Report Date: 29-Nov-21

Unit of Scope Completed Remaining Planned Actual Progress


Activities Weight % Planned Start Planned Finish Actual Start Actual Finish Remarks
Measure Quantity Quantity Quantity Completion % Completion % Variance %
Conctruction of Buried Chemical Trenches 100.00% 3-Oct-21 30-Nov-21 22-Aug-21 11.07% 9.69% -1.38%
Chemical Trench at C001 to C002 1.64% 18-Oct-21 30-Nov-21 18-Oct-21 52.50% 65.50% 13.00%
Pre-concrete works 30.00% 18-Oct-21 14-Nov-21 18-Oct-21 14-Nov-21 100.00% 100.00% 0.00%
Excavation and dewatering 30.00% m3 63.75 63.75 0.00 18-Oct-21 20-Oct-21 18-Oct-21 20-Oct-21 100.00% 100.00% 0.00%
Backfilling and Compaction 20.00% m2 32.50 32.50 0.00 20-Oct-21 22-Oct-21 20-Oct-21 22-Oct-21 100.00% 100.00% 0.00%
Blinding or Lean concrete Pouring 20.00% m3 2.44 2.44 0.00 4-Nov-21 4-Nov-21 4-Nov-21 4-Nov-21 100.00% 100.00% 0.00%
Waterproofing works 20.00% m2 40.00 40.00 0.00 8-Nov-21 12-Nov-21 8-Nov-21 12-Nov-21 100.00% 100.00% 0.00%
Screeding concrete pouring 10.00% m3 0.69 0.69 0.00 13-Nov-21 14-Nov-21 13-Nov-21 13-N0V-21 100.00% 100.00% 0.00%
Concrete works for Raft 25.00% 15-Nov-21 30-Nov-21 15-Nov-21 90.00% 100.01% 10.01%
Steel fixing for Raft with wall kickers 40.00% tons 1305.16 1305.16 0.00 15-Nov-21 18-Nov-21 15-Nov-21 18-Nov-21 100.00% 100.00% 0.00%
Formwork installation for Raft with wall kickers 30.00% m2 15.00 15.00 0.00 19-Nov-21 21-Nov-21 19-Nov-21 21-Nov-21 100.00% 100.00% 0.00%
Inspection and concrete pouring for Raft 20.00% m3 6.88 6.88 0.00 22-N0V-21 23-Nov-21 22-N0V-21 23-Nov-21 100.00% 100.07% 0.07%
Curing and deshuttering for Raft 10.00% m2 15.00 15.00 0.00 30-Nov-21 30-Nov-21 30-Nov-21 30-Nov-21 0.00% 100.00% 100.00%
Concrete works for Walls 35.00% 0.00% 30.00% 30.00%
Chipping and Steel fixing for Walls 30.00% tons 1363.91 1363.91 0.00 0.00% 100.00% 100.00%
Formwork installation for Walls 40.00% m2 97.50 97.50 0.00% 0.00% 0.00%
Inspection and concrete pouring for Walls 20.00% m3 10.63 10.63 0.00% 0.00% 0.00%
Curing and deshuttering for Walls 10.00% m2 97.50 97.50 0.00% 0.00% 0.00%
Post-concrete works 10.00% 0.00% 0.00% 0.00%
Waterproofing works for walls 30.00% m2 55.00 55.00 0.00% 0.00% 0.00%
Backfilling and Compaction 30.00% m3 43.13 43.13 0.00% 0.00% 0.00%
Chipping and Pouring of Sloping screed 30.00% m 25.00 25.00 0.00% 0.00% 0.00%
Installation of Pre-cast / GRP Covers 10.00% m 25.00 25.00 0.00% 0.00% 0.00%
Chemical Trench at C002 to C003 1.96% 28-Oct-21 25-Nov-21 28-Oct-21 55.00% 65.50% 10.50%
Pre-concrete works 30.00% 28-Oct-21 12-Nov-21 28-Oct-21 12-Nov-21 100.00% 100.00% 0.00%
Excavation and dewatering 30.00% m3 86.70 86.70 0.00 28-Oct-21 1-Nov-21 28-Oct-21 1-Nov-21 100.00% 100.00% 0.00%
Backfilling and Compaction 20.00% m2 39.00 39.00 0.00 1-Nov-21 3-Nov-21 1-Nov-21 3-Nov-21 100.00% 100.00% 0.00%
Blinding or Lean concrete Pouring 20.00% m3 5.85 5.85 0.00 4-Nov-21 4-Nov-21 4-Nov-21 4-Nov-21 100.00% 100.00% 0.00%
Waterproofing works 20.00% m2 48.00 48.00 0.00 8-Nov-21 11-Nov-21 8-N0V-21 11-Nov-21 100.00% 100.00% 0.00%
Screeding concrete pouring 10.00% m3 1.98 1.98 0.00 12-Nov-21 12-Nov-21 12-N0V-21 12-Nov-21 100.00% 100.00% 0.00%
Concrete works for Raft 25.00% 13-Nov-21 25-Nov-21 13-Nov-21 30-Nov-21 100.00% 100.00% 0.00%
Steel fixing for Raft with wall kickers 40.00% tons 1564.44 1564.44 0.00 13-Nov-21 15-Nov-21 13-Nov-21 16-Nov-21 100.00% 100.00% 0.00%
Formwork installation for Raft with wall kickers 30.00% m2 18.00 18.00 0.00 15-Nov-21 17-Nov-21 16-Nov-21 22-Nov-21 100.00% 100.00% 0.00%
Inspection and concrete pouring for Raft 20.00% m3 8.25 8.25 0.00 18-Nov-21 19-Nov-21 3-Dec-21 4-Dec-21 100.00% 100.00% 0.00%
Curing and deshuttering for Raft 10.00% m2 18.00 18.00 0.00 20-Nov-21 25-Nov-21 5-Dec-21 11-Dec-21 100.00% 100.00% 0.00%
Concrete works for Walls 35.00% 0.00% 30.00% 30.00%
Chipping and Steel fixing for Walls 30.00% tons 1637.60 1637.60 0.00 0.00% 100.00% 100.00%
Formwork installation for Walls 40.00% m2 117.00 117.00 0.00% 0.00% 0.00%
Inspection and concrete pouring for Walls 20.00% m3 6.38 6.38 0.00% 0.00% 0.00%
Curing and deshuttering for Walls 10.00% m2 66.00 66.00 0.00% 0.00% 0.00%
Post-concrete works 10.00% 0.00% 0.00% 0.00%
Waterproofing works for walls 30.00% m2 66.00 66.00 0.00% 0.00% 0.00%
Backfilling and Compaction 30.00% m3 64.25 64.25 0.00% 0.00% 0.00%
Chipping and Pouring of Sloping screed 30.00% m 30.00 30.00 0.00% 0.00% 0.00%
Installation of Pre-cast / GRP Covers 10.00% m 30.00 30.00 0.00% 0.00% 0.00%
Chemical Trench at C003 to C004 0.65% 6-Oct-21 29-Oct-21 9-Oct-21 11-Nov-21 90.00% 65.50% -24.50%
Pre-concrete works 30.00% 6-Oct-21 14-Oct-21 9-Oct-21 11-Nov-21 100.00% 100.00% 0.00%
Excavation and dewatering 30.00% m3 28.90 28.90 0.00 6-Oct-21 7-Oct-21 9-Oct-21 9-Oct-21 100.00% 100.00% 0.00%
Backfilling and Compaction 20.00% m2 13.00 13.00 0.00 8-Oct-21 9-Oct-21 12-Oct-21 14-Oct-21 100.00% 100.00% 0.00%
Blinding or Lean concrete Pouring 20.00% m3 1.95 1.95 0.00 10-Oct-21 10-Oct-21 7-Nov-21 7-Nov-21 100.00% 100.00% 0.00%
Waterproofing works 20.00% m2 16.00 16.00 0.00 11-Oct-21 13-Oct-21 8-Nov-21 9-N0V-21 100.00% 100.00% 0.00%
Screeding concrete pouring 10.00% m3 0.66 0.66 0.00 14-Oct-21 14-Oct-21 11-N0V-21 11-Nov-21 100.00% 100.00% 0.00%
Concrete works for Raft 25.00% 15-Oct-21 22-Oct-21 12-Nov-21 30-Nov-21 100.00% 100.00% 0.00%
Steel fixing for Raft with wall kickers 40.00% tons 522.93 522.93 0.00 15-Oct-21 17-Oct-21 12-Nov-21 16-Nov-21 100.00% 100.00% 0.00%
Formwork installation for Raft with wall kickers 30.00% m2 6.00 6.00 0.00 17-Oct-21 19-Oct-21 16-Nov-21 22-Nov-21 100.00% 100.00% 0.00%
Inspection and concrete pouring for Raft 20.00% m3 2.75 2.75 0.00 20-Oct-21 20-Oct-21 3-Dec-21 4-Dec-21 100.00% 100.00% 0.00%
Curing and deshuttering for Raft 10.00% m2 6.00 6.00 0.00 21-Oct-21 22-Oct-21 5-Dec-21 11-Dec-21 100.00% 100.00% 0.00%
Concrete works for Walls 35.00% 23-Oct-21 29-Oct-21 100.00% 30.00% -70.00%
Chipping and Steel fixing for Walls 30.00% tons 546.82 546.82 0.00 23-Oct-21 25-Oct-21 100.00% 100.00% 0.00%
Formwork installation for Walls 40.00% m2 39.00 39.00 25-Oct-21 27-Oct-21 100.00% 0.00% -100.00%
Inspection and concrete pouring for Walls 20.00% m3 2.13 2.13 28-Oct-21 28-Oct-21 100.00% 0.00% -100.00%
Curing and deshuttering for Walls 10.00% m2 22.00 22.00 29-Oct-21 29-Oct-21 100.00% 0.00% -100.00%
Post-concrete works 10.00% 0.00% 0.00% 0.00%
Waterproofing works for walls 30.00% m2 22.00 22.00 0.00% 0.00% 0.00%
Backfilling and Compaction 30.00% m3 21.42 21.42 0.00% 0.00% 0.00%
Chipping and Pouring of Sloping screed 30.00% m 10.00 10.00 0.00% 0.00% 0.00%
Installation of Pre-cast / GRP Covers 10.00% m 10.00 10.00 0.00% 0.00% 0.00%
Chemical Trench at C052 to C053 1.11% 28-Oct-21 30-Nov-21 28-Oct-21 10-Nov-21 54.64% #DIV/0! #DIV/0!
Pre-concrete works 30.00% 28-Oct-21 10-Nov-21 28-Oct-21 10-Nov-21 100.00% 100.00% 0.00%
Excavation and dewatering 30.00% m3 33.40 33.40 0.00 28-Oct-21 29-Oct-21 28-Oct-21 29-Oct-21 100.00% 100.00% 0.00%
Backfilling and Compaction 20.00% m2 25.50 25.50 0.00 1-Nov-21 2-Nov-21 1-Nov-21 2-Nov-21 100.00% 100.00% 0.00%
Blinding or Lean concrete Pouring 20.00% m3 1.50 1.50 0.00 2-Nov-21 2-Nov-21 2-Nov-21 2-Nov-21 100.00% 100.00% 0.00%
Waterproofing works 20.00% m2 25.00 25.00 0.00 8-Nov-21 9-Nov-21 8-Nov-21 9-Nov-21 100.00% 100.00% 0.00%
Screeding concrete pouring 10.00% m3 0.70 0.70 0.00 10-Nov-21 10-Nov-21 10-Nov-21 10-Nov-21 100.00% 100.00% 0.00%
Concrete works for Raft 25.00% 11-Nov-21 30-Nov-21 11-Nov-21 30-Nov-21 98.57% 99.85% 1.28%
Steel fixing for Raft with wall kickers 40.00% tons 0.71 0.71 0.00 11-Nov-21 12-Nov-21 11-Nov-21 12-Nov-21 100.00% 99.58% -0.42%
Formwork installation for Raft with wall kickers 30.00% m2 15.30 15.30 0.00 11-Nov-21 17-Nov-21 11-Nov-21 17-Nov-21 100.00% 100.00% 0.00%
Inspection and concrete pouring for Raft 20.00% m3 6.68 6.68 0.00 11-Nov-21 16-Nov-21 11-Nov-21 18-Nov-21 100.00% 100.07% 0.07%
Curing and deshuttering for Raft 10.00% m2 26.70 26.70 0.00 23-Nov-21 30-Nov-21 23-Nov-21 30-Nov-21 85.71% 100.00% 14.29%
Concrete works for Walls 35.00% 0.00% 100.00% 100.00%
Chipping and Steel fixing for Walls 30.00% tons 1238.52 1238.52 0.00 0.00% 100.00% 100.00%
Formwork installation for Walls 40.00% m2 63.80 63.80 0.00 0.00% 100.00% 100.00%
Inspection and concrete pouring for Walls 20.00% m3 7.15 7.15 0.00 0.00% 100.00% 100.00%
Curing and deshuttering for Walls 10.00% m2 13.20 13.20 0.00 0.00% 100.00% 100.00%
Post-concrete works 10.00% #DIV/0! 0.00% #DIV/0! #DIV/0!
Waterproofing works for walls 30.00% m2 0.00 0.00% #DIV/0! #DIV/0!
Backfilling and Compaction 30.00% m3 0.00 0.00% #DIV/0! #DIV/0!
Chipping and Pouring of Sloping screed 30.00% m 0.00 0.00% #DIV/0! #DIV/0!
Installation of Pre-cast / GRP Covers 10.00% m 0.00 0.00% #DIV/0! #DIV/0!
Chemical Trench at C053 to C054 0.78% 28-Oct-21 17-Nov-21 28-Oct-21 #DIV/0! 54.69% #DIV/0! #DIV/0!
Pre-concrete works 30.00% 28-Oct-21 10-Nov-21 28-Oct-21 10-Nov-21 100.00% 100.00% 0.00%
Excavation and dewatering 30.00% m3 24.00 24.00 0.00 28-Oct-21 29-Oct-21 28-Oct-21 29-Oct-21 100.00% 100.00% 0.00%
Backfilling and Compaction 20.00% m2 18.00 18.00 0.00 1-Nov-21 2-Nov-21 1-Nov-21 2-Nov-21 100.00% 100.00% 0.00%
Blinding or Lean concrete Pouring 20.00% m3 1.00 1.00 0.00 2-Nov-21 2-Nov-21 2-Nov-21 2-Nov-21 100.00% 100.00% 0.00%
Waterproofing works 20.00% m2 36.00 36.00 0.00 8-Nov-21 9-Nov-21 8-Nov-21 9-Nov-21 100.00% 100.00% 0.00%
Screeding concrete pouring 10.00% m3 0.45 0.45 0.00 10-Nov-21 10-Nov-21 10-Nov-21 10-Nov-21 100.00% 100.00% 0.00%
Concrete works for Raft 25.00% 11-Nov-21 30-Nov-21 11-Nov-21 30-Nov-21 98.75% 100.00% 1.25%
Steel fixing for Raft with wall kickers 40.00% tons 0.75 0.75 0.00 11-Nov-21 12-Nov-21 11-Nov-21 12-Nov-21 100.00% 100.00% 0.00%
Formwork installation for Raft with wall kickers 30.00% m2 25.00 25.00 0.00 11-Nov-21 17-Nov-21 11-Nov-21 17-Nov-21 100.00% 100.00% 0.00%
Inspection and concrete pouring for Raft 20.00% m3 4.20 4.20 0.00 11-Nov-21 16-Nov-21 11-Nov-21 18-Nov-21 100.00% 100.00% 0.00%
Curing and deshuttering for Raft 10.00% m2 35.00 35.00 0.00 22-Nov-21 30-Nov-21 22-Nov-21 30-Nov-21 87.50% 100.00% 12.50%
Concrete works for Walls 35.00% 0.00% 100.00% 100.00%
Chipping and Steel fixing for Walls 30.00% tons 1363.91 1363.91 0.00 0.00% 100.00% 100.00%
Formwork installation for Walls 40.00% m2 72.50 72.50 0.00 0.00% 100.00% 100.00%
Inspection and concrete pouring for Walls 20.00% m3 7.50 7.50 0.00 0.00% 100.00% 100.00%
Curing and deshuttering for Walls 10.00% m2 42.50 42.50 0.00 0.00% 100.00% 100.00%
Post-concrete works 10.00% #DIV/0! 0.00% #DIV/0! #DIV/0!
Waterproofing works for walls 30.00% m2 0.00 0.00% #DIV/0! #DIV/0!
Backfilling and Compaction 30.00% m3 0.00 0.00% #DIV/0! #DIV/0!
Chipping and Pouring of Sloping screed 30.00% m 0.00 0.00% #DIV/0! #DIV/0!
Installation of Pre-cast / GRP Covers 10.00% m 0.00 0.00% #DIV/0! #DIV/0!
Chemical Trench at C004 to C005 1.64% 8-Oct-21 27-Nov-21 8-Oct-21 47.50% 65.51% 18.01%
Pre-concrete works 30.00% 8-Oct-21 18-Nov-21 8-Oct-21 100.00% 100.04% 0.04%
Excavation and dewatering 30.00% m3 61.63 61.63 0.00 8-Oct-21 9-Oct-21 8-Oct-21 9-Oct-21 100.00% 100.00% 0.00%
Backfilling and Compaction 20.00% m2 32.50 32.50 0.00 10-Oct-21 12-Oct-21 10-Oct-21 12-Oct-21 100.00% 100.00% 0.00%
Blinding or Lean concrete Pouring 20.00% m3 2.44 2.44 0.00 8-Nov-21 8-Nov-21 8-Nov-21 8-Nov-21 100.00% 100.00% 0.00%
Waterproofing works 20.00% m2 40.00 40.00 0.00 10-Nov-21 15-Nov-21 10-Nov-21 15-Nov-21 100.00% 100.00% 0.00%
Screeding concrete pouring 10.00% m3 0.69 0.69 0.00 18-Nov-21 18-Nov-21 18-Nov-21 18-Nov-21 100.00% 100.36% 0.36%
Concrete works for Raft 25.00% 20-Nov-21 27-Nov-21 20-Nov-21 27-Nov-21 70.00% 100.01% 30.01%
Steel fixing for Raft with wall kickers 40.00% tons 1305.16 1305.16 0.00 20-Nov-21 23-Nov-21 20-Nov-21 23-Nov-21 100.00% 100.00% 0.00%
Formwork installation for Raft with wall kickers 30.00% m2 15.00 15.00 0.00 23-Nov-21 27-Nov-21 23-Nov-21 27-Nov-21 100.00% 100.00% 0.00%
Inspection and concrete pouring for Raft 20.00% m3 6.88 6.88 0.00 0.00% 100.07% 100.07%
Curing and deshuttering for Raft 10.00% m2 15.00 15.00 0.00 0.00% 100.00% 100.00%
Concrete works for Walls 35.00% 0.00% 30.00% 30.00%
Chipping and Steel fixing for Walls 30.00% tons 1363.91 1363.91 0.00 0.00% 100.00% 100.00%
Formwork installation for Walls 40.00% m2 72.50 72.50 0.00% 0.00% 0.00%
Inspection and concrete pouring for Walls 20.00% m3 7.50 7.50 0.00% 0.00% 0.00%
Curing and deshuttering for Walls 10.00% m2 42.50 42.50 0.00% 0.00% 0.00%
Post-concrete works 10.00% 0.00% 0.00% 0.00%
Waterproofing works for walls 30.00% m2 42.50 42.50 0.00% 0.00% 0.00%
Backfilling and Compaction 30.00% m3 44.13 44.13 0.00% 0.00% 0.00%
Chipping and Pouring of Sloping screed 30.00% m 25.00 25.00 0.00% 0.00% 0.00%
Installation of Pre-cast / GRP Covers 10.00% m 25.00 25.00 0.00% 0.00% 0.00%
Chemical Trench at C004 to C006 2.94% 0.00% 18.27% 18.27% still did not get for excavation approval
Pre-concrete works 30.00% 0.00% 60.88% 60.88%
Excavation and dewatering 30.00% m3 141.53 141.53 0.00 0.00% 100.00% 100.00%
Backfilling and Compaction 20.00% m2 58.50 45.00 13.50 0.00% 76.92% 76.92%
Blinding or Lean concrete Pouring 20.00% m3 4.39 3.40 0.99 0.00% 77.49% 77.49%
Waterproofing works 20.00% m2 72.00 72.00 0.00% 0.00% 0.00%
Screeding concrete pouring 10.00% m3 1.24 1.24 0.00% 0.00% 0.00%
Concrete works for Raft 25.00% 0.00% 0.00% 0.00%
Steel fixing for Raft with wall kickers 40.00% tons 2346.67 2346.67 0.00% 0.00% 0.00%
Formwork installation for Raft with wall kickers 30.00% m2 27.00 27.00 0.00% 0.00% 0.00%
Inspection and concrete pouring for Raft 20.00% m3 12.38 12.38 0.00% 0.00% 0.00%
Curing and deshuttering for Raft 10.00% m2 27.00 27.00 0.00% 0.00% 0.00%
Concrete works for Walls 35.00% 0.00% 0.00% 0.00%
Chipping and Steel fixing for Walls 30.00% tons 2533.33 2533.33 0.00% 0.00% 0.00%
Formwork installation for Walls 40.00% m2 202.50 202.50 0.00% 0.00% 0.00%
Inspection and concrete pouring for Walls 20.00% m3 11.25 11.25 0.00% 0.00% 0.00%
Curing and deshuttering for Walls 10.00% m2 27.00 27.00 0.00% 0.00% 0.00%
Post-concrete works 10.00% 0.00% 0.00% 0.00%
Waterproofing works for walls 30.00% m2 112.50 112.50 0.00% 0.00% 0.00%
Backfilling and Compaction 30.00% m3 112.28 112.28 0.00% 0.00% 0.00%
Chipping and Pouring of Sloping screed 30.00% m 45.00 45.00 0.00% 0.00% 0.00%
Installation of Pre-cast / GRP Covers 10.00% m 45.00 45.00 0.00% 0.00% 0.00%
Chemical Trench at C006 to C009 6.21% 3-Oct-21 8-Nov-21 22-Aug-21 50.00% 64.70% 14.70%
Pre-concrete works 30.00% 22-Aug-21 0.00% 79.03% 79.03%
Excavation and dewatering 30.00% m3 298.78 236.00 62.78 22-Aug-21 26-Sep-21 0.00% 78.99% 78.99%
Backfilling and Compaction 20.00% m2 123.50 97.71 25.79 27-Aug-21 4-Sep-21 0.00% 79.12% 79.12%
Blinding or Lean concrete Pouring 20.00% m3 9.26 7.32 1.94 14-Sep-21 14-Sep-21 0.00% 79.03% 79.03%
Waterproofing works 20.00% m2 152.00 120.26 31.74 19-Sep-21 23-Sep-21 0.00% 79.12% 79.12%
Screeding concrete pouring 10.00% m3 2.61 2.06 0.55 25-Sep-21 25-Sep-21 0.00% 78.85% 78.85%
Concrete works for Raft 25.00% 3-Oct-21 8-Oct-21 10-Oct-21 60.00% 79.11% 19.11%
Steel fixing for Raft with wall kickers 40.00% tons 4954.07 3919.59 1034.48 26-Oct-21 3-Nov-21 0.00% 79.12% 79.12%
Formwork installation for Raft with wall kickers 30.00% m2 57.00 45.09 11.91 3-Oct-21 4-Oct-21 7-0ct-21 9-Oct-21 100.00% 79.11% -20.89%
Inspection and concrete pouring for Raft 20.00% m3 26.13 20.67 5.46 5-Oct-21 5-Oct-21 10-Oct-21 12-Oct-21 100.00% 79.12% -20.88%
Curing and deshuttering for Raft 10.00% m2 57.00 45.09 11.91 6-Oct-21 8-Oct-21 14-Oct-21 19-ct-21 100.00% 79.11% -20.89%
Concrete works for Walls 35.00% 20-Oct-21 8-Nov-21 20-Oct-21 100.00% 57.00% -43.00%
Chipping and Steel fixing for Walls 30.00% tons 5348.15 3305.00 2043.15 20-Oct-21 22-Oct-21 20-Oct-21 22-Oct-21 100.00% 61.80% -38.20%
Formwork installation for Walls 40.00% m2 427.50 264.00 163.50 23-Oct-21 26-Oct-21 23-Oct-21 26-Oct-21 100.00% 61.75% -38.25%
Inspection and concrete pouring for Walls 20.00% m3 23.75 9.00 14.75 2-Nov-21 2-Nov-21 2-Nov-21 2-Nov-21 100.00% 37.89% -62.11%
Curing and deshuttering for Walls 10.00% m2 57.00 35.23 21.77 3-Nov-21 8-Nov-21 3-Nov-21 8-Nov-21 100.00% 61.81% -38.19%
Post-concrete works 10.00% 0.00% 12.63% 12.63%
Waterproofing works for walls 30.00% m2 237.50 100.00 137.50 0.00% 42.11% 42.11%
Backfilling and Compaction 30.00% m3 237.03 237.03 0.00% 0.00% 0.00%
Chipping and Pouring of Sloping screed 30.00% m 95.00 95.00 0.00% 0.00% 0.00%
Installation of Pre-cast / GRP Covers 10.00% m 95.00 95.00 0.00% 0.00% 0.00%
Chemical Trench at C009 to C012 5.76% 3-Oct-21 21-Oct-21 4-Sep-21 63.00% 22.18% -40.82%
Pre-concrete works 30.00% 4-Sep-21 0.00% 25.21% 25.21%
Excavation and dewatering 30.00% m3 179.67 51.00 128.67 4-Sep-21 6-Sep-21 0.00% 28.39% 28.39%
Backfilling and Compaction 20.00% m2 114.40 26.00 88.40 7-Sep-21 11-Sep-21 0.00% 22.73% 22.73%
Blinding or Lean concrete Pouring 20.00% m3 8.58 2.08 6.50 14-Sep-21 14-Sep-21 0.00% 24.24% 24.24%
Waterproofing works 20.00% m2 140.80 34.29 106.51 19-Sep-21 23-Sep-21 0.00% 24.35% 24.35%
Screeding concrete pouring 10.00% m3 2.42 0.59 1.83 0.00% 24.34% 24.34%
Concrete works for Raft 25.00% 3-Oct-21 10-Oct-21 3-Oct-21 100.00% 29.49% -70.51%
Steel fixing for Raft with wall kickers 40.00% tons 4589.04 1117.69 3471.35 3-Oct-21 5-Oct-21 3-Oct-21 5-Oct-21 100.00% 24.36% -75.64%
Formwork installation for Raft with wall kickers 30.00% m2 52.80 12.85 39.95 5-Oct-21 7-Oct-21 9-Oct-21 12-Oct-21 100.00% 24.34% -75.66%
Inspection and concrete pouring for Raft 20.00% m3 24.20 5.89 18.31 8-Oct-21 8-Oct-21 13-Oct-21 14-Oct-21 100.00% 24.34% -75.66%
Curing and deshuttering for Raft 10.00% m2 52.80 40.00 12.80 9-Oct-21 10-Oct-21 15-Oct-21 21-Oct-21 100.00% 75.76% -24.24%
Concrete works for Walls 35.00% 11-Oct-21 16-Oct-21 21-Oct-21 100.00% 19.06% -80.94%
Chipping and Steel fixing for Walls 30.00% tons 4954.07 947.00 4007.07 11-Oct-21 12-Oct-21 21-Oct-21 22-Oct-21 100.00% 19.12% -80.88%
Formwork installation for Walls 40.00% m2 272.80 52.00 220.80 12-Oct-21 14-Oct-21 23-Oct-21 24-Oct-21 100.00% 19.06% -80.94%
Inspection and concrete pouring for Walls 20.00% m3 14.30 2.73 11.57 15-Oct-21 15-Oct-21 2-Nov-21 2-Nov-21 100.00% 19.09% -80.91%
Curing and deshuttering for Walls 10.00% m2 52.80 9.95 42.85 16-Oct-21 16-Oct-21 3-Nov-21 8-Nov-21 100.00% 18.84% -81.16%
Post-concrete works 10.00% 18-Oct-21 21-Oct-21 11-Nov-21 30.00% 5.71% -24.29%
Waterproofing works for walls 30.00% m2 158.58 30.19 128.39 18-Oct-21 21-Oct-21 11-Nov-21 18-Nov-21 100.00% 19.04% -80.96%
Backfilling and Compaction 30.00% m3 130.17 130.17 0.00% 0.00% 0.00%
Chipping and Pouring of Sloping screed 30.00% m 88.00 88.00 0.00% 0.00% 0.00%
Installation of Pre-cast / GRP Covers 10.00% m 88.00 88.00 0.00% 0.00% 0.00%
Chemical Trench at C009 to C015 7.52% 0.00% 0.00% 0.00%
Pre-concrete works 30.00% 0.00% 0.00% 0.00%
Excavation and dewatering 30.00% m3 446.78 446.78 0.00% 0.00% 0.00%
Backfilling and Compaction 20.00% m2 195.50 195.50 0.00% 0.00% 0.00%
Blinding or Lean concrete Pouring 20.00% m3 14.66 14.66 0.00% 0.00% 0.00%
Waterproofing works 20.00% m2 230.00 230.00 0.00% 0.00% 0.00%
Screeding concrete pouring 10.00% m3 4.31 4.31 0.00% 0.00% 0.00%
Concrete works for Raft 25.00% 0.00% 0.00% 0.00%
Steel fixing for Raft with wall kickers 40.00% tons 5997.04 5997.04 0.00% 0.00% 0.00%
Formwork installation for Raft with wall kickers 30.00% m2 69.00 69.00 0.00% 0.00% 0.00%
Inspection and concrete pouring for Raft 20.00% m3 31.63 31.63 0.00% 0.00% 0.00%
Curing and deshuttering for Raft 10.00% m2 69.00 69.00 0.00% 0.00% 0.00%
Concrete works for Walls 35.00% 0.00% 0.00% 0.00%
Chipping and Steel fixing for Walls 30.00% tons 5914.07 5914.07 0.00% 0.00% 0.00%
Formwork installation for Walls 40.00% m2 517.50 517.50 0.00% 0.00% 0.00%
Inspection and concrete pouring for Walls 20.00% m3 57.50 57.50 0.00% 0.00% 0.00%
Curing and deshuttering for Walls 10.00% m2 69.00 69.00 0.00% 0.00% 0.00%
Post-concrete works 10.00% 0.00% 0.00% 0.00%
Waterproofing works for walls 30.00% m2 287.50 287.50 0.00% 0.00% 0.00%
Backfilling and Compaction 30.00% m3 338.68 338.68 0.00% 0.00% 0.00%
Chipping and Pouring of Sloping screed 30.00% m 115.00 115.00 0.00% 0.00% 0.00%
Installation of Pre-cast / GRP Covers 10.00% m 115.00 115.00 0.00% 0.00% 0.00%
Chemical Trench at C015 to C017 2.29% 0.00% 0.00% 0.00%
Pre-concrete works 30.00% 0.00% 0.00% 0.00%
Excavation and dewatering 30.00% m3 141.05 141.05 0.00% 0.00% 0.00%
Backfilling and Compaction 20.00% m2 77.00 77.00 0.00% 0.00% 0.00%
Blinding or Lean concrete Pouring 20.00% m3 5.78 5.78 0.00% 0.00% 0.00%
Waterproofing works 20.00% m2 87.50 87.50 0.00% 0.00% 0.00%
Screeding concrete pouring 10.00% m3 1.75 1.75 0.00% 0.00% 0.00%
Concrete works for Raft 25.00% 0.00% 0.00% 0.00%
Steel fixing for Raft with wall kickers 40.00% tons 1825.19 1825.19 0.00% 0.00% 0.00%
Formwork installation for Raft with wall kickers 30.00% m2 21.00 21.00 0.00% 0.00% 0.00%
Inspection and concrete pouring for Raft 20.00% m3 17.50 17.50 0.00% 0.00% 0.00%
Curing and deshuttering for Raft 10.00% m2 21.00 21.00 0.00% 0.00% 0.00%
Concrete works for Walls 35.00% 0.00% 0.00% 0.00%
Chipping and Steel fixing for Walls 30.00% tons 1970.37 1970.37 0.00% 0.00% 0.00%
Formwork installation for Walls 40.00% m2 157.50 157.50 0.00% 0.00% 0.00%
Inspection and concrete pouring for Walls 20.00% m3 17.50 17.50 0.00% 0.00% 0.00%
Curing and deshuttering for Walls 10.00% m2 21.00 21.00 0.00% 0.00% 0.00%
Post-concrete works 10.00% 0.00% 0.00% 0.00%
Waterproofing works for walls 30.00% m2 87.50 87.50 0.00% 0.00% 0.00%
Backfilling and Compaction 30.00% m3 98.53 98.53 0.00% 0.00% 0.00%
Chipping and Pouring of Sloping screed 30.00% m 35.00 35.00 0.00% 0.00% 0.00%
Installation of Pre-cast / GRP Covers 10.00% m 35.00 35.00 0.00% 0.00% 0.00%
Chemical Trench at C017 to C018 5.23% 0.00% 0.00% 0.00%
Pre-concrete works 30.00% 0.00% 0.00% 0.00%
Excavation and dewatering 30.00% m3 322.40 322.40 0.00% 0.00% 0.00%
Backfilling and Compaction 20.00% m2 176.00 176.00 0.00% 0.00% 0.00%
Blinding or Lean concrete Pouring 20.00% m3 13.20 13.20 0.00% 0.00% 0.00%
Waterproofing works 20.00% m2 200.00 200.00 0.00% 0.00% 0.00%
Screeding concrete pouring 10.00% m3 4.00 4.00 0.00% 0.00% 0.00%
Concrete works for Raft 25.00% 0.00% 0.00% 0.00%
Steel fixing for Raft with wall kickers 40.00% tons 4171.85 4171.85 0.00% 0.00% 0.00%
Formwork installation for Raft with wall kickers 30.00% m2 48.00 48.00 0.00% 0.00% 0.00%
Inspection and concrete pouring for Raft 20.00% m3 40.00 40.00 0.00% 0.00% 0.00%
Curing and deshuttering for Raft 10.00% m2 48.00 48.00 0.00% 0.00% 0.00%
Concrete works for Walls 35.00% 0.00% 0.00% 0.00%
Chipping and Steel fixing for Walls 30.00% tons 4503.70 4503.70 0.00% 0.00% 0.00%
Formwork installation for Walls 40.00% m2 248.00 248.00 0.00% 0.00% 0.00%
Inspection and concrete pouring for Walls 20.00% m3 40.00 40.00 0.00% 0.00% 0.00%
Curing and deshuttering for Walls 10.00% m2 48.00 48.00 0.00% 0.00% 0.00%
Post-concrete works 10.00% 0.00% 0.00% 0.00%
Waterproofing works for walls 30.00% m2 200.00 200.00 0.00% 0.00% 0.00%
Backfilling and Compaction 30.00% m3 225.20 225.20 0.00% 0.00% 0.00%
Chipping and Pouring of Sloping screed 30.00% m 80.00 80.00 0.00% 0.00% 0.00%
Installation of Pre-cast / GRP Covers 10.00% m 80.00 80.00 0.00% 0.00% 0.00%
Chemical Trench at C018 to C019 0.98% 0.00% 0.00% 0.00%
Pre-concrete works 30.00% 0.00% 0.00% 0.00%
Excavation and dewatering 30.00% m3 60.45 60.45 0.00% 0.00% 0.00%
Backfilling and Compaction 20.00% m2 33.00 33.00 0.00% 0.00% 0.00%
Blinding or Lean concrete Pouring 20.00% m3 2.48 2.48 0.00% 0.00% 0.00%
Waterproofing works 20.00% m2 37.50 37.50 0.00% 0.00% 0.00%
Screeding concrete pouring 10.00% m3 0.75 0.75 0.00% 0.00% 0.00%
Concrete works for Raft 25.00% 0.00% 0.00% 0.00%
Steel fixing for Raft with wall kickers 40.00% tons 782.22 782.22 0.00% 0.00% 0.00%
Formwork installation for Raft with wall kickers 30.00% m2 9.00 9.00 0.00% 0.00% 0.00%
Inspection and concrete pouring for Raft 20.00% m3 7.50 7.50 0.00% 0.00% 0.00%
Curing and deshuttering for Raft 10.00% m2 9.00 9.00 0.00% 0.00% 0.00%
Concrete works for Walls 35.00% 0.00% 0.00% 0.00%
Chipping and Steel fixing for Walls 30.00% tons 844.44 844.44 0.00% 0.00% 0.00%
Formwork installation for Walls 40.00% m2 46.50 46.50 0.00% 0.00% 0.00%
Inspection and concrete pouring for Walls 20.00% m3 7.50 7.50 0.00% 0.00% 0.00%
Curing and deshuttering for Walls 10.00% m2 9.00 9.00 0.00% 0.00% 0.00%
Post-concrete works 10.00% 0.00% 0.00% 0.00%
Waterproofing works for walls 30.00% m2 37.50 37.50 0.00% 0.00% 0.00%
Backfilling and Compaction 30.00% m3 42.23 42.23 0.00% 0.00% 0.00%
Chipping and Pouring of Sloping screed 30.00% m 15.00 15.00 0.00% 0.00% 0.00%
Installation of Pre-cast / GRP Covers 10.00% m 15.00 15.00 0.00% 0.00% 0.00%
Chemical Trench at C019 to C020 2.94% 0.00% 0.00% 0.00%
Pre-concrete works 30.00% 0.00% 0.00% 0.00%
Excavation and dewatering 30.00% m3 181.35 181.35 0.00% 0.00% 0.00%
Backfilling and Compaction 20.00% m2 99.00 99.00 0.00% 0.00% 0.00%
Blinding or Lean concrete Pouring 20.00% m3 7.43 7.43 0.00% 0.00% 0.00%
Waterproofing works 20.00% m2 112.50 112.50 0.00% 0.00% 0.00%
Screeding concrete pouring 10.00% m3 2.25 2.25 0.00% 0.00% 0.00%
Concrete works for Raft 25.00% 0.00% 0.00% 0.00%
Steel fixing for Raft with wall kickers 40.00% tons 2346.67 2346.67 0.00% 0.00% 0.00%
Formwork installation for Raft with wall kickers 30.00% m2 27.00 27.00 0.00% 0.00% 0.00%
Inspection and concrete pouring for Raft 20.00% m3 22.50 22.50 0.00% 0.00% 0.00%
Curing and deshuttering for Raft 10.00% m2 27.00 27.00 0.00% 0.00% 0.00%
Concrete works for Walls 35.00% 0.00% 0.00% 0.00%
Chipping and Steel fixing for Walls 30.00% tons 2533.33 2533.33 0.00% 0.00% 0.00%
Formwork installation for Walls 40.00% m2 139.50 139.50 0.00% 0.00% 0.00%
Inspection and concrete pouring for Walls 20.00% m3 22.50 22.50 0.00% 0.00% 0.00%
Curing and deshuttering for Walls 10.00% m2 27.00 27.00 0.00% 0.00% 0.00%
Post-concrete works 10.00% 0.00% 0.00% 0.00%
Waterproofing works for walls 30.00% m2 112.50 112.50 0.00% 0.00% 0.00%
Backfilling and Compaction 30.00% m3 126.68 126.68 0.00% 0.00% 0.00%
Chipping and Pouring of Sloping screed 30.00% m 45.00 45.00 0.00% 0.00% 0.00%
Installation of Pre-cast / GRP Covers 10.00% m 45.00 45.00 0.00% 0.00% 0.00%
Chemical Trench at C021 to C022 0.98% 0.00% 0.00% 0.00%
Pre-concrete works 30.00% 0.00% 0.00% 0.00%
Excavation and dewatering 30.00% m3 40.95 40.95 0.00% 0.00% 0.00%
Backfilling and Compaction 20.00% m2 25.50 25.50 0.00% 0.00% 0.00%
Blinding or Lean concrete Pouring 20.00% m3 1.91 1.91 0.00% 0.00% 0.00%
Waterproofing works 20.00% m2 30.00 30.00 0.00% 0.00% 0.00%
Screeding concrete pouring 10.00% m3 0.56 0.56 0.00% 0.00% 0.00%
Concrete works for Raft 25.00% 0.00% 0.00% 0.00%
Steel fixing for Raft with wall kickers 40.00% tons 782.22 782.22 0.00% 0.00% 0.00%
Formwork installation for Raft with wall kickers 30.00% m2 9.00 9.00 0.00% 0.00% 0.00%
Inspection and concrete pouring for Raft 20.00% m3 5.63 5.63 0.00% 0.00% 0.00%
Curing and deshuttering for Raft 10.00% m2 9.00 9.00 0.00% 0.00% 0.00%
Concrete works for Walls 35.00% 0.00% 0.00% 0.00%
Chipping and Steel fixing for Walls 30.00% tons 844.44 844.44 0.00% 0.00% 0.00%
Formwork installation for Walls 40.00% m2 46.50 46.50 0.00% 0.00% 0.00%
Inspection and concrete pouring for Walls 20.00% m3 5.63 5.63 0.00% 0.00% 0.00%
Curing and deshuttering for Walls 10.00% m2 9.00 9.00 0.00% 0.00% 0.00%
Post-concrete works 10.00% 0.00% 0.00% 0.00%
Waterproofing works for walls 30.00% m2 30.00 30.00 0.00% 0.00% 0.00%
Backfilling and Compaction 30.00% m3 27.23 27.23 0.00% 0.00% 0.00%
Chipping and Pouring of Sloping screed 30.00% m 15.00 15.00 0.00% 0.00% 0.00%
Installation of Pre-cast / GRP Covers 10.00% m 15.00 15.00 0.00% 0.00% 0.00%
Chemical Trench at C021 to C023 9.48% 0.00% 0.00% 0.00%
Pre-concrete works 30.00% 0.00% 0.00% 0.00%
Excavation and dewatering 30.00% m3 471.98 471.98 0.00% 0.00% 0.00%
Backfilling and Compaction 20.00% m2 246.50 246.50 0.00% 0.00% 0.00%
Blinding or Lean concrete Pouring 20.00% m3 18.49 18.49 0.00% 0.00% 0.00%
Waterproofing works 20.00% m2 290.00 290.00 0.00% 0.00% 0.00%
Screeding concrete pouring 10.00% m3 5.44 5.44 0.00% 0.00% 0.00%
Concrete works for Raft 25.00% 0.00% 0.00% 0.00%
Steel fixing for Raft with wall kickers 40.00% tons 7561.48 7561.48 0.00% 0.00% 0.00%
Formwork installation for Raft with wall kickers 30.00% m2 87.00 87.00 0.00% 0.00% 0.00%
Inspection and concrete pouring for Raft 20.00% m3 54.38 54.38 0.00% 0.00% 0.00%
Curing and deshuttering for Raft 10.00% m2 87.00 87.00 0.00% 0.00% 0.00%
Concrete works for Walls 35.00% 0.00% 0.00% 0.00%
Chipping and Steel fixing for Walls 30.00% tons 8162.96 8162.96 0.00% 0.00% 0.00%
Formwork installation for Walls 40.00% m2 652.50 652.50 0.00% 0.00% 0.00%
Inspection and concrete pouring for Walls 20.00% m3 72.50 72.50 0.00% 0.00% 0.00%
Curing and deshuttering for Walls 10.00% m2 87.00 87.00 0.00% 0.00% 0.00%
Post-concrete works 10.00% 0.00% 0.00% 0.00%
Waterproofing works for walls 30.00% m2 290.00 290.00 0.00% 0.00% 0.00%
Backfilling and Compaction 30.00% m3 321.18 321.18 0.00% 0.00% 0.00%
Chipping and Pouring of Sloping screed 30.00% m 145.00 145.00 0.00% 0.00% 0.00%
Installation of Pre-cast / GRP Covers 10.00% m 145.00 145.00 0.00% 0.00% 0.00%
Chemical Trench at C023 to C024 0.65% 0.00% 0.00% 0.00%
Pre-concrete works 30.00% 0.00% 0.00% 0.00%
Excavation and dewatering 30.00% m3 20.40 20.40 0.00% 0.00% 0.00%
Backfilling and Compaction 20.00% m2 13.00 13.00 0.00% 0.00% 0.00%
Blinding or Lean concrete Pouring 20.00% m3 0.98 0.98 0.00% 0.00% 0.00%
Waterproofing works 20.00% m2 16.00 16.00 0.00% 0.00% 0.00%
Screeding concrete pouring 10.00% m3 0.28 0.28 0.00% 0.00% 0.00%
Concrete works for Raft 25.00% 0.00% 0.00% 0.00%
Steel fixing for Raft with wall kickers 40.00% tons 521.48 521.48 0.00% 0.00% 0.00%
Formwork installation for Raft with wall kickers 30.00% m2 6.00 6.00 0.00% 0.00% 0.00%
Inspection and concrete pouring for Raft 20.00% m3 2.75 2.75 0.00% 0.00% 0.00%
Curing and deshuttering for Raft 10.00% m2 6.00 6.00 0.00% 0.00% 0.00%
Concrete works for Walls 35.00% 0.00% 0.00% 0.00%
Chipping and Steel fixing for Walls 30.00% tons 562.96 562.96 0.00% 0.00% 0.00%
Formwork installation for Walls 40.00% m2 31.00 31.00 0.00% 0.00% 0.00%
Inspection and concrete pouring for Walls 20.00% m3 5.00 5.00 0.00% 0.00% 0.00%
Curing and deshuttering for Walls 10.00% m2 6.00 6.00 0.00% 0.00% 0.00%
Post-concrete works 10.00% 0.00% 0.00% 0.00%
Waterproofing works for walls 30.00% m2 18.00 18.00 0.00% 0.00% 0.00%
Backfilling and Compaction 30.00% m3 11.40 11.40 0.00% 0.00% 0.00%
Chipping and Pouring of Sloping screed 30.00% m 10.00 10.00 0.00% 0.00% 0.00%
Installation of Pre-cast / GRP Covers 10.00% m 10.00 10.00 0.00% 0.00% 0.00%
Chemical Trench at C025 to C026 0.65% 0.00% 0.00% 0.00%
Pre-concrete works 30.00% 0.00% 0.00% 0.00%
Excavation and dewatering 30.00% m3 20.40 20.40 0.00% 0.00% 0.00%
Backfilling and Compaction 20.00% m2 13.00 13.00 0.00% 0.00% 0.00%
Blinding or Lean concrete Pouring 20.00% m3 0.98 0.98 0.00% 0.00% 0.00%
Waterproofing works 20.00% m2 16.00 16.00 0.00% 0.00% 0.00%
Screeding concrete pouring 10.00% m3 0.28 0.28 0.00% 0.00% 0.00%
Concrete works for Raft 25.00% 0.00% 0.00% 0.00%
Steel fixing for Raft with wall kickers 40.00% tons 521.48 521.48 0.00% 0.00% 0.00%
Formwork installation for Raft with wall kickers 30.00% m2 6.00 6.00 0.00% 0.00% 0.00%
Inspection and concrete pouring for Raft 20.00% m3 2.75 2.75 0.00% 0.00% 0.00%
Curing and deshuttering for Raft 10.00% m2 6.00 6.00 0.00% 0.00% 0.00%
Concrete works for Walls 35.00% 0.00% 0.00% 0.00%
Chipping and Steel fixing for Walls 30.00% tons 562.96 562.96 0.00% 0.00% 0.00%
Formwork installation for Walls 40.00% m2 31.00 31.00 0.00% 0.00% 0.00%
Inspection and concrete pouring for Walls 20.00% m3 3.00 3.00 0.00% 0.00% 0.00%
Curing and deshuttering for Walls 10.00% m2 6.00 6.00 0.00% 0.00% 0.00%
Post-concrete works 10.00% 0.00% 0.00% 0.00%
Waterproofing works for walls 30.00% m2 18.00 18.00 0.00% 0.00% 0.00%
Backfilling and Compaction 30.00% m3 13.40 13.40 0.00% 0.00% 0.00%
Chipping and Pouring of Sloping screed 30.00% m 10.00 10.00 0.00% 0.00% 0.00%
Installation of Pre-cast / GRP Covers 10.00% m 10.00 10.00 0.00% 0.00% 0.00%
Chemical Trench at C025 to C027 6.54% 0.00% 0.00% 0.00%
Pre-concrete works 30.00% 0.00% 0.00% 0.00%
Excavation and dewatering 30.00% m3 252.00 252.00 0.00% 0.00% 0.00%
Backfilling and Compaction 20.00% m2 170.00 170.00 0.00% 0.00% 0.00%
Blinding or Lean concrete Pouring 20.00% m3 12.75 12.75 0.00% 0.00% 0.00%
Waterproofing works 20.00% m2 200.00 200.00 0.00% 0.00% 0.00%
Screeding concrete pouring 10.00% m3 3.75 3.75 0.00% 0.00% 0.00%
Concrete works for Raft 25.00% 0.00% 0.00% 0.00%
Steel fixing for Raft with wall kickers 40.00% tons 5214.81 5214.81 0.00% 0.00% 0.00%
Formwork installation for Raft with wall kickers 30.00% m2 60.00 60.00 0.00% 0.00% 0.00%
Inspection and concrete pouring for Raft 20.00% m3 37.50 37.50 0.00% 0.00% 0.00%
Curing and deshuttering for Raft 10.00% m2 60.00 60.00 0.00% 0.00% 0.00%
Concrete works for Walls 35.00% 0.00% 0.00% 0.00%
Chipping and Steel fixing for Walls 30.00% tons 5629.63 5629.63 0.00% 0.00% 0.00%
Formwork installation for Walls 40.00% m2 310.00 310.00 0.00% 0.00% 0.00%
Inspection and concrete pouring for Walls 20.00% m3 32.50 32.50 0.00% 0.00% 0.00%
Curing and deshuttering for Walls 10.00% m2 60.00 60.00 0.00% 0.00% 0.00%
Post-concrete works 10.00% 0.00% 0.00% 0.00%
Waterproofing works for walls 30.00% m2 180.00 180.00 0.00% 0.00% 0.00%
Backfilling and Compaction 30.00% m3 165.50 165.50 0.00% 0.00% 0.00%
Chipping and Pouring of Sloping screed 30.00% m 100.00 100.00 0.00% 0.00% 0.00%
Installation of Pre-cast / GRP Covers 10.00% m 100.00 100.00 0.00% 0.00% 0.00%
Chemical Trench at C027 to C030 1.31% 0.00% 0.00% 0.00%
Pre-concrete works 30.00% 0.00% 0.00% 0.00%
Excavation and dewatering 30.00% m3 40.80 40.80 0.00% 0.00% 0.00%
Backfilling and Compaction 20.00% m2 26.00 26.00 0.00% 0.00% 0.00%
Blinding or Lean concrete Pouring 20.00% m3 1.95 1.95 0.00% 0.00% 0.00%
Waterproofing works 20.00% m2 32.00 32.00 0.00% 0.00% 0.00%
Screeding concrete pouring 10.00% m3 0.55 0.55 0.00% 0.00% 0.00%
Concrete works for Raft 25.00% 0.00% 0.00% 0.00%
Steel fixing for Raft with wall kickers 40.00% tons 1042.96 1042.96 0.00% 0.00% 0.00%
Formwork installation for Raft with wall kickers 30.00% m2 12.00 12.00 0.00% 0.00% 0.00%
Inspection and concrete pouring for Raft 20.00% m3 5.50 5.50 0.00% 0.00% 0.00%
Curing and deshuttering for Raft 10.00% m2 12.00 12.00 0.00% 0.00% 0.00%
Concrete works for Walls 35.00% 0.00% 0.00% 0.00%
Chipping and Steel fixing for Walls 30.00% tons 1125.93 1125.93 0.00% 0.00% 0.00%
Formwork installation for Walls 40.00% m2 58.00 58.00 0.00% 0.00% 0.00%
Inspection and concrete pouring for Walls 20.00% m3 6.50 6.50 0.00% 0.00% 0.00%
Curing and deshuttering for Walls 10.00% m2 12.00 12.00 0.00% 0.00% 0.00%
Post-concrete works 10.00% 0.00% 0.00% 0.00%
Waterproofing works for walls 30.00% m2 36.00 36.00 0.00% 0.00% 0.00%
Backfilling and Compaction 30.00% m3 26.30 26.30 0.00% 0.00% 0.00%
Chipping and Pouring of Sloping screed 30.00% m 20.00 20.00 0.00% 0.00% 0.00%
Installation of Pre-cast / GRP Covers 10.00% m 20.00 20.00 0.00% 0.00% 0.00%
Chemical Trench at C030 to C031 0.98% 0.00% 0.00% 0.00%
Pre-concrete works 30.00% 0.00% 0.00% 0.00%
Excavation and dewatering 30.00% m3 30.60 30.60 0.00% 0.00% 0.00%
Backfilling and Compaction 20.00% m2 19.50 19.50 0.00% 0.00% 0.00%
Blinding or Lean concrete Pouring 20.00% m3 1.46 1.46 0.00% 0.00% 0.00%
Waterproofing works 20.00% m2 24.00 24.00 0.00% 0.00% 0.00%
Screeding concrete pouring 10.00% m3 0.41 0.41 0.00% 0.00% 0.00%
Concrete works for Raft 25.00% 0.00% 0.00% 0.00%
Steel fixing for Raft with wall kickers 40.00% tons 782.22 782.22 0.00% 0.00% 0.00%
Formwork installation for Raft with wall kickers 30.00% m2 9.00 9.00 0.00% 0.00% 0.00%
Inspection and concrete pouring for Raft 20.00% m3 4.13 4.13 0.00% 0.00% 0.00%
Curing and deshuttering for Raft 10.00% m2 9.00 9.00 0.00% 0.00% 0.00%
Concrete works for Walls 35.00% 0.00% 0.00% 0.00%
Chipping and Steel fixing for Walls 30.00% tons 844.44 844.44 0.00% 0.00% 0.00%
Formwork installation for Walls 40.00% m2 43.50 43.50 0.00% 0.00% 0.00%
Inspection and concrete pouring for Walls 20.00% m3 4.88 4.88 0.00% 0.00% 0.00%
Curing and deshuttering for Walls 10.00% m2 9.00 9.00 0.00% 0.00% 0.00%
Post-concrete works 10.00% 0.00% 0.00% 0.00%
Waterproofing works for walls 30.00% m2 27.00 27.00 0.00% 0.00% 0.00%
Backfilling and Compaction 30.00% m3 19.73 19.73 0.00% 0.00% 0.00%
Chipping and Pouring of Sloping screed 30.00% m 15.00 15.00 0.00% 0.00% 0.00%
Installation of Pre-cast / GRP Covers 10.00% m 15.00 15.00 0.00% 0.00% 0.00%
Chemical Trench at C029 to C031 1.44% 0.00% 0.00% 0.00%
Pre-concrete works 30.00% 0.00% 0.00% 0.00%
Excavation and dewatering 30.00% m3 44.88 44.88 0.00% 0.00% 0.00%
Backfilling and Compaction 20.00% m2 28.60 28.60 0.00% 0.00% 0.00%
Blinding or Lean concrete Pouring 20.00% m3 2.15 2.15 0.00% 0.00% 0.00%
Waterproofing works 20.00% m2 35.20 35.20 0.00% 0.00% 0.00%
Screeding concrete pouring 10.00% m3 0.61 0.61 0.00% 0.00% 0.00%
Concrete works for Raft 25.00% 0.00% 0.00% 0.00%
Steel fixing for Raft with wall kickers 40.00% tons 1147.26 1147.26 0.00% 0.00% 0.00%
Formwork installation for Raft with wall kickers 30.00% m2 13.20 13.20 0.00% 0.00% 0.00%
Inspection and concrete pouring for Raft 20.00% m3 6.05 6.05 0.00% 0.00% 0.00%
Curing and deshuttering for Raft 10.00% m2 13.20 13.20 0.00% 0.00% 0.00%
Concrete works for Walls 35.00% 0.00% 0.00% 0.00%
Chipping and Steel fixing for Walls 30.00% tons 1238.52 1238.52 0.00% 0.00% 0.00%
Formwork installation for Walls 40.00% m2 63.80 63.80 0.00% 0.00% 0.00%
Inspection and concrete pouring for Walls 20.00% m3 7.15 7.15 0.00% 0.00% 0.00%
Curing and deshuttering for Walls 10.00% m2 13.20 13.20 0.00% 0.00% 0.00%
Post-concrete works 10.00% 0.00% 0.00% 0.00%
Waterproofing works for walls 30.00% m2 39.60 39.60 0.00% 0.00% 0.00%
Backfilling and Compaction 30.00% m3 28.93 28.93 0.00% 0.00% 0.00%
Chipping and Pouring of Sloping screed 30.00% m 22.00 22.00 0.00% 0.00% 0.00%
Installation of Pre-cast / GRP Covers 10.00% m 22.00 22.00 0.00% 0.00% 0.00%
Chemical Trench at C031 to C032 5.23% 0.00% 0.00% 0.00%
Pre-concrete works 30.00% 0.00% 0.00% 0.00%
Excavation and dewatering 30.00% m3 163.20 163.20 0.00% 0.00% 0.00%
Backfilling and Compaction 20.00% m2 104.00 104.00 0.00% 0.00% 0.00%
Blinding or Lean concrete Pouring 20.00% m3 7.80 7.80 0.00% 0.00% 0.00%
Waterproofing works 20.00% m2 128.00 128.00 0.00% 0.00% 0.00%
Screeding concrete pouring 10.00% m3 2.20 2.20 0.00% 0.00% 0.00%
Concrete works for Raft 25.00% 0.00% 0.00% 0.00%
Steel fixing for Raft with wall kickers 40.00% tons 4171.85 4171.85 0.00% 0.00% 0.00%
Formwork installation for Raft with wall kickers 30.00% m2 48.00 48.00 0.00% 0.00% 0.00%
Inspection and concrete pouring for Raft 20.00% m3 22.00 22.00 0.00% 0.00% 0.00%
Curing and deshuttering for Raft 10.00% m2 48.00 48.00 0.00% 0.00% 0.00%
Concrete works for Walls 35.00% 0.00% 0.00% 0.00%
Chipping and Steel fixing for Walls 30.00% tons 4503.70 4503.70 0.00% 0.00% 0.00%
Formwork installation for Walls 40.00% m2 232.00 232.00 0.00% 0.00% 0.00%
Inspection and concrete pouring for Walls 20.00% m3 20.80 20.80 0.00% 0.00% 0.00%
Curing and deshuttering for Walls 10.00% m2 48.00 48.00 0.00% 0.00% 0.00%
Post-concrete works 10.00% 0.00% 0.00% 0.00%
Waterproofing works for walls 30.00% m2 144.00 144.00 0.00% 0.00% 0.00%
Backfilling and Compaction 30.00% m3 110.40 110.40 0.00% 0.00% 0.00%
Chipping and Pouring of Sloping screed 30.00% m 80.00 80.00 0.00% 0.00% 0.00%
Installation of Pre-cast / GRP Covers 10.00% m 80.00 80.00 0.00% 0.00% 0.00%
Chemical Trench at C032 to C034 2.94% 0.00% 0.00% 0.00%
Pre-concrete works 30.00% 0.00% 0.00% 0.00%
Excavation and dewatering 30.00% m3 91.80 91.80 0.00% 0.00% 0.00%
Backfilling and Compaction 20.00% m2 58.50 58.50 0.00% 0.00% 0.00%
Blinding or Lean concrete Pouring 20.00% m3 4.39 4.39 0.00% 0.00% 0.00%
Waterproofing works 20.00% m2 72.00 72.00 0.00% 0.00% 0.00%
Screeding concrete pouring 10.00% m3 1.24 1.24 0.00% 0.00% 0.00%
Concrete works for Raft 25.00% 0.00% 0.00% 0.00%
Steel fixing for Raft with wall kickers 40.00% tons 2346.67 2346.67 0.00% 0.00% 0.00%
Formwork installation for Raft with wall kickers 30.00% m2 27.00 27.00 0.00% 0.00% 0.00%

Conctruction of Buried Chemical Trenches PageI 1 of 18


Activities Weight % Unit of Scope Completed Remaining Planned Start Planned Finish Actual Start Actual Finish Planned Actual Progress Remarks
Measure Quantity Quantity Quantity Completion % Completion % Variance %
Conctruction of Buried Chemical Trenches 100.00% 3-Oct-21 30-Nov-21 22-Aug-21 11.07% 9.69% -1.38%
Inspection and concrete pouring for Raft 20.00% m3 12.38 12.38 0.00% 0.00% 0.00%
Curing and deshuttering for Raft 10.00% m2 27.00 27.00 0.00% 0.00% 0.00%
Concrete works for Walls 35.00% 0.00% 0.00% 0.00%
Chipping and Steel fixing for Walls 30.00% tons 2533.33 2533.33 0.00% 0.00% 0.00%
Formwork installation for Walls 40.00% m2 130.50 130.50 0.00% 0.00% 0.00%
Inspection and concrete pouring for Walls 20.00% m3 14.63 14.63 0.00% 0.00% 0.00%
Curing and deshuttering for Walls 10.00% m2 27.00 27.00 0.00% 0.00% 0.00%
Post-concrete works 10.00% 0.00% 0.00% 0.00%
Waterproofing works for walls 30.00% m2 81.00 81.00 0.00% 0.00% 0.00%
Backfilling and Compaction 30.00% m3 59.18 59.18 0.00% 0.00% 0.00%
Chipping and Pouring of Sloping screed 30.00% m 45.00 45.00 0.00% 0.00% 0.00%
Installation of Pre-cast / GRP Covers 10.00% m 45.00 45.00 0.00% 0.00% 0.00%
Chemical Trench at C034 to C036 1.64% 0.00% 0.00% 0.00%
Pre-concrete works 30.00% 0.00% 0.00% 0.00%
Excavation and dewatering 30.00% m3 51.00 51.00 0.00% 0.00% 0.00%
Backfilling and Compaction 20.00% m2 32.50 32.50 0.00% 0.00% 0.00%
Blinding or Lean concrete Pouring 20.00% m3 2.44 2.44 0.00% 0.00% 0.00%
Waterproofing works 20.00% m2 40.00 40.00 0.00% 0.00% 0.00%
Screeding concrete pouring 10.00% m3 0.69 0.69 0.00% 0.00% 0.00%
Concrete works for Raft 25.00% 0.00% 0.00% 0.00%
Steel fixing for Raft with wall kickers 40.00% tons 1303.70 1303.70 0.00% 0.00% 0.00%
Formwork installation for Raft with wall kickers 30.00% m2 15.00 15.00 0.00% 0.00% 0.00%
Inspection and concrete pouring for Raft 20.00% m3 6.88 6.88 0.00% 0.00% 0.00%
Curing and deshuttering for Raft 10.00% m2 15.00 15.00 0.00% 0.00% 0.00%
Concrete works for Walls 35.00% 0.00% 0.00% 0.00%
Chipping and Steel fixing for Walls 30.00% tons 1407.41 1407.41 0.00% 0.00% 0.00%
Formwork installation for Walls 40.00% m2 72.50 72.50 0.00% 0.00% 0.00%
Inspection and concrete pouring for Walls 20.00% m3 8.13 8.13 0.00% 0.00% 0.00%
Curing and deshuttering for Walls 10.00% m2 15.00 15.00 0.00% 0.00% 0.00%
Post-concrete works 10.00% 0.00% 0.00% 0.00%
Waterproofing works for walls 30.00% m2 45.00 45.00 0.00% 0.00% 0.00%
Backfilling and Compaction 30.00% m3 32.88 32.88 0.00% 0.00% 0.00%
Chipping and Pouring of Sloping screed 30.00% m 25.00 25.00 0.00% 0.00% 0.00%
Installation of Pre-cast / GRP Covers 10.00% m 25.00 25.00 0.00% 0.00% 0.00%
Chemical Trench at C034 to C037 1.64% 0.00% 0.00% 0.00%
Pre-concrete works 30.00% 0.00% 0.00% 0.00%
Excavation and dewatering 30.00% m3 63.00 63.00 0.00% 0.00% 0.00%
Backfilling and Compaction 20.00% m2 42.50 42.50 0.00% 0.00% 0.00%
Blinding or Lean concrete Pouring 20.00% m3 3.19 3.19 0.00% 0.00% 0.00%
Waterproofing works 20.00% m2 50.00 50.00 0.00% 0.00% 0.00%
Screeding concrete pouring 10.00% m3 0.94 0.94 0.00% 0.00% 0.00%
Concrete works for Raft 25.00% 0.00% 0.00% 0.00%
Steel fixing for Raft with wall kickers 40.00% tons 1303.70 1303.70 0.00% 0.00% 0.00%
Formwork installation for Raft with wall kickers 30.00% m2 15.00 15.00 0.00% 0.00% 0.00%
Inspection and concrete pouring for Raft 20.00% m3 9.38 9.38 0.00% 0.00% 0.00%
Curing and deshuttering for Raft 10.00% m2 15.00 15.00 0.00% 0.00% 0.00%
Concrete works for Walls 35.00% 0.00% 0.00% 0.00%
Chipping and Steel fixing for Walls 30.00% tons 1407.41 1407.41 0.00% 0.00% 0.00%
Formwork installation for Walls 40.00% m2 77.50 77.50 0.00% 0.00% 0.00%
Inspection and concrete pouring for Walls 20.00% m3 12.50 12.50 0.00% 0.00% 0.00%
Curing and deshuttering for Walls 10.00% m2 15.00 15.00 0.00% 0.00% 0.00%
Post-concrete works 10.00% 0.00% 0.00% 0.00%
Waterproofing works for walls 30.00% m2 45.00 45.00 0.00% 0.00% 0.00%
Backfilling and Compaction 30.00% m3 37.00 37.00 0.00% 0.00% 0.00%
Chipping and Pouring of Sloping screed 30.00% m 25.00 25.00 0.00% 0.00% 0.00%
Installation of Pre-cast / GRP Covers 10.00% m 25.00 25.00 0.00% 0.00% 0.00%
Chemical Trench at C037 to C038 0.33% 0.00% 0.00% 0.00%
Pre-concrete works 30.00% 0.00% 0.00% 0.00%
Excavation and dewatering 30.00% m3 11.03 11.03 0.00% 0.00% 0.00%
Backfilling and Compaction 20.00% m2 8.50 8.50 0.00% 0.00% 0.00%
Blinding or Lean concrete Pouring 20.00% m3 0.64 0.64 0.00% 0.00% 0.00%
Waterproofing works 20.00% m2 10.00 10.00 0.00% 0.00% 0.00%
Screeding concrete pouring 10.00% m3 0.19 0.19 0.00% 0.00% 0.00%
Concrete works for Raft 25.00% 0.00% 0.00% 0.00%
Steel fixing for Raft with wall kickers 40.00% tons 260.74 260.74 0.00% 0.00% 0.00%
Formwork installation for Raft with wall kickers 30.00% m2 3.00 3.00 0.00% 0.00% 0.00%
Inspection and concrete pouring for Raft 20.00% m3 1.88 1.88 0.00% 0.00% 0.00%
Curing and deshuttering for Raft 10.00% m2 3.00 3.00 0.00% 0.00% 0.00%
Concrete works for Walls 35.00% 0.00% 0.00% 0.00%
Chipping and Steel fixing for Walls 30.00% tons 281.48 281.48 0.00% 0.00% 0.00%
Formwork installation for Walls 40.00% m2 12.50 12.50 0.00% 0.00% 0.00%
Inspection and concrete pouring for Walls 20.00% m3 1.25 1.25 0.00% 0.00% 0.00%
Curing and deshuttering for Walls 10.00% m2 3.00 3.00 0.00% 0.00% 0.00%
Post-concrete works 10.00% 0.00% 0.00% 0.00%
Waterproofing works for walls 30.00% m2 7.50 7.50 0.00% 0.00% 0.00%
Backfilling and Compaction 30.00% m3 7.08 7.08 0.00% 0.00% 0.00%
Chipping and Pouring of Sloping screed 30.00% m 5.00 5.00 0.00% 0.00% 0.00%
Installation of Pre-cast / GRP Covers 10.00% m 5.00 5.00 0.00% 0.00% 0.00%
Chemical Trench at C037 to C039 0.33% 0.00% 0.00% 0.00%
Pre-concrete works 30.00% 0.00% 0.00% 0.00%
Excavation and dewatering 30.00% m3 10.20 10.20 0.00% 0.00% 0.00%
Backfilling and Compaction 20.00% m2 6.50 6.50 0.00% 0.00% 0.00%
Blinding or Lean concrete Pouring 20.00% m3 0.49 0.49 0.00% 0.00% 0.00%
Waterproofing works 20.00% m2 8.00 8.00 0.00% 0.00% 0.00%
Screeding concrete pouring 10.00% m3 0.14 0.14 0.00% 0.00% 0.00%
Concrete works for Raft 25.00% 0.00% 0.00% 0.00%
Steel fixing for Raft with wall kickers 40.00% tons 260.74 260.74 0.00% 0.00% 0.00%
Formwork installation for Raft with wall kickers 30.00% m2 3.00 3.00 0.00% 0.00% 0.00%
Inspection and concrete pouring for Raft 20.00% m3 1.38 1.38 0.00% 0.00% 0.00%
Curing and deshuttering for Raft 10.00% m2 3.00 3.00 0.00% 0.00% 0.00%
Concrete works for Walls 35.00% 0.00% 0.00% 0.00%
Chipping and Steel fixing for Walls 30.00% tons 281.48 281.48 0.00% 0.00% 0.00%
Formwork installation for Walls 40.00% m2 14.50 14.50 0.00% 0.00% 0.00%
Inspection and concrete pouring for Walls 20.00% m3 1.63 1.63 0.00% 0.00% 0.00%
Curing and deshuttering for Walls 10.00% m2 3.00 3.00 0.00% 0.00% 0.00%
Post-concrete works 10.00% 0.00% 0.00% 0.00%
Waterproofing works for walls 30.00% m2 9.00 9.00 0.00% 0.00% 0.00%
Backfilling and Compaction 30.00% m3 6.58 6.58 0.00% 0.00% 0.00%
Chipping and Pouring of Sloping screed 30.00% m 5.00 5.00 0.00% 0.00% 0.00%
Installation of Pre-cast / GRP Covers 10.00% m 5.00 5.00 0.00% 0.00% 0.00%
Chemical Trench at C017 to C040 5.23% 0.00% 0.00% 0.00%
Pre-concrete works 30.00% 0.00% 0.00% 0.00%
Excavation and dewatering 30.00% m3 260.40 260.40 0.00% 0.00% 0.00%
Backfilling and Compaction 20.00% m2 136.00 136.00 0.00% 0.00% 0.00%
Blinding or Lean concrete Pouring 20.00% m3 10.20 10.20 0.00% 0.00% 0.00%
Waterproofing works 20.00% m2 160.00 160.00 0.00% 0.00% 0.00%
Screeding concrete pouring 10.00% m3 3.00 3.00 0.00% 0.00% 0.00%
Concrete works for Raft 25.00% 0.00% 0.00% 0.00%
Steel fixing for Raft with wall kickers 40.00% tons 4171.85 4171.85 0.00% 0.00% 0.00%
Formwork installation for Raft with wall kickers 30.00% m2 48.00 48.00 0.00% 0.00% 0.00%
Inspection and concrete pouring for Raft 20.00% m3 30.00 30.00 0.00% 0.00% 0.00%
Curing and deshuttering for Raft 10.00% m2 48.00 48.00 0.00% 0.00% 0.00%
Concrete works for Walls 35.00% 0.00% 0.00% 0.00%
Chipping and Steel fixing for Walls 30.00% tons 4503.70 4503.70 0.00% 0.00% 0.00%
Formwork installation for Walls 40.00% m2 360.00 360.00 0.00% 0.00% 0.00%
Inspection and concrete pouring for Walls 20.00% m3 40.00 40.00 0.00% 0.00% 0.00%
Curing and deshuttering for Walls 10.00% m2 48.00 48.00 0.00% 0.00% 0.00%
Post-concrete works 10.00% 0.00% 0.00% 0.00%
Waterproofing works for walls 30.00% m2 200.00 200.00 0.00% 0.00% 0.00%
Backfilling and Compaction 30.00% m3 177.20 177.20 0.00% 0.00% 0.00%
Chipping and Pouring of Sloping screed 30.00% m 80.00 80.00 0.00% 0.00% 0.00%
Installation of Pre-cast / GRP Covers 10.00% m 80.00 80.00 0.00% 0.00% 0.00%
Chemical Trench at C040 to C041 0.33% 0.00% 0.00% 0.00%
Pre-concrete works 30.00% 0.00% 0.00% 0.00%
Excavation and dewatering 30.00% m3 13.18 13.18 0.00% 0.00% 0.00%
Backfilling and Compaction 20.00% m2 6.50 6.50 0.00% 0.00% 0.00%
Blinding or Lean concrete Pouring 20.00% m3 0.49 0.49 0.00% 0.00% 0.00%
Waterproofing works 20.00% m2 8.00 8.00 0.00% 0.00% 0.00%
Screeding concrete pouring 10.00% m3 0.14 0.14 0.00% 0.00% 0.00%
Concrete works for Raft 25.00% 0.00% 0.00% 0.00%
Steel fixing for Raft with wall kickers 40.00% tons 260.74 260.74 0.00% 0.00% 0.00%
Formwork installation for Raft with wall kickers 30.00% m2 3.00 3.00 0.00% 0.00% 0.00%
Inspection and concrete pouring for Raft 20.00% m3 1.38 1.38 0.00% 0.00% 0.00%
Curing and deshuttering for Raft 10.00% m2 3.00 3.00 0.00% 0.00% 0.00%
Concrete works for Walls 35.00% 0.00% 0.00% 0.00%
Chipping and Steel fixing for Walls 30.00% tons 281.48 281.48 0.00% 0.00% 0.00%
Formwork installation for Walls 40.00% m2 22.50 22.50 0.00% 0.00% 0.00%
Inspection and concrete pouring for Walls 20.00% m3 2.50 2.50 0.00% 0.00% 0.00%
Curing and deshuttering for Walls 10.00% m2 3.00 3.00 0.00% 0.00% 0.00%
Post-concrete works 10.00% 0.00% 0.00% 0.00%
Waterproofing works for walls 30.00% m2 12.50 12.50 0.00% 0.00% 0.00%
Backfilling and Compaction 30.00% m3 8.68 8.68 0.00% 0.00% 0.00%
Chipping and Pouring of Sloping screed 30.00% m 5.00 5.00 0.00% 0.00% 0.00%
Installation of Pre-cast / GRP Covers 10.00% m 5.00 5.00 0.00% 0.00% 0.00%
Chemical Trench at C040 to C042 1.96% 0.00% 0.00% 0.00%
Pre-concrete works 30.00% 0.00% 0.00% 0.00%
Excavation and dewatering 30.00% m3 97.65 97.65 0.00% 0.00% 0.00%
Backfilling and Compaction 20.00% m2 51.00 51.00 0.00% 0.00% 0.00%
Blinding or Lean concrete Pouring 20.00% m3 3.83 3.83 0.00% 0.00% 0.00%
Waterproofing works 20.00% m2 60.00 60.00 0.00% 0.00% 0.00%
Screeding concrete pouring 10.00% m3 1.13 1.13 0.00% 0.00% 0.00%
Concrete works for Raft 25.00% 0.00% 0.00% 0.00%
Steel fixing for Raft with wall kickers 40.00% tons 1564.44 1564.44 0.00% 0.00% 0.00%
Formwork installation for Raft with wall kickers 30.00% m2 18.00 18.00 0.00% 0.00% 0.00%
Inspection and concrete pouring for Raft 20.00% m3 11.25 11.25 0.00% 0.00% 0.00%
Curing and deshuttering for Raft 10.00% m2 18.00 18.00 0.00% 0.00% 0.00%
Concrete works for Walls 35.00% 0.00% 0.00% 0.00%
Chipping and Steel fixing for Walls 30.00% tons 1688.89 1688.89 0.00% 0.00% 0.00%
Formwork installation for Walls 40.00% m2 135.00 135.00 0.00% 0.00% 0.00%
Inspection and concrete pouring for Walls 20.00% m3 15.00 15.00 0.00% 0.00% 0.00%
Curing and deshuttering for Walls 10.00% m2 18.00 18.00 0.00% 0.00% 0.00%
Post-concrete works 10.00% 0.00% 0.00% 0.00%
Waterproofing works for walls 30.00% m2 75.00 75.00 0.00% 0.00% 0.00%
Backfilling and Compaction 30.00% m3 66.45 66.45 0.00% 0.00% 0.00%
Chipping and Pouring of Sloping screed 30.00% m 30.00 30.00 0.00% 0.00% 0.00%
Installation of Pre-cast / GRP Covers 10.00% m 30.00 30.00 0.00% 0.00% 0.00%
Chemical Trench at C043 to C048 7.52% 0.00% 0.00% 0.00%
Pre-concrete works 30.00% 0.00% 0.00% 0.00%
Excavation and dewatering 30.00% m3 303.03 303.03 0.00% 0.00% 0.00%
Backfilling and Compaction 20.00% m2 149.50 149.50 0.00% 0.00% 0.00%
Blinding or Lean concrete Pouring 20.00% m3 11.21 11.21 0.00% 0.00% 0.00%
Waterproofing works 20.00% m2 184.00 184.00 0.00% 0.00% 0.00%
Screeding concrete pouring 10.00% m3 3.16 3.16 0.00% 0.00% 0.00%
Concrete works for Raft 25.00% 0.00% 0.00% 0.00%
Steel fixing for Raft with wall kickers 40.00% tons 5997.04 5997.04 0.00% 0.00% 0.00%
Formwork installation for Raft with wall kickers 30.00% m2 69.00 69.00 0.00% 0.00% 0.00%
Inspection and concrete pouring for Raft 20.00% m3 31.63 31.63 0.00% 0.00% 0.00%
Curing and deshuttering for Raft 10.00% m2 69.00 69.00 0.00% 0.00% 0.00%
Concrete works for Walls 35.00% 0.00% 0.00% 0.00%
Chipping and Steel fixing for Walls 30.00% tons 6474.07 6474.07 0.00% 0.00% 0.00%
Formwork installation for Walls 40.00% m2 517.50 517.50 0.00% 0.00% 0.00%
Inspection and concrete pouring for Walls 20.00% m3 57.50 57.50 0.00% 0.00% 0.00%
Curing and deshuttering for Walls 10.00% m2 69.00 69.00 0.00% 0.00% 0.00%
Post-concrete works 10.00% 0.00% 0.00% 0.00%
Waterproofing works for walls 30.00% m2 287.50 287.50 0.00% 0.00% 0.00%
Backfilling and Compaction 30.00% m3 199.53 199.53 0.00% 0.00% 0.00%
Chipping and Pouring of Sloping screed 30.00% m 115.00 115.00 0.00% 0.00% 0.00%
Installation of Pre-cast / GRP Covers 10.00% m 115.00 115.00 0.00% 0.00% 0.00%
Chemical Trench at C048 to C051 5.56% 0.00% 0.00% 0.00%
Pre-concrete works 30.00% 0.00% 0.00% 0.00%
Excavation and dewatering 30.00% m3 223.98 223.98 0.00% 0.00% 0.00%
Backfilling and Compaction 20.00% m2 110.50 110.50 0.00% 0.00% 0.00%
Blinding or Lean concrete Pouring 20.00% m3 8.29 8.29 0.00% 0.00% 0.00%
Waterproofing works 20.00% m2 136.00 136.00 0.00% 0.00% 0.00%
Screeding concrete pouring 10.00% m3 2.34 2.34 0.00% 0.00% 0.00%
Concrete works for Raft 25.00% 0.00% 0.00% 0.00%
Steel fixing for Raft with wall kickers 40.00% tons 4432.59 4432.59 0.00% 0.00% 0.00%
Formwork installation for Raft with wall kickers 30.00% m2 51.00 51.00 0.00% 0.00% 0.00%
Inspection and concrete pouring for Raft 20.00% m3 23.38 23.38 0.00% 0.00% 0.00%
Curing and deshuttering for Raft 10.00% m2 51.00 51.00 0.00% 0.00% 0.00%
Concrete works for Walls 35.00% 0.00% 0.00% 0.00%
Chipping and Steel fixing for Walls 30.00% tons 4785.19 4785.19 0.00% 0.00% 0.00%
Formwork installation for Walls 40.00% m2 382.50 382.50 0.00% 0.00% 0.00%
Inspection and concrete pouring for Walls 20.00% m3 42.50 42.50 0.00% 0.00% 0.00%
Curing and deshuttering for Walls 10.00% m2 51.00 51.00 0.00% 0.00% 0.00%
Post-concrete works 10.00% 0.00% 0.00% 0.00%
Waterproofing works for walls 30.00% m2 212.50 212.50 0.00% 0.00% 0.00%
Backfilling and Compaction 30.00% m3 147.48 147.48 0.00% 0.00% 0.00%
Chipping and Pouring of Sloping screed 30.00% m 85.00 85.00 0.00% 0.00% 0.00%
Installation of Pre-cast / GRP Covers 10.00% m 85.00 85.00 0.00% 0.00% 0.00%
Chemical Trench at C042 to C047 3.60% 0.00% 0.00% 0.00%
Pre-concrete works 30.00% 0.00% 0.00% 0.00%
Excavation and dewatering 30.00% m3 109.86 109.86 0.00% 0.00% 0.00%
Backfilling and Compaction 20.00% m2 71.50 71.50 0.00% 0.00% 0.00%
Blinding or Lean concrete Pouring 20.00% m3 5.36 5.36 0.00% 0.00% 0.00%
Waterproofing works 20.00% m2 88.00 88.00 0.00% 0.00% 0.00%
Screeding concrete pouring 10.00% m3 1.51 1.51 0.00% 0.00% 0.00%
Concrete works for Raft 25.00% 0.00% 0.00% 0.00%
Steel fixing for Raft with wall kickers 40.00% tons 2868.15 2868.15 0.00% 0.00% 0.00%
Formwork installation for Raft with wall kickers 30.00% m2 33.00 33.00 0.00% 0.00% 0.00%
Inspection and concrete pouring for Raft 20.00% m3 15.13 15.13 0.00% 0.00% 0.00%
Curing and deshuttering for Raft 10.00% m2 33.00 33.00 0.00% 0.00% 0.00%
Concrete works for Walls 35.00% 0.00% 0.00% 0.00%
Chipping and Steel fixing for Walls 30.00% tons 3096.30 3096.30 0.00% 0.00% 0.00%
Formwork installation for Walls 40.00% m2 165.00 165.00 0.00% 0.00% 0.00%
Inspection and concrete pouring for Walls 20.00% m 17.19 17.19 0.00% 0.00% 0.00%
Curing and deshuttering for Walls 10.00% m 33.00 33.00 0.00% 0.00% 0.00%
Post-concrete works 10.00% 0.00% 0.00% 0.00%
Waterproofing works for walls 30.00% m2 96.25 96.25 0.00% 0.00% 0.00%
Backfilling and Compaction 30.00% m3 70.68 70.68 0.00% 0.00% 0.00%
Chipping and Pouring of Sloping screed 30.00% m 55.00 55.00 0.00% 0.00% 0.00%
Installation of Pre-cast / GRP Covers 10.00% m 55.00 55.00 0.00% 0.00% 0.00%

Conctruction of Buried Chemical Trenches PageI 2 of 18


Unit of Scope Completed Remaining
Activities Weight %
Measure Length Width Depth Total Quantity Quantity Quantity
Conctruction of Buried Chemical Trenches 100.00%
CheChemical Trench at C001 to C002 1.67%
Pre-concrete works 30.00%
Excavation and dewatering 30.00% m3 25.00 1.70 1.50 63.75 10 31.875 31.88
Backfilling and Compaction 20.00% m2 25.00 1.30 32.50 20 5 15
Blinding or Lean concrete Pouring 20.00% m 3
25.00 1.30 0.08 2.44 10 5 5
Waterproofing works 20.00% m2 25.00 1.60 40.00 10 5 5
Screeding concrete pouring 10.00% m3 25.00 1.10 0.03 0.69 10 5 5
Concrete works for Raft 25.00%
Steel fixing for Raft with wall kickers 40.00% tons 1468.30 0.89 1305.16 10 5 5
Formwork installation for Raft with wall kickers 30.00% m2 25.00 0.30 15.00 20 5 15
Inspection and concrete pouring for Raft 20.00% m3 25.00 1.10 0.25 6.88 10 5 5
Curing and deshuttering for Raft 10.00% m2 25.00 0.30 15.00 10 5 5
Concrete works for Walls 35.00%
Chipping and Steel fixing for Walls 30.00% tons 1534.40 0.89 1363.91 10 5 5
Formwork installation for Walls 40.00% m2 25.00 1.95 97.50 20 5 15
Inspection and concrete pouring for Walls 20.00% m3 25.00 0.25 0.85 10.63 10 5 5
Curing and deshuttering for Walls 10.00% m2 25.00 1.95 97.50 10 5 5
Post-concrete works 10.00%
Waterproofing works for walls 30.00% m2 25.00 1.10 55.00 10 5 5
Backfilling and Compaction 30.00% m3 43.13 20 5 15
Chipping and Pouring of Sloping screed(Epoxy Coating) 30.00% m 25.00 25.00 10 5 5
Installation of Pre-cast / GRP Covers 10.00% m 25.00 25.00 10 5 5
CheChemical Trench at C002 to C003 2.00%
Pre-concrete works 30.00%
Excavation and dewatering 30.00% m3 30.00 1.70 1.70 86.70 10 5 5
Backfilling and Compaction 20.00% m2 30.00 1.30 39.00 20 5 15
Blinding or Lean concrete Pouring 20.00% m3 30.00 1.30 0.08 5.85 10 5 5
Waterproofing works 20.00% m2 30.00 1.60 48.00 10 5 5
Screeding concrete pouring 10.00% m3 30.00 1.10 0.03 1.98 10 5 5
Concrete works for Raft 25.00%
Steel fixing for Raft with wall kickers 40.00% tons 1760.00 0.89 1564.44 10 5 5
Formwork installation for Raft with wall kickers 30.00% m2 30.00 0.30 18.00 20 5 15
Inspection and concrete pouring for Raft 20.00% m3 30.00 1.10 0.25 8.25 10 5 5
Curing and deshuttering for Raft 10.00% m2 30.00 0.30 18.00 10 5 5
Concrete works for Walls 35.00%
Chipping and Steel fixing for Walls 30.00% tons 1840.00 0.89 1637.60 10 5 5
Formwork installation for Walls 40.00% m2 30.00 1.95 117.00 20 5 15
Inspection and concrete pouring for Walls 20.00% m 3
30.00 0.25 0.85 6.38 10 5 5
Curing and deshuttering for Walls 10.00% m2 30.00 1.10 66.00 10 5 5
Post-concrete works 10.00%
Waterproofing works for walls 30.00% m2 30.00 1.10 66.00 10 5 5
Backfilling and Compaction 30.00% m3 64.25 20 5 15
Chipping and Pouring of Sloping screed(Epoxy Coating) 30.00% m 30.00 30.00 10 5 5
Installation of Pre-cast / GRP Covers 10.00% m 30.00 30.00 10 5 5
CheChemical Trench at C003 to C004 0.67%
Pre-concrete works 30.00%
Excavation and dewatering 30.00% m3 10.00 1.70 1.70 28.90 10 5 5
Backfilling and Compaction 20.00% m2 10.00 1.30 13.00 20 5 15
Blinding or Lean concrete Pouring 20.00% m 3
10.00 1.30 0.08 1.95 10 5 5
Waterproofing works 20.00% m2 10.00 1.60 16.00 10 5 5
Screeding concrete pouring 10.00% m 3
10.00 1.10 0.03 0.66 10 5 5
Concrete works for Raft 25.00%
Steel fixing for Raft with wall kickers 40.00% tons 588.30 0.89 522.93 10 5 5
Formwork installation for Raft with wall kickers 30.00% m2 10.00 0.30 6.00 20 5 15
Inspection and concrete pouring for Raft 20.00% m3 10.00 1.10 0.25 2.75 10 5 5
Curing and deshuttering for Raft 10.00% m2 10.00 0.30 6.00 10 5 5
Concrete works for Walls 35.00%
Chipping and Steel fixing for Walls 30.00% tons 614.40 0.89 546.82 10 5 5
Formwork installation for Walls 40.00% m2 10.00 1.95 39.00 20 5 15
Inspection and concrete pouring for Walls 20.00% m3 10.00 0.25 0.85 2.13 10 5 5
Curing and deshuttering for Walls 10.00% m2 10.00 1.10 22.00 10 5 5
Post-concrete works 10.00%
Waterproofing works for walls 30.00% m2 10.00 1.10 22.00 10 5 5
Backfilling and Compaction 30.00% m3 21.42 20 5 15
Chipping and Pouring of Sloping screed(Epoxy Coating) 30.00% m 10.00 10.00 10 5 5
Installation of Pre-cast / GRP Covers 10.00% m 10.00 10.00 10 5 5
CheChemical Trench at C004 to C005 1.67%
Pre-concrete works 30.00%
Excavation and dewatering 30.00% m3 25.00 1.70 1.45 61.63 10 5 5
Backfilling and Compaction 20.00% m2 25.00 1.30 32.50 20 5 15
Blinding or Lean concrete Pouring 20.00% m3 25.00 1.30 0.08 2.44 10 5 5
Waterproofing works 20.00% m2 25.00 1.60 40.00 10 5 5
Screeding concrete pouring 10.00% m3 25.00 1.10 0.03 0.69 10 5 5
Concrete works for Raft 25.00%
Steel fixing for Raft with wall kickers 40.00% tons 1468.30 0.89 1305.16 10 5 5
Formwork installation for Raft with wall kickers 30.00% m2 25.00 0.30 15.00 20 5 15
Inspection and concrete pouring for Raft 20.00% m3 25.00 1.10 0.25 6.88 10 5 5
Curing and deshuttering for Raft 10.00% m2 25.00 0.30 15.00 10 5 5
Concrete works for Walls 35.00%
Chipping and Steel fixing for Walls 30.00% tons 1534.40 0.89 1363.91 10 5 5
Formwork installation for Walls 40.00% m2 25.00 1.45 72.50 20 5 15
Inspection and concrete pouring for Walls 20.00% m 3
25.00 0.25 0.60 7.50 10 5 5
Curing and deshuttering for Walls 10.00% m2 25.00 0.85 42.50 10 5 5
Post-concrete works 10.00%
Waterproofing works for walls 30.00% m2 25.00 0.85 42.50 10 5 5
Backfilling and Compaction 30.00% m3 44.13 20 5 15
Chipping and Pouring of Sloping screed(Epoxy Coating) 30.00% m 25.00 25.00 10 5 5
Installation of Pre-cast / GRP Covers 10.00% m 25.00 25.00 10 5 5
CheChemical Trench at C004 to C006 3.00%
Pre-concrete works 30.00%
Excavation and dewatering 30.00% m3 45.00 1.70 1.85 141.53 10 5 5
Backfilling and Compaction 20.00% m2 45.00 1.30 58.50 20 5 15
Blinding or Lean concrete Pouring 20.00% m3 45.00 1.30 0.08 4.39 10 5 5
Waterproofing works 20.00% m2 45.00 1.60 72.00 10 5 5
Screeding concrete pouring 10.00% m3 45.00 1.10 0.03 1.24 10 5 5
Concrete works for Raft 25.00%
Steel fixing for Raft with wall kickers 40.00% tons 2640.00 0.89 2346.67 10 5 5
Formwork installation for Raft with wall kickers 30.00% m2 45.00 0.30 27.00 20 5 15
Inspection and concrete pouring for Raft 20.00% m3 45.00 1.10 0.25 12.38 10 5 5
Curing and deshuttering for Raft 10.00% m2 45.00 0.30 27.00 10 5 5
Concrete works for Walls 35.00%
Chipping and Steel fixing for Walls 30.00% tons 2850.00 0.89 2533.33 10 5 5
Formwork installation for Walls 40.00% m2 45.00 2.25 202.50 20 5 15
Inspection and concrete pouring for Walls 20.00% m 3
45.00 0.25 1.00 11.25 10 5 5
Curing and deshuttering for Walls 10.00% m2 45.00 0.30 27.00 10 5 5
Post-concrete works 10.00%
Waterproofing works for walls 30.00% m2 45.00 1.25 112.50 10 5 5
Backfilling and Compaction 30.00% m3 112.28 20 5 15
Chipping and Pouring of Sloping screed(Epoxy Coating) 30.00% m 45.00 45.00 10 5 5
Installation of Pre-cast / GRP Covers 10.00% m 45.00 45.00 10 5 5
CheChemical Trench at C006 to C009 6.33%
Pre-concrete works 30.00%
Excavation and dewatering 30.00% m3 95.00 1.70 1.85 298.78 10 5 5
Backfilling and Compaction 20.00% m2 95.00 1.30 123.50 20 5 15
Blinding or Lean concrete Pouring 20.00% m 3
95.00 1.30 0.08 9.26 10 5 5
Waterproofing works 20.00% m2 95.00 1.60 152.00 10 5 5
Screeding concrete pouring 10.00% m 3
95.00 1.10 0.03 2.61 10 5 5
Concrete works for Raft 25.00%
Steel fixing for Raft with wall kickers 40.00% tons 5573.33 0.89 4954.07 10 5 5
Formwork installation for Raft with wall kickers 30.00% m2 95.00 0.30 57.00 20 5 15
Inspection and concrete pouring for Raft 20.00% m3 95.00 1.10 0.25 26.13 10 5 5
Curing and deshuttering for Raft 10.00% m2 95.00 0.30 57.00 10 5 5
Concrete works for Walls 35.00%
Chipping and Steel fixing for Walls 30.00% tons 6016.67 0.89 5348.15 10 5 5
Formwork installation for Walls 40.00% m2 95.00 2.25 427.50 20 5 15
Inspection and concrete pouring for Walls 20.00% m3 95.00 0.25 1.00 23.75 10 5 5
Curing and deshuttering for Walls 10.00% m2 95.00 0.30 57.00 10 5 5
Post-concrete works 10.00%
Waterproofing works for walls 30.00% m2 95.00 1.25 237.50 10 5 5
Backfilling and Compaction 30.00% m3 237.03 20 5 15
Chipping and Pouring of Sloping screed(Epoxy Coating) 30.00% m 95.00 95.00 10 5 5
Installation of Pre-cast / GRP Covers 10.00% m 95.00 95.00 10 5 5
CheChemical Trench at C009 to C012 5.87%
Pre-concrete works 30.00%
Excavation and dewatering 30.00% m3 88.00 1.70 1.20 179.67 10 5 5
Backfilling and Compaction 20.00% m2 88.00 1.30 114.40 20 5 15
Blinding or Lean concrete Pouring 20.00% m3 88.00 1.30 0.08 8.58 10 5 5
Waterproofing works 20.00% m2 88.00 1.60 140.80 10 5 5
Screeding concrete pouring 10.00% m3 88.00 1.10 0.03 2.42 10 5 5
Concrete works for Raft 25.00%
Steel fixing for Raft with wall kickers 40.00% tons 5162.67 0.89 4589.04 10 5 5
Formwork installation for Raft with wall kickers 30.00% m2 88.00 0.30 52.80 20 5 15
Inspection and concrete pouring for Raft 20.00% m3 88.00 1.10 0.25 24.20 10 5 5
Curing and deshuttering for Raft 10.00% m2 88.00 0.30 52.80 10 5 5
Concrete works for Walls 35.00%
Chipping and Steel fixing for Walls 30.00% tons 5573.33 0.89 4954.07 10 5 5
Formwork installation for Walls 40.00% m2 88.00 1.55 272.80 20 5 15
Inspection and concrete pouring for Walls 20.00% m 3
88.00 0.25 0.65 14.30 10 5 5
Curing and deshuttering for Walls 10.00% m2 88.00 0.30 52.80 10 5 5
Post-concrete works 10.00%
Waterproofing works for walls 30.00% m 2
88.00 0.90 158.58 10 5 5
Backfilling and Compaction 30.00% m3 130.17 20 5 15
Chipping and Pouring of Sloping screed(Epoxy Coating) 30.00% m 88.00 88.00 10 5 5
Installation of Pre-cast / GRP Covers 10.00% m 88.00 88.00 10 5 5
CheChemical Trench at C009 to C015 7.67%
Pre-concrete works 30.00%
Excavation and dewatering 30.00% m3 115.00 2.10 1.85 446.78 10 5 5
Backfilling and Compaction 20.00% m2 115.00 1.70 195.50 20 5 15
Blinding or Lean concrete Pouring 20.00% m 3
115.00 1.70 0.08 14.66 10 5 5
Waterproofing works 20.00% m2 115.00 2.00 230.00 10 5 5
Screeding concrete pouring 10.00% m 3
115.00 1.50 0.03 4.31 10 5 5
Concrete works for Raft 25.00%
Steel fixing for Raft with wall kickers 40.00% tons 6746.67 0.89 5997.04 10 5 5
Formwork installation for Raft with wall kickers 30.00% m2 115.00 0.30 69.00 20 5 15
Inspection and concrete pouring for Raft 20.00% m3 115.00 1.10 0.25 31.63 10 5 5
Curing and deshuttering for Raft 10.00% m2 115.00 0.30 69.00 10 5 5
Concrete works for Walls 35.00%
Chipping and Steel fixing for Walls 30.00% tons 6653.33 0.89 5914.07 10 5 5
Formwork installation for Walls 40.00% m2 115.00 2.25 517.50 20 5 15
Inspection and concrete pouring for Walls 20.00% m3 115.00 0.25 2.00 57.50 10 5 5
Curing and deshuttering for Walls 10.00% m2 115.00 0.30 69.00 10 5 5
Post-concrete works 10.00%
Waterproofing works for walls 30.00% m2 115.00 1.25 287.50 10 5 5
Backfilling and Compaction 30.00% m3 338.68 20 5 15
Chipping and Pouring of Sloping screed(Epoxy Coating) 30.00% m 115.00 115.00 10 5 5
Installation of Pre-cast / GRP Covers 10.00% m 115.00 115.00 10 5 5
CheChemical Trench at C015 to C017 2.33%
Pre-concrete works 30.00%
Excavation and dewatering 30.00% m3 35.00 2.60 1.55 141.05 10 5 5
Backfilling and Compaction 20.00% m2 35.00 2.20 77.00 20 5 15
Blinding or Lean concrete Pouring 20.00% m3 35.00 2.20 0.08 5.78 10 5 5
Waterproofing works 20.00% m2 35.00 2.50 87.50 10 5 5
Screeding concrete pouring 10.00% m 3
35.00 2.00 0.03 1.75 10 5 5
Concrete works for Raft 25.00%
Steel fixing for Raft with wall kickers 40.00% tons 2053.33 0.89 1825.19 10 5 5
Formwork installation for Raft with wall kickers 30.00% m2 35.00 0.30 21.00 20 5 15
Inspection and concrete pouring for Raft 20.00% m3 35.00 2.00 0.25 17.50 10 5 5
Curing and deshuttering for Raft 10.00% m2 35.00 0.30 21.00 10 5 5
Concrete works for Walls 35.00%
Chipping and Steel fixing for Walls 30.00% tons 2216.67 0.89 1970.37 10 5 5
Formwork installation for Walls 40.00% m2 35.00 2.25 157.50 20 5 15
Inspection and concrete pouring for Walls 20.00% m3 35.00 0.25 2.00 17.50 10 5 5
Curing and deshuttering for Walls 10.00% m2 35.00 0.30 21.00 10 5 5
Post-concrete works 10.00%
Waterproofing works for walls 30.00% m2 35.00 1.25 87.50 10 5 5
Backfilling and Compaction 30.00% m3 98.53 20 5 15
Chipping and Pouring of Sloping screed(Epoxy Coating) 30.00% m 35.00 35.00 10 5 5
Installation of Pre-cast / GRP Covers 10.00% m 35.00 35.00 10 5 5
CheChemical Trench at C017 to C018 5.33%
Pre-concrete works 30.00%
Excavation and dewatering 30.00% m3 80.00 2.60 1.55 322.40 10 5 5
Backfilling and Compaction 20.00% m2 80.00 2.20 176.00 20 5 15
Blinding or Lean concrete Pouring 20.00% m3 80.00 2.20 0.08 13.20 10 5 5
Waterproofing works 20.00% m2 80.00 2.50 200.00 10 5 5
Screeding concrete pouring 10.00% m3 80.00 2.00 0.03 4.00 10 5 5
Concrete works for Raft 25.00%
Steel fixing for Raft with wall kickers 40.00% tons 4693.33 0.89 4171.85 10 5 5
Formwork installation for Raft with wall kickers 30.00% m2 80.00 0.30 48.00 20 5 15
Inspection and concrete pouring for Raft 20.00% m3 80.00 2.00 0.25 40.00 10 5 5
Curing and deshuttering for Raft 10.00% m2 80.00 0.30 48.00 10 5 5
Concrete works for Walls 35.00%
Chipping and Steel fixing for Walls 30.00% tons 5066.67 0.89 4503.70 10 5 5
Formwork installation for Walls 40.00% m2 80.00 1.55 248.00 20 5 15
Inspection and concrete pouring for Walls 20.00% m 3
80.00 0.25 2.00 40.00 10 5 5
Curing and deshuttering for Walls 10.00% m2 80.00 0.30 48.00 10 5 5
Post-concrete works 10.00%
Waterproofing works for walls 30.00% m 2
80.00 1.25 200.00 10 5 5
Backfilling and Compaction 30.00% m3 225.20 20 5 15
Chipping and Pouring of Sloping screed(Epoxy Coating) 30.00% m 80.00 80.00 10 5 5
Installation of Pre-cast / GRP Covers 10.00% m 80.00 80.00 10 5 5
CheChemical Trench at C018 to C019 1.00%
Pre-concrete works 30.00%
Excavation and dewatering 30.00% m3 15.00 2.60 1.55 60.45 10 5 5
Backfilling and Compaction 20.00% m2 15.00 2.20 33.00 20 5 15
Blinding or Lean concrete Pouring 20.00% m 3
15.00 2.20 0.08 2.48 10 5 5
Waterproofing works 20.00% m2 15.00 2.50 37.50 10 5 5
Screeding concrete pouring 10.00% m 3
15.00 2.00 0.03 0.75 10 5 5
Concrete works for Raft 25.00%
Steel fixing for Raft with wall kickers 40.00% tons 880.00 0.89 782.22 10 5 5
Formwork installation for Raft with wall kickers 30.00% m2 15.00 0.30 9.00 20 5 15
Inspection and concrete pouring for Raft 20.00% m3 15.00 2.00 0.25 7.50 10 5 5
Curing and deshuttering for Raft 10.00% m2 15.00 0.30 9.00 10 5 5
Concrete works for Walls 35.00%
Chipping and Steel fixing for Walls 30.00% tons 950.00 0.89 844.44 10 5 5
Formwork installation for Walls 40.00% m2 15.00 1.55 46.50 20 5 15
Inspection and concrete pouring for Walls 20.00% m3 15.00 0.25 2.00 7.50 10 5 5
Curing and deshuttering for Walls 10.00% m2 15.00 0.30 9.00 10 5 5
Post-concrete works 10.00%
Waterproofing works for walls 30.00% m2 15.00 1.25 37.50 10 5 5
Backfilling and Compaction 30.00% m3 42.23 20 5 15
Chipping and Pouring of Sloping screed(Epoxy Coating) 30.00% m 15.00 15.00 10 5 5
Installation of Pre-cast / GRP Covers 10.00% m 15.00 15.00 10 5 5
CheChemical Trench at C019 to C020 3.00%
Pre-concrete works 30.00%
Excavation and dewatering 30.00% m3 45.00 2.60 1.55 181.35 10 5 5
Backfilling and Compaction 20.00% m2 45.00 2.20 99.00 20 5 15
Blinding or Lean concrete Pouring 20.00% m3 45.00 2.20 0.08 7.43 10 5 5
Waterproofing works 20.00% m2 45.00 2.50 112.50 10 5 5
Screeding concrete pouring 10.00% m3 45.00 2.00 0.03 2.25 10 5 5
Concrete works for Raft 25.00%
Steel fixing for Raft with wall kickers 40.00% tons 2640.00 0.89 2346.67 10 5 5
Formwork installation for Raft with wall kickers 30.00% m2 45.00 0.30 27.00 20 5 15
Inspection and concrete pouring for Raft 20.00% m3 45.00 2.00 0.25 22.50 10 5 5
Curing and deshuttering for Raft 10.00% m2 45.00 0.30 27.00 10 5 5
Concrete works for Walls 35.00%
Chipping and Steel fixing for Walls 30.00% tons 2850.00 0.89 2533.33 10 5 5
Formwork installation for Walls 40.00% m2 45.00 1.55 139.50 20 5 15
Inspection and concrete pouring for Walls 20.00% m3 45.00 0.25 2.00 22.50 10 5 5
Curing and deshuttering for Walls 10.00% m2 45.00 0.30 27.00 10 5 5
Post-concrete works 10.00%
Waterproofing works for walls 30.00% m 2
45.00 1.25 112.50 10 5 5
Backfilling and Compaction 30.00% m3 126.68 20 5 15
Chipping and Pouring of Sloping screed(Epoxy Coating) 30.00% m 45.00 45.00 10 5 5
Installation of Pre-cast / GRP Covers 10.00% m 45.00 45.00 10 5 5
CheChemical Trench at C021 to C022 1.00%
Pre-concrete works 30.00%
Excavation and dewatering 30.00% m3 15.00 2.10 1.30 40.95 10 5 5
Backfilling and Compaction 20.00% m2 15.00 1.70 25.50 20 5 15
Blinding or Lean concrete Pouring 20.00% m 3
15.00 1.70 0.08 1.91 10 5 5
Waterproofing works 20.00% m2 15.00 2.00 30.00 10 5 5
Screeding concrete pouring 10.00% m3 15.00 1.50 0.03 0.56 10 5 5
Concrete works for Raft 25.00%
Steel fixing for Raft with wall kickers 40.00% tons 880.00 0.89 782.22 10 5 5
Formwork installation for Raft with wall kickers 30.00% m2 15.00 0.30 9.00 20 5 15
Inspection and concrete pouring for Raft 20.00% m3 15.00 1.50 0.25 5.63 10 5 5
Curing and deshuttering for Raft 10.00% m2 15.00 0.30 9.00 10 5 5
Concrete works for Walls 35.00%
Chipping and Steel fixing for Walls 30.00% tons 950.00 0.89 844.44 10 5 5
Formwork installation for Walls 40.00% m2 15.00 1.55 46.50 20 5 15
Inspection and concrete pouring for Walls 20.00% m 3
15.00 0.25 1.50 5.63 10 5 5
Curing and deshuttering for Walls 10.00% m2 15.00 0.30 9.00 10 5 5
Post-concrete works 10.00%
Waterproofing works for walls 30.00% m 2
15.00 1.00 30.00 10 5 5
Backfilling and Compaction 30.00% m3 27.23 20 5 15
Chipping and Pouring of Sloping screed(Epoxy Coating) 30.00% m 15.00 15.00 10 5 5
Installation of Pre-cast / GRP Covers 10.00% m 15.00 15.00 10 5 5
CheChemical Trench at C021 to C023 9.67%
Pre-concrete works 30.00%
Excavation and dewatering 30.00% m3 145.00 2.10 1.55 471.98 10 5 5
Backfilling and Compaction 20.00% m2 145.00 1.70 246.50 20 5 15
Blinding or Lean concrete Pouring 20.00% m3 145.00 1.70 0.08 18.49 10 5 5
Waterproofing works 20.00% m2 145.00 2.00 290.00 10 5 5
Screeding concrete pouring 10.00% m 3
145.00 1.50 0.03 5.44 10 5 5
Concrete works for Raft 25.00%
Steel fixing for Raft with wall kickers 40.00% tons 8506.67 0.89 7561.48 10 5 5
Formwork installation for Raft with wall kickers 30.00% m2 145.00 0.30 87.00 20 5 15
Inspection and concrete pouring for Raft 20.00% m3 145.00 1.50 0.25 54.38 10 5 5
Curing and deshuttering for Raft 10.00% m2 145.00 0.30 87.00 10 5 5
Concrete works for Walls 35.00%
Chipping and Steel fixing for Walls 30.00% tons 9183.33 0.89 8162.96 10 5 5
Formwork installation for Walls 40.00% m2 145.00 2.25 652.50 20 5 15
Inspection and concrete pouring for Walls 20.00% m3 145.00 0.25 2.00 72.50 10 5 5
Curing and deshuttering for Walls 10.00% m2 145.00 0.30 87.00 10 5 5
Post-concrete works 10.00%
Waterproofing works for walls 30.00% m2 145.00 1.00 290.00 10 5 5
Backfilling and Compaction 30.00% m3 321.18 20 5 15
Chipping and Pouring of Sloping screed(Epoxy Coating) 30.00% m 145.00 145.00 10 5 5
Installation of Pre-cast / GRP Covers 10.00% m 145.00 145.00 10 5 5
CheChemical Trench at C023 to C024 0.67%
Pre-concrete works 30.00%
Excavation and dewatering 30.00% m3 10.00 1.70 1.20 20.40 10 5 5
Backfilling and Compaction 20.00% m2 10.00 1.30 13.00 20 5 15
Blinding or Lean concrete Pouring 20.00% m3 10.00 1.30 0.08 0.98 10 5 5
Waterproofing works 20.00% m2 10.00 1.60 16.00 10 5 5
Screeding concrete pouring 10.00% m3 10.00 1.10 0.03 0.28 10 5 5
Concrete works for Raft 25.00%
Steel fixing for Raft with wall kickers 40.00% tons 586.67 0.89 521.48 10 5 5
Formwork installation for Raft with wall kickers 30.00% m2 10.00 0.30 6.00 20 5 15
Inspection and concrete pouring for Raft 20.00% m3 10.00 1.10 0.25 2.75 10 5 5
Curing and deshuttering for Raft 10.00% m2 10.00 0.30 6.00 10 5 5
Concrete works for Walls 35.00%
Chipping and Steel fixing for Walls 30.00% tons 633.33 0.89 562.96 10 5 5
Formwork installation for Walls 40.00% m2 10.00 1.55 31.00 20 5 15
Inspection and concrete pouring for Walls 20.00% m3 10.00 0.25 2.00 5.00 10 5 5
Curing and deshuttering for Walls 10.00% m2 10.00 0.30 6.00 10 5 5
Post-concrete works 10.00%
Waterproofing works for walls 30.00% m 2
10.00 0.90 18.00 10 5 5
Backfilling and Compaction 30.00% m3 11.40 20 5 15
Chipping and Pouring of Sloping screed(Epoxy Coating) 30.00% m 10.00 10.00 10 5 5
Installation of Pre-cast / GRP Covers 10.00% m 10.00 10.00 10 5 5
CheChemical Trench at C025 to C026 0.67%
Pre-concrete works 30.00%
Excavation and dewatering 30.00% m3 10.00 1.70 1.20 20.40 10 5 5
Backfilling and Compaction 20.00% m2 10.00 1.30 13.00 20 5 15
Blinding or Lean concrete Pouring 20.00% m3 10.00 1.30 0.08 0.98 10 5 5
Waterproofing works 20.00% m2 10.00 1.60 16.00 10 5 5
Screeding concrete pouring 10.00% m 3
10.00 1.10 0.03 0.28 10 5 5
Concrete works for Raft 25.00%
Steel fixing for Raft with wall kickers 40.00% tons 586.67 0.89 521.48 10 5 5
Formwork installation for Raft with wall kickers 30.00% m2 10.00 0.30 6.00 20 5 15
Inspection and concrete pouring for Raft 20.00% m 3
10.00 1.10 0.25 2.75 10 5 5
Curing and deshuttering for Raft 10.00% m2 10.00 0.30 6.00 10 5 5
Concrete works for Walls 35.00%
Chipping and Steel fixing for Walls 30.00% tons 633.33 0.89 562.96 10 5 5
Formwork installation for Walls 40.00% m2 10.00 1.55 31.00 20 5 15
Inspection and concrete pouring for Walls 20.00% m3 10.00 0.25 1.20 3.00 10 5 5
Curing and deshuttering for Walls 10.00% m2 10.00 0.30 6.00 10 5 5
Post-concrete works 10.00%
Waterproofing works for walls 30.00% m2 10.00 0.90 18.00 10 5 5
Backfilling and Compaction 30.00% m3 13.40 20 5 15
Chipping and Pouring of Sloping screed(Epoxy Coating) 30.00% m 10.00 10.00 10 5 5
Installation of Pre-cast / GRP Covers 10.00% m 10.00 10.00 10 5 5
CheChemical Trench at C025 to C027 6.67%
Pre-concrete works 30.00%
Excavation and dewatering 30.00% m3 100.00 2.10 1.20 252.00 10 5 5
Backfilling and Compaction 20.00% m2 100.00 1.70 170.00 20 5 15
Blinding or Lean concrete Pouring 20.00% m3 100.00 1.70 0.08 12.75 10 5 5
Waterproofing works 20.00% m2 100.00 2.00 200.00 10 5 5
Screeding concrete pouring 10.00% m3 100.00 1.50 0.03 3.75 10 5 5
Concrete works for Raft 25.00%
Steel fixing for Raft with wall kickers 40.00% tons 5866.67 0.89 5214.81 10 5 5
Formwork installation for Raft with wall kickers 30.00% m2 100.00 0.30 60.00 20 5 15
Inspection and concrete pouring for Raft 20.00% m3 100.00 1.50 0.25 37.50 10 5 5
Curing and deshuttering for Raft 10.00% m2 100.00 0.30 60.00 10 5 5
Concrete works for Walls 35.00%
Chipping and Steel fixing for Walls 30.00% tons 6333.33 0.89 5629.63 10 5 5
Formwork installation for Walls 40.00% m2 100.00 1.55 310.00 20 5 15
Inspection and concrete pouring for Walls 20.00% m3 100.00 0.25 1.30 32.50 10 5 5
Curing and deshuttering for Walls 10.00% m2 100.00 0.30 60.00 10 5 5
Post-concrete works 10.00%
Waterproofing works for walls 30.00% m2 100.00 0.90 180.00 10 5 5
Backfilling and Compaction 30.00% m3 165.50 20 5 15
Chipping and Pouring of Sloping screed(Epoxy Coating) 30.00% m 100.00 100.00 10 5 5
Installation of Pre-cast / GRP Covers 10.00% m 100.00 100.00 10 5 5
CheChemical Trench at C027 to C030 1.33%
Pre-concrete works 30.00%
Excavation and dewatering 30.00% m3 20.00 1.70 1.20 40.80 10 5 5
Backfilling and Compaction 20.00% m2 20.00 1.30 26.00 20 5 15
Blinding or Lean concrete Pouring 20.00% m3 20.00 1.30 0.08 1.95 10 5 5
Waterproofing works 20.00% m2 20.00 1.60 32.00 10 5 5
Screeding concrete pouring 10.00% m3 20.00 1.10 0.03 0.55 10 5 5
Concrete works for Raft 25.00%
Steel fixing for Raft with wall kickers 40.00% tons 1173.33 0.89 1042.96 10 5 5
Formwork installation for Raft with wall kickers 30.00% m2 20.00 0.30 12.00 20 5 15
Inspection and concrete pouring for Raft 20.00% m3 20.00 1.10 0.25 5.50 10 5 5
Curing and deshuttering for Raft 10.00% m2 20.00 0.30 12.00 10 5 5
Concrete works for Walls 35.00%
Chipping and Steel fixing for Walls 30.00% tons 1266.67 0.89 1125.93 10 5 5
Formwork installation for Walls 40.00% m2 20.00 1.45 58.00 20 5 15
Inspection and concrete pouring for Walls 20.00% m3 20.00 0.25 1.30 6.50 10 5 5
Curing and deshuttering for Walls 10.00% m2 20.00 0.30 12.00 10 5 5
Post-concrete works 10.00%
Waterproofing works for walls 30.00% m 2
20.00 0.90 36.00 10 5 5
Backfilling and Compaction 30.00% m3 26.30 20 5 15
Chipping and Pouring of Sloping screed(Epoxy Coating) 30.00% m 20.00 20.00 10 5 5
Installation of Pre-cast / GRP Covers 10.00% m 20.00 20.00 10 5 5
CheChemical Trench at C030 to C031 1.00%
Pre-concrete works 30.00%
Excavation and dewatering 30.00% m3 15.00 1.70 1.20 30.60 10 5 5
Backfilling and Compaction 20.00% m2 15.00 1.30 19.50 20 5 15
Blinding or Lean concrete Pouring 20.00% m3 15.00 1.30 0.08 1.46 10 5 5
Waterproofing works 20.00% m2 15.00 1.60 24.00 10 5 5
Screeding concrete pouring 10.00% m 3
15.00 1.10 0.03 0.41 10 5 5
Concrete works for Raft 25.00%
Steel fixing for Raft with wall kickers 40.00% tons 880.00 0.89 782.22 10 5 5
Formwork installation for Raft with wall kickers 30.00% m2 15.00 0.30 9.00 20 5 15
Inspection and concrete pouring for Raft 20.00% m 3
15.00 1.10 0.25 4.13 10 5 5
Curing and deshuttering for Raft 10.00% m2 15.00 0.30 9.00 10 5 5
Concrete works for Walls 35.00%
Chipping and Steel fixing for Walls 30.00% tons 950.00 0.89 844.44 10 5 5
Formwork installation for Walls 40.00% m2 15.00 1.45 43.50 20 5 15
Inspection and concrete pouring for Walls 20.00% m3 15.00 0.25 1.30 4.88 10 5 5
Curing and deshuttering for Walls 10.00% m2 15.00 0.30 9.00 10 5 5
Post-concrete works 10.00%
Waterproofing works for walls 30.00% m2 15.00 0.90 27.00 10 5 5
Backfilling and Compaction 30.00% m3 19.73 20 5 15
Chipping and Pouring of Sloping screed(Epoxy Coating) 30.00% m 15.00 15.00 10 5 5
Installation of Pre-cast / GRP Covers 10.00% m 15.00 15.00 10 5 5
CheChemical Trench at C029 to C031 1.47%
Pre-concrete works 30.00%
Excavation and dewatering 30.00% m3 22.00 1.70 1.20 44.88 10 5 5
Backfilling and Compaction 20.00% m2 22.00 1.30 28.60 20 5 15
Blinding or Lean concrete Pouring 20.00% m3 22.00 1.30 0.08 2.15 10 5 5
Waterproofing works 20.00% m2 22.00 1.60 35.20 10 5 5
Screeding concrete pouring 10.00% m3 22.00 1.10 0.03 0.61 10 5 5
Concrete works for Raft 25.00%
Steel fixing for Raft with wall kickers 40.00% tons 1290.67 0.89 1147.26 10 5 5
Formwork installation for Raft with wall kickers 30.00% m2 22.00 0.30 13.20 20 5 15
Inspection and concrete pouring for Raft 20.00% m3 22.00 1.10 0.25 6.05 10 5 5
Curing and deshuttering for Raft 10.00% m2 22.00 0.30 13.20 10 5 5
Concrete works for Walls 35.00%
Chipping and Steel fixing for Walls 30.00% tons 1393.33 0.89 1238.52 10 5 5
Formwork installation for Walls 40.00% m2 22.00 1.45 63.80 20 5 15
Inspection and concrete pouring for Walls 20.00% m3 22.00 0.25 1.30 7.15 10 5 5
Curing and deshuttering for Walls 10.00% m2 22.00 0.30 13.20 10 5 5
Post-concrete works 10.00%
Waterproofing works for walls 30.00% m 2
22.00 0.90 39.60 10 5 5
Backfilling and Compaction 30.00% m3 28.93 20 5 15
Chipping and Pouring of Sloping screed(Epoxy Coating) 30.00% m 22.00 22.00 10 5 5
Installation of Pre-cast / GRP Covers 10.00% m 22.00 22.00 10 5 5
CheChemical Trench at C031 to C032 5.33%
Pre-concrete works 30.00%
Excavation and dewatering 30.00% m3 80.00 1.70 1.20 163.20 10 5 5
Backfilling and Compaction 20.00% m2 80.00 1.30 104.00 20 5 15
Blinding or Lean concrete Pouring 20.00% m3 80.00 1.30 0.08 7.80 10 5 5
Waterproofing works 20.00% m2 80.00 1.60 128.00 10 5 5
Screeding concrete pouring 10.00% m 3
80.00 1.10 0.03 2.20 10 5 5
Concrete works for Raft 25.00%
Steel fixing for Raft with wall kickers 40.00% tons 4693.33 0.89 4171.85 10 5 5
Formwork installation for Raft with wall kickers 30.00% m2 80.00 0.30 48.00 20 5 15
Inspection and concrete pouring for Raft 20.00% m3 80.00 1.10 0.25 22.00 10 5 5
Curing and deshuttering for Raft 10.00% m2 80.00 0.30 48.00 10 5 5
Concrete works for Walls 35.00%
Chipping and Steel fixing for Walls 30.00% tons 5066.67 0.89 4503.70 10 5 5
Formwork installation for Walls 40.00% m2 80.00 1.45 232.00 20 5 15
Inspection and concrete pouring for Walls 20.00% m3 80.00 0.20 1.30 20.80 10 5 5
Curing and deshuttering for Walls 10.00% m2 80.00 0.30 48.00 10 5 5
Post-concrete works 10.00%
Waterproofing works for walls 30.00% m 2
80.00 0.90 144.00 10 5 5
Backfilling and Compaction 30.00% m3 110.40 20 5 15
Chipping and Pouring of Sloping screed(Epoxy Coating) 30.00% m 80.00 80.00 10 5 5
Installation of Pre-cast / GRP Covers 10.00% m 80.00 80.00 10 5 5
CheChemical Trench at C032 to C034 3.00%
Pre-concrete works 30.00%
Excavation and dewatering 30.00% m3 45.00 1.70 1.20 91.80 10 5 5
Backfilling and Compaction 20.00% m2 45.00 1.30 58.50 20 5 15
Blinding or Lean concrete Pouring 20.00% m3 45.00 1.30 0.08 4.39 10 5 5
Waterproofing works 20.00% m2 45.00 1.60 72.00 10 5 5
Screeding concrete pouring 10.00% m3 45.00 1.10 0.03 1.24 10 5 5
Concrete works for Raft 25.00%
Steel fixing for Raft with wall kickers 40.00% tons 2640.00 0.89 2346.67 10 5 5
Formwork installation for Raft with wall kickers 30.00% m2 45.00 0.30 27.00 20 5 15
Inspection and concrete pouring for Raft 20.00% m 3
45.00 1.10 0.25 12.38 10 5 5
Curing and deshuttering for Raft 10.00% m2 45.00 0.30 27.00 10 5 5
Concrete works for Walls 35.00%
Chipping and Steel fixing for Walls 30.00% tons 2850.00 0.89 2533.33 10 5 5
Formwork installation for Walls 40.00% m2 45.00 1.45 130.50 20 5 15
Inspection and concrete pouring for Walls 20.00% m3 45.00 0.25 1.30 14.63 10 5 5
Curing and deshuttering for Walls 10.00% m2 45.00 0.30 27.00 10 5 5
Post-concrete works 10.00%
Waterproofing works for walls 30.00% m2 45.00 0.90 81.00 10 5 5
Backfilling and Compaction 30.00% m3 59.18 20 5 15
Chipping and Pouring of Sloping screed(Epoxy Coating) 30.00% m 45.00 45.00 10 5 5
Installation of Pre-cast / GRP Covers 10.00% m 45.00 45.00 10 5 5
CheChemical Trench at C034 to C036 1.67%
Pre-concrete works 30.00%
Excavation and dewatering 30.00% m3 25.00 1.70 1.20 51.00 10 5 5
Backfilling and Compaction 20.00% m2 25.00 1.30 32.50 20 5 15
Blinding or Lean concrete Pouring 20.00% m3 25.00 1.30 0.08 2.44 10 5 5
Waterproofing works 20.00% m2 25.00 1.60 40.00 10 5 5
Screeding concrete pouring 10.00% m3 25.00 1.10 0.03 0.69 10 5 5
Concrete works for Raft 25.00%
Steel fixing for Raft with wall kickers 40.00% tons 1466.67 0.89 1303.70 10 5 5
Formwork installation for Raft with wall kickers 30.00% m2 25.00 0.30 15.00 20 5 15
Inspection and concrete pouring for Raft 20.00% m3 25.00 1.10 0.25 6.88 10 5 5
Curing and deshuttering for Raft 10.00% m2 25.00 0.30 15.00 10 5 5
Concrete works for Walls 35.00%
Chipping and Steel fixing for Walls 30.00% tons 1583.33 0.89 1407.41 10 5 5
Formwork installation for Walls 40.00% m2 25.00 1.45 72.50 20 5 15
Inspection and concrete pouring for Walls 20.00% m3 25.00 0.25 1.30 8.13 10 5 5
Curing and deshuttering for Walls 10.00% m2 25.00 0.30 15.00 10 5 5
Post-concrete works 10.00%
Waterproofing works for walls 30.00% m 2
25.00 0.90 45.00 10 5 5
Backfilling and Compaction 30.00% m3 32.88 20 5 15
Chipping and Pouring of Sloping screed(Epoxy Coating) 30.00% m 25.00 25.00 10 5 5
Installation of Pre-cast / GRP Covers 10.00% m 25.00 25.00 10 5 5
CheChemical Trench at C034 to C037 1.67%
Pre-concrete works 30.00%
Excavation and dewatering 30.00% m3 25.00 2.10 1.20 63.00 10 5 5
Backfilling and Compaction 20.00% m2 25.00 1.70 42.50 20 5 15
Blinding or Lean concrete Pouring 20.00% m3 25.00 1.70 0.08 3.19 10 5 5
Waterproofing works 20.00% m2 25.00 2.00 50.00 10 5 5
Screeding concrete pouring 10.00% m3 25.00 1.50 0.03 0.94 10 5 5
Concrete works for Raft 25.00%
Steel fixing for Raft with wall kickers 40.00% tons 1466.67 0.89 1303.70 10 5 5
Formwork installation for Raft with wall kickers 30.00% m2 25.00 0.30 15.00 20 5 15
Inspection and concrete pouring for Raft 20.00% m 3
25.00 1.50 0.25 9.38 10 5 5
Curing and deshuttering for Raft 10.00% m2 25.00 0.30 15.00 10 5 5
Concrete works for Walls 35.00%
Chipping and Steel fixing for Walls 30.00% tons 1583.33 0.89 1407.41 10 5 5
Formwork installation for Walls 40.00% m2 25.00 1.55 77.50 20 5 15
Inspection and concrete pouring for Walls 20.00% m3 25.00 0.25 2.00 12.50 10 5 5
Curing and deshuttering for Walls 10.00% m2 25.00 0.30 15.00 10 5 5
Post-concrete works 10.00%
Waterproofing works for walls 30.00% m2 25.00 0.90 45.00 10 5 5
Backfilling and Compaction 30.00% m3 37.00 20 5 15
Chipping and Pouring of Sloping screed(Epoxy Coating) 30.00% m 25.00 25.00 10 5 5
Installation of Pre-cast / GRP Covers 10.00% m 25.00 25.00 10 5 5
CheChemical Trench at C037 to C038 0.33%
Pre-concrete works 30.00%
Excavation and dewatering 30.00% m3 5.00 2.10 1.05 11.03 10 5 5
Backfilling and Compaction 20.00% m2 5.00 1.70 8.50 20 5 15
Blinding or Lean concrete Pouring 20.00% m3 5.00 1.70 0.08 0.64 10 5 5
Waterproofing works 20.00% m2 5.00 2.00 10.00 10 5 5
Screeding concrete pouring 10.00% m3 5.00 1.50 0.03 0.19 10 5 5
Concrete works for Raft 25.00%
Steel fixing for Raft with wall kickers 40.00% tons 293.33 0.89 260.74 10 5 5
Formwork installation for Raft with wall kickers 30.00% m2 5.00 0.30 3.00 20 5 15
Inspection and concrete pouring for Raft 20.00% m 3
5.00 1.50 0.25 1.88 10 5 5
Curing and deshuttering for Raft 10.00% m2 5.00 0.30 3.00 10 5 5
Concrete works for Walls 35.00%
Chipping and Steel fixing for Walls 30.00% tons 316.67 0.89 281.48 10 5 5
Formwork installation for Walls 40.00% m2 5.00 1.25 12.50 20 5 15
Inspection and concrete pouring for Walls 20.00% m3 5.00 0.25 1.00 1.25 10 5 5
Curing and deshuttering for Walls 10.00% m2 5.00 0.30 3.00 10 5 5
Post-concrete works 10.00%
Waterproofing works for walls 30.00% m2 5.00 0.75 7.50 10 5 5
Backfilling and Compaction 30.00% m3 7.08 20 5 15
Chipping and Pouring of Sloping screed(Epoxy Coating) 30.00% m 5.00 5.00 10 5 5
Installation of Pre-cast / GRP Covers 10.00% m 5.00 5.00 10 5 5
CheChemical Trench at C037 to C039 0.33%
Pre-concrete works 30.00%
Excavation and dewatering 30.00% m3 5.00 1.70 1.20 10.20 10 5 5
Backfilling and Compaction 20.00% m2 5.00 1.30 6.50 20 5 15
Blinding or Lean concrete Pouring 20.00% m3 5.00 1.30 0.08 0.49 10 5 5
Waterproofing works 20.00% m2 5.00 1.60 8.00 10 5 5
Screeding concrete pouring 10.00% m3 5.00 1.10 0.03 0.14 10 5 5
Concrete works for Raft 25.00%
Steel fixing for Raft with wall kickers 40.00% tons 293.33 0.89 260.74 10 5 5
Formwork installation for Raft with wall kickers 30.00% m2 5.00 0.30 3.00 20 5 15
Inspection and concrete pouring for Raft 20.00% m3 5.00 1.10 0.25 1.38 10 5 5
Curing and deshuttering for Raft 10.00% m2 5.00 0.30 3.00 10 5 5
Concrete works for Walls 35.00%
Chipping and Steel fixing for Walls 30.00% tons 316.67 0.89 281.48 10 5 5
Formwork installation for Walls 40.00% m2 5.00 1.45 14.50 20 5 15
Inspection and concrete pouring for Walls 20.00% m3 5.00 0.25 1.30 1.63 10 5 5
Curing and deshuttering for Walls 10.00% m2 5.00 0.30 3.00 10 5 5
Post-concrete works 10.00%
Waterproofing works for walls 30.00% m2 5.00 0.90 9.00 10 5 5
Backfilling and Compaction 30.00% m3 6.58 20 5 15
Chipping and Pouring of Sloping screed(Epoxy Coating) 30.00% m 5.00 5.00 10 5 5
Installation of Pre-cast / GRP Covers 10.00% m 5.00 5.00 10 5 5
CheChemical Trench at C017 to C040 5.33%
Pre-concrete works 30.00%
Excavation and dewatering 30.00% m3 80.00 2.10 1.55 260.40 10 5 5
Backfilling and Compaction 20.00% m2 80.00 1.70 136.00 20 5 15
Blinding or Lean concrete Pouring 20.00% m3 80.00 1.70 0.08 10.20 10 5 5
Waterproofing works 20.00% m2 80.00 2.00 160.00 10 5 5
Screeding concrete pouring 10.00% m3 80.00 1.50 0.03 3.00 10 5 5
Concrete works for Raft 25.00%
Steel fixing for Raft with wall kickers 40.00% tons 4693.33 0.89 4171.85 10 5 5
Formwork installation for Raft with wall kickers 30.00% m2 80.00 0.30 48.00 20 5 15
Inspection and concrete pouring for Raft 20.00% m 3
80.00 1.50 0.25 30.00 10 5 5
Curing and deshuttering for Raft 10.00% m2 80.00 0.30 48.00 10 5 5
Concrete works for Walls 35.00%
Chipping and Steel fixing for Walls 30.00% tons 5066.67 0.89 4503.70 10 5 5
Formwork installation for Walls 40.00% m2 80.00 2.25 360.00 20 5 15
Inspection and concrete pouring for Walls 20.00% m3 80.00 0.25 2.00 40.00 10 5 5
Curing and deshuttering for Walls 10.00% m2 80.00 0.30 48.00 10 5 5
Post-concrete works 10.00%
Waterproofing works for walls 30.00% m2 80.00 1.25 200.00 10 5 5
Backfilling and Compaction 30.00% m3 177.20 20 5 15
Chipping and Pouring of Sloping screed(Epoxy Coating) 30.00% m 80.00 80.00 10 5 5
Installation of Pre-cast / GRP Covers 10.00% m 80.00 80.00 10 5 5
CheChemical Trench at C040 to C041 0.33%
Pre-concrete works 30.00%
Excavation and dewatering 30.00% m3 5.00 1.70 1.55 13.18 10 5 5
Backfilling and Compaction 20.00% m2 5.00 1.30 6.50 20 5 15
Blinding or Lean concrete Pouring 20.00% m3 5.00 1.30 0.08 0.49 10 5 5
Waterproofing works 20.00% m2 5.00 1.60 8.00 10 5 5
Screeding concrete pouring 10.00% m3 5.00 1.10 0.03 0.14 10 5 5
Concrete works for Raft 25.00%
Steel fixing for Raft with wall kickers 40.00% tons 293.33 0.89 260.74 10 5 5
Formwork installation for Raft with wall kickers 30.00% m2 5.00 0.30 3.00 20 5 15
Inspection and concrete pouring for Raft 20.00% m3 5.00 1.10 0.25 1.38 10 5 5
Curing and deshuttering for Raft 10.00% m2 5.00 0.30 3.00 10 5 5
Concrete works for Walls 35.00%
Chipping and Steel fixing for Walls 30.00% tons 316.67 0.89 281.48 10 5 5
Formwork installation for Walls 40.00% m2 5.00 2.25 22.50 20 5 15
Inspection and concrete pouring for Walls 20.00% m3 5.00 0.25 2.00 2.50 10 5 5
Curing and deshuttering for Walls 10.00% m2 5.00 0.30 3.00 10 5 5
Post-concrete works 10.00%
Waterproofing works for walls 30.00% m2 5.00 1.25 12.50 10 5 5
Backfilling and Compaction 30.00% m3 8.68 20 5 15
Chipping and Pouring of Sloping screed(Epoxy Coating) 30.00% m 5.00 5.00 10 5 5
Installation of Pre-cast / GRP Covers 10.00% m 5.00 5.00 10 5 5
CheChemical Trench at C040 to C042 2.00%
Pre-concrete works 30.00%
Excavation and dewatering 30.00% m3 30.00 2.10 1.55 97.65 10 5 5
Backfilling and Compaction 20.00% m2 30.00 1.70 51.00 20 5 15
Blinding or Lean concrete Pouring 20.00% m3 30.00 1.70 0.08 3.83 10 5 5
Waterproofing works 20.00% m2 30.00 2.00 60.00 10 5 5
Screeding concrete pouring 10.00% m3 30.00 1.50 0.03 1.13 10 5 5
Concrete works for Raft 25.00%
Steel fixing for Raft with wall kickers 40.00% tons 1760.00 0.89 1564.44 10 5 5
Formwork installation for Raft with wall kickers 30.00% m2 30.00 0.30 18.00 20 5 15
Inspection and concrete pouring for Raft 20.00% m3 30.00 1.50 0.25 11.25 10 5 5
Curing and deshuttering for Raft 10.00% m2 30.00 0.30 18.00 10 5 5
Concrete works for Walls 35.00%
Chipping and Steel fixing for Walls 30.00% tons 1900.00 0.89 1688.89 10 5 5
Formwork installation for Walls 40.00% m2 30.00 2.25 135.00 20 5 15
Inspection and concrete pouring for Walls 20.00% m3 30.00 0.25 2.00 15.00 10 5 5
Curing and deshuttering for Walls 10.00% m2 30.00 0.30 18.00 10 5 5
Post-concrete works 10.00%
Waterproofing works for walls 30.00% m2 30.00 1.25 75.00 10 5 5
Backfilling and Compaction 30.00% m3 66.45 20 5 15
Chipping and Pouring of Sloping screed(Epoxy Coating) 30.00% m 30.00 30.00 10 5 5
Installation of Pre-cast / GRP Covers 10.00% m 30.00 30.00 10 5 5
CheChemical Trench at C043 to C048 7.67%
Pre-concrete works 30.00%
Excavation and dewatering 30.00% m3 115.00 1.70 1.55 303.03 10 5 5
Backfilling and Compaction 20.00% m2 115.00 1.30 149.50 20 5 15
Blinding or Lean concrete Pouring 20.00% m3 115.00 1.30 0.08 11.21 10 5 5
Waterproofing works 20.00% m2 115.00 1.60 184.00 10 5 5
Screeding concrete pouring 10.00% m3 115.00 1.10 0.03 3.16 10 5 5
Concrete works for Raft 25.00%
Steel fixing for Raft with wall kickers 40.00% tons 6746.67 0.89 5997.04 10 5 5
Formwork installation for Raft with wall kickers 30.00% m2 115.00 0.30 69.00 20 5 15
Inspection and concrete pouring for Raft 20.00% m 3
115.00 1.10 0.25 31.63 10 5 5
Curing and deshuttering for Raft 10.00% m2 115.00 0.30 69.00 10 5 5
Concrete works for Walls 35.00%
Chipping and Steel fixing for Walls 30.00% tons 7283.33 0.89 6474.07 10 5 5
Formwork installation for Walls 40.00% m2 115.00 2.25 517.50 20 5 15
Inspection and concrete pouring for Walls 20.00% m3 115.00 0.25 2.00 57.50 10 5 5
Curing and deshuttering for Walls 10.00% m2 115.00 0.30 69.00 10 5 5
Post-concrete works 10.00%
Waterproofing works for walls 30.00% m2 115.00 1.25 287.50 10 5 5
Backfilling and Compaction 30.00% m3 199.53 20 5 15
Chipping and Pouring of Sloping screed(Epoxy Coating) 30.00% m 115.00 115.00 10 5 5
Installation of Pre-cast / GRP Covers 10.00% m 115.00 115.00 10 5 5
CheChemical Trench at C048 to C051 5.67%
Pre-concrete works 30.00%
Excavation and dewatering 30.00% m3 85.00 1.70 1.55 223.98 10 5 5
Backfilling and Compaction 20.00% m2 85.00 1.30 110.50 20 5 15
Blinding or Lean concrete Pouring 20.00% m3 85.00 1.30 0.08 8.29 10 5 5
Waterproofing works 20.00% m2 85.00 1.60 136.00 10 5 5
Screeding concrete pouring 10.00% m3 85.00 1.10 0.03 2.34 10 5 5
Concrete works for Raft 25.00%
Steel fixing for Raft with wall kickers 40.00% tons 4986.67 0.89 4432.59 10 5 5
Formwork installation for Raft with wall kickers 30.00% m2 85.00 0.30 51.00 20 5 15
Inspection and concrete pouring for Raft 20.00% m3 85.00 1.10 0.25 23.38 10 5 5
Curing and deshuttering for Raft 10.00% m2 85.00 0.30 51.00 10 5 5
Concrete works for Walls 35.00%
Chipping and Steel fixing for Walls 30.00% tons 5383.33 0.89 4785.19 10 5 5
Formwork installation for Walls 40.00% m2 85.00 2.25 382.50 20 5 15
Inspection and concrete pouring for Walls 20.00% m3 85.00 0.25 2.00 42.50 10 5 5
Curing and deshuttering for Walls 10.00% m2 85.00 0.30 51.00 10 5 5
Post-concrete works 10.00%
Waterproofing works for walls 30.00% m2 85.00 1.25 212.50 10 5 5
Backfilling and Compaction 30.00% m3 147.48 20 5 15
Chipping and Pouring of Sloping screed(Epoxy Coating) 30.00% m 85.00 85.00 10 5 5
Installation of Pre-cast / GRP Covers 10.00% m 85.00 85.00 10 5 5
CheChemical Trench at C042 to C047 3.67%
Pre-concrete works 30.00%
Excavation and dewatering 30.00% m3 55.00 1.70 1.18 109.86 10 5 5
Backfilling and Compaction 20.00% m2 55.00 1.30 71.50 20 5 15
Blinding or Lean concrete Pouring 20.00% m3 55.00 1.30 0.08 5.36 10 5 5
Waterproofing works 20.00% m2 55.00 1.60 88.00 10 5 5
Screeding concrete pouring 10.00% m3 55.00 1.10 0.03 1.51 10 5 5
Concrete works for Raft 25.00%
Steel fixing for Raft with wall kickers 40.00% tons 3226.67 0.89 2868.15 10 5 5
Formwork installation for Raft with wall kickers 30.00% m2 55.00 0.30 33.00 20 5 15
Inspection and concrete pouring for Raft 20.00% m 3
55.00 1.10 0.25 15.13 10 5 5
Curing and deshuttering for Raft 10.00% m2 55.00 0.30 33.00 10 5 5
Concrete works for Walls 35.00%
Chipping and Steel fixing for Walls 30.00% tons 3483.33 0.89 3096.30 10 5 5
Formwork installation for Walls 40.00% m2 55.00 1.50 165.00 20 5 15
Inspection and concrete pouring for Walls 20.00% m 55.00 0.25 1.25 17.19 10 5 5
Curing and deshuttering for Walls 10.00% m 55.00 0.30 33.00 10 5 5
Post-concrete works 10.00%
Waterproofing works for walls 30.00% m2 55.00 0.88 96.25 10 5 5
Backfilling and Compaction 30.00% m3 70.68 20 5 15
Chipping and Pouring of Sloping screed(Epoxy Coating) 30.00% m 55.00 55.00 10 5 5
Installation of Pre-cast / GRP Covers 10.00% m 55.00 55.00 10 5 5
. . . . . .
.
.
Completion % Remarks
.
42.78% .
66.56% .
125.63% .
318.75% .
25.00% .
50.00% .
50.00% .
50.00% .
42.50% .
50.00% .
25.00% .
50.00% .
50.00% .
40.00% .
50.00% .
25.00% .
50.00% .
50.00% .
42.50% .
50.00% .
25.00% .
50.00% .
50.00% .
42.38% .
45.00% .
50.00% .
25.00% .
50.00% .
50.00% .
50.00% .
42.50% .
50.00% .
25.00% .
50.00% .
50.00% .
40.00% .
50.00% .
25.00% .
50.00% .
50.00% .
42.50% .
50.00% .
25.00% .
50.00% .
50.00% .
42.38% .
45.00% .
50.00% .
25.00% .
50.00% .
50.00% .
50.00% .
42.50% .
50.00% .
25.00% .
50.00% .
50.00% .
40.00% .
50.00% .
25.00% .
50.00% .
50.00% .
42.50% .
50.00% .
25.00% .
50.00% .
50.00% .
42.38% .
45.00% .
50.00% .
25.00% .
50.00% .
50.00% .
50.00% .
42.50% .
50.00% .
25.00% .
50.00% .
50.00% .
40.00% .
50.00% .
25.00% .
50.00% .
50.00% .
42.50% .
50.00% .
25.00% .
50.00% .
50.00% .
42.38% .
45.00% .
50.00% .
25.00% .
50.00% .
50.00% .
50.00% .
42.50% .
50.00% .
25.00% .
50.00% .
50.00% .
40.00% .
50.00% .
25.00% .
50.00% .
50.00% .
42.50% .
50.00% .
25.00% .
50.00% .
50.00% .
42.38% .
45.00% .
50.00% .
25.00% .
50.00% .
50.00% .
50.00% .
42.50% .
50.00% .
25.00% .
50.00% .
50.00% .
40.00% .
50.00% .
25.00% .
50.00% .
50.00% .
42.50% .
50.00% .
25.00% .
50.00% .
50.00% .
42.38% .
45.00% .
50.00% .
25.00% .
50.00% .
50.00% .
50.00% .
42.50% .
50.00% .
25.00% .
50.00% .
50.00% .
40.00% .
50.00% .
25.00% .
50.00% .
50.00% .
42.50% .
50.00% .
25.00% .
50.00% .
50.00% .
42.38% .
45.00% .
50.00% .
25.00% .
50.00% .
50.00% .
50.00% .
42.50% .
50.00% .
25.00% .
50.00% .
50.00% .
40.00% .
50.00% .
25.00% .
50.00% .
50.00% .
42.50% .
50.00% .
25.00% .
50.00% .
50.00% .
42.38% .
45.00% .
50.00% .
25.00% .
50.00% .
50.00% .
50.00% .
42.50% .
50.00% .
25.00% .
50.00% .
50.00% .
40.00% .
50.00% .
25.00% .
50.00% .
50.00% .
42.50% .
50.00% .
25.00% .
50.00% .
50.00% .
42.38% .
45.00% .
50.00% .
25.00% .
50.00% .
50.00% .
50.00% .
42.50% .
50.00% .
25.00% .
50.00% .
50.00% .
40.00% .
50.00% .
25.00% .
50.00% .
50.00% .
42.50% .
50.00% .
25.00% .
50.00% .
50.00% .
42.38% .
45.00% .
50.00% .
25.00% .
50.00% .
50.00% .
50.00% .
42.50% .
50.00% .
25.00% .
50.00% .
50.00% .
40.00% .
50.00% .
25.00% .
50.00% .
50.00% .
42.50% .
50.00% .
25.00% .
50.00% .
50.00% .
42.38% .
45.00% .
50.00% .
25.00% .
50.00% .
50.00% .
50.00% .
42.50% .
50.00% .
25.00% .
50.00% .
50.00% .
40.00% .
50.00% .
25.00% .
50.00% .
50.00% .
42.50% .
50.00% .
25.00% .
50.00% .
50.00% .
42.38% .
45.00% .
50.00% .
25.00% .
50.00% .
50.00% .
50.00% .
42.50% .
50.00% .
25.00% .
50.00% .
50.00% .
40.00% .
50.00% .
25.00% .
50.00% .
50.00% .
42.50% .
50.00% .
25.00% .
50.00% .
50.00% .
42.38% .
45.00% .
50.00% .
25.00% .
50.00% .
50.00% .
50.00% .
42.50% .
50.00% .
25.00% .
50.00% .
50.00% .
40.00% .
50.00% .
25.00% .
50.00% .
50.00% .
42.50% .
50.00% .
25.00% .
50.00% .
50.00% .
42.38% .
45.00% .
50.00% .
25.00% .
50.00% .
50.00% .
50.00% .
42.50% .
50.00% .
25.00% .
50.00% .
50.00% .
40.00% .
50.00% .
25.00% .
50.00% .
50.00% .
42.50% .
50.00% .
25.00% .
50.00% .
50.00% .
42.38% .
45.00% .
50.00% .
25.00% .
50.00% .
50.00% .
50.00% .
42.50% .
50.00% .
25.00% .
50.00% .
50.00% .
40.00% .
50.00% .
25.00% .
50.00% .
50.00% .
42.50% .
50.00% .
25.00% .
50.00% .
50.00% .
42.38% .
45.00% .
50.00% .
25.00% .
50.00% .
50.00% .
50.00% .
42.50% .
50.00% .
25.00% .
50.00% .
50.00% .
40.00% .
50.00% .
25.00% .
50.00% .
50.00% .
42.50% .
50.00% .
25.00% .
50.00% .
50.00% .
42.38% .
45.00% .
50.00% .
25.00% .
50.00% .
50.00% .
50.00% .
42.50% .
50.00% .
25.00% .
50.00% .
50.00% .
40.00% .
50.00% .
25.00% .
50.00% .
50.00% .
42.50% .
50.00% .
25.00% .
50.00% .
50.00% .
42.38% .
45.00% .
50.00% .
25.00% .
50.00% .
50.00% .
50.00% .
42.50% .
50.00% .
25.00% .
50.00% .
50.00% .
40.00% .
50.00% .
25.00% .
50.00% .
50.00% .
42.50% .
50.00% .
25.00% .
50.00% .
50.00% .
42.38% .
45.00% .
50.00% .
25.00% .
50.00% .
50.00% .
50.00% .
42.50% .
50.00% .
25.00% .
50.00% .
50.00% .
40.00% .
50.00% .
25.00% .
50.00% .
50.00% .
42.50% .
50.00% .
25.00% .
50.00% .
50.00% .
42.38% .
45.00% .
50.00% .
25.00% .
50.00% .
50.00% .
50.00% .
42.50% .
50.00% .
25.00% .
50.00% .
50.00% .
40.00% .
50.00% .
25.00% .
50.00% .
50.00% .
42.50% .
50.00% .
25.00% .
50.00% .
50.00% .
42.38% .
45.00% .
50.00% .
25.00% .
50.00% .
50.00% .
50.00% .
42.50% .
50.00% .
25.00% .
50.00% .
50.00% .
40.00% .
50.00% .
25.00% .
50.00% .
50.00% .
42.50% .
50.00% .
25.00% .
50.00% .
50.00% .
42.38% .
45.00% .
50.00% .
25.00% .
50.00% .
50.00% .
50.00% .
42.50% .
50.00% .
25.00% .
50.00% .
50.00% .
40.00% .
50.00% .
25.00% .
50.00% .
50.00% .
42.50% .
50.00% .
25.00% .
50.00% .
50.00% .
42.38% .
45.00% .
50.00% .
25.00% .
50.00% .
50.00% .
50.00% .
42.50% .
50.00% .
25.00% .
50.00% .
50.00% .
40.00% .
50.00% .
25.00% .
50.00% .
50.00% .
42.50% .
50.00% .
25.00% .
50.00% .
50.00% .
42.38% .
45.00% .
50.00% .
25.00% .
50.00% .
50.00% .
50.00% .
42.50% .
50.00% .
25.00% .
50.00% .
50.00% .
40.00% .
50.00% .
25.00% .
50.00% .
50.00% .
42.50% .
50.00% .
25.00% .
50.00% .
50.00% .
42.38% .
45.00% .
50.00% .
25.00% .
50.00% .
50.00% .
50.00% .
42.50% .
50.00% .
25.00% .
50.00% .
50.00% .
40.00% .
50.00% .
25.00% .
50.00% .
50.00% .
42.50% .
50.00% .
25.00% .
50.00% .
50.00% .
42.38% .
45.00% .
50.00% .
25.00% .
50.00% .
50.00% .
50.00% .
42.50% .
50.00% .
25.00% .
50.00% .
50.00% .
40.00% .
50.00% .
25.00% .
50.00% .
50.00% .
42.50% .
50.00% .
25.00% .
50.00% .
50.00% .
42.38% .
45.00% .
50.00% .
25.00% .
50.00% .
50.00% .
50.00% .
42.50% .
50.00% .
25.00% .
50.00% .
50.00% .
40.00% .
50.00% .
25.00% .
50.00% .
50.00% .
42.50% .
50.00% .
25.00% .
50.00% .
50.00% .
42.38% .
45.00% .
50.00% .
25.00% .
50.00% .
50.00% .
50.00% .
42.50% .
50.00% .
25.00% .
50.00% .
50.00% .
40.00% .
50.00% .
25.00% .
50.00% .
50.00% .
42.50% .
50.00% .
25.00% .
50.00% .
50.00% .
42.38% .
45.00% .
50.00% .
25.00% .
50.00% .
50.00% .
50.00% .
42.50% .
50.00% .
25.00% .
50.00% .
50.00% .
40.00% .
50.00% .
25.00% .
50.00% .
50.00% .
42.50% .
50.00% .
25.00% .
50.00% .
50.00% .
42.38% .
45.00% .
50.00% .
25.00% .
50.00% .
50.00% .
50.00% .
42.50% .
50.00% .
25.00% .
50.00% .
50.00% .
40.00% .
50.00% .
25.00% .
50.00% .
50.00% .
42.50% .
50.00% .
25.00% .
50.00% .
50.00% .
42.38% .
45.00% .
50.00% .
25.00% .
50.00% .
50.00% .
50.00% .
42.50% .
50.00% .
25.00% .
50.00% .
50.00% .
40.00% .
50.00% .
25.00% .
50.00% .
50.00% .
42.50% .
50.00% .
25.00% .
50.00% .
50.00% .
. . .