You are on page 1of 5

Km.

7 Tigatto Road, Buhangin, Davao City

PROJECT ACCOMPLISHMENT REPORT


PROJECT STATUS:
Accomplishment to Date : 61.76
Required as per PERT CPM : 100.00
Period Accomplishment : 3.45

CUMULATIVE PROGRESS
SCHEDULED
ITEM NO. ACTIVITY DESCRIPTION UNIT
QUANTITY (PERT-CPM)

PART B: Other General Requirements


B.5 Project Billboard /Signboard each 4.00
B.7(1) Occupational Safety and Health Program mo 4.00
B.7(1) Traffic Management mo 4.00
B.9 Mobilization and Demobilization ls 1.00
B.4(1) Construction Survey & Staking km 2.04
PART C: Earthworks
101(1) Removal of Structures and Obstructions ls 1.00
102(1) (including
UnsuitableRestorations-wooden
Excavation house) cu.m. 15,130.70
103(1)a Structure Excavation cu.m. 3,345.00
103(6)a Pipe Culvert and Drain Excavation cu.m. 10.25
104(2)a Embankment (from Borrow) cu.m. 9,616.03
PART D: Subbase and Base Course
200(1) Aggregate Subbase Course cu.m. 821.50
PART G: Drainage and Slope Protection Structures
404(1)a Reinforcing Steel Grade 40 kg 64,676.60
405(1)a3 Structural Concrete Class A cu.m. 698.79
500(1)b1 Pipe Culvert, 610mm dia. (24" dia.) ln.m. 20.00
505(1)b7 Pipe Culverts, 1830mm dia. (72" dia.) ln.m. 333.00
502(1)g Manhole (1830mm dia. RCPC) each 20.00
510(1) Bed Course Granular Material cu.m. 1,510.06
510(2) Concrete (Slope Protection) cu.m. 1,984.62
EXTRA WORK
401(1)a1 Metal Railing Ln.m. 484.00
101(3)b3 Removal of Existing Concrete Pavement sq.m. 28.50
101(2)f Removal of RCPC(60" diam.) - 1520mm ln.m. 13.00
101(2) Removal of Existing Headwall each 6.00
502(1)g PCC Pavement (Unreinforced) 0.28 m. thk. sq.m. 11.40

Total
Page No.:

o City

T REPORT

Period : Aug 1-31, 2019 PROJECT COST:


Project ID No. : 18LC-0104 Budget to Date
:
Project Code Name : Actual Budget
La Filipina Drainage Canal : 46,763,373.61

CUMULATIVE PROGRESS
CUMMULATIVE
HEDULED ACCOMPLISHMENT
NET WT. NET WT. REMARKS
QUANTITY
% %

0.040 4.00 0.040 Completed


0.144 4.00 0.144 Completed
0.103 4.00 0.103 Completed
0.031 0.50 0.016 Issue with RROW
0.081 2.04 0.081 Completed

0.207 0.85 0.176 Issue with RROW


8.800 12,276.97 7.140 On going
1.979 3,405.65 2.015 Completed
0.005 11.36 0.006 Completed
12.048 3,845.23 4.818 On going

1.070 - -

9.033 58,858.07 8.220 On going


9.457 568.67 7.696 Due for Pouring
0.156 1.000 0.008
12.257 320.00 11.778 19 left
6.448 20.00 6.448
2.930 670.41 1.301 On going
30.811 753.63 11.700 On going

4.233 0.00
0.011 14.25 0.01 half of existing RCPC
0.036 6 0.02 demolished
0.053 3 0.03
0.043 0.00 After Box Culvert

100 61.757
Km.7 Tigatto Road, Buhangin, Davao City

PROJECT TARGET REPORT


PROJECT STATUS:
Accomplishment to Date : 53.94 Period : July 1-31, 2019 PROJECT COST:
Required as per PERT CPM : 100.00 Project ID No. : 18LC-0104 Budget to Date :
Period Accomplishment : 0.00 Project Code Name : La Filipina Drainage Canal Actual Budget : 47,530,183.04

CUMULATIVE PROGRESS
CUMMULATIVE ACCOMPLISHMENT TO
SCHEDULED
ACCOMPLISHMENT
TARGET DATE Month of JULY
ITEM NO. ACTIVITY DESCRIPTION UNIT REMARKS
QUANTITY NET WT. NET WT. NET WT. NET WT.
(PERT-CPM)
QUANTITY QUANTITY QUANTITY Week 1 Week 2 Week 3 Week 4
% % % %
PART B: Other General Requirements 1 2 3 4 5 6 8 9 10 11 12 13 15 16 17 18 19 20 22 23 24 25 26 27
B.5 Project Billboard /Signboard each 4.00 0.040 4.00 0.040 - - Completed
B.7(1) Occupational Safety and Health Program mo 4.00 0.144 4.00 0.144 - - Completed
B.7(1) Traffic Management mo 4.00 0.103 4.00 0.103 - - Completed
B.9 Mobilization and Demobilization ls 1.00 0.031 0.50 0.016 - -
B.4(1) Construction Survey & Staking km 2.04 0.082 2.04 0.082 - - Completed
PART C: Earthworks
Removal of Structures and Obstructions
101(1) (including Restorations-wooden house) ls 1.00 0.207 0.85 0.176 With Revisions

102(1) Unsuitable Excavation cu.m. 16,518.00 9.608 12,276.97 7.141 On going


103(1)a Structure Excavation cu.m. 3,406.00 2.015 3,405.65 2.015 Completed
103(3) Foundation Fill cu.m. 10.00 0.021 9.04 0.020
103(6)a Pipe Culvert and Drain Excavation cu.m. 11.36 0.006 11.36 0.006 Completed
104(2)a Embankment (from Borrow) cu.m. 9,851.00 12.342 3,845.23 4.818
PART D: Subbase and Base Course
200(1) Aggregate Subbase Course cu.m. 944.00 1.229 - -
PART G: Drainage and Slope Protection Structures
404(1)a Reinforcing Steel Grade 40 kg 54,913.00 7.669 52,611.25 7.348 328.82 0.046 328.820 0.046 On going 0.046
405(1)a3 Structural Concrete Class A cu.m. 589.87 7.983 568.67 7.696 21.19 0.287 On going 0.287
500(1)b1 Pipe Culvert, 610mm dia. (24" dia.) ln.m. 21.00 0.164 1.000 0.008 20.00 0.156 On going 0.156
505(1)b7 Pipe Culverts, 1830mm dia(72" dia.) ln.m. 348.00 12.809 320.00 11.778 -
502(1)g Manhole (1830mm dia. RCPC) each 21.00 6.770 20.00 6.448 - considered completed

510(1) Bed Course Granular Material cu.m. 1,736.04 3.369 361.35 0.701 319.16 0.619 52.610 0.102 On going 0.155 0.155 0.155 0.155

510(2) Concrete (Slope Protection) cu.m. 2,280.68 35.407 347.86 5.400 419.28 6.509 69.090 On going
1.070 1.627 1.627 1.627 1.627

TOTAL 100.00 53.940 7.62 1.22 Total 1.828 1.782 1.782 2.225
Cummulative 7.62

Prepared by:
Renzo Ray M. Olivar
Office Engineer
Verified Correct by:
Project Inspector / Assistant Chief Engineer

Approved by:
Chief Engineer

You might also like