You are on page 1of 1

COST ESTIMATION AND SCOPE OF WORK

CONSTRUCTION PROJECT PROPOSED MEDIUM-RISE COMMERCIAL AND OFFICE BUILDING PROJECT


NAME OF BUILDING DOCS Commercial Building
CONSTRUCTION TEAM PHD Construction and Engineering Services (Group 4_4CEA)

COST ESTIMATE
ECCR
CONSIDERATIONS QUANTITY UNIT

LOT AREA 2000 SQM


BUILDING FOOTPRINT 950 SQM
FLOOR AREA/ LEVEL
Basement 950 SQM
Podium 950 SQM
Tower 830 SQM
NO. OF LEVEL
Basement 2 FLOOR
Podium 3 FLOORS
Tower 2 FLOORS
Rooftop 1 FLOOR
TOTAL FLOOR AREA 7240 SQM

COST SQM ₱ 50,000 PESOS

TOTAL ESTIMATED COST ₱ 362,000,000.00 PESOS

SCOPE OF WORKS
COST(total cost x
percentage
MAJOR WORKS PERCENTAGE %

Earthworks 1.03 ₱ 3,728,600.00


Formworks 2.05 ₱ 7,421,000.00
Structural 32 ₱ 115,840,000.00
Masonry 9.5 ₱ 34,390,000.00
Electrical 4.7 ₱ 17,014,000.00
Mechanical 2.6 ₱ 9,412,000.00
Plumbing 7 ₱ 25,340,000.00
Roof 12 ₱ 43,440,000.00
Ceiling 7.1 ₱ 25,702,000.00
Floor Finishes 6.72 ₱ 24,326,400.00
Wall Finishes 4.3 ₱ 15,566,000.00
Doors and Windows 5.4 ₱ 19,548,000.00
Painting 5.6 ₱ 20,272,000.00

TOTAL 100 ₱ 362,000,000.00