WEEKLY STATUS REPORT

(by Contract)
As of July 13, 2021

PROJECT TITLE: CONSTRUCTION OF ABAB EARTH COVERED MAGAZINE BUILDING (IGLOO) LOCATION: TOW WEST ABAB, Brgy San Miguel PPC, Palawan

CONTRACTING AMOUNT: P 12,588,322.85 CONTRACTOR: L.B.LEONCIO TRADING AND CONSTRUCTION


DURATION: DATE STARTED: MAY 3, 2021 EDOC: FEBRUARY 26,2022
EXTENSION/SUSPENSION: FINAL TARGET DATE:

WEIGHT IN AMOUNT LAST % COMPLETED TO SCHEDULED EQUIVALENT IN


THIS REPORT TO DATE VARIANCE
% REFERENCE REPORT DATE ACCOMP DAYS
ITEM NO. SCOPE OF WORKS
(refer to PERT/
(a) (b) (c) (b+c=d) (a*d)/100 (-/+) (+ Ahead/ - Delay)
CPM/ S-CURVE)
PART II OTHER GENERAL REQUIREMENTS 0.00 0.00% 0.000% 0.00% 0
B.3 Permits and Clearances 0.10% 12,434.26 0.05% 0.05% 0.05% 0.022%
B.5 Project Billboard/ Signboard 0.03% 3,189.66 0.03% 0.03% 0.03% 0.006%
B.7(2) Occupational Safety and Health Program 0.12% 15,320.74 0.12% 0.12% 0.12% 0.028%
B.9. Mobilization/Demobilization 0.77% 97,095.39 0.39% 0.39% 0.39% 0.386%
III CIVIL,MECHANICAL,ELECTRICAL AND SANITARY/PLUMBING WORKS 0.00% 0
PART A EARTHWORK
105(1)a Subgrade Preparation, Common Material 0.23% 29,547.72 0.03% 0.03% 0.03% 0.000%
803(1)a Structure Excavation, Common Material 1.26% 158,722.93 0.60% 0.60% 0.60% 1.261%
804(1)a Embankment from Structure Excavation 0.63% 78,722.41 0.26% 0.26% 0.26% 0.250%
804(1)b Embankment from Borrow 9.61% 1,209,735.03 0.64% 0.64% 0.64% 0.000%
804(4) Gravel Fill 1.51% 190,502.71 0.53% 0.53% 0.53% 0.486%
807(14) Gate 4.10% 515,651.54
PART B PLAIN AND REINFORCED CONCRETE WORK
900(1)c1 Structural Concrete, Class A, 28 Days 34.62% 4,358,374.24 2.68% 2.68% 2.68% 4.773%
902(1)a Reinforcing Steel (Deformed), Grade 40 19.90% 2,504,728.84 2.45% 2.45% 2.45% 3.208%
902(1)b Reinforcing Steel (Deformed), Grade 60 0.57% 71,358.40 0.50% 0.50% 0.50% 0.170%
903(1) Formworks and Falseworks 4.20% 528,874.08 1.05% 1.05% 1.05% 0.000%
903(2) Formworks and Falseworks 4.42% 556,916.16 0.48% 0.48% 0.48% 0.150%
PART C FINISHINGS AND OTHER CIVIL WORKS
1006(6) Steel Door and Frames 0.51% 64,765.72
1016(1)a Waterproofing, Cement Base 5.75% 723,422.39
1016(1)b Waterproofing, Liquid 4.00% 502,993.03
1027(1) Cement Plaster Finish 0.64% 80,652.66
1046(2)a1 CHB Non-Load Bearing (including Reinforcing Steel), 100mm 1.17% 147,292.85
PART D ELECTRICAL WORKS
1109(3) Air Terminal 2.28% 286,792.26
PART H MISCELLANEOUS STRUCTURES
622(1)b Coco-Net, CN700 1.81% 228,167.29
622(3)a Vegetation, Grass-Cover 1.77% 223,062.53
TOTAL 100% 12,588,322.85 9.81% 9.81% 9.81% 10.74% 0.93%

Prepared by: Submitted by:

Signature Signature

RICHARD S. ABIA LORENZO B. LEONCIO


PROJECT ENGINEER AUTHORIZED MANAGIN OFFICER

Attachment:
Progress Photographs