Professional Documents
Culture Documents
ELEMENTAL COST
ANALYSIS
2) To enable cost information to be collated and produced in a manner which can assist in the cost
controlling of future building projects. A standard set of building elements and components are a
prerequisite.
3) Cost control is achieved by preparing an estimate of construction cost based on the information
gleaned from this analysis in the very early stages of a development, especially when little or no
design information is available.
The primary purpose of an elemental cost analysis is (Cont’d)
4) The need for an elemental classification is most apparent in the economic evaluation
of building alternatives at the design stage. Cost estimates using a format based on a
detailed measurement (e.g. taking off) are time consuming, costly and inappropriate
at the early design stages.
The list of elements, however, is a compromise between this definition and what is
considered practical.
The primary purpose of an elemental cost analysis is
6) The elemental cost analysis allows for varying degrees of detail related (or a
systematic breakdown) to the design process;
broad costs for building types are needed during the initial period and
progressively more detail is required as the design is developed.
7) The elemental costs are related to square metre of gross internal floor area and
also to a parameter more closely identifiable with the elements function – the
element unit quantity (EUR).
TOOL TO PREPARE ECA
This INFORMATION are required during prepare the Elemental
Cost Analysis:-
The document below analyses the Elemental rate per unit as well as
the cost per GFSA as well as the Sub-Elemental rate per unit. The GFSA
rate as below, is one of up to 10 functional quantities that can be used
to compare the rate of an Element. To change the GFSA quantity insert
the new quantity in the Quantity column.
The Basic Principle
of Elemental Cost
Analysis Practice by
PWD/JKR:
INST IT UTION OF SURVEYORS MALAYSIA BUILDING
COST INFORMAT ION CENT RE
28 weeks
Preliminaries
Contigencies
RM
RM
177,157.15
PWD/JKR:
Numbers of Tenders Issued : 32 Contract Sum RM 3,931,663.80
FORM 1
ANALYSIS OF SINGLE BUILDING
Design/Shape Informa tion
Accomodation a nd Design Fea tures:
The rectangular shape multi-purpose hall comprising of 2 storey with hall area, VIP room, office, meeting room, audio room, toilet and changing room.
Are a s :
Functiona l unit: 612 m² De sign / Sha pe s
Lower Ground Floor 92 m² Percentage of Gross Floor Area
Ground floor 760 m²
Upper Floors 237 m² External Wall Area = 910 (a) Below Ground Floor %
Gross Floor Are a 1089 m² Gross Floor Area 1089
(b) Single-Storey
%
Usable Area 612 m² = 0.84 Construction
Circulation Area 173 m²
Ancillary Area 291 m² (c) Two-storey
100 %
Internal Division 14 m² Store y Heights: Construction
Gross Floor Are a 1089 m²
Av. Below Ground Floor 1.52 m (d) 3-storey
N/A
Floor Spaces NOT Enclosed: 199 m² Construction
At Ground Floor 3.05 m
Roof Area : 1172 m² (e) 20-storey
N/A
(Structural and Plant Rooms) Above Ground Floor 3.96 m Construction
(average)
Brie f Cost
Contract sum RM 1,997,464.55 Functional Unit Costs :
excluding external works RM 2,508.64 per m2
Provisional Sums RM 350,000.00
2 Superstructure
2A Frame 88,793.60 81.54 1,089 m² 81.54 1.00 121.00 14,366.00 1,163.00
2B Upper Floor 7,754.20 7.12 237 m² 32.72 0.22 16.13 22.00 111.40
2C Roof 137,900.00 126.63 1,347 m² 102.38 1.24 4.00 32.00
2D Stairs 9,413.20 8.64 11.00 522.00 58.00
2E External W all 28,337.50 26.02 910 m² 31.14 0.84
2F W indows & External Doors 27,769.50 25.50 125 m² 222.16 0.11
2G Internal W alls & Partitions 10,690.00 9.82 391 m² 27.34 0.36
ECA:
2H Internal Doors 8,452.50 7.76 47 m² 179.84 0.04
FORM 2
3. Finishes
3A Internal W all Finishes 40,852.00 37.51 1,836 m² 22.25 0.02
3B Internal Floor Finishes 113,459.50 104.19 1,090 m² 104.14 0.10
3C Internal Ceiling Finishes 46,112.00 42.34 1,308 m² 35.25 0.03
3D External Finis hes 51,608.60 47.39
5. Services
5A Sanitary Appliances 12,090.00 11.10 83 Nos 145.66 0.08
5B Plumbing Installation 43,775.00 40.20
5C Refuse Disposal
5D Air-conditioning & Ventilation 100,089.00 91.91
System
5E Electrical Installation 384,382.50 352.97
5F Fire Protection Installation 42,038.45 38.60
5G Lift & Conveyor Installation
5H Communication Installation
5J Special Installation
5K Builder's Profit & Attendance
on Services
5L Builder's W ork in Connection
W ith Services
6. External W orks
6A Site W ork 322,342.10 296.00
6B Drainage 62,765.25 57.64
6C External Services
6D Ancillary Buildings 78,306.20 71.91
6E Recreational Facilities
1 PRELIMINARIES 177,157.15
2 BUILDING WORKS
NEW PRICE FOR THE a) ASRAMA 603,339.90
PROPOSED BUILDING b) DEWAN SERBAGUNA & PEJABAT 701,248.90