(COST ANALYSIS)
FORMWORK
DESCRIPTION :
UNIT :
TYPE :
TIMBER FORMWORK
DATA
Material
12 mm thk Plywood (2.40 x 1.20)
Timber (1.42m/tonne)
Nail (0.35kg/m)
=
=
=
RM37.00 /m
RM900.00 /tonne
RM4.50 /kg
Labour
Carpenter
General labour
=
=
RM90.00 /day
RM55.00 /day
CALCULATION
RM
RM
RM
A. MATERIAL COST
i) 12 mm thk Plywood
RM 37.00/m2
(2.40 m x 1.20 m)
RM12.85 /m
ii) Timber
Quantity of timber (strut & support)
Cost of timber/m
Cost of timber/m
= 0.06 m/m
=
RM900 /tonne
1.42 m / tonne
RM633.80 /m
RM38.03 /m
RM50.88 /m
RM 50.88 /m
6 times
RM8.48 /m
RM1.58 /m
RM10.05 /m
Add :
10% Wastage
RM1.01
RM11.06 /m
B. LABOUR COST
i) Labour cost for erecting
1 Carpenter x
1 general labour x
RM 90.00
8 hrs
1.00 hr
m
RM11.25 /m
RM 55.00
8 hrs
0.75 hr
m
RM5.16 /m
0.75 hr
m
RM5.16 /m
notes QSD231/syhidi/2011
RM 55.00
8 hrs
RM21.56 /m
formwork/page1
C. TOTAL COST
Cost for material & labour
RM32.62 /m
Add :
15% Profit & Overhead
RM4.89
RATE FORMWORK
notes QSD231/syhidi/2011
RM37.52 /m
formwork/page2