REINFORCED INSITU CONCRETE

Formwork
Assumption list:

10% of wastage

Struts = 0.04m3/m2

Nails = 0.35kg/m2

1 carpenter is needed to prepare and fix the formwork = 1.00 hour

1 general worker is needed to assist in preparing and fixing the formwork = 0.75 hour

1 general worker is needed to dismantle and keep the formwork = 0.75 hour

Average working hour per day = 8 hours

15% profit and overhead

Reference list:

Plywood = RM50.00/piece

Dimension of plywood = 2.44m x 1.22m

No of usage of formwork = 4 times

Timber (mixed light hardwood) = RM1271.00/m3

Cost of nails = RM4.50/kg

Wages of carpenter= RM80.00/day

Wages of general worker = RM60.00/day


Sides of pile caps vertical – m2
Calculation:
Material Cost

Plywood = RM50.00/ (2.44m x 1.22m) = RM16.80

Timber = RM1271.00 x 0.04m3/m2 = RM50.84

Cost of plywood and timber used for 4 times = RM67.64

Cost of plywood and timber used for 1 time = RM 16.91

Cost of nails = RM4.50 x 0.35kg/m2 = RM1.58

Cost of material/m2 = RM18.49

10% of wastage = RM1.85

Subtotal = RM20.34

Labour cost

1 carpenter is needed to prepare and fix the formwork = 1.00 hour x (RM80.00/8
hours) = RM10.00

1 general worker is needed to assist in preparing and fixing the formwork = 0.75 hour
x (RM60.00/8hours) = RM5.63

1 general worker is needed to dismantle and keep the formwork = 0.75 hour x
(RM60.00/8hours) = RM5.63

Total cost = RM41.60

15% profit and overhead = RM6.24

Price/m2 = RM47.84
REINFORCED INSITU CONCRETE
Formwork
Sides of column stumps vertical– m2
Calculation:

Material Cost

Plywood = RM50.00/ (2.44m x 1.22m) = RM16.80

Timber = RM1271.00 x 0.04m3/m2 = RM50.84

Cost of plywood and timber used for 4 times = RM67.64

Cost of plywood and timber used for 1 time = RM 16.91

Cost of nails = RM4.50 x 0.35kg/m2 = RM1.58

Cost of material/m2 = RM18.49

10% of wastage = RM1.85

Subtotal = RM20.34

Labour cost

1 carpenter is needed to prepare and fix the formwork = 1.00 hour x (RM80.00/8
hours) = RM10.00

1 general worker is needed to assist in preparing and fixing the formwork = 0.75 hour
x (RM60.00/8hours) = RM5.63

1 general worker is needed to dismantle and keep the formwork = 0.75 hour x
(RM60.00/8hours) = RM5.63

Total cost = RM41.60

15% profit and overhead = RM6.24

Price/m2 = RM47.84
REINFORCED INSITU CONCRETE
Formwork
Faces of lift pit walls vertical– m2
Calculation:
Material Cost

Plywood = RM50.00/ (2.44m x 1.22m) = RM16.80

Timber = RM1271.00 x 0.04m3/m2 = RM50.84

Cost of plywood and timber used for 4 times = RM67.64

Cost of plywood and timber used for 1 time = RM 16.91

Cost of nails = RM4.50 x 0.35kg/m2 = RM1.58

Cost of material/m2 = RM18.49

10% of wastage = RM1.85

Subtotal = RM20.34

Labour cost

1 carpenter is needed to prepare and fix the formwork = 1.00 hour x (RM80.00/8
hours) = RM10.00

1 general worker is needed to assist in preparing and fixing the formwork = 0.75 hour
x (RM60.00/8hours) = RM5.63

1 general worker is needed to dismantle and keep the formwork = 0.75 hour x
(RM60.00/8hours) = RM5.63

Total cost = RM41.60

15% profit and overhead = RM6.24

Price/m2 = RM47.84
REINFORCED INSITU CONCRETE
Formwork
Faces of ramp retaining wall vertical– m2
Calculation:

Material Cost

Plywood = RM50.00/ (2.44m x 1.22m) = RM16.80

Timber = RM1271.00 x 0.04m3/m2 = RM50.84

Cost of plywood and timber used for 4 times = RM67.64

Cost of plywood and timber used for 1 time = RM 16.91

Cost of nails = RM4.50 x 0.35kg/m2 = RM1.58

Cost of material/m2 = RM18.49

10% of wastage = RM1.85

Subtotal = RM20.34

Labour cost

1 carpenter is needed to prepare and fix the formwork = 1.00 hour x (RM80.00/8
hours) = RM10.00

1 general worker is needed to assist in preparing and fixing the formwork = 0.75 hour
x (RM60.00/8hours) = RM5.63

1 general worker is needed to dismantle and keep the formwork = 0.75 hour x
(RM60.00/8hours) = RM5.63

Total cost = RM41.60

15% profit and overhead = RM6.24

Price/m2 = RM47.84
REINFORCED INSITU CONCRETE
Formwork
Sides and soffits of suspended ground beam vertical– m2
Calculation:

Material Cost

Plywood = RM50.00/ (2.44m x 1.22m) = RM16.80

Timber = RM1271.00 x 0.04m3/m2 = RM50.84

Cost of plywood and timber used for 4 times = RM67.64

Cost of plywood and timber used for 1 time = RM 16.91

Cost of nails = RM4.50 x 0.35kg/m2 = RM1.58

Cost of material/m2 = RM18.49

10% of wastage = RM1.85

Subtotal = RM20.34

Labour cost

1 carpenter is needed to prepare and fix the formwork = 1.00 hour x (RM80.00/8
hours) = RM10.00

1 general worker is needed to assist in preparing and fixing the formwork = 0.75 hour
x (RM60.00/8hours) = RM5.63

1 general worker is needed to dismantle and keep the formwork = 0.75 hour x
(RM60.00/8hours) = RM5.63

Total cost = RM41.60

15% profit and overhead = RM6.24

Price/m2 = RM47.84
REINFORCED INSITU CONCRETE
Formwork
Assumption list:

10% of wastage

Struts = 0.05m3/m2

Nails = 0.35kg/m2

1 carpenter is needed to prepare and fix the formwork = 1.00 hour

1 general worker is needed to assist in preparing and fixing the formwork = 0.75 hour

1 general worker is needed to dismantle and keep the formwork = 0.75 hour

Average working hour per day = 8 hours

15% profit and overhead

Reference list:

Plywood = RM50.00/piece

Dimension of plywood = 2.44m x 1.22m

No of usage of formwork = 4 times

Timber (mixed light hardwood) = RM1271.00/m3

Cost of nails = RM4.50/kg

Wages of carpenter= RM80.00/day

Wages of general worker = RM60.00/day


Soffit of suspended ground slab strutting height not exceeding 3.50m– m2
Calculation:
Material Cost

Plywood = RM50.00/ (2.44m x 1.22m) = RM16.80

Timber = RM1271.00 x 0.05m3/m2 = RM63.55

Cost of plywood and timber used for 4 times = RM80.35

Cost of plywood and timber used for 1 time = RM20.09

Cost of nails = RM4.50 x 0.35kg/m2 = RM1.58

Cost of material/m2 = RM21.67

10% of wastage = RM2.17

Subtotal = RM23.84

Labour cost

1 carpenter is needed to prepare and fix the formwork = 1.00 hour x (RM80.00/8
hours) = RM10.00

1 general worker is needed to assist in preparing and fixing the formwork = 0.75 hour
x (RM60.00/8hours) = RM5.63

1 general worker is needed to dismantle and keep the formwork = 0.75 hour x
(RM60.00/8hours) = RM5.63

Total cost = RM45.10

15% profit and overhead = RM6.77

Price/m2 = RM51.87
REINFORCED INSITU CONCRETE
Formwork
Soffit of apron slab strutting height not exceeding 3.50m– m2
Calculation:

Material Cost

Plywood = RM50.00/ (2.44m x 1.22m) = RM16.80

Timber = RM1271.00 x 0.05m3/m2 = RM63.55

Cost of plywood and timber used for 4 times = RM80.35

Cost of plywood and timber used for 1 time = RM20.09

Cost of nails = RM4.50 x 0.35kg/m2 = RM1.58

Cost of material/m2 = RM21.67

10% of wastage = RM2.17

Subtotal = RM23.84

Labour cost

1 carpenter is needed to prepare and fix the formwork = 1.00 hour x (RM80.00/8
hours) = RM10.00

1 general worker is needed to assist in preparing and fixing the formwork = 0.75 hour
x (RM60.00/8hours) = RM5.63

1 general worker is needed to dismantle and keep the formwork = 0.75 hour x
(RM60.00/8hours) = RM5.63

Total cost = RM45.10

15% profit and overhead = RM6.77

Price/m2 = RM51.87
REINFORCED INSITU CONCRETE
Formwork
Assumption list:

10% of wastage

Nails = 0.35kg/m2

1 carpenter is needed to prepare and fix the formwork = 0.50 hour

1 general worker is needed to dismantle and keep the formwork = 0.20 hour

Average working hour per day = 8 hours

15% profit and overhead

Reference list:

Plywood = RM50.00/piece

Dimension of plywood = 2.44m x 1.22m

No of usage of formwork = 4 times

Cost of nails = RM4.50/kg

Wages of carpenter= RM80.00/day

Wages of general worker = RM60.00/day


Edges of ramp raft foundations not exceeding 250mm deep– m
Calculation:
Material Cost

Plywood = RM50.00/ 2.44m = RM20.49

Cost of plywood and timber used for 4 times = RM20.49

Cost of plywood and timber used for 1 time = RM5.12

Cost of nails = RM4.50 x 0.35kg/m2 x 2.44m= RM3.84

Cost of material/m2 = RM8.96

10% of wastage = RM0.90

Subtotal = RM9.86

Labour cost

1 carpenter is needed to prepare and fix the formwork = 0.50 hour x (RM80.00/8
hours) = RM5.00

1 general worker is needed to dismantle and keep the formwork = 0.20 hour x
(RM60.00/8hours) = RM1.50

Total cost = RM16.36

15% profit and overhead = RM2.45

Price/m2 = RM18.81
REINFORCED INSITU CONCRETE
Formwork
Edges of suspended ramp slabs not exceeding 250mm deep– m
Calculation:
Material Cost

Plywood = RM50.00/ 2.44m = RM20.49

Cost of plywood and timber used for 4 times = RM20.49

Cost of plywood and timber used for 1 time = RM5.12

Cost of nails = RM4.50 x 0.35kg/m2 x 2.44m= RM3.84

Cost of material/m2 = RM8.96

10% of wastage = RM0.90

Subtotal = RM9.86

Labour cost

1 carpenter is needed to prepare and fix the formwork = 0.50 hour x (RM80.00/8
hours) = RM5.00

1 general worker is needed to dismantle and keep the formwork = 0.20 hour x
(RM60.00/8hours) = RM1.50

Total cost = RM16.36

15% profit and overhead = RM2.45

Price/m2 = RM18.81
REINFORCED INSITU CONCRETE
Formwork
Edges of suspended ground slab not exceeding 250mm deep– m
Calculation:
Material Cost

Plywood = RM50.00/ 2.44m = RM20.49

Cost of plywood and timber used for 4 times = RM20.49

Cost of plywood and timber used for 1 time = RM5.12

Cost of nails = RM4.50 x 0.35kg/m2 x 2.44m= RM3.84

Cost of material/m2 = RM8.96

10% of wastage = RM0.90

Subtotal = RM9.86

Labour cost

1 carpenter is needed to prepare and fix the formwork = 0.50 hour x (RM80.00/8
hours) = RM5.00

1 general worker is needed to dismantle and keep the formwork = 0.20 hour x
(RM60.00/8hours) = RM1.50

Total cost = RM16.36

15% profit and overhead = RM2.45

Price/m2 = RM18.81
REINFORCED INSITU CONCRETE
Formwork
Edges of drop not exceeding 250mm deep – m
Calculation:
Material Cost

Plywood = RM50.00/ 2.44m = RM20.49

Cost of plywood and timber used for 4 times = RM20.49

Cost of plywood and timber used for 1 time = RM5.12

Cost of nails = RM4.50 x 0.35kg/m2 x 2.44m= RM3.84

Cost of material/m2 = RM8.96

10% of wastage = RM0.90

Subtotal = RM9.86

Labour cost

1 carpenter is needed to prepare and fix the formwork = 0.50 hour x (RM80.00/8
hours) = RM5.00

1 general worker is needed to dismantle and keep the formwork = 0.20 hour x
(RM60.00/8hours) = RM1.50

Total cost = RM16.36

15% profit and overhead = RM2.45

Price/m2 = RM18.81
REINFORCED INSITU CONCRETE
Formwork
Edges of apron slabs not exceeding 250mm deep– m
Calculation:
Material Cost

Plywood = RM50.00/ 2.44m = RM20.49

Cost of plywood and timber used for 4 times = RM20.49

Cost of plywood and timber used for 1 time = RM5.12

Cost of nails = RM4.50 x 0.35kg/m2 x 2.44m= RM3.84

Cost of material/m2 = RM8.96

10% of wastage = RM0.90

Subtotal = RM9.86

Labour cost

1 carpenter is needed to prepare and fix the formwork = 0.50 hour x (RM80.00/8
hours) = RM5.00

1 general worker is needed to dismantle and keep the formwork = 0.20 hour x
(RM60.00/8hours) = RM1.50

Total cost = RM16.36

15% profit and overhead = RM2.45

Price/m2 = RM18.81