Construction of Evacuation Center, Purok Tisa, Barangay Don Jose,

Dinas, Zamboanga del Sur

CONTRACT ID. NO.:


EFFECTIVITY OF CONTRACT:
EXPIRY DATE:
CONTRACT DURATION: 180 CD
CONTRACT COST: Php 34,416,077.14

CONSTRUCTION SCHEDULE AND S-CURVE

ITEM ESTIMATED COST


DESCRIPTION QTY UNIT WT.%
NO. TOTAL(P) UNIT COST
Part A: FACILITIES FOR THE ENGINEERS
A.1.1(3) Construction of Field Office for Engineer 1.00 L.S 582,091.43 582,091.43 1.00

A.1.1(11) Provision of Furnitures/Fixtures, Equipment, & Appliances 1.00 L.S 5,992.68 5,992.68 1.00
for the Field Office for the Engineer

A.1.1(11) Operation and Maintenance of 4x4 Pick-Up Type 1.00 L.S 205,584.18 205,584.18 1.00
for the Field Office for the Engineer
Part B: OTHER GENERAL REQUIREMENTS
B.4(1) Construction Survey & Staking 1.00 63,203.48 63,203.48 1.00
B.5 Project Billboard/Signboard 1.00 L.S 63,203.48 63,203.48 1.00
B.7 Occupation Safety & Health 876.83 cu.m 464,107.22 529.30 1.00
B.9 Mobilization and Demobilization 735.35 cu.m 49,667.57 67.54 1.00
Part C: EARTHWORKS
104(2)a Embankment from Borrow 589.00 sq.m 1,254,466.66 2,129.82 1.00
Part D: SUBBASE AND BASE COURSE
200(1) Aggregate Subbase Course 705.49 cu.m 4,178,389.76 5,922.67 1.00
Part E: DRAINAGE AND SLOPE PROTECTION STRUCTURE
404(1)a Reinforcing Steel, Grade 40 38,134.81 kgs 2,844,555.74 74.59 1.00
404(1)b Reinforcing Steel, Grade 60 1.00 L.S 1,604,484.45 1,604,484.45 1.00
405(1)b3 Stuctural Concrete, Class "A" 1.00 L.S 1,604,484.45 1,604,484.45 1.00
508(1) Hand Laid Rock Embankment 1.00 L.S 544,525.35 544,525.35 1.00
Part F: MISCELLANEOUS STRUCTURE
715(1) Geotextile 1.00 L.S 1,205,403.56 1,205,403.56 1.00
Part G: BANK AND SLOPE PROTECTION WORKS
1716(6) Hot Water Lines 1.00 L.S 27,492.51 27,492.51 1.00
1716(12) Cistern Tank 1.00 L.S 431,694.10 431,694.10 1.00
1716(16) Ceiling (Marine Plywood) 894.63 sq.m 854,520.26 955.17 1.00
1710(2)a Hardware (Hinges, Door Knob) 133.00 set 43,177.68 324.64 1.00
Part H: FLOOD CONTROL AND DRAINAGE 450,871.18
1701(1) Unsuitable Excavation 1.00 L.S 95,109.54 95,109.54 1.00
1704(2)a Embankment (Selected Borrow) 1.00 L.S 203,922.67 203,922.67 1.00