Location: Phase 2B, Block 4 Lot 7, The Glens, Park Spring Village, San Pedro, Laguna
BILL OF MATERIALS
Ground Floor Area: Total Floor Area:
Second Floor Area: Total Lot Area: 135 sq. m. Materials Labor Description Quantity Unit Remarks Unit Price Amount Unit Price Amount A.) General Requirements Clearing and grubbing 67.50 sqm. - 33.71 2,275.43 Mobilization/Demobilization 1.00 lot - 8,500.00 8,500.00 Temporary Field Office, Warehouse, etc. 1.00 lot
Utilities (Electrical & Water Consumptions) 1.00 lot by client/owner
Clearing, Hauling Out/Disposal of Debris/Material 45.00 sqm. - 74.80 3,366.00 Handling Construction Safety and Security 1.00 lot - - Soil Poisoning Staking and Building Lay-out Area 67.50 sqm. 100.00 6,750.00 92.06 6,214.05 Sub total 6,750.00 20,355.48 B.) Permits and Fees Processing Fee (Home Owner) 1.00 lot by client/owner Building Permit 1.00 lot by client/owner Barangay Permit 1.00 lot by client/owner Fire Permit 1.00 lot by client/owner Occupancy Permit 1.00 lot by client/owner Local Government Tax 1.00 lot by client/owner Meralco Connection 1.00 lot by client/owner Water Supply Connection 1.00 lot by client/owner Site Survey 1.00 lot by client/owner Sub total - - C.) Board up and Temporary Fence GI Sheet Lumber GI Wire CWN Sub total - - D.) Structure Excavation Footing 9.07 cum. 90.00 816.48 400.00 3,628.80 Wall footing 14.80 cum. 90.00 1,332.00 400.00 5,920.00 Sub total 2,148.48 9,548.80 E.) Backfilling of Excavated Materials Footing 9.07 cum. 90.00 816.48 300.00 2,721.60 Wall footing 6.66 cum. 90.00 599.40 300.00 1,998.00 Sub total 1,415.88 4,719.60 F.) Lot Leveling and Compaction Ground floor 40.00 sqm. 37.50 1,500.00 50.00 2,000.00 Sub total 1,500.00 2,000.00 G.) Reinforcing Bars Foundations : Column, Tie-beam, Wall Footing, Second Floor Beam, Roof Beam, CHB laying, Exposed Column, Canopy, Stair, Electrical Post Foundation Reinforcement 109.20 kg/s 45.50 4,968.60 17.20 1,878.24 Deformed Bar-16mm x 6m pcs - Grade 33 Deformed Bar-12mm x 6m 20.00 pcs - Grade 33 Deformed Bar-10mm x 6m pcs - Grade 33 #16 Tie wire 2.18 kg/s 90.00 196.56 Wall Footing Reinforcement 280.14 kg/s 45.50 12,746.37 17.20 4,818.41 Deformed Bar-16mm x 6m pcs - Grade 33 Deformed Bar-12mm x 6m 37.00 pcs - Grade 33 Deformed Bar-10mm x 6m 21.00 pcs - Grade 33 #16 Tie wire 5.60 kg/s 90.00 504.25 Columns Reinforcement 307.68 kg/s 45.50 13,999.44 17.20 5,292.10 Deformed Bar-16mm x 6m pcs - Grade 33 Materials Labor Description Quantity Unit Remarks Unit Price Amount Unit Price Amount Deformed Bar-12mm x 6m 40.00 pcs - Grade 33 Deformed Bar-10mm x 6m 24.00 pcs - Grade 33 #16 Tie wire 6.15 kg/s 90.00 553.82 Sub total 32,969.05 11,988.74 H.) 4" Gravel Bedding Gravel 2.20 cum. 1,300.00 2,860.00 130.00 286.00 Sub total 2,860.00 286.00 I.) Reinforced Concrete Foundation 21 Mpa (3,000 psi) Formworks sqm. 363.82 - 242.54 - Concrete Pouring (one-bagger) 2.56 cum. 1,050.00 2,688.00 Cement (40kg) 27.00 bag's 230.00 6,210.00 Sand 1.54 cum. 1,250.00 1,920.00 Gravel 2.56 cum. 1,300.00 3,328.00 Wall Footing 21 Mpa (3,000 psi) Formworks sqm. 363.82 - 242.54 - Concrete Pouring (one-bagger) 5.55 cum. 1,050.00 5,827.50 Cement (40kg) 59.00 bag's 230.00 13,570.00 Sand 3.33 cum. 1,250.00 4,162.50 Gravel 5.55 cum. 1,300.00 7,215.00 Columns 21 Mpa (3,000 psi) Formworks 23.46 sqm. 363.82 8,535.22 242.54 5,689.99 Concrete Pouring (one-bagger) 1.96 cum. 1,050.00 2,052.75 Cement (40kg) 21.00 bag's 230.00 4,830.00 Sand 1.17 cum. 1,250.00 1,466.25 Gravel 1.96 cum. 1,300.00 2,541.50 Sub total 53,778.47 16,258.24 J.) Masonry CHB Perimeter Walls 80.78 sqm. 242.55 19,593.19 4" CHB Laying including Rebars; Class B 1010.00 pcs 14.00 14,140.00 Cement (40kg) 45.00 bag's 230.00 10,350.00 Deformed Bar-10mm x 6m 92.00 pcs 134.00 12,328.00 Grade 33 #16 Tie wire 3.15 kg/s 90.00 283.54 Sand 10.10 cum. 1,250.00 12,621.88 Plastering (1/2" thick); Class B 161.56 sqm. 75.00 12,117.00 Cement (40kg) 48.47 bag's 230.00 11,147.64 Sand 6.46 cum. 1,250.00 8,078.00 Plastering to Corners 18.00 lm. 45.00 810.00 - Sub total 69,759.05 31,710.19 K.) Metal Works Gate and Fence Tubular 2"x3"x1.5mm thk-6m 4.00 pcs 1,182.00 4,728.00 Tubular 2"x2"x1.5mm thk-6m 16.00 pcs 940.00 15,040.00 Tubular 1 1/2"x1 1/2"x1.2mm thk-6m 34.00 pcs 633.00 21,522.00 Sub total 41,290.00 14,451.50 L.) Painting Works Exterior, exposed column and walls (semi gloss flat 80.78 sq. m. 225.00 18,175.50 latex fin.) Gate and Fence 10.50 sq. m. 210.00 2,205.00 Sub total 20,380.50 8,152.20 Materials Labor Description Amount Unit Price Amount Unit price Amount
TOTAL ESTIMATED PROJECT COST Php 232,851.43 Php 119,470.75 352,322.17