Enviro Infra Engineers Ltd

17.5 MLD STP, ZONE-4, Nava Raipur Atal Nagar


Completion Summary
% counting for balance work Since 20th march 2023
Date : 07-04-2023
Respective Quantity balance on Up to Target date of
Structure Up to date Today % achieved
20 March 2023 Yesterday completion
Shuttering (Sqm) 585.24 445.20 435.2 10.00 76.07%
Reinforcement (MT) 11.37 6.60 6.6 0.00 58.05% 15-04-2023
Concrete (Cum) 68.95 6.85 6.851 0.00 9.94%
SPS
Brickwork (cum) 315.00 0.00 0 0 0.00% 30-04-2023
Plaster (Sqm) 702.00 0.00 0 0 0.00% 12-05-2023
Flooring Stones 600.00 0.00 0 0 0.00% 22-05-2023
Shuttering (Sqm) 421.00 219.88 217 2.88 52.23%
Reinforcement (MT) 6.28 5.80 5.7 0.10 92.29% 02-05-2023
PTU
Concrete (Cum) 94.83 53.36 53 0.36 56.27%
Flooring Stones 0 20-05-2023
Shuttering (Sqm) 302.72 62.48 62.48 0 20.64%
Reinforcement (MT) 9.14 3.77 3.32 0.45 41.23%
Chlorine & Concrete (Cum) 47.13 3.80 3.796 0 8.05% 20-05-2023
Tonner Brickwork (cum) 44.90 0.00 0 0 0.00%
Building Plaster (Sqm) 387.20 0.00 0 0 0.00% 30-05-2023
Flooring tiles 0.00 0 0
Flooring Stones 0.00 0 0 10-06-2023

Shuttering (Sqm) 782.32 228.50 208.5 20 29.21%


Reinforcement (MT) 16.03 4.31 4.31 0 26.89%
Rapid Sand
Concrete (Cum) 100.05 0.00 0 0 0.00% 15-05-2023
Filter
Brickwork (cum)
Plaster (Sqm)
Shuttering (Sqm) 364.00 45.00 45 0 12.36%
Reinforcement (MT) 7.30 2.40 2.4 0 32.85%
SBR
Concrete (Cum) 47.85 0.00 0 0.00% 30-04-2023
Component
Brickwork (cum)
Plaster (Sqm)
Shuttering (Sqm) 1200.00 164.55 164.55 0 13.71%
Reinforcement (MT) 11.00 3.25 3.25 0 29.55%
Concrete (Cum) 85.00 6.00 6 0 7.06% 15-05-2023
Brickwork (cum) 0.00 0
TWRPH
Plaster (Sqm) 0.00 0
Flooring Stones 0.00 0
Door 0.00 0
Windows 0.00 0
Shuttering (Sqm) 0.00 0
Reinforcement (MT) 0.00 0
20-06-2023
Enviro Infra Engineers Ltd
17.5 MLD STP, ZONE-4, Nava Raipur Atal Nagar
Completion Summary
% counting for balance work Since 20th march 2023
Date : 07-04-2023
Respective Quantity balance on Up to Target date of
Structure Up to date Today % achieved
20 March 2023 Yesterday completion
Concrete (Cum) 0.00 0 20-06-2023
Dirty
Brickwork (cum) 0.00 0
Backwash
Plaster (Sqm) 0.00 0
Flooring tiles 0.00 0
Flooring Stones 0.00 0
Shuttering (Sqm) 0.00 0
Reinforcement (MT) 0.00 0
Concrete (Cum) 0.00 0
DWPE dosing
Brickwork (cum) 0.00 0
tank
Plaster (Sqm) 0.00 0
Flooring tiles 0.00 0
Flooring Stones 0.00 0
Brickwork (cum) 52.00 48.04 48.04 0 92.38%
Plaster (Sqm) 549.00 213.00 200 13 38.80% 22-04-2023
Blower Flooring tiles 0.00 0
Building Flooring Stones 0.00 0
Door 0.00 0
Windows 0.00 0
Flooring Stones 0.00 0
Admin Block Door 0.00 0
Windows 0.00 0 30-04-2023
Flooring tiles (Sqm) 697.67 0.00 0 0.00%
Wall tiles (Sqm) 204.65 59.88 39.87952 20 29.26%
Staff Quarters Granite (Sqm) 74.42 42.00 36 6 56.44%
Door 0.00 0
Windows 0.00 0 15-05-2023
Brickwork (cum) 18.00 18.00 18 100.00%
Plaster (Sqm) 145.00 145.00 145 100.00%
Toilet Block
Flooring tiles 0.00 0
Flooring Stones 0.00 0 30-04-2023
Campus Filling Compacted soil (Cum) 16000.00 4180.00 4024 156 26.13% 30-07-2023
Internal Road 30-05-2023
ENVIRO INFRA ENGINEERS LTD
17.5 MLD Sewerage Treatment Plant, Nava Raipur Atal Nagar
Date : 07-04-2023
Shuttering Reinforcement
Description of Work Filling M-30 Pouring PCC Brickwork Plaster tiles Contractor Manpower Machinery
Qty Binding (MT)
bracket beam and chhaja shuttering supporting Pankaj Kr Ray
and scaffolding 11
10 0 0
SPS 0 0
0
Total 10.00 0.00 0.00 0.00 0.00 0.00
(Screw conveyer portion) one side 2nos Mushlim Ansari
3
column reinforcement binding & shuttering 2.88 0.1 0

PTU 11
Deshuttering of wall 0 0 0 manas ranjan
Mushlim Ansari
4
Column concrete pouring 2nos (chute location) 0 0 0.36
Total 2.88 0.10 0.36
0 Mushalim Ansari 0
TWRPH 0 0 0
Total 0 0 0 0 0 0 0 36
RSF wall shuttering W1 /W3 first lift up to 2.4m
height , 20 0 Mushalim Ansari 10 134.4
RSF
Wall repairing honeycomb after deshuttering manas Ranjan 2
Total 0 20 0 0 0 0 0
Dirty Backwash
0
Blower Plaster external wall 13 Vijay yadav 9
Total 0 0 0 0 0 0 13
Reinforcement binding in plinth beam 0 0.45 0.00
CTR 0 0 Mushalim Ansari 4
Total 0 0.45 0

Nalla Training Water logging /Dewatering Manas Ranjan 1


1hyva
Soil filling Soil filling resume today 19 trip 182.4 1 excavator 210
Door frame fixing 4nos manas ranjan 3
Putty in walls Nitin Kumar 3
Staff Quarter
Flooring 20 Ganga Prasad 5
Curing Manas Ranjan 0
Anil Kumar
Admin Building Fittings electrical appliances Kushwaha 3
at SBR selector zone 1 basin cleaning
Cleaning/House
complete, second basin cleaning in progress
keeping
Beam breaking Manas Ranjan 6
2 Excavator
Pipeline Pipe laying 40m length and 1 manhole fixing Manas Ranjan 7 1 hydra

Total 182.40 32.88 0.55 0.36 0.00 0.00 13.00 20.00 82


ENVIRO INFRA ENGINEERS LIMITED
17.5 MLD STP ZONE -4 Collection Network
Pipeline Up to Date Progress
Date : 07-04-2023
Manhole Dia of Network Excavation Pipe Laying MH Manhole
Location Back-filling Manhole R-2 Conical Rungs FRP Cover Manpower Machinery Remark
Node Pipe Length (Meter) (Meter) Nos. Base+R1

Today Over all Today Overall Today Overall Today Overall Today overall Today Overall Today Overall Today Overall

17
Rakhi PS to STP-4 1828 1473 200 420
3
STP-3 to Sector 29 1649 1652 200 90
Balco to Khapri 1652 1654 200 60 2

Mini Market 1739 1752 400 420 13


Jungle Safari to
2
khandwa 1274 1276 400 60

EAR towards
6
Khandwa 1340 1346 500 200
Sector 31 Avinash
15
county 1609 1624 500 450

Sector 26 to EAR 1790 1443 600 480 480 480 480 16 0 18 0 15 0 0 0 12 0 0 0


EAR Sector 31 1632 1364 600 60 2

EAR Sector 30 1407 1417 700 300 10


EAR Sector 26 1417 1431 800 460 25 25 20 20 14 1 1 Excavator-1
EAR Sector 26 to 8
18
sector 25 1431 1449 900 318 20 300 20 277.5 40 110 0 8 0 3 0 3 Excavator-2

Total progress 3390 45 805 40 777.5 40 590 118 1 27 0 18 0 0 0 15 0 0 Crane


% Progress till date 24.26% 23.43% 17.78% 22.88% 15.25% 0.00% 12.71% 0.00% 8

Resources at Site
Readings
Machinery Running Hour
Opening Closing
Excavator 1 1972.9 1979.1 6.2
Excavator 2 3042.2 3046.3 4.1
Hydra 5hr
Tractor 3
Manpower Manas Ranjan 8nos