Description Unit Qty Rate Amount

Mortar Ratio 1:3 and 15mm thk Plastering on


Concrete Surface
Details of cost of Brick work for - 10 Sqm
Materials
Cement Bags 1.63 350 571
Sand Cum 0.17 1500 261
Manpower
Supervisor Day 0.05 800 40
Mason Day 1.0 700 700
Male Mazdoor Day 1 600 720
Waterman Day 0.1 450 45
Sub total 2337
Tools & Tackles 1% 23
Power Consumption 2.5% 58
Add for Sundries & Contingencies 3% 70
Add for Over head & Contractor profit 10% 234
Total 2722
Price per Sqm 272