You are on page 1of 35

BSR 562 MEASUREMENT

AND ESTIMATING II

By DR NOREHAN HAJI MOHD NOOR


TOPIC 4: Analysis of Prices
 Finishes;
 Demolition and alteration works
including underpinning, temporary
works, repair and maintenance
works.
i) ELEMENTS TO BE BUILD UP RATES:-
 FLOOR & WALL

ii) TYPE OF FINISHES:-


 Tiling works
 Cement Rendering / Cement-sand – to floor
 Cement Plastering – to wall
 Skirting
 Painting
what is the function of
FINISHES????
FINISHES @ Kemasan PADA BANGUNAN –

bertujuan untuk mencantikkan bangunan dan


juga untuk keselesaan penghuninya.
Kemasan bangunan termasuklah kemasan
luaran dan dalaman bangunan – Internal &
External Finishes .
Ianya terdiri daripada kemasan seperti siling,
kemasan dinding dan kemasan lantai.
Terkandung dalam section F, SMM2.
CERAMIC
NON-SLIPPERY CERAMIC - FLOOR
• Granolithic flooring / paving
is usually consists of mix of
cement, sand and hard
aggregate, can be polished
to a smooth finish and
sealed with a durable
surface coat.

• Sometimes, top surface. It


comprises hard aggregates,
cement and sand which are
blended with water and
sometimes POLYMERS to
make a workable mix.

Granite chippings
ESTIMATING : UNIT PRICES OF FINISHES
Types and Method of Finishes

Types of Finishes Types of Screed


1.0 Cement & Sand Rendering
@ Paving To Floor slab
2.0 Cement & Sand Plastering To Wall - By hand
3.0 Tiling Work - 2 types of (i) CEMENT SCREED - By Machinery
Screed (ii) CEMENT PASTE
4.0 PAINTING WORKS
EXAMPLE 1: FLOOR - CEMENT RENDERING
25 mm thick cement and sand (1:3), paving with steel trowelled finish to floor
level or to falls n.e. 15° from horizontal on concrete base. - m2

Data:
Material prices (including delivery to site)
Cement RM 10.40 / Bag
Sand RM 26.00 / m3
Labour rates
Pavior RM 58.00 / day
Unskilled worker RM 40.00 / day
Labour Output
Scope of work
Unskilled worker/m2 Pavior/M2
Mixing mortar / screed 2.00 hours / m3
Spreading & levelling paving 0.33 Hour/m2 0.33 Hour/m2
Profit 16%
ANSWER - 2 stages of calculation
Total
(I) Stage 1: CARI 'MORTAR COST' for 1 m³ (C&S (1:3)
a) Material Cost
Cement & sand mortar (1:3) RM
1 m³
m3 cement
cement x 28 bag x RM 10.40 = 291.20
3 m³ sand x RM 26.00 = 78.00
4 m³ 369.20
Add: 33.33 % Waste & shrinkage & consolidation
33.33% x RM 369.20 = 123.05
So, Cost of 4 m³ = 492.25
= RM 492.25
4
:. Cost for 1 m³ material = 123.06
b) Labour cost
Mixing mortar for 1 m3
Unskilled labour 2.00 hrs x RM 40.00
m³ 8 = 10.00
Mortar Cost / m3 = 133.06

(II) Stage 2: CARI Kos Untuk 'FLOOR RENDERING' Per m²


a) Material Cost
For 25mm thk mortar @ 0.025 m
So, = 0.025 m x RM 133.06 = 3.33
m3
b) Labour cost
Spreading & levelling paving
Renderer = 0.33 hr x RM 58.00 = 2.39
8
Unskilled Labour = 0.33 hr x RM 40.00 = 1.65
8
= 7.37
c) ADD: Profit = 16% x RM 7.37 = 1.18

Cost of floor rendering per m2 = 8.55


EXAMPLE 2: MORTAR COST MIXED BY MACHINERY @ CONCRETE MIXER

25 mm thick cement and sand (1:3), screeded bed to floor level or to falls n.e.
15° from horizontal on concrete base. - m2

Data:
1.0 Rental cost of concrete mixer 5 / 3 1/2 m3 = RM 330.00 / month
(Including transportation)
2.0 The average of working days of the machine is 24 days / month
3.0 Operator cost RM 50.00 / day
4.0 General worker RM 40.00 / day
5.0 Diesel RM 1.60 / liter - needs 1.10 liter / day
6.0 Oil & grease RM 22.00 / liter - needs 0.06 liter / day
7.0 Output of Machinery = 1.25 m3 / hr
Materials Prices :-
8.0 Cement 10.40 / Bag
9.0 Sand 26.00 / m3
Subtotal TOTAL
CEMENT MORTAR (1:3): (RM) (RM)

a) Material Cost
1 m³ cement x 28 bag x RM 10.40 291.2
3 m³ sand x RM 26.00 78.00
4 m³ 369.20
Add: 33.33 % Waste
33.33% x RM 369.20 123.05
So, Cost of 4 m³ 492.25
= RM 492.25
4
:. Cost for 1 m³ MORTAR 123.06
b) Machinery Cost
- Rental cost of concrete mixer / month = RM 330.00
@24days 24 13.75
- Operation cost / day
1 Operator 50.00
1 General worker 40.00
- Diesel for 1 day = 1.10 liter x 8 hours x RM 1.60 14.08
- Oil & grease = 0.06 liter x 8 hours x RM 22.00 10.56
Cost / day 128.39
so, Cost / hour (1 day = 9 hours) 128.39
8 16.05
Output of Concrete Mixer = 1.25 m3 / hr
Cost of Mixing / m3 = = RM 16.05 12.84
1.25
Cost Mortar / m3 135.90
c) ADD: Profit = 16% x RM 135.90 = 21.74
Cost of floor rendering per m2 = 157.65
EXAMPLE 3: FLOOR TILES WITH CEMENT PASTE

300mm x 300mm x 7mm thick Homogeneous tile bedded, jointed and pointed in
cement paste to floor level or to falls n.e. 15 on screeded bed. – m²

Data:
Material prices (including delivery to site)
Cement RM 14.00 / Bag
Homogeneous tiles RM 2.40 / pcs
Labour rates
Tiler RM 58.00 / day
Unskilled worker RM 40.00 / day
Scope of work Labour Output
Tiler Unskilled worker
Mixing cement paste 1.30 hours / m3
Levelling & fixing tile 1.45 hrs/ m2 1.20 hrs / m2
Profit 13%
ANSWER - 2 stages of calculation
Subtotal TOTAL
(I) Stage 1: Cari 'COST OF CEMENT PASTE' for 1 m³ (RM) (RM)

a) Material Cost
Cement paste = 28 bag x RM 14.00 392.00
ADD: 5 % Wastage = 5% x RM 392.00 19.60

b) Labour cost
Mixing cement paste
Unskilled Labour = 1.30 hrs x RM 40.00 6.50
m³ 8
Cost of Cement Paste / m³ 418.10

(II) Stage 2: CARI Kos Untuk 'FLOOR TILES' Per m²

a) Material Cost - for Homogeneous


- Pertama, mesti kira dahulu berapa keping Tiles untuk 1 m2 ??
Method to calculate the maximum numbers of tile pieces
Lets say 300mm x 300mm x 7mm thick Homogeneous tile

Length - 1m / 1000 mm
300 300 300
300

300
Width
1m / 1000mm
300

For Example - size tile is 300 length x 300 mm width


so, Length = 1000 mm
300 mm
= 3.33 pieces
Width = 1000 mm
300 mm
= 3.33 pieces
Bilangan maksima tiles untuk 1m2 lantai:
Luas = L x W
= 3.33 x 3.33
11.1 pieces
(II) Stage 2: CARI Kos Untuk 'FLOOR TILES' Per m²

a) Material Cost - for Homogeneous


- Pertama, mesti kira dahulu berapa keping Tiles untuk 1 m2 ??

Homogeneous tiles 11 pcs x RM 2.40 26.40


ADD: 5 % Wastage 5% X RM 26.40 1.32
Cement paste (20 mm thick) 0.02 m x RM 418.10 8.36

b) Labour cost
Tiler - Levelling & fixing tile 1.45 hrs x RM 58.00 10.51
m³ 8
Unskilled Labour 1.20 hrs x RM 40.00 6.00
m³ 8
52.59 52.59
c) Add: Profit 13% x RM 52.59 6.84
Cost of tiles per m2 59.43
1st: Calculate the total pieces of Wall tile per m2
Size : 250 mm x 200 mm white glazed wall tile
Length - 1m @ 1000 mm = 4 pieces
250 mm

250 250 250 250

200 1 2 3 4

200 2
Width - 1 m @ 1000 mm
200 mm
200 3

= 5 pieces
200 4

200 5

so, Length = 1000 mm


250 mm
= 4.0 pieces

Width = 1000 mm
200 mm
= 5.0 pieces

Bilangan maksima tiles untuk 1m2 lantai:


Luas = L x W
= 4x5
= 20.0 pieces
ANSW ER - 2 stages of calculation
Subtotal TOTAL
(I) Stage 1: COST OF CEMENT PASTE' for 1 m³ (RM) (RM)

a) Material Cost
Cement paste = 28 bag x RM 14.00 392.00
ADD: 5 % Wastage = 5% x RM 392.00 19.60

b) Labour cost
Mixing cement paste
Unskilled Labour = 1.45 hrs x RM 43.00 7.79
m³ 8
Cost of Cement Paste / m³ 419.39

(II) Stage 2: WALL TILES COST' Per m²

a) Material Cost

Wall tile - pcs / m2 20 pcs x RM 1.80 36.00


ADD: 5 % Wastage 5% X RM 36.00 1.80

Cement paste (20 mm thick) 0.02 m x RM 419.39 8.39 46.19

b) Labour cost

Tiler - Levelling & fixing tile 1.15 hrs x RM 58.00 8.34


m³ 8

Unskilled Labour 1.15 hrs x RM 40.00 5.75 14.09


m³ 8

Total material + Labour 60.28

c) Add: Profit 18% x RM 60.28 10.85

Cost of tiles per m2 71.12


EXAMPLE 5: FLOOR TILES WITH CEMENT SCREED

300mm x 300mm x 7mm thick Homogeneous tile bedded, jointed and pointed
in 13 mm thick cement screed (1:4) to floor level or to falls n.e. 15 on
screeded bed. – m²

Data:
Material prices (including delivery to site)
Cement RM 11.50 / Bag
Sand RM 33.00 / m3
Homogeneous tiles RM 2.40 / pcs

Labour rates

Tiler RM 70.00 / day


Unskilled worker RM 50.00 / day
Labour Output
Scope of work
Unskilled worker Tiler
Mixing mortar / screed 2.00 hrs / m3
Levelling & fixing tile 1.20 hrs/ m2 1.45 hrs/ m2

Profit 25%
ANSW ER - 2 stages of calculation
Subtotal TOTAL
(I) Stage 1: COST OF MORTAR CEMENT SCREED (1:4)' for 1 m³ (RM) (RM)

a) Material Cost
Cement & sand mortar (1:4)
1 m3 cement = 28 bag x RM 11.50 322.00
4 m3 sand x RM 33.00 132.00
5 m3 454.00
Add : 33.33 % waste = 33.33% x RM 454.00 151.32
So, Cost of 5 m3 605.32
= RM 605.32
:. Cost of 1 m3 material 5 121.06

b) Labour cost
Mixing mortar per 1 m3
Unskilled labour 2.00 hr /m³ x RM 50.00 12.50
8

Mortar Cost / m3 133.56

(II) Stage 2: TILES COST per m²


a) Material Cost

Homogeneous - 300 x 300 mm = 11 pcs x RM 2.40 26.40


ADD: 5 % Wastage 5% x RM 26.40 1.32

Cement screed (13 mm thick) = 0.013 m x RM 133.56 1.74 29.46

b) Labour cost
Tiler - Levelling & fixing tile 1.45 hrs x RM 70.00 12.69
m³ 8

Unskilled Labour 1.20 hrs x RM 50.00 7.50


m³ 8 20.19

49.64
c) Add: Profit 25% x RM 49.64 12.41
Cost of tiles per m2 62.05
EXAMPLE 6
30 mm thick cement and sand (1:2) skirting 350 mm high with rounded top
edge and cove bottom to wall on brickwork base – m
Data:
Material prices (including delivery to site)
Cement RM 18.50 / Bag
Sand RM 41.00 / m3
Labour rates
Pavior RM 82.00 / day
Unskilled worker RM 40.00 / day
Labour Output
Scope of work
Unskilled worker / m2 Pavior / m2
Mixing mortar / screed 2.20 hours / m3
Spreading & levelling paving 0.55 Hour / m 0.55 Hour / m
Profit 16%
Answer - 2 stages
STAGE 1 - Cost for 30 mm thick cement and sand (1:2) - unit in m2
STAGE 2 - Cost for Skirting 350 mm high - unit in m

1) Mortar Cost RM RM
Cement & sand mortar
1 m3 cement = 28 bag x RM 18.50 /bag = 518.00
2 2 m3 x RM 41.00 /m3 = 82.00
3 m3 600.00
ADD : 33.33 % shrinkage, waste & consolidation
33.3% x RM 600.00 = 199.98
So, Cost of 3 m3 = 799.98
:. Cost of 1 m3 = RM 799.98
3 = 266.66
2) Labour cost
Mixing mortar per 1 m3
Unskilled worker 2.20 hr x RM 40.00 = 11.00
m3 8 hr
Mortar Cost / m3 = 277.66

For 30 mm thick C & S mortar for skirting = 0.030 m


So, Cost of 0.030 m x RM 277.66 = 8.33 /m2
2) Build-up For Skirting
1) Material Cost
For 350 mm HIGH skirting per m
350 m x RM 8.33
1000 m² = 2.92 /m

2) Labour cost
Pavior 0.55 hr x RM 82.00 = 5.64 /m
m 8

Unskilled worker 0.55 hr x RM 40.00 = 2.75 /m


m 8
= 11.30 /m
ADD: Profit 16% x RM 11.30 = 1.81
Cost of Skirting 350 mm high / m = 13.11 /m

You might also like