MEASUREMENT OF CONSTRUCTION WORKS III

(COST ANALYSIS)

FORMWORK
DESCRIPTION :

UNIT :

TYPE :

TIMBER FORMWORK

Formwork to horizontal soffit of slab

DATA
Material
12 mm thk Plywood (2.40 x 1.20)
Timber (1.42m/tonne)
Nail (0.35kg/m)

=
=
=

RM37.00 /m
RM900.00 /tonne
RM4.50 /kg

Labour
Carpenter
General labour

=
=

RM90.00 /day
RM55.00 /day

CALCULATION

RM

RM

RM

A. MATERIAL COST
i) 12 mm thk Plywood

RM 37.00/m2
(2.40 m x 1.20 m)

RM12.85 /m

ii) Timber
Quantity of timber (strut & support)
Cost of timber/m

Cost of timber/m

= 0.06 m/m
=

RM900 /tonne
1.42 m / tonne

RM633.80 /m

= RM633.80 /m x 0.06 m/m

Cost of plywood and timber for 6 times

RM38.03 /m

RM50.88 /m

Cost of plywood and timber for 1 times :


=
iii) Nails

RM 50.88 /m
6 times

RM8.48 /m

= 0.35 kg/m x RM 4.50 kg

RM1.58 /m
RM10.05 /m

Add :
10% Wastage

RM1.01

Therefore, Material cost

RM11.06 /m

B. LABOUR COST
i) Labour cost for erecting
1 Carpenter x

1 general labour x

RM 90.00
8 hrs

1.00 hr
m

RM11.25 /m

RM 55.00
8 hrs

0.75 hr
m

RM5.16 /m

0.75 hr
m

RM5.16 /m

ii) Labour cost for distmantling


1 general labour x
Therefore, Labour Cost

notes QSD231/syhidi/2011

RM 55.00
8 hrs

RM21.56 /m

formwork/page1

MEASUREMENT OF CONSTRUCTION WORKS III


(COST ANALYSIS)

C. TOTAL COST
Cost for material & labour

RM32.62 /m

Add :
15% Profit & Overhead

RM4.89

RATE FORMWORK

notes QSD231/syhidi/2011

RM37.52 /m

formwork/page2