Professional Documents
Culture Documents
AND ESTIMATING II
Granite chippings
ESTIMATING : UNIT PRICES OF FINISHES
Types and Method of Finishes
Data:
Material prices (including delivery to site)
Cement RM 10.40 / Bag
Sand RM 26.00 / m3
Labour rates
Pavior RM 58.00 / day
Unskilled worker RM 40.00 / day
Labour Output
Scope of work
Unskilled worker/m2 Pavior/M2
Mixing mortar / screed 2.00 hours / m3
Spreading & levelling paving 0.33 Hour/m2 0.33 Hour/m2
Profit 16%
ANSWER - 2 stages of calculation
Total
(I) Stage 1: CARI 'MORTAR COST' for 1 m³ (C&S (1:3)
a) Material Cost
Cement & sand mortar (1:3) RM
1 m³
m3 cement
cement x 28 bag x RM 10.40 = 291.20
3 m³ sand x RM 26.00 = 78.00
4 m³ 369.20
Add: 33.33 % Waste & shrinkage & consolidation
33.33% x RM 369.20 = 123.05
So, Cost of 4 m³ = 492.25
= RM 492.25
4
:. Cost for 1 m³ material = 123.06
b) Labour cost
Mixing mortar for 1 m3
Unskilled labour 2.00 hrs x RM 40.00
m³ 8 = 10.00
Mortar Cost / m3 = 133.06
25 mm thick cement and sand (1:3), screeded bed to floor level or to falls n.e.
15° from horizontal on concrete base. - m2
Data:
1.0 Rental cost of concrete mixer 5 / 3 1/2 m3 = RM 330.00 / month
(Including transportation)
2.0 The average of working days of the machine is 24 days / month
3.0 Operator cost RM 50.00 / day
4.0 General worker RM 40.00 / day
5.0 Diesel RM 1.60 / liter - needs 1.10 liter / day
6.0 Oil & grease RM 22.00 / liter - needs 0.06 liter / day
7.0 Output of Machinery = 1.25 m3 / hr
Materials Prices :-
8.0 Cement 10.40 / Bag
9.0 Sand 26.00 / m3
Subtotal TOTAL
CEMENT MORTAR (1:3): (RM) (RM)
a) Material Cost
1 m³ cement x 28 bag x RM 10.40 291.2
3 m³ sand x RM 26.00 78.00
4 m³ 369.20
Add: 33.33 % Waste
33.33% x RM 369.20 123.05
So, Cost of 4 m³ 492.25
= RM 492.25
4
:. Cost for 1 m³ MORTAR 123.06
b) Machinery Cost
- Rental cost of concrete mixer / month = RM 330.00
@24days 24 13.75
- Operation cost / day
1 Operator 50.00
1 General worker 40.00
- Diesel for 1 day = 1.10 liter x 8 hours x RM 1.60 14.08
- Oil & grease = 0.06 liter x 8 hours x RM 22.00 10.56
Cost / day 128.39
so, Cost / hour (1 day = 9 hours) 128.39
8 16.05
Output of Concrete Mixer = 1.25 m3 / hr
Cost of Mixing / m3 = = RM 16.05 12.84
1.25
Cost Mortar / m3 135.90
c) ADD: Profit = 16% x RM 135.90 = 21.74
Cost of floor rendering per m2 = 157.65
EXAMPLE 3: FLOOR TILES WITH CEMENT PASTE
300mm x 300mm x 7mm thick Homogeneous tile bedded, jointed and pointed in
cement paste to floor level or to falls n.e. 15 on screeded bed. – m²
Data:
Material prices (including delivery to site)
Cement RM 14.00 / Bag
Homogeneous tiles RM 2.40 / pcs
Labour rates
Tiler RM 58.00 / day
Unskilled worker RM 40.00 / day
Scope of work Labour Output
Tiler Unskilled worker
Mixing cement paste 1.30 hours / m3
Levelling & fixing tile 1.45 hrs/ m2 1.20 hrs / m2
Profit 13%
ANSWER - 2 stages of calculation
Subtotal TOTAL
(I) Stage 1: Cari 'COST OF CEMENT PASTE' for 1 m³ (RM) (RM)
a) Material Cost
Cement paste = 28 bag x RM 14.00 392.00
ADD: 5 % Wastage = 5% x RM 392.00 19.60
b) Labour cost
Mixing cement paste
Unskilled Labour = 1.30 hrs x RM 40.00 6.50
m³ 8
Cost of Cement Paste / m³ 418.10
Length - 1m / 1000 mm
300 300 300
300
300
Width
1m / 1000mm
300
b) Labour cost
Tiler - Levelling & fixing tile 1.45 hrs x RM 58.00 10.51
m³ 8
Unskilled Labour 1.20 hrs x RM 40.00 6.00
m³ 8
52.59 52.59
c) Add: Profit 13% x RM 52.59 6.84
Cost of tiles per m2 59.43
1st: Calculate the total pieces of Wall tile per m2
Size : 250 mm x 200 mm white glazed wall tile
Length - 1m @ 1000 mm = 4 pieces
250 mm
200 1 2 3 4
200 2
Width - 1 m @ 1000 mm
200 mm
200 3
= 5 pieces
200 4
200 5
Width = 1000 mm
200 mm
= 5.0 pieces
a) Material Cost
Cement paste = 28 bag x RM 14.00 392.00
ADD: 5 % Wastage = 5% x RM 392.00 19.60
b) Labour cost
Mixing cement paste
Unskilled Labour = 1.45 hrs x RM 43.00 7.79
m³ 8
Cost of Cement Paste / m³ 419.39
a) Material Cost
b) Labour cost
300mm x 300mm x 7mm thick Homogeneous tile bedded, jointed and pointed
in 13 mm thick cement screed (1:4) to floor level or to falls n.e. 15 on
screeded bed. – m²
Data:
Material prices (including delivery to site)
Cement RM 11.50 / Bag
Sand RM 33.00 / m3
Homogeneous tiles RM 2.40 / pcs
Labour rates
Profit 25%
ANSW ER - 2 stages of calculation
Subtotal TOTAL
(I) Stage 1: COST OF MORTAR CEMENT SCREED (1:4)' for 1 m³ (RM) (RM)
a) Material Cost
Cement & sand mortar (1:4)
1 m3 cement = 28 bag x RM 11.50 322.00
4 m3 sand x RM 33.00 132.00
5 m3 454.00
Add : 33.33 % waste = 33.33% x RM 454.00 151.32
So, Cost of 5 m3 605.32
= RM 605.32
:. Cost of 1 m3 material 5 121.06
b) Labour cost
Mixing mortar per 1 m3
Unskilled labour 2.00 hr /m³ x RM 50.00 12.50
8
b) Labour cost
Tiler - Levelling & fixing tile 1.45 hrs x RM 70.00 12.69
m³ 8
49.64
c) Add: Profit 25% x RM 49.64 12.41
Cost of tiles per m2 62.05
EXAMPLE 6
30 mm thick cement and sand (1:2) skirting 350 mm high with rounded top
edge and cove bottom to wall on brickwork base – m
Data:
Material prices (including delivery to site)
Cement RM 18.50 / Bag
Sand RM 41.00 / m3
Labour rates
Pavior RM 82.00 / day
Unskilled worker RM 40.00 / day
Labour Output
Scope of work
Unskilled worker / m2 Pavior / m2
Mixing mortar / screed 2.20 hours / m3
Spreading & levelling paving 0.55 Hour / m 0.55 Hour / m
Profit 16%
Answer - 2 stages
STAGE 1 - Cost for 30 mm thick cement and sand (1:2) - unit in m2
STAGE 2 - Cost for Skirting 350 mm high - unit in m
1) Mortar Cost RM RM
Cement & sand mortar
1 m3 cement = 28 bag x RM 18.50 /bag = 518.00
2 2 m3 x RM 41.00 /m3 = 82.00
3 m3 600.00
ADD : 33.33 % shrinkage, waste & consolidation
33.3% x RM 600.00 = 199.98
So, Cost of 3 m3 = 799.98
:. Cost of 1 m3 = RM 799.98
3 = 266.66
2) Labour cost
Mixing mortar per 1 m3
Unskilled worker 2.20 hr x RM 40.00 = 11.00
m3 8 hr
Mortar Cost / m3 = 277.66
2) Labour cost
Pavior 0.55 hr x RM 82.00 = 5.64 /m
m 8