You are on page 1of 4

EARTHWORKS

Excavation

Assumptions:
Hiring cost of excavator = RM 600.00 per day
Wage of an excavator operator = RM 130.00 per day
Wage of a banksman (direct the excavator) = RM 65.00 per day
Cost of diesel = RM 2.00 per litre
Cost of oil and grease = RM 3.00 per hour
Diesel consumption = 10 litres per hour
Output of excavator production = 10m per hour
Cost of dump truck (including operator) = RM 500.00 per day
Number of dumper to cart away = 5 dump trucks
Output of dumper truck production = 3 min per m
Working hours = 8 hours per day
Profit and overhead = 15%

RM RM/m
Excavation Cost
a) Hiring cost = (RM 600.00/8hours) = 75.00
b) Wage of an excavator = (RM 130.00/8hours) = 16.25
c) Wage of a banksman = (RM 65.00/8hours) = 8.13
d) Diesel = (RM 2.00 per litre x 10 litres per hour) = 20.00
e) Oil and grease = 3.00
Total cost of excavation per hour = 122.38
Excavation cost per m = (RM122.38/10m) = 12.24

Removing Cost
a) Cost of dumper per hour = 5 x (RM 500.00/8hrs) = 312.50
Cost of dumper per m = (3min/60min) x RM312.50/hr = 15.63

Total cost of oversite excavation per m = 27.86


15% OHP = 4.18
Total unit rate (RM) per m = 32.04

1
EARTHWORKS
Hardcore

Assumptions:
Cost of hardcore (inclusive delivery to site) = RM 35.00 per m
Hiring charge of vibrate compactor (inclusive fuel) = RM 80.00 per day
Wage of an operator = RM 75.00 per day
Wage of a general worker = RM 65.00 per day
Vibrate compactor output = 15m per hour
General labour output = 0.15 hour per m
Working hours = 8 hours per day
Consolidation due to compaction and wastage = 25%
Profit and overhead = 15%

RM RM/m
Material Cost
a) Cost of hardcore = (100mm/1000mm) x RM35/m = 3.50
b) Add 25% consolidation = 25% x RM 3.50 = 0.88
Total material cost per m 4.38

Labour Cost
a) Wage of general worker =
= (RM65.00/8hrs) x 0.10 hour per m 1.25

Plant Cost
a) Hiring cost of compactor = RM80.00/8hrs = 10.00
b) Wage of an operator = RM75.00/8hrs = 9.38
Total plant cost for 15m per hour = 19.38
Cost of plant per m = RM19.38/15m = 1.29

Total cost of 100mm thick hardcore per m = 6.92


15% OHP = 1.04
Total unit rate (RM) per m = 7.95

2
EARTHWORKS
Polythene Sheet

Assumptions:
Cost of 12' x 180' x 125mm Thick polythene sheet = RM 90.00 per roll
Number of general labour = 2
Wage of general labour = RM 65.00 per day
Output of laying polythene sheet = 0.08 hour per m
Working hours = 8 hours per day
Allowance for wastage and laps = 5%
Profit and overhead = 15%

RM RM/m
Material Cost
a) Cost of polythene sheet = RM 90/( 3.66m x 54.86m ) = 0.45
b) Allowance for laps = 5% x RM0.45 = 0.02
Cost of material per m = 0.47

Labour cost
a) Wage of general labour
= 2 x (RM65.00/8hrs) x 0.08 hours per m = 1.30

Total cost per m = 1.77


OHP, 15% = 0.27
Total unit rate (RM) per m = 2.04

3
EARTHWORKS
Anti-Termite

Assumptions:
Cost of Anti - Termite = RM 6.50 per m
Number of general labour = 2
Wage of general labour = RM 65.00 per day
Output of anti-termite treatment = 0.04 hour per m each labour
Working hours = 8 hours per day
Profit and overhead = 15%

RM RM/m
Material Cost
a) Cost of anti-termite = 6.50
Cost of material per m = 6.50

Labour cost
a) Wage of general labour
= 2 x (RM65.00/8hrs) x 0.04 hours per m = 0.65

Total cost per m = 7.15


OHP, 15% = 1.07
Total unit rate (RM) per m = 8.22

You might also like