You are on page 1of 6

ROAD & HARDSTANDING

Filling crusher run base course, 150mm thick, compacted in layers of 75mm thick
maximum [RM/M2]

Price Data (Delivered to site)

Material

Crusher run. – RM65/m3 [100mm thick = 0.128m3/m2]

Plant & Equipment

Vibratory road roller (hired) – RM300/day

Back pusher (hired) – RM200/day

Labour

General labourer – RM50/day

Machine output

Levelling 75mm thick crusher run = 120m2/hr/layer

Rolling 75mm thick crusher run = 56m2/hr/layer

Labour output

Directing unloading of crusher run on site - 0.10hr/m2

Overheads – 8%,

Profit – 2%
[Take area of road 1.00m2]

A. Material

150mm thick crusher run

| 150mm | x 0.128m3 @RM65.00/m3 RM12.48


| 100mm |

B. Plant & Equipments

i. Levelling 2 layers of crusher run,


75mm thick maximum

2x| 1m2 | @RM200.00/day RM 0.42


|120m2/hr/layer|

ii. Compacting 2 layers of crusher run,


75mm thick maximum

2x| 1m2 | @RM300.00/day RM 1.34 RM1.76


| 56m2/hr/layer| RM14.24

C. Labour

Directing unloading of crusher run on site

0.10hr/m2@ RM50.00/day] RM 0.63


RM14.87

Allow for overheads – 8% RM1.19

Allow for profit – 2% RM0.30 RM 1.49

Rate per m2 for this item RM16.36


Filling premix (ACW 20) base including bituminous tack coat (measured separately),
70mm thick to be deposited and compacted in layers of 35mm maximum thick.
[RM/m2]

Price Data (Delivered to site)

Material

Premix ACW 20 wearing course – RM80/tonne

[Covering capacity for 100mm thick = 3.88tonne/m2]

Plant

Vibratory road roller (hired) – RM300/day

Mechanical paver (hired) – RM300/day

30 tonnes Pneumatic roller (hired) – RM250/day

1 tonne lorry (hired) – RM100/day

[Transportation cost for each plant to and from site is charged at RM1200/tonne of materials laid for the
project]

Labour

Foreman – RM60.00/day

General labourer – RM50/day

Machine output

Levelling 35mm thick wearing course = 80m2/hr/layer

Rolling 35mm thick wearing course = 46m2/hr/layer

Labour output

Directing unloading wearing course on site - 0.10hr/m2

Overheads – 8%,

Profit – 2%
[Quantity of wearing course for the project is assumed 3500m2]

A. Material

Premix asphalt 70mm thick

| 70mm | @ 3.88m²/tonne @ RM80.00/tonne


| 100mm | RM217.60

B. Plant & Equipments

i. Levelling 2 layers of premix using Mechanical Paver & lorry


35mm thick maximum

2x| 1m2 | @ l RM400.00/day l


2
|80m /hr/layer| l 8 hrs/day l RM1.25

ii. Compacting 2 layers of premix using Pneumatic & road roller


35mm thick maximum

2x| 1m2 | @ l RM550.00/day l RM2.99


| 46m2/hr/layer| l 8 hrs/day l

C. Transportation plant to & from site

3 nr @ RM1200/tonne RM3600
| 3500m2 | RM 2.80
|2.72m2/tonne |

D. Labour

1 nr foremen @RM60.00/day RM7.50/hr

6 nr general labourers @RM40.00/day RM30.00/hr

RM37.50/hr

i. Directing unloading of premix on site

0.10hr/m2@ RM37.50/hr RM 3.75


RM 228.39

Allow for Overheads – 8% RM 18.27


Allow for profit – 2% RM 4.57 RM 22.84

Rate per m2 for this item RM251.23


One coat of approved thermoplastics reflective road paint, including clearing surface from dirt,
grease oil laitance or other foreign matters, double continuous line not exceeding 150mm wide.
[RM/M]

Price Data (Delivered to site)

Thermoplastic road painting powder –RM 60/bag (weight per bag - 25kg)
(Consumption: 5kg/m2 - thickness: 1.8mm)

Glass beads –RM35/bag (weight per bag - 25kg)


(Rate of application - 13.6kg/m2

Propane gas (say) – RM1.00/m2

Road marking equipments incl. operator (hired) – RM100/day


(Output: 0.03hr/m2)

Labour output for preparation of road surface – 0.025hr/m2.


Wages - RM8.00/hr.

A. Material

Thermoplastic plastic road paint | 5kg/m2 |@65.00/bag RM13.00


| 25kg |

Glass beads |13.6kg/m2 | @RM35.00/bag RM19.04


| 25kg |

Propane gas (say) RM 1.00


RM33.04
Allow 2% wastage RM 0.66 RM33.70

B. Plant and Equipments

Hire road marking equipments (incl. operator)


0.03hr/m2 @ RM12.50/hr RM 0.38

C. Labour

2 general labours for preparation of surface:


0.025hr/m2@RM8.00/hr RM 0.40
RM34.48

Cost per m = | 0.30m2/m |@RM34.48 RM10.34


| 1m2 |

Overhead 10% RM1.03


Profit 2% RM0.21 RM1.24
RM11.58

You might also like