Professional Documents
Culture Documents
Prepared By
AFZAL SAMA PSD22012
MEET SHAH PSD22194
Architectural Drawing
56.5 m
Problem Statement :-
1)
• G+9 storeys
• Without Provision of separation joint in building
• Determine whether building is torsionally irregular or not as per IS
1893:2016.
• Suggest different alternatives to mitigate the effect of torsion in
building.
37.5 m
6m 3m
No column distance
between two column is Introduction of column.
around 6 m Column distance between
two column is around 3 m
Final Structural System
FINAL ITERATION 3m
FIRST ITERATION 6m
INITIAL ITERATION
SECOND ITERATION
ETABS MODEL
ETABS MODEL
FIRST ITERATION SECOND ITERATION
• Spacing between • Spacing between
some column is some column is
around 5-6m around 3-4m
• Outcome Large • Outcome Small AST
AST required and required and no
need for large need for large
dimension of the dimension of the
element. element.
Load Consideration & Static check
Manual ETABS
Dead Load (As Per I.S 875 Part 1) Total Load for Static check Load Case Error(%)
(kN) (kN)
Slab Load (125 mm Thick) :- 3.125 kN/m2 Dead 5475.00 5726 -4.38
Typical floor of the Architectural drawing was Modelled in
Slab Load (150 mm Thick) :- 3.75 kN/m2 SUNK 467.97 476 -1.69
Etabs however Loads were calculated manually which Wall 3037 3019 0.60
Wall (Density 15 kN/m3) :- 3.825 kN/m
Floor finish :- 1.5 kN/m2 Includes Dead Load & Self Weight in Dead load (self- Floor
Finish 1503.88 1503 0.06
• Density of cement mortar :- 20.4 kN/m 3 weight, Sunk load , floor finish, wall load) were calculated Live 2268.959 2260 0.40
• Thickness of layer :- 15 mm and Percentage error was estimated.
Total Load 12752.81 12984 -1.78
• Density of Sand :- 18.5 kN/m 3
TOTAL LOAD CALCULATION
• Thickness of Layer :- 25 mm
• Density of marble :-26.7 kN/m 3 Intensity check
• Thickness of marble :- 25 mm
• Total :- 1.427 kN/m2 Manual ETABS Load Intensity
Load Case Error (%) Manual ETABS
Terrace Waterproofing :- 1.5 kN/m2 (kN) (kN)
(kN/m ) (kN/m2)
2
Overhead Water Tank (10000 liters assumed) :- 4.98 Dead 5475.00 5726 -4.38 5.62 5.87
kN/m2 Sunk 467.97 476 -1.69 0.48 0.49
Sunk slab (250 mm) :- 3.5 kN/m2 Wall 3037 3019 0.60 3.11 3.10
• Depth of Sunk slab :- 0.3 m Floor ETABS MODELED FOR TYPICAL FLOOR
Finish 1503.88 1503 0.06 1.54 1.54
• Density of filling material :- 12 kN/m 3
• Thickness of Filling Material :- 0.28 m
Live
Total Load
2268.959
12752.81
2260
12984
0.40
-1.78
2.33
13.08
2.32
13.32
Load Intensity
• Density of Water Proofing :- 4.9 kN/m 3
• Thickness of Water Proofing :- 0.02 m 17%
Total area of typical floor :- 975 m2
• Total load :- 3.458 kN/m2 44%
Total Load Intensity :- 13.08 kN/m2 12%
LIVE LOAD (As Per I.S 875 Part 2) Total Percentage Error :- 1.78 % 23% 4%
Bedroom, Kitchen, Hall, Dinning, Toilet :- 2 kN/m2
Passage, Balconies :- 3 kN/m2
Dead Sunk Wall
Floor Finish Live
Earthquake Base Shear Calculation
NOTATION DESCRIPTION VALUE UNIT REFRENCE
BASE SHEAR MANUAL ETABS %ERROR
Seismic Zone V
Z Seismic Zone Factor 0.36 CL.6.4.2 EQX (kN) 11304.5 10924.04 3.36
I Importance Factor 1.2 CL.7.2.3
R Response Reduction Factor 5 CL.7.2.6 EQY (kN) 11304.5 10924.04 3.36
1% 2079-2385 300*600
2% 2385-3465 300*700
Storey Shear Check Manual & Etabs
CUMULATIVE
FLOOR HI WI (kN) WIHI2 WIHI2/ΣWIHI2 QI
QI (kN)
TERRACE 32.6 9343.75 9930163.75 0.20 2363.01 2363.01
Story9 29.6 11289 9890970.24 0.20 2353.68 4716.7
Story8 26.6 11289 7987644.84 0.16 1900.76 6617.466
Story7 23.6 11289 6287521.44 0.13 1496.19 8113.665
Story6 20.6 11289 4790600.04 0.10 1139.98 9253.651
Story5 17.6 11289 3496880.64 0.07 832.12 10085.78
Story4 14.6 11289 2406363.24 0.05 572.62 10658.41
Story3 11.6 11289 1519047.84 0.03 361.47 11019.88
Story2 8.6 11289 834934.44 0.01 198.68 11218.57
Story1 5.6 11289 354023.04 0.007 84.24 11302.81
GF 2 2137 8548 0.00017 2.03 11304.85
BASE 0 0 0 0 11304.85
TOTAL = 47506697.51
MANUAL STOREY SHEAR CALCULATION
ETABS MAX STOREY DIRFT ALONG X ETABS MAX STOREY DIRFT ALONG X After applying cracked moment
Story8 26.6 Top 0.00505 0.00064 Story8 26.6 Top 0.00965 0.00159 of inertia Max Storey drift
increased by around 1.91 times.
Story8 26.6 Top 0.00036 0.00449 Story8 26.6 Top 0.00084 0.0093
Max Storey Displacement
Without Crack moment of inertia With Crack moment of inertia
WATER
15.87 31.67 16.62 30.67
TANK
Remark: - The Centre of mass and Centre of rigidity has been plotted of storey two so it has
eccentricity between COM & COR which will create torsion in the structure
Frame Participation
FRAME PARTICIPATION IN X DIRECTION FRAME PARTICIPATION IN Y DIRECTION
REMARK: - It was observed that a greater number of through frame attract REMARK: - It was observed that a greater number of through frame attract
more load and hence more load was attracted by shear wall. Overall, 100 % more load and hence more load was attracted by shear wall. Overall, 100 %
Base shear of VBX was taken by frames shown in the above figure. In the Base shear of VBY was taken by frames shown in the above figure. In the
ETABS result it was understood that the total VBX of 101% was with 1% of ETABS result it was understood that the total VBX of 97% was with 3% of
error. error.
Further Work