REHABILITATION OF DRAINAGE, GRANTS (SANGANDAAN), QUEZON CITY

as of October 18, 2021


P.O.W. Actual Accomplishment
ITEM No. Description
Quantity Unit % of Work Quantity Unit Actual % of Work
B.5 Project Billboard/Signboard, DPWH 2.00 each 0.11% 2.00 each 0.11%
B.7 Occupational Safety and Health Program 8.00 months 1.78% 8.00 months 1.78%
B.8 Traffic Management 8.00 months 1.36% 8.00 months 1.36%
B.9 Mobizilation/Demobilzation 1.00 l.s. 0.68% 1.00 l.s. 0.68%
101(1) Removal of Structures and Obstructions 1.00 l.s. 0.61% 1.00 l.s.s 0.61%

101(3)b3 Removal of Actual Structures/Obstruction (0.23m 1,602.00 sq.m. 4.14% - sq.m. 0.00%
thick, PCCP Unreinforced)

101(4)c Removal of Actual Structures/Obstruction (Curb and 632.00 l.m. 0.73% - l.m. 0.00%
Gutter)
Removal of Actual Structures/Obstruction (0.10m
101(3)d 632.00 sq.m. 0.98% - sq.m. 0.00%
thick, Sidewalk)
102(2) Surplus Common Excavation 431.00 cu.m. 0.33% - cu.m. 0.00%
103(1)b Structure Excavation (Soft Rock) 1,213.04 cu.m. 3.75% - cu.m. 0.00%
201(1) Aggregate Base Course 438.20 cu.m. 4.85% - cu.m. 0.00%
Portland Cement Concrete Pavement (t=0.23m thick;
311(1)f3 1,602.00 sq.m. 22.78% - sq.m. 0.00%
550F Mpa, 3 days(Unreinforced))
500(1)a1 Pipe Culverts (610 mm, Class II, RCPC) 24.00 l.m. 0.45% #NAME? l.m. #NAME?
500(1)a3 Pipe Culverts (910 mm, Class II, RCPC) 572.00 l.m. 21.77% - l.m. 0.00%
502(1)a1 Manholes (610 mm dia. Concrete) 4.00 each 2.03% - each 0.00%
502(1)a3 Manholes (910 mm dia. Concrete) 32.00 each 24.28% - each 0.00%
502(5) Metal Frames and Gratings 36.00 pairs 1.46% - pairs 0.00%
600(4) Concrete Curb and Gutter (Cast in Place) 632.00 l.m. 4.73% - l.m. 0.00%
601(1) Sidewalk (100mm thick) 632.00 sq.m. 3.18% - sq.m. 0.00%
100% Total Accomplishment #NAME?

Prepared by: Checked by: Approved by:

Niño N. De Leon Jorge A. Pacunana Jay R. Amansec


REHABILITATION OF DRAINAGE, GRANTS ST. (SANGANDAAN), QUEZON CITY
as of October 18, 2021

DATE PAVEMENT UNIT SIDEWALK UNIT CURB & UNIT Box Culvert UNIT RCP 36" UNIT RCP 24" UNIT STEEL UNIT MANHOLE Unit MANHOLE Unit Work Cost Cash Advance/
with RSB & with Frame &
GUTTER GRATINGS 36" Concrete Unit Cover Unit 24" Billing

0 sq.m. 0 sq.m. 0 l.m. 0 l.m. 0 pcs 0 pcs 0 pcs 0 pcs 0 pcs 0 pcs 0 pcs Total
Total CA/Billing
Amount (per unit) 120 85 120 250 250 200 500 5500 3000 2500 5000 Accomplisment
Total Amount - - - - - - - - - - - -
Less: 10% retention - - - - - - - - - - - - -
Collectable - - - - - - - - - - - -
₱0.00

Prepared by: Checked by: Approved by:

Niño N. De Leon Jorge A. Pacunana Jay R. Amansec


GRANTS WEEKLY ACCOMPLISHMENT
as of July 2 to July 8, 2021

Description Quantity Unit Unit Cost Direct Cost


PAVEMENT sq.m x 120 = -
RCPC 24" pcs x 200 = -
RCPC 36" pcs x 250 = -
SIDEWALK sq.m x 85 = -
BOX CULVERT l.m. x 250 = -
CURB & GUTTER l.m. x 120 = -
MANHOLE 36" units x 5500 = -
with RSB and Concrete units x 3000 = -
with Cover and Frame units x 2500 = -
STEEL GRATINGS units x 500 = -
MANHOLE 24" units x 5000 = -
STEEL GRATINGS units x 500 = -
Total Accomplishment: -
Less 10% Retention: 0.00
Current Accomplishment: ₱0.00
Less CA:
₱0.00

Request for Cash Advance:

Requested by: Prepared by:

Junior Meones Niño N. De Leon

Checked by: Approved by:

Jorge A. Pacunana Jay R. Amansec