Republic of the Philippines

DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS


OFFICE OF THE DISTRICT ENGINEER
Zamboanga del Sur 1st Engineering District
Pagadian City

Accomplishment no.
_________

Contrat ID :16JE0003
Name of Project :Rehabilitation/Reconstruction/Upgrading of Damaged Paved National Roads
including Drainage Based on Pavement Management System/Highway Dev't & Management-4
Station :K1666+000 to K1666+600
Location :Sindangan-Siayan-Dumingag-Mahayag Road
Contractor: :Ramona Construction And Enterprises
Contrac Amount: : 14,258,998.31
Status of the Project: STATEMENT OF WORK ACCOMPLISHMENT (SWA)
(As of ______________________________________)

% RELATIVE
ITEM NO. DESCRIPTION QUANTITY UNIT UNIT COST TOTAL Wt. QUANTITY ACCOMPLIS
PREV. THIS PERIOD
1 Maintainance and Protection of Traffic 3.50 Mo. 26,027.43 91,096.01 0.639%
101(4)b Removal of Existing Asphalt pavement 5,161.40 Sq.m. 107.70 555,882.78 3.898%
102(2)b Roadway Excavation (Surplus Common) 79.16 Cu.m. 141.14 11,172.64 0.078%
104(1)b Embankment (from Excavation) 9.83 Cu.m. 204.19 2,007.19 0.014%
105(2) Subgrade Preparation (common soil) 5,161.40 Sq.m. 16.26 83,924.36 0.589%
200 Aggregate Sub-Base Course 1,396.74 Cu.m. 1,034.29 1,444,634.21 10.131%
300(1) Gravel Surface Course (uncrushed) 288.84 Cu.m. 1,179.32 340,634.79 2.389%
311(1)a.5 PCCP (Plain)-Conventional Method, 280mm thick 3,886.00 Sq.m. 1,508.24 5,861,020.64 41.104%
506 Stone Masonry 1,420.29 Cu.m. 3,633.96 5,161,277.05 36.197%
FEA 1.1 Construction Safety and Health Program 1.00 Lot 65,690.60 65,690.60 0.461%
FEA 1.2 Bunkhouse, Type II and complete Equipment 1.00 L.S. 519,905.64 519,905.64 3.646%
SPL 1 Mobilization & Demobilization 1.00 L.S. 121,752.40 121,752.40 0.854%
TOTAL 14,258,998.31 100.00%

Prepared by: Checked & Verified by:

ENGR. JESUS A. MANIAGO JR. Engr.Roger A. Acedillo


Project Engineer Authorized Managing Officer
IGHWAYS

strict

Project Duration: 105 Calendar Days


Date Started:
Target Completion Date:
% Proj. Accomp. To Date:
Slippage;

T (SWA)
_______)

ACCOMPLISHMENT %
Y ACCOMPLISHMENT % ACCOMPLISHMENT VALUE OF ACCOMPLISHMENT WEIGHTED REMARKS
HIS PERIOD TO DATE PREV. THIS PERIOD TO DATE PREV. THIS PERIOD TO DATE ACCOMP.

Approved by:

Acedillo TESSIE J. YU
ging Officer Proprietor