

Target Accomplishment this Week= 5.00%


STATUS OF ACCOMPLISHMENT– EXTERIOR GLASS AND GLAZING WORKS-
PHILIPS GLASS

Target Accomplishment this Week=21.00%


STATUS OF ACCOMPLISHMENT– CIVIL WORKS FOR CHANGE OF ELEVATION

Target Accomplishment this Week= 8.00%


ATUS OF ACCOMPLISHMENT– COMBINED TRADES
Previous Present
Relative
Scope Of Work Contract Amount
Weight Actual Weighted Actual Weighted

Civil & Structural


380,000,000.00 53.56% 91.86% 48.85% 92.20% 49.03%
Works

Plumbing & Sanitary


24,700,000.00 3.48% 30.67% 1.06% 1.07%
Works
30.89%
Exterior AAC Walls 29,000,000.00 4.09% 32.93% 1.34% 33.55% 1.36%
Fire Protection Works 16,800,000.00 2.37% 40.92% 0.96% 41.78% 0.98%
Mechanical Works 80,000,000.00 11.28% 24.17% 2.03% 24.82% 2.08%

Electrical Works 60,000,000.00 8.46% 30.90% 3.46% 3.51%


31.38%
Electronics/Auxiliary
34,500,000.00 4.86% 17.32% 0.84% 0.85%
Works
17.70%

Interior AAC Walls 56,500,000.00 7.96% 4.59% 0.36% 0.38%


4.76%
Exterior Glass &
28,000,000.00 3.95% 20.50% 0.80% 0.86%
Glazing
22.07%
Civil Works for Change
5,127,927.19 0.72% 6.19% 0.04% 0.07%
of Elevation
9.83%
Progressive Total 714,627,927.19 100.00% 59.74% 60.20%
SITE LOGISTICS

AAC Wall Installations Start of Glazing Installations

Site Offices
Fire Pro

Phase 2 Phase 3 AC
Location of Conference Installation of MEPF Laying of rebars and C ES
& Sample Room concreting 2F-RD S
Installation of MEPF

Access for large Medical


Equipment

Bun ECS
se
kho u
RRS
Office
il RRSECS se,
Phase 4 & 5 Temfac

ACCE
ou
& Wareh
ho p Glass
Erection is Going on. M e c h. S se
O ffi ce

S
unkhou
Elect. B ffice

S
M e c h. and O
use
Bunkho

Spurway Temfacil
STEEL ERECTION – PHASE 3

COMPLETED
Phase 4

Phase 2 Phase 3
Phase 1 Phase 6 Phase 6
Completed Completed
Completed

Phase 5
ERECTION IS
GOING-0N

Phase Estimated Qty. Previous To Date Total

1 500 MT 500.00 MT Completed 500.00 MT

2 450 MT 450.00 MT Completed 450.00 MT

3 300 MT 300.00 MT Completed 300.00 MT

4, 5 & 6 185 MT 12.00 MT 18.00 MT 58.00 MT

Total 1,435 MT 1,306.00 MT


ELIVERY OF PRE-ENGINEERED STEEL

DELIVERY STATUS OF PRE-ENGINEERED STEEL COLUMNS & BEAMS

Shipment Quantity Unit RW Date Delivered BL CO PL Inspection Test Remarks

1 103.58594 Metric Tons 5.55% 8-Feb-21 Issued Issued Issued Done Done Installed 103.58594

2 106.61831 Metric Tons 5.72% 10-Feb-21 Issued Issued Issued Done Done Installed 210.20425

3 119.26694 Metric Tons 6.39% 25-Feb-21 Issued Issued Issued Done Done Installed 329.47118

4 133.84113 Metric Tons 7.17% 20-Mar-21 Issued Issued Issued Done Done Installed 463.31231

5 51.93006 Metric Tons 2.78% 18-Mar-21 Issued Issued Issued Done Done Installed 515.24237

6 138.53309 Metric Tons 7.43% 7-Apr-21 Issued Issued Issued Done Done Installed 653.77546

7 117.00135 Metric Tons 6.27% 5-Apr-21 Issued Issued Issued Done Done Installed 770.77681

8 261.29903 Metric Tons 14.01% 4-May-21 Issued Issued Issued Done Done Installed 1,032.07584

9 195.68156 Metric Tons 10.49% 10-May-21 Issued Issued Issued Done Done Installed 1,227.75740

10 163.79140 Metric Tons 8.78% 25-Jun-21 Issued Issued Issued Done Done Installed 1,391.54880

On-going
11 139.49624 Metric Tons 7.48% 27-Jul-21 Issued Issued Issued Done Done 1,531.04504
installation
On-going
12 160.00674 Metric Tons 8.58% 12-Jul-2-2 Issued Issued Issued Done Done 1,691.05178
installation

Remaining 170.40724 Metric Tons 9.35%

Total 1,865.459 Metric Tons 100.00% Delivered 90.65%


DELIVERY OF BOLTS

DELIVERY STATUS FOR BOLTS

Shipment Quantity Unit RW Date Delivered BL CO PL Inspection Test Remarks

1 3.75707 Metric Tons 7.48% 8-Feb-21 Issued Issued Issued Done Done Installed 3.75707

2 3.86706 Metric Tons 7.70% 10-Feb-21 Issued Issued Issued Done Done Installed 7.62413

3 4.32582 Metric Tons 8.61% 25-Feb-21 Issued Issued Issued Done Done Installed 11.94996

4 4.85443 Metric Tons 9.67% 20-Mar-21 Issued Issued Issued Done Done Installed 16.80439

5 1.88351 Metric Tons 3.75% 18-Mar-21 Issued Issued Issued Done Done Installed 18.68790

6 5.02461 Metric Tons 10.01% 7-Apr-21 Issued Issued Issued Done Done Installed 23.71251

On-going
7 4.24365 Metric Tons 8.45% 5-Apr-21 Issued Issued Issued Done Done 27.95616
installation

On-going
8 9.47734 Metric Tons 18.87% 4-May-21 Issued Issued Issued Done Done 37.43350
installation

On-going
9 7.09739 Metric Tons 14.13% 10-May-21 Issued Issued Issued Done Done 44.53089
installation

On-going
10 5.68511 Metric Tons 11.32% 25-Jun-21 Issued Issued Issued Done Done 50.21600
installation

Total 50.216 Metric Tons 100.00% Delivered 100.00%


ELIVERY OF STEEL DECK & SHEAR STUDS

DELIVERY STATUS FOR STEEL DECK

Shipment Quantity Unit RW Date Delivered BL CO PL Inspection Test Remarks

8 9,404.010 m2 37.04% 4-May-21 Issued Issued Issued Done Done Installed 9,404.010

Installed
9 8,426.890 m2 33.19% 10-May-21 Issued Issued Issued Done Done 17,830.900

10 6,055.900 m2 23.85% 25-Jun-21 Issued Issued Issued Done Done Installed 23,886.800

Remaining 1,504.280 m2 5.92% 25,391.080

Total 25,391.080 m2 100.00% Delivered 94.08%

DELIVERY STATUS FOR SHEAR STUDS

Shipment Quantity Unit RW Date Delivered BL CO PL Inspection Test Remarks

On-going
8 31,960.000 pcs 66.25% 4-May-21 Issued Issued Issued Done Done 31,960.000
installation

On-going
Remaining 16,283.050 pcs 33.75% 12-Jul-22 Issued Issued Issued Done Done 48,243.050
Unloading

Total 48,243.050 pcs 100.00% Delivered 100.00%


LIVERY OF WIRES AND CABLES- ELECTRICAL WORKS

Remaining Remaining
Item Description In (BOX) Meters Out (BOX) Meters Remarks
(BOX) (Meters)
3.5mm
1 THHN/THWN 23 3,450 23 3450 23 0.00 Complete qty.
(BLACK)
3.5mm
2 THHN/THWN 74 11,100 24 3600 50 7500 Complete qty.
(RED)
3.5mm
3 THHN/THWN 74 11,100 24 3600 50 7500 Complete qty.
(BLUE)
3.5mm
4 THHN/THWN 74 11,100 24 3600 7500 Complete qty.
50
(YELLOW)
3.5mm
5 THHN/THWN 134 20,100 24 3600 110 16,500 Complete qty.
(WHITE)
2.00 mm TW
6 171 25,650 20 3000 151 22,650 Complete qty.
(GREEN)
3.5mm
7 THHN/THWN 1 180 180 Complete qty.
(WHITE ROLL)

100mm2 (19X6mm)
8 1 1,500 1,500 Complete qty.
Comp. BS CU
LIVERY OF MATERIALS FOR CHANGE OF ELEVATION

Item Description In Out Remaining Remarks

122pcs 116 6 Complete qty.


1 Portland Cement
600lenght. 407 193 Complete qty.
2 100mmø Reinforcement Bars
Marine Plywood 40sheets 11 29 Complete qty.
3
2x2x8 CocoLumber
140pcs 69 61 Complete qty.
4
2x4x8 CocoLumber
60pcs 13 47 Complete qty.
5

Tie Wire 35kls 20 15 Complete qty.


6
EADY-MIXED CONCRETE POURING

Actual
Actual
Area BOQ This Actual Total Percentage Remaining Remarks
Previous
Week

Phase 1 1,278.48 1,236.82 1,236.82 96.74% 3.26% LGF

Phase 2 1,469.02 1,357.58 1,357.58 92.41% 7.59% LGF

LGF, 6th 7th


Phase 3 1,386.39 1,192.27 1,192.27 86.00% 14.00%
and RD.

Phase 4 630.12 466.78 466.78 74.08% 25.92%

Phase 5 574.33 451.14 451.14 78.55% 21.45%

Phase 6 730.12 410.70 410.70 56.25% 43.75%

TOTAL 6,068.46 5,115.30 5,115.30 84.29% 15.71%


ALITY ASSURANCE – MATERIAL TESTING FOR CONCRETE
ALITY ASSURANCE – MATERIAL TESTING FOR CONCRETE
ALITY ASSURANCE – MATERIAL TESTING FOR CONCRETE
ALITY ASSURANCE – MATERIAL TESTING FOR CONCRETE
LITY ASSURANCE – MATERIAL TESTING FOR REBARS AND ANCHOR BOLTS
REQUIRED (MPa) RESULTS (MPa)
DESCRIPTION DATE DELIVERED SUPPLIER REMARKS
Yield Point Tensile Strength Yield Point Tensile Strength

10Ǿ Rebar 3-Oct-20 Davao Diamond Industrial Supply 275.00 480.00 395.00 547.00 PASSED

12Ǿ Rebar 4-Oct-20 Davao Diamond Industrial Supply 275.00 480.00 429.00 548.00 PASSED

20Ǿ Rebar 5-Oct-20 Davao Diamond Industrial Supply 415.00 550.00 446.00 576.00 PASSED

25Ǿ Rebar 6-Oct-20 Davao Diamond Industrial Supply 415.00 550.00 460.00 621.00 PASSED

28Ǿ Rebar 7-Oct-20 Davao Diamond Industrial Supply 415.00 550.00 487.00 640.00 PASSED

32Ǿ Rebar 8-Oct-20 Davao Diamond Industrial Supply 415.00 550.00 495.00 674.00 PASSED

28Ǿ Rebar 26-Nov-20 Davao Diamond Industrial Supply 415.00 550.00 487.00 650.00 PASSED

28Ǿ Rebar 2-Dec-20 Davao Diamond Industrial Supply 415.00 550.00 490.00 656.00 PASSED

10Ǿ Rebar 8-Dec-20 Davao Diamond Industrial Supply 275.00 480.00 427.00 579.00 PASSED

12Ǿ Rebar 8-Dec-20 Davao Diamond Industrial Supply 275.00 480.00 398.00 548.00 PASSED

20Ǿ Rebar 8-Dec-20 Davao Diamond Industrial Supply 415.00 550.00 557.00 678.00 PASSED

25Ǿ Rebar 8-Dec-20 Davao Diamond Industrial Supply 415.00 550.00 505.00 646.00 PASSED

28Ǿ Rebar 8-Dec-20 Davao Diamond Industrial Supply 415.00 550.00 490.00 643.00 PASSED

10Ǿ Rebar 8-Mar-21 Davao Diamond Industrial Supply 275.00 480.00 382.00 573.00 PASSED

12Ǿ Rebar 8-Mar-21 Davao Diamond Industrial Supply 275.00 480.00 380.00 548.00 PASSED

25Ǿ Rebar 8-Mar-21 Davao Diamond Industrial Supply 415.00 550.00 485.00 611.00 PASSED

32Ǿ Rebar 8-Mar-21 Davao Diamond Industrial Supply 415.00 550.00 472.00 699.00 PASSED

25 mm Ø Anchor Bolt 5-Nov-20 Davao Diamond Industrial Supply 830.00 953.00 PASSED

25 mm Ø Anchor Bolt 11-Feb-21 Davao Diamond Industrial Supply 830.00 1,010.00 PASSED
10Ǿ Rebar Davao Diamond Industrial Supply
09-Feb-22 275.00 480.00 420.00 586.00 PASSED
LITY ASSURANCE – DIMENSIONAL & TENSILE TESTING FOR BOLTS
k s l d Tensile Strength

REQUIRED
22.10 - 22.90 54 - 55 99.83 - 100.2 35.48 - 36 800 MPa
SAMPLE DATE DELIVERED SUPPLIER REMARKS
mm mm mm mm 115,940 psi

Aspire Steel
Sample 2 M36X100 8-Feb-21 22.65 54.68 99.68 35.65 890 PASSED
Vietnam
Aspire Steel

RESULTS
Sample 2 M36X100 8-Feb-21 22.75 54.69 99.98 35.74 920 PASSED
Vietnam
Aspire Steel
Sample 3 M36X100 8-Feb-21 22.62 54.72 99.95 35.58 880 PASSED
Vietnam
Aspire Steel
Sample 4 M36X100 8-Feb-21 22.64 54.58 99.68 35.69 895 PASSED
Vietnam

k s l d Tensile Strength

REQUIRED
SAMPLE DATE DELIVERED SUPPLIER 22.10 - 22.90 54 - 55 119.3 - 120.7 35.48 - 36 800 MPa REMARKS
mm mm mm mm 115,940 psi
Aspire Steel
Sample1 M36X120 10-Feb-21 22.62 54.65 119.68 35.63 885 PASSED
Vietnam
Aspire Steel

RESULTS
Sample 2 M36X120 10-Feb-21 22.75 54.62 119.98 35.72 910 PASSED
Vietnam
Aspire Steel
Sample 3 M36X120 10-Feb-21 22.66 54.75 119.95 35.59 890 PASSED
Vietnam
Aspire Steel
Sample 4 M36X120 10-Feb-21 22.68 54.62 119.68 35.71 900 PASSED
Vietnam k s l d Tensile Strength

REQUIRED
SAMPLE DATE DELIVERED SUPPLIER 22.10 - 22.90 54 - 55 129.3 - 130.7 35.48 - 36 800 MPa REMARKS
mm mm mm mm 115,940 psi
Aspire Steel
Sample1 M36X130 25-Feb-21 22.63 54.68 129.68 35.55 900 PASSED
Vietnam
Aspire Steel

RESULTS
Sample 2 M36X130 25-Feb-21 22.76 54.62 129.98 35.61 910 PASSED
Vietnam
Aspire Steel
Sample 3 M36X130 25-Feb-21 22.63 54.7 129.95 35.58 895 PASSED
Vietnam
Aspire Steel
Sample 4 M36X130 25-Feb-21 22.64 54.56 129.68 35.57 900 PASSED
Vietnam

k = thickness of Hexa Nut / s = width of hexa nut / l = length of bolt / d = diameter of bolt
ALITY ASSURANCE –TORQUE TESTING OF BOLTS

Total number of joints tested to date : 402


196days of testing.
LITY ASSURANCE – TESTING FOR STRUCTURAL STEEL ELEMENT
REQUIREMENT RESULT
DATE DELIVERED DESCRIPTION SUPPLIER REMARKS
Thickness Width Yield Strength Tensile Strength Thickness Width Yield Strength Tensile Strength

STEEL PLATE ASPIRE STEEL 250 Mpa


February 10, 2021 6 40 ± 2 400-500 Mpa 6 38.6 431.93 518.3 PASSED
(50x500x6) INTERNATIONAL (Minimum)
STEEL PLATE ASPIRE STEEL 250 Mpa
February 10, 2021 8 40 ± 2 400-500 Mpa 8 38.6 469.72 544.2 PASSED
(50x500x8) INTERNATIONAL (Minimum)
STEEL PLATE ASPIRE STEEL 250 Mpa
February 10, 2021 10 40 ± 2 400-500 Mpa 10 40.7 422.75 486.7 PASSED
(50x500x10) INTERNATIONAL (Minimum)
STEEL PLATE ASPIRE STEEL 250 Mpa
February 10, 2021 12 40 ± 2 400-500 Mpa 12 41.6 390.76 517 PASSED
(50x500x12) INTERNATIONAL (Minimum)
STEEL PLATE ASPIRE STEEL 250 Mpa
February 10, 2021 16 40 ± 2 400-500 Mpa 16 38.5 519.66 581.4 PASSED
(50x500x16) INTERNATIONAL (Minimum)
STEEL PLATE ASPIRE STEEL 250 Mpa
February 10, 2021 20 40 ± 2 400-500 Mpa 20 41 384.28 546.5 PASSED
(50x500x20) INTERNATIONAL (Minimum)
STEEL PLATE ASPIRE STEEL 250 Mpa
February 25, 2021 6 40 ± 2 400-500 Mpa 6 42 396.96 516 PASSED
(50x500x6) INTERNATIONAL (Minimum)
STEEL PLATE ASPIRE STEEL 250 Mpa
February 25, 2021 8 40 ± 2 400-500 Mpa 8 42 401.92 535.9 PASSED
(50x500x8) INTERNATIONAL (Minimum)
STEEL PLATE ASPIRE STEEL 250 Mpa
February 25, 2021 10 40 ± 2 400-500 Mpa 10 40.7 428.72 500.2 PASSED
(50x500x10) INTERNATIONAL (Minimum)
STEEL PLATE ASPIRE STEEL 250 Mpa
February 25, 2021 12 40 ± 2 400-500 Mpa 12 42 456.51 535.9 PASSED
(50x500x12) INTERNATIONAL (Minimum)
STEEL PLATE ASPIRE STEEL 250 Mpa
February 25, 2021 16 40 ± 2 400-500 Mpa 16 40 500.17 719 PASSED
(50x500x16) INTERNATIONAL (Minimum)
STEEL PLATE ASPIRE STEEL 250 Mpa
February 25, 2021 20 40 ± 2 400-500 Mpa 20 41.5 470.04 554.4 PASSED
(50x500x20) INTERNATIONAL (Minimum)
STEEL PLATE ASPIRE STEEL
250 Mpa PASSED
October 16, 2021 (50x500x20) INTERNATIONAL 20 40 ± 2 400-500 Mpa 20 38 405.40 502.8
(Minimum)

STEEL PLATE ASPIRE STEEL


250 Mpa PASSED
October 16, 2021 (50x500x20) INTERNATIONAL 20 40 ± 2 400-500 Mpa 20 38 405.40 516.0
(Minimum)
ALITY ASSURANCE – TESTING FOR BI PIPES OF FIRE PROTECTION
HEALTH & SAFETY – COMBINED TRADES

Trade Previous Weeks Cumulative Present Week Cumulative

Civil & Structural 456,046.00 458,398.00

Plumbing & Sanitary 108,208.00 110,560.00

Exterior AAC Walls 82,440.00 84,204.00

Fire Protection 16,392.00 16,824.00

Electrical 16,908.00 17,438.00

Mechanical 32,880.00 33,888.00

Electronics / Auxiliary 9,552.00 9,848.00

Interior AAC Walls 12,288.00 24,576.00

Exterior Glass & Glazing 7,680.00 15,360.00

Civil Woks for Change of elevation 192 576.00

Total Safe Man-Hours 722,426.00 731,426.00

Average Daily Manpower 93 85


OGRESS PHOTOS – CIVIL /STRUCTURAL – FRONT VIEW

Present Week

Previous Week
OGRESS PHOTOS – CIVIL /STRUCTURAL – LEFT SIDE VIEWS
OGRESS PHOTOS – CIVIL /STRUCTURAL – OTHER VIEWS
GRESS PHOTOS – CIVIL /STRUCTURAL – STEEL ERECTION AT PHASE4 @ THE TOP
GRESS PHOTOS – CIVIL /STRUCTURAL – STEEL ERECTION AT PHASE 4 & 5
OGRESS PHOTOS – CIVIL /STRUCTURAL – VIEW FROM THE TOP
OGRESS PHOTOS - PHASE 3 - 6F STEEL DECKING WORKS
OGRESS PHOTOS - PHASE 3 - 7F STEEL DECKING WORKS
OGRESS PHOTOS - PHASE 3 – ROOF DECK STEEL DECKING WORKS
ROGRESS PHOTOS – CIVL / STRUCTURAL – SUSPENDED SLABS – Phase 1
OGRESS PHOTOS – CIVL / STRUCTURAL – SUSPENDED SLABS – Phase 2

PHASE 2- 2F PHASE 2- 3F PHASE 2- 4F

PHASE 2- 5F PHASE 2- 6F PHASE 2- 7F

PHASE 2- RD
OGRESS PHOTOS – CIVL / STRUCTURAL – SUSPENDED SLABS – Phase 3

PHASE 3- 2F PHASE 3- 3F

PHASE 3- 4F PHASE 3- 5F
PROGRESS PHOTOS - EXTERNAL AAC WALLS – Phase 1 to 2

2nd FL 3rd FL 4th FL

5th FL 6th FL 7th FL


OGRESS PHOTOS - PLUMBING & SANITARY –SOIL & DRAINAGE PIPES - Phase 1 - 2

PHASE 1- 2F PHASE 2- 2F PHASE 1- 3F PHASE 2


3F

PHASE 1- 4F PHASE 2- 4F PHASE 1- PHASE 1-


5F 6F
OGRESS PHOTOS - FIRE PROTECTION WORKS – CROSS MAIN & BRANCHES – Phase

PHASE 1- PHASE 1- PHASE 1- PHASE 1-


2F 3F 4F 5F

PHASE 2- PHASE 2- PHASE 2- PHASE 2-


2F 3F 4F 4F
PROGRESS PHOTOS - MECHANICAL WORKS – Phase 1 & 2
GRESS PHOTOS - ELECTRICAL WORKS – WIRES & CABLES INSTALLATION.
GRESS PHOTOS -2ND & 3RD FLOOR-INTERIOR AAC WALLS- SPURWAY ENTERPRISE
GRESS PHOTOS -EXTERIOR GLASS AND GLAZING WORKS- PHILIPS GLASS
PROGRESS PHOTOS -CIVIL WORKS FOR CHANGE OF ELEVATION
PROGRESS PHOTOS - COMBINED MEPF ABOVE CEILING INSTALLATIONS - 2F
PROGRESS PHOTOS - COMBINED MEPF ABOVE CEILING INSTALLATIONS -3F
PROGRESS PHOTOS - COMBINED MEPF ABOVE CEILING INSTALLATIONS – 4F
PROGRESS PHOTOS - COMBINED MEPF ABOVE CEILING INSTALLATIONS – 5F
UPDATE ON BILLINGS
RDED CONTRACTS & VALUE OF ACCOMPLISHMENT TO DATE
RDED CONTRACTS & VALUE OF ACCOMPLISHMENT TO DATE
TATUS OF PROCUREMENT
TATUS OF PROCUREMENT
TATUS OF PROCUREMENT
OK-AHEAD SCHEDULE & MILESTONE TARGET DATES
Activity Target Dates Remarks
CP-01: Civil & Structural Works August 20, 2022 93.00%

Complete Steel Erection for Building Superstructure October 31, 2021 Delayed at 85.01%

Concrete Topping-Off Building Superstructure November 30, 2021 Delayed at 87.91%


Complete Steel Erection for 2nd Floor Driveway December 31, 2021

Plumbing and Sanitary Works (Started 6-1-21) August 20, 2022 31.50%
Exterior AAC Walls (Started 8-9-21) August 20, 2022 33.00%
Fire Protection Works (Started 7-1-21) August 20, 2022 42.00%
Mechanical Works (Started 8-16-21) August 20, 2022 31.50%
Electrical Works (Started 8-30-21) August 20, 2022 25.00%
Electronics / Auxiliary Works (Started 10-25-21) August 20, 2022 18.00%

Exterior Glazing, Windows and Doors (Started 8-9-21) August 20, 2022 23.00%

Interior AAC, Drywall, Ceiling & Vinyl Floor August 20, 2022 5.00%

OSM Lighting Fixtures & Wiring Devices (NOA 9-13-21) August 20, 2022 Start deliveries

Award Other Basic Architectural & Other Packages Until August to September 2022

MEPF and Medical Equipment Testing & Commissioning September 15 to October 15, 2022

Progressive Inspections by concerned Government Agencies (Fire, OBO, DOH,


October 15 to November 31, 2022
EMB, etc.) to Acceptance

Project Completion for 1st Priority (GF – 5F) December 31, 2022
September 21, 2020 to December 31, 2022 / 619 Calendar
Overall Schedule
Days
EVISED PROJECTED OVERALL SCHEDULE