DPWH - CAGAYAN SECOND DISTRICT ENGINEERING OFFICE

CONTRACTOR'S STATEMENT OF WORK ACCOMPLISHED

Project ID: 20BC0049


Project Name: Construction/Improvement of Access Road Leading to Declared Tourism Destinations-Access Road leading to Mingay Beach Resorts
San Juan, Sta. Praxedes, CagayanNorth Road to Pineapple and Sarakat Plantation
Project Name:
Contractor: DYLAN EQUIPMENT, CONSTRUCTION & SUPPLIES San Juan, Sta. Praxedes, Cagayan Payment Certificate No.____________________
Sheet___________________of_______________
TOTAL UNIT PRICE TOTAL QTY. QTY TOTAL QTY.
ITEM NO. DESCRIPTION UNIT CONTRACT IN APPROVED IN APPROVED IN TO THIS COST OF COST TO
QUANTITY PESOS PREV. BILLING THIS BILLING DATE THIS BILLING DATE
PART A FACILITIES FOR THE ENGINEER
A.1.4(1) Provision of Progress Photographs months 6.40 304.78 1.60 1.60 487.65 487.65
TOTAL PART A
PART B OTHER GENERAL REQUIREMENTS
B.5 Project Billboard/Signboard ea 2.00 3,365.79 2.00 2.00 6,731.58 6,731.58
B.7(2) Occupational Safety and Health Program l.s. 1.00 69,191.52 0.25 0.25 17,297.88 17,297.88
B.8(2) Traffic Management l.s. 1.00 28,051.26 0.25 0.25 7,012.82 7,012.82
B.9 Mobilization/Demobilization l.s. 1.00 235,966.72 0.50 0.50 117,983.36 117,983.36
TOTAL PART B
PART C EARTHWORKS
10(3)a1 Individual Removal of Trees (150-300 mm dia), small ea 85.00 516.57 85.00 85.00 43,908.45 43,908.45
100(3)a2 Individual Removal of Trees (301-500 mm dia), small ea 9.00 739.93 9.00 9.00 6,659.37 6,659.37
103(3) Individual Removal of Trees (501-700mm dia), small ea 1.00 11,149.31 1.00 1.00 11,149.31 11,149.31
101(4)a3 Removal of Actual Structures/Obstruction, 910mm dia RCPC ln.m. 4.00 715.00 - - -
101(4)a5 Removal of Actual Structures/Obstruction, 1220mm dia RCPC ln.m. 5.00 953.51 - - -
102(2) Surplus Common Excavation cu.m. 27,548.00 183.22 22,038.40 22,038.40 4,037,875.65 4,037,875.65
103(1)a Structure Excavation (Common Soil) cu.m. 1,993.76 291.95 749.26 749.26 218,745.00 218,745.00
103(3) Foundation Fill cu.m. 301.55 810.28 113.32 113.32 91,822.95 91,822.95
103(6)a Pipe Culvert and Drain Excavation (Common Soil) cu.m. 75.51 291.95 - - - -
104(1)a Embankment from Roadway Excavation (Common Soil) cu.m. 337.00 121.85 286.45 286.45 34,903.93 34,903.93
105(1)a Subgrade Preparation (Common Material) sq.m. 6,104.00 20.31 3,834.00 3,834.00 77,868.54 77,868.54
TOTAL PART C
PART D SUBBASE AND BASE COURSES
200(1) Aggregate Subbase Course cu.m. 1,643.00 578.05 142.00 142.00 82,083.10 82,083.10
TOTAL PART D
PART E SURFACE COURSES
311(1)a Portland Cement Concrete Pavement (Unreinforced), 0.15 m thick, 14 days sq.m. 1,081.00 785.86 305.00 305.00 239,687.30 239,687.30
311(1)e1 Portland Cement Concrete Pavement (Unreinforced), 0.23 m thick, 14 days sq.m. 6,710.00 1,202.02 - - - -
TOTAL PART E
PART G DRAINAGE AND SLOPE PROTECTION STRUCTURES
405(1)a3 Structural Concrete, Class A, 20.68MPa at 28 days cu.m. 939.48 6,209.30 390.00 390.00 2,421,627.00 2,421,627.00
404(1)a Reinforcing Steel, Grade 40 kgs. 46,100.82 68.24 28,512.14 28,512.14 1,945,668.24 1,945,668.24
500(1)a3 Pipe Culverts, 910 mm dia. Class II RCPC ln.m. 66.00 4,533.56 - - - -
505(2)a Grouted Riprap, Class A cu.m. 1.14 3,607.05 - - - -
511(1)a3 Gabions cu.m. 150.00 8,482.42 - - - -
TOTAL PART G
PART H MISCELLANEOUS
603(3)a1 Metal Guardrail (Metal Beam) Including Post, Single, W-Beam ln.m. 330.00 3,602.97 - - - -
603(4)a Metal Beam End Piece, Fish Tail ea 10.00 2,012.95 - - - -
605(6)c1 Hazard Markers, 450x600mm, Chevron Signs ea 60.00 23,294.32 - - - -
TOTAL PART H
TOTAL
WE HEREBY CERTIFY that the Statement of TOTAL 9,361,512.13 9,361,512.13
Work Accomplished on this page is true and correct.
NOTED:

DYLAN EQUIPMENT, CONSTRUCTION & SUPPLIES MARIO C. NATIVIDAD LORNA B. ASUTEN


Contractor's Project Engineer Chief, Construction Section District Engineer