QUANTITY ESTIMATION

GM : Pemindahan kabel & pipa air dari dalam parit Ex-WS dengan WH

No. Description Unit P (m) L (m) T (m) A (M2) V (M3) Subtotal


1 Concrete Cutting M1
Road 8.00 x 2.00
Bike Parking 2.40 x 2.00

2 Wiremesh for Floor Kg


a. Wiremesh for Road
BRC M6 8.00 x 0.40 3.20 1.00
BRC M8 8.00 x 0.40 3.20 1.00
b. Wiremesh for Bike Parking
BRC M6 2.40 x 0.40 0.96 1.00
BRC M8 2.40 x 0.40 0.96 1.00

3 Rebar Kg
Cakar ayam d9; 0,75mL; (Road) 8.00 x 0.40 3.20 6.40
Cakar ayam d9; 0,75mL; (Bike Park) 2.40 x 0.40 0.96 1.92

4 Form Work Ekspose A1 M2


Road 0.40 x 0.25 0.10 1.00

5 Demolition Work ( floor / road ) M3


Road 8.00 x 0.40 0.25 3.20 0.80 1.00
Bike Parking 2.40 x 0.40 0.25 0.96 0.24 1.00
Paving Block 1.40 x 0.40 0.25 0.56 0.14 1.00
Pipe Holes 6" (Perforate) 0.15 0.02 0.003 2.00
Pipe Holes 2" (Perforate) 0.15 0.002 0.0003 2.00

6 Excavation M3
Turf 4.30 x 0.40 0.38 1.72 0.65 1.00
Road 8.00 x 0.40 0.38 3.20 1.22 1.00
Paving Block 1.40 x 0.40 0.38 0.56 0.21 1.00
Bike Parking 2.40 x 0.40 0.38 0.96 0.36 1.00

7 Disposal M3
Road (gravel & sand) 8.00 x 0.40 0.30 3.20 0.96 1.00

8 Install PVC M1
PVC Pipe 2" 8.00 x 4.00

9 Fill Base Coarse ( Class B ) M3


Road (Gravel) 8.00 x 0.40 0.10 3.20 0.32 1.00

10 Sand Fill M3
Road (Sand) 8.00 x 0.40 0.20 3.20 0.64 1.00
QUANTITY ESTIMATION
GM : Pemindahan kabel & pipa air dari dalam parit Ex-WS dengan WH

No. Description Unit P (m) L (m) T (m) A (M2) V (M3) Subtotal


11 Compaction M3
Road (Sand) 8.00 x 0.40 0.20 3.20 0.64 1.00

12 Back Fill M3
Road (Soil) 8.00 x 0.40 0.08 3.20 0.26 1.00
Turf 4.30 x 0.40 0.38 1.72 0.65 1.00
Paving Block 1.40 x 0.40 0.38 0.56 0.21 1.00
Bike Parking 2.40 x 0.40 0.38 0.96 0.36 1.00

13 Plastic Layer M2
Road 8.00 x 0.40 3.20 1.00

14 Concrete K-225 1B (Normal) M3


Road 8.00 x 0.40 0.25 3.20 0.80 1.00
Bike Parking 2.40 x 0.40 0.25 0.96 0.24 1.00
Paving Block 1.40 x 0.40 0.25 0.56 0.14 1.00

15 Trowel Finish 1 M2
Road 8.00 x 0.40 3.20 1.00

P : Panjang/Length (M)
L : Lebar/Width (M)
T : Tinggi/Height (M)
A : Luas/Area (PxL) (M2)
V : Volume (PxLxT) (M3)
parit Ex-WS dengan WH Date : 9/17/2019
Estimate By : Parindragala
CIVIL

Qty Converse Total Grand Total

1.00 16.00 M1
1.00 4.80 M1
20.80 M1

1.00 3.86 12.35 Kg


1.00 5.45 17.44 Kg

1.00 3.86 3.71 Kg


1.00 5.45 5.23 Kg
38.73 Kg

1.00 0.50 2.40 Kg


1.00 0.50 0.72 Kg
3.12 Kg

2.00 0.20 M2
0.20 M2

1.00 0.80 M3
1.00 0.24 M3
1.00 0.14 M3
1.00 0.01 M3
2.00 0.001 M3
1.19 M3

1.00 0.65 M3
1.00 1.22 M3
1.00 0.21 M3
1.00 0.36 M3
2.45 M3

1.00 0.96 M3
0.96 M3

1.00 32.00 M1
32.00 M1

1.00 0.32 M3
0.32 M3

1.00 0.64 M3
0.64 M3
parit Ex-WS dengan WH Date : 9/17/2019
Estimate By : Parindragala
CIVIL

Qty Converse Total Grand Total

1.00 0.64 M3
0.64 M3

1.00 0.26 M3
1.00 0.65 M4
1.00 0.21 M3
1.00 0.36 M3
1.49 M3

1.00 3.20 M2
3.20 M2

1.00 0.80 M3
1.00 0.24 M3
1.00 0.14 M3
1.18 M3

1.00 3.20 M2
3.20 M2
Form No: EN/F/08
Issue :0

Bill of Quantity
Company : PT. Cunningham Lindsey
Handling Unit : END-CIVIL Date : 17-Sep-19
Work Tracking No.
GM : Pemindahan kabel & pipa air dari dalam parit Ex-WS dengan WH SAP Doc No.
Title

Unit Price (Rp) Price (Rp)


No Work Description Unit Q'ty Remark
Wage Material Wage Material Sub Total

1 Concrete Cutting m' 20.80 85,000 1,768,000 1,768,000 t=5cm or up to BRC (top layer)
2 Wiremesh for Floor kg 38.73 2,000 16,000 77,459 619,674 697,133 deform U50, standart M8 or M6, SNI
3 Rebar kg 3.12 2,500 16,000 7,800 49,920 57,720 deformed bar (U39, SNI)
4 Form Work Ekspose A1 m2 0.20 150,000 30,000 30,000 plywood 12mm, incl.frame, scaffolding & oil form
5 Demolition Work ( floor / road ) m3 1.19 900,000 1,068,017 1,068,017 all floor/road; incl.cleaning; all by contractor
6 Excavation m3 2.45 80,000 195,776 195,776 all by contractor, incl.soil leveling, pave stacking A=1,4mx0,4m
7 Disposal m3 0.96 70,000 67,200 67,200 all by contractor, incl.cleaning area
8 Install PVC m' 32.00 5,000 25,000 160,000 800,000 960,000 dia.2" (WAVIN standard)
9 Fill Base Coarse ( Class B ) m3 0.32 50,000 400,000 16,000 128,000 144,000 all by contractor (batu pecah), t=30cm must compacted
10 Sand Fill m3 0.64 50,000 200,000 32,000 128,000 160,000 all by contractor
11 Compaction m3 0.64 25,000 16,000 16,000 by compactor or vibro roller, incl.leveling soil
12 Back Fill m3 1.49 70,000 104,104 104,104 all by contractor, incl.soil leveling, compacted
13 Plastic Layer m2 3.20 4,000 7,500 12,800 24,000 36,800 polyurethene (black or white)
14 Concrete K-225 1B (Normal) m3 1.18 150,000 1,250,000 177,000 1,475,000 1,652,000 all by contractor, incl.vibrator, curing & delivery
15 Trowel Finish 1 m2 3.20 20,000 64,000 64,000 exclude floor hardener

Total 3,796,156 3,224,594 7,020,749


-

ROUNDED 3,790,000 3,220,000 7,010,000

Ka (wa) Sie Estimator