You are on page 1of 2

Grecom Paint Applicators Services

Project: Warehouse
Location: Rizal Technopark, Highway 2000
Taytay, Rizal

BILL OF QUANTITIES

Labor Only
Scope of Work Qty. unit Unit Rate Amount

Preliminaries

Mobilization/Demobilization 1.00 lot 180,000.00 180,000.00


Bonds and Insurances 1.00 lot 25,000.00 25,000.00
Management of the Works 1.00 lot 576,000.00 576,000.00
Safety and Security 1.00 lot 252,000.00 252,000.00
Temporary Facilities 1.00 lot 75,000.00 75,000.00

Siteworks/Civil Works

Clearing/Grubbing 2065.00 m2 55.11 113,795.01


Excavation/Backfilling & Compaction 433.25 m3 132.26 57,299.78
Lay-out 1575.00 m2 71.64 112,830.64
Gravel Bedding 100.00 m3 110.21 11,021.31

Structural Works

Concrete Works 425.10 m3 132.26 56,221.58


Rebar Works 42088.48 kg 24.17 1,017,259.02
Formworks 1186.37 m2 165.32 196,129.91

Architectural Works

Wall Plastering 2667.07 m2 192.87 514,404.73


External Waterproofing 1333.53 m2 16.53 22,045.92
Floor Finish 1575.00 m2 104.70 164,906.32
CHB Walls 1254.61 m2 275.53 345,687.18
Painting 2113.00 m2 60.62 128,084.13
Tiling Works 42.00 m2 220.43 9,257.90
Ceiling Works 42.00 m2 165.32 6,943.42

Plumbing Works

Plumbing Fixtures 1.00 lot 22,869.21 22,869.21


Storm Drainage System 1.00 lot 78,141.07 78,141.07
Sewer System 1.00 lot 18,570.90 18,570.90
Potable Water System 1.00 lot 16,531.96 16,531.96

Grand Total 4,000,000.00

Prepared by: Approved by:


Alvin C. Estay Gemma C. Venus
Quantity Surveyor Manager

You might also like