TAKE OF SHEET

PEKERJAAN BRONJONG

Kabupaten : Padang Lawas Utara Jenis Prasarana : Bronjong


Kecamatan : Dolok Take Of Sheet Lokasi :
Desa : Pasar Sipiongot Volume : 200 M3
Kiri kanan
Potongan I. Pasangan Batu Kali'
Panjang : 32 Mtr V1= ( 0,5 X 2,0 X 16,0 )X 2,0 = 32,0 M3
0,50 mtr V2= ( 0,5 X 1,5 X 16,0 )X 2,0 = 24,0 M3
0,50 mtr V3= ( 0,5 X 1,0 X 16,0 )X 2,0 = 16,0 M3
2,0 mtr 0,50 mtr
V4= ( 0,5 X 1,5 X 16,0 )X 2,0 = 24,0 M3
0,50 mtr
Total 96,0 M3
2,0 mtr

Potongan II Pasangan Batu Kali' Kiri


Panjang : 25 Mtr
V1= ( 0,5 X 2,0 X 25,0 ) X 1,0 = 25,0 M3
1,5 mtr 0,50 mtr V2= ( 0,5 X 1,5 X 25,0 ) X 1,0 = 18,8 M3
0,50 mtr V3= ( 0,5 X 1,0 X 25,0 ) X 1,0 = 12,5 M3
1,50 mtr Total 56,3 M3

Potogan III Pasangan Batu Kali' Kanan


Panjang : 40 Mtr
0,50 mtr V1= ( 0,5 X 2,0 X 20,0 )X 2,0 = 40,0 M3
0,50 mtr V2= ( 0,5 X 1,5 X 20,0 )X 2,0 = 30,0 M3
2.0 mtr 0,50 mtr V3= ( 0,5 X 1,0 X 20,0 )X 2,0 = 20,0 M3
0,50 mtr V4= ( 0,5 X 1,5 X 20,0 )X 2,0 = 30,0 M3
2,0 mtr Total 120,0 M3

Potongan IV Pasangan Batu Kali' Kiri Kanan


Panjang : 50 Mtr
V1= ( 0,5 X 1,5 X 25,0 ) X 2,0 = 37,5 M3
V2= ( 0,5 X 1,0 X 25,0 ) X 2,0 = 25,0 M3
1,0 mtr 0,50 mtr
0,50 mtr
Total 62,5 M3
1,5 Meter

Potongan V
Panjang: 33 Mtr Pasangan Batu Kali' Kiri

V1= ( 0,5 X 1,5 X 33,0 ) X 1,0 = 24,8 M3


1,0 Meter
0,50 mtr V2= ( 0,5 X 1,0 X 33,0 ) X 1,0 = 16,5 M3
1,0 mtr
0,50 mtr
Total 41,3 M3
1,5 Meter

Potongan VI
Panjang: 20 Mtr Pasangan Batu Kali' Kanan

1,5 mtr V1= ( 0,5 X 2,0 X 20,0 )X 1,0 = 20,0 M3


0,50 mtr
0,50 mtr
V2= ( 0,5 X 1,5 X 20,0 )X 1,0 = 15,0 M3
2,0 mtr 0,50 mtr V3= ( 0,5 X 1,0 X 20,0 )X 1,0 = 10,0 M3
0,50 mtr V4= ( 0,5 X 1,5 X 20,0 )X 1,0 = 15,0 M3
Total 60,0 M3
2,00 mtr

Jumlah Total 436,0 M3

Di Buat Oleh :
PAIMAHON HARAHAP
KAUR PEMB. DESA
DAFTAR HARGA BAHAN

Desa : Pasar Sipiongot


Kecamatan : Dolok
Kabupaten : Padang Lawas Utara

Satuan
No Jenis Bahan Transportasi Harga Satuan ( Rp )
Volume

I UPAH
1 Pekerja Anyaman Rp 75.000,00
HOK
2 Pekerja Pemasangan Dan Pengisi Batu Rp 100.000,00

II Bahan Lokal
1 Batu Kali M3 Rp 250.000,00
2 Ijuk M2 Rp 15.000,00
3 Tanah Timbunan M3 Rp 100.000,00

III Bahan Non Lokal


1 Kawat Bronjong 4 mm @ 50 Kg Balt Rp 850.000,00
2 Besi 12 mm Ujg 135.000,00
IV Alat
1 Linggis Buah Rp 75.000,00
2 Sekop Buah Rp 55.000,00
12500
27500 710.000,00 BALT
10.000,00

17.000,00
PANJANG TOTAL : 200 Meter
Pek.Bronjong 4 Trap : 100 Mtr

0,5 1
1.5 Mtr
0,5
1.0 mtr
2,0 0,5
1.0 mtr

2.0 mtr 0,5

2,0
2

Keterangan
Panjang Rencana = 100,00 m
Pek. Bronjong Jumlah Trap = 4,00 bh
tinggi = 0,50 m
lebar = 1,00 m
volume = 2,00 m2
= 200,00 m3
Koporan
tinggi = 0,50 m
lebar = 2,00 m
1,00 m2
volume = 100,00 m3
Total Volume = 300,00 m3

Pek. Timbunan lebar atas = 0,50 m


lebar bawah = 2,00 m
Tinggi = 2,00 m
Perhit = 2,50 m2
volume = 125,00 m3

Pek. Galian Tanah Koporan


Lebar = 2,00 m
Tinggi = 0,50 m
Luas = 1,00 m2
volume = 100,00 m3

Pek Tiang pancang jml batang = 50,00 btg


panjang = 100,00 m
= 25,00 Ujg
Panjang 93 Mtr.
Pek. Lapisan Ijuk = 4x0.5x93 = 200 M2
Vol = 20 Glg
Pek.Bronjong 2 Trap : 50 Mtr
0,5 1

0,5

1,0 0,5
1.0 mtr

1.5 mtr 0,5

1,0
1,5

Keterangan
Panjang Rencana = 50,00 m
Pek. Bronjong Jumlah Trap = 2,00 bh
tinggi = 0,50 m
lebar = 1,00 m
volume = 1,00 m2
= 50,00 m3
Koporan
tinggi = 0,50 m
lebar = 1,50 m
0,75 m2
volume = 37,50 m3
Total Volume = 87,50 m3

Pek. Timbunan lebar atas = 0,50 m


lebar bawah = 1,00 m
Tinggi = 1,00 m
Perhit = 0,75 m2
volume = 18,75 m3

Pek. Galian Tanah Koporan


Lebar = 1,50 m
Tinggi = 0,50 m
Luas = 0,75 m2
volume = 37,50 m3

Pek Tiang pancang jml batang = 25,00 btg


panjang = 50,00 m
= 13,00 Ujg

Panjang 73 Mtr.
Pek. Lapisan Ijuk = 2x0.5x73 = 50 M2
Vol = 5 Glg
Pek.Bronjong 3 Trap : 50 Mtr

0,5 1

0,5
1.5 mtr
1,5 0,5
1.0 mtr

1.50 mtr 0,5

2,0
1,5

Keterangan
Panjang Rencana = 50,00 m
Pek. Bronjong Jumlah Trap = 3,00 bh
tinggi = 0,50 m
lebar = 1,00 m
volume = 1,50 m2
= 75,00 m3
Koporan
tinggi = 0,50 m
lebar = 1,50 m
0,75 m2
volume = 37,50 m3
Total Volume = 112,50 m3

Pek. Timbunan lebar atas = 0,50 m


lebar bawah = 2,00 m
Tinggi = 1,50 m
Perhit = 1,88 m2
volume = 46,88 m3

Pek. Galian Tanah Koporan


Lebar = 1,50 m
Tinggi = 0,50 m
Luas = 0,75 m2
volume = 37,50 m3

Pek Tiang pancang jml batang = 25,00 btg


panjang = 50,00 m
= 13,00 Ujg

Panjang 25 Mtr.
Pek. Lapisan Ijuk = 3x0.5x25 = 75 M2
Vol = 7,5 Glg

REKAPAN PEKERJAAN BRONJONG JLH SATUAN


1 BATU KALI 436,00 M3
2 TIMBUNAN TANAH 190,63 M3
3 GALIAN TANAH KOPORAN 175,00 M3
4 TIANG PANCANG 51,00 UJG Pipa
17,00 UJG Besi 12"
5 IJUK 38,00 GLG
Daftar Analisa Satuan
Pembangunan Bronjong
Desa Pasar Sipiongot

1 Pekerjaan Kawat Bronjong / 6 M3


50 Kg Kawat Bronjong Rp 800.000,00 Rp 160.000,00
1 Hok Pekerja Penganyam Rp 75.000,00 Rp 12.500,00
1 Hok Pekerja Pemasangan Rp 100.000,00 Rp 16.666,67

Jumlah Rp 189.166,67

2 Pekerjaan Pemasangan Ijuk ( M2 )


1 M2 Ijuk Rp 15.000,00 Rp 15.000,00
0,15 Hok Pekerja Rp 75.000,00 Rp 11.250,00

Jumlah Rp 26.250,00

3 Pekerjaan Timbunan Tanah ( M3 )


1 M3 Tanah Timbunan Biasa Rp 100.000,00 Rp 100.000,00
1 Hok Pekerja Rp 75.000,00 Rp 75.000,00

Jumlah Rp 175.000,00

Pasar Sipiongot, Juli 2022


Kaur Pemb. Desa

( Paimahon Harahap )
RENCANA ANGGARAN BIAYA
PEKERJAAN BRONJONG

PROPINSI : SUMATERA UTARA Volume : 200 M3


KABUPATEN : PADANG LAWAS UTARA Kegiatan : Penimbunan Tanah
KECAMATAN : DOLOK
DESA : PASAR SIPIONGOT

URAIAN SATUAN KEBUTUHAN HARGA SATUAN TOTAL BIAYA

BAHAN
1. Timbunan Tanah Biasa M3 190,63 100.000,00 19.062.500,00
2
3
4
5
6
7

ALAT
1. Sekop Buah 5,00 55.000,00 275.000,00
2
3
4
5
6

UPAH
1. Pekerja HOK 190,63 75.000,00 14.296.875,00
2

SUB TOTAL 230.000,00 33.634.375,00


HOK
TOTAL BIAYA 33.634.375,00

Diketahi Oleh : Pasar Sipiongot, Juli 2022


Kepala Desa Pasar Sipiongot Dibuat Oleh :

( Paimahon harahap )
( Muhammad Efendi Harahap ) kaur Pemb. Desa
RENCANA ANGGARAN BIAYA
PEKERJAAN BRONJONG

PROPINSI : SUMATERA UTARA Volume : 200 M3


KABUPATEN : PADANG LAWAS UTARA Kegiatan : Penganyaman dan
KECAMATAN : DOLOK Pengisian Kawat
DESA : PASAR SIPIONGOT Bronjong

URAIAN SATUAN KEBUTUHAN HARGA SATUAN TOTAL BIAYA

BAHAN
1. Kawat Bronjong BALT 34,00 850.000,00 28.900.000
2. Batu Kali M3 436,00 250.000,00 109.000.000
3.Besi 12 " Angker/Pancang Ujg 17,00 135.000,00 2.295.000
4
5
6
7

ALAT
1. Linggis Buah 5,00 75.000,00 375.000
2
3
4
5
6

UPAH
1. Pekerja Penganyam HOK 200,00 75.000,00 15.000.000
2. Pekerja Pemasangan HOK 200,00 100.000,00 20.000.000
dan Pengisi Batu

SUB TOTAL 1.485.000,00 175.570.000,00


HOK
TOTAL BIAYA 175.570.000,00

Diketahi Oleh : Pasar Sipiongot, Juli 2022


Kepala Desa Pasar Sipiongot Dibuat Oleh :

( Paimahon harahap )
( Muhammad Efendi Harahap ) kaur Pemb. Desa
RENCANA ANGGARAN BIAYA

PROPINSI : SUMATERA UTARA Volume : 200 M3


KABUPATEN : PADANG LAWAS UTARA Kegiatan : Pemasangan Ijuk
KECAMATAN : DOLOK
DESA : PASAR SIPIONGOT

URAIAN SATUAN KEBUTUHAN HARGA SATUAN TOTAL BIAYA

BAHAN
1. Ijuk M2 380,00 15.000,00 5.700.000,00
2
3
4
5
6
7

ALAT

2
3
4
5
6

UPAH
1. Pekerja HOK 57,00 75.000,00 4.275.000,00
2

SUB TOTAL 9.975.000,00


HOK
TOTAL BIAYA 9.975.000,00

Diketahi Oleh : Pasar Sipiongot, Juli 2022


Kepala Desa Pasar Sipiongot Dibuat Oleh :

( Paimahon harahap )
( Muhammad Efendi Harahap ) kaur Pemb. Desa
REKAPITULASI
RENCANA ANGGARAN BIAYA
PEKERJAAN BRONJONG

RENCANA ANGGARAN BIAYA PRASARANA

Desa : Pasar Sipiongot Kegiatan : Pembangunan Baru


Kecamatan : Dolok Ukuran / Volume : 200 M3
Kabupaten : Padang Lawas Utara
Provinsi : Sumut

HARGA
NO URAIAN SATUAN KEBUTUHAN SATUAN TOTAL BIAYA
Rp.
A. BAHAN
1 Batu Kali M3 436 Rp 250.000,00 109.000.000,00
2 Ijuk M2 380 Rp 15.000,00 5.700.000,00
3 Tanah Timbunan M3 190,625 Rp 100.000,00 19.062.500,00
4 Kawat Bronjong 4 mm @ 50 Kg BALT 34 Rp 850.000,00 28.900.000,00
5 Pipa 1.25"& Besi 12 mm Full Btg 17 Rp 135.000,00 2.295.000,00

Sub Total (1) 164.957.500


B. ALAT
1 Linggis BH 5 Rp 75.000 375.000,00
2 Skop BH 5 Rp 55.000 275.000,00

Sub Total (2) 650.000,00


C. UPAH
1. Pekerja HOK 248 Rp 75.000 18.600.000,00
2. Pekerja Anyam HOK 200 Rp 75.000 15.000.000,00
3. Pekerja Pengisian Batu HOK 200 Rp 100.000 20.000.000,00
Sub Total (3) 53.600.000
Total (1+2+3) 218.557.500

TOTAL BIAYA 218.557.500

Diketahi Oleh : Pasar Sipiongot, Juli 2022


Kepala Desa Pasar Sipiongot Dibuat Oleh :

( Paimahon harahap )
( Muhammad Efendi Harahap ) kaur Pemb. Desa

9.RAB BRONJONG MOODUlio