ITEM DESCRIPTION Q'TY UNIT MATERIAL COST (US$) LABOR COST (US$) TOTAL REMARKS
BW-7.2 BEAM
BW-7.2.1 Reinforcement 8027.25 Kg 0.95 7,625.89 0.15 1,204.09 8,829.98
BW-7.2.2 Formwork 383.96 m2 7.5 2,879.72 7.50 2,879.72 5,759.44
BW-7.2.3 Concrete 38.52 m3 80 3,081.91 15.00 577.86 3,659.77
BW-7.2.4 Concrete Curing 38.52 m3 10 385.24 5.00 192.62 577.86
Sub-total (BW-7.2): 13,972.75 4,854.28 18,827.04
BW-7.3 SLAB
BW-7.3.1 Reinforcement 6359.22 Kg 0.95 6,041.26 0.15 953.88 6,995.14
BW-7.3.2 Formwork 412.00 m2 7.5 3,090.00 7.50 3,090.00 6,180.00
BW-7.3.3 Concrete 60.56 m3 80 4,845.12 15.00 908.46 5,753.58
BW-7.3.4 Concrete Curing 60.56 m3 20 1,211.28 5.00 302.82 1,514.10
BW-7.3.5 Support 1483.20 m3 3.5 5,191.20 3.50 5,191.20 10,382.40
Sub-total (BW-7.3): 20,378.86 10,446.36 30,825.22
BW-7.4 STAIR
BW-7.4.1 Reinforcement 998.55 Kg 0.95 948.62 0.15 149.78 1,098.41
BW-7.4.2 Formwork 20.78 m2 7.5 155.85 7.50 155.85 311.70
BW-7.4.3 Concrete 3.22 m3 80 257.60 15.00 48.30 305.90
BW-7.4.4 Concrete Curing 3.22 m3 10 32.20 5.00 16.10 48.30
BW-7.4.4 Support 43.20 m3 3.5 151.20 3.50 151.20 302.40
Sub-total (BW-7.4): 1,545.47 521.23 2,066.71
BW-8.2 BEAM
BW-8.2.1 Reinforcement 5005.35 Kg 0.95 4,755.08 0.15 750.80 5,505.89
BW-8.2.2 Formwork 221.08 m2 7.5 1,658.06 7.50 1,658.06 3,316.13
BW-8.2.3 Concrete 24.02 m3 80 1,921.61 15.00 360.30 2,281.91
BW-8.2.3 Concrete Curing 24.02 m3 10 240.20 5.00 120.10 360.30
Sub-total (BW-8.2): 8,574.95 2,889.27 11,464.22
BW-8.3 SLAB
BW-8.3.1 Reinforcement 3773.86 Kg 0.95 3,585.16 0.15 566.08 4,151.24
BW-8.3.2 Formwork 244.50 m2 7.5 1,833.75 7.50 1,833.75 3,667.50
BW-8.3.3 Concrete 35.94 m3 80 2,875.32 15.00 539.12 3,414.44
BW-8.3.4 Concrete Curing 35.94 m3 10 359.42 5.00 179.71 539.12
BW-8.3.5 Support 880.20 m3 3.5 3,080.70 3.50 3,080.70 6,161.40
2
Sub-total (BW-8.3): 11,734.35 6,199.36 17,933.71
BW-8.4 STAIR
BW-8.4.1 Reinforcement 998.55 Kg 0.95 948.62 0.15 149.78 1,098.41
BW-8.4.2 Formwork 20.78 m2 7.5 155.85 7.50 155.85 311.70
BW-8.4.3 Concrete 3.22 m3 80 257.60 15.00 48.30 305.90
BW-8.4.4 Concrete Curing 3.22 m3 10 32.20 5.00 16.10 48.30
BW-8.4.5 Support 43.20 m3 0 0.00 0.00 0.00 0.00
Sub-total (BW-8.4): 1,394.27 370.03 1,764.31
BW-9.2 BEAM
BW-9.2.1 Reinforcement 3461.85 Kg 0.95 3,288.76 0.15 519.28 3,808.04
BW-9.2.2 Formwork 143.90 m2 7.5 1,079.21 7.50 1,079.21 2,158.43
BW-9.2.3 Concrete 15.17 m3 80 1,213.49 15.00 227.53 1,441.01
BW-9.2.4 Concrete Curing 15.17 m3 10 151.69 5.00 75.84 227.53
Sub-total (BW-9.2): 5,733.14 1,901.86 7,635.00
BW-9.3 SLAB
BW-9.3.1 Reinforcement 2620.70 Kg 0.95 2,489.66 0.15 393.10 2,882.77
BW-9.3.2 Formwork 159.00 m2 7.5 1,192.50 7.50 1,192.50 2,385.00
BW-9.3.3 Concrete 21.70 m3 80 1,736.28 15.00 325.55 2,061.83
BW-9.3.4 Concrete Curing 21.70 m3 10 217.04 5.00 108.52 325.55
BW-9.3.5 Support 524.70 m3 3.5 1,836.45 3.50 1,836.45 3,672.90
Sub-total (BW-9.3): 7,471.93 3,856.12 11,328.05
BW-9.4 STAIR
BW-9.4.1 Reinforcement 149.10 Kg 0.95 141.65 0.15 22.37 164.01
BW-9.4.2 Formwork 11.80 m2 7.5 88.50 7.50 88.50 177.00
BW-9.4.3 Concrete 1.46 m3 80 117.15 15.00 21.97 139.12
BW-9.4.4 Concrete Curing 1.46 m3 10 14.64 5.00 7.32 21.97
BW-9.4.5 Support 17.16 m3 3.5 60.06 3.50 60.06 120.12
Sub-total (BW-9.4): 422.00 200.21 622.21
BW-10.2 BEAM
BW-10.2.1 Reinforcement 1048.95 Kg 0.95 996.50 0.15 157.34 1,153.85
BW-10.2.2 Formwork 39.27 m2 7.5 294.49 7.50 294.49 588.98
BW-10.2.3 Concrete 4.17 m3 80 333.80 15.00 62.59 396.38
BW-10.2.4 Concrete Curing 4.17 m3 10 41.72 5.00 20.86 62.59
3
Sub-total (BW-10.2): 1,666.51 535.28 2,201.79
BW-10.3 SLAB
BW-10.3.1 Reinforcement 824.12 Kg 0.95 782.91 0.15 123.62 906.53
BW-10.3.2 Formwork 50.00 m2 7.5 375.00 7.50 375.00 750.00
BW-10.3.3 Concrete 6.83 m3 80 546.00 15.00 102.38 648.38
BW-10.3.4 Concrete Curing 6.83 m3 10 68.25 5.00 34.13 102.38
BW-10.3.5 Support 65.00 m3 3.5 227.50 3.50 227.50 455.00
Sub-total (BW-10.3): 1999.66 862.62 2862.28
BW-10.4 STAIR
BW-10.4.1 Reinforcement 54.93 Kg 0.95 52.19 0.15 8.24 60.42
BW-10.4.2 Formwork 8.08 m2 7.50 60.64 7.50 60.64 121.27
BW-10.4.3 Concrete 1.09 m3 80.00 86.98 15.00 16.31 103.29
BW-10.4.4 Concrete Curing 1.09 m3 10.00 10.87 5.00 5.44 16.31
BW-10.4.5 Support 3.42 m3 3.5 11.99 3.50 11.99 23.97
Sub-total (BW-10.4): 222.66 102.61 325.26
BW-11.2 BEAM
BW-11.2.1 Reinforcement for second beam 454.65 Kg 0.95 431.92 0.15 68.20 500.12
BW-11.2.2 Formwork for second beam 24.38 m2 7.50 182.81 7.50 182.81 365.63
BW-11.2.3 Concrete Grade 25 for second beam 2.49 m3 80.00 199.50 15.00 37.41 236.91
BW-11.2.4 Concrete Curing 2.49 m3 10.00 24.94 5.00 12.47 37.41
Sub-total (BW-11.2): 839.17 300.89 1,140.05
BW-11.3 SLAB
BW-11.3.1 Reinforcement 361.18 Kg 0.95 343.12 0.15 54.18 397.30
BW-11.3.2 Formwork 21.00 m2 7.50 157.50 7.50 157.50 315.00
BW-11.3.3 Concrete 2.87 m3 80.00 229.32 15.00 43.00 272.32
BW-11.3.4 Concrete Curing 2.87 m3 10.00 28.67 5.00 14.33 43.00
BW-11.3.5 Support 35.70 m3 3.5 124.95 3.50 124.95 249.90
Sub-total (BW-11.3): 883.56 393.96 1277.51